australian society for concrete pavements - ascp … papers/paper 08... · australian society for...
TRANSCRIPT
Australian Society for Concrete Pavements
4th Concrete Pavements Conference
CRCP Roundabouts – A Theoretical Case Study
Tim Buckingham-Jones BEng (Hons) DipEngPrac CPEng NER
Senior Pavement Engineer
Aurecon
ABSTRACT
The use of concrete roundabouts in NSW, in recent times, is generally limited to a steel fibre
reinforced concrete pavement (SFCP). The higher flexural strength and ‘toughness’ being
beneficial in areas where conventional slab geometric limits often need to be exceeded due
to the complex geometry.
An alternative to SFCP is the use of Continuously Reinforced Concrete Pavement (CRCP) in
roundabout applications. This approach has found acceptance in Europe, namely in Belgium
and the Netherlands, and in more recent years the United States.
On a 2014 ASCP visit to Belgium a number of CRCP installations, including two
roundabouts, were inspected. Whilst only a brief visit, the roundabout installations were
performing well, and demonstrated that there is potential application for this technology in
Australia.
This paper presents a theoretical case study of the design of a CRCP roundabout in
Australia. The purpose is to clarify the potential opportunities and raise issues that may
present barriers to implementation. The paper will provide the industry an opportunity to
assess in further detail a CRCP roundabout pavement design.
ASCP 4th Concrete Pavements Conference 2
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Introduction
In July 2014 a group of Australian engineers toured Belgium, visiting a number of concrete
roads around the country. The visit included 3 continuously reinforced concrete pavement
(CRCP) roundabouts of variable age. From the visual inspection during the visit, and by all
accounts, the CRCP roundabouts were performing well.
Even before this visit there had been discussion in Australia regarding the suitability of
CRCP as an alternative to steel fibre reinforced concrete pavement (SFCP) typically adopted
for roundabout construction in NSW.
This paper has been prepared to provide a more detailed analysis of the potential for CRCP
roundabouts under current Australia design standards. The intention of this paper is not to
explore new innovations with respect to the structural design of CRCP, but merely to use the
tools and techniques currently available to the designer and apply these to a CRCP
roundabout design.
This paper will summarise local and overseas practice and provide potential CRCP designs
for 2 existing SFCP roundabouts such that a comparison may be undertaken by road
authorities, consultants and contractors alike.
Current concrete roundabout practices
Australia
Construction of concrete roundabouts in Australia is generally in the form of plain concrete or
SFCP in a conventional jointed layout. For heavy duty applications on the state highway
network in NSW the SFCP variety is the current default pavement type.
Figure 1 – Typical SFCP radial joint layouts used in NSW (RTA, 2004)
The SFCP base thickness varies based on the anticipated traffic loading, but recent
experience suggests a base thickness between 180 – 250 mm is usually adopted. Designs
typically incorporate a lean-mix concrete subbase (LCS) to which wax curing and interlayer
debonding treatments are applied.
ASCP 4th Concrete Pavements Conference 3
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Approach zones are constructed of the same SFCP type, with anchor lugs installed to
restrain terminal end movement associated with thermal movements of the slabs.
Europe
Both jointed concrete pavement and CRCP are used in Europe. Per Debroux et al (1998)
and Rens (2013) CRCP was only used for the first time in 1995 in Belgium. The first
examples are now almost 20 years old and are still in good condition today. Many others
have been built in the meantime in Belgium, France and the Netherlands, with positive
results.
Figure 2 – Typical CRCP roundabout joint layout (Rens, 2013)
United States
There seems to be limited experience with CRCP for roundabout applications within the
United States. One notable application is reported on by Plei (2016), the Almeda Paisano
roundabouts.
When describing the reasons for pursuing a CRCP roundabout option, in leiu of other jointed
concrete pavement options Plei notes the following:
“…certain issues can make [conventional jointed] roundabouts difficult to construct and
maintain. The inherent form of the roundabout makes the layout of joints, sawcut timing, and
joint maintenance challenging – often more art than science”. (Plei, 2016)
Accordingly, CRCP was selected for the project.
ASCP 4th Concrete Pavements Conference 4
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
A CRCP base thickness of 200 was adopted for the project, over 100 mm of HMAC (dense
graded asphalt) over 150 mm of lime stabilised subgrade material.
Figure 3 – Almeda Paisano roundabouts, Texas (Source: Plei, 2016)
Why CRCP for roundabouts?
Reasons for considering a concrete pavement for roundabout construction is primarily
associated with the ability of a concrete pavement to withstand deformation due to the high
centripetal forces encountered at a roundabout.
Figure 4 – CRCP roundabout in Herselt, Belgium
Whilst a jointed SFCP is the default concrete roundabout pavement choice in Australia, there
has been discussion in recent years regarding the potential of CRCP as a valid and perhaps
more desirable solution.
The theoretical attractions of a CRC pavement option include:
ASCP 4th Concrete Pavements Conference 5
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
▪ A concrete slab layout that is tied together results in a lower likelihood that in the heat
of summer slabs will ‘wander’ with the result being a loss of load transfer at joints
when slabs subsequently cool and contract. An example of such slab movement is
presented as a case study, in Tamworth NSW.
▪ The elimination of a significant number of contraction joints required in jointed
concrete pavement and thus avoid loading of the slab corners. The elimination of
these sawn joints also presents advantages, particularly in noise sensitive areas
where night time saw-cutting is often required after daytime concrete pours.
▪ The potential to reduce the number of construction joints, with the result being a
shorter construction programme.
▪ Potential to provide a surface treatment (eg. asphalt) without the maintenance
concerns associated with overlaying a significant number of contraction joints. It is
acknowledged that this treatment would need special consideration due to the risks
of deformation and delamination of any asphalt surfacing.
These claims obviously require further investigation and discussion, but serve as a starting
point for the investigation presented herein.
Case study – Tamworth, NSW Australia
Concerns have existed within the industry regarding the risk of a portion, or ‘wedge’, of the
roundabout pushing out because of thermal stresses during summer expansions. To date
only one example of this has been reported, in Tamworth in 2013, near the entrance to the
Australia Equine and Livestock Events Centre (AELEC).
The SFCP roundabout in question was designed and constructed by Tamworth Regional
Council in 2008 – 09, and to a very high standard and there are no indications that this event
is related to design or construction omissions.
The slab movement was reported in 2013, approximately 4 years after opening, with a
portion of the radial layout having shifted outwards. The movement caused tiebars in a short
section of a tied hinge joint to yield, with a resulting contraction and hinge joint opening of
between 25 and 30 mm.
The movement introduces significant concerns as the load transfer is effectively eliminated
between slabs at contraction joints that have opened up, and in the case of yielded tiebars
between slabs each side of the (former) longitudinal hinge joint.
Remedial works were undertaken by the council to correct the slab movement in the form of
horizontal slab jacking and cross stitching. It was completed in a timely and professional
manner and there have been no signs to date of a recurrence.
ASCP 4th Concrete Pavements Conference 6
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Figure 5 - Roundabout on the New England Highway, Tamworth (Courtesy of Tamworth Regional Council)
CRCP roundabouts – theoretical case studies
The main objective of this paper is to compare a CRCP roundabout pavement design with
the current standard SFCP. To do this 2 existing roundabouts have been selected that have
both recently been designed and constructed. They include:
▪ The George Booth roundabout, located in the Hunter Valley, NSW; and
▪ The Eungai roundabout, located at Stuarts Point Interchange just north of Kempsey,
NSW.
The full design details prepared for the above roundabouts are presented as Figure A.1 and
Figure A.2 included in Annexure A. The SFCP designs for comparison are presented in
Annexure B, as Figure B.1 and B.2 respectively.
ASCP 4th Concrete Pavements Conference 7
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
George Booth roundabout
The George Booth roundabout was constructed in NSW as part of the Hunter Expressway
Alliance project between 2010 and 2013. The roundabout consists of 2 lanes of circulating
traffic, with a central heavy vehicle overrun area. Details of the as-built roundabout are as
follows:
▪ Inner radius: 20 m
▪ Outer radius: 30 m
▪ Design traffic: 6.35 x 107 HVAG’s
▪ Pavement type: SFCP base over LMC subbase
Eungai roundabout (West)
The western roundabout at the Stuarts Point Interchange near Eungai, NSW, was
constructed as part of the Pacific Highway Upgrade between Frederickton and Eungai
between 2014 and 2016. The roundabout consists of a relatively narrow single circulating
carriageway. Details of the as-built roundabout are as follows:
▪ Inner radius: 23 m
▪ Outer radius: 30 m
▪ Design traffic: 3.38 x 107
▪ Pavement type: SFCP base over LMC subbase
CRCP roundabout thickness design
To compare the thickness design for a CRCP alternative the current Australian concrete
pavement structural design methodology has been followed, including Austroads provisions
as follows:
Austroads (2012) states:
“The geometry of roundabouts usually dictates that traffic will travel through them at
relatively low speeds. Where a lean concrete subbase is provided joint erosion is unlikely to
be the controlling factor in their pavement life. Under these conditions, the thickness design
for roundabouts is carried out only for the fatigue analysis. The load safety factors that
should be adopted for rigid pavements for roundabouts in order to cater for radial/centripetal
forces transmitted to the outer wheels is a value for a specific project reliability with the
addition of 0.3.”
The resulting design base thickness, inclusive of the increased project reliability, has been
summarised in Table 1 for various concrete pavement types. Note that where the CRCP
‘design’ base thickness exceeds the ‘minimum’ base thickness per Austroads (2012) then
the SFCP option is generally thinner. This is the result of the increased flexural strength of
ASCP 4th Concrete Pavements Conference 8
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
the SFCP concrete mix, 5.5 MPa in lieu of the 4.5 MPa assumed for concrete base,
increasing the fatigue life of the concrete slab.
Table 1 demonstrates that where more than one type of concrete pavement is specified the
thickness design would need to be checked for both types. For example, if a CRCP central
zone (circulating carriageway) is specified, an approach pavement consisting of SFCP would
suit given the thickness design is generally less than that required for CRCP.
Table 1 – Base thickness design for various concrete pavement types
Case Study Design traffic
(HVAG)
Design base thickness (Note 1)
CRCP SFCP PCP
George Booth
roundabout
6.35 x 107 210 (230) 190 (230) 220 (250)
Eungai roundabout 3.38 x 107 210 (180) 190 (180) 220 (200)
Notes
1. Thickness in brackets is the minimum thickness per Austroads (2012) Table 9.7.
2. Construction tolerances have been excluded from the design base thickness.
Design detailing
Two fundamentals in the detailing of a roundabout include a) the joint layout and b) the
reinforcement quantity and layout.
Joint layout
There are 3 key zones of the roundabout as defined by RTA (2004) and illustrated in Figure
6. Considering these zones, it is possible to determine the key considerations for a CRCP
alternative.
Figure 6 – Roundabout zones as defined in RTA, 2004
ASCP 4th Concrete Pavements Conference 9
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Central zone
The approach adopted for this exercise has been to include CRCP within the ‘central zone’
and the ‘transition zone’. The CRCP within the central zone is expect to be relatively
straightforward with slab width generally being constant for the circulating carriageway.
The exception to this is at the outer edge where the slab needs to step out to allow for a 1.0
m wide slab to commence within the transition zone, as seen in Figure 7. This proposed
construction joint (type C7) should strictly be full width of the circulating slab, however the
provision of trimmer bars per a typical pit intrusion detail is considered appropriate. The
absence of a full width construction joint at these locations is consistent with European
practice as outlines by Rens (2013).
Central zone ‘stepping’ in the Eungai
roundabout (See Figure A.2 in Annex A)
Central zone ‘stepping’ on site in Belgium
(Photo: Rens, 2013)
Figure 7 – Central zone ‘stepping’ to allow a new 1.0 m wide slab within the transition zone
Transition zone
It is noted that the ‘transition zone’ in Belgium (shown in Figure 2) is typically a mesh-
reinforced slab, in lieu of CRCP.
If a CRCP transition zone was adopted in these zones there is uncertainty as to the crack
direction within the slabs. Cracks would likely propagate from the circulating carriageway
slab, from induced joints in the tied kerb, and at the re-entrant angle formed by the type 2
construction joint in the transition zone. As a result it is unclear how cracking would form
within this slab, and hence whether the longitudinal steel would be in the correct orientation
to resist the resulting movements.
Provision of conventional jointed SFCP slabs within this zone also presents issues. The
movement that would be anticipated at resulting sawn contraction joints would be large
reducing load transfer efficiency during cooler periods. The movement would also likely be in
a direction that is not perpendicular to the joint itself as the roundabout and the jointed slabs
would be moving in different directions.
ASCP 4th Concrete Pavements Conference 10
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Provision of long SFCP-R slabs within the transition zone, when compared with conventional
joint layout, would likely address these concerns. By providing sufficient mesh in the slab to
resist crack opening irrespective of the crack geometry, the slabs could be expected to
behave in a similar fashion to the long slab jointed reinforced concrete pavements. (A
similarity could be drawn with the long SFCP-R slabs adopted at bridge approach zones
where skews prevent CRCP being adopted. See RMS CRCP Standard Drawings, 2016).
A distinct difference that this approach would allow versus the conventional SFCP jointed
roundabout is the ‘squaring’ of the isolation joint, between the transition and approach
zones. See Figure 8 below for an example. This provides for better slab corner angles, with
a corresponding reduction in stress associated with more acute slab corners.
Conventional jointed (SFCP) layout at interface
between transition and approach zones. Note
the skewed type 14 isolation joint.
Proposed CRCP layout at interface between
transition and approach zones. Note the
square type 14 isolation joint.
Figure 8 – Differing alignments of the isolation joints (type 14 joints) at the same location, at the interface
between the transition and approach zones.
Approach zone
The ‘approach zone’ has been detailed as jointed concrete (SFCP type). This is similar to
overseas practice, although typically with the addition of SFCP in lieu of plain or mesh
reinforced plain concrete.
This is considered the most suitable layout for the following reasons:
▪ The approach zone has been detailed with an isolation joint, as depicted in Figure 8.
The vastly different directions of movement of the CRCP circulating carriageway and
the approach zone makes it undesirable to tie the approach legs to the transition
zone.
▪ The difficulty in anchoring, or controlling the movement of a CRCP approach leg.
With an isolation joint between the transition and approach zones this approach
zone would likely by a long jointed reinforced concrete slab, with excessive
movements resulting at the isolation joint. The jointed approach zone minimises the
movement at the isolation joint (type 14 joint), thus reducing the movements the joint
and sealant needs to be designed to cater for.
ASCP 4th Concrete Pavements Conference 11
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
▪ The thickness design for SFCP is typically less than that for the CRCP base due to
the higher flexural strength. If a plain concrete mix were to be adopted the approach
zone base thickness would likely need to increase as indicated by Table 1.
Terminal anchors are proposed, consistent with current practice for SFCP roundabouts.
These terminal anchors restrict movements against the adjoining flexible pavement.
Reinforcement
Longitudinal steel
The current longitudinal steel requirements for a mass steel ratio of between 0.67% and
0.72% is consistent with the requirements in Europe for CRCP roundabouts. Rens (2013) is
worth noting:
“The longitudinal reinforcement in a roundabout should exactly follow the curve of the
roundabout. In order to facilitate the bending of the longitudinal (concentric) reinforcement
bars, it is recommended to limit the diameter to 16 mm.”
Therefore, using the formulas presented in Austroads (2012) the resulting spacing of
longitudinal 16 mm deformed steel bars is as follows:
▪ George Booth roundabout: 120 mm (for 250 mm CRCP base thickness)
▪ Eungai roundabout: 140 mm (for 210 mm base thickness)
Regarding splicing, Rens 2013 notes:
“… it is difficult to maintain a constant angle of splicing a (to the perpendicular of the tangent
of the axis of the road i.e. the radius). This means that the length of overlap should be varied
as a function of the radius of the circle formed by the longitudinal reinforcement, or that, in
other words, the length of the longitudinal reinforcement should be reduced towards the
inner edge of the roundabout ring. It is important to avoid a concentration of splices in the
same radial section, so that not all the splices lie on the same radial line.”
Whilst the splicing would need careful attention on site, it is expected to be achievable per
European experience outlined above.
Transverse steel and tiebars
Provision of transverse reinforcement in CRCP is primarily to provide support for the
longitudinal steel, with a maximum spacing of 750 mm adopted to prevent ‘sagging’ of the
longitudinal steel. However, in Australian practice the transverse steel is also designed to act
as a tie-bar in the case of any unplanned cracking in the concrete base.
Tiebars are provided to ensure close contact is maintained between slabs thus ensuring load
transfer is maintained at formed construction or sawn induced joints.
The number of tiebars is determined using the subgrade drag theory per Austroads (2012).
The amount of steel needs to be sufficient to overcome stresses associated with adjacent
slabs contracting away from the joint during the cooler months.
ASCP 4th Concrete Pavements Conference 12
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
A key input to the subgrade drag theory is the distance to the nearest un-tied joint, or ‘relief
edge’. This is essentially the nearest edge of the concrete base that is free to move during
thermal (cooling) contractive movements. For the circulating carriageway in a roundabout
situation the relief edge could be assumed to be the inner and outer edge of the concrete
base, or tied kerbs where they exist.
However, with a CRCP roundabout the circulating carriageway is acting as a ‘ring’, with
contractive movements towards the centroid. In this instance the centroid would be the
centre of the roundabout. As a result there is a question as to whether the transverse steel in
CRCP roundabouts would need to be designed using the outer edge of the roundabout as
the relief edge due to the inner edge contracting away from any longitudinal joint within the
circulating carriageway. This is likely to be more critical in smaller roundabouts where the
‘ring’ movements toward the centroid are likely to be more distinct.
Construction and maintenance considerations
Whilst far from comprehensive, the following paragraphs investigate the impact of CRCP
roundabouts on the construction phase and future maintenance.
Construction of the roundabout under traffic
Where vertical levels or traffic management impose constraints to the construction of the
new roundabout the resulting construction joint locations need to be considered. This is often
difficult during the design phase as the detailed construction staging layout is generally
finalised at a later date. An example of a complex traffic staging arrangement was the
George Booth Roundabout that required construction in distinct stages to keep the existing
road network operational. A snapshot of the staging works is shown in Figure 9.
Where traffic staging constraints are known to exist the designer can provide flexibility to the
contractor by, as much as possible, not restricting the location of construction joints. In
SFCP design, the type 7 transverse formed construction joints must be located a minimum
of 1.5 m from adjacent sawn contraction joints (although this has been relaxed to 1.0 m in
some circumstances). This requires slabs on the inner circulating carriageway to be at least
3.0 m in length before a construction joint may be formed within. Figure 10 gives an example
of the staggered layout that results where a concrete roundabout is constructed in stages.
In a CRCP roundabout there is no such restriction as there are no transverse sawn
contraction joints. The transverse formed construction joint can be located to best suit the
proposed construction staging.
ASCP 4th Concrete Pavements Conference 13
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Stage 1, construction of the new George Booth
roundabout (to the right of the photo) whilst the
original roundabout (to the left of the photo) remained
operational. (Photo: Hunter Expressway Alliance)
Stage 2, temporary layout to facilitate construction of
the remainder of the new concrete roundabout.
(Photo: Hunter Expressway Alliance)
Figure 9 – Construction of the George Booth roundabout under traffic.
Figure 10 – Formed construction joints (joint type 7) staggered to meet offset requirements to transverse
contraction joints (joint type 8) (Photo by the author)
Maintenance of a CRCP roundabout
The anticipated maintenance regime for a CRCP roundabout is not to vary significantly from
current SFCP roundabout maintenance regimes, although notable advantages of CRCP
would include:
▪ Fewer sawn contraction joints, with a corresponding reduction in joint seal
maintenance.
▪ Potential to provide a surface course overlay within the circulating carriageway
without the potential reflective crack issues associated with sawn contraction joints.
Whilst only ever reported in one instance, to the authors knowledge, the issue that has
arisen at the SFCP roundabout in Tamworth is not likely to arise with CRCP. Given the
circulating carriageway is effectively tied together as a continuous ring there is little likelihood
ASCP 4th Concrete Pavements Conference 14
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
of individual segments being pushed outwards, with resulting joint opening as seen in
Tamworth.
Conclusion
The use of CRCP for roundabout pavements would, after undertaking an exercise in the
design and comparison with the SFCP options, seem promising. There are some obvious
advantages of CRCP when compared with current SFCP roundabouts including:
▪ A concrete slab layout that is tied together, resulting in a lower likelihood that in the
heat of summer slabs will ‘wander’ with the result being a loss of load transfer at
joints when slabs subsequently cool and contract.
▪ The elimination of a significant number of contraction joints required in jointed
concrete pavement and thus avoid loading of the slab corners, and reducing joint
seal maintenance.
▪ The potential to reduce the number of construction joints, with the result being a
shorter construction programme.
▪ Potential to provide a surface treatment (eg. asphalt) without the maintenance
concerns associated with overlaying a significant number of contraction joints.
The issues for further discussion include, but are not limited to, the following:
▪ The proposed pavement within the ‘transition zone’ of the roundabout. Is SFCP-R,
with no contraction joints, the appropriate slab type?
▪ Design of the transverse reinforcement, and is the conventional ‘relief edge’ still
applicable in a CRCP roundabout given the contraction in cooler months of the ‘ring’
as a whole?
The roundabout design for industry feedback have been included in Annexure A, with SFCP
design for comparison purposes included in Annexure B.
Recommendations
Subject to industry feedback on the proposed designs, inclusion of CRCP as an alternative
to SFCP roundabouts is recommended. The most appropriate pavement type can then be
selected for individual sites to suit traffic staging.
Construction of a trial CRCP roundabout is encouraged, with a notable opportunity being the
Pacific Highway Woolgoolga to Ballina project, where several roundabouts are proposed.
ASCP 4th Concrete Pavements Conference 15
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Acknowledgements:
The comments and views expressed in this paper are those of the author and not
necessarily of Aurecon.
The author would like to acknowledge the following people:
▪ Luc Rens and Anne Beeldens for kindly hosting the ASCP delegation in Belgium
2014.
▪ Tamworth Regional Council (TRC), for permission to publish the case study of the
roundabout on the New England Highway, and to Geoff Ayton for his assistance in
this regard.
References:
1. Austroads Guide to Pavement Technology Part 2: Pavement Structural Design,
2012
2. Debroux, R.Dumont, R. Ployaert, C. Roundabouts in Continuously Reinforced
Concrete Design – Construction, 8th International Symposium on Concrete Road,
Lisbon, September 1998
3. Plei, Michael N. Roundabouts Built with CRCP, modernroads.net/blog/texas-crcp-
roundabouts, June 2016.
4. Rens, L. Concrete Roundabouts, European Concrete Paving Association
(EUPave), December 2013
5. Roads and Maritime NSW, CRCP Standard Drawings Series ‘CC’, January 2016
6. Roads and Traffic Authority (RTA) NSW, Concrete Roundabout Pavements; A
Guide to their Design and Construction, 2004
7. Stet, Marc J.A, van Leest, Adrian J, Jurriaans, George, Guidelines for Concrete
Roundabouts; The Dutch Practice,
ASCP 4th Concrete Pavements Conference 16
CRCP Roundabouts – A Theoretical Case Study, Tim Buckingham-Jones
Annexures
Annex A – CRCP Roundabout Design Examples
Figure A.1 – George Booth Roundabout CRCP Jointing Plan
Figure A.2 – Eungai Roundabout (West) CRCP Jointing Plan
Figure A.3 – Typical Cross Sections
Annex B – SFCP Roundabout Design Examples
Figure B.1 – George Booth Roundabout SFCP Jointing Plan
Figure B.2 – Eungai Roundabout (West) SFCP Jointing Plan
1A.3
BARRIER KERB ANDGUTTER (TYPE SA)
MOUNTABLEKERB (TYPE SF)
MOUNTABLEKERB (TYPE SF)
MOUNTABLE KERB ANDGUTTER (TYPE SE)
BARRIER KERB (TYPE SM)
BARRIER KERB ANDGUTTER (TYPE SA)MOUNTABLE
KERB (TYPE SF)
BARRIER KERB ANDGUTTER (TYPE SA)
BARRIER KERB ANDGUTTER (TYPE SA)
MOUNTABLEKERB (TYPE SF)
4.0
4.0
VARIES
TYPE 12 TERMINAL ANCHOR ATINTERFACE WITH BRIDGEAPPROACH SLAB
TYPE 6 TERMINAL ANCHORAT INTERFACE WITHFLEXIBLE PAVEMENT
TYPE 6 TERMINAL ANCHORAT INTERFACE WITHFLEXIBLE PAVEMENT
TYPE 6 TERMINAL ANCHOR ATINTERFACE WITH FLEXIBLE PAVEMENT
BLOCKOUT FORDRAINAGE PITS
BLOCKOUT FORDRAINAGE PITS
INNER RADIUS: 20 m
OUTER RADIUS: ~30 m
SEE INSET
LONGITUDINALCONSTRUCTIONJOINT (TYPE C2)
N12 TIEBARS
INSET - REINFORCING PLANNOT TO SCALE
LONGITUDINALCONSTRUCTIONJOINT (TYPE C2)
N16 TIED UNDERTERMINATING 'C' BARSN12 TRANSVERSESTEEL 'A' BARSN16 LONGITUDINALSTEEL 'C' BARS
CONST. JOINT (TYPE C2)
KERB ANDGUTTER (TIED)
N12 TRIMMER BARS ATRE-ENTRANT ANGLE
KERB ANDGUTTER (TIED)
C2
C2
F2
F2
F2
F2
F14
F14
F2
C2
C2
C2
C2
C2
C2
F2
F2
F2
F2
C2
F2
F2F2
C2
C2
C2
C2
C2
C2
C2
C2C2
F2F2F2
F7
F2
F14
C2
F2
F14
F14
F2
F2
F2
F14
F2
F2
F2
F2
F14
F14
F14
F2
F8
T
Y
P
F
8
F8
T
Y
P
F
8
F8
T
Y
P
F
8
F
8
T
Y
P
F
8
F
8
T
Y
P
F
8
F8
T
Y
P
F
8
F
8
T
Y
P
F
8
C2C2
C2C2
C2C2
F2
F2
1.0 MIN.
NOTES1. FOR CRCP DETAILS REFER TO ROADS AND MARITIME
STANDARD DRAWINGS SERIES 'CC' EDITION 4 REVISION 0.FOR SFCP DETAILS REFER TO ROADS AND MARITIMESTANDARD DRAWINGS 'SFCP FOR ROUNDABOUTS' EDITION4 REVISION 0.
SFCP JOINT TYPE (NOTE 1)
TERMINAL ANCHOR (NOTE 1)
CRCP SLAB
CRCP JOINT TYPE (NOTE 1)C2
F2
LEGEND
SFCP SLAB
SFCP-R SLAB (MESH REINFORCED)
SCALE George Booth Roundabout CRCP Jointing Plan CRCP Roundabouts
Figure A.1
0 10 20 m
2A.3
3
.5
3
.4
BARRIER KERB ANDGUTTER (TYPE SL)
BARRIER KERB ANDGUTTER (TYPE SL)
MOUNTABLE KERB(TYPE SF)
MOUNTABLE KERB(TYPE SF)
BARRIER KERB(TYPE SM)
TYPE 12 TERMINAL ANCHOR ATINTERFACE WITH BRIDGEAPPROACH SLAB
TYPE 6 TERMINAL ANCHOR ATINTERFACE WITH PCP RAMPPAVEMENTS
TYPE 6 TERMINAL ANCHOR ATINTERFACE WITH FLEXIBLE PAVEMENT
TYPE 6 TERMINAL ANCHORAT INTERFACE WITH PCPRAMP PAVEMENTS
F14
F14
C2
C2
C2
C2
F2
F2
F2
F2
F2
F2
C2
C2
F2 C2
F2
C2
C2
F2
C2
F2
F2
F2
F8
T
Y
P
F
8
F8
T
Y
P
F
8
F8
F8
F14
F14F14
F14
C7
C2
C2
C2
C2
C2
INNER RADIUS: 23 mOUTER RADIUS: 30 m
SCALE Eungai Roundabout (West) CRCP Jointing Plan CRCP Roundabouts
Figure A.2
0 10 20 m
NOTES1. FOR CRCP DETAILS REFER TO ROADS AND MARITIME
STANDARD DRAWINGS SERIES 'CC' EDITION 4 REVISION 0.FOR SFCP DETAILS REFER TO ROADS AND MARITIMESTANDARD DRAWINGS 'SFCP FOR ROUNDABOUTS' EDITION4 REVISION 0.
SFCP JOINT TYPE (NOTE 1)
TERMINAL ANCHOR (NOTE 1)
CRCP SLAB
CRCP JOINT TYPE (NOTE 1)C2
F2
LEGEND
SFCP SLAB
SFCP-R SLAB (MESH REINFORCED)
TYPICAL CROSS SECTIONGEORGE BOOTH ROUNDABOUT
SECTION 1A.1SCALE 1 : 50
LMC SUB BASECRCP
LANDSCAPED MEDIAN 7003500400040002000
TYPE SM BARRIER KERB
TYPE SE MOUNTABLEKERB AND GUTTER
TYPE SA BARRIERKERB AND GUTTER
TRAVEL LANE5000
TRAVEL LANE6000
CIRCULATING CARRIAGEWAY11000500 CLEAR
MESH REINFORCEDCONCRETE INFILL
CROSSFALL
NO FINES CONCRETE EDGEDRAIN WRAPPED IN GEOTEXTILE
C2C2C2C2
TYPICAL CROSS SECTIONEUNGAI ROUNDABOUT (WEST)
SECTION 1A.2SCALE 1 : 50
LMC SUB BASECRCP
500 3400 3500
TYPE SL BARRIERKERB AND GUTTER
CIRCULATING CARRIAGEWAY6900
CROSSFALL
NO FINES CONCRETE EDGEDRAIN WRAPPED IN GEOTEXTILE
LANDSCAPED MEDIAN
500
TYPE SL BARRIERKERB AND GUTTER
MESH REINFORCED CONCRETE
C2
500
OVERRUN AREA FORHEAVY VEHICLES
SCALE Typical Cross Sections CRCP Roundabouts
Figure A.3
(As noted)
BARRIER KERB ANDGUTTER (TYPE SA)
MOUNTABLEKERB (TYPE SF)
MOUNTABLEKERB (TYPE SF)
MOUNTABLE KERB ANDGUTTER (TYPE SE)
BARRIER KERB (TYPE SM)
BARRIER KERB ANDGUTTER (TYPE SA)
MOUNTABLEKERB (TYPE SF)
BARRIER KERB ANDGUTTER (TYPE SA)
BARRIER KERB ANDGUTTER (TYPE SA)
MOUNTABLEKERB (TYPE SF)
TYPE 12 TERMINAL ANCHOR ATINTERFACE WITH BRIDGEAPPROACH SLAB
TYPE 6 TERMINAL ANCHORAT INTERFACE WITHFLEXIBLE PAVEMENT
TYPE 6 TERMINAL ANCHORAT INTERFACE WITHFLEXIBLE PAVEMENT
TYPE 6 TERMINAL ANCHOR ATINTERFACE WITH FLEXIBLE PAVEMENT
BLOCKOUT FORDRAINAGE PITS
BLOCKOUT FORDRAINAGE PITS
INNER RADIUS: 20 mOUTER RADIUS: ~30 m
4.3
2.0
4.0
4.0
4.0
4.0
2.5MIN
F2
F2
F2
F14
F14
F14
F14
F7
F7
F7
F7
F7
F7
F7
F7
F7
F7
F7
F7
F2
F14
F2
F2
F2
F14
T
Y
P
F
8
T
Y
P
F
8
F7
F2
F2
F2
F2
Kf4
F1
F7
F2
F14
F7
F2
F2
F14
F2
F2
F2
F1
F2
F1
F14
F2
F2
F2
F2
F7
F
1
4
F14
F4
F4
F2
T
Y
P
F
8
T
Y
P
F
8
SCALE George Booth Roundabout SFCP Jointing Plan CRCP Roundabouts
Figure B.1
0 10 20 m
NOTES1. FOR CRCP DETAILS REFER TO ROADS AND MARITIME
STANDARD DRAWINGS SERIES 'CC' EDITION 4 REVISION 0.FOR SFCP DETAILS REFER TO ROADS AND MARITIMESTANDARD DRAWINGS 'SFCP FOR ROUNDABOUTS' EDITION4 REVISION 0.
SFCP JOINT TYPE (NOTE 1)
TERMINAL ANCHOR (NOTE 1)
SFCP WITH MESH (SFCP-R)
F2
LEGEND
3.5
3.5
F2
F14
F2
F2
F2
F2
F2
F14
F2
P7
F2
F2
F2
F14
F2
F2
F2
F2
F2
F2
F2
F2
F2
F6
F2
F14
F2
F2
F8
F2
P7
T
Y
P
F
8
T
Y
P
F
8
T
Y
PF
8
T
Y
P
F
8
TY
P
F8
T
Y
P
F
8
T
Y
P
F
8
TYP
F8
T
Y
P
F
8
F8
F8
F14
K4
K4
F14
K4
F14
F8
TYPE 12 TERMINAL ANCHOR ATINTERFACE WITH BRIDGEAPPROACH SLAB
TYPE 6 TERMINAL ANCHOR ATINTERFACE WITH PCP RAMPPAVEMENTS
TYPE 6 TERMINAL ANCHOR ATINTERFACE WITH FLEXIBLE PAVEMENT
TYPE 6 TERMINAL ANCHORAT INTERFACE WITH PCPRAMP PAVEMENTS
SCALE Eungai Roundabout (West) SFCP Jointing Plan CRCP Roundabouts
Figure B.2
0 10 20 m
NOTES1. FOR CRCP DETAILS REFER TO ROADS AND MARITIME
STANDARD DRAWINGS SERIES 'CC' EDITION 4 REVISION 0.FOR SFCP DETAILS REFER TO ROADS AND MARITIMESTANDARD DRAWINGS 'SFCP FOR ROUNDABOUTS' EDITION4 REVISION 0.
SFCP JOINT TYPE (NOTE 1)
TERMINAL ANCHOR (NOTE 1)
SFCP WITH MESH (SFCP-R)
F2
LEGEND