IPPC Licence Review (P0442-01) 24 th July 2012 Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents C1.1 Organisational Chart C1.2 Quality, Safety and Environmental (QSE) Policy Statement C1.3 Roles & Responsibilities of Key Environmental Personnel C2.1 ISO 14001 Accreditation Certificate C2.2 List of Environmental and QSE Management System Procedures

Upload: dangdien

Post on 28-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 1 of 11

Attachment C Management of the Installation

Table of Contents

C1.1 Organisational Chart

C1.2 Quality, Safety and Environmental (QSE) Policy Statement

C1.3 Roles & Responsibilities of Key Environmental Personnel

C2.1 ISO 14001 Accreditation Certificate

C2.2 List of Environmental and QSE Management System Procedures

Page 2: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 2 of 11

C1.1 Organisational Chart

Head of Distilling

Operations

Quality

Assurance

Manager

Environmental

& Energy

Manager

Bond Process

Manager

Master

Distiller Engineering

Manager

PA Head of

Distilling

Operations

Quality &

Environmental

Services

Laboratory

Technicians

Production

Services

Process

Engineer

Production

Services

Operatives

Administrator

/Stock

Controller

Transport

Supevisor

Bond

Supervisors

DriversBond

Operatives

Coopers

Engineering

Supervisor

Electrical

Safety

Officer

Electrical Fitters

Engineering

Storemen

Mechanical

Fitters

Production

Supervisors

Production

Operatives

Receptionist

Health, Safety

& Fire Officer

Health & Safety

Manager

Distillery

Operations

Manager

QSE Systems

Co-ordinator

Page 3: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 3 of 11

C1.2 Quality, Safety and Environment Policy Statement

Page 4: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 4 of 11

C1.3 Roles & Responsibilities of Key Environmental Personnel

Environmental & Energy Manager

Main Duties & Responsibilities Include:

• Complying with the IPPC licence (no. P0442-01),

• Complying with all environmentally related regulatory and legislative requirements;

• Ensuring the on-going effectiveness and compliance of operation of the Waste Water

Treatment Plant (WWTP) to meet licence requirements (IPPC no. P0442-01) with the

assistance of the Production Services Process Engineer and the WWTP operators;

• Ensuring compliance with emission limits (atmospheric, aqueous, noise etc.) pertaining to

the site (IPPC licence no. P0442-01);

• Receiving, documenting and responding to environmental complaints and other

communications from external interested parties;

• Conserving natural resources and achieving associated usage reduction targets;

• Ensuring that, when necessary, incidents / non-conformances are reported to the relevant

regulatory authorities;

• Ensuring that adequate resources including human resources and specialised skills,

technology and financial resources essential to the implementation and control of the

environmental management system, are available to maintain the Midleton management

system at its required level;

• Overall direction and guidance in conjunction with the Health & Safety Manager in

relation to arrangements for Emergency Preparedness and Response;

• Dealing with external regulatory bodies relating to the environment, and some in

conjunction with the Group Health & Safety Manager (e.g. licence reviews and appeals);

• Ensuring that all the applicable environmental management system procedures are

adhered to;

• Communicating roles and responsibilities in relation to environment within the Midleton

management system;

• Maintaining the Log of Communications and Reports to / from IDL Midleton (EPR009)

in relation to the environment;

• Ensuring that environmental records are maintained as required;

• Ensuring that all employees, including new employees, receive adequate environmental

training;

• Ensuring that relevant environmentally related equipment is adequately maintained;

• Reporting to the relevant statutory authorities e.g. the Environmental Protection Agency;

• Ensuring compliance with the Greenhouse Gas Permit GHG-005;

• Reporting on energy monitoring and conservation measures at the site;

• Ensuring that the drainage systems (organic and foul etc.) are checked and surveyed and

any damages repaired as necessary;

• Undertaking bund integrity checks at the frequencies specified in the Integrated Pollution

Prevention & Control Licence (no. P0442-01);

• Coordinating bulk tank integrity checks.

Page 5: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 5 of 11

Production Services Process Engineer

Main Duties & Responsibilities:

• Supervise Operation WWTP and controls

• Monitoring and compliance IPPC license activities on site

• Maintenance of records as appropriate

• Supervision of four operatives

• Report to EPA when Environmental Manager not available

• Problem Solving WWTP.

• Operation of permit to work system

• Compliance IPPC, 14001, 22000 and FEMAS

• Communication with operatives

• Check laboratory results

• Round the clock support WWTP

• Preparation for audits

WWTP Operative

Main Duties & Responsibilities:

• Operate WWTP as per documented procedures and maintenance manuals in accordance

with IPPC license

• Emptying Bunds.

• Ensure in depth knowledge of SOPs that apply to production services department

involving ISO14001, 22000, FEMAS

• Housekeeping hygiene requirements

• Ensure all relevant operations are carried out in accordance with the appropriate

procedures.

General Operative

Main Duties & Responsibilities:

• Waste handling segregation and management

• Site management – road sweeping cutting long grass

• Ensure in-depth knowledge of SOPs that apply to production services department

involving ISO14001, 22000, FEMAS

• Housekeeping hygiene requirements

• Ensure all relevant operations are carried out in accordance with the appropriate

procedures

Page 6: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 6 of 11

QSE Systems Co-ordinator

Main Duties & Responsibilities:

• Ensuring that QSE Management System procedures and records are reviewed authorised

and issued to demonstrate document control commensurate with the requirement of the

ISO 9001, ISO 22000 and FEMAS, OHSAS 18001 and ISO 14001 Standards.

• Co-ordinating the annual Management Review and issuing minutes of same.

• Co-ordinating departmental QSE meetings and issuing minutes of same.

• Conducting internal, supplier and waste contractor audits as requested.

• Preparing and distributing the QSE Quarterly Report.

• Compiling QSE KPI’s for Midleton Distilleries.

• Ensuring that all process, quality, food and feed safety, safety and environmental

incidents and non-conformances are reported in accordance with the Midleton integrated

QSE management system.

• Maintaining the registers of waste records (hazardous and non-hazardous) and waste

collection permits; ensuring accessibility to same at all times. This involves monthly

contact with waste contractors to ensure delivery of:

o Waste monthly reports.

o Copies of waste documentation which Midleton Distilleries is required to have on

file.

o Reviewed waste collection and waste facility permits.

• Advising the Environmental & Energy Manager on the annual transfer of waste data

required for the Environmental Protection Agency's Annual Environmental Report

commensurate with IPPC licence (no. P0442-01) requirements and the annual/biannual

Pernod Ricard KPI environmental report.

• Arranging, scheduling and directing internal audits of the QSE Management Systems, as

directed by the QSE Managers, to ensure continued adherence to documented

requirements.

• Educating site personnel in the area of Environmental Awareness and QSE IT Systems.

Page 7: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 7 of 11

Attachment C2 Management of the Installation

C2.1 ISO 14001 Accreditation Certificate

C2.2 List of Environmental and QSE Management System Procedures

Page 8: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 8 of 11

C2.1 ISO 14001 Accreditation Certificate

Page 9: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 9 of 11

C2.2 Environmental and QSE Management System Procedures

Environmental Procedures Masterlist

ID Description

EPP Environmental Procedure

EPR Environmental Record

Ref. No. SOP Title

EPP001 Operation of the Waste Water Treatment Plant (WWTP)

EPP004 Handling & Disposal of Non-hazardous Waste from IDL

EPP005 Handling & Disposal of Hazardous Waste from IDL

EPP006 Environmental Complaints

EPP008 Procedure for Emptying of Bunds at IDL

EPP009 Spill Control at IDL

EPP010 MSDS Management at IDL

EPP011 Control of Site Drawings

EPP012 Environmental Monitoring

EPP016 Procedure for the Bulk Unloading of Oils & Chemicals

EPP019 Material Segregation Policy at IDL

EPP020 Waste Tracking

EPP023 Procedure for Determining Total Organic Carbon (TOC)

EPP024 Procedure for Checking Oil Water Interceptors

EPP025 Procedure for the Operation of Storm Water Isolation Valves

EPP026 Ecological Management

EPP027 Quality Check on Water Seal

EPP028 Procedure for Operating Valves on the Storm Water Line at Treated Effluent

Outfall

EPP029 Pest Control

EPP046 Greenhouse Gas Monitoring & Reporting

EPP047 Operation of the Waste Water Treatment Plant (WWTP) Centrifuge

EPP048 Procedure for Use of Hot Washer

EPP049 Procedure for Use of Mobile Petrol Power Washer

EPP050 Spill Control Training

EPP051 Spill Kit Inspection Procedure

Page 10: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 10 of 11

Ref. No. Environmental Record Title

EPR004 Waste Management Record

EPR008 Record of Visual Checks on Spill Control Equipment

EPR009 Log of Environmental Comunications to IDL

EPR010 Bund Checklist

EPR020 Environmental Audit Checklist-Waste Contractors

ERP021/QS003 Attendance Record

EPR022 Internal Incident Record Sheet

EPR025 WWTP Plant (SCADA) Equipment Checklist

EPR027 Record for Quality Check on Water Seal

EPR030 Environmental Complaints Record Sheet

EPR034 Evaluation of New Products and Processes

EPR036 Weekly Site Breakdown

EPR037 Week Profile Main ESB

EPR039 Surface Water (SWE 2 & 3) Emissions

EPR040 Process Emissions (SWE1) to Water Record

EPR041 Masterlist of Bunds at IDL

EPR043 Check on Over Ground Conveyance System

EPR044 Waste Water Treatment Plant (WWTP) Log of Flow Through Plant

EPR045 SE1 Exceedance Fax Notification

EPR046 Waste Water Treatment Plant (WWTP) SCADA Instrument Readings

EPR047 Waste Water Treatment Plant (WWTP) Visual Inspection of Plant

EPR048 Calibration Records for on site TOC Meters

EPR049 Monitoring Log for Onsite TOC Meter

EPR051 Waste Water Treatment Plant (WWTP) Spot Sample Check

N/A SH1 Organic Register

N/A Integrated Pollution Prevention Control (IPPC) Licence No.P0442-01.

N/A Environmental-related Preventative Maintenance Records

N/A EFF01

N/A Gas Invoices

N/A Electricity Invoices

N/A Register of Environmental Regulations

N/A Water Meter Readings

N/A Environmental Aspects & Impacts

N/A Cleaning record for toilets and washbasins

N/A Waste Register

EPP012-Appendix 1

Environmental Monitoring Matrix

Page 11: Attachment C Management of the Installation Table of Contents · Irish Distillers Ltd. Attachment C Revision A Page 1 of 11 Attachment C Management of the Installation Table of Contents

IPPC Licence Review (P0442-01) 24th

July 2012

Irish Distillers Ltd. Attachment C Revision A

Page 11 of 11

Management System Procedures Masterlist (Quality, Safety and Environmental)

QSE001 Document Control

QSE002 Internal Audits

QSE003 Training

QSE004 Registers of Regulations

QSE005 Management Review

QSE006 Change Management - Control of New Processes & Materials and Changes to Existing Processes

QSE007 QSE Monitoring

QSE008 Internal Emergency Plan

QSE009 Product Realisation Prerequisite Programme

QSE010 Procedures for Setting & Monitoring Objectives & Targets Programme

QSE011 Incidents, Corrective Action & Control of Nonconformances

QSE012 Product Identification,Traceability & Control of Nonconforming Product

QSE013 Calibration

QSE014 Purchasing

QSE015 Control of Suppliers

QSE016 Goods Inwards Inspection

QSE017 Contract Review

QSE018 Handling, Storage, Packaging, Preservation & Delivery

QSE019 Control of Customer Supplied Product

QSE019 Control of Customer Supplied Product

QSE020 Complaints Handling

QSE021 HACCP Plan

QSE022 Identification of Environmental Aspects & Evaluation of Environmental Impacts

QSE023 QSE Records

QSE024 Induction Training for Contractors & Visitors

QSE025 Food Safety (HACCP) Hazard Identification & Risk Assessment Methodology

QSE026 Product Recall

QSE028 Management of Safety Critical Components/Systems at Midleton Distilleries