autoclave qualification some practical advice
TRANSCRIPT
7/21/2019 Autoclave Qualification Some Practical Advice
http://slidepdf.com/reader/full/autoclave-qualification-some-practical-advice 1/4
Special Edition: Utilities Qualification 149
utoclaveQualification
Some
Practical
Advice
By Gamal Amer Ph.D.
Robert G. Beane Jr.
Validation and Process Associates
------------------------------------t\-----------------------------------
D
espite the fact that the sub
ject
of
autoclave qualifica
tion has been the topic of
numerous articles, books, and sym
posia in the past decade, autoclave
qualification shortcomings are a
mong the leading source of FD 483
citations reported for the biotech
industry. This article attempts to pre
sent a hands-on approach to efficient
ly and reliably qualify autoclaves .
This article assumes that the reader is
somewhat familiar with the basic the
oretical development of steam steril
ization and equipment qualification.
Autoclave qualification, or for
that matter qualification
of
any piece
of equipment, should begin after the
equipment is installed
and
fully
commissioned. Designing the In
stallation and Operational Qualification IQ/OQ) to
also serve as the commissioning and start-up docu
ment
is
a practice that
has
recently gained populari
ty,
but
is not recommended . Such thinking arose
because organizations believe that it will lead to
time as well as resource saving. However, when
qualification serves as the commissioning and start
up function, failures and deviations from protocol
acceptance criteria will
most
likely result thus in
creasing cost. A better approach for saving time and
money would
be
to consider all the operational re
quirements for the autoclave prior to ordering and
commissioning the autoclave with
qualification
expected to
verify
these functional requirements . Such
an approach would also avoid du
plication
of
effort and lead to a
smooth qualification. A factory ac
ceptance test, prior to receiving the
autoclave at the facility, should be
performed. Once the autoclave is
installed,
it
should be rigorously
commissioned and then started. In
other words, the autoclave should
be
thoroughly tested during the
commissioning and start-up phase
All bugs must
be
fixed, and the
autoclave must be in proper work
ing condition before the qualifica
tion phase can proceed.
Prior to beginning the qualifica
tion effort, assessments of the mater
ial being autoclaved should be made for cycle devel
opment. Some parameters to consider are susceptibil
ity of the load to the heating conditions, maintenance
of sterility after autoclaving, differences in solids and
liquids heating, and the effect of trapped air. Load pat
terns should be established, assigned to cycles, and
tested. These tests should verify, at a minimum, tha
the load was not affected by the heat profile, the con
tainer integrity has not been compromised, and the
sterility of the load has been achieved. This is typical
ly done by a combination of heat penetration studie
and biological testing.
7/21/2019 Autoclave Qualification Some Practical Advice
http://slidepdf.com/reader/full/autoclave-qualification-some-practical-advice 2/4
Special Edition: Utilities Qualification150
Installation Qualification IQ)
Upon completion
o
the load and cycle develop
ment, the IQ phase is initiated. Equipment IQs are gen
erally similar and vary little from one kind o equip
ment to another. Therefore, the IQ portion
o
the qual
ification will not be emphasized in this discussion. In
general, the IQ may verify the following information:
1 Equipment specifications: verification o pri
mary system components.
2. Component/Auxiliary equipment specifica
tions: verification o secondary system com
ponents.
3. Instrument specifications and calibration:
verification o associated critical and non
critical instruments.
4. Materials
o
construction: verification
o
product and non-product contacting surfaces.
5. Filter schedules: verification o system fil
ters with associated replacement procedures.
6. Control systems: verification o system con
trol type and necessity for individual control
system qualification.
7. Utility connections: verification that required
utilities are installed as required.
8. Design specifications and drawings: verifica
tion o system specifications and associated
diagrams.
9. Installation documentation and drawings: ver
ification o system schematics and as-built
diagrams.
10. Standard Operating Procedures SOPs) and re
lated programs: verification of approved SOPs
for start-up, shutdown, operation, preventive
maintenance, cleaning, calibration, and change
control.
11. Certification documents: verification o all
certifications resulting from the installation
o
the system.
12. Required training documents and procedures:
verification
o
the establishment and imple
mentation
o
approved training procedures.
Documents and manuals should be reviewed thor
oughly to confirm and assure that the information col
lected during the IQ phase
o
the qualification effort
is accurate and contradictions
do
not occur.
Gamal Amer Ph.D. and Robert
G
Beane Jr.
Operational Qualification OQ)
Depending on the complexity o the autoclave
control system, a variety o different tests should be
performed during the OQ portion o the qualifica
tion effort. The most important issue to keep in mind
when conducting the OQ
is
temperature mapping
o
the empty chamber.
Empty chamber tests, which should be performed
to verify the proper operation o the autoclave, are
normally designed to test and determine the hot and
cold spots for thermocouple placement. During an
empty chamber run, a sufficient number o thermo
couples, depending on the volume
o
the chamber,
should be distributed to establish the temperature
profile within the chamber and verify that there is a
minimum
o
temperature differential and fluctuation
during a cycle. The thermocouples should be:
• positioned throughout the chamber and within
the anticipated hot and cold regions, the steam
inlet, and condensate drain.
• held in position with heat resistant tape, or a
similar material that will not affect the temper
ature sensing capabilities o the thermocouples.
• positioned at the extremities
o
the chamber,
but slightly off the surface o the inside cham
ber; two to four inches, depending on the size
o the autoclave, is usually sufficient.
Other important factors to consider when devel
oping tests for an autoclave OQ include:
• Control system setup: Is the system set up to
operate by recording the Fo value o a control
thermocouple or by ramping and holding a
temperature for a period o time?
• System safety features: Are there locks on the
autoclave doors during pressurization cycles?
Should the system enter a slow exhaust mode i
shut down during a run? Does the system sound
an audible alarm when the cycle is complete?
• Quality o cooling water or air injects: Any me
dium that comes in contact with the sterilized
load should be shown to contain a low biobur
den and be part o a monitoring program.
• Vacuum and/or relative pressurization: Chamber
7/21/2019 Autoclave Qualification Some Practical Advice
http://slidepdf.com/reader/full/autoclave-qualification-some-practical-advice 3/4
Special Edition: Utilities Qualification 151
operation while running loaded chambers and assess
ing the minimum lethality levels. In addition, these
tests should be developed to verify the heat penetra
tion throughout the load and the sterility level
reached. Tests conducted during a PQ are normally
comprised
o
two components; heat penetration stud
ies and biological challenge tests. The heat penetra
tion studies are performed to verify that each position
within the load is exposed to sufficient heat for prop
er sterilization. These tests are conducted in a manner
similar to the OQ empty chamber tests, except that
the thermocouples are positioned within the load
instead
o
the chamber extremities.
Thermocouples should be strategically distrib
uted within the load with the purpose
o
measuring
the temperature and lethality at the locations that
may represent the most difficult heat penetration sit
uation. Special care should be taken to monitor large
thermal masses, highly insulated components, and
all product-contacting surfaces. Once these locations
have been identified, the actual placement
o
the
thermocouple wires should ensure that the thermal
center o the component is measured and that no
harm comes to the thermocouples. Load carts and
metal covers can easily damage thermocouple wires
and ruin tests i allowed.
The biological challenge tests are conducted at
the same time as the penetration studies by means
o
Biological Indicators (BIs). These BIs can be ob
tained in a variety
o
different types, including
ampoules, spore strips, discs, and suspensions. Re
gardless
o
the type chosen, positive controls should
be collected for each test performed. Special care
should be taken to record the organism s name, the
BI supplier, spore population, lot number, expiration
date, and specific resistance information. Typically
in autoclave qualification,
B. stearothermophilus
BIs with a spore population
o
1
6
are used. How
ever, other commercial BIs are available for moist
heat sterilization studies that are comprised
o
other
organisms such as B. subtilus B. coagulans and C
sporogenes
with populations from
1
3
to 1
9
and
possibly higher. BI requirements depend on the par
ticular load and sterilization requirements. However,
justification should be provided at the time o quali
fication. When conducting the studies, the BIs
should, at a minimum, be placed in the components
adjacent to the thermocouples, but ideally
as
close as
Gamal Amer Ph.D. and Robert G. Beane Jr
possible to the thermal areas, which are being mea
sured by the thermocouples. Tests are typically con
ducted multiple times and with worst-case scenarios
in mind. However, it is strongly recommended that
tests be conducted at a minimum in triplicate for
each load pattern.
inal Reports
Final reports, summarizing the results
o
the stud
ies, should be generated after completion
o
each
qualification step. All raw data generated, including
biological indicator growth results, should be attach
ed to the executed protocol. Autoclave re-qualifica
tion should occur periodically, according to estab
lished change control procedures and with associated
test protocols, to verify that the autoclave has re
mained in a validated state.
Summary
In summary, autoclave qualification is a fact
o
life in the pharmaceutical and biotechnology in
dustries, but doesn t have to be a source
o
stress
i
the system qualification is carefully thought out and
approached logically. The confirmatory nature
o
validation suggests that the system s operation
should be known prior to conducting qualification
tests. Once installed, load development tests should
be run to establish a baseline for the system. Once
established, the system qualification can start. The
system should be installed according to manufactur
er specifications, calibrated, connected to appropriate
utilities, and have associated diagrams and SOPs
established and available. The autoclave control sys
tem should be tested by means
o
logical system tests
to verify proper system operation and temperature
distribution. Furthermore, temperature penetration
tests and biological challenge tests should be per
formed to confirm the sterility
o
the materials afte
undergoing an established cycle. 0
7/21/2019 Autoclave Qualification Some Practical Advice
http://slidepdf.com/reader/full/autoclave-qualification-some-practical-advice 4/4
Special Edition: Utilities Qualification152
An exclusive lexicon of
more than 750 terms,
symbols, references and
acronyms commonly used
in drug and diagnosticindustries.
▼ Defines FDA terminol-
ogy and compares it to
common industry
usage.
▼ Establishes an educational foundation
for in-house compliance training.
Save 20% Off the Regular Price of $99.00
Defining the
Industry
PO Box 6004
Duluth, MN 55806Phone: 218.740.7028 or
888.524.9922 US Only Fax: 218.740.6308E-mail: [email protected]
Web Site: www.ivthome.com
O n l y $ 7 9 .0 0 F r e e w i t h
M e m b e r s h i p
\di-’fin-ing\th \‘in-d s-tre e e