    ATLANTIC YARDS CONSTRUCTION UPDATEWeeks of September 30

    thand October 7

    th

    In an effort to keep the Atlantic Yards Community aware of upcoming constructionactivities, ESD and Forest City Ratner provide the following outline of anticipatedupcoming construction activities. We hope it keeps you informed and helps you planfor any possible inconveniences. Please let us know if theres any way we canimprove these updates.

    If you have any questions please feel free to contact ESDs Manager, AtlanticYards Project Community/Government Relations or at 212-803-3736 or

    [email protected]

    Please note: the scope and nature of activities are subject to change based uponfield conditions. In addition, during the utility work water shut-offs may berequired; these shutdowns are done under the oversight of DEP and propertyowners will be given advance notice. All work has been approved by appropriateCity and State agencies where required.

    B-2 Tower, Modular Residential

    Completion of Erection of Structural Steel within the B2 site and Dean Street transferfoundation will be completed during this reporting period. A separate logistics/site

    safety plan has been submitted for this work and approved by DOB. Installation of formwork and rebar for the metal deck slabs, cellar and 1

    stfloor

    will continue during this reporting period.

    Commence work related to the concrete cellar floors. Pour will take placeover a two day period with approximately 8 to 10 trucks per day.

    Installation of temporary power and lights will continue during this reportingperiod.

    Daily cleanup activities of sidewalks and streets are ongoing as required.

    Tentatively there are no construction activities scheduled for the upcomingSaturdays during this reporting period.

    http://www.esd.ny.gov/http://www.esd.ny.gov/mailto:[email protected]:[email protected]://www.esd.ny.gov/
  • 7/27/2019 Atlantic Yards Construction Alert, September 30 2013

    2/2

    LIRR Yard Activit ies Block 1120 & 1121

    Pacific Street, between Carlton and 6th Avenues, has been converted back totwo way traffic. Parking is permitted on both sides of Pacific Street.

    Punch list work will be ongoing during this reporting period.

    Noise and Dust mitigation practices and monitoring will continue throughoutthe duration of the work.

    How to Reach Our Community Liaison Office (CLO)

    The Community Liaison Office is located at 752 Pacific Street. The CLOs hoursare M-F from 9am 4pm and the phone number, 866-923-5315 and email,

    [email protected] will remain the same. Visitors seeking theoffice should enter through the guard booth at the corner of Carlton Avenue andPacific Street.

    mailto:[email protected]:[email protected]