    Operation Management

    Critical path methods

    Introduction:

    We have selected marble factory for applying critical path methods concepts. In this business

    there are many process involves in cutting of marble pieces.

    1. Oder of raw material to supplier.2. Unloading of raw material.3. Transfer of raw material from stocks to section machine.4. Transfer of marble pieces from section machine to small cutting pieces machine.5. Transfer of marble pieces from small cutting pieces to polishing machine.6. If special cutting machine.7. Shifting final marble piece into finished goods store.8. Finished marble piece sending to customers.

    Explanation of business process:

    1. Oder of raw material to supplier:In 1

    ststage of this business they first place order of raw material. They are purchasing

    raw material from different areas of (KPK) and Karachi. If they purchase Raw material

    from Swat or Sawabi it takes one or two day to reach in factory.

    If they buy raw material from Karachis suppliers then this order takes 3 or 4 days to

    reach in factory.

    2. Unloading of raw material:When consignment of raw material reaches in factory .the management hires 4 or 5

    labors for unloading of stock. They unload one truck of raw material within 4 r 5 hours.

    3. Transfer of raw material from raw material stocks to section machine:In this step factorys permanent employed labor are used for shifting raw material from

    stock to Section machine. Section machine is used to convert big blacks into small

    blacks. At this machine train labor is employed.

  • 8/13/2019 Assignemts of Operation Mamagment.edited

    2/6

    4. Transfer of marble pieces from section machine to small cutting pieces machine :In this stage helping labor are used to shift material from section machine to othermachine. When section completes its work of cutting big block in to small blacks then

    these small black shifted to small cutting machine for converting into one by one pieces

    . At this machine one skilled is labor is employed some he works for fixed salary and

    some works for extra time and get wages according to work which he has performed.

    5. Transfer of marble pieces from small cutting pieces to polishing machine When small black have been completed then these blocks shifted to polishing machine

    or designing machine. If special designing is not required then these marble tiles shiftedpolishing machine. If in the case if polish is not required then these marble directly

    transferred to finished good stock.

    6. If special cutting machine:When small cutting machine completes its work then these pieces can be shifted to three

    places like one special cutting machine, polishing machine or finished goods store. If special

    design is required for any order then required pieces are shifted to special cutting machine.

    At special cutting machine there one of experience and skilled labor is employed for

    designing.

    7. Shifting final marble piece into finished goods store:When all types of work done on the marble pieces at all stage then these pieces are shifted

    to finished goods stocks.

    8. Finished marble piece sending to customers:At the last stage of process the finished goods are delivered to customers. Here helping labor

    are used for uploading finished goods on truck.

  • 8/13/2019 Assignemts of Operation Mamagment.edited

    3/6

    Activity list for the Darya marble factory project:

    Activity Activity Description Immediate

    predecessor

    Completion

    time(Hrs)

    A Oder of raw material to supplier. - 96

    B Unloading of raw material. A 3

    C Transfer of raw material from stocks to sectionmachine.

    B 24

    D Transfer of marble pieces from section machineto small cutting pieces machine.

    C 8

    E Transfer of marble pieces from small cuttingpieces to polishing machine

    D 72

    F special cutting machine D 6

    G Shifting final marble piece into finished goodsstore.

    E,F 1

    H Finished marble piece sending to customers G 1

    Darya marble Critical path method of Graph:

    A [0-96 ] B [96-99] C [99-123] D [123-131] E [131-203] G [203-204] H [204-205]

    96[0-96] 3 [96-99] 24[99-123] 8 [123-131] 72 [131-203] 1 [203-204] 1[204-205]

    F [131-137]

    6 [131-137]

    1 2 3 45 6

    7

    9

  • 8/13/2019 Assignemts of Operation Mamagment.edited

    4/6

    Critical path:

    In this project all the activities threaded as critical point from point A, B, C, D, E F,

    G and H.

    Tabulate ES, EF, LS, LF, and Slack time:

    Activity Earliest

    Start

    (ES)

    Latest

    Start

    (LS)

    Earliest

    Finish

    (EF)

    Latest

    Finish

    (LF)

    Slack

    (LS-ES)

    Critical

    Path

    A 0 0 96 0 0 Yes

    B 96 96 99 96 0 yes

    C 99 99 123 99 0 Yes

    D 123 123 131 123 0 Yes

    E 131 131 203 203 0 Yes

    F 131 131 137 137 0 Yes

    G 203 203 204 204 0 Yes

    H 204 204 205 205 0 Yes

    Uncertain activity time:

    Once we have established a network for project, we will need information on the

    time required to complete each activity. This information will be used in

    calculation of the duration of entire project and scheduling of specific activities.

    Manager has experience and historical data necessary to provide accurate activity

    tine estimate.

    In order to incorporate uncertainty activity time into the network analysis, we will

    need to obtain three time estimates for each activity. The three estimates are

  • 8/13/2019 Assignemts of Operation Mamagment.edited

    5/6

    Optimistic time (a) The Activity time if everything progresses in ideal time. Most Probable time (m) the most likely activity time under normal

    conditions.

    Pessimistic time (b) the activity time if encourage significant breakdownand/or delays.

    The three Estimates enable the manger to develop a best guess of most likely

    activity time and then express the uncertainty by providing the estimate

    ranging from best possible (optimistic) time to worst possible (pessimistic)

    time.

    Table:

    Optimistic, Most Probable, and pessimistic Activity time Estimated (In Hours) for Darya

    marble factory project.

    Activity Optimistic

    (a)

    Most probable

    (m)

    Pessimistic

    (b)

    A 48 96 144

    B 2 3 4

    C 16 24 30D 6 8 10

    E 48 72 96

    F 4 6 8

    G 0.5 1 2

    H 0.5 1 2

  • 8/13/2019 Assignemts of Operation Mamagment.edited

    6/6

    Variability of project completion Time:

    In carrying out the critical path calculation, we treated the activity time as fixed at their

    expected value; we are now ready to consider the uncertainty in the activity time and

    determine the effect this uncertainty or variability has on the project completion date. Recall

    that the critical path determines the duration of entire project.

    For Darya marble factory project the critical path A, B, C, D, E, F, E, G and G resulted expected

    project completion time of 205 hours.

    Expected time formula T=a+4m+b/6

    Table of Expected time and variation

    Activity Expected time Variance

    A 96 256

    B 3 0.11

    C 23.67 5.44

    D 8 0.44

    E 72 64

    F 6.5 0.44

    G 1.08 0.0625

    H 1.08 0.0625