assignment capacity. 2 ardavan asef-vaziri march, 2015capacity- basics mamossaassaf inc. fabricates...

14
Assignment Capacity

Upload: theodore-franklin

Post on 08-Jan-2018

218 views

Category:

Documents


0 download

DESCRIPTION

3 Ardavan Asef-Vaziri March, 2015Capacity- Basics Key Problem 2: Flow Time (a) What is the Theoretical Flow Time? (The minimum time required to produce a garage from start to finish.) Roof Path: 15+8 = 23 Base Path: = 25 Max = = 35 Theoretical Flow Time = 35 8 R-Form 10 B-Form 15 R-Punch B- 12 Weld 10 Assembly 3 Roof Base Door Critical Path = Max(33,35) = 35

TRANSCRIPT

Page 1: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

AssignmentCapacity

Page 2: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

2Ardavan Asef-Vaziri March, 2015Capacity- Basics

MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching press (15 minutes per roof) and then formed in a roof forming press (8 minutes per roof). Bases are punched in a base punching press (3 minutes per base) and then formed in a base forming press (10 minutes per base), and the formed base is welded in a base welding machine (12 minutes per base). The base sub-assembly and the roof then go to final assembly where they are welded together (10 minutes per garage) on an assembly welding machine to complete the garage. Assume one operator at each station.

Key Problem 2

8R-Form

10B-Form

15R-Punch

B-Punch12

Weld 10Assembly

3

Roof

BaseDoor

Page 3: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

3Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Flow Time

(a) What is the Theoretical Flow Time? (The minimum time required to produce a garage from start to finish.)

Roof Path: 15+8 = 23Base Path: 3+10+12 = 25

Max = 25 + 10 = 35

Theoretical Flow Time = 35

8R-Form

10B-Form

15R-Punch

B-Punch12

Weld 10Assembly

3

Roof

BaseDoor

Critical Path = Max(33,35) = 35

Page 4: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

4Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Capacity(b) What is the capacity of the system in terms of garages per hour?

R-Punch:1/15 per min. or 4 per hr.R-Form:1/8 per min. or 7.5 per hr.B-Punch:1/3 per min. or 20 per hr.B-Form:1/10 per min. or 6 per hr.Welding: 1/12 per min. or 5 per hr.Assembly: 1/10 per min. or 6 per hr.

Process Capacity is 4 per hour(c) If you want to increase the process capacity, what is the activity process that you would put some additional resource?

R-Punch

8R-Form

10B-Form

15R-Punch

B-Punch12

Weld 10Assembly

3

Roof

BaseDoor

Page 5: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

5Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Capacity(d) Compute utilization of al the resources at the full process capacity. In other words, assume that the throughput is equal to process capacity. Through put = 4

R-Punch Utilization = 4/4 = 100%.R-Form Utilization = 4/7.5 = 53.33%.B-Punch Utilization = 4/20 = 20%.B-Form Utilization = 4/ 6 = 66.67%.Welding Utilization = 4/5 = 80%.Assembly Utilization = 4/6 = 66.67%No Process can work at 100% capacity. Impossible.

In reality, utilization of all the

resources will be less than what we

have computed.This process can never produce 4

flow units per hour continually.

Page 6: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

6Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Bottleneck Shift

Process Capacity is 5 per hour

(e) Suppose we double the capacity of the bottleneck by adding the same capital and human resources. What is the new capacity of the system.

8R-Form

10B-Form

15R-Punch

B-Punch12

Weld 10Assembly

3

Roof

BaseDoor

R-Punch

R-Punch: 2/15 per min. or 8 per hr.R-Form:1/8 per min. or 7.5 per hr.B-Punch:1/3 per min. or 20 per hr.B-Form:1/10 per min. or 6 per hr.Welding: 1/12 per min. or 5 per hr.Assembly: 1/10 per min. or 6 per hr.

Page 7: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

7Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Diminishing Marginal Return(f) We doubled the capacity of the bottleneck but the capacity of the system increased by only 25%. This situation is an example of what managerial experiment?1) Bottleneck shifts from R-Punch to Welding2) Diminishing Marginal Return

Page 8: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

8Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Pooling and Cross Trainingg) Now suppose we return back to the original situation

where we have a single machine and a single operator at each operation. However, also suppose that we pool R-Punch and B-Punch machines and we cross-train their operations and form a new resource pool named Punch where both R-Punch and B-Punch operations can be done in this resource pool. What is the new capacity of the system? R-Form

8R-

Form

B-Form

10B-

Form 12

WeldWeld

10Assembl

y

R-Punch

15R-Punch

B-Punch B-Punch

3

R-Punch

15Punch

B-Punch Punch

3

Assembly

Page 9: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

9Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Pooling and Cross TrainingR-Form

8R-

Form

B-Form

10B-

Form 12

WeldWeld

10Assembl

y

R&B-Punch Punch

Punch15,3

Assembly

Punch: 2/18 per min. or 6.67 per hr.R-Form:1/8 per min. or 7.5 per hr.B-Form:1/10 per min. or 6 per hr.Welding: 1/12 per min. or 5 per hr.Assembly: 1/10 per min. or 6 per hr.

Process Capacity is 5 per hour

Page 10: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

10Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Productivity Improvement -Method, Training, Technology, Managementh) This situation is an example of what managerial experiment?1) Cross training and pooling can increase the capacity

2) Usually cost of cross training and pooling is lower than the cost of adding the second resource unit.

i) Now suppose by investing in improved jigs and fixtures (technology), and also by implementing a better method of doing the job, and also training, we can reduce the welding time from 12 minutes to 10 minutes. What is the new capacity of the system ?

Page 11: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

11Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: More Than One Bottleneck

j) Why it is impossible to work at 100% of capacity? There are 3 bottlenecks. This is a risky situation. Any of the bottlenecks could cause the throughput of the system to fall below 6 per hour. The more bottlenecks in the system, the higher the probability of not meeting the capacity. Suppose punch fail to provide input to B-Form for 1 hour, or B-Form fails to provide Weld, or Weld fails to provide Assembly- That hour of capacity perishes.

Process Capacity is 6 per hour

R-Form

8R-

Form

B-Form

10B-

Form 10

WeldWeld

10Assembl

y

R&B-Punch Punch

Punch15,3

Assembly

Page 12: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

12Ardavan Asef-Vaziri March, 2015Capacity- Basics

Key Problem 2: Critical ChainR-Form

8R-

Form

B-Form

10B-

Form

R-Punch

15Punch

B-Punch Punch

10

WeldWeld

Assembly

10Assembl

y

3

Assembly

10Assembl

y

23Path

2

23Path

1

Not only the system has two bottlenecks, but one bottleneck feeds the second. Furthermore. Both paths to the last bottleneck are critical. They can both increase the flow time.

Page 13: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

13Ardavan Asef-Vaziri March, 2015Capacity- Basics

Lessons Learned1. When we relax a Bottleneck Resource, the Bottleneck

shifts to another resource2. By doubling the bottleneck resource, the capacity

usually does not double. This could be interpreted as diminishing marginal return situation.

3. One other way to increase capacity is cross training (for human resources ) and pooling (for Capital Resources).

4. Usually cost of cross training and pooling is lower than the cost of adding the second resource unit.

Page 14: Assignment Capacity. 2 Ardavan Asef-Vaziri March, 2015Capacity- Basics MamossaAssaf Inc. fabricates garage doors. Roofs are punched in a roof punching

14Ardavan Asef-Vaziri March, 2015Capacity- Basics

Lessons Learned5. One other way to increase capacity in to reduce unit

load. This is done by better management, (a) better methods, (b) training, (c) replacing human resources by capital resources (more advanced technology), and (d) better management.

6. Processes cannot work at 100% capacity. Capacity is perishable- it is lost if input is not ready. The more the bottleneck recourses the lower the utilization.

7. Convergence points are important in managing the flow time. The more convergence points the high the probability of the flow time exceed the average flow time.