attachment d · 2015-02-17 · attachment d waddock composting epa licence application page 9 of 22...
TRANSCRIPT
Attachment D
Waddock Composting EPA Licence Application Page 1 of 22
Attachment D
Infrastructure & Operation
Attachments in this section include:
D.1 Operational Information Requirements
D.2 Additional Requirements for Waste Activities not Covered Above or Elsewhere
D.2.1 Wastes to be Accepted
D.2.2 Waste Acceptance Procedures
D.2.3 Waste and Material Outputs from Waste Activities
D.2.4 Principles of Self Sufficiency and Proximity
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 2 of 22
Attachment D.1: Operational Information Requirements Development History Established in 2005, Waddock Composting Facility, Ltd. is a Local Authority permitted and
Department of Agriculture Animal By Products approved composting facility utilising in-vessel
batch tunnel technology to produce high-quality compost for agricultural, horticultural,
landscaping and gardening markets. Located in north County Carlow, the facility is 6 KM off
of the new M9 motorway from Exit 4 for Castledermot making it easily accessible from the
Midlands, Leinster and parts of Munster.
In 2010, the facility was upgraded to increase capacity and improve environmental
performance and management, especially in relation to odour control. The facility utilises a
state-of-the-art process control system that allows the Operator to fully manage the
composting process and track batches through the facility for traceability purposes.
The upgrade included a state-of-the-art tipping building and mixing area, six purpose-
built sealed composting tunnels, upgraded process control, ventilation and odour control
systems and fire retention tanks complete with rainwater harvesting.
In September 2011, Waddock Composting was issued with an updated permit for this site
from Carlow County Council, register number WFP-CW-11-05-01. This permit outlines the
scope of activities permitted on site in accordance with the Third Schedule, Part I, of the
Waste Management (Facility Permit and Registration) Regulations 2007 as amended.
In 2013, Waste Facility Permit Number WFP-CW-13-1 was issued to Waddock Composting by
Carlow County Council. The permitted tonnage under this permit is 24,999 tonnes per annum.
The following attachment describes the plant, methods, processes and operations of
Waddock Composting Facility Ltd.
Facility Design Hardstand and Drainage The entire facility and perimeters of the waste buildings are paved in impermeable concrete
hardstand with the exception of the car parking area and an area at the back of the facility
which is hard standing.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 3 of 22
Photograph1:
The waste building is completely
surrounded by drainage infrastructure at
all areas where potential foul run off may
be emitted. This is in the form of ACO
drains on all hardstanding areas
highlighted in the photograph 1 above.
A concrete “moate” style drainage channel
between the car parking area and the
adjacent side of the building as highlighted
in the photograph below diverts clean
rainwater to the surface water drainage.
Photograph 2:
Sewerage and Surface Water Drainage Infrastructure Leachate from within the composting building is diverted to the underground leachate
collection holding tank. This leachate is fed back and reused in the composting process. In the
event that any excess leachate runoff that is not reused in the process arises, this is sent to
Athy Waste Water Treatment Plant. All rainwater runoff from the site area beyond the ACO
drains is diverted to the surface water pipework which drains into the stream running along
the eastern boundary of the facility and feeds into the Aghalona River. See Facility Layout Plan
Drawing 2.
As part of this licence application it is proposed to install a Class 1 full retention interceptor
at the facility. Once this interceptor is installed, all surface water runoff will be diverted to the
interceptor prior to discharge to the surface water stream.
The only foul water at the facility is from the facility offices. This waste water is diverted to
the on-site septic tank.
Please refer to attached drawing numbers Drawing 1, Drawing 2, Drawing 3, and Drawing 4
for details of existing and proposed drainage infrastructure at the facility as well as roof water
collection system layout.
Site Security The site is bounded on all sides by security stock proof fencing and concrete block walls. The site entrance is via locked security gates and all buildings are secured with roller shutter doors and Security lights that come on at night.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 4 of 22
Site Access The facility is well serviced with road networks and is located close to the M9 motorway and is accessed along the R418.
Design and Location of Fuel Storage Areas
Fuels stored on-site include diesel, engine and hydraulic oils. All fuels and oils used at the
facility are stored in bunded areas. The diesel tank on-site is a self bunded diesel bouser. All
oils are stored in a locked storage container in bunds. Material Safety Data Sheets are
maintained on-site for all fuels and chemicals. Sufficient absorbent materials and spill kits are
maintained on-site to deal with any potential or accidental spillages or leaks. Designated staff
are trained in the use of spill kits and how to handle a fuel or oil spill.
Waste Inspection Area
Waste tipping and inspection areas have been designated in the reception building. All waste
is inspected upon arrival at the weighbridge prior to tipping into one of three submerged
tipping bunkers where the waste is inspected to ensure that the material conforms to the
waste acceptance criteria. The waste inspection and tipping area can be seen on the attached
Site Layout Plan Drawing 1. A procedure for waste acceptance SOP#01 is attached to Section
C of this application. This describes the criteria for waste acceptance and procedure for
checking all loads prior to and following acceptance.
All waste is inspected upon entry and upon tipping to ensure that the waste is acceptable.
Any non-acceptable items identified are rejected from the facility at this stage and reloaded
back onto the same receptacle/container.
Composting Infrastructure Tables 1 and 2 below set out the principal processing plant and equipment on-site:
Table 1. Principal Processing Plant and Equipment
Machine Make Model Registration Serial Number
Loading Shovel JCB 437 HT 141 CW 704
Loading Shovel JCB 414 S 12 CW 892 1242623
Trommel Screen Redwood Systems WAD280313 2013 WAD280313
Power Washer Honda GX 340 (Red)
Electric Steam Washer
Karcher HDS-10/20-4M 010988
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 5 of 22
Table 2. Environmental Equipment Log:
Equipment Type
Ventilation Fan 22 KW
Primary Composting Bay 1,2 & 3 Inlet Fan 15 KW
Primary Composting Bays Extraction Fan 37 KW
Scrubber Pump 7.5 KW
ABP 1,2,3 & 4 Inlet & Outlet Fans 4 KW
Temperature Probes PT100 3 Wire
Manual Temperature Probe Reotemp
Leachate Recirculation pump Submersible pump
Manual PH metres Oakton
Fire Extinguishers Aenor
Process Control Software Program Scada
The main composting infrastructure currently consists of a waste intake area with three
tipping bays, temporary storage area, six primary composting bays, four ABP composting
tunnels, six footbaths, screening plant, biofilter and ancillary equipment as detailed in the
table above.
The tipping area is totally enclosed with three rolling doors at the back of the facility to allow
collection or delivery vehicles to tip their loads from the delivery area into one of three
submerged or below-grade bunkers within the enclosed reception shed.
The tipping area has sufficient space to store fresh bulking materials (wood chips, hay,
sawdust, etc.) and oversized materials from the screening process. By tipping and storing
different materials in their own individual areas, the operator has the ability to control the
mixing and blending process.
The inside dimensions of the composting tunnels are 20 x 5.7 x 5m (l*w*h). Each of the
tunnels are controlled by the Redwood composting process control system. This The
Redwood process computer is located in the operator’s control room located in the main
facility offices. The custom designed software allows dynamic control and pre-programming
of process key setpoints for each composting activity or unit. All results are monitored,
recorded and displayed on the computer screen on a continual basis. Recorded results are
compared to setpoint data simultaneously.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 6 of 22
Based on this comparison and the range tolerance specified for process variables, the
computer adjusts air and water flows and conditions affecting the tunnels, the building area,
the scrubbers and the biofilter. Access to the Redwood System is tightly controlled and is
restricted to Managers with in depth knowledge of the composting process are trained on
and have access to the Redwood software control system.
The Operating Manual for the Redwood system is attached to this section.
The Maintenance of Machinery & Environmental Equipment is set out in SOP#12 attached in
Section C of this application.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 7 of 22
Processes Composting Process – Waste Acceptance and Treatment Standard Operating Procedure SOP#02 in Section C of this application details all of the processing steps necessary to produce a pasteurised and safe compost product in accordance with Conditions for Approval and Operation of Composting Plants Treating Animal By-Products in Ireland, EU Regulation (EC) No. 1774/2002 and Waste Facility Permit No. WFP-CW-13-1. The processing of animal by-products by the Waddock Composting Facility consists of the following ten steps:
1. Feedstock reception 2. Feedstock preparation 3. Temporary storage of blended feedstocks 4. Primary tunnel composting 5. Turning and primary tunnel composting repeated 6. Screening to 12mm 7. Pasteurisation tunnel composting (1st barrier) 8. Turning and pasteurisation tunnel composting (2nd barrier) 9. Pathogen testing 10. Maturation, product storage and release
These steps are described in detail in Standard Operating Procedure SOP #02 and Odour Management Plan attached in Section C of this application. Cleaning of Delivery Area, Intermediate Area and Trucks Leaving the Facility The facility is designed with clean, intermediate and dirty areas in line with Animal By Product
Regulations as per the process flow diagram Drawing 6 below (a larger version of Drawing is
also attached.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 8 of 22
Drawing 6, Process Flow Diagram
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 9 of 22
A power wash is in place at the facility in accordance with the requirements of the Animal By
Products Regulations and is a critical aspect of the on-site HACCP Plan. The power washer is
connected to rain water harvesting system firstly and is backed up by the mains water supply.
All vehicles tipping in the delivery area must be washed down if necessary.
If a machine or equipment needs to exit the reception building for Maintenance, repair,
replacement, etc. they are washed with a steam power washer or a cold powerwasher with
Jet 5 Hydrox 5 or similar disinfectant (active ingredient is peroxyacetic or peracetic acid) and
recorded on LOG #18 Machinery & Equipment Existing Reception Shed Cleaning Log.
Standard Operating Procedure SOP#03 attached in Section C describes in detail the procedure
for cleaning the delivery area. Standard Operating Procedure SOP#15 attached in Section C
describes the procedures in place for cleaning plant and vehicles leaving the shed.
Standard Operating Procedure SOP#06 attached in Section C describes the procedures for
ABP Tunnel Inspection, Filling, Sealing within the pasteurization tunnels & Cleaning of the
Intermediate Area. This procedure includes layout plans of the clean, intermediate and dirty
areas of the facility.
Abatement The necessary pieces of environmental abatement equipment at the facility are the biofilter and the silt trap and proposed interceptor. Biofilter An open-vessel biofilter system consisting of a media bed containing contaminant degrading microorganisms, a media support structure, a foul air distribution system, and a sprinkler system method of controlling the biofilter moisture content is in place at the facility. The media can consist of various materials including soil, woodchip, peat, compost, sand or synthetic material (plastic packing material). Typically, the foul airstream to be treated is distributed over the bottom of the biofilter bed and forced upward through the media. The moist filter media provides physical and chemical conditions appropriate for the transfer of the contaminants from the vapour phase and supports microbial biodegradation of the adsorbed and absorbed contaminants. A full specification of the biofilter is attached to this section. Figure 1 below is a simplified schematic of Waddock Composting Facility’s biofilter.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 10 of 22
Figure 2 - Biofilter Schematic
A foul airstream containing biodegradable organic and inorganic odorous compounds passes through an air-distribution system underneath the filter medium. The air piping system is set on cement blocks to raise it off the ground so the air can be evenly distributed under the pipe. A medium such as chip wood with a particle size up to 100mm is spread loosely and evenly over the air distribution system. The old woodchip is screened along with the new woodchip at a rate of 4:1 through a 12mm trommel and the >12mm woodchip is placed around the pipes up to a height of 1.5m and then the 0 – 100mm is placed to the full height of 3m. By mixing the new with the old woodchip, reintroduction of the bacteria into the new media bed takes place. The media provides an environment for microorganisms that biologically degrade the odorous compounds. Interceptor It is proposed to install a Class 1 Full Retention Interceptor at the facility the details of which are attached labelled “Interceptor Data Sheet”. The proposed location of this is detailed in Drawing 2 attached.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 11 of 22
Ancillary Processes Traffic Control A traffic management system is in place at the facility. All vehicles enter and exit the facility
via the main entrance facility which is outlined in Drawing 6 above. Due to the location of the
site entrance there is sufficient vehicle queuing space for all vehicles.
A speed limit of 10km/hr is in place at the facility. Vehicles are directed to the tipping area by
the weighbridge operative who control the volume of vehicles to each of the buildings.
All Other Services
Other services at the facility include ESB which is supplied from the National Grid Network.
Water is supplied to the facility from the mains. Rain water is also harvested on site.
A telecommunications service is set up at the facility offices. This enables external
communications to be made by phone, fax or email.
Site Accommodation On-site accommodation includes facility offices, welfare facilities and a staff canteen as
outlined in the site layout plan Drawing 1.
Fire Control System A system for fire control is in place at the facility. Fire extinguishers are placed at fire point
locations throughout the facility and are serviced on an annual basis (or as used) by an
external contractor. All staff are trained in fire safety.
Fire fighting water retention tanks have been installed at the facility. These tanks are concrete
tanks with a capacity of 13,948 gallons per tank. Two tanks have been installed at the facility
giving a total of 27,896 gallons of available water that can be used for fire fighting in the event
of a fire at the facility.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 12 of 22
D.2 Additional requirements for waste Activities (not covered above or elsewhere) (All Class 11
of the First Schedule of the EPA Act 1992, as amended)
D.2.1 Wastes to be accepted
The maximum annual tonnage of waste to be handled at the site and the year to which the quantity
relates is indicated as follows:
Maximum Annual Tonnage (tonnes) 24,900
Year 2015
Table 3. Attachment D.2 details the waste types to be accepted
EWC Code
Waste Description Waste description
Tonnes per annum (2013)
Tonnes per annum (2014)
Tonnes per annum Proposed 02 01
Wastes from agriculture, horticulture, aquaculture, forestry, hunting and fishing.
(the actual description of the waste, not the text accompanying the EWC code)
02 01 01 Sludges from washing and cleaning
Washings 64.56 0 100
02 01 02 Animal tissue waste 20
02 01 03 Plant tissue waste 20
02 01 05 Animal faeces, urine and manure (including spoiled straw), effluent 780
02 01 07 Waste from forestry 20
02 02
Wastes from the preparation and processing of meat, fish and other foods of animal origin
02 02 01 Sludges from washing and cleaning 20
02 02 02 Animal tissue waste 20
02 02 03 Materials unsuitable for consumption or processing 20
02 02 04 Sludges from on-site effluent treatment
Factory Sludge 1,399.78 1129.44 20
02 02 99 Wastes not otherwise specified Monashell 3.04 10
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 13 of 22
02 03
Wastes from fruit, vegetables, cereals, edible oils, cocoa, coffee, tea and tobacco preparation and processing; conserve producton; yeast and yeast extract production, molasses preparation and fermentation
02 03 01 Sludges from washing, cleaning, peeling, centrifuging and separation 20
02 03 04 Materials unsuitable for consumption or processing
Fruit & Veg 81.8 0 100
02 03 05 Sludges from on-site effluent treatment 20
02 03 99 Wastes not otherwise specified 20
02 04 Wastes from sugar processing
02 04 03 Sludges from on-site effluent treatment 20
02 05 Wastes from the dairy products industry
02 05 01 Materials unsuitable for consumption or processing (from dairy industry)
Whey/Milk Products
100.18 68.12 150
02 05 02 Sludges from on-site effluent treatment
Dairy Sludge 95.72 30.6 50
02 06 Wastes from the baking and confectionary industry
02 06 01 Materials unsuitable for consumption or processing (from baking and confectionary) 20
02 06 03 Sludges from on-site effluent treatment
Factory Sludge 760.28 1360.32 1200
02 07 Wastes from the production of alcoholic and non-alcoholic beverages
02 07 01 Wastes from washing, cleaning and mechanical reduction or raw materials 20
02 07 02 Wastes from spirit distillation Brewers Grain 163.04 190.94 200
02 07 04 Materials unsuitable for consumption or processing
Kieseluhr 42.86 0 50
02 07 05 Sludges from on-site effluent treatment
Distillation Sludge 0 13.46 100
02 07 99 Waste not otherwise specified 20
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 14 of 22
03 01 Wastes from wood processing and the production of panels and furniture
03 01 01 Waste bark and cork 20
03 01 05 Sawdust, shavings, cuttings, wood, particle board and veneer 20
03 03 Wastes from pulp, paper and cardboard production and processing
03 03 01 Waste bark and wood 20
03 03 05 De-inking sludges from paper recycling 20
03 03 08 Wastes from sorting of paper and cardboard destined for recycling 20
03 03 11 Sludges from on-site effluent treatment other than those mentioned in 03 03 10 20
04 02 Wastes from the textile industry
04 02 10 Organic matter from natural products (for example grease, wax) 20
04 02 20 Sludges from on-site effluent treatment other than those mentioned in 04 02 19 20
07 05 Wastes from the MFSU of chemicals
07 05 12 Sludges from on-site effluent treatment other than those mentioned in 07 05 11 20
07 05 14 Solid wastes other than those mentioned in 07 05 13 20
07 05 99 Wastes not otherwise specified 20
15 01 Packaging (including separately collected municipal packaging waste)
15 01 03 Wooden Packaging 20
1502 Absorbents, filter materials, wiping cloths and protective clothing
15 02 03 Absorbents, filter materials, wiping cloths and protective clothing 20
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 15 of 22
17 02 Wood, glass and plastic
17 02 01 Wood 20
19 02 Waste from the physico/chemical treatment of wastes
19 02 06 Sludges from physico/chemical other than those mentioned in 19 02 05
20
19 06 Wastes from the anaerobic treatment of waste
19 06 06 Digestate from anaerobic treatment of animal and vegetable manure 20
19 08 Wastes from water treatment plants not otherwise specified
19 08 05 Sludges from treatment of urban waste water
Sewer Sludge 1,958.72 1127.66 20
19 08 09 Grease and oil mixture from oil/water separation containing only edible oil and fats
Sludge 220.3 150.92 200
19 08 99 Wastes not otherwise specified 20
19 09
Wastes from the preparation of water intended for human consumption or water from industrial use
19 09 01 Solid waste from primary filtration and screenings 20
19 09 02 Sludges from water clarification Alumn Sludge 1,641.26 1975.96 1200
19 09 04 Spent activated carbon Sludge 20
19 12 Wastes from the mechanical treatment of waste not otherwise specified.
19 12 07 Wood other than those mentioned in 19 12 06 600
19 12 12
Other wastes (including mixtures of materials) from mechanical treatment of waste other than those mentioned in 19 12 11 20
20 01 Seperately collected fractions
20 01 01 Paper and Cardboard 20
20 01 08 Biodegradable kitchen and canteen waste
Food Waste 10,978.81 15,388.30 18500
20 01 25 Edible oil and fat Grease Trap 392.02 593.06 800
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 16 of 22
20 02 Garden and park waste
20 02 01 Biodegradable waste (garden and park wastes)
Green waste 18.18 4.4 100
20 03 Other municipal wastes
20 03 01 Mixed municipal waste 0 0 20
20 03 04 Septic tank sludge Septic Sludge 2.4 8.36 20
TOTAL 17922.95 22041.54 24900
Certain wastes to be accepted are classified as animal by-products in accordance with Regulation
1069/2009.
The following table 4 shows the waste types to be accepted at the facility which are classified as animal by-products:
Table 4: Waste types to be accepted at the Facility which are classified as ABP
Waste Description
EWC Code
ABP
Designation
Hazardous
Waste (Yes or
No)
Food Waste 20 01 08 Yes No
Animal Tissue Waste 02 01 02 Yes No
Animal faeces, urine and manure
(including spoiled straw), effluent
02 01 05 Yes No
Sludges from Washing and Cleaning 02 02 01 Yes No
Animal Tissue Waste 02 02 02 Yes No
Materials unsuitable for consumption or processing
02 02 03 Yes No
Sludges from onsite effluent treatment 02 02 04 Yes No
Dairy Sludge 02 05 02 Yes No
Whey/Milk Products 02 05 01 Yes No
Mixed Municipal Waste 20 03 01 Yes No
Other wastes (including mixtures of materials) from mechanical treatment of waste other than those mentioned in 19 12 11
19 12 12 Yes No
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 17 of 22
D.2.2 Waste Acceptance All materials are accepted at the facility in accordance with the Waste Acceptance Procedure
SOP#1 attached and the Procedure for Facility Operation and Efficient Process Control SOP#2
attached in Section C. Prior to entry to the waste buildings details of the load are recorded on
the weighbridge docket, including vehicle registration, waste type, EWC code, date, time,
haulier, customer and the gross weight of the load. Once these details have been recorded
and an initial waste inspection is carried out, the driver is directed to the correct tipping area
for the particular waste type.
Once the waste has been tipped in the waste inspection area, has been subject to inspection
and considered to be acceptable the driver is directed back onto the weighbridge for second
weighing after the vehicle has been washed. Once the vehicles un-laden weight is recorded a
nett weight is generated, a ticket is printed. Tickets for all loads are printed on quadruplicate
dockets. One copy is given to the driver, one is retained for invoicing and one is placed in the
Batch Profile Folder as records for inspection from regulatory bodies such as the County
Council; Department of Agriculture, Fisheries and Food or the EPA. The fourth copy is placed
into a separate folder for future reference once all the necessary logs have been completed.
If a load arrives at the facility which is deemed to contain unacceptable material, the load is
not accepted and is rejected at the gate to the facility.
Where a load has been tipped and non-conforming materials are found to be present in the
load, the non-conforming material is reloaded and is removed off-site to an appropriately
licenced treatment facility as soon as practicable. The supplier of the non-conforming waste
is informed.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 18 of 22
D.2.3 Waste and material outputs from waste activities
Waste Outputs
The following residual waste outputs are generated at the facility and account for approximately
12% of the overall intake tonnage. Currently, the residual waste is sent to Powerstown Landfill or
Drehid Landfill.
Table 5: Residual Waste Outputs
Waste Description
EWC Code
Hazardous
(Yes or No)
Non Composted Fraction 19 05 01 No
Overs 19 05 99 No
Sewer Sludge Removed 19 08 05 No
Catering Waste Returned 20 01 08 No
Material Outputs
Approximately 88% of the output from the facility is high-quality compost material for agricultural,
horticultural, landscaping and gardening markets.
The requirements of article 28 of the European Communities (Waste Directive) Regulations 2011
are addressed as follows:
The end product produced at the facility is in strict compliance with the Compost Quality Standard
set out in the waste facility permit which states:
No sample shall exceed 1.2 times the quality limit values set. The following criteria (where they apply to compost) are
deemed a quality standard for the use of compost as a soil improver and should not be deemed as criteria for fertiliser.
In addition N, P, K, NH4-N, NO3-N, pH and dry matter content should also be measured.
A. Compost Maturity
The state of the curing pile must be conducive to aerobic biological activity.
Compost shall be deemed to be mature if it meets two of the following groups of requirements or other maturity test
as may be agreed by the Council:
1. Specific Oxygen Uptake Rate < 13 mmol O2/kg OS/h (Bord Na Mona Test Method)
2. Compost will not re-heat upon standing to greater than 20 oC above ambient temperature and compost must
be cured for at least 21 days.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 19 of 22
Compost from Stabilised Biowaste, with non source segregated biowaste feedstock, shall meet the following
requirement:
1. AT4 test value of <10 mg O2/g DM
B. Trace Elements Concentration Limits (notes 1,2,3,7)
Parameter (mg/kg, dry mass) Compost Quality StandardsNote 5 Stabilised Biowaste Note 5
Class 1 Class 2
Cadmium (Cd) 0.7 1.5 5
Chromium (Cr) 100 150 600
Copper (Cu) 100 150 600
Mercury (Hg) 0.5 1 5
Nickel (Ni) 50 75 150
Lead (Pb) 100 150 500
Zinc (Zn) 200 400 1500
PolyChlorintated Biphenyls (PCB’s) - - 0.4
Polynuclear Aromatic Hydrocarbons (PAH’s) - - 3
Impurities >2mm Note 6 <0.5% <0.5% <3%
Gravel and Stones >5mm Note 6 <5% <5% -
Note 1: These limits apply to the compost just after the composting phase and prior to mixing with any other materials.
Note 2: Incoming sludges (other than sewage sludges) shall be monitored quarterly (on a client by client basis) for the
parameters outlined in this table in addition to Selenium (Se) and Molybdenum (Mo).
Note 3: Monitoring of Arsenic (As) is required if waste timber is used in the composting process.
Note 4: The above alone should not be taken as an indication of suitability for addition to soil as the cumulative metal
additions to soil should be first calculated.
Note 5: Normalised to 30% organic matter content
Note 6: Compost must not contain any sharp foreign matter measuring over a 2 mm dimension that may cause damage
or injury to humans, animals and plants during or resulting from its intended use.
Note 7: Standards from Working Document on Biological Treatment of Biowaste, second edition 2001.
C. Pathogens
Each compost batch shall be monitored to ensure compliance with the following:
Pathogenic organism content must not exceed the following limits:
Salmonella sp. Absent in 25g n=5
Faecal Coliforms 1000 Most Probable Number (MPN) in 1g n=5
Where: n = Number of samples to be tested.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 20 of 22
Faecal coliforms should be sampled after the pasteurisation process.
D. Other Test Requirements
Where sewage sludge is part of the compost feedstock, and compost will be landspread, the test requirements outlined
in the following document are required: “Code of Good Practice for the use of Biosolids in Agriculture” DEHLG.
Where bio-stabilised waste is to be deposited at landfill it must meet the following standards:
Offensive odours are minimised and that the Respiration Activity after four days (AT4) is <10 mg O2/g DM (until 1-1-
2016), and <7 mg O2/g DM thereafter.
One test is required every 1,000 tonnes of stabilised biowaste.
In the event that there is an inadequate supply of biodegradable waste for composting Waddock
Composting Facility Ltd. proposes to accept MSW for drying/stabilisation. This material will be
handled in the exact same manner as the biodegradable waste and will be subject to the same
‘composting’ processes. There will be no mixing of this waste type and biodegradable waste in the
tunnels. Following stabilisation the compost like output (fines) will be screened from the bulk
material and used for landfill engineering. The residual fraction will be sent off site for manufacture
into Solid Recovered Fuel (SRF) or Refuse Derived Fuel or possibly for landfill. Because Waddock
Composting Facility Ltd has three waste acceptance bays the two waste streams can be accepted
without crossover and should Waddock Composting Facility Ltd. propose to accept MSW they will
provide a storage plan to the Agency prior to acceptance. This will detail where and how the
material will be stored prior to being stabilised and will also detail how the products from this
process will be stored on site prior to removal.
D.2.4 Principles of self-sufficiency and proximity
Waddock Compost Facility Ltd. is committed to the recycling of organic waste from all sources
including Household, Commercial and Industrial, and where appropriate Construction and
Demolition. Waddock Compost Facility Ltd. wishes to utilise its state of the art technology to
capacity and therefore requires an Industrial Emissions Licence to reflect the classes of waste
activity proposed. By doing this WCFL will contribute significantly to the national composting
tonnage capacity available to waste operators necessary to enable the diversion of biodegradable
waste from landfill.
This will contribute to Ireland’s efforts to meet EU targets of biodegradable municipal waste
(BMW) accepted at landfill for disposal as set out by the EU Landfill Directive (1999/31/EC).
The EU Landfill Directive (1999/31/EC) prescribes a staged reduction in the quantities of
biodegradable municipal waste (BMW) allowed to landfill.
The Landfill Directive imposes restrictions on the consignment of certain wastes to landfill. Landfill
operators must demonstrate that all waste accepted has been subjected to pre-treatment
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 21 of 22
effective from 16th July 2009 for facilities commenced since 16th July 2001. Article 5 of the
Directive sets mandatory targets for diversion of biodegradable municipal waste (BMW) from
landfill. It is now mandatory to reduce biodegradable municipal wastes (BMW) going to landfill to
35% of the total amount (by weight) that was produced in 1995 (427,000t) by 2016. An assessment
of risk carried out by the EPA in 2012 has found that Ireland is at risk of not meeting these statutory
obligations. The report also anticipates that municipal waste arising’s will increase by 825,000
tonnes (to 3.7m tonnes) within the next 15 years and found that; “the predicted growth of
municipal waste within the coming decade will necessitate investment in waste management
infrastructure”. The report also highlighted the need for much more rapid progress in the
provision of sustainable alternatives.
This subject development will provide a vital cog in the wheel of Ireland achieving these
mandatory targets by continuing to provide a processing facility for biodegradable material that
can be accepted for composting and treatment at the facility. Policy documents from the EU such
as ‘The Resource Efficiency Roadmap’ and the Governments document ‘A Resource Opportunity-
Waste Management Policy in Ireland’ highlight a sea change in opinion which now views BMW as
a valuable resource with a huge economical potential. They highlight that Ireland must also now
plan more fundamentally for alternative approaches that will allow us to effectively eliminate our
use of landfill within the next decade. The proposed development will contribute some of the
necessary infrastructure required to do this. Through the recycling and composting of organic
material at the subject development far more productive products (such as compost) are created
then would be the case if the facility did not exist and the material was simply landfilled.
Despite this looming landfill deadline of 2016 the recovery and recycling of organic waste in
Ireland is currently well below par. While the most pressing immediate driver must remain
compliance with the landfill Directive limits, the DEHLG policy document Waste Management
Policy in Ireland 2012 states that; ‘Ireland must also now plan more fundamentally for alternative
approaches that will allow us effectively to eliminate our use of landfill within the next decade’.
If permitted the subject proposal will recycle up to 24,900 tonnes of biodegradable waste and as
such will become an important player in helping to meet Ireland’s diversion targets and
requirement for progressive waste management infrastructure.
The location of the proposed development adjacent to the M9 Dublin to Waterford Motorway on
the Carlow Kildare border has the following advantages;
The existing land use policies for the site support the development of the subject
application and subsequently there are no non-conforming land uses immediately
surrounding the site. Most importantly the subject site is fundamentally suitable for
the location of the proposed development.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Attachment D
Waddock Composting EPA Licence Application Page 22 of 22
It is in close proximity to a large customer base, both from the South East Region and
from the Greater Dublin Area. The proximity (ca. 6km) of the M9 Dublin to Waterford
motorway means ease of access from significant customer base.
Its location on the site of the existing facility will mean that existing infrastructure can
be utilised to maximum capacity without the need for major structural development.
The existing site already has good quality infrastructure in place such as roads, services
(water and foul sewers), and telecommunications to support the subject
development.
There is no requirement for any additional construction at the facility.
Figure 3: Site Location
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Redwood Systems Operations & Technical Manual for
Waddock Composting Facility,
Killamaster,
Co. Carlow
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Contents Computer Operations ........................................................................................................................................................... 3
PLC Wiring .......................................................................................................................................................................... 24
PLC Input/Output List ...................................................................................................................................................... 31
Technical Data .................................................................................................................................................................... 36
Performance of Composting System at Waddock Composting, Killamaster, Co. Carlow ................................................... 37
Aeration System .......................................................................................................................................................... 37
Extraction System ........................................................................................................................................................ 37
Ventilation System ...................................................................................................................................................... 37
Bio Filter ...................................................................................................................................................................... 38
Scrubber...................................................................................................................................................................... 39
Overview of the Aeration and Extraction Systems of the Six tunnels. ........................................................................... 40
Fan Performance Data ........................................................................................................................................................ 41
List of Parts ......................................................................................................................................................................... 43
Aeration System .............................................................................................................................................................. 44
Extraction System ........................................................................................................................................................... 44
Ventilation System .......................................................................................................................................................... 44
Scrubber ......................................................................................................................................................................... 44
Dampers ......................................................................................................................................................................... 44
Probes............................................................................................................................................................................. 44
Control System ................................................................................................................................................................ 45
PLC Software ................................................................................................................................................................... 45
PLC Card Layout .............................................................................................................................................................. 46
Drawings ............................................................................................................................................................................. 47
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
Computer Operations
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
On start up of the CitectScada system, this is the screen that you are presented with which is called the Overview. This will give you the basic information on the performance of each bay; the inlet fan speed, the position of the damper, the controlling temperature of that bay and the outlet fan speed. On the bottom of the screen you are presented with 8 options which will give you further details on the control and management of the system. To access any of these you must have a Log In username and password.
OVERVIEW
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
This view gives a detailed description of each bay. From here you have full access and control to the running of the system. You can turn the motors on or off; change the speed of the motors, the position of the dampers and whether to run the system in manual or automatic. This is where you would enter the starting parameters for the automatic sequence (explained in Parameters).
PRODUCTION UNITS
Click here to change damper position
Click here to change motor speed
Pile number displayed here
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:39
To change anything in this section simply click on the item and, if it is amendable, you will be presented with a pop up window. For example if you are changing the position of the damper and you will be asked at what percentage you wish the damper to be open. Enter the number on the key pad and the damper will move to that position. Note: If a Bay is running in automatic you can still override the parameters in manual mode.
PRODUCTION UNITS
Click here to alter between manual and auto
Click here to enter parameters for automatic sequence
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
To create a new pile number click on one of the boxes as shown above. Once you click New Pile No. it is generated and stored in the database. The pile numbers are generated automatically in sequence. You can enter all the relevant information about that pile here i.e. description, screening date, mixing date etc. To move the pile from area to area click on the Target, select where you would like it moved to and click “move pile”. NB When making any changes ensure to press save pile.
Click here to enter information for a pile number.
Invoice no/ weighbridge no. goes here.
Description of product
Click here to generate a new pile number.
PRODUCTION UNITS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
A batch number is generated only in the ABP bays and is done so automatically as soon as the auto sequence is started.
PRODUCTION UNITS
Batch number generated in auto cycle on ABP bays.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
When an alarm is generated a detailed list appears in the Alarms section. From here you can see what and where the alarm is. To acknowledge an alarm double click it and it will turn a deeper red. Anything not acknowledged will remain a brighter orange colour. The alarm will continue to generate however, if the problem has not been resolved. A full history of alarms will continue to store here and can be viewed at any time
ALARMS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
At any time you can view the trend history of the bays. You will be presented with a split screen which will enable you load the information from 2 different bays, the same bay at different time intervals etc.
TRENDS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
By clicking on the folder as shown above you will be presented with a list of pre defined Bay trends containing all relevant parameters for that bay. The subsequent graph that is displayed is shown in real time with a default display of 10 minutes.
TRENDS
Click here to open up the pop up box shown
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
TRENDS
Click here to manually enter probes/alarms
Click here to show the individual information boxes (in yellow)
Moving this time line will give you a detailed description of the time interval selected.
Time interval displayed here
Click here to manually enter dates and times
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
When you choose the automatic mode you will be asked to enter a set of parameters for that sequence. On the first page a list of default operating limits for the inlet motor speeds will be on your left. Under that you have the option of setting offsets to the outlet speed for that production unit and damper for that bay. On the right is displayed the current Bay and 3 options. To change the set enter the appropriate bay and click Read Set. When you click the following pages the parameters for that bay can be seen. If you make any changes to the parameters for a Bay you must click Save Set to save them. Warning! By clicking Clear Set you will erase all parameters for that bay.
PARAMETERS
Default motor operating limits
Outlet and Damper offsets
Current Bay parameters
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
On the second page of the Parameters you will have an option of delaying the automatic start up in days, hours and minutes. You also have further options; to start on the delayed time entered only, or to start when either the delay time had expired or the product has reached a certain temperature.
Enter start up delay here
Enter temperature delay here
PARAMETERS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
On the third page of the Parameters you have the option of selecting the motor speeds for each temperature zone reached. In this example only one zone is displayed which instructs the fan to operate at 1250rpm up to a temperature of 15⁰C. If the temperature rises above this a further automatic sequence will begin (settings for which are on the next page). You can choose up to 5 different zones. For instance zone 2 could be: up to 25⁰C run at 1500rpm, zone 3 could be: up to 30⁰C run at 1750rpm and so on. Once the temperature rises above the last zones settings, the automatic sequence will follow on to the next step.
Enter cycle and duty times here
Choose number of zones here
Enter temperature and rpm settings here
PARAMETERS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
You have a further option of having the fan come on for set periods of time and then off again by utilising the cycle/duty option. If Always On is selected the fan will remain on for the duration of the sequence. If Timed is selected then the fan will still follow the auto sequence however it can be configured to only come on for say 10 minutes and off for 50 minutes. It will continue to do this repeatedly until deselected.
PARAMETERS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
On the fourth page of the Parameters is where you can specify the system to process at specific times and temperatures, and within a certain range of motor speeds. In the process duration enter the temperature you would like the product to process at and the length of time which it is to be processed for; for example 70C for 1 hour.
PARAMETERS
Enter temperature and time settings here
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
On the final page of the Parameter settings you have the option of a shutdown delay. This refers to the shutdown of the automatic sequence so you still have the option of keeping the motors running after a sequence has finished as specified in the previous page. You can enter a time delay in days, hours and minutes and the rpm at which it is to run at when shutdown happens. You have a further 3 options on how it shuts down: Delay only will shut down on the specified time only; Delay or Temp will shut down on either the specified time or when a specific temperature has been reached; Delay or Temp and Maintain will shut down on delay or when a specific temperature has been reached and will maintain that temperature. Note: Remember to Save Set when changing any parameter.
Enter time delay and rpm settings here
Enter temperature and time delay settings here
PARAMETERS
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
In the Engineering page this is where the operating limits for the outlet fan are. This is also where you can set the temperature and time parameters for the pasteurisation zone.
Engineering
Set pasteurisation parameters here
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
When an automatic cycle has finished, a detailed description of that cycle is stored in the History database. By using the system manually the relevant information for each pile is also available however it will have to be obtained manually e.g. searching for the appropriate trend time frame.
HISTORY
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
HISTORY
Click here to transfer data to Selected Record
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
For example locate the pile number you want in the list. Click on the box next to the pile number and it will highlight that line. Now click on download and all the information for that process will be loaded into the Selected Record on the left, as shown above. By clicking on the arrow pointing to each process and selecting process temp or pasteurisation temp, a trend is automatically generated for that process.
Click here to highlight a particular process
HISTORY
Indicates if process parameters have been met as defined in Engineering.
Select either one to display the trends for that period.
For in
spec
tion p
urpo
ses o
nly.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
By selecting either process or pasteurise for a particular bay you will be presented with the screen above. All information about that pile number including the trend for that chosen period is displayed.
HISTORY
Trend showing the time period for the process highlighted.
Description of everything for that pile contained on the chart
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
PLC Wiring
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
TERMINAL BLOCK 1
1
ABP1 Inlet Fan Running 49
High level scrubber
2
ABP1 Inlet Fan Tripped 50
Low level scrubber
3
ABP1 Inlet Fan Hand
51
Not Used
4
ABP1 Inlet Fan Auto
52
Not Used
5
ABP1 Inlet Fan E Stop 53
Not Used
6
ABP1 Outlet Fan Running 54
Not Used
7
ABP1 Outlet Fan Tripped 55
Not Used
8
ABP1 Outlet Fan Hand 56
Not Used
9
ABP1 Outlet Fan Auto 57
Not Used
10
ABP1 Outlet Fan E Stop 58
Not Used
11
ABP2 Inlet Fan Running 59
Not Used
12
ABP2 Inlet Fan Tripped 60
Not Used
13
ABP2 Inlet Fan Hand
61
Not Used
14
ABP2 Inlet Fan Auto
62
Not Used
15
ABP2 Inlet Fan E Stop 63
Not Used
16
ABP2 Outlet Fan Running 64
Not Used
17
ABP2 Outlet Fan Tripped 65
ABP1 Inlet Run
18
ABP2 Outlet Fan Hand 66
ABP1 Inlet Reset 19
ABP2 Outlet Fan Auto 67
ABP1 Inlet Leache Valve
20
ABP2 Outlet Fan E Stop 68
ABP1 Outlet Run 21
ABP3 Inlet Fan Running 69
ABP1 Outlet Reset
22
ABP3 Inlet Fan Tripped 70
ABP1 Outlet Leache Valve 23
ABP3 Inlet Fan Hand
71
ABP2 Inlet Run
24
ABP3 Inlet Fan Auto
72
ABP2 Inlet Reset 25
ABP3 Inlet Fan E Stop 73
ABP2 Inlet Leache Valve
26
ABP3 Outlet Fan Running 74
ABP2 Outlet Run 27
ABP3 Outlet Fan Tripped 75
ABP2 Outlet Reset
28
ABP3 Outlet Fan Hand 76
ABP2 Outlet Leache Valve 29
ABP3 Outlet Fan Auto 77
ABP3 Inlet Run
30
ABP3 Outlet Fan E Stop 78
ABP3 Inlet Reset 31
ABP4 Inlet Fan Running 79
ABP3 Inlet Leache Valve
32
ABP4 Inlet Fan Tripped 80
ABP3 Outlet Run
33
ABP4 Inlet Fan Hand
81
ABP3 Outlet Reset 34
ABP4 Inlet Fan Auto
82
ABP3 Outlet Leache Valve
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
35
ABP4 Inlet Fan E Stop 83
ABP4 Inlet Run 36
ABP4 Outlet Fan Running 84
ABP4 Inlet Reset
37
ABP4 Outlet Fan Tripped 85
ABP4 Inlet Leache Valve 38
ABP4 Outlet Fan Hand 86
ABP4 Outlet Run
39
ABP4 Outlet Fan Auto 87
ABP4 Outlet Reset 40
ABP4 Outlet Fan E Stop 88
ABP4 Outlet Leache Valve
41
Vent 1 open selector
89
Ventilation local/remote lamp
42
Vent 2 open selector
90
Scrubber pump Run
43
Ventilation VSD speed1 91
Scrubber pump Reset
44
Ventilation VSD speed2 92
Not Used
45
Ventilation VSD speed3 93
Not Used
46
Ventilation local/remote button 94
Not Used
47
Scrubber pump running 95
Not Used
48
Scrubber pump tripped 96
Not Used
1 97
Bio Filter Damper 1
98
Bio Filter Damper 2 99
Bio Filter Damper 3
100
Bio Filter Damper 4 101
Bio Filter Damper 5
102
Not Used 103
Not Used
104
Not Used 105
Not Used
106
Not Used 107
Not Used
108
Not Used 109
Not Used
110
Not Used
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
TERMINAL BLOCK 2
1
41
0V
2
42
24V Inlet Damper Bay 4 3
43
I+
4
44
COMM 5
45
0V
6
46
24V Inlet Damper Bay 5 7
47
I+
8
48
COMM 9
49
0V
10
50
24V Inlet Damper Bay 6 11
51
I+
12
52
COMM 13
53
0V
14
54
24V
Not Used
15
55
I+ 16
56
COMM
17
57
0V
18
58
24V Not Used
19
59
I+ 20 0 - 24V DC
60
COMM
21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
TERMINAL BLOCK 3
White(+)/Red/Red - [Wire from white connector in probe head to be wired to 1st slot (closest to back plate).
Red terminals in slots 2 and 3
1
PT 100 Bay1 PT100 1 49 0V
2
PT 100 Bay1 PT100 2 50 24V Outlet Damper Bay 5
3
PT 100 Bay2 PT100 1 51 I+ 4
PT 100 Bay2 PT100 2 52 COMM
5
PT 100 Bay3 PT100 1 53 0V
6
PT 100 Bay3 PT100 2 54 24V Outlet Damper Bay 6
7
PT 100 Bay4 PT100 1 55 I+ 8
PT 100 Bay4 PT100 2 56 COMM
9
PT 100 Bay5 PT100 1 57 0V
10
PT 100 Bay5 PT100 2 58 24V Ventilation Damper 1
11
PT 100 Bay6 PT100 1 59 I+ 12
PT 100 Bay6 PT100 2 60 COMM
13
PT 100 ABP1 PT100 1 61 0V
14
PT 100 ABP1 PT100 2 62 24V Ventilation Damper 2
15
PT 100 ABP1 PT100 3 63 I+ 16
PT 100 ABP1 PT100 4 64 COMM
17
PT 100 ABP1 PT100 5 65
0V
18
PT 100 ABP2 PT100 1 66
24V ABP1 Inlet Fan Speed
19
PT 100 ABP2 PT100 2 67
I+ 20
PT 100 ABP2 PT100 3 68
COMM
21
PT 100 ABP2 PT100 4 69
0V
22
PT 100 ABP2 PT100 5 70
24V ABP2 Inlet Fan Speed
23
PT 100 ABP3 PT100 1 71
I+ 24
PT 100 ABP3 PT100 2 72
COMM
25
PT 100 ABP3 PT100 3 73
0V
26
PT 100 ABP3 PT100 4 74
24V ABP3 Inlet Fan Speed
27
PT 100 ABP3 PT100 5 75
I+ 28
PT 100 ABP4 PT100 1 76
COMM
29
PT 100 ABP4 PT100 2 77
0V
30
PT 100 ABP4 PT100 3 78
24V ABP4 Inlet Fan Speed
31
PT 100 ABP4 PT100 4 79
I+ 32
PT 100 ABP4 PT100 5 80
COMM
33 1 black 0V
81 0V
34 2 Red 24V Outlet Damper Bay 1 82 24V ABP1 Outlet Fan Speed
35 3 white I+
83 I+
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
36 5 orange COMM
84 COMM
37 0V
85
0V
38 24V Outlet Damper Bay 2 86
24V ABP2 Outlet Fan Speed
39 I+
87
I+ 40 COMM
88
COMM
41 0V
89
0V
42 24V Outlet Damper Bay 3 90
24V ABP3 Outlet Fan Speed
43 I+
91
I+ 44 COMM
92
COMM
45 0V
93
0V
46 24V Outlet Damper Bay 4 94
24V ABP4 Outlet Fan Speed
47 I+
95
I+ 48 COMM
96
COMM
4 97
0V
98
24V Inlet Damper Bay 1 99
I+
100
COMM 101
0V
102
24V Inlet Damper Bay 2 103
I+
104
COMM 105
0V
106
24V Inlet Damper Bay 3 107
I+
108
COMM 109
E
110
U 111
V Scrubber Pump
112
W 113
U
114
V 3F15 115
W
116
U 117
V 2F15
118
W 119
U
120
V 1F15 121
W
122
U 123
V 1F22
124
W 125
U
126
V 1F37
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
127
W 128
N
129
E
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
PLC Input/Output List
Digital Inputs Rack Slot Channel
0 2 0 X40 ABP1_IF_RUN ABP1 Inlet Fan Running 1 X41 ABP1_IF_TRIP ABP1 Inlet Fan Tripped 2 X42 ABP1_IF_HAND ABP1 Inlet Fan Hand
3 X43 ABP1_IF_AUTO ABP1 Inlet Fan Auto 4 X44 ABP1_IF_ESTOP ABP1 Inlet Fan E Stop
5 X45 ABP1_OF_RUN ABP1 Outlet Fan Running 6 X46 ABP1_OF_TRIP ABP1 Outlet Fan Tripped 7 X47 ABP1_OF_HAND ABP1 Outlet Fan Hand 8 X48 ABP1_OF_AUTO ABP1 Outlet Fan Auto
9 X49 ABP1_OF_ESTOP ABP1 Outlet Fan E Stop A X4A ABP2_IF_RUN ABP2 Inlet Fan Running B X4B ABP2_IF_TRIP ABP2 Inlet Fan Tripped C X4C ABP2_IF_HAND ABP2 Inlet Fan Hand
D X4D ABP2_IF_AUTO ABP2 Inlet Fan Auto E X4E ABP2_IF_ESTOP ABP2 Inlet Fan E Stop
F X4F ABP2_OF_RUN ABP2 Outlet Fan Running
0 3 0 X50 ABP2_OF_TRIP ABP2 Outlet Fan Tripped 1 X51 ABP2_OF_HAND ABP2 Outlet Fan Hand
2 X52 ABP2_OF_AUTO ABP2 Outlet Fan Auto 3 X53 ABP2_OF_ESTOP ABP2 Outlet Fan E Stop 4 X54 ABP3_IF_RUN ABP3 Inlet Fan Running 5 X55 ABP3_IF_TRIP ABP3 Inlet Fan Tripped 6 X56 ABP3_IF_HAND ABP3 Inlet Fan Hand
7 X57 ABP3_IF_AUTO ABP3 Inlet Fan Auto 8 X58 ABP3_IF_ESTOP ABP3 Inlet Fan E Stop
9 X59 ABP3_OF_RUN ABP3 Outlet Fan Running A X5A ABP3_OF_TRIP ABP3 Outlet Fan Tripped
B X5B ABP3_OF_HAND ABP3 Outlet Fan Hand C X5C ABP3_OF_AUTO ABP3 Outlet Fan Auto D X5D ABP3_OF_ESTOP ABP3 Outlet Fan E Stop E X5E ABP4_IF_RUN ABP4 Inlet Fan Running F X5F ABP4_IF_TRIP ABP4 Inlet Fan Tripped
0 4 0 X60 ABP4_IF_HAND ABP4 Inlet Fan Hand 1 X61 ABP4_IF_AUTO ABP4 Inlet Fan Auto
2 X62 ABP4_IF_ESTOP ABP4 Inlet Fan E Stop 3 X63 ABP4_OF_RUN ABP4 Outlet Fan Running 4 X64 ABP4_OF_TRIP ABP4 Outlet Fan Tripped 5 X65 ABP4_OF_HAND ABP4 Outlet Fan Hand 6 X66 ABP4_OF_AUTO ABP4 Outlet Fan Auto
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
7 X67 ABP4_OF_ESTOP ABP4 Outlet Fan E Stop 8 X68 VENT1_OPEN_SWITCH Vent 1 open selector
9 X69 VENT2_OPEN_SWITCH Vent 2 open selector A X6A VENT_FAN_SPD1 Ventilation VSD speed1
B X6B VENT_FAN_SPD2 Ventilation VSD speed2 C X6C VENT_FAN_SPD3 Ventilation VSD speed3 D X6D VENT_LOCAL_REM Ventilation local/remote button E X6E SCRUBBER_RUN Scrubber pump running F X6F SCRUBBER_TRIP Scrubber pump tripped
0 5 0 X70 SCRUBBER_HL High level scrubber 1 X71 SCRUBBER_LL Low level scrubber
2 X72
3 X73 4 X74 5 X75 6 X76 7 X77 8 X78
9 X79
A X7A
B X7B
C X7C D X7D E X7E
F X7F
Digital Outputs Rack Slot Channel
0 6 0 Y80 ABP1_INLET_FAN_RUN_CMD ABP1 Inlet Run 1 Y81 ABP1_INLET_FAN_RESET_CMD ABP1 Inlet Reset 2 Y82 ABP1_INLET_LEACHATE_VALVE ABP1 Inlet Leache Valve
3 Y83 ABP1_OUTLET_FAN_RUN_CMD ABP1 Outlet Run 4 Y84 ABP1_OUTLET_FAN_RESET_CMD ABP1 Outlet Reset 5 Y85 ABP1_OUTLET_LEACHATE_VALVE ABP1 Outlet Leache Valve
6 Y86 ABP2_INLET_FAN_RUN_CMD ABP2 Inlet Run 7 Y87 ABP2_INLET_FAN_RESET_CMD ABP2 Inlet Reset 8 Y88 ABP2_INLET_LEACHATE_VALVE ABP2 Inlet Leache Valve
9 Y89 ABP2_OUTLET_FAN_RUN_CMD ABP2 Outlet Run
A Y8A ABP2_OUTLET_FAN_RESET_CMD ABP2 Outlet Reset B Y8B ABP2_OUTLET_LEACHATE_VALVE ABP2 Outlet Leache Valve
C Y8C ABP3_INLET_FAN_RUN_CMD ABP3 Inlet Run D Y8D ABP3_INLET_FAN_RESET_CMD ABP3 Inlet Reset E Y8E ABP3_INLET_LEACHATE_VALVE ABP3 Inlet Leache Valve
F Y8F ABP3_OUTLET_FAN_RUN_CMD ABP3 Outlet Run
0 7 0 Y90 ABP3_OUTLET_FAN_RESET_CMD ABP3 Outlet Reset
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
1 Y91 ABP3_OUTLET_LEACHATE_VALVE ABP3 Outlet Leache Valve
2 Y92 ABP4_INLET_FAN_RUN_CMD ABP4 Inlet Run
3 Y93 ABP4_INLET_FAN_RESET_CMD ABP4 Inlet Reset 4 Y94 ABP4_INLET_LEACHATE_VALVE ABP4 Inlet Leache Valve
5 Y95 ABP4_OUTLET_FAN_RUN_CMD ABP4 Outlet Run 6 Y96 ABP4_OUTLET_FAN_RESET_CMD ABP4 Outlet Reset 7 Y97 ABP4_OUTLET_LEACHATE_VALVE ABP4 Outlet Leache Valve
8 Y98 VENT_LOCAL_REM_LAMP Ventilation local/remote lamp
9 Y99 SCRUBBER_RUN_CMD Scrubber pump Run
A Y9A SCRUBBER_RESET_CMD Scrubber pump Reset
B Y9B
C Y9C D Y9D E Y9E F Y9F
0 8 0 YA0 DAMPER_BIOFILTER1 Bio Filter Damper 1 1 YA1 DAMPER_BIOFILTER2 Bio Filter Damper 2
2 YA2 DAMPER_BIOFILTER3 Bio Filter Damper 3
3 YA3 DAMPER_BIOFILTER4 Bio Filter Damper 4 4 YA4 DAMPER_BIOFILTER5 Bio Filter Damper 5 5 YA5
6 YA6 7 YA7 8 YA8
9 YA9
A YAA
B YAB
C YAC D YAD E YAE F YAF
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
PT100 Rack Slot Channel
1 0 1 D800 PT100_1PT1 Bay1 PT100 1 2 D801 PT100_1PT2 Bay1 PT100 2 3 D802 PT100_2PT1 Bay2 PT100 1 4 D803 PT100_2PT2 Bay2 PT100 2 5 D804 PT100_3PT1 Bay3 PT100 1 6 D805 PT100_3PT2 Bay3 PT100 2 7 D806 PT100_4PT1 Bay4 PT100 1 8 D807 PT100_4PT2 Bay4 PT100 2
1 1 1 D808 PT100_5PT1 Bay5 PT100 1 2 D809 PT100_5PT2 Bay5 PT100 2 3 D810 PT100_6PT1 Bay6 PT100 1 4 D811 PT100_6PT2 Bay6 PT100 2 5 D812 PT100_ABP1PT1 ABP1 PT100 1 6 D813 PT100_ABP1PT2 ABP1 PT100 2 7 D814 PT100_ABP1PT3 ABP1 PT100 3 8 D815 PT100_ABP1PT4 ABP1 PT100 4
1 2 1 D816 PT100_ABP1PT5 ABP1 PT100 5 2 D817 PT100_ABP2PT1 ABP2 PT100 1 3 D818 PT100_ABP2PT2 ABP2 PT100 2 4 D819 PT100_ABP2PT3 ABP2 PT100 3 5 D820 PT100_ABP2PT4 ABP2 PT100 4 6 D821 PT100_ABP2PT5 ABP2 PT100 5 7 D822 PT100_ABP3PT1 ABP3 PT100 1 8 D823 PT100_ABP3PT2 ABP3 PT100 2
1 3 1 D824 PT100_ABP3PT3 ABP3 PT100 3 2 D825 PT100_ABP3PT4 ABP3 PT100 4 3 D826 PT100_ABP3PT5 ABP3 PT100 5 4 D827 PT100_ABP4PT1 ABP4 PT100 1 5 D828 PT100_ABP4PT2 ABP4 PT100 2 6 D829 PT100_ABP4PT3 ABP4 PT100 3 7 D830 PT100_ABP4PT4 ABP4 PT100 4 8 D831 PT100_ABP4PT5 ABP4 PT100 5 Analogue Outputs
Rack Slot Channel 0 9 1 D900 DAMPER_BAY1 Outlet Damper Bay 1
2 D901 DAMPER_BAY2 Outlet Damper Bay 2 3 D902 DAMPER_BAY3 Outlet Damper Bay 3 4 D903 DAMPER_BAY4 Outlet Damper Bay 4 5 D904 DAMPER_BAY5 Outlet Damper Bay 5 6 D905 DAMPER_BAY6 Outlet Damper Bay 6 7 D906 DAMPER_VENT1 Ventilation Damper
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
1
8 D907 DAMPER_VENT2 Ventilation Damper 2
0 10 1 D908 ABP1_INLET_FAN_SPEED ABP1 Inlet Fan Speed
2 D909 ABP2_INLET_FAN_SPEED ABP2 Inlet Fan Speed 3 D910 ABP3_INLET_FAN_SPEED ABP3 Inlet Fan Speed 4 D911 ABP4_INLET_FAN_SPEED ABP4 Inlet Fan Speed 5 D912 ABP1_OUTLET_FAN_SPEED ABP1 Outlet Fan Speed 6 D913 ABP2_OUTLET_FAN_SPEED ABP2 Outlet Fan Speed 7 D914 ABP3_OUTLET_FAN_SPEED ABP3 Outlet Fan Speed 8 D915 ABP4_OUTLET_FAN_SPEED ABP4 Outlet Fan Speed
0 11 1 D916 DAMPER_BAY7 Inlet Damper Bay 1 2 D917 DAMPER_BAY8 Inlet Damper Bay 2 3 D918 DAMPER_BAY9 Inlet Damper Bay 3 4 D919 DAMPER_BAY10 Inlet Damper Bay 4 5 D920 DAMPER_BAY11 Inlet Damper Bay 5 6 D921 DAMPER_BAY12 Inlet Damper Bay 6 7 D922
8 D923 Analogue Inputs
Rack Slot Channel 1 7 1 D1000 PHM1 PH Meter
2 D1001 3 D1002 4 D1003
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Technical Data
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Performance of Composting System at Waddock Composting, Killamaster, Co. Carlow
Regarding the installation at the Waddock Composting plant at the above address the performance data is outlined below:
Aeration System There are 3 fans fitted for the six aeration tunnels. They are a 15kw 3ph 2 pole motor and each fan aerates 2 bays. All three of these fans are manufactured from 304 2B stainless steel with material thickness ranging from 2.5mm to 5mm. They are of fully welded construction and are a heavy duty type.
These fans are all controlled with VFD’s so that the airflow can be controlled more effectively.
The VFD’s receive a temperature feedback from the probes in the bay and the speed of the blowers are controlled automatically from this feedback. So as the temperature within the bay varies, the speed of the blower varies. The temperature probes are fed back into the PLC control board and read by the PLC. This then sends a signal to the VFD and sets the correct speed. By diverting the signal through the PLC system, it gives a far greater degree of automation to the system.
Extraction System The main extraction fan is a 37kW fan extracting from all six tunnels. This fan is directly driven with a 37kw
3ph 4pole motor. This fan is manufactured from 304 2B stainless steel with material thickness ranging from
2.5mm to 5mm. It is of fully welded construction and a heavy duty type.
From the fan data sheet provided it can be seen that negative pressure will always be maintained within the building even at full capacity.
Ventilation System A single extraction fan is fitted which is directly driven with a 22kw 3ph 4pole motor. This fan is
manufactured from 304 2B stainless steel with material thickness ranging from 2.5mm to 5mm. It is of fully
welded construction and a heavy duty type. This fan is positioned close to the bio-filter.
This fan will be controlled via a VFD which will allow variable speeds to be set. Also included is a small
control panel that can be mounted out in the premises, housing two rotary switches to control this fan as
well. This has the advantage of been able to turn on and off the fan at different speeds without having to go
back to the PC. With the first rotary switch, for instance position 1 = 20% of max. airflow, position 2 =40% of
max etc. The second rotary switch will either open both dampers so that ventilation takes place from the
whole premises, or one damper is open and one damper closed so that ventilation can take place from
either the apex near the new bays or from above the existing bays.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Bio Filter The bio-filter has been sized based on the maximum airflows from all three areas combined. Using a
retention time of 60seconds and a bio-filter media depth of 3 metres the required area is 300m2. The
drawing shows dimensions of 17.6 metres by 17 metres. Note: that is very unlikely that all systems will be at
full airflow simultaneously. It is also worth noting that if the bio-filter area is increased and the bed depth
reduces but keeping the volume the same, the kw required by the fans decreases.
The preferred filter medium is wood chip with no fines. In Irish weather conditions, we have found that the
introduction of fines tend, over time to compact and cause extra resistance on the fan and decrease the
airflow. Also by grading the wood chip, i.e. large chips at the bottom and smaller towards the top, leads to a
better distribution of air through the filter.
The filter has been designed to be sectioned off into three zones and it operates as follows.
When all three systems are in use, dampers 2 and 4 are closed and dampers 1, 3 and 5 are open. The full
biofilter is being used. As it in intended that the ventilation fan will not be on all the time it is proposed that
when it is off, that damper 3 will close and damper 2 will open, which will increase the biofilter area
available for the main extraction fan (37kw). It would result in a retention time of 100 seconds.
With regard to the centre biofilter section drying out due the air entering it from the ventilation fan, this fan
will usually only be used when steam is seen converging at the apex, which is a sign that the air is wet. More
importantly, bear in mind that this air goes through a scrubber, which it is scoured with water which will
greatly increase the humidity of the air leaving it. Additionally, as mentioned above, when the ventilation fan
is off this section of the bio-filter is automatically changed over to be used for the extraction of the six bays,
which is wet air and will keep the bio-filter moist, as well as increasing the retention time to 100 seconds.
For maintenance and media replacement ensure that the ventilation fan is off at all times. Section 2 can be
worked on.
With dampers 1, 3 and 4 closed and dampers 2 and 5 open, section 1 is diverted into section 2, and the 30kw
can operate up to 70% of airflow before the retention time of 60 seconds is exceeded. Section 2 can be
worked on.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
With dampers 2 and 3 closed, and dampers 1, 4 and 5 open section 3 is diverted into section 2, section 3 can
now be worked on.
In relation to the odour efficiency of the bio-filter, this is hard to quantify. Certainly having a 60 seconds
retention time when fans are operating at full speed is an excellent retention time. Also based on having
scrubbers preceding the bio-filter to remove the ammonia (which can break down the bio-filter and cause it
to stop working) and using our airflows, efficiency levels of 98-99% should be possible. Reported data
suggests efficiencies of greater than 99% are achievable with far less retention time. Basing calculations on
10,000OU/m3 on the air input, then assuming a 99% efficiency, a figure of 100OU/m3 would be the exhaust
air concentration.
Scrubber The scrubber that is installed is a wet scrubber. The main purpose of the scrubber is to reduce the levels of ammonia emissions.
The principles of operation are as follows:
Ammonia laden air enters the scrubber above the water table at the bottom.
Air nozzles spray high pressure water mist down through the scrubber and over two layers of scrubber packing media.
The ammonia impinges on these two layers of packing and the water mist as it passes up through the scrubber.
The water and ammonia fall into the water tank and the ammonia free air leaves through the top.
The sizes are designed to correspond with the associated fan airflow. Using a water medium with no additive
is very typical and will achieve results well in excess of 99%, even at ammonia concentration levels as high as
80ppm. By adding a small quantity of sulphuric acid to maintain a PH of about 8, even higher results are
obtained.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Overview of the Aeration and Extraction Systems of the Six tunnels.
To achieve the desired results it is imperative that both the aeration system and the extraction system work
in harmony. For negative pressure to be achieved the combined maximum air flow of the three aeration fans
has to be less that the maximum airflow of the extraction fan. We have taken this into consideration in our
design and the fan performance data can be studied on the data sheet provided. It should also be noted that
it would be very rare that all three aeration fans would be operating at full speed (cooling mode) at the same
time.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Fan Performance Data
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
18.5kw fan
2,700m3/hr @ 100pa. 2,850m3/hr @ 80pa. 2,420m3/hr @ 60pa.
37kw Main Extraction Fan.
22,100m3/hr @ 100pa.
25,500m3/hr @ 80pa. 27,200m3/hr @ 60pa. 28,900m3/hr @ 40pa.
22kw Ventilation Fan.
13,600m3/hr @100pa.
15,300m3/hr @ 80pa. 17,000m3/hr @ 60pa.
For in
spec
tion p
urpo
ses o
nly.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
List of Parts
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Aeration System
3 off 18.5kW 3ph 2 pole direct driven motors
Extraction System
1 off 37kW 3ph 4 pole direct driven motor
Ventilation System
1 off 22kW 3ph 4 pole motor
Scrubber
Lowara SHE 50-125/40/P Stainless Steel pump 1.5kW
Dampers
Belimo NM24A-SR 24VAC/DC
Probes
4 foot long PT100 3 wire probes, complete with handles
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Control System
Control system is all Mitsubishi equipment consisting of the following;
1 off PLC Q series CPU module 1024/2048 I/0
Power base unit
Power supply unit
1 off serial input module
1 off serial output module
PT100 input modules
VFD’s input modules
VFD’s output modules
Series CC master link
CC link interface to each VFD
600 point server conn., serial driver
1 off 37kw VFD
1 off 22kw VFD
3 off 18.5kw VFD’s
1 off 24VDC 10A power supply
PLC Software
Mitsubishi GX Works
Citect Scada
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
PLC Card Layout
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Drawings
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Redwood SystemsParkway Building,Whitestwon Ind Est,Tallaght,Dublin 24.Tel: 01-4596756; Fax: 01-4610452
Proposal For: Waddock Composting
Project: New Composting System
Drawn By: Fergus O'Brien
Date: 13-7-10
Scale: Not to scale
Reference: WC13710
Waddock Composting Civil holes in tunnel wall 11 off pipes per bay (500mm spacing)
hole size to suit 4" wavin
Centre line of bay
5822.5 mm
5522.5 mm
300.0 mm
500.0 mm
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
Redwood SystemsParkway Building,Whitestwon Ind Est,Tallaght,Dublin 24.Tel: 01-4596756; Fax: 01-4610452
Proposal For: Waddock Composting
Project: New Composting System
Drawn By: Fergus O'Brien
Date: 10-5-10
Scale: Not to scale
Reference: WC10510/6m
Waddock Composting Aerationfan for New bays
Flexible Duct Connection
Wavin Bend
Connection Spigot
Control dampers
5.5m bay 5.5m bay
11 off pipes per bay (500mm spacing)
5522.5mm 55225mm
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
BIOFILTER OPERATION & MAINTENANCE GUIDANCE 1
O P E R A T I O N A N D M A I N T E N A N C E G U I D A N C E
BIOFILTER OPERATIONAL GUIDANCE FOR
WADDOCK COMPOSTING
Waddock Composting Ltd.
DESCRIPTION OF THE TECHNOLOGY
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
2
Definition of Biofiltration
Biofiltration is the use of microorganisms growing in a media bed to remove and oxidize compounds in a foul airstream. A typical biofilter consists of a media bed containing contaminant degrading microorganisms, a media support structure, a foul air distribution system, and some method of controlling the biofilter moisture content. The media can consist of various materials including soil, woodchip, peat, compost, sand or synthetic material (plastic packing material). Typically, the foul airstream to be treated is distributed over the bottom of the biofilter bed and forced upward through the media. The moist filter media provides physical and chemical conditions appropriate for the transfer of the contaminants from the vapor phase and supports microbial biodegradation of the adsorped and absorbed contaminants. The figure below is a simplified schematic of Waddock Composting Facility’s (WCF) open-vessel biofilter system.
FIGURE 1
Schematic of Biofilter
A foul airstream containing biodegradable organic and inorganic odorous compounds passes through an air-distribution system underneath the filter medium. The air piping
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
3
system is set on cement blocks to raise it off the ground so the air can be evenly distributed under the pipe.
A medium such as chip wood with a particle size up to 100mm is spread loosely and evenly over the air distribution system. We screen the old woodchip along with the new woodchip at a rate of 4:1 through a 12mm trommel and place the >12mm woodchip around the pipes up to a height of 1.5m and then we place the 0 – 100mm to the full height of 3m. By mixing the new with the old woodchip we are reintroducing the bacteria into the new media bed. The media provides an environment for microorganisms that biologically degrade the odorous compounds. The filter media serves four primary purposes. It provides;
A stable matrix through which the airstream flows evenly
A surface area and moist medium for sorption of odorous compounds
Large surface area for microbial attachment and growth
A source of nutrients and water for the microorganisms.
Construction of Biofilter; January of 2011.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
4
Biofilters have successfully removed a wide range of inorganic and organic compounds in gas streams. Easily biodegradable odorous compounds such as aldehydes and organic acids as well as sulfur dioxide, nitrous oxides, and hydrogen sulfide, can be removed to a level of 99% or better with biofilters. Volatile organic compounds including methane, propane have been removed to 90% or better with biofilters. Ammonia, amines and other nitrogen-based compounds in low concentrations can also be effectively reduced. The removal efficiencies for each system are a function of numerous design and operating criteria, such as media type, temperature, pH, superficial velocity, and moisture content. Three process mechanisims remove odorous compounds in a biofilter; sorption, biological degradation, and chemical oxidation. A portion of the contaminants in the foul airstream are adsorbed on the surface of the biofilter media and the rest of the contaminants are absorbed by the thin film of liquid (biofilm) surrounding each of the media particles.
Microorganisms in the biofilm oxidize the contaminants and use energy released for maintenance of their own cell material and growth. During biological oxidation, various organic and inorganic compounds are degraded. Organic compounds consisting of carbon, hydrogen and oxygen are fully degraded into carbon dioxide and water. Inorganic compounds, including ammonia (NH3) and hydrogen sulfide (H2S), yield compounds, which form acids.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
5
OPERATION AND DESIGN PARAMETERS
Several parameters need to be considered and properly maintained in order for a biofilter to effectively control odors. These factors all have one main goal: to provide a suitable environment to sustain the microorganisms responsible for the biofiltration process.
Moisture Control
The proper moisture content of the biofilter is essential for the biofilter to perform at its maximum efficiency. Odorous compounds need to be adsorped or absorbed by the moisture-rich biofilm before microorganisms can use these compounds as a food source. If the biofilm is absent or not thick enough, the ultimate density of the microorganisms cannot be reached. Consequently, the biofilter will perform below expected levels.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
6
The optimum moisture content varies with the particular filter medium and should be determined on a case-by-case basis. A general range of 40% to 70% is considered typical with a target of 60% being ideal. A sprinkler system is used to control (increase) the media’s moisture level.
Temperature
Microbial activity must be maintained in the biofilter to remove the odorous compounds. Biological activity increases by a factor of approximately 2 for each 10o rise. A temperature range between 70oF and 98oF is considered ideal for the biofiltration process. If temperatures are lower the biofilter will continue to work, but at a reduced rate. Extreme cold temperatures can cause the microorganisms to become dormant. Higher temperatures will accelerate the decomposition (service life) of the media.
pH
The pH of the biofilter should be maintained at or near neutral to facilitate maximum microbial activity required for maximum odour control.
Foul Air Residence Time
Absorption, adsorption, and biodegradation rates vary depending on the biofilter media and the foul airstream compounds being treated. The odorous constituents should be identified and quantified prior to the biofilter design and installation. This will ensure that the proper biofilter size and media is selected.
Review of field experience and references indicates a suggested retention time range of 30 to 180 seconds. High rate compost style biofilter systems are typically designed for 30 seconds or less retention time. This type of system may require that the odorous air be preheated in order to maintain a higher rate of degradation. These higher rate systems also require special attention to detail regarding air distribution and moisture control. Lower rate, simpler open vessel compost systems are typically designed for 45 to 60 seconds retention time.
Oxygen Concentration
The oxygen level is important to the biofiltration process since most of the degradations are aerobic. The microorganisms use the dissolved oxygen in the biofilm. In some cases, the controlling factor to biofilter loading may be oxygen to the biofilter system. Typically however, loading rates are sufficient to maintain aerobic conditions.
If anaerobic conditions develop due either to overloading or short circuiting the biofilter may become the source of odors rather than the device for removing them.
Air Flow Distribution
The airflow distribution section of the Biofilter is located above ground in the media bed. The system consists of a pipe cut in half horizontally and placed on 4 inch blocks so that the odorous air can be evenly distributed through the media. In open top biofilters, the system may also remove excess water caused by precipitation.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
7
Leachate Control
Excess water is collected from the biofilter. The leachate from the biofilter is collected and drained back into the wastewater treatment system.
Microorganisms
Microorganisms are the workhorses of the biofiltration system. All biofilter design criteria are geared to provide optimal conditions for the microorganisms. Bacteria, actinomycetes and fungi are the principal microorganisms involved in the biological oxidation process. These microorganisms will grow on media such as chipwood.
The microorganisms live in the thin biofilm on the surface area of the filter media. As the foul airstream enters the biofilter, the contaminants diffuse and are either adsorped or absorbed into the biofilm. The microorganisms oxidize the contaminants to non-odorous and non-toxic compounds. The species of microorganisms active in a biofilter vary depending upon the compounds present in the foul airstream and have been shown to vary within the depth of the media.
Two groups of aerobic microorganisms are vital to microbial conversion of the foul airstream contaminants in the biofilter media: autolithotrophic and heteroorganotrophic. Both types obtain the required energy for cell function through chemical reactions
Autolithotrophic bacteria use carbon, present in the foul airstream as carbon dioxide to produce new cell material. A limited number of inorganic compounds in nature are suitable for autolithotrophic degradation. Ammonia and hydrogen sulfide are the primary compounds important to biofiltration applications in wastewater treatment.
The second type of bacteria, heteroorganotrophic bacteria, utilize carbon in the gaseous pollutant as sources for cell growth. The majority of the bacteria used for biofiltration are heteroorganotrophic. Most organic compounds present in foul airstreams ( such as Mercaptans) can be utilized by heteroorganotrophes.
MEDIA
Media Design
A good biofilter media should possess the following characteristics:
Supports a large diverse microbial population,
pH buffering capabilities
ability to retain microbes
appropriate density
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
8
physically stable
low pressure drop
production of clear drainage water (leachate)
high bearing strength.
The media design involves a number of elective decisions, including media ingredients, particle sizing, cross-sectional depth, surface loading rate per square foot, porosity, and desired service life. These parameters are dependant on the foul airstream characteristics, including contaminants of concern and loading rate
Media Replacement
Media replacement can be initiated based on a media effective depth, observations of surface irregularities and exhaust odor, PH irregularities, TVC’s or based on back pressure measurements. All of these are reasonable approaches, and they can be used together if necessary.
The operators create a basic decision model for media exchange based on age, surface appearance, effective depth, exhaust quality, and backpressure. This requires a procedure to record performance right from the beginning on a new or replaced biofilter. It will be important that these measurements are used for future decisions. The recommendations below are intended to provide some structure to this approach. For example, if any of the model parameters exceed a selected specification (i.e. depth is less than four feet, surface has dry spots, or the exhaust has odors present) the biofilter media should be replaced. It should be noted that backpressure will be unique to each biofilter but trends over time can indicate problems, such as a gradually rising backpressure that consumes horsepower and reduces airflow. Depth and age are also closely correlated. If the biofilter looses too much effective depth, it generally also has reached an advanced age since the depth decreases over time. The performance of the biofilter will only be as good as the uniformity of the media.
Cautionary advice about premature media failure
If the resulting airflow across the biofilter surface is unbalanced due to variable media porosity or inconsistent composition, the problem will only become worse over time. The result will be a much shorter residence time than intended (meaning incomplete odor removal) as the airflow favors the portion of the filter with the lowest resistance.
For example, part of the filter might have 60 seconds of residence time and other parts might have 180 seconds. Over time these same rates might drift further apart to 40 seconds and 240 seconds respectively as the problem gets worse. Of course, the airflow that only has 40 seconds may still have odors in it.
Uneven airflow will make replacement of the media a necessity well before anticipated, so careful attention and supervision during the mixing and placement procedure is well worth the time.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
9
Bio Filter Air Balance based on 2000pa.
Side Elevation of Ducting & Damper
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
����������� CARLOW PRECAST TANKS Manufacturers and Suppliers of Septic and Effluent Tanks for Sewage Treatment Systems, Water Reservoirs,
Pumping Chambers, Culverts and Special Products.
CP8 BP – Bypass Oil Water Separator. Rev. A – 06/03/09
Page 1 of 3
Technical Data Sheet: CP8 BP Bypass Oil Water Separator.
Type:
Class 1 Separator - Discharged effluent to contain < 5 mg/litre when
tested in accordance with IS EN 858.
Max. Treated Flow:
8 l/s
Storm Flow:
80 l/s
Max. Catchment Area:
4,400 m2
Lid:
Conventionally reinforced precast concrete lid.
Separator: Steel fibre reinforced precast concrete tank with integral steel fibre
reinforced concrete internal weir and baffle walls.
Coalescer: ‘Ortner Wassertechnic’ FIC 10 with float type automatic closure
device. (Closure device automatically shuts the outlet from the main
separation chamber if the oil storage capacity is exceeded)
Load Capacity:
The tank and lid are designed for a soil overburden depth of up to 1m and the most critical of a 10
kN/m2 imposed UDL or a 5,850 kg wheel load acting at any point on the lid surface. Heavy duty
lids can be manufactured for more onerous load applications.
Materials:
Concrete:
Strength Grade: C60/75 (75N)
Min. Cement Content: 350 kg/m3
Max. Water / Cement Ratio 0.5
Max. Aggregate Size: 14mm
Max. Slump: Not applicable – Self compacting mix.
Additives: Glenium – Plasticiser / Water reducing agent.
Crushed Limestone Powder – Filler
Reinforcement:
Lid: High yield type two reinforcement to BS 4449
Tank: 40 kg/m3 - 47/1.0 ‘Duoloc’ Steel fibre reinforcement
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:40
����������� CARLOW PRECAST TANKS Manufacturers and Suppliers of Septic and Effluent Tanks for Sewage Treatment Systems, Water Reservoirs,
Pumping Chambers, Culverts and Special Products.
CP8 BP – Bypass Oil Water Separator. Rev. A – 06/03/09
Page 2 of 3
Liquid Retention:
The separator is designed to be watertight in accordance with BS 8007 – ‘Code of practice for
design of concrete structures for retaining aqueous liquids’.
Ventilation:
The main separation chamber should be ventilated in accordance with BS 8301 – ‘Code of
practice for building drainage’. A 100mm diameter opening is provided in the lid for this
purpose.
Design Life:
The separator & lid have a design life of 50 years in a ‘severe’ category environment as defined
by BS 8110.
Warranty:
The product warranty covers the first fifteen years from the date of delivery.
Manufacture:
Quality of manufacture, standard of workmanship & dimensional tolerances comply with BS
8110 Pt. 1. The separator is cast in one pour to prevent the formation of a cold joint. All precast
concrete elements are cured for a minimum of 48 hours prior to delivery.
Access Requirements:
The separator and lid are generally delivered on a platform bodied truck with a hydraulic jib. Up
to 6m reach is possible from the back of the truck to the centre point of the placement position. A
minimum of 4m entrance width and clear height are required.
Excavation & Base preparation requirements:
The depth of excavation should exceed the finished base level by a minimum of 150mm. The
excavation should then be brought to level using crushed rock aggregate (40mm max. size),
which must be compacted and levelled. In exceptional circumstances (Particularly heavy surface
loading or unusually soft ground) a reinforced concrete base may be required.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:41
����������� CARLOW PRECAST TANKS Manufacturers and Suppliers of Septic and Effluent Tanks for Sewage Treatment Systems, Water Reservoirs,
Pumping Chambers, Culverts and Special Products.
CP8 BP – Bypass Oil Water Separator. Rev. A – 06/03/09
Page 3 of 3
The sides of the excavation must be suitably battered to avoid risk of collapse. To minimise the
risks associated with deep, open excavations it is recommended that completion should be
coordinated to coincide with the arrival of the separator. During placement it is imperative that
personnel do not stand beneath a suspended load.
The safety of the excavation and the general works remains the responsibility of the purchaser.
Backfilling
The excavation may be backfilled using excavated material provided that topsoil is not used
below a depth of 150mm and the backfill is free of large stones and cobbles (Larger than 75mm
approx.). Where excavated material is unsuitable for backfilling crushed rock fill may be used
(50mm maximum diameter). Backfilling should be completed in horizontal layers not exceeding
500mm depth, lightly compacted on completion of each layer. The lid should be placed in
position before backfilling begins to avoid unnecessary contamination of the separator.
Fitting of Connecting Pipes:
The inlet and outlet openings are fitted with moulded EDPM wall seals permitting a push through
seal of connecting pipes (Up to 300mm diameter). The wall seals have an expected working life
of greater than 50 years and are watertight to 0.5 Bar of external water pressure.
Floatation:
It is important to note that the separator will float if submerged in water when empty. If it is
anticipated that external water levels will rise higher than 550mm above the base of the separator
then a floatation check must be performed. Pending the result of this check appropriate anti
floatation measures may be required. These measures include adding additional soil overburden
or drilling steel dowel bars into the separator at base level and pouring a hoop of insitu ballast
concrete.
Design Compliances:
BS 8007 Code of practice for design of concrete structures for retaining aqueous
liquids.
BS 8110: Pt. 1 The structural use of concrete
Dramix Design Guidelines for Steel Fibre Reinforced Concrete Structures
- BEKAERT.
PPG3 Use & Design of Oil Separators in Surface Water Drainage Systems – EPA
IS EN 858: Pt.1 Separator Systems for light liquids.
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:41
For
insp
ectio
n pur
pose
s only
.
Conse
nt of
copy
right
owne
r req
uired
for a
ny ot
her u
se.
EPA Export 17-02-2015:23:10:41