assessing ccs technologies towards large-scale deployments · complemented with a risk analysis...

109
Assessing CCS technologies towards large-scale deployments Dealing with Uncertainty in the O&G sector – a case study approach Pedro José Côrte-Real Ramalho Rolim Thesis to obtain the Master of Science Degree in Mechanical Engineering Supervisor: Prof. Manuel Frederico Tojal de Valsassina Heitor Examination Committee Chairperson: Prof. Mário Manuel Gonçalves da Costa Supervisor: Prof. Manuel Frederico Tojal de Valsassina Heitor Member of the Committee: Eng. Joaquim Neto Filipe November 2015

Upload: others

Post on 30-May-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

Assessing CCS technologies towards large-scale deployments

Dealing with Uncertainty in the O&G sector – a case study approach

Pedro José Côrte-Real Ramalho Rolim

Thesis to obtain the Master of Science Degree in

Mechanical Engineering

Supervisor: Prof. Manuel Frederico Tojal de Valsassina Heitor

Examination Committee

Chairperson: Prof. Mário Manuel Gonçalves da Costa

Supervisor: Prof. Manuel Frederico Tojal de Valsassina Heitor

Member of the Committee: Eng. Joaquim Neto Filipe

November 2015

Page 2: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

ii

Page 3: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

i

Acknowledgments

To Professor Manuel Valsassina Heitor, who led me throughout this thesis, I wish to express my

sincere thanks for introducing and encouraging me in such diverse areas of interest and in different

perspectives.

I want to manifest my gratitude to all the personnel in ProjectoDetalhe for being always so kind

and receptive to my ideas and doubts. Here, a special regard to Eng. Joaquim Neto Filipe and Eng.

Jorge Silva for the patience and availability even when setbacks arose.

Merit and recognition must go as well to all interviewed specialists, who gave me their valuable

insights adding value to this work.

My sincere thanks to all my colleagues for all the help and guidance during the past months at

IN+.

Yielding and providing important inside knowledge and partnership, I want to leave here a word

of appreciation to CIUDEN, headed by Eng. Lionel Loubeau.

I wish also to thank all my family and close friends to whom I will be eternally grateful for

accompanying me throughout the past years.

Lastly and most importantly, I would like to thank my parents, siblings and girlfriend for their never

ending support, tolerance and dedication.

Page 4: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

ii

Page 5: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

iii

Abstract

This dissertation assesses and discusses the potential of Carbon Capture and Storage (CCS)

large-scale deployments, under a context of increasing uncertainty. This eco-friendly solution is

investigated through the analysis of 4 case studies evaluating carbon dioxide transportation and storage

technologies. For transportation, pipelines and ships are comparatively assessed through an extensive

analysis covering costs, design approaches, construction and operation procedures. In addition,

reservoirs and injection processes are studied regarding carbon storage technologies, taking into

account monitoring and verification requirements.

The methodology used throughout this work relies on a case study basis, examined through an

extensive literature review and foresights of specialists from different areas. This methodology is

complemented with a risk analysis based on the IRGC risk governance framework, where drivers,

stakeholders and recommendations are pointed towards a sustainable growth in an era of constant

Energy Transitions and unknowns.

This thesis focus on the complex interaction between the O&G sector prosperity and the

development of CCS. Four possible emergent scenarios are build, having as variables the

competitiveness between energy sources and the geopolitical stabilization. Evidence gained from the

case studies is integrated and framed in those scenarios, where the potential of CCS is discussed in

each one, showing the challenging competition between technologies and environments and

acknowledging that no scenario will be determinant by itself, but rather all of them will compete and

coexist with one other in different contexts. The analysis demonstrates the importance of flexibility in

engineering design to tackle the challenge of growing uncertainty in global markets.

Keywords:

CCS; Carbon Mitigation; Oil&Gas; Technology Development; Uncertainty; Risk Governance.

Page 6: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

iv

Page 7: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

v

Resumo

Esta dissertação avalia e discute o potencial de implementação em larga-escala da Captura e

Armazenamento de Carbono (CCS). Num contexto de incerteza energética, esta solução é investigada

recorrendo a 4 casos de estudo avaliando tecnologias existentes de transporte e armazenamento de

dióxido de carbono. Para o transporte, pipelines e navios são comparados através de uma análise

intensiva cobrindo custos e procedimentos em termos de design, construção e operação. No

armazenamento, reservatórios e processos de injeção são estudados tendo em conta todas as

posteriores exigências de monitorização e verificação.

A metodologia usada ao longo deste trabalho baseia-se em casos de estudo, examinados através de

uma extensiva revisão de literatura e opiniões de especialistas de diferentes áreas. Esta metodologia

é complementada com uma análise de riscos baseada no modelo de governança de risco desenvolvido

pelo IRGC. Assim, drivers, investidores e recomendações são apontadas tentando alcançar um

crescimento sustentável numa era caracterizada por constantes transições no sector da energia.

Esta tese foca-se na complexa interação entre a prosperidade do sector do O&G e o desenvolvimento

do CCS nas últimas décadas. Quatro emergentes cenários são construídos, tendo como variáveis a

concorrência entre fontes de energia e a sustentabilidade geopolítica. O potencial do CCS é discutido

em cada um deles, mostrando não só a desafiante competição entre tecnologias e ambientes de

desenvolvimento mas também que provavelmente todos os cenários coexistirão em diferentes

contextos. A análise demonstra ainda a importância da flexibilidade no design de engenharia

desafiando a crescente incerteza inerente aos mercados globais.

Palavras-Chave:

CCS; Mitigação de Carbono; Oil&Gas; Desenvolvimento de Tecnologia; Incerteza; Governança de

Risco.

Page 8: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

vi

Page 9: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

vii

Contents

1. Introduction and Research Methodology ....................................................................... 1

1.1. Context and Motivation ................................................................................................ 1

1.1.1. Towards an International Observatory of Global Policies for the Sustainable Exploration of South Atlantic ............................................................................................................ 3

1.2. Technological Overview of Carbon Capture and Storage ........................................... 4

1.2.1. Project’s Lifecycle .................................................................................................... 4

1.2.2. Stages Overview ...................................................................................................... 6

1.3. Learning from Market Exploration in the Oil & Gas Industry ....................................... 8

1.4. Technological Systems and Trajectories ................................................................... 11

1.4.1. Observing Pre-Salt challenges .............................................................................. 12

1.4.2. CCS in Thermal Power Stations – Potential Technological Trajectories .............. 13

1.5. Research Problem ..................................................................................................... 14

1.6. Research Methodology .............................................................................................. 14

1.6.1. Case Study Analysis Definition .............................................................................. 14

1.6.2. International Risk Governance Council Framework .............................................. 15

1.6.3. Flexibility in Engineering Design ............................................................................ 19

1.7. Thesis’s Outline ......................................................................................................... 20

2. Assessing Carbon Dioxide Transportation Technologies .......................................... 21

2.1. CO2 Transportation Network ..................................................................................... 21

2.2. Pipelines Transportation ............................................................................................ 22

2.2.1. Case Study 1 – Technology Development Plant es.CO2 ...................................... 22

2.2.2. Design Approach ................................................................................................... 25

2.2.3. Operation and Maintenance .................................................................................. 29

2.2.4. End-of-life .............................................................................................................. 30

2.2.5. Challenges ............................................................................................................. 31

2.3. Ships Transportation ................................................................................................. 33

2.3.1. Case Study 2 – LCO2 Carrier Ship ........................................................................ 33

2.3.2. Design Approach ................................................................................................... 34

2.3.3. Operation Conditions ............................................................................................. 36

2.3.4. Challenges ............................................................................................................. 37

2.4. Comparative Analysis ................................................................................................ 38

2.5. Risk Analysis ............................................................................................................. 41

2.5.1. Drivers and Stakeholders ...................................................................................... 41

2.5.2. Risks Identification ................................................................................................. 42

2.5.3. Managing Risks and Recommendations ............................................................... 42

3. Assessing Carbon Dioxide Storage Technologies ...................................................... 44

3.1. Case Study Description ............................................................................................. 44

3.1.1. Case Study 3: Weyburn-Midale Enhanced Oil Recovery Project ......................... 44

3.1.2. Case Study 4: Statoil Carbon Storage Projects .................................................... 47

Page 10: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

viii

3.2. Reservoirs .................................................................................................................. 50

3.3. Injection Well ............................................................................................................. 55

3.4. Measurement, Monitoring and Verification ................................................................ 57

3.5. Risk Analysis ............................................................................................................. 59

3.5.1. Drivers and Stakeholders ...................................................................................... 59

3.5.2. Risks Identification ................................................................................................. 60

3.5.3. Managing Risks and Recommendations ............................................................... 61

4. Discussion and Summary ............................................................................................... 62

4.1. Summary ................................................................................................................... 62

4.2. Technological Challenges Overview ......................................................................... 65

4.3. Risks in the CCS Industry .......................................................................................... 66

4.3.1. Benefits, Drivers and Stakeholders ....................................................................... 66

4.3.2. Risks Identification ................................................................................................. 67

4.3.3. Managing Risks and Recommendations ............................................................... 68

4.4. Achievements Timeline ............................................................................................. 69

4.5. Scenario Building for the CCS Industry ..................................................................... 71

4.5.1. Energy Transitions: Risks and Challenges ............................................................ 75

4.6. Opportunities for Portugal .......................................................................................... 77

4.7. Concluding Remarks ................................................................................................. 79

4.8. Limitations and Further Work .................................................................................... 80

References ................................................................................................................................. 81

Annex A: Clusters for an effective Risk Assessment and Managing ........................................... a

Annex B: Pipeline Design Flow Diagram ......................................................................................c

Annex C: Carbon Dioxide Phase Diagram ................................................................................... d

Annex D: List of interviewed specialists ....................................................................................... e

Annex E: Interviews Transcript ..................................................................................................... f

Page 11: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

ix

List of Figures

Figure 1.1 – Lifecycle’s stages for a CCS project implementation .......................................................... 4

Figure 1.2 – Correlation between the evolution of barrel oil price and investment in CCS. .................... 8

Figure 1.3 – The three segments of Oil&Gas Industry Value Chain. ...................................................... 9

Figure 1.4 – Technological trajectories: FPSO, platforms and subsea technology. ............................. 12

Figure 1.5 – Risk handling phases and their linkages, following an international governance framework. ............................................................................................................................................................... 18

Figure 2.1 – Aerial view of the es.CO2 Technology Development Centre (Cubillos del Sil, Spain). .... 23

Figure 2.2 – CO2 pipeline incidents by cause and location from 1986 to 2008. ................................... 32

Figure 2.3 – Configuration of a ship-based CCS chain. ........................................................................ 34

Figure 2.4 – General characteristics of the LCO2 carrier. ..................................................................... 35

Figure 2.5 – General arrangement plan and particulars of the LCO2 carrier. ....................................... 36

Figure 2.6 – Possible schedule configuration and tasks distribution for a CCS ship transportation of 200 km (top) and 600 km (bottom). .............................................................................................................. 37

Figure 2.7 – Incidents by type from 2005 to 2014. ................................................................................ 37

Figure 2.8 – Different networks composed by different spines: pipeline onshore, pipeline offshore and ship. ....................................................................................................................................................... 39

Figure 3.1 – Oil production over the time and future predictions for the Weyburn and Midale fields. .. 45

Figure 3.2 – Statoil’s CCS projects timeline evolution. ......................................................................... 47

Figure 3.3 – Schematic representation of Sleipner CCS project........................................................... 48

Figure 3.4 - Steps to follow to choose a suitable storage location. ....................................................... 50

Figure 3.5 – Effects of Direct Ocean CO2 Injection on Deep-Sea Meiofauna. On the left, the progressive vector diagram illustrating flow, from the left to the right. A black circle notes the start of each day. On the right, the pH perturbations during the CO2 depletion. ..................................................................... 53

Figure 3.6 – Trapping contributions from different mechanisms and security increase over the time for CO2 injection. ......................................................................................................................................... 54

Figure 3.7 – Typical CO2 injection well and wellhead configuration. ..................................................... 55

Figure 3.8 – Possible leakage pathways in an abandoned well: a) and b) between casing and cement wall and plug, respectively; c) through cement plugs; d) through casing; e) through cement wall; f) between cement wall and rock. ............................................................................................................. 56

Figure 3.9 – Injection rates of different projects compared with the CO2 emissions of a 500MW coal power plant. ........................................................................................................................................... 57

Figure 3.10 – Different monitoring techniques and their application range. .......................................... 59

Figure 4.1 – Evolution of the number of CCS projects, investment and carbon managed. .................. 62

Figure 4.2 – Public perception of CCS contribution to mitigate the climate change. ............................ 63

Figure 4.3 – Leakage risk profile associated with the injection of carbon dioxide. ............................... 68

Figure 4.4 – Qualitative evolution of the CCS industry, split into three phases: Research, Demonstration and Commercialization. ......................................................................................................................... 70

Figure 4.5 – Future plausible scenarios for the O&G industry. ............................................................. 71

Figure 4.6 – CCS importance in emergent scenarios of the Oil&Gas industry. .................................... 74

Figure 4.7 – Location and description of potential storage areas and clusters for Portugal. Also showing the economically viable pipeline routes from and between the main CO2 source regions. .................. 78

Page 12: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

x

List of Tables

Table 1.1 – Distribution of CCS projects worldwide, grouped by continents and countries. ................... 2

Table 1.2 – Capture processes: advantages/disadvantages and its actual diffusion in the power industry. ................................................................................................................................................................. 6

Table 1.3 – Differences between existing and new CO2 pipelines. ......................................................... 7

Table 2.1 – Main characteristics of the experimental transportation unit of Cubillos del Sil, Spain. ..... 24

Table 2.2 – Design factor dependence on locations and scenarios. .................................................... 26

Table 2.3 – Location Classes description. ............................................................................................. 26

Table 2.4 – Possible materials candidates for pipeline design depending on the stream composition. 28

Table 2.5 – Identified threats differences between general and carbon dioxide pipelines. .................. 32

Table 2.6 – Table of costs for the three networks, split into investment and operational expenditures. ............................................................................................................................................................... 40

Table 2.7 – Overall comparison of the pros of both pipelines and ships. ............................................. 41

Table 2.8 – Drivers and Stakeholders involved in the transportation process of a CCS project. ......... 41

Table 2.9 - Systemic risks for the pipeline and ship transportation process. ........................................ 42

Table 3.1 – Examples of Features, Events and Processes (FEPs) for Weyburn-Midale CO2-EOR project. ............................................................................................................................................................... 46

Table 3.2 – Comparison of Sleipner and Snøhvit cases. ...................................................................... 49

Table 3.3 – Drivers and Stakeholders involved in the storage process of a CCS project. ................... 59

Table 3.4 – Systemic risks for the onshore, offshore and ocean storage process. .............................. 60

Table 4.1 – Highest maturity level observed for each CCS component and specific technology. ........ 65

Table 4.2 – Drivers and Stakeholders involved in the storage process of a CCS project. ................... 67

Table 4.3 – Systemic risks associated with CCS technological system. .............................................. 67

Table 4.4 – Strategies plans to change global scenarios, following the paths identified in the figure 4.6. ............................................................................................................................................................... 75

Page 13: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

xi

Abbreviations

BOP Blowout Preventer MCS Monitoring, Control and Surveillance

CAPEX Capital Expenditure MMV Measurement, Monitoring and Verification

CCS Carbon Capture and Storage MODU Mobile Offshore Drilling Units

CIUDEN Formación Ciudad de la Energía NSR Northern Sea Route

CFB Circulating Fluidised Bed

CPU Compression and Purification Unit

OIPG International Observatory of Global

Policies for the Sustainable Exploration of

Atlantic

DNV Det Norske Veritas OPEC Organization of Petroleum Exporting

Countries

EC European Commission OPEX Operational Expenditure

ECBM Enhanced Coalbed Methane Recovery OTPPC Offshore Thermal Power Plant with

Carbon Capture and Storage

EIA Environmental Impact Assessment P&ID Piping and Instrumentation Diagram

EGR Enhanced Gas Recovery R&D Research and Development

EOR Enhanced Oil Recovery R&D&I Research, Development and

Investigation

FEED Front-End Engineering Design ROV Remotely Operated Vehicle

FEPS Features, Events and Processes SBP Spar Buoy Platform

FPSO Floating, Production, Storage and

Offloading

SCADA Supervisory Control and Data

Acquisition Systems

FSRU Floating Storage and Regasification Units STP Standard Temperature and Pressure

GBS Gravity Based Structures TCM Technology Centre Mongstad

IMP Integrity Management Process TLP Tension Leg Platform

IMS Integrity Management System TPDs Technology Development Plants

IRGC International Risk Governance Council UK United Kingdom

LC Location Class USA United States of America

LPG Liquefied Petroleum Gas

Page 14: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

xii

Page 15: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

1

1. Introduction and Research Methodology

1.1. Context and Motivation

Today's energy sector is involved in major changes mainly due to the appearance and

development of new technologies. Many of the long-held tenets of the energy sector are being rewritten.

Major importers are becoming exporters, while countries long-defined as major energy exporters are

also becoming leading centers of global demand growth. Awareness of the dynamics underpinning

energy markets is essential for decision makers attempting to reconcile economic, energy and

environmental objectives. The right combination of policies and technologies is proving that links

between economic growth, energy demand and energy-related CO2 emissions can be weakened [1].

This structural change in the dynamics of the energy market, towards a low-emission scenario, is

the result of one of the major problems that world is facing at the moment: Global Warming. Driven by

the security of supply and climate change concerns, decarbonisation of energy supply has become a

priority for many countries. As global energy demand continues to grow together with dependence on

fossil fuels, the need to decarbonise as well as diversify energy supply is becoming ever more pressing

[2].

Currently existing fleet of fossil fuel combustion power plants generate significant amounts of

carbon dioxide emissions into the atmosphere (more than 12 billion tonnes of CO2 per year [3]), which

are believed to be the main cause of climate change [4]. If this trend continues, it will put emissions on

a trajectory corresponding to an average global temperature increase of around 6 °C in the long term

[5]. Nevertheless, they produce even when it’s not windy or sunny and contribute to a diversified energy

sources, so fossil fuel power stations must be complementary to intermittent renewables and inflexible

nuclear energy [6].

In a near future, however, these carbon dioxide emissions will be more controlled and even taxed.

Solutions are beginning to be implemented to maintain the sustainability of the fossil fuels consumption,

reaching the emission reduction goal of the European Commission (EC), which forces the sector to

reduce its emissions by 96-99% by 2050 [7]. EC foresees that the electricity mix will be therefore

dominated by three generator types: 1) renewable sources with a share of 59-83% of generated

electricity, 2) Carbon Capture and Storage (CCS) with a share of 7-32%, and 3) nuclear energy with a

share of 3-19% [8].

CCS places fossil fuels in a new lighting halt and make it possible to imagine and discuss about

a future with a maintained use of fossil fuels, while at the same time caring about the climate [1].

Basically, it is a technological system that captures the carbon dioxide after it is produced and stores it

in geological traps. The uncertainty threatened to inhibit investment in renewable energy in the grounds

that the prospect of large volumes of cheap gas might appear to provide a cheaper route to a lower

carbon economy [9]. Renewable energy presents some technical issues still remaining to be solved,

e.g. variable production, storage, efficiency, grid management, costs, among others. In this context a

rapid move away from fossil fuels is unlikely. The long life spans of energy supply infrastructures, energy

Page 16: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

2

security production and costs are just some reasons to be named, so such a rapid move could

destabilize world economies [10].

A successful innovation process within the field of Carbon Capture and Storage - which is the

process towards a future where CCS technology not only is possible, but is in use as an important part

of everyday industrial processes – is dependent on scientific achievement, industrial involvement, and

public funding [11]. In these days, this technological system is far away from general acceptance and

implementation. One may identify the real dissemination all over the world, examining table 1.1 where

several projects are distributed by countries. The definitions of different states that characterize the

project will be clarified afterwards.

Table 1.1 – Distribution of CCS projects worldwide, grouped by continents and countries.

Continent Country Projects Total Actives Completed Hold Terminated Potential

Africa Algeria 1 1 0 0 0 1 0

Australia Australia 17 17 7 0 3 6 1

North America

Canada 14

67

7 2 2 2 1

US 51 23 2 6 18 2

Mexico 2 1 0 0 0 1

South America Brazil 2 2 2 0 0 0 0

Asia

China 8

15

3 0 1 0 4

Saudi Arabia 1 0 0 0 0 1

UAE 2 0 0 1 0 1

Malaysia 1 0 0 1 0 0

South Korea 2 2 0 0 0 0

Taiwan 1 1 0 0 0 0

Europe

UK 6

43

0 0 3 1 2

France 3 3 0 0 0 0

Germany 4 0 1 1 2 0

Italy 4 2 0 1 1 0

Netherlands 6 4 1 0 1 0

Norway 6 4 0 1 1 0

Scotland 5 1 0 1 3 0

Czech Republic 2 0 0 0 0 2

Denmark 1 0 0 1 0 0

Poland 2 1 0 0 1 0

Spain 2 1 0 0 1 0

Iceland 1 1 0 0 0 0

Romania 1 0 0 0 0 1

From the table is notorious that the major developers of CCS projects are located in the North

America, particularly the United States. In Europe, the focus is mainly in countries situated more to the

North. South America and Africa have no relevance in the global panorama, being represented only by

2 and 1 projects, respectively. This sharp difference is once more explained by the investment and

industrialization contrasts between developed and developing countries.

Page 17: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

3

These numbers should not deceive or hide the reality. Each country has millions of carbon dioxide

sources, emitting several tonnes of it every single day. As so, 145 projects worldwide, of which less than

half in an active state, represent almost nothing in the mitigation of problems related with global warming.

Reasons of this poor adhesion should be investigated, since they can vary from the large initial

investments to public unacceptance or lack of knowledge. After this investigation and identification,

recommendations and policy measures should be drawn and put into action. The motivation for this

thesis is therefore to explore the potential and future of the use of CCS technology, specially addressing

the transport and storage stages (as the capture is more related with the chemical field). Individual

emphasis will be given to European, South American and African countries in a way to overcome the

foreseeable challenges and allow the sustainable exploration of the ocean, particularly the South

Atlantic.

1.1.1. Towards an International Observatory of Global Policies for the Sustainable

Exploration of South Atlantic

The increase supply of hydrocarbons in the North Atlantic (USA, Canada and potentially Mexico)

and in South Atlantic (Brazil, West Africa and potentially Venezuela) diminishes the economic risks of

disruptions in the Middle East oil supply for the Atlantic nations. In addition, the expansion of the Panama

Canal in times of increased uncertainty in the energy markets and potential production of unconventional

gas worldwide, may foster new systemic risks to emerge in the Atlantic, particularly in South Atlantic.

This will probably occur together with traffic and major commercial sea routes, which will be significantly

enhanced with the emergence of new industries in several parts of the Atlantic coast, including East and

West Africa and Northern Brazil [12].

There may be no other industry today that demands a more diverse set of human, political,

mechanical and technological capabilities than the oil and gas industry. Competition for natural

resources has driven companies to explore and produce in harsh, remote and even hostile locations,

where even the simplest of logistical tasks can be difficult and costly [13]. Discovered resources under

the pre-salt layer unveil the possibility that Brazil multiply its reserves and doubles the production until

the end of the present decade. These transformations will not automatically occur: they will rely on the

capacity of the Brazilian economy. The country in general and the companies in particular must face

several economic, technological and ecological challenges in order to make it all worthwhile [14].

The ultimate goal of this initiative is, therefore, to promote a consortium in the form of an

International Observatory, “OIPG – South Atlantic”, to stimulate participatory risk governance activities,

to support the design of public policies and the sustainable development of the industry. It is particularly

aimed to help improving the understanding of new innovation dynamics and technology-based services.

It is intended to stimulate qualified employment and investment in knowledge and R&D in Atlantic

regions, promoting their endogenous growth and facilitating new opportunities for industrial development

based on new technologies for global markets. Pilot case studies should be performed mainly on four

technology platforms: Observation Systems: Ocean Monitoring, Control and Surveillance (MCS); Ocean

Subsea Technologies; Ocean Surface Technologies and Port Technologies and Systems [12].

Page 18: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

4

This thesis should be incorporated in this project and will be focused in the last platform identified:

Port Technologies and Systems, through strategies designed to minimize health, safety and

environmental risks.

1.2. Technological Overview of Carbon Capture and Storage

As already introduced in the subsection 1.1, Carbon Capture and Storage is seen as a potential

abatement measure to help slow or invert climate changes which could be the answer for the transition

between today’s and more environmental friendly technologies [4].

In summary, the aim of CCS is to capture the CO2 produced and transport it to a place where it

can be stored for a very long period avoiding releases for the environment [10]. All the process, thus,

can be split into three main phases: the capture of carbon dioxide, its transportation and its storage. All

of them involve a wide range of challenges, technologies and regulations. Following the EU CCS

Directive, commercial CO2 capture, transport and storage activities are highly likely to be obligated to

be subjected to an Environmental Impact Assessment (EIA) to acquire those permits [15], [16].

1.2.1. Project’s Lifecycle

Before explaining the main challenges of each phase (capture, transport and storage), let one

start by describing the lifecycle of a CCS project, stage-by-stage. An integrated project is involved in

each element of the CCS chain – capture, transport and storage, which means that the lifecycle

described in the figure 1.1 may be applied in each phase.

A project is considered to be in ‘development planning’ when it is in the Identify, Evaluate, or

Define stage. A project is considered to have entered the active part when a positive final investment

decision has been taken (usually at the conclusion of the Define stage). When construction and related

commissioning activities are completed (Execute step), the project is in operation (Operate stage).

Finally, the project moves to the process of ceasing operations (Closure stage) and its consequences

[17].

Figure 1.1 – Lifecycle’s stages for a CCS project implementation

Identify

Evaluate

Define

Execute

Operation

Closure

Post-closure

Investment

Decision

Decommissioned

Planning

Active

Closing

Page 19: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

5

At the Identify stage, early studies and preliminary comparisons between alternatives are carried

out. The main objective is to determine the business viability and potential opportunities to be explored.

For example, an oil and gas company believes it could take concentrated CO2 from one of its natural

gas processing facilities and inject and store it to increase oil production at one of its existing facilities.

To start the process, the company would conduct preliminary desktop analysis of both the surface and

subsurface requirements of the project to determine if the concept is viable and attractive. It is important

that during this stage, proponents consider all relevant aspects of the project (stakeholder management,

project delivery, regulatory approvals, and infrastructure, as well as physical CCS facilities). Before

progressing to Evaluate stage, all options that meet the overall concept should be clearly identified [17].

In the Evaluate stage, the range of options that could be employed is examined to build on the

broad project concept. For the oil and gas company, this would involve exploring: which of its facilities,

and possibly even facilities of other companies, might be best placed to provide the concentrated CO2

for the project pipeline routes that could be utilised from each of these sites, and even alternative

transport options such as shipping; which oil production field is suitable for injection based on its

proximity to the concentrated CO2 source, stage of oil production at the field, and other site factors.

For each option primarily identified, the costs, benefits, risks, and opportunities are identified.

During the Evaluate stage, project proponents must continue to consider all relevant aspects of the

project. At the end of this stage, the preferred option is selected and becomes the subject of the Define

stage. No other options are studied in the Define stage.

In the Define stage, the selected option is investigated in greater detail through feasibility and

preliminary front-end engineering design (FEED). For the oil and gas company, this would involve

determining specific technology to be used, design and overall project costs, required permits and

approvals, and key risks to the project. Other activities during the Define stage include conducting

focused stakeholder engagement processes, seeking out finance or funding opportunities, and

undertaking tender processes for engineering, procurement, and contracting suppliers.

At this lifecycle point, the project must be sufficiently defined for a final investment decision to be

made. In the aggregate, the Identify, Evaluate, and Define stages can take between four and seven

years.

In the Execute stage, the detailed engineering design is finalised. Construction and

commissioning of the plant occurs, and the organisation to operate the facility is established. Once this

is completed, the project then moves into the Operate stage - where the CCS project is operated within

regulatory requirements, and maintained and modified, as needed, to improve performance.

In the Closure stage, the CCS project is decommissioned to comply with regulatory requirements.

The site is rehabilitated for future defined use and resources are allocated to manage post-closure

responsibilities. In the Post-closure period, the project is considered ‘Closed’, with assets

decommissioned and a post-closure monitoring program implemented [17].

Page 20: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

6

1.2.2. Stages Overview

Capture

Capture technologies separate carbon dioxide from gases and may be done, basically, by three

different methods: pre-combustion, post-combustion and oxy-fuel combustion systems [18]–[22]:

Pre-combustion refers to the carbon dioxide removal from the fuel before the combustion is

completed, involving its gasification and partial oxidisation. The gasification is a process where the fuel

is partially oxidized in steam and oxygen/air under high temperature and pressure to form synthesis gas.

This synthesis gas, or syngas, is a mixture of hydrogen, carbon monoxide, carbon dioxide, and smaller

amounts of other gaseous components, such as methane. The syngas can then undergo the water-gas

shift reaction to convert CO and water (H2O) to H2 and CO2, producing a H2 and CO2-rich gas mixture.

The CO2 can then be captured and the H2-rich fuel may be combusted in a modified gas turbine or fuel

cell producing power and water.

Post-combustion capture occurs in the downstream of the fuel combustion unit, where the

carbon dioxide is separated from flue gases. CO2 can be captured by a variety of techniques such as

absorption, membrane separation or cryogenic separation. Under the current state of technology, only

absorption and to some extent membranes are considered to be economically viable technologies. In

absorption techniques, carbon dioxide is absorbed from the flue gas in a separation tower using a

solvent [21], [22]. After the separation, it is regenerated by heating in a recovery column at temperatures

over 100˚C.

Oxy-fuel combustion is a variant of the post-combustion capture process. The oxygen required

is separated from air prior to combustion and the fuel is combusted in oxygen diluted with recycled flue-

gas rather than by air. This oxygen-rich and nitrogen-free atmosphere results in final flue-gases

consisting mainly of carbon dioxide and water, producing a more concentrated CO2 stream, enabling an

easier capture.

All techniques require a compression and dehydration of carbon dioxide before the transportation.

Gathering the three processes in the table 1.2:

Table 1.2 – Capture processes: advantages/disadvantages and its actual diffusion in the power industry.

Advantages Disadvantages State of the Art

Pre-

Multiple fuels can be used; Hydrogen produced can be reutilised; Increased efficiency gains from integration of the technology into power plants.

High construction costs; Reliability of all components for efficient integration; Decreased short-term flexibility

Evaluation

Post-

Can be applied to already constructed plants (retrofit); Little impacts on the existing power plant; Staged introduction which reduces disruption to the plant as well as investment risk.

Large energy penalty associated with thermal solvent regeneration; Large equipment requirements due to high volumes of flue gas; Corrosion of the equipment; Solvent degradation; Releases of harmful solvent/products.

Operation

Oxy-

Comparative ease with which CO2 can be separated (no solvent is required); Very high capture levels; Small physical size of the unit; Possibility of retrofit to an existing plant with some alterations.

Inflexibility due to the use of multiple burners; Large energy penalty of the air separation unit; High combustion temperatures; SOx emissions require an extra purification stage for the CO2;

Operation at sub-atmospheric pressure to prevent leakage.

Definition

Page 21: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

7

Transport

In most cases it is unlikely that sources of CO2 will be near to anywhere that could be suitable for

storage of CO2. This means the CO2 will require transportation to the storage sites by pipeline, road

tanker or ship. [23], [24].

Transporting carbon dioxide is the most technically mature step in Carbon Capture and Storage,

being already a known technology with significant experience. Technologies involved in pipeline

transportation are the same as those used extensively for transporting natural gas, oil and many other

fluids around the world. In some cases it may be possible to re-use existing pipelines. In the United

States there are by now more than 6000 km of CO2 pipes. There is also experience, albeit limited, with

transport of CO2 using offshore pipelines in the Snøhvit project in Norway. Each CCS project would

choose the most appropriate method for transporting carbon dioxide and be subject to planning and

health and safety regulation [22], [23].

There are, however, some differences between the carbon dioxide captured transportation and

commercial transportation, carrying new challenges and special design considerations. In terms of

pipelines, which is the transportation mode most used for large and continuous emissions (as a power

plant is example of), one may identify the following differences in the table 1.3 [25]:

Table 1.3 – Differences between existing and new CO2 pipelines. (Adapted from: [25])

Existing CO2 Pipelines New CO2 Pipelines

Enhanced Oil Recovery (EOR) CCS

Nearly Pure CO2 from dome fields Impurities, depending on the capture method

Remote, unpopulated areas Populated areas

Static Demand Fluctuation Demand (due to load factors)

Storage

Once the carbon dioxide (CO2) has been transported, it has to be stored. Two main ways exist to

do that: geological storage and ocean storage.

The first one refers to subsurface geological formations, where CO2 can be stored in pore space

of sedimentary rocks. Those formations, that are typically located several kilometres under the earth’s

surface, have large pressures and temperatures such that carbon dioxide will be in the liquid or

‘supercritical phase’ [26], [27].

Further than geological formations, ocean direct storage appears as a potential alternative. Ocean

storage and its ecological impacts are still in the research phase. Clearly, an ocean carbon sequestration

program will be successful only if its intended benefits outweigh its liabilities [28].

During and even after the injection, it is indispensable to monitor the storage site, demonstrating

the effectiveness of the storage project and to check for any possible leakage. Migration of CO2 from

the storage reservoir could possibly occur through poorly sealed and improperly abandoned wellbores

or transmissive faults and fractures in the cap rock. An escape of carbon dioxide from storage could be

detected through losses in the reservoir, migration in the rock above the reservoir and elevated

CO2 concentrations in the surface environment [26]. There is a range of monitoring techniques that can

be deployed to monitor the migration of CO2 in the reservoir and detect a possible leakage.

Currently, the state of the art of injecting carbon dioxide deep underground for storage is relevant.

There is already considerable experience at a number of industrial-scale CCS projects. These storage

Page 22: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

8

sites have been carefully selected and the evidence from monitoring suggests that the carbon

dioxide has been completely and safely locked into the geological formations. Carbon dioxide has been

stored for over 30 years in Enhanced Oil Recovery Projects and storage projects are on-going, with, for

example, the Sleipner project operating since 1996. Other projects include BP’s In Salah project in

Algeria and the Weyburn-Midale project in Canada [29].

Usage

Carbon dioxide utilization is attractive because it can offset a part of the cost of CCS. CO2 can be

used either directly as a working fluid or as a feedstock of chemical synthesis processes. The latter

usage can be a challenge because this molecule is thermodynamically stable. Current examples for

CO2 utilization are urea, refrigeration systems, inert agent for food packaging, welding systems, fire

extinguishers, water treatment processes, horticulture, and many other smaller-scale applications [4]. It

can also be used for the production of organic chemicals, polymers and fuels. However, the scale of

possible utilization is small compared to manmade emissions, and the utilization is usually in a short

term. Therefore, the industrial utilization of carbon dioxide is not expected to mitigate man-made

emissions significantly [27].

1.3. Learning from Market Exploration in the Oil & Gas Industry

It is of extreme importance to understand the O&G industry’s value chain, because it ends up

very similar with the CCS industry requirements. Further than similar, they are interconnected: the

investment in CCS technology strongly depends of the O&G sector prosperity and knowledge, as will

be witnessed throughout this thesis. One may try to establish a relation between the investment in CCS

projects and the oil price, both divided by the major value of the visible range (dimensionless). As the

oil prices increase, more money the companies spend in R&D, including these projects. The effects are

felt after a slightly time delay as shown in the figure 1.2:

Figure 1.2 – Correlation between the evolution of barrel oil price and yearly investment in CCS.

(Data from: www.macrotrends.net/1369/crude-oil-price-history-chart and http://www.netl.doe.gov)

The value chain analysis, as popularized by Porter [30], investigates the sequence of consecutive

activities which are required to bring a product or service from conception and procurement, through the

different phases of production and distribution, to the final customer.

0

0,2

0,4

0,6

0,8

1

Investment Evolution Oil Price Evolution

Page 23: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

9

The oil and gas industry encompasses a range of different activities and processes which jointly

contribute to the transformation of underlying petroleum resources into useable end-products valued by

industrial and private customers. These different activities are inherently linked with each other

(conceptually, contractually and/or physically), and these linkages might occur within or across individual

firms, and within or across national boundaries [31]. As the figure 1.3 suggests, the Oil&Gas value chain

can be broken into three main segments: upstream, midstream and downstream.

Figure 1.3 – The three segments of Oil&Gas Industry Value Chain.

(Source: http://files.gereports.com/wp-content/uploads/2010/10/infra_products_image_lg.jpg)

As observed, CCS value chain is inverted compared with the O&G: it begins in the capture,

located in the downstream, and goes to the upstream, where is located the storage reservoir.

The upstream can be divided into two phases: the first phase consists only in the search and

prospection of oil, gas or ores reserves in different terrains. The extraction of the raw materials, that has

the major technological challenges, constitutes the second phase. Here is where the subsea exploration

and all related technology can be found.

The midstream can be defined as the segment of transport of raw materials. It is an extreme

challenging process, as a result of the locations of the extraction stations, and in which several

technological innovations can come up, as for example in the pipe construction industry but also in the

naval.

The final segment, the downstream, is where oil processing and refining is done, being afterwards

a final product and presented to the client. In the following subsection it will be better addressed the

upstream and the midstream segments, which are the basis for the analysis of the subsequent chapters.

Page 24: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

10

Upstream Oil&Gas Value Chain Description

The Upstream value chain, of the offshore Oil&Gas exploration, can be particularly interesting to

mitigate the knowledge gap that exists in carbon dioxide storage. It is divided into smaller segments:

Reservoir Information – consists on the exploration of subsoil through reservoir imaging

systems and geological/geophysical equipments. Seismic analysis and the mapping of the wells is

made. This step is mostly conducted by geologists, who examine the terrain and rocky areas. Small

changes in Earth’s gravitational field and significant changes in magnetic fields can be indicators of the

presence of reservoirs. The most widely used technique offshore consists in evaluating seismic

reactions through compressed air guns or explosives. Through the reflection of shock waves with the

help of high sensitivity microphones and vibration detectors, the thickness of the various layers of the

soil are identified, thus building detailed maps of the subsoil [32][33].

Drilling and Casing Wells – here the site is prepared, physically and legally. Multiple holes are

drilled to be possible to prepare the main hole, in which is introduced the so-called conductor pipe (that

will connect to the rest of the production equipment). Offshore fields need support from specific modules:

Mobile Offshore Drilling Units (MODU). They launch the riser, which is the element that allows the

connection between the outside and the bottom of the sea. It is through this element that all fluids move

and also the drilling strings, used to drill to the desired reservoir. On the surface there is the Blowout

Preventer (BOP), which allows to control the entire system in case of imminent increase of abnormal

pressure that could lead to an uncontrolled explosion. Sorts of caps are used to seal the well and is

used mud or seawater to provide the pressure to insure the stability of the structure. Upon reaching the

predetermined depth, the well is coated with cement, to prevent it from collapsing. Then the well is ready

for the extraction phase [32], [33].

Infrastructure, Production and Maintenance – after having the infrastructure ready, extraction

of products is made through a suction process which is powered by an electrical system that feeds the

extraction pumps. In cases where oil is heavy it is necessary to create a second hole for the injection of

water or carbon dioxide, so as to increase the pressure in the reservoir. The latter process is called

Enhanced Oil Recovery (EOR) [32], [33].

Deactivation – after an analysis of the reservoir sustainability, and then concluded the

impracticality of it, is conducted a process of plugging the reservoir. In addition to this is also made a

clean sweep of the area, treatment of various natural surroundings and removal of infrastructures. It is

required by law to keep a check and monitoring of the field in post abandonment of the well [32], [33].

Midstream Oil&Gas Value Chain Description

Oil&Gas Midstream value chain can improve the necessary knowledge to transport the carbon

dioxide efficiently and securely. Midstream activities include the transport, storage and processing. The

transport can be made by two main options: storage vessels or pipelines. The midstream has not a life-

cycle as complex as the upstream has. Even so, one may identify the followings:

Liquefaction – if the transportation is by a storage vessel, such as in ships used for offshore

explorations, the hydrocarbon must be liquefied to allow a larger quantity in the same vessel (by an

Page 25: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

11

increase of the density, roughly 600 times [34]). In that way, the transportation is more economically

viable. Pipelines do not require this step, most of the times, but they are not used in offshore explorations

that are too far away from the shore.

Transport – refers to the transportation per se, from the exploration to the refinery, and from

there to the final consumer. It requires a lot of technological challenges, such as the construction,

maintenance and constant monitoring. In the case of pipelines, there is a need of pump stations along

the way. The cryogenic temperatures of the liquefied natural gas (-162ºC) make this stage very

problematic [34].

Regasification – after the transportation of natural gas, for example, it is necessary to reconvert

the LNG to the gas phase, which require a regasification terminal. They may be classified depending on

the facility set-up: onshore terminals, offshore gravity based structures (GBS) or offshore floating

storage and regasification units (FSRU) [35].

1.4. Technological Systems and Trajectories

According to [2] and [3], advances in a given technology rely on advances of other technologies

and allows possible future advances of many others. A technological system is a set of radical and

incremental cross-linked innovations. May be considered, therefore, as the final assembly of several

subsystems. As an example, Carbone Capture and Storage can be seen as the technological system

while the capture mode or the storage vessel (particularly its properties: material, size…) may be

labelled as the technology itself.

It is important to notice that not all technologies are complementary. Some of them are in direct

competition with each other. They can offer different solutions for the same problem, each with its own

advantages and disadvantages. As example, one may indicate the competition between the capture

systems used in Carbon Capture and Storage. They are different systems, each one of them with its

own pros and cons identified previously, designed for the same purpose: the capture of CO2.

Under certain conditions, the competition among technologies is supplanted by the competition

between technological systems. The choice of a dominant technology becomes a competition between

companies or even between national economies [38]. Technological trajectories, thus, are shaped by

the selection context: a range of social, institutional, economic and environmental situations [39]. These

factors may change the economic performance of new technologies, adding to them even more

uncertainty. According to [38], [40], [41], the search for the efficient set of technologies is a complex

process governed by firms. Full of failures and successes, technological learning is a key aspect of the

process. Firms move their innovation activities through technological trajectories, creating evolutionary

patterns that lead to a set of cumulative technological characteristics, eventually diffused in the

production of goods and services. A technological trajectory is standard way of solving problems within

the framework of a certain technological paradigm.

After the deployment of a dominant trajectory prevails, the uncertainty may decrease, as it outlines

a more predictable future. The search for economies of scale becomes a central aspect of the process

and the incremental innovations become increasingly relevant aspect of it [36]. Notably, once a

technology is adopted by a large group of firms, it becomes dominant despite the fact that larger

Page 26: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

12

economic benefits can be expected from other technological trajectories [38]. This situation typifies what

the literature calls a technological lock-in, meaning that firms are reluctant to take risks associated with

the adoption of different, although theoretically more efficient, innovations.

1.4.1. Observing Pre-Salt challenges

A perfect demonstration of the before exposed is the Petrobras’ case, where the pre-salt

discoveries begins to constitute a technological divide. For that explorations, Petrobras evaluated the

possibility of using new offshore production systems. Despite the enormous economic potential of the

reserves located in this new oil frontier, the number of technological obstacles (such as logistics, geology

and environmental protection) to be overcome to enable hydrocarbon production is significant. One can

identify three main technological trajectories, expressed as well in the figure 1.4 [38]:

Continuity – to move forward into the floating production system technological trajectory

adopted in the Campos Basin, characterized by the use of wet completion system, flexible

risers and Floating, Production, Storage and Offloading (FPSO) or semisubmersibles

platforms;

Intermediary – to start the use of platforms operated with dry completion, such as Tension

Leg Platform (TLP) and Spar Buoy Platform (SBP) using rigid risers;

Disruptive or Subsea to beach – to perform radical innovations such as multiphase

pumping and laser drilling that would enable the elimination of platforms.

Figure 1.4 – Technological trajectories: FPSO, platforms and subsea technology.

(Source: http://www.offshoreenergytoday.com)

Associated to each of these technological trajectories are different potential risks and benefits.

The continuity path has the advantage of being already an established concept, quite used all over the

world. Even so, new trajectories are being deeply studied, from the technological barriers to the

bureaucratic. It is fundamental to try to understand where change can be suitable, at several points of

Page 27: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

13

view – as the ultimate choice will not be solely determined by the pre-salt technological challenges, but

also by the Brazilian regulations and policies.

1.4.2. CCS in Thermal Power Stations – Potential Technological Trajectories

As already introduced, the scenario of taxed carbon emissions in the near future starts to agitate

the electricity sector, for example. The still high dependence of this sector from thermal power stations,

which burn fossil fuels producing too much carbon dioxide, easily suggests to the experts that a change

of paradigms is nearby.

One may say that the easy answer involves the dismantling of these units, ceasing CO2

emissions, and investing on the renewable energy. Throughout the last years several efforts have been

made in this way. Yet, a couple of obstacles inhibits a faster dissemination of renewables. The large

investments needed, the production intermittence and the interests of the industry already settled are

examples of those barriers.

From other point of view, the answer for that problem may be more focused on a less radical

innovation. If emissions cannot be much more controlled than now, the solution must involve the capture

and storage of those malicious chemicals present on the flue gases. Carbon Capture and Storage, as

previously identified, seems to be in the pole position to assume that role.

Learning from the Pre-Salt challenges pronounced on the previous subsection, one may think on

a disruptive concept as the Subsea to beach is. A portable offshore thermal power station, equipped

with CO2 injection facilities, fits on that category, revolutionizing all the electricity sector. The idea of

offshore station is not new, as it can be found on offshore wind power, for example. On the other hand,

the notion of portable is not original either. It is inspired on the FPSO’s used on the Oil&Gas exploration.

This disruptive technological system may be also baptised as “Subsea to beach”, since the electricity

comes to the shore under water. It may be labelled as OTPPC, as the acronym for Offshore Thermal

Power Plant with Carbon capture and storage. However, due to the crisis in the oil price, investment in

FPSO’s is slowing down, which may compromise the development of this solution.

This is a concrete example of the CCS application impact, showing that this technological system

may not only improve the ecological footprint but also reshape a whole sector, as is the case of the

electricity sector. Summarizing the last three paragraphs, each one describing a different potential

trajectory:

Continuity – to move forward into renewable energy, reinforcing the investment and

studying better ways to improve net results.

Intermediary – to continue fossil fuels consumption, but capturing carbon dioxide in order

to mitigate the climatic issues. This trajectory may include an investment on renewables

as well, but better balanced between the two types of energy.

Disruptive or Subsea to beach – to perform radical innovations in electricity generation

such as the portable power station, transmitting electrical power through subsea cables

over long distances.

Page 28: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

14

1.5. Research Problem

As seen, Carbon Capture and Storage technological system is not being substantially explored

worldwide. This thesis aims to identify the viability and sustainability of CCS growth and deployment in

times of uncertainty and energy transitions.

Therefore, through a strong and consolidated methodology described in the next section,

technologies regarding transportation and storage of carbon dioxide are going to be assessed and

discussed. Gathering all the knowledge, one will evaluate the effect of the Oil&Gas sector in the Carbon

Capture and Storage industry and which might be the importance of CCS in emergent scenarios

identified for the O&G industry. One will elaborate also a risk analysis, based on the framework

established by the International Risk Governance Council, identifying drivers, risks and

recommendations to improve the engagement of stakeholders and CCS sustainability.

1.6. Research Methodology

A research, wherever the subject is included, that aims to produce credible and useful results or

conclusions must be supported by a strong and consistent methodology. Technological Systems is an

emerging field at the intersection of engineering, management, and the social sciences. Designing

complex technological systems requires not only traditional engineering systems, but also knowledge

of public policy issues and awareness of societal norms and preferences. In order to meet the challenges

of rapid technological change and of scaling systems in size, scope and complexity, Engineering

Systems promote the development of new approaches, frameworks and theories to analyse, design,

deploy and manage these systems [42].

In this section the methodology used to progress through the research problem is presented.

Following a case study analysis definition and its recognized validity, a brief overview of the concepts

used along this thesis is given. Lastly, the risk governance methodology and the necessary flexibility in

engineering design are described, which allows an identification of risks and benefits of each trajectory.

1.6.1. Case Study Analysis Definition

This methodology originates from human and social sciences as well as evaluative research [43].

It is the science of the singular; it aims to understand what is distinctive of a case defined as specific, a

complex functioning thing, whether it be a person, a clinic, a classroom, an institution, a program, a

policy, a process or a system [44]–[46]. A variety of data may be collected to help deepen understanding

of the case and in qualitative studies this commonly includes interview, observation and document

analysis. No particular method of data analysis is associated with case study methodology: the

researcher is able to choose from a broad range of methods and will be guided by the focus of the case

study and research question [47].

The whole process has several steps, including: definition of research questions, specification of

the population in case, selection of more than one data collection methods, combination of multiple

investigators’ different data, data overlapping and opportunistic collection, data analyse and its

comparison with conflicting literature and reaching closure [48]. This theory is applied to science when

there is enough data to overlap and to get to real conclusions. All the theory must then be evaluated,

Page 29: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

15

parsimonious, testable and logically coherent [49]. All the process is pretty similar to the so known

“Reverse Engineering”.

This technique of creating new theories with case study basis has a great success on generating

novel theory by juxtaposition and by reconciliation of different types of data. Many say that this technique

is biased to corroborate with the investigator’s preconceptions, as the investigator will always try to

establish, even subconsciously, a linkage between his predictions or knowledge and the data collected.

Recent achievements defend that the only negative possibility comes from the staggering volume of rich

data that can lead the investigator to try to capture everything [48].

The case studies analysed in the next chapters aim to understand, through real and consolidated

examples, the applicability and viability of this technological system. They follow an extensive literature

review and interviews to understand the foresights of the experts in academia, scientific institutions and

industry. The term ”foresight” has been used to describe how to face long-term issues, essentially as

new policy tools to deal with problems in science, technology and/or innovation systems. While a few

tools and techniques have been developed, they represent an unprecedented diffusion of forecasting,

planning and participatory approaches to long-term issues [50].

Conclusions and recommendations taken from the case studies are presented in the end of each

chapter, supported by the extensive data from literature and interviews, following the framework of risk

governance, which consists on the selection of the major benefits, risks and principal recommendations

(benefits/risks analysis). In the last chapter a technology foresight is made, trying to understand if this

technological system will prevail in the near future and its limits of applicability, identifying the potential

opportunities for new projects and the potentially role that the Portuguese industry might develop.

1.6.2. International Risk Governance Council Framework

A risk governance, as defined by [51], is the identification, assessment, management and

communication of risk in a broad context. Many current risk issues are complex, uncertain, or even

ambiguous. In most cases, the potential benefits and risks interconnect. The aim of a better risk

governance analysis and framework is to help experts and academia to design policies, regulatory

frameworks and industrial strategies to enable societies to benefit from change while minimising the

negative consequences of associated risks.

The framework followed in this thesis is the one created by the International Risk Governance

Council (IRGC). This is an independent organisation whose purpose is to improve the understanding

and management of emerging systemic risks that may have significant impacts on human health and

safety, the environment, the economy and society at large. IRGC’s work includes developing concepts

of risk governance, anticipating major risk issues and developing and providing risk governance policy

recommendations for key decision makers.

IRGC’s mission is to facilitate a better understanding of risks and their scientific, political, social,

and economic contexts. It also provides support on how to manage them when there are knowledge

gaps, time constraints and policy trade-offs. IRGC believes that improvements in risk governance are

essential to taking optimal risk-related decisions and to maximising public trust in risk management

processes, structures and decisions. Concretely, the goal is to minimize:

Page 30: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

16

Inequitable distribution of risks and benefits between countries, organisations and social

groups;

Differing approaches to assessing and managing the same risk;

Excessive focus on highly profile risks, neglecting higher probability but lower profile risks;

Inadequate consideration of risk trade-offs;

Failure to understand secondary effects and linkages between issues;

Cost of inefficient regulations;

Decisions that take inappropriate account of public perception;

Loss of public trust.

For that, the IRGC’s framework comprises five linked phases:

1. Pre-assessment;

2. Appraisal;

3. Characterisation and evaluation;

4. Management;

5. Communication.

These interlinked phases, described in the next pages, together provide a means to gain a

thorough understanding of a risk and to develop options for dealing with it.

Risk handling is not just about risk management: it starts at the much earlier stage of risk pre-

assessment. Here the essential aspects of the risk are identified in order to provide a structured

definition of the problem.

To clarify the various perspectives on a risk, to define the issue to be looked at and to form the

baseline for how a risk is assessed and managed is essential to establish a normalized categorization

of risks – whether they are originated from natural, technological, economic or environmental causes.

This categorization may be split into four main classes: simple, complex, uncertain or ambiguous. Other

complementary aspects are the risk’s degree of novelty, scope, range, time horizon, type of hazard and

delay.

It is important to assure a meaningful engagement with the stakeholders, particularly how they

see the risk and whether or not there are any applicable legal or other existing rules or processes. This

evaluation may be done throughout interviews or conferences, involving all the stakeholders.

Risk appraisal develops and synthesizes the knowledge base for the decision on whether or not

a risk should be taken and, if so, how the risk can possibly be reduced or contained. This stage is the

most significant for all the technology related risks, comprising both a scientific and a concern risk

assessment. The first one consist of a conventional assessment of the risk’s factual, physical and

measurable characteristics including the probability of it happening. On the other hand, a concern risk

assessment ensures that decision makers account for how the risk is viewed when values and emotions

come into play. It refers to a systematic analysis of the associations and perceived consequences

(benefits and risks) that stakeholders, individuals, groups or different cultures may associate with a

hazard or cause of hazard. Each brings to the open different types of questions:

Page 31: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

17

Scientific risk assessment: what are the potential damages or adverse effects? What is

the probability of occurrence? How ubiquitous and persistent could the damage be? Can it be

reversed? How clearly can cause-effect relationships be established? What scientific, technical

and analytical approaches, knowledge and expertise should be used to better assess these

impacts? What are the primary and secondary benefits, opportunities and potential adverse

effects?

Concern risk assessment: what are the public’s concerns and perceptions? What is the

social response to the risk? Is there the possibility of political mobilization or potential conflict?

What role are existing institutions, governance structures and the media playing in defining public

concerns? Are risk managers likely to face controversial responses from differences in

stakeholder objectives and values, or from inequities in the distribution of benefits and risks?

A good risk characterization and evaluation is an essential tool to justify the decisions taken

throughout the management of risks. This stage ensures that the evidence based on scientific facts is

combined with a thorough understanding of societal values when making the judgment of a particular

risk as acceptable, tolerable or intolerable. Here is important to keep in mind that “no evidence of proof

is not evidence of no proof”.

All the acceptable and, more importantly, the tolerable risks will need appropriate and adequate

risk management. It involves the design and implementation of the actions and remedies required to

avoid, reduce, transfer or retain the risks. Decisions are taken and put into practice, based on the

development of a range of options and a consideration of the most appropriate of them. Risk

management includes not only the generation, assessment, evaluation and selection and

implementation of appropriate risk reduction options, but also monitoring their effectiveness and

reviewing the decision if necessary.

Throughout this phases, the communication between the involved parts is of the utmost

importance. It enables stakeholders and civil society in general to understand the risk itself, as well as

their particular role and responsibilities in the risk governance process. Once the risk management is

made, communication should explain the rationale for the decision and allow people to make informed

choices. If all this process is developed on a two-way philosophy, all the participants have a voice in it.

Effective communication is the key to create trust in risk management.

To survey the strength and validity of this framework, one may identify a series of risk

governance deficits that are grouped into two broad clusters [51]:

Cluster A: related to the assessment and understanding of risks, including the collection

and development of knowledge. They affect the decisions that will be made with regard

to risk management.

Cluster B: related to the management of risks, the acceptance of responsibility and the

taking of action in order to reduce, mitigate or avoid the risk.

These clusters may be found as decision maps (annex A) to facilitate the detection of possible

deficits on a particular project, and will be used along this thesis.

Page 32: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

18

The approach here presented allows the emphasis on conveying systematic knowledge. It

assures transparent and clever decisions, supported by relevant experiential and practical knowledge.

The integration among several risk domains, different actor groups and of theory and practice, permits

an integrated and interdisciplinary approach to the sectors and themes ensuring quality on identifying

and managing the risks [52]. The framework stresses the broader social, institutional, political and

economic contexts that must be taken into account in risk-related decision-making. The figure 1.5 (next

page) shows the connections between all the mentioned categories in a lifecycle format, splitting the

phases into two main domains: the assessment and the management.

Figure 1.5 – Risk handling phases and their linkages, following an international governance framework.

(Source: [52])

Some Definitions

After the description of the framework followed in this work let one just clarify some of the

definitions and key-words used throughout the next chapters, according to [53]:

Risk is an uncertain (generally adverse) consequence of an event or activity with respect to

something that human’s value. Risks are often accompanied by opportunities.

Systemic risks are embedded in the larger context of societal, financial and economic

consequences and are at the intersection between natural events, economic, social and technological

developments and policy-driven actions. They arise from the interactions and interdependence of the

components forming an integrated whole [54]. Such risks are not confined to national borders; they

cannot be managed through the actions of a single sector; they require a robust governance approach

if they are to be adequately managed. The governance of systemic risks requires cohesion between

countries and the inclusion within the process of governments, industry, academia and civil society.

Page 33: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

19

Complexity refers to difficulties in identifying and quantifying causal links between a multitude of

potential causal agents and specific observed effects. Complex Systems are by definition composed of

many parts that interact with and adapt to each other, offering highly complex risks.

Uncertainty refers to a lack of clarity or quality of the scientific or technical data. Highly uncertain

risks include many natural disasters, acts of terrorism and sabotage and the long-term effects of

introducing genetically modified species into the natural environment. Ambiguity results from divergent

or contested perspectives on the justification, severity or wider meanings associated with a given threat.

Governance refers to the actions, processes, traditions and institutions by which authority is

exercised and decisions are taken and implemented.

Risk Governance, as already explained, deals with the identification, assessment, management

and communication of risks in a broad context. It includes the totality of actors, rules, conventions,

processes and mechanisms and is concerned with how relevant risk information is collected, analysed

and communicated, and how management decisions are taken. It applies the principles of good

governance that include transparency, effectiveness and efficiency, accountability, strategic focus,

sustainability, equity and fairness, respect for the rule of law and the need for the chosen solution to be

politically and legally feasible as well as ethically and publicly acceptable.

Risk Governance Deficits is defined as deficiencies (where elements are lacking) or failures

(where actions are not taken or prove unsuccessful) in risk governance structures and processes.

Deficits hinder fair and efficient risk governance and increase the severity and cost of a risk event.

Risk Management refers to the process of accepting, avoiding, transferring or controlling the risk

to an acceptable level considering associated costs and benefits of any actions taken [54].

1.6.3. Flexibility in Engineering Design

As said long ago by Isaac Asimov, the only constant is change, continuing change, inevitable

change; that is the dominant factor in society today. No sensible decision can be made any longer

without taking into account not only the world as it is, but the world as it will be.

In order to achieve the best results in an engineering project, such as a CCS project, there is

need to adapt to circumstances as they arise. It is necessary to have designs that can be easily modified

to take advantage of new opportunities or mitigate adversities. The future is uncertain: design that does

not account for a range of possibilities that may occur over a long lifetime runs the risk of leaving

significant value untapped or even incurring major losses. This uncertain future provides not only a

range of risks, but also a variety of opportunities.

Once the uncertainty is recognized, the design approach may be made with robustness or

flexibility. Robustness is the world in which traditional engineers feel at home, requiring a reasonable

overdesign of the system so that it functions well under all scenarios. However, this approach commits

all capital upfront and is thus very costly because only one of the futures will occur. In many

circumstances, it is smarter to build enough flexibility in the system to allow the system operator to adapt

it to changing circumstances.

Design flexibility has the power to exploit uncertainties in technological systems, increasing the

expected value of our projects significantly by designing them cleverly to deal with future eventualities.

The prediction of these eventualities is the main challenge. Humans have no omniscience to predict

Page 34: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

20

precisely what may happen. They have to be satisfied with good estimates of the distribution of

possibilities, of the range of what may happen and the relative likelihoods of various scenarios.

According to [42], estimating the distribution of future possibilities is a five-step process:

1. Identify the important factors;

2. Analyse historical trends;

3. Identify trend-breakers;

4. Establish forecast (in)accuracy;

5. Build a dynamic model.

It is not obvious which flexibilities will add the most value to a project. The answer depends on

many interacting factors, such as the nature of the system, the kinds and intensities of uncertainties as

well as the cost of implementing that flexibility.

1.7. Thesis’s Outline

The methodology employed is founded on a case study basis research where, for both carbon

dioxide transport and storage, one will present two case studies of projects that added value to the CCS

general knowledge. Supported by an International Risk Governance Council Framework, through an

extensive bibliographic research and experts’ foresights, the engineering challenges, ranges of

applicability and operation, investments, public concerns and the managing of the risks are the centre

of each study. The foresights were collected through interviews to different experts from the industry

and academia (interviewees list available in the annex D and transcription in the annex E). Chapter 2

and 3 deal, respectively, with the transportation and storage of carbon dioxide.

In the last chapter, a summary and an overview of the technological challenges is performed.

Besides, all the knowledge gained from all the case studies is integrated and framed in the global

scenario of the Oil&Gas industry, taking into account the big unknowns and the growing uncertainty in

the global economy. There are also addressed opportunities for Portugal and the engineering role in the

prosperity of this technological system, towards an International Observatory of Global Policies (OIPG),

along with the inherent limitations and further work.

Page 35: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

21

2. Assessing Carbon Dioxide Transportation Technologies

Carbon dioxide transportation is the middle step between capture and storage. It is of extreme

importance in a Carbon Capture and Storage project, since it connects the source and the reservoir,

affecting the viability of the whole project.

In this chapter one will start by clarifying the transportation network, facing afterwards the two

main transportation methods: pipeline and ship. Both are going to be analysed through a case study for

each one: Cubillos del Sil (Spain) for pipelines, and LCO2 carrier for ship transportation. A design

approach, construction, operation and maintenance procedures will be identified for each one, along

with a comparative cost analysis. The chapter ends with a risk analysis where challenges, risks and

stakeholders are assessed.

2.1. CO2 Transportation Network

Carbon dioxide is transported from the capture to the storage site through a complex

transportation network. This network is designed accordingly to specifications and exigencies of each

project. The main objective of the projector is to design this network to transport CO2 on an efficient and

reliable manner, taking into account the investment and operation/maintenance costs. Contributions to

the normal production, i.e. regularity and availability on the carbon dioxide transportation, will be different

from component to component of the system. The impact from each component (or set of components)

on a system will mainly depend on the level of redundancy, the function of the component in the system,

the failure frequency and the downtime (given a failure) [55].

Transport may be made through storage tanks (in ships, trucks or even rails) or pipelines. The

choice whether to use vessels or pipelines, or even both, strongly depends on the project’s conditions.

The whole network should be planned and constructed from the beginning at regional or national level

and oversized to meet transportation needs of multiple CO2 sources. This integrated perspective would

take advantage of economies of scale and enable the connection of additional CO2 sources with sinks

in the course of the pipeline lifetime. Opposite approaches, as the single source to single site is example,

are likely to impede large scale deployment of CCS as it will not permit the expansion and sharing of

built infrastructure with other sources, especially in more densely populated areas where there is need

to transport carbon dioxide from multiple anthropogenic sources. These sources, in turn, will be required

to develop their own pipelines, resulting in deployment delays due to permitting procedures, and

additional costs, since pipeline costs do not scale proportionally with transport capacities [56].

Thus, sources and reservoirs may be connected in two main different strategies:

Multiple sources to site: diverse sources feeding the same reservoir;

Multiple sources to multiple sites: one source provide carbon dioxide for two or more

reservoirs, while the same reservoir is fed by different sources.

The first strategy is adopted when a relatively large reservoir exists near the sources, being the

only one ready to receive carbon dioxide. It allows a reduction of investment costs, since there are quite

less necessity of equipments and infrastructures as they are shared by all the sources.

Page 36: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

22

On the other hand, if the grid is composed by several sources and reservoirs, there is a major

flexibility in terms of transportation routes, future expansion to other sources and there are more

available reservoirs to inject CO2. This advantages may reduce some risks and increase the efficiency

of the whole project, which might counterbalance the larger investment in equipments, infrastructures

and even in human resources needed.

2.2. Pipelines Transportation

2.2.1. Case Study 1 – Technology Development Plant es.CO2

Even though in the past decades several pipelines transporting carbon dioxide were projected

and successfully operated, the engineering behind it is not yet perfectly known. In Cubillos del Sil (Leon,

Spain) there is a Technology Development Centre, called es.CO2, testing different areas related with

CO2 capture and transport. This facility, whose objective is to develop technologies to reach industrial

scale, belongs to CIUDEN and is part of phase 1 of the Compostilla project.

In July 2009, European Council and the European Parliament adopted the European

Commission’s proposal for the European Energy Programme for Recovery (EEPR). The EEPR funds

projects in the fields of energy, including CO2 Capture and Storage. In December 2009, EEPR granted

financial assistance to 6 CCS demonstration projects, including the OXYCFB300 Compostilla Project in

Northwest Spain, initiative run by a public-private consortium. This Compostilla project was thought in 2

phases to reduce significantly economic and technical risks as well as to enhance experience and

technical support:

Phase 1: Technology Development – construction of three Technology Development

Plants (TPDs) at pilot scale, each one addressing a different CCS step (capture, transport

and storage). This phase also includes the survey and geological characterisation of a

safe and suitable geological CO2 storage at demo scale, the development of the Project

FEED including the capture plant, pipeline and the injection infrastructure, the permitting

process and the associated engineering studies required to guarantee the successful

delivery of Phase II.

Phase 2: Technology Demonstration – capture, transport and storage technologies

tested in the Phase 1 will be scaled up to a demo scale. The Project aims to construct a

300MWe Circulating Fluidised Bed (CFB) oxycombustion Demo Plant at ENDESA’s

Compostilla. Captured CO2 will be injected into a deep saline geological formation.

The partners involved in this consurtium were, by order of importance: ENDESA Generacion;

CIUDEN and Foster Wheeler. ENDESA is the coordinator of the project and the owner of the

Compostilla power station in Cubillos del Sil (Leon, Northwest Spain), which is the planned site for the

300 MWe Capture Demonstration Plant. Fundacion Ciudad de la Energia (CIUDEN) conducts R&D

activities in the field of CCS through the construction and operation of three Technology Development

Plants. Finally, Foster Wheeler is the technological provider of the Circulating Fluidised Bed units in the

Capture TDP and Demo plant.

Page 37: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

23

Phase 1, where CIUDEN was the responsible, was concluded successfully and is still in operation.

However, phase 2 was cancelled due to the lack of regulatory policies and because ENDESA, that was

the leader, renounced to do it.

One will focus the case study in the TDP of Cubillos del Sil described above, since it is the platform

where transportation via pipeline is being more deeply assessed. This es.CO2 Centre has a semi-

industrial size, including the systems shown in the figure 2.1:

Figure 2.1 – Aerial view of the es.CO2 Technology Development Centre (Cubillos del Sil, Spain).

In this case study one will concentrate on the unit 6, CO2 Transport Experimental Facility, which

tests the carbon dioxide behaviour in pipelines transportation. Experiments are performed in 6 different

experimental areas and the facility is held inside of a thermally isolated and temperature controlled

building, avoiding the influence of environmental temperature changes during experiments. The

installation can be divided in two systems: the feeding & preparation and the experimentation. The main

technical characteristics are described in the table 2.1 (next page).

Before operation, the coils and the buffer tank are filled with carbon dioxide. This carbon dioxide

may be provided by two different sources: captured at the CPU or commercial pure CO2. The filling

process is performed by two pumps from either location. The quality and composition of CO2 depends

on the source and on the capture technology. Moreover, the facility is equipped with a doping system

that is able to simulate different compositions by adding trace elements.

The pressure to transport CO2 through the pipeline, to carry out any experiment, is achieved by a

membrane pump. Temperature is regulated using 3 heat exchangers by means of steam and chilled

water. Temperature and pressure are generally set to achieve dense phase CO2 conditions.

1 – Fuel Preparation

System

2 – Pulverized Coal Bed

3 – Circulating Fluidized

Bed Boiler

4 – Flue Gas Cleaning

System

5 – Compression and

Purification Unit (CPU)

6 – Transport Experimental

Facility

7 – Bubbling Bed Biomass

Gasifier

8 – CCS Laboratory

Page 38: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

24

Table 2.1 – Main characteristics of the experimental transportation unit of Cubillos del Sil, Spain.

Feeding & Preparation System

CO2 temperature and pressure from CPU -34ºC; 14.5 bar

Commercial CO2 temperature and pressure -17.2ºC; 20 bar

Feeding pumps pressure and flow 80-110 bar; 1m3/h

Heat exchanger From 10ºC to desired temperature

Buffer tank 4.5 m3

Doping SOx; NOx; H2O; CO; H2S; H2; CH4; N2;

O2; Ar

Experimentation System

10 tube coils 8 carbon steel; 1 stainless steel; 1

duplex stainless steel

Coils length and diameter 300 m each and 2”

Circulation pump Membrane pump, 80-110 bar

3 heat exchangers 10-31ºC (capable to run experiments at two different temperatures at the same

time)

6 experimental areas Depressurisation; Leakage; Fracture; Corrosion; Instrumentation; Pressure

drop

The research lines being assessed in this transportation unit are:

Development of tools for scaling up;

Carbon dioxide transport behaviour under different conditions and impurities;

Material affection by CO2 streams;

Start-up and shut-down routines, and transient periods;

Instrumentation development and advanced process simulation.

At least for an initial and development state of Carbon Capture and Storage concepts, pipelines

are seen as the preferable solution for carbon dioxide transportation. While there is a current perception

that transporting CO2 via pipelines does not represent a significant barrier to implement large-scale

CCS, there is significantly less industry experience than for hydrocarbon (e.g. natural gas) service. Thus,

there is a number of issues that need to be adequately understood and the associated risks effectively

managed, despite the fact that there is no indication that problems for carbon dioxide pipelines are any

more challenging than those already set by hydrocarbon pipelines, or at least that they cannot be

resolved [57].

Pipelines transportation may be classified in two different categories: those that are constructed

and operated on land and the others that are positioned underwater. The first ones are known as

“Onshore Pipelines”, while the underwater are recognized as “Offshore Pipelines”. There is no properly

a choice between the two types, they might be seen as complementary instead of competitors. For

example, for an offshore reservoir both ways might be needed if the source is not located in the

shoreline.

Today, CO2 is mainly transported by pipelines for industrial purposes. The majority of those

pipelines are found in North America, where there is over 30 years of experience, mainly from natural

deposits and gas processing plants for enhanced oil recovery (EOR). The only existing offshore pipeline

for transporting CO2 is the Snøhvit pipeline (Norway), which has been transporting CO2 obtained from

natural gas extraction through a 153 km seabed pipeline since May 2008 (Case Study 4).

Page 39: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

25

An important feature to highlight is the possibility to requalify a pipeline that is or was normally

used for natural gas transportation, for example. This requalification allow important savings in the

investment costs, which might contribute to raise the interest on CCS projects, as it will be further

assessed in this chapter.

A pipeline project entails several phases, from the concept and design to the abandonment,

passing by construction and operation/maintenance. The next sections describe these stages, covering

also the pipeline requalification scenario.

2.2.2. Design Approach

In the very beginning of a pipeline design, concepts and numerous alternatives must be

developed and analysed, finding the best solutions accordingly to the premises and norms that have to

be followed. At this stage the agenda is outlined, anticipating necessities for the design and construction.

It is important at this point, as previously alerted, to foresee the potential sources near the one being

studied. Building a large network clustering different sources, which might allow important savings in

investment costs, should always be a priority.

Methodology

Established the main features of the project, engineers start to design the entirely pipeline,

connecting the source to the sink or, if it is the case, to the network already existing. Here, some critical

criteria must be delimited and followed all over the design process, including [55]:

System dynamics: dynamic interaction between system components;

Flow assurance modelling: modelling of hydrate potential, hydraulics, pressure

transients;

Validation of dispersion modelling methods: clarification of source terms, accurate

modelling, empirical modelling, definition of distances between pipelines and habitation;

Physical properties: validation of multi-component modelling techniques, empirical data

generation;

Mechanical design: fracture control prediction and techniques, material selection.

Accordingly to [58], there are influential inputs that influence the piping design: fluid properties;

environment; effects of pressure and temperature; design conditions; supply and demand

magnitude/locations; codes and standards; route, topography and access; environmental impact;

economics; hydrological impact; seismic and volcanic impacts; material; construction; commissioning;

operation; protection and integrity. The fluid’s pressure and temperature determine its phase, which is

of major interest to predict corrosion, pressure drops and flow rate. The terrain’s elevation or slope

affects strongly the pressure drops and the flow rate needed to transport the fluid from one point to

another. Furthermore, the terrain’s topography should be evaluated, such as its live and dead loads, the

tendency for earthquakes, waves and tidal currents (in the case of offshore pipelines), which defines if

the pipeline is going to be buried or not.

Page 40: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

26

Regulation

There are some specifications, given in certain norms, which must be rigorously followed

accordingly to the issue being studied. CO2 pipelines shall be designed in accordance with industry

recognized standards and applicable regulatory requirements [59]. Land and marine pipelines are not

as different, in a regulation point of view, as may appear. Offshore pipelines design do not have to worry

about population density and esthetical issues. As so, they are based on similar premises, differing

mainly on the construction and operation procedures.

In the methodology phase there is a step of fundamental importance: the choice of the design

factor. It will be systematically taken into account all over the designing process, and should be reviewed

every time that appears a significant modification in the project. Before the choice of the safety factor,

which is the ratio between the material strength and the expectable service load, there are norms that

establish how much of the material strength the item is required to withstand. For carbon dioxide,

accordingly to the ISO 13623, it comes in the table 2.2. for onshore and offshore pipelines:

Table 2.2 – Design factor dependence on locations and scenarios. (Adapted from: [59])

Scenarios Onshore Offshore

General route 0.77 (LC > 1); 0.83 (LC = 1)

0.77 (LC > 1); 0.83 (LC = 1)

Crossings

- Minor roads 0.77

- Major roads, canals, rivers, lakes 0.67

- Shipping lanes, anchoring areas, harbour entrances

0.77

- Landfalls 0.77

Pig traps and multi-pipe slug catchers 0.67 0.67

Special constructions 0.67

Risers and primary piping 0.67

Where LC stands for Location Class, which in the view of the same norm means:

Table 2.3 – Location Classes description. (Source: [59])

LC Description

1 Locations subject to infrequent human activity with no permanent human habitation. Is intended to reflect inaccessible areas such as deserts and tundra regions

2 Locations with a population density of less than 50 persons per square kilometre. Is intended to reflect such areas as wasteland, grazing land, farmland and other sparsely populated areas

3

Locations with a population density of 50 persons or more but less than 250 per square kilometre, with multiple dwelling units, with hotels or office buildings where no more than 50 persons may gather regularly and with occasional industrial buildings. Is intended to reflect areas where the population density is intermediate between LC2 and LC4, such as fringe areas around cities and towns

4 Locations with a population density of 250 persons or more per square kilometre, except where a LC5 prevails. Is intended to reflect areas such as suburban housing developments, residential areas, industrial areas and other populated areas

5 Locations with areas where multi-storey buildings (four or more floors above ground level) are prevalent and where traffic is heavy or dense and where there may be numerous other utilities underground

Page 41: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

27

Simulation Models

In the methodology phase the mathematical and physical models that are going to be used must

be selected. There are two major criteria that have to be adopted in the study of the pipeline integrity:

the one to control the fracture propagation and the equation of state of the stream. They are changing

and being improved systematically, but not even all the experts trust in the same models.

For the fracture arrest conditions, ductile fracture does not propagate if the pipeline is designed

according to the following:

3.33

𝜎𝑑

𝜎𝑓

>2

𝜋cos−1 (exp (−

𝜋 𝐸𝑁

24))

(3.1)

𝜎𝑑 =𝑃𝑑𝐷

2𝑡

(3.2)

𝐸𝑁 =(𝐸 𝐶𝑣)

12

𝐴𝜎𝑓2 (

𝐷𝑡

2)

(3.3)

Where:

A Area beneath Charpy notch [m2] Cv Charpy notch material toughness [J] D Outside pipe diameter [m] E Young’s modulus [Pa] EN Normalised toughness parameter Pd Decompressed pressure, [Pa] t Pipe wall thickness [m] σd Decompressed pipe hoop stress [Pa] σf Pipe steel flow stress [Pa]

The stream’s equation of state selection is a bit more complicated. Significant discussion on the

subject has taken place in articles and conferences, however no consensus has been reached. There

are three most known and used to describe the state of matter under a given set of physical conditions,

even though giving different results that influence pipeline design.

Design

Once everything is planned and outlined, the project moves to the design stage. Knowing the

location of the source and the sink, the best route to follow, if it is going to be an onshore and/or offshore

project, if the pipeline is going to cross populated areas, if it is mandatory that the pipeline be buried and

so on, it is time to think what materials, infrastructures and components must be used.

The primarily objective is to transport carbon dioxide, from a point A to a point B, as safe and

reliable as possible. However, the engineer should incorporate some external aspects when analysing

the results. Incorporate that pipelines in a global network and the accessibility for the trucks that

transport the pipeline to construction site are examples of that. Overall costs should always be taken

into account, but not always the cheapest solution is the preferable.

Nowadays no one projects a pipeline without the fully support of a specialized software. There

are many software available in the market, all of them having similar characteristics. These

Page 42: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

28

computational programs operate on a tri-dimensional referential, which facilitates the design.

Additionally, they are equipped with simulation analysis, which allows the study of the behaviour of a

certain material, flow, dimensions and so on. Through this approach, several variables are iterated and

the optimal one is found, for the premises and objectives established.

As already introduced, the composition of the carbon dioxide stream depends on the capture

system and on the source itself. The most efficient way to transport it is in the dense phase, above the

critical point (73bars, 31ºC). Generally, CO2 is transported at temperature and pressure ranges between

13ºC and 43ºC and 85 and 150 bars, respectively. The upper temperature limit is determined by the

compressor-station discharge temperature and the temperature limits of the external pipeline coating

material, whereas the lower temperature limit is set by winter ground temperature [60].

When stream properties are fully set, the pipeline material may be selected. This selection should

be compatible with all states of the CO2 stream, covering also the potential low temperature conditions

that might be caused by a depressurization situation, being resistant to the corrosion as much as

possible. Based on the ISO 15156, pipeline material should be carefully chosen from the shortlist shown

in the table 2.4. It depends mainly of the presence of free water, which is basically water not dissolved

in the dense CO2 phase, i.e. a separate phase containing water that requires more resistant materials.

This can be pure water, water with dissolved salts, water wet salts, water glycol mixtures or other

mixtures containing water. Other important constituent is the hydrogen sulphide, H2S, which is

dangerously flammable, with a strong odour and extremely toxic.

Table 2.4 – Possible materials candidates for pipeline design depending on the stream composition.

(Adapted from: [59])

No free water With free water

Material Types Pure CO2 CO2 + H2S Pure CO2 CO2 + H2S

C- and low alloy steel

304

316

13Cr

22Cr (duplex)

25Cr (duplex)

Nickel based alloys

Components

Pipelines are not only constituted by the pipe shell itself. Along the pipeline’s course, they are

equipped with several components and infrastructures, each with its own function, used to assure a safe

and reliable transport, keeping the fluid and the pipeline’s integrity within operational conditions. One

may identify the main components: valves; compressors; booster pumps; PIG launchers and receivers;

batching stations and instrumentation; metering stations; Supervisory Control and Data Acquisition

(SCADA) systems.

As the pipeline is being designed, the engineer add these components and infrastructures as they

are needed. Here, the software assumes a huge role, as the user may easily add or remove components

or even modify the pipeline layout, accordingly to the simulations results, finding iteratively the best

configuration possible.

Page 43: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

29

The final step that concludes the piping design is the elaboration of the so called Piping and

Instrumentation Diagram (P&ID). It plays a significant role in the maintenance and modification of the

process that it describes. It is critical to demonstrate the physical sequence of equipment and systems,

as well as how these systems connect. Accordingly to the Institute of Instrumentation and Control, P&IDs

are diagrams that show the interconnection of process equipments and the instrumentation used to

control the process. They are a pictorial representation of key piping and instrument details, control and

shutdown schemes, safety and regulatory requirements and of basic start up and operational

information.

Summarizing all the design approach one may draw a flowchart that illustrates the sequence and

interconnection between the several steps described before (see annex B).

2.2.3. Operation and Maintenance

Pre-Commissioning

Before the green light to start normal operation, it is mandatory to perform some tests to verify

the pipeline reliability. Visual inspections should always be realized during pipe construction and

assembly. Alongside, some structural tests may be performed, as the acoustical test or x-ray are

examples of. The principal test comes when the pipeline is already installed, or at least a section of it. It

is called the “hydrostatic test”, used to confirm the integrity in terms of strength and leakages. Basically,

and in accordance with the norm ISO 13623 for onshore and with the norm DNV-OS-F101 for offshore

pipelines, the pipeline section is filled with water, which may be dyed to aid in visual leak detection, until

the specified test pressure is reached (usually 1.5 times the calculation pressure). Strength is usually

tested by measuring permanent deformation of the container, while a possible leak may be visually

identified.

After the conclusion of the hydrostatic test, special attention should be given to dewatering of the

pipeline system prior to filling it with carbon dioxide. The high solubility of water in dense phase CO2

may be beneficial as to ease the requirement to drying compared with streams of carbon dioxide in a

gaseous state. It should, however, be noted that in the initial stage of the first-fill, CO2 will always be in

gaseous phase. Due to the particular corrosion issues, pipeline should be dried to a dew point of -40 ºC

to -45ºC (at ambient pressure) before being ready to normal operation [59].

In many cases there is a considerable time delay between pre-commissioning and operation,

which might reach several weeks or even months. In these cases is important to conserve pipeline

integrity through preservation techniques, such as the filling with N2 or dry air.

Commissioning

This is an intermediate step before the start of normal operation. Here, the operator must assure

that the pipeline is filled with a fluid quality in accordance with requirements at the receiving end

(reservoir).

Before the initial filling, pipeline is as defined by the pre-commissioning, which means that special

attention might be needed in the case of a preservation substance was used. As the carbon dioxide

enters the pipeline it will mix with the substance already there. Experience shows that dense phase CO2

and N2 do not always mix well and therefore a PIG between the two media may be required [59]. This

Page 44: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

30

PIG, further than cleaning the pipe, should be used to perform a baseline inspection, determining the

condition and integrity of the pipeline. This inspection shall be used as reference for later inspections.

Integrity Management System

Management of a safe and reliable pipeline operation is greatly facilitated through the use of the

Integrity Management System (IMS). IMS outlines the capacity of an asset to perform its required

function effectively and efficiently whilst protecting health, safety and the environment. It is a tool to

ensure that, over the whole lifecycle of the project, integrity of the people, systems, processes, and

resources are in place. IMS is comprised of many elements and the terminology of them may differ in

different codes and standards. In addition, the operator must be aware about differences between

onshore and offshore pipelines that may exist in each element.

As idealized, and accordingly to the code DNV OS F-101 and DNV-RP-F116, the Integrity

Management Process (IMP) is considered the core of the IMS. It incorporates numerous elements and

activities that shall include, but not be limited to, risk assessment activities, integrity assessment

activities (as regular inspections) and response activities (interventions and monitoring, for example).

Complementing this process some additional considerations must be addressed, as the organisation

and personnel, contingency plans, audits, reviews and so on.

2.2.4. End-of-life

Re-qualification

A re-qualification of an abandoned pipeline system, once used for natural gas for example, is an

alternative way of implementing CCS. It contributes to a reduction of investment costs as much as the

network is prepared to directly face a change for carbon dioxide.

Re-qualified pipelines shall comply with the same requirements as the ones specifically designed

for carbon dioxide transportation. Any deviation identified shall be considered, evaluated from a

technical and costly point of view, and concluded whether it is acceptable or not. When analysing data

from concept, design, construction and operation of the existing pipeline, the deviations identified might

compromise and discourage the re-qualification.

One may outline all re-qualification steps based on [59]. First, a decision is taken to evaluate an

existing pipeline system – initiation. Secondly, there is need to address the technical integrity and

conditions of the pipeline system, through an integrity assessment. If everything goes well, the hydraulic

analysis comes next, where a flow assessment is performed to identify feasibility with reference to

transportation capacity and corresponding pressure and temperature distribution along the route. The

system as it is designed should be evaluated according to the specific safety requirement for CO2

pipelines, through a safety evaluation. Gathering the results from the hydraulic analysis and the safety

evaluation, the premises of the project are totally established. It follows the reassessment phase, where

a prognostic is made about the integrity and, if it is not acceptable, modifications needed are identified.

If these modifications are not costly or technically feasible, the re-qualification process is interrupted.

Otherwise, the modifications are studied, designed and all the re-qualified system is documented and

implemented.

Page 45: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

31

Abandonment

Closing the pipeline system lifecycle appears the abandonment stage. The pipeline might become

no longer useful for many reasons: depletion of the hydrocarbon reservoir, technological issues, financial

difficulties, public acceptance or even because of an incident during operation. In some cases, they

might be deactivated or taken out of service for shorts periods of time before they are abandoned [61].

In the case of carbon dioxide pipelines used for carbon capture and storage, there are two more reasons

that might be added: the deactivation of the source of CO2 or when the reservoir becomes completely

full.

Abandoning a pipeline network requires the accomplishment of several procedures:

1) The operator must develop an abandonment plan, with input from all the stakeholders: the

landowner, environmental or other technical experts and any others;

2) The operator makes a formal appliance to the Board/Government for permission to abandon

the pipeline;

3) Once the application is complete, a public hearing is held to decide whether the

abandonment would be in the public interest and whether the procedures proposed would

provide for adequate safety and protection of the environment.

The abandonment plan shall, thus, address key issues related to public and environmental

protection. These might include: pipeline and its equipment cleanliness and end of life; ground settling;

possible soil and groundwater contamination; water crossings; soil erosion; etc. Sometimes there is the

scenario where the simply abandonment is environmentally better than the dismantling of all the system.

Moreover, the cost of dismantling a pipeline might be quite significant and should be considered by the

stakeholders, in order to make responsible decisions.

2.2.5. Challenges

Reviewing all the previously exposed about pipelines transportation, there are several challenges

and obstacles to overcome. They must be explored to deploy Carbon Capture and Storage to a world

scale, on an efficient and sustainable way. The major challenge might be considered the maintenance

of a hazard-free industry. The concepts validation and public acceptance strongly depends on that. If

there is not an incident of major consequences as CCS is being implemented, more projects might

deserve a chance by the involved stakeholders. Accordingly to the experience already collected, the

main differences may be identified in the table 2.5 (next page), in terms of threats, between the normal

pipelines and the CO2 ones:

Page 46: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

32

Table 2.5 – Identified threats differences between general and carbon dioxide pipelines. Adapted from: [59]

Threat General pipelines CO2 pipelines

Tim

e

De

pe

nde

nt

External corrosion

Internal corrosion Depends

Stress corrosion cracking

Fatigue

Materials’ degradation

Manufacturing, welding and equipment defects

Tim

e

Ind

epe

nd

en

t

Manufacturing and welding defects

Incorrect operations

Weather/Outside force

Equipment failure

Stability

Repair/Welding issues

Shut-in

Blow down/depressurization

Investigating data records, shown in the figure 2.2, framing from 1986 to 2008, there were

registered the following incidents by category:

Figure 2.2 – CO2 pipeline incidents by cause and location from 1986 to 2008. (Data Source: CONCAWE)

There were registered, in average, 2 incidents per year or 0.36 per year per 1000 km, none of

them presenting serious consequences. Comparing to the 0.22 incidents per year per 1000 km shown

by the natural gas transmission network, one may conclude that it is already a good indicator, which

tends to diminish as experience and know-how increase. For hazardous liquids, this rate assumes the

value of 0.82, which expresses that carbon dioxide appears to have more in common with the natural

gas than with any hazardous substance.

Others challenges, if overtaken, might boost significantly the CCS deployment [58] such as:

The transfer of the US and Canadian experience into a global market;

The application of the technology offshore and the consequences of reduced access;

The transport of carbon dioxide from anthropogenic sources containing impurities and

hence the need to describe the behaviour of the carbon dioxide stream through

appropriate equations of state;

The higher population density found in other global locations including Europe and the

associated health and safety implications of on-land pipeline routing.

0

5

10

15

20

Number of Incidents Location of Failure

Page 47: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

33

2.3. Ships Transportation

2.3.1. Case Study 2 – LCO2 Carrier Ship

Offshore geological reservoirs to store captured carbon dioxide demand a transportation that

crosses the ocean from the shore to the site itself. As studied in the previous subchapter, pipeline

transportation seems to assume a major role in CO2 transportation for Carbon Capture and Storage

applications. However, for long distances and deep waters the piping solution becomes extremely

difficult and expensive to implement. Thus arises the carbon dioxide transportation by ship.

Only a few CCS reports were made covering this transportation alternative. Nevertheless,

commercial maritime transport of CO2 has been going on for many years, and many projects try to point

out that shipping may be a good alternative to pipeline transport under certain conditions. In the first

instance, use of ships provide flexibility in operation both with regard to the type and number of sources

as well as storage sites. Furthermore, ships also offer benefits due to short delivery time and potential

for reuse in other projects or even in non-CO2 transport. As result, they are well suited for demo CCS

projects [62]. Here, one decided to focus on the LCO2 carrier, projected by CHIYODA corporation and

the Global CCS Institute, reported on [63], and projected to operate in the Northern Sea Route (NSR).

Regarding carbon dioxide properties needed, it may be transported in two different options: in a

compressed or in a liquefied state, properly described in the next two paragraphs.

Compressed CO2 in ships may be directly compared to transportation in pipelines. For that

reason, transport conditions and consequential design premises are quite similar: the temperature will

be around 25ºC and the pressure above 75 bar, reducing the risk of two phase flow. Still, the inspection

procedures are much more aided in ships, comparing with underwater pipelines. However, this concept

remains unproven and without international regulations.

Liquefied CO2 has virtually the same properties as water: it is a colourless low viscosity fluid, with

density around 1.1 g/cm3, depending on temperature conditions. For commercial use (as food and

beverages, cleaning, chemical…), carbon dioxide is nowadays transported in the liquefied state, with

pressures between 15 and 18 bar and temperatures from -22ºC to -28ºC [62]. For CCS purpose, CO2

should be transported near the triple point, increasing the fluid density and the economic efficiency.

Transportation in marine environments might be needed, for some projects, just to complement

land transportation made through pipelines. Barges may also be used instead of ships for small

distances, as in the case of rivers and canals. A large number of them are in operation today, but not

for carbon dioxide transportation. This type of transport presents advantages in terms of investment and

operation costs, but are considered unsuited for offshore unloading operations.

In this section, according to the trends and applicability of the previous exposed, it will be

assessed the transportation of liquefied CO2 by ships, focused particularly from the liquefaction to the

unloading step. The injection will be further addressed in the chapter 3.

Page 48: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

34

2.3.2. Design Approach

Transportation by ship involves several infrastructures, each one with its own components and

regulations. A possible ship-based CCS chain is drawn in the figure 2.3. To complete the “marine cycle”

it is needed a liquefaction system, a ship carrier and an injection unit. This chain in particular was

idealized to have as much mobility as possible: liquefaction and injection units are easily transported to

serve a similar project in a different location.

Figure 2.3 – Configuration of a ship-based CCS chain. (Source: [64])

The ship docks near the barge to fill its tanks with the captured carbon dioxide. When the process

is finished, the ship has to do the voyage between the shore and the injection site and back. The cycle

of ship transportation is therefore discrete, whilst the carbon dioxide is continuously captured at the plant

on land. As result, this marine transportation chain shall include a tank after the liquefaction system,

used as a buffer for temporary storage.

Regarding barges and ships there is already a lot of information about regulations, design

specifications and operation procedures. Moreover, existing ships or barges may be adopted and

adapted to fulfil the necessities of a CCS project. Analysing in detail those infrastructures from the very

beginning of its construction ends up being redundant and falls outside of the scope of this thesis.

Tanks

Carbon dioxide tanks are designed based on the same premises as existing liquefied gas tanks.

Design methodology for LPG cargo tanks is well understood and is regulated by international standards

(specifically the "International Code for the Construction and Equipment of Ships Carrying Liquefied

Gases in Bulk”; IGC code) and Classification Societies (such as DNV, BV and LRS). There are three

types of tank structure for liquid gas transport [57]:

Pressure – designed to prevent the cargo gas from boiling under ambient air conditions;

Low-temperature – designed to operate at a sufficiently low temperature to keep cargo

as a liquid under atmospheric pressure;

Semi-refrigerated – designed taking into consideration combined conditions of

temperature and pressure necessary for cargo gas to be kept as a liquid.

Page 49: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

35

As seen, at atmospheric pressure, carbon dioxide might be in gas or in solid phase, depending

on the temperature. For standard temperature and pressure (STP) conditions, 0ºC and 1 bar, it is in the

gas phase (as may be seen in the carbon dioxide diagram – annex C). Decreasing temperature, keeping

the atmospheric pressure, is not sufficient by itself to liquefy the CO2. Instead, that combination directly

turns CO2 into the solid phase, known as “dry ice”. Liquefied CO2 only exists at pressures well above

the atmospheric.

The low-temperature tank type is not compatible with those characteristics, as carbon dioxide

would always be on a dry ice state. Between the pressure type and the semi-refrigerated, the last one

is the most preferred by ship designers. It has both pressure and temperature as variables, which allows

a more rigorous control and flexibility under different atmospheric conditions. For the semi-refrigerated

tank, the minimum operational point is around (-54ºC; 6 bar) to (-50ºC; 7 bar), which is near the triple

point, where fluid density is higher.

In the LCO2 carrier case, for optimisation proposes, operational point is established to be around

(-10ºC; 2.65 bar or 2.65 MPa). It is important to refer that the pressure of the tank rises during operation,

due to the ship’s motion and solar incidence, at an expected rate of 0.033 MPa per day of cruise.

Considering the Northern Sea Route, the maximum time distance that may be acceptable is around 3

days cruise duration. Hence, maximum working pressure will be around 2.8 MPa.

The tank for this kind of ship, in order to maximize transported volume and respecting all the

norms and specifications is designed in the figure 2.4:

Figure 2.4 – General characteristics of the LCO2 carrier. (Source: [63])

Tanks 2 Volume 1500 m3 each Design Pressure 3.10 MPa Radius of one cylinder 3.5 m Length 26.96 m

The material should be resistant enough to deal with extreme conditions that the tank will face.

Generally, the material selected is a quenched and tempered carbon steel, specific for low temperature

use. At the conditions of -10ºC, and according to the steel sheet JIS SHY685, it offers a tensile strength

of 795 N/mm2 and a yield strength of 685 N/mm2.

Page 50: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

36

Ships

Ship design and construction requires a large research, analysis and investment to leave the

design sheet and to become a reality. Characteristics specifications depend on the projects’

requirements, which vary from case to case. The ship is intended to have the particulars shown in the

figure 2.5:

Figure 2.5 – General arrangement plan and particulars of the LCO2 carrier. (Source: [63])

L 94.2m

L (pp) 89.6m

B (mould) 14.6m

D (mould) 6.9m

d (design) 5.6m

Side thruster 1150kW (2sets)

Azimuth Propeller 3000kW

Power Generator (Diesel) 3500kW (2sets)

Ship Service Speed 15.0 Knot

2.3.3. Operation Conditions

In carbon dioxide ship transportation there are many parts playing at the same time. In normal

operation conditions, it ends up being a repetitive cycle. It begins with the capture of carbon dioxide from

the flue gases, pursued by dehydration and compression for pipeline transport. Afterwards, the liquefied

unit turns the gas into liquid, storing it in the temporary tank. At this point starts the real ship

transportation cycle: as the ship docks, its tanks are filled and it is ready to go for the storage site. There,

carbon dioxide is injected to the geological reservoir and the ship comes back to shore, closing the

cycle.

The main part of operation begins in the loading and ends when the ship comes back to the port,

after injecting carbon dioxide in the offshore reservoir. Operation procedures are then essentially

constituted by 4 steps: loading, transport to the site, unloading and return to the port.

Loading refers to the procedure of filling the tanks with liquid carbon dioxide stored in buffers.

For that, there is necessity of pumps adapted for high pressures and low temperatures. As safety

procedure, cargo tanks are initially filled with gaseous CO2 to remove any residue of humid air and

prevent the possibility of dry-ice creation.

The transport operation to the site is not different from other transportations by ship. However,

there is one issue that shall be considered. As seen, tank pressure increases day-by-day due to the

heat transfer from the environment, which may boil the liquefied carbon dioxide. Gaseous CO2 may be

easily discharged together with exhaust gases of the ship’s engines. Doing so releases, of course, CO2

to the air, eliminating the zero emissions idea. This idea may be achieved through a capture and

refrigeration unit that captures the stream of boiled and exhausted gases, refrigerating and storing them

back in the tank.

Page 51: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

37

When the ship reaches the injection unit, it has to unload liquid CO2 from the tanks. Liquid CO2

must be replaced with dry gaseous CO2 to prevent contamination of humid air, being afterwards recycled

and liquefied when the tank is refilled.

Finally, the cargo returns to the port to do the next voyage. When the CO2 tanker is in the dock

for repair or inspection, or even to transport a different fluid in the next operation, gaseous carbon dioxide

existent in the tank should be purged1 with dry-air.

Those operations are rigorously planned and scheduled to assure a maximum efficiency. For

shorter distances, typically under 200 km, there is only necessity of 2 ships doing this cycle in a

desynchronized way. For larger distances more ships are needed to avoid an excessive accumulation

of captured carbon dioxide on temporary tanks. If 3 ships are considered, tasks may be distributed as

demonstrated in the figure 2.6:

Ship Day i Day (i+1) Day (i+2)

#1 loading transport unloading injection back (Repeat)

#2 injection back loading transport unloading

Ship Day i Day (i+1) Day (i+2)

#1 transport unloading injection back loading

#2 back loading transport unloading injection

#3 injection back loading transport unloading

Figure 2.6 – Possible schedule configuration and tasks distribution for a CCS ship transportation of 200 km (top) and 600 km (bottom).

2.3.4. Challenges

Many factors hold shipping carbon dioxide transportation deployment. They must be seen as

challenges to identify, study and overcome. Experience of other marine related industries should be

gathered and understood, avoiding start from scratch and jumping up to high standard levels. These

knowledge may be acquired through statistical data: incidents occurred by ship type and also the type

of incidents occurred. Accordingly to the data provided by [65], one may draw the figure 2.7:

Figure 2.7 – Incidents by type from 2005 to 2014. (Data from: [65])

1 Purify the tank through the elimination of impurities that may contaminate and modify the CO2

properties.

0 30 60 90 120 150 180

2005

2007

2009

2011

2013

Number of Incidents

Year

Foundered

Collision

Wrecked

Fire/Explosion

Machinery

Hull Damage

Miscellaneous

Contact

Page 52: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

38

In terms of incidents, the biggest percentages have to do with human fails, like collisions, sunk or

stranded ships. Similarly, fires and explosions should be taken into account due to the danger of tanks’

explosion. Oil tankers, particularly, may provide useful information and data about hydrocarbon

transportation, which has, as seen, quite similar requirements to carbon dioxide transportation.

Container ships might also contribute to the development of CO2 vessels, as they are much regulated

in terms of containers displacement and weight distributions along the ship. They had only 1 and 4

accidents, respectively, which might be a good indicator about the expected safety standards that CCS

ships will have.

Other challenges, besides the necessary shipping skill pointed out, may be identified:

Logistic models to improve the overall efficiency and results;

Constant modelling and monitoring of sea conditions to anticipate adverse conditions that

may result in serious dangers;

Tools to optimize new-built ship dimensions and properties or/and requalify existing ones;

Studies to improve the energy efficiency spent on the liquefaction and unloading units;

Investment in solutions that provide a larger flexibility and a larger range of uses, as the

barges are example of;

Constant parameters correction to optimize the whole process, as the buffer storage

capacity or CO2 purity requirements.

2.4. Comparative Analysis

The choice between transportation modes, when both are feasible, should be based on the results

and conclusions of an exhaustive comparative analysis. This analysis should address several

parameters, including costs, environmental consequences, existent regulatory framework, public

acceptance and so on. Stakeholders, particularly those that are going to invest money in the project, will

firstly look into the costs category. If the values differ significantly from ship to pipelines, for instance, it

is almost an impossible mission to convince them to prefer the most expensive solution in detriment of

the cheapest one. A comparative analysis should, therefore, begin with a costs comparison among the

several possible scenarios for each project.

Currently, there is a lack of data in this field for Carbon Capture and Storage projects, due to its

embryonic deployment. Besides, very few studies and reports were made to date focusing specifically

on the cost of CO2 transport in the context of CCS. Furthermore, even if ship transport is an obvious

complement or alternative to pipelines, few studies include this possibility. The most recent and

generally accepted study contemplating both transportation modes, foreseeing the post-demonstration

scenario, was made by [66] and is going to be reproduced in this subsequent section, followed by a

general pros and cons examination.

Costs

This study entails the three different transportation possibilities analysed before: onshore

pipelines, offshore pipelines and ship tanks. It will be not applied to a certain project or region but to a

general case. In that sense, different spine distances between the source and the sink are studied,

particularly: 180, 500, 750 and 1500 km. This was chosen to very roughly approximate non-trivial

Page 53: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

39

transport costs seen for onshore locations of 100 km or more (e.g. Compostilla, Spain; Porto Tolle, Italy;

east coast locations of the UK; and some onshore in Germany), though it is not specific to any one

location. For offshore locations, 180 km is an arbitrary distance but a starting point to analyse costs to

reach Dutch and UK southern North Sea locations and UK, Norwegian and Danish central North Sea

locations, although there is a considerable variation. The maximum distance, 1500 km, covers longer-

term access to the northern North Sea offshore storage locations via network solutions to CO2 transport

from continental Europe or the Baltic Sea states.

These distances are the “spine” of the transportation network, completed by feeders and

distribution parts, which are the connection by pipelines of the source to the spine and the connection

between the spine and the reservoir, respectively. These two small parts are common to all scenarios,

being its costs equal for each one. They are just necessary complements that should be added to the

diverse scenarios in order to get an accurate value of the costs and not only terms of comparison

between different cases. The project lifetime is assumed to be around 40 years, 1 for construction and

the rest in operation. The volume transported is typically of a post-demonstration project: 20 mega tons

per year. All scenarios were assessed in terms of investment (distributed over 12 years) and operational

expenditures, split in feeders, spine, distribution and network total costs. The final unit cost, the main

parameter of comparison, is therefore calculated in euros per ton of CO2 transported (€/ton). A

representation is in the figure 2.8 followed by the overall results shown in the table 2.6.

Figure 2.8 – Different networks composed by different spines: pipeline onshore, pipeline offshore and ship. (Adapted from:[66])

Page 54: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

40

Table 2.6 – Table of costs for the three networks, split into investment and operational expenditures. (Adapted from: [66])

Cost Item Feeders Distribution Onshore

Spine Offshore

Spine Ship

Spine

Total Network

1

Total Network

2

Total Network

3

180 k

m

CAPEX (M€) 30.12 152.15 287.14 423.78 642.04 469.41 606.14 824.31

Annuity (M€/y) 2.53 12.76 24.08 35.54 53.84 39.37 50.83 69.13

OPEX (M€/y) 0.12 9.51 1.08 7.90 143.62 10.71 17.53 153.25

Total Cost (M€/y) 2.65 22.27 25.16 43.44 197.46 50.18 68.36 222.38

Unit Cost (€/Ton CO2) 2.50 3.42 11.12

500 k

m

CAPEX (M€) 30.12 152.15 774.08 1035.41 756.35 956.35 1217.68 938.62

Annuity (M€/y) 2.53 12.76 64.91 86.83 63.43 80.20 102.12 78.72

OPEX (M€/y) 0.12 9.51 3.00 21.94 156.37 12.63 31.57 166.00

Total Cost (M€/y) 2.65 22.27 67.91 108.77 219.79 92.83 133.69 244.71

Unit Cost (€/Ton CO2) 4.64 6.68 12.24

750 k

m

CAPEX (M€) 30.12 152.15 1148.58 1522.08 868.99 278.59 1704.35 1051.26

Annuity (M€/y) 2.53 12.76 96.32 130.16 72.87 19.79 145.45 88.16

OPEX (M€/y) 0.12 9.51 4.50 32.91 167.10 110.45 42.54 176.73

Total Cost (M€/y) 2.65 22.27 100.82 163.07 239.97 125.74 187.99 264.89

Unit Cost (€/Ton CO2) 6.29 9.40 13.24

1500 k

m

CAPEX (M€) 30.12 152.15 2283.10 3501.10 1120.59 2465.37 3683.37 1302.86

Annuity (M€/y) 2.53 12.76 191.46 293.60 93.98 206.75 308.89 109.27

OPEX (M€/y) 0.12 9.51 9.00 65.82 203.71 18.63 75.45 213.34

Total Cost (M€/y) 2.65 22.27 200.46 359.42 297.70 225.38 384.34 322.62

Unit Cost (€/Ton CO2) 11.27 19.22 16.13

As expected, network unit cost accompanies the distance increase in all the cases. Between

transport cost of onshore and offshore pipelines, it may be concluded that offshore cost is always higher

than the onshore one. The choice whether to use onshore or offshore pipelines is mainly constrained

by the reservoir location. If it is offshore, obviously that offshore pipelines are the only possibility between

those two. For onshore reservoirs, and if in the route between the source and the sink is a river or a sea,

the two possibilities might be feasible. In that case, the study of the distances and the determination of

which solution seems to be the cheapest should be performed.

A more realistic comparison is the one between offshore pipelines and ships. For marine

environments, there is no other solutions practicably for now. Results reveal that for distances smaller

than 750 km, pipeline solution is by far the cheapest one, under the conditions assumed. However, at a

certain point, the investment needed in the construction of offshore pipelines counterbalances the larger

operational costs of ships. Breakeven point appears, thus, before the 1500 km spine distance, where

shipping becomes less expensive.

Page 55: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

41

Overall Pros and Cons

Besides cost, some other parameters should be part of the comparison and should be taken into

account, even representing a minor weight in the final decision. Some pros of each transportation mode

may be pointed in the table 2.7:

Table 2.7 – Overall comparison of the pros of both pipelines and ships.

Pipelines + Ships +

Low Opex Low Capex

Both onshore and offshore Large flexibility (volume and route)

Continuous flow Re-use potential

Less processes Public acceptance

No operational skill required Easy decommissioning

Less affected by environmental conditions High safety redundancy

2.5. Risk Analysis

Transportation of carbon dioxide has been successfully operated in the past decades, serving

several projects in different locations spread by Europe, United States and Canada. However, there is

not a perfect cause-effect notion about physical and chemical phenomena. Facilities as the es.CO2 is

example, are needed to scale up this technological system to an industrial size.

In this section one will develop an analysis of the drivers and risks perceived by the different

stakeholders involved in the transportation chain. As a final remark, some recommendations are drawn

to manage risks and reduce the knowledge gap in terms of regulation, which is currently incapacitating

the concretisation of several projects that are cancelled in the execution phase.

2.5.1. Drivers and Stakeholders

As there are general drivers for the overall CCS industry development, there are some specific

issues that may foster the transportation deployment in terms of technical knowledge and general

acceptance. These drivers must stimulate and be stimulated by the stakeholders, as pointed in the table

2.8:

Table 2.8 – Drivers and Stakeholders involved in the transportation process of a CCS project.

Drivers Stakeholders

Infrastructure re-use and requalification; Carbon dioxide sources administrators;

Financial underwriting companies;

The public;

Pipeline’s and Ship’s developers;

O&G companies;

Insurance companies;

Local and national regulators;

Climate regime administrators.

CO2 transport for second objective projects, such as Enhanced Oil Recovery;

Ship’s share between different stakeholders;

Regulatory stringency;

Technology development through economic or political

motives;

Involvement of insurance companies.

Page 56: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

42

2.5.2. Risks Identification

Assessing risks is a key-step to allow the sustainable deployment of transportation related

technologies. Risks differ according with the transport type, pipeline or ship, depending on several

characteristics that define each one. Dividing the risks by technical and regulatory/economic and splitting

between pipeline and ship transportation, one may build the table 2.9:

Table 2.9 - Systemic risks for the pipeline and ship transportation process.

Technical Risks Regulatory/Economic Risks

Pip

eli

nes

Integration/adaption of solutions takes time; Cyber-attacks, which might compromise the viability of

the project;

Innovation is limited for reused infrastructures; Territory occupation taxes may drive off the investors;

Monitoring activities are prone to cyber-attacks, which

might affect the transportation security;

Temptation to increase the flow rate, which may cause

accidents;

Dependence on monitoring techniques to assure

safety practices, especially in buried and in offshore

pipelines;

Strict regulations in the admission of new technology,

which might slow its adoption;

Extra-care needed when crossing populated areas or

the ocean; Increased costs from the terrain increased complexity;

Control and maintenance of deep-water systems

highly dependent on sensors and remote systems, still

less accurate;

Excessive CAPEX and public difficult acceptance

associated;

Sh

ips

Newly concept – almost no data available; Regulation on the ship’s sharing;

Requires more infrastructures to liquefy the carbon

dioxide;

Strict regulations in the admission of new technology,

which might slow its adoption

Contamination of the water; Excessive CAPEX and OPEX associated;

Dependent on weather conditions (waves, tides…) Business risk of investing in low maturity technologies;

Interaction with and damage of the meiofauna; Maritime taxes may drive off the investors;

2.5.3. Managing Risks and Recommendations

The basis of an effective risk assessment and management is to know what stills unknown. As

seen over this chapter, the knowledge that exists today of CO2 transportation is supported mainly by

empirical experience over the past decades on commercial activities involving CO2. Some direct

guidelines were withdrawn from the O&G sector, used to transport fluids through pipelines and ship

tankers.

However, transportation is still seen as a new technology and many questions remain to be

answered to decrease the uncertainties, regarding both pipelines and ships. This knowledge gap

includes the following categories:

o Storage necessities – greater knowledge of storage in tanks, such as buffers or ships;

Page 57: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

43

o Stream composition – study the behaviour and the effects of varying the purity of the

CO2 stream in different materials;

o Transient periods – understand the start-up and shut-down routines and other transient

periods;

o Negative impacts – confidence would be further enhanced by increased knowledge;

o Monitoring and instrumentation techniques – improve simulation, accuracy and cost-

effectiveness;

o Mitigation and remediation – lack of specific emergency plans for possible accidents,

as in the case of an explosion;

o Costs control – improve the knowledge of costs for the project and for the regulatory

compliance;

o Regulation and responsibility framework – clarify the role of each stakeholder and

project.

In an initial phase of CCS concepts, regulation becomes the ideal tool to properly manage risks.

The risks identified in the last section might require the development of an international regulatory

regime, ensuring, for every project, consistent monitoring and verification practices and accurate

reporting of global benefits and harms. This regulation should also provide specifications regarding

offshore transportation, where jurisdiction might not exist. Nevertheless, this regulation needs to be

flexible and adaptive, allowing an empirical learning. Guidelines for building an effective regulatory

system may be identified:

Scale of activity – transportation will be larger in scale than most currently covered under

legislation;

Monitoring and instrumentation practices – carbon dioxide demand specific control

necessities that should be clearly identified;

Specific risks management requirements – CO2 poses risks that are different from the

other fluids disposed in tanks or pipelines;

Uncertainties associated – regulation designed to manage transportation of carbon

dioxide should be adaptive and emphasize learning-by-doing;

Provide access to data and public input – the management of CO2 transportation must

be transparent, creating protocols between different entities and facilitating the access to

the results that may contribute to the development of other projects (as the Cubillos –

Compostilla is example of). Moreover, input from the public should be stimulated and

taken into account.

These regulations or recommended practices must be discussed and approved by the several

stakeholders that will affect or be affected during the lifetime of the project, ensuring a securely and

effectively manage of risks. Some other regulations, which are not directly linked with the project itself,

should be debated and implemented in order to motivate investment in this technological system. Taxes,

tradable permits or credits or financial programs are example of mechanisms that might be imposed by

the government of each interested country, stimulating a sustainable growth of CCS projects.

Page 58: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

44

3. Assessing Carbon Dioxide Storage Technologies

Carbon dioxide storage is the last step of the CCS chain. However, it is the proven evidence that

the last may not be the least. The reservoir choice is one of the major contributors for the viability of a

CCS project. If the location of the storage site is too far from the carbon dioxide source, or even if its

properties and characteristics turn the injection process too difficult, the whole project may be

compromised.

In this chapter, potential reservoirs and selection techniques are going to be identified, followed

by injection procedures and monitoring necessities. This topics are going to be addressed having as

starting point the case studies described below, regarding CO2 sequestration. The chapter ends with a

risk analysis, where some risks and recommendations are drawn.

3.1. Case Study Description

3.1.1. Case Study 3: Weyburn-Midale Enhanced Oil Recovery Project

Weyburn and Midale adjacent oil fields are operated by the Canada’s largest oil company:

EnCana. Weyburn field was discovered in 1954 with an estimated 1.4 billion barrels of original oil. In

1955 the production started and by 1963 was around 31500 barrels of oil per day. Starting in 1964,

water was pumped into injection wells in order to increase daily oil production. By 1966 production

reached 47200 barrels per day, declining steadily over the next 20 years until it dropped to 9400 barrels.

At that point, more vertical wells were drilled. In the 90’s horizontal wells came up and contributed to a

22000 barrels/day production. By 1998, roughly 330 million barrels of oil had been produced – about

23% of the oil in the reservoir [67]. Production was again declining rapidly. It was predicted that, unless

a new solution could be found to enhance oil recovery, total production would be no more than 350

million barrels – just 25% of the original oil in place.

In 1984, on the other side of the boarder (North Dakota; 320km distance), United States

government supported the building of the Great Plains Synfuels Plant. The goal of this facility was to

produce methane from coal, encouraging investment in alternative fuels, separating synthetic natural

gas from other compounds (mostly CO2). In 1997, Dakota Gasification Company, responsible for that

plant, agreed to send all the waste gas from the plant to Weyburn and Midale oil fields – through a

pipeline. In 2000 the CO2 transport infrastructure commenced its activity, daily transporting 8855 tons

of waste gas of which 96% is carbon dioxide. This level of purity is ideal for EOR purposes, as carbon

dioxide presents a higher dissolution when small impurities are present.

When CO2 supercritical fluid is pumped at high pressure into the reservoir, CO2 mixes with the

oil, causing it to swell and become less viscous. Swelling forces oil out of the pores in the rocks, so that

it can flow more easily. Water is pumped into the injection wells, alternating with CO2, to push the

released oil toward producer wells. Some of the injected CO2 at both Weyburn (6500 tons/day) and

Midale (2000 tons/day) is pumped back to the surface together with oil and water, then separated and

re-injected. At the end of the enhanced oil recovery period, it is expected that virtually all the injected

and recycled CO2 was permanently stored. It is predicted that the CO2 EOR operation enables an

Page 59: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

45

additional 220 million barrels of oil to be produced, extending the field’s commercial life by approximately

25 years. The whole evolution may be seen in the figure 3.1.

Figure 3.1 – Oil production over time and future predictions for the Weyburn and Midale fields.

(Source: [68])

The project had a total capital cost of 720 million dollars, 100 million of it being for the pipeline

construction. It is also anticipated that about 40 million tons of CO2 (30 in the Weyburn and 10 in the

Midale oil field) will be injected and become permanently stored 1500 m underground over the lifetime

of this project [69]. There is worldwide interest in this test of the viability of underground storage for

large-scale reduction in CO2 emissions to the atmosphere. The Weyburn CO2 Monitoring and Storage

Project is funded by several international energy companies, the U.S. and Canadian governments, and

the European Union. So far, no leaks have been detected and none of the gas has escaped to the

surface.

In order to further identify and assess the risks, it was made by the projectors a list of Features,

Events and Processes (FEPs), which together describe the geological storage system. Features are

physical characteristics of the system properties (porosity, permeability, wells…); events are discrete

occurrences that may affect the system (earthquakes, leaks, fractures…); and processes are physico-

chemical processes that influence the evolution of the system (fluid behaviour, corrosion evolution,

minerals precipitation…). Table 3.1 (next page) summarizes the FEPs list for this project:

Page 60: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

46

Table 3.1 – Examples of Features, Events and Processes (FEPs) for Weyburn-Midale CO2-EOR project. (Adapted from: [69])

SYSTEM FEPs

Rock Properties

Mechanical properties;

Mineralogy;

Organic matter composition;

Presence and nature of tectonic faults and fractures;

Cap rock integrity.

Hydrogeological Properties

Cross-formation flow;

Fluid characteristics of the rock;

Geometry and driving force of groundwater flow system;

Groundwater flow (including rate and direction);

Hydraulic pressure;

Hydrogeological properties of the rock;

Pore blockage;

Saline (or fresh) groundwater intrusion;

Transport pathways.

Chemical/Geochemical

Carbonation;

Colloid generation;

Borehole seal degradation (cement / concrete);

Dissolution of minerals/precipitates/organic matter;

Dissolution of CO2;

Dissolved organic material;

Groundwater chemistry;

Methanogenesis and microbial activity;

Mineral surface processes;

Precipitation and mineralisation properties;

Reactive gaseous contaminants;

Salinity gradient.

CO2 properties and transport

Advective flow and colloid transport;

Diffusion and dispersion;

Gas flow and source term distribution;

Thermodynamic state;

Abandoned Wells

Annular space;

Unsealed boreholes;

Corrosion of metal casing and its propagation;

Incomplete records of abandonment.

Geology

Local seismicity;

Temperature and thermal field;

Local uplift and subsidence.

Other Gases

Gas pressure (bulk gas);

Release and transport of impurities.

NON-SYSTEM FEPs (External)

Climate change;

Cross-formation flows;

Earthquakes;

Induced seismicity and fault activation;

Glaciation;

Mining and other underground activities;

Future monitoring;

Sea-level change;

Rock movements;

Future wells impact;

Page 61: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

47

3.1.2. Case Study 4: Statoil Carbon Storage Projects

Statoil is a Norwegian multinational leading company in the Oil and Gas sector, founded in 1972

and 2/3 leaded by the government. They are considered one of the most technological advanced

companies, particularly about Carbon Capture and Storage projects. Statoil understands carbon dioxide

capture as, in the near future, one of the most important and promising climate measures. They pretend

to be one step further by building a technology centre, composed by several projects. The objective is

to develop more cost-effective technologies for carbon capture from different sources. Using those

projects as the basis for that centre, Statoil intends to generate significant business from carbon dioxide

management, mainly focusing on the storage step.

They are involved in 4 major projects: Sleipner West (Norway); Snøhvit (Norway); Mongstad

(Norway) and In Salah (Algeria). Sleipner West and Snøhvit projects are currently in operation, while

the In Salah is in a dormant status and Mongstad was cancelled. Figure 3.2 illustrates the timeline

evolution of Statoil’s projects:

Figure 3.2 – Statoil’s CCS projects timeline evolution. (Adapted from: www.statoil.com)

In the In Salah project, carbon dioxide was captured from the extracted natural gas, for both

commercial and technical reasons. It started in 2004, storing below ground more than three million

tonnes of CO2. Due to preliminary conclusions regarding the reservoir properties (mainly related to

capacity), the injection of CO2 was reduced in mid-2010 and stopped in June of 2011 as a safety

measure. Newer well data and seismic results are now used to assess the current injection strategy.

The Mongstad was a two-phase project. First, in June 2007, it was constructed the CO2

Technology Centre Mongstad (TCM), involving a partnership between the Norwegian state, Statoil,

Shell, and Sasol. The goal of TCM was to gain enough knowledge to move for phase 2, where a full-

scale facility capable of capturing CO2 from both the combined heat and power station and other relevant

emission sources at the refinery was planned. In September 2013, after several delays due to the lack

of regulatory framework, the Norwegian Government received massive criticism concerning the project

management and cost-control of the project. Consequently, the government decided to cancel the large-

scale CCS project and to only move on with the TCM, making it in a leading arena for development,

Page 62: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

48

testing and qualification of CO2 capture technology, contributing to international dissemination, reduction

of costs and risks of full-scale projects.

Sleipner West

It is an offshore gas field proven in 1974 and located in the North Sea (240 km west of Stavanger,

Norway) at 2500 m depth. It is the second largest gas producer in the region, delivering gas to the

continent and to the United Kingdom. This natural gas contains a high percentage of carbon dioxide

and, because of that, Statoil build a special platform containing a treatment plant that separates the

excessive carbon dioxide – called Sleipner T (see figure 3.3).

In 1991 the government started to implement CO2 taxes for offshore oil and gas activities,

charging about $50 per ton of CO2 released into the atmosphere. Statoil decided therefore to implement

an injection facility, baptised Sleipner A, directly injecting carbon dioxide in a saline aquifer formation

located around 1000m below the seabed. This reservoir, called Utsira formation, has an expected

capacity of 600 billion tons CO2 – the equivalent to all human-made CO2 production for the next 20

years. Since 1996, the starting date of the project, there was captured and injected per annum one

million tonnes of carbon dioxide from natural gas production.

Statoil has been focused on sharing information and experience from Sleipner results, which led

the company to actively participate and advise on the regulatory framework concerning the storage of

carbon dioxide, both nationally and internationally. In addition to a number of international research

institutions, Norwegian institutions SINTEF and NTNU have been deeply involved. The subsurface

storage has been mapped in various research projects, some of which partly funded by EU. Seismic

surveys and other measurements show that storage and extent of CO2 underground are in line with the

plans established prior to injection. Several articles have been published based on data from Sleipner.

Figure 3.3 – Schematic representation of Sleipner CCS project. (Adapted from: www.steverichey.com)

Page 63: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

49

Snøhvit

A liquefied natural gas facility has been built at Melkøya, near Hammerfest in northern Norway.

At this LNG plant is used offshore gas taken from the Snøhvit oil and gas field (located at 145km from

the plant, 2500m deep below the seabed, 300 m of water depth), explored by Statoil company. This field

was developed with subsea installations, being the gas transported through a multiphase pipeline since

October 2007. It is the first major development on the Norwegian continental shelf with no surface

installations, designed to be over-trawlable so that neither they nor fishing equipment will suffer any

damage from coming into contact.

At the LNG plant the gas is liquefied by cooling it down to -163 degrees Celsius. This makes

possible its exportation by ship to Europe and USA. However, Snøhvit gas generally contains 5-6%

CO2, which freezes to solid matter (dry ice) at a higher temperature than natural gas. Therefore, it must

be removed before the gas is cooled into LNG. Moreover, CO2 also has to be separated from

hydrocarbons at a sufficiently early stage in the process, so that the gas mixture does not freeze and

block heat exchangers in the processing plant.

As such, Statoil decided to sequestrate that carbon dioxide in April 2008. A separate pipeline

transported CO2 back to the Snøhvit field, where it was stored in an appropriate geological layer of

porous sandstone, called the Tubåen formation, until 2011. Thenceforth, the storage was moved to the

original reservoir where natural gas was removed, called Stø formation.

A dedicated monitoring programme has been established to examine how carbon dioxide

behaves in the reservoir, partly financed by EU. The reservoir is monitored using 4D-seismic technology,

and no leakage has been detected.

A front-to-front of these two studied projects is presented in the table 3.2, showing that they are

very similar except in two categories of costs. Capture and transport is less costly in the Sleipner case

as it captures and injects in the same place, avoiding the transportation infrastructure. At the same time,

storage in the Snøhvit is more expensive, since the reservoir is two times deeper.

Table 3.2 – Comparison of Sleipner and Snøhvit cases. (Adapted from: [70])

Project Sleipner Snøhvit

Starting date 1996 2008 Location Offshore Offshore Storage type Deep Saline Aquifer Deep Saline Aquifer CO2 injection rate (Mt CO2 yr-1) 1 0.7 Pipeline length (km) 0 145 Initial number of wells 1 1 Capital Investment Costs (M€)

Capture and Transport 79 143 Compression and Dehydration 79 70 Pipeline - 73 Drilling and well completion 15 25 Storage 15 48 Facilities Not available 12 Other Not available 11

Total capital investment costs (M€) 94 191

Page 64: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

50

3.2. Reservoirs

Selection Criteria

In the case study 3 described, the storage reservoir was not a variable of the project as it was

considered as an Enhanced Oil Recovery project. Thus, the reservoir had to be the one where Oil/Gas

exploration was occurring. The selection criteria, in this cases, is only used to understand the possibility

and viability of injecting and storing carbon dioxide in that formation and location, without considering

any other possibilities.

When the project starts from the very beginning and the storage reservoir is not constrained,

different types of storage reservoirs, related with its location or geological characteristics, may be

considered. Selecting whether it is suitable to store carbon dioxide involves numerous and complex

steps, which might be split in four levels:

1st level: tectonic setting; basin size; depth; hydrodynamic and geothermal regimes; on/offshore;

accessibility; existing petroleum and coal resources; industry maturity [71].

2nd level: distance from CO2 source; seal capacity; trap type; storage capacity; injectivity;

existing natural resources [72].

3rd level: structural and stratigraphic model; engineering characterisation (simulations, process

plan, monitoring plan); socio-economic characterisation (economics; risk and uncertainty

evaluation) [73].

4th level: deployment (proved capacity, monitoring, economics, injection, regulations) [73].

The figure 3.4 summarizes these steps, on a pyramidal overview. As one moves up the pyramid,

through an increase of data collected and effort, the uncertainty decreases as well as the effective

storage volume (initial forecast is generally majored):

Figure 3.4 - Steps to follow to choose a suitable storage location. (Source: [74])

Page 65: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

51

Potential Reservoirs

Currently, considered storage options for CO2 in geological media, which respect all the

necessary conditions broken down by the described criteria, are: deep saline formations; depleted or in

depletion oil and gas fields; unmineable coal seams and even the ocean. Those reservoirs may be

classified as valued or non-value added sites:

Non-value added sites: developed only for CO2 storage such as the case study 1 and 4,

like depleted oil and gas reservoirs, the ocean and deep saline formations;

Value added sites: as in case studies 3, developed primarily for enhanced recovery of

fossil fuel fluids and storage of CO2 as a secondary benefit, such as sites for enhanced

oil recovery (EOR), enhanced gas recovery (EGR) and enhanced coalbed methane

recovery (ECBM).

Deep Saline Formations

Carbon dioxide is an ideal candidate for aquifer storage because of its high density and high

solubility in water at the relatively high pressures which exist in deeper aquifers [69]. They are located

several kilometres below the surface, containing water that is considered unusable due to its excessive

content of salt and minerals. They could host large amounts of CO2 trapped by the formation pressure

(cap rock), representing the largest potential storage capacity in the long term. However, currently they

are less well understood and global capacity estimates vary significantly due to different assumptions

made by different entities about the volume of the reservoir already filled with other fluids, CO2 density

under the reservoir conditions and the maximum allowable volume. It ranges from 87 to 14000 Gt of

carbon [69], which corresponds to 326 to 52500 Gt of carbon dioxide.

Depleted Oil and Gas Reservoirs

An obvious and proven answer for the storage problem is the use of O&G reservoirs that are no

longer in use. If the reservoir stored the hydrocarbon for so long, it is able as well to store carbon dioxide

in the future. There are several advantages in this reusing strategy: trapping mechanisms and reservoir

properties are well known and some of the existing infrastructure used in the oil extraction may be

employed. Even so, reservoirs that have had a large number of extraction wells might not be

appropriated, since they increase substantially leakage pathways for CO2.

There are differences between a reuse of an oil and a gas reservoir. An abandoned oil reservoir

has generally large quantities of residual oil remaining in it. As such, it is very unlikely that stakeholders

approve a usage of the reservoir as a storage facility unless some oil recovery strategy may be

implemented. At this point, there is need to further assess some legal questions regarding the ownership

of these residual hydrocarbons. In the case of a depleted gas reservoir up to 90% of the original content

has been removed, in normal cases. The reason for this much higher extraction rate is the fuel’s higher

compressibility and lower viscosity, compared to oil. As so, the reservoir can genuinely be considered

as depleted and the stakeholders do not create difficulties for CO2 storage. Estimated global storage of

oil fields is 150Gt CO2 (40Gt C), while the depleted gas reservoirs may represent 520Gt CO2 (140Gt C).

Page 66: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

52

In Depletion Oil and Gas Reservoirs

In active oil and gas fields that are reaching the end of their productivity, carbon dioxide may be

used to increase hydrocarbon quantities recovered from the porous rocks, as scrutinised in the case

studies described in this chapter. Injected CO2 increases the pressure of the cap, pushing the stored

hydrocarbon towards the production wells, enhancing the recovery of a significant amount of it. In the

case of the oil, oil-carbon dioxide mixture is separated at the surface and the oil is used as fuel in the

normal way. This carbon dioxide may be re-injected or injected in deep aquifers.

This process, called Enhanced Oil/Gas Recovery (EOR/EGR), can be very attractive since the

cost of CCS may be offset. The use of CO2 can recover up to 12% of remaining fuels, which has a huge

economic impact. As the depleted/inactive oil and gas reservoirs, these sites are more likely to be used

for early projects as extensive information from geological and hydrodynamic assessments is already

available. However, other methods will become more viable as technology is being developed. Globally,

the EOR has an estimated capacity of 20 to 65Gt C. The EGR has not yet an estimate and is still being

tested, as the pressure needed to recover the remaining gas is higher (as explained above).

Unmineable Coal Seams

Another possible storage medium is the unmineable coal, which is the coal that cannot be

extracted due to its location conditions. In this cases, carbon dioxide may be injected into suitable coal

seams, where it will be adsorbed onto the coal, locking it up permanently. In this process, methane that

was not extracted by normal depressurisation techniques (around 50%), may be recovered (ECBM).

Moreover, coal can adsorb about twice as much CO2 by volume as methane, so even if recovered

methane is burned and the resulting CO2 is injected, the coal bed can still provide net storage. A nearly

pure stream of carbon dioxide is not required for this storage process, as residual gases are not

adsorbed and will came out together with methane. The estimate, on a global level, for this type of

reservoir yields a potential of 82 to 263 Gt C.

Ocean

This type of storage is almost completely disruptive compared with the ones previously exposed.

It is evidently offshore, while the previous ones described may be either onshore or offshore. It is simply

related with the different densities of salted water and carbon dioxide. Ocean storage may be done in

two ways: by injecting and dissolving carbon dioxide into the water column below 1000 meters or by

depositing carbon dioxide onto the sea floor at depths below 3000 meters, where CO2 is denser than

water and is expected to form a lake that would delay its dissolution into the surrounding environment.

In both cases, it may be done through a pipeline or a ship + platform.

Clearly, an ocean carbon sequestration program will be successful only if its intended benefits (a

stabilization of atmospheric CO2 and mitigation of climate warming consequences for terrestrial and

shallow water ocean systems) outweigh its liabilities (energy expended on sequestration and damage

to deep-sea ecosystems). Presently, there is a lack of sufficient information to perform this balance.

An interesting study has been performed by the Monterey Bay Aquarium Research Institute,

entitled “Effects of Direct Ocean CO2 Injection on Deep-Sea Meiofauna” [28]. The results, observed by

a Remotely Operated Vehicle (ROV), clearly illustrate the necessity of a knowledge improvement about

Page 67: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

53

different variables before this process may become a reality. Figure 3.5 on the left shows the progressive

vector of the flow at depths below 3600m, concluding that the CO2 plume will disperse in several

directions (even though the mean flow goes to southeast. On the right it is represented the pH variation

detected by the ROV sensor, explained by the dissolution (lowering the pH of the water) and the currents

(bringing new water with a neutral pH):

Figure 3.5 – Effects of Direct Ocean CO2 Injection on Deep-Sea Meiofauna. On the left, the progressive

vector diagram illustrating flow, from the left to the right. A black circle notes the start of each day. On the right, the pH perturbations during the CO2 depletion. (Source: [28])

Trapping Mechanisms

At the storage site, carbon dioxide is injected under pressure into the geological formation. It must

be injected at depths below 0.8 km, as CO2 increases in density with depth and becomes a supercritical

fluid below that depth. Supercritical fluids, as seen, take up much less space and diffuse better than

either gases or ordinary liquids through the tiny pore spaces in storage rocks. At this conditions, the CO2

is less dense than the existing water in the reservoir. Therefore, it rises upwards due to the buoyancy

force where there is a necessity of a trapping mechanism that retains the injected carbon dioxide in the

subsurface.

Four main ways are identified as the main trapping mechanisms in which dense carbon dioxide

may be trapped at depths below 800 m: structural/stratigraphic; residual; solubility or mineral:

Structural/Stratigraphic – it is the first mechanism preventing the migration of the carbon dioxide.

As the injected CO2 rises up through the porous rocks, it becomes trapped when it finds the top of the

formation constituted by an impermeable layer of cap rock. Structural traps are found mainly due to

anticlines or faults, while stratigraphic traps exist due to unconformities or changes in the rock type,

being practically the same traps that kept oil and natural gas securely trapped for millions of years. In

deep aquifers generally there is no cap rock that sustains the carbon dioxide efficiently. It is expected

to migrate under the force of buoyancy, taking a pathway determined by the complex plumbing of the

sedimentary basin. According to [69], only a few deep aquifers will leak significantly over human time

scales (hundreds of years).

Page 68: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

54

Residual – As the injected carbon dioxide moves up through the geological storage site towards

the cap rock, some of it is left behind in microscopic pore spaces of the rock. Some reservoir rocks have

the capacity to behave like a sponge, holding the liquid carbon dioxide (droplets) in its pore spaces,

avoiding carbon dioxide migration even under high pressure.

Solubility – This phase of the trapping process involves the dissolution of carbon dioxide in

existing water in the porous rock. This water containing CO2 will become denser than the surrounding

fluids and will sink to the bottom of the rock formation, decreasing leakage risk.

Mineral – As the dissolution of carbon dioxide occurs in water, it forms a weak carbonic acid. Over

the time, this acid can react with surrounding minerals and form solid carbonate minerals, as a coating

on the rock. This trapping mechanism effectively binds the CO2 to the rock.

As the storage mechanisms change over time from structural to residual, dissolution and then

mineral storage, carbon dioxide becomes less and less mobile. Therefore the longer carbon dioxide is

stored the lower the risk of any leakage, as shown in the figure 3.6:

Figure 3.6 – Trapping contributions from different mechanisms and security increase over the time for CO2

injection. (Source: [4])

Page 69: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

55

3.3. Injection Well

The injection process requires advanced technology to ensure a safe and efficient injection of

large quantities of carbon dioxide into the subsurface. Many of the technology was already developed

and used on the O&G sector. Furthermore, and as already pointed out, Enhanced Oil Recovery has

been made in some cases injecting carbon dioxide. As so, the concepts of drilling, injection, stimulations

and completions for CO2 injection wells are already studied and practised.

Design Approach

An injection well is a device that pumps the fluid deep underground, where the reservoir is located.

A scheme of a CO2 injection well and wellhead is shown in the figure 3.7. An injection well is commonly

equipped with two valves: one for regular use and another reserved for safety shutoff. It is recommend

to use a third valve, called downhole safety valve, which is responsible for automatically shut down the

well, preventing a backflow scenario. A downhole configuration includes a double-grip packer and an

on-off tool. Downhole components for CO2 are better prepared to handle higher pressures and higher

corrosion than the ones used to inject natural gas for the same purpose – EOR.

Figure 3.7 – Typical CO2 injection well and wellhead configuration. (Source: [70])

Recent technology implemented in the O&G sector, which removes the oil by a horizontally well

may be exponentially explored by the CCS projects, as it already happened in the case study 4. It

increases storage capacity and the maximum injection rate of a certain reservoir, as it creates an

injection profile that reduces adverse effects of high-permeability zones.

The number of wells depend on several factors: injection rate; formation properties (porosity;

thickness…); maximum injection pressures and availability of land-surface free area to drill new injection

wells. An injection with fewer wells is preferable as the possible migration/leakage paths is reduced.

Generally, the number of needed wells increases with low-permeability sediments, thin storage

formations and if they are vertical wells. Overall cost of the injection process depends greatly of the

Page 70: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

56

wells number design optimization. Fewer wells does not directly imply a reduction of costs, as the

technology needed may be more expensive.

Operation Conditions

In order to inject carbon dioxide into the storage formation, the downhole injection pressure needs

to be higher than the reservoir fluid pressure. Otherwise, the fluid existent in the reservoir will push

carbon dioxide and will cause the backflow scenario. However, increasing pressure may induce

fractures in the formation, which may destroy the reservoir and promote several leaks. Regulatory

agencies normally limit the maximum downhole pressure, taking into account the measurements of the

formation stresses and pore fluid pressures.

Abandonment

Abandonment procedures should be carried out to prevent contamination of the surrounding

environment. The well must be closed or otherwise carbon dioxide may migrate up the well and into

shallow drinking waters, for example. These procedures generally require placing cement or mechanical

plugs in all or part of the well, as it happens in the O&G industry. Extra care has to be taken to use

sealing plugs and cement that are resistant to the carbon dioxide.

The cement plug will act as the main barrier to future CO2 migration. A major issue is related to

the sealing quality of the cement plug and the bonding quality with the penetrated cap rock, as shown

in the figure 3.8. Micro-channels created near the wellbore during drilling or milling operations should

be sealed with cement. Fluid could also be flushed into the storage reservoir to displace the CO2 and

help to improve the cementing quality and bonding to the sealing cap rock. Casing protective materials

and alternative casing materials, such as composites, should also be evaluated for possible and

alternative abandonment procedures. Sealing performance of abandoned wells may need to be

monitored for some time after storage operations are completed [70].

Figure 3.8 – Possible leakage pathways in an abandoned well: a) and b) between casing and cement wall

and plug, respectively; c) through cement plugs; d) through casing; e) through cement wall; f) between cement wall

and rock. (Source: [75])

Page 71: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

57

Challenges

Technical challenges that still to be discussed and researched are mainly related to long-term

effects. Knowledge of injection and storage processes was cloned from the Oil&Gas sector, which has

been doing similar activities in the past decades. As shown in figure 3.9, injection rates in the order of

magnitude of a 500MW coal power plant storage necessities had been already reached and greatly

overpassed by Enhanced Oil Recovery projects. It is proved, thus, that storage of carbon dioxide is

feasible with the existing technology. Advancements on the technology and knowledge of the processes

will afford a more sustainable and faster growth.

Figure 3.9 – Injection rates of different projects compared with the CO2 emissions of a 500MW coal power

plant. (Data from: [76])

Weyburn EOR project has the same injection rate needed for a 500MW coal power plant. For that

reason, direct comparisons and conclusions may be withdrawn from there for that kind of projects. The

case study 4, regarding the Sleipner and Snøhvit projects, have not an injection rate much below the

one needed for a 500MW coal power plant, which reinforces the importance of those projects developed

by the Norwegian company Statoil.

3.4. Measurement, Monitoring and Verification

Monitoring activities should follow all the storage phases: pre-operation; operation; closure and

post-closure. The confidence of a safely injected and stored carbon dioxide can be achieved by using

Measurement, Monitoring and Verification (MMV) technologies. Further than that, it also provides

verification to both numerical modelling and performance assessment and the necessary accounting

metrics for emissions trading scenarios based on geological storage, which assumes primordial

importance in the development phase of CCS projects.

The project should be assessed by a monitoring program on three different domains: subsurface;

near-surface and atmospheric. The phenomena that may cause some perturbations for those domains

are related with:

0

5000

10000

15000

20000

25000

Inje

ctio

n R

ate

(to

nn

es/d

ay)

EOR

Storage

500MW Coal Power Plant

Page 72: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

58

Migration – referring to the movement of fluids (as the injected CO2) within the injection formation.

This may involve vertically or horizontally movement in the designated subsurface domain.

Leakage – referring also to the movement of fluids but outside of the formation/reservoir, in the

near-surface domain. This phenomena is especially important to control since that a leakage of CO2

may contaminate the biosphere.

Seepage – referring to the movement of fluids from the geosphere to the biosphere, acting on the

near-surface and atmospheric domain.

There are a number of key steps involved in the design of a systematic approach to successfully

plan monitoring programs [69]: defining project conditions; predicting mechanisms that control

behaviour; answering technical questions; selecting parameters to be measured and identifying their

role in technical questions; determining the magnitude of expected change in parameters; selecting

instrumentation and monitoring approaches/systems; selecting instrument or monitoring locations;

determining timeframes and the depth for monitoring.

Monitoring Technologies

Monitoring technologies for CCS projects, as it happened with the transportation of carbon

dioxide, learned a lot from the O&G sector. Many of the techniques were adapted for site

characterisation, where the data obtained is used to understand the viability of the reservoir in terms of

characteristics, challenges and risks. Other new techniques are being studied to improve the knowledge

about carbon dioxide storage state.

Monitoring the reservoir involves: seismic imaging and downhole pressure/temperature

measurements; gravimetry, electromagnetics and other. For leakage monitoring onshore, surface or

atmospheric techniques such as eddy covariance, open path lasers, soil gas flux and concentration

measurements can be deployed. Leakage into the marine environment can be detected and measured

using seabed and water-column acoustic imaging and sampling, water geochemistry, benthic chambers,

and ROV observation of seabed fauna. These technologies are represented in the figure 3.10 and may

be rearranged in three categories: geophysical, geochemical and environmental. [26], [69]

Geophysical – This field uses seismic, electromagnetic, gravity, micro-seismic and displacement

sensors and petro physical measurements. The migration path of carbon dioxide may be known by the

surface seismic monitoring. It maps the CO2 plume, through the comparison between the initial surveys

carried out before the injection and the surveys repeated during and after the injection. Micro-seismic

surveys are mostly used to monitor the possible reactivation of fractures or other seismic faults due to

the vibration released during the injection process.

Geochemical – Example of this techniques are geochemical analysis of fluids, gases, rocks, soil,

ground and surface water and even of the atmosphere. It is possible to tag the CO2 stream, through

chemical tracers, in order to verify the plume behaviour. High quality fluid and gas samples, through a

monitoring well, may be collected at several depths and afterwards chemically and isotopically tested in

order to detect if there is any carbon dioxide presence.

Environmental – This techniques include atmospheric gas detection/dispersion modelling and

soil analysis. These measurements are collected by atmospheric stations, as a CO2 flux tower is

example of, or by analysing the soil in several locations of the project area.

Page 73: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

59

Figure 3.10 – Different monitoring techniques and their application range. (Source: www.ccsbrowser.com)

3.5. Risk Analysis

Storage of carbon dioxide is not a newly concept, it has been successfully used in the last 30

years in small applications. At a commercial/industrial scale, storage deployment started in the Canada

and in Norway twenty years ago. Drivers were different for the two cases, the first aimed enhance the

recovery rate of the oil reserves and the second project intended to mitigate the impact of emission

taxes and separate excessive content of CO2 in the gas. However, there are still difficulties and

unknowns to be overcome regarding technological, economical and public acceptance about the carbon

dioxide sequestration.

In this section, as in the chapter 2, one will develop an analysis of drivers and risks perceived by

the different stakeholders associated with this CCS step. As a final remark, some recommendations are

drawn to manage risks and reduce the knowledge gap that is currently incapacitating the concretisation

of several projects that are cancelled in the execution phase.

3.5.1. Drivers and Stakeholders

Behind the common drivers for the overall CCS industry development, there are some specific

issues that may foster the storage evolution in terms of technical knowledge and general acceptance.

These drivers must stimulate and be stimulated by the stakeholders, as pointed in the table 3.3:

Table 3.3 – Drivers and Stakeholders involved in the storage process of a CCS project.

Drivers Stakeholders

CO2 storage as second objective, such as Enhanced Oil

Recovery projects;

Carbon dioxide sources administrators;

Financial underwriting companies;

The public;

Geological storage sites developers;

O&G companies;

Insurance companies;

Local and national regulators;

Climate regime administrators.

Infrastructure re-use, like platforms and wells;

Regulatory stringency;

Technology development through economic or political

motives

Involvement of insurance companies, covering damages

caused by leakages, for example.

Page 74: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

60

3.5.2. Risks Identification

Assessing risks is a key-step to allow the sustainable deployment of the storage related

technologies, as it is for the transportation. Risks differ according with the storage mechanism and

formation, they depend on several characteristics that define each one. Dividing the risks by technical

and regulatory/economic, as made in the last chapter, and splitting between onshore/offshore and ocean

storage, one may build the table 3.4:

Table 3.4 – Systemic risks for the onshore, offshore and ocean storage process.

Technical Regulatory/Economic

On

sh

ore

/Off

sh

ore

Integration/adaption of solutions takes time – delays of

Oil&Gas production;

Cyber-attacks, which might compromise the viability of

the project;

Innovation is limited for reused infrastructures; Sequestration taxes may drive off the investors;

Relocation of platforms is rare and difficult; Temptation to increase the recovery rate, which may

cause accidents;

Monitoring activities are prone to cyber-attacks, which

might affect the storage security;

Project development and investment highly dependent

on O&G prices

Water/ground contamination on the vicinities of the

injection well/reservoir;

Strict regulations in the admission of new technology,

which might slow its adoption

Dependence on monitoring techniques, as there are

no other methods; Excessive CAPEX and OPEX (offshore) associated;

Induced seismic events; Increased costs from the increased complexity;

Control/maintenance of deep-water systems highly

dependent on sensors/remote systems, which are still

less accurate;

Oc

ea

n

Newly concept – almost no data available; Public acceptance is more difficult;

Requires remotely operated vehicles for monitoring

operations;

Strict regulations in the admission of new technology,

which might slow its adoption

Increased difficulties to simulate in laboratory; Excessive CAPEX associated;

Control and maintenance of deep-water systems

highly dependent on sensors and remote systems, still

less accurate;

Business risk of investing in low maturity technologies;

Contamination of the water and interaction with the

meiofauna; Sequestration taxes may drive off the investors;

Dependent on weather conditions (waves, tides…)

Page 75: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

61

3.5.3. Managing Risks and Recommendations

The basis of an effective risk assessment and management is to know what stills unknown. As

seen over this chapter, knowledge that exists today of CO2 injection and storage is supported mainly in

earth sciences, O&G experience over the past decades and on commercial activities involving CO2 in

the last 30 years. However, carbon dioxide injection and storage is still seen as a new technology and

many questions remain to be answered to decrease uncertainties. This knowledge gap comprises the

following categories:

o Storage mechanisms – greater knowledge of geochemical trapping, adsorption and

desorption and their long-term impacts;

o Storage capacity – need of more development on assessment methodologies;

o Negative impacts – confidence would be further enhanced by increased knowledge;

o Monitoring and verification techniques – improve accuracy and cost-effectiveness;

o Mitigation and remediation – lack of emergency plans for possible accidents, as in the

case of a carbon dioxide leakage;

o Costs control – improve the knowledge of costs for non-EOR projects and for the

regulatory compliance;

o Regulation and responsibility framework – clarify the role of each stakeholder and

project.

The ideal tool to properly manage risks, in an initial phase of CCS concepts, is through regulation.

The risks identified in the last section may require the development of an international regulatory regime,

ensuring, for every project, consistent monitoring and verification practices and accurate reporting of

global benefits and harms. This regulation should also provide specifications regarding the injection and

storage in the oceans and beneath the seabed, where jurisdiction might not exist. Nevertheless, this

regulation needs to be flexible and adaptive, allowing an empirical learning.

Guidelines for building an effective regulatory system may be identified based on [69]:

Scale of activity – storage and injection processes will be larger in scale than most

currently covered under legislation;

Monitoring and verification practices – not all existing regulations require monitoring

and verification of the stored carbon dioxide;

Specific risks management requirements – CO2 poses risks that are different from the

other fluids disposed underground;

Uncertainties associated – regulation designed to manage injection and storage of

carbon dioxide should be adaptive and emphasize learning-by-doing;

Provide access to data – the management of CO2 storage must be transparent, creating

protocols between different entities and facilitating the access to the results that may

contribute to the development of other projects (as the Hontomín – Compostilla is

example of);

Enable public input – information about the project should be made available to the

public and input from the public should be facilitated and taken into account.

Page 76: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

62

4. Discussion and Summary

4.1. Summary

The extraction and combustion of world’s rich resources of oil, coal and natural gas at current or

even increasing rates, releasing more of the stored carbon into the atmosphere, is no longer

environmentally acceptable. Hence, Carbon dioxide Capture and Storage technologies currently being

developed must be widely deployed. Therefore, the main purpose of this thesis until here was to identify,

assess and understand the technological evolution, such as design, construction and operation

requirements of carbon dioxide transportation and storage.

In the introductory chapter 1, the world distribution of relevant projects of CCS was identified and

categorized into actives, completed, hold, terminated or potential projects. Worldwide, there are

currently 145 projects, of which 63 actives, 6 completed, 22 holding, 38 already terminated and 16

potential projects. The main conclusion withdrawn from that distribution was the embryonic contribution

that they make in global terms against the endless number of carbon dioxide sources, which turns

difficult any kind of foresight regarding the future role of CCS technologies. Nevertheless, the trend is

positive and in the past decade, as illustrated in the figure 4.1, the investment and the projects are

growing in a sustainable way.

Figure 4.1 – Evolution of the number of CCS projects, investment and carbon managed. (Data from: [77])

It was discussed also the difference between a technological system, which is a set of radical and

incremental cross-linked innovations, and the technology itself. Together, they define and are defined

by the so called technological trajectories, shaped by a range of social, institutional, economic and

environmental situations. In this scope, three main technological trajectories were presented regarding

the CCS implementation in thermal power plants:

Continuity – change totally for renewable energy, reinforcing the investment and

improving efficiency results;

Intermediary – continue fossil fuels consumption but capturing carbon dioxide, mitigating

climacteric issues. In parallel, invest must be given as well to the renewables;

0

10

20

30

40

50

60

70

80

90

Cumulative Projects

Cumulative Investment (€)*10^-9

Cumulative Carbon Managed (Tonnes/Day)*10^-4

Page 77: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

63

Disruptive – radical innovations in the electricity generation such as portable power

stations, transmitting electrical power through subsea cables over long distances.

These technological trajectories show the possible influence that CCS projects may have in re-

shaping other related industries, as the technology improves and new concepts are explored. For that,

dissemination of the required knowledge about Carbon Capture and Storage has a long way to go, to

leave from a utopic idea to a changing concepts reality. Accordingly to a Social Perception Study,

performed by “Fundación Ciudad de la Energía” (CIUDEN), the public sensitivity when asked if Carbon

Capture and Storage may contribute to mitigate the climate change is shown in the graphic of figure 4.2:

Figure 4.2 – Public perception of CCS contribution to mitigate the climate change. (Source: CIUDEN)

The people inquired were randomly selected, without receiving any information (left) about

Carbon Capture and Storage technological system. Thus, one may conclude that 83% of the population

does not think that CCS will perform an important role in a climate change mitigation strategy. However,

the lack of knowledge about this theme may be observed in the graphic on the right, where information

was given to the people inquired and the question was made again. The number of people agreeing

that CCS may be the solution for climate change control increased more than four times.

An immediate conclusion is, thus, that general public opinion and acceptance strongly depends

on the knowledge that they have about Carbon Capture and Storage. It is a good indicator, as they

immediately trust in this system soon after receiving information about it. However, it shows also the

lack of knowledge that is still present about this reality – which is a strong barrier to CCS deployment.

Afterwards, still in the first chapter, it was explained the methodology to be used throughout the

thesis, strongly based on a case study analysis, broaden the view of the technology application and

deepening the overall understanding of what is being studied. The methodology was influenced also by

a combination of risk analysis and flexibility in engineering design, based on a robust Risk Governance

Framework (IRGC), allowing the identification of drivers, stakeholders, challenges, risks and benefits.

The second chapter was dedicated exclusively to carbon dioxide transportation: either by pipeline

or ship. After the description of the transportation network, where the connection between the source

No opinion;

38%

Not the solution;

16%

Agree; 17%

Disagree; 28%

No opinion;

18%

Agree; 75%

Disagree; 7%

No information After information

Page 78: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

64

and reservoir is projected and optimized, both transportation modes are singularly explained through a

case study research for each one:

Case Study 1 – Technology Development Plant es.CO2: description of the Spanish

experimental facility of Carbon Capture and Storage, involving the transportation of

carbon dioxide using pipelines.

Case Study 2 – LCO2 Carrier Ship: ship specially conceived for CO2 transportation, in

a liquefied state.

A general comparative analyses is also made, comparing the various costs of each transportation

mode for four different distances. Finally, in the last section, are addressed drivers, stakeholders, risks

and recommendations.

Carbon Dioxide Storage is considered in the chapter 3, where reservoirs, injection wells and

monitoring technologies are deeply analysed. This analysis is made using two more case studies of

CCS projects:

Case Study 3 – Weyburn-Midale Enhanced Oil Recovery Project: example of a

successfully Enhanced Oil Recovery project, where carbon dioxide was not stored as

primer objective.

Case Study 4 – Statoil Carbon Storage Projects: deep study of the Statoil’s

contribution for CCS development, mainly due environmental requirements established

by the Norwegian government and policy makers.

As in chapter 2, in the last section of that chapter are addressed drivers, stakeholders, risks and

recommendations.

In this final chapter, chapter 4, the knowledge gained from the analysis done in the previous

chapters and summarized above must be gathered and integrated in the global scenario of a constant

change in energy demand and sources, called “Energy Transitions Era”. Considering past events,

unknowns and growing uncertainty in the global economy, one will identify the technological paths that

CCS industry may follow and how they can influence and be influenced by possible energetic scenarios

and industrial policies.

A recurring theme in this thesis is change: in scenarios, contexts, technological systems and

technologies. This dynamic evolution create many opportunities to be exploited. As so, and as said in

the chapter 1, this thesis is performed under the scope of the International Observatory of Global Policies

(OIPG), particularly linked to the +atlantic project. This thesis share, therefore, the project’s objective:

an international agenda aimed to promote the scientific, technological and industrial capacity of Portugal

towards the sustainable exploration of the Atlantic, taking advantage of the many opportunities arising

internationally: the new oil and gas discoveries in Portuguese speaking countries; the extension of the

Portuguese continental shelf; and the shift in paradigm towards subsea exploration.

Page 79: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

65

4.2. Technological Challenges Overview

Carbon Capture and Storage technological system has yet a lot of challenges to face and

overcome. A good indicator of these amount of barriers, which might delay the implementation of this

technological system is the current development status, maturity of the technologies and related

industries. After the analysis made to the different case studies, both in chapter 3 and 4, one may now

really understand the highest state of the art founded on the several components that make part of the

CCS chain, pointed in the table 4.3. There are four possible development phases: research,

demonstration, economically feasible under specific conditions and mature.

Table 4.1 – Highest maturity level observed for each CCS component and specific technology. (Adapted from: [4])

CCS Component CCS Technology

Rese

arc

h P

ha

se

Dem

on

str

ati

on

Ph

as

e

Eco

no

mic

ally

Feasib

le

Matu

re

Capture

Post-Combustion

Pre-Combustion

Oxy-Fuel

Transportation Pipeline

Shipping

Geological Storage

Enhanced Oil Recovery

Oil/Gas Fields

Saline Formations

Enhanced Coal Bed Methane Recovery

Ocean Storage Dissolution Type

Lake Type

Industrial Uses of CO2

Transportation of carbon dioxide, as discussed in the chapter 3, achieved high standard levels

even though some phenomena regarding the properties of the fluid are not still fully understood. The

case study 3 and 4 show that a learn-by-doing mentality is perhaps the strongest way to build knowledge

and experience in pipeline transportation. In these cases, it was used overdesigned equipment and a

fail control strategy. Regarding shipping transportation, this mentality is less adopted due to difficulties

in monitoring and fail control procedures.

The storage knowledge was extremely leveraged by the Oil & Gas expertise, research and

experience in the past decades. Enhanced Oil Recovery enabled not only the improvement of the

extraction coefficient of the reservoir but also the indirect development of carbon dioxide sequestration

techniques and technologies.

Page 80: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

66

4.3. Risks in the CCS Industry

Gathering both analysis regarding transportation and storage, one may now establish a more

generalist risk analysis involving the whole CCS industry and evaluating global benefits and risks of this

technology. This analysis follows once more the IRGC methodology and takes into account the major

concerns of the industry, experts and academics.

This is an essential part of the technological system development in order to gather vital

information to overcome, analyse, govern and manage all the possible events, creating some knowledge

on the uncertainty, permitting from the very beginning a flexible design approach.

4.3.1. Benefits, Drivers and Stakeholders

Supported by a flexible but solid design approach, potential benefits from CCS were identified by

R&D agendas and experts’ foresights:

Fossil fuels consumption in a carbon constrained world;

Reduction of harmful emissions;

Non-disruptive transition to low-carbon energy systems;

Industry’s usage of the captured carbon dioxide;

Oil and Gas extra recovery from depleting reservoirs;

Economic competitiveness and prosperity;

Reduction of the Capital Expenditure (CAPEX) and the Operational Expenditure (OPEX);

Attract new players and so more investments;

Enhance the competitiveness of a country’s manufacturing sector, especially subsectors;

Energy security;

Create direct and indirect employment;

Provide a basis for new industries and development of existing ones;

Promote a development of R&D agendas in other industries (by using a majority of the

state of the art technology);

Development of the scientific community by creating relations and partnerships between

industries and academia, in order to further develop new technologies and better

frameworks and methodologies.

Page 81: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

67

Drivers that have the capability to foster CCS development and implementation on a certain

country are identified in the table 4.1, driven by different stakeholders. These benefits and drivers are

just some examples of results pointed on several agendas for the technological and industrial

development that can result from an investment in new ways and different techniques to create bases

for a solid development and solution of existent problems [20].

Table 4.2 – Drivers and Stakeholders involved in the storage process of a CCS project.

Drivers Stakeholders

Climate policy; Public in general;

CO2 emissions generators;

CO2 pipelines/vessels operators;

Geological storage site developers;

Local and national entities;

Climate regime administrators;

Insurance companies;

Financial underwriting companies.

Energy infrastructure;

CO2 regulatory stringency;

Projects’ location;

Subsurface property rights.

4.3.2. Risks Identification

Some risks are inherent to CCS development and implementation. It is a new technology, which

requires an additional effort to understand and detect possible future scenarios and risks. Identifying

them in three categories, as exposed in the table 4.2:

Table 4.3 – Systemic risks associated with CCS technological system.

Risks

Technical Regulatory/Economic

Carb

on

Cap

ture

an

d S

tora

ge

Monitoring activities are prone to cyber-attacks, which might affect the storage

security;

Cyber-attacks, which might compromise the

viability of the project;

Degradation of local air quality and water resources;

Subsea property owners;

Civil disruptions or Natural catastrophes; Strict regulations on the admission of

new technology and safety guidelines;

Damage for the human health and

ecosystems; New regulations and goals set for the emission of harming elements;

Water/ground contamination on the vicinities

of the injection well/reservoir; Community stress and economic instability;

Capture, Transport or Storage leakages; Slowing the rate of investment in more sustainable energy systems;

Dependence on monitoring techniques, as there are no other methods;

Economy indirect changes;

Control/maintenance of deep-water systems

highly dependent on sensors/remote

systems, which are still less accurate.

Financial viability.

Page 82: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

68

4.3.3. Managing Risks and Recommendations

If stakeholders want to prevent risks, or at least want to control them, enabling a sustainable

growth, the most important aspect to have into account is the necessity of setting a constant high level

of research and development. This thought allows a positive contribute to different other sectors and a

strong preparation for the many coming challenges. Some useful recommendations to prevent and

manage risks may be drawn:

Establish a framework encouraging responsible operation and investment;

Balance stability and predictability with flexibility and adaptability to scientific information;

Development based on solid technical findings and develop a diverse portfolio of projects;

Provide ease of implementation for both regulators and industry, operating transparently;

Provide scientific and technical answers to key regulatory and legal concerns;

Employ harmonised monitoring, measurement and verification standards to enable cross-

comparison of technologies and be subject to comparative assessment.

Results made available to the public and allow public engagement and education;

Development of generalised site selection guidelines and GHG accounting protocols;

Improvement and standardisation of modelling techniques;

Development of necessary modifications to existing regulations;

Negotiation of specialised arrangements for long-term liabilities at a number of early sites;

Creation of financial policies to expand exploration to different locations;

A regulatory system to effectively govern the new changes in production, including

necessary permitting fees to support required regulatory activities, should be established,

with meticulous attention to the principles of sound science, data quality, transparency and

opportunity for local community and stakeholder participation;

Baseline conditions of some critical metrics should be measured and monitored to detect

any adverse changes resulting from development;

Since effective risk management at sites is feasible, companies should adhere to it;

Practices and strive to develop a strong safety culture, which includes sustained

commitment to worker safety, community health and environmental protection.

The ideal tool to manage the risks is a risk profile where one can see the evolution path and

identify the critical periods, as demonstrated in the figure 4.3:

Figure 4.3 – Leakage risk profile associated with the injection of carbon dioxide. (Source: [78])

Page 83: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

69

4.4. Achievements Timeline

A technological system generally follows a trajectory path which may be split into three phases: I

– research; II – demonstration and III – commercialization. It begins in the research phase, where

concepts and components are studied and tested. After, it enters in the demonstration phase where

bigger investments are made to demonstrate the viability of real projects, pointing to a reduction of costs

and a maturation of technology. Finally, the technological system is considered as being in the

commercialization phase, being widely implemented and successfully operating.

Carbon Capture and Storage is following this type of trajectory, being actually in the

demonstration phase after several years of research and development leveraged by the O&G industry.

The main events that fostered CCS deployment in the past years are identified next and the

correspondent graphic of its evolution may be found in the figure 4.4 (next page). There, it is observed

three knowledge trajectories corresponding each one to the phases described, following the “S-Curve”

learning model. The first is split into two, representing the mentality shift, after the 2000’s, of the

exclusive Enhanced Oil Recovery purpose of CCS projects.

Ph

as

e I

1970 Use of CO2 for commercial EOR projects

1989 CCS technologies program at MIT

1991 Norwegian government imposed CO2 emissions taxes

Sleipner project plan

1996 Sleipner operation started

1997 Dakota Gasification Company agreed to send CO2 to Weyburn

1998 Weyburn plan

2000 Injection began at Weyburn

2001 RECOPOL project

UNFCC invited IPCC to prepare a special report about CCS

2003 Formation of the Carbon Sequestration Leadership Forum

2004 In Salah Project operation started

2005 Formation of CCSA in UK

Norwegian collaboration with UK

CCS integrated into the Chinese Natural Development Plan

2006 Coach Project (collaboration between China and EU)

2007 Cooperation agreement between Australia and China

Ph

as

e II

2008 Carbon Assessment Software developed by MIT

Clear-coal debut project in Germany

Post-Combustion project in China

Snhovit project started

2009 Formation of the Global CCS Institute

2012 Mongstad project in Algeria

Page 84: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

70

Figure 4.4 – Qualitative evolution of the CCS industry, split into three phases: Research, Demonstration and Commercialization.

1970 1990 2000 2008 2015

Europe End of EOR mentality

1970 – 2008 PHASE I – Research Appearance of the first EOR projects using Carbon Dioxide. Research programs founded and encouraged by the emission taxes imposed by the Norwegian government. A mentality shift occurred in the new century, where CCS started to be seen as a mitigation strategy, supported by international organizations.

Time

CC

S K

now

led

ge

Norway Government imposed CO2 emission taxes.

Norway, Sleipner Start of the offshore platform project

2008 – 2020 PHASE II - Demonstration

Huge formation of research and development centres of CCS technologies,

where O&G companies invested part of their profits. Several agreements

between different countries were achieved. Due to the barrel price drop, the

investment in CCS was partially slowed down, but the objectives are still the

reduction of overall costs and unknowns.

Germany and China Debut projects Norway Snhovit offshore project

2020+ PHASE III – Commercialization Deployment of CCS industry, mitigating carbon dioxide impacts, investing also in renewable energy. More and bigger projects, affecting a wider range of CO2 sources.

Worldwide Formation of the

Global CCS Institute

Canada, Weyburn Start of the project, including 320km of pipeline transportation

Worldwide IPCC special report

Worldwide Collaboration between Norway and UK, China and EU, China and Australia

Norway Mongstad project

Worldwide Formation of the Clean Energy programme

Spain CIUDEN formation

Worldwide Transport of CO2 for commercial purposes.

United States

Sharon Ridge project, the

first EOR project using

CO2, capturing 1.3 million

tonnes annually.

United States CCS technologies program started at MIT

2020

Page 85: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

71

4.5. Scenario Building for the CCS Industry

Carbon Capture and Storage knowledge and projects are strongly linked with the balance

between the Oil & Gas sector prosperity and environmental friendly systems and concerns. Hence, it is

of an extreme importance to project the future role, positioning and necessities that CCS industry may

assume, merging it with varied range of scenarios that may arise in the Oil & Gas sector, turning it as

much flexible as possible.

Few areas of economy are as volatile and dynamic as the oil and gas sector. The multiplicity of

factors that influence the directions of the petroleum production chain is huge, making the task of

preparing strategies and action plans a great challenge. Technological advances, supply and demand,

prices, business models, sustainability, demographic change, armed conflicts and geopolitical disputes;

these are just some of the variables that are likely to be on the horizon, year after year. And how does

one map the changes the market will hold for its actors over a more distant future, in a segment with

high production costs and long-term returns and in which long-term planning is essential? There is no

crystal ball for such a complex panorama. But there are scenarios: sets of hypotheses that, rather than

predicting the future, describe a range of possibilities. They are projections prepared based on data that,

studied today, can enable companies to make better decisions. The scenarios emphasize descriptions

of the external environment (instead of focusing on the internal context of companies). They employ

narrative techniques that instigate consideration of unexpected situations and challenge common sense,

but always maintaining plausibility. And, when well developed, they offer a guide that allows managers

to recognize the changes that are coming and prepare for them in advance. [79]

Accordingly to the Vision for 2040 [79], studied by Delloite, future base scenarios of the O&G

depend mainly on two variables/drivers: global political-economic environment and energy source

competitiveness. As so, one may draw the figure 4.5, illustrating energetic scenarios and their relative

position when different combination of those variables is assumed:

Figure 4.5 – Future plausible scenarios for the O&G industry. (Adapted from: [79])

Energy Source Competitiveness

Ge

op

oli

tica

l

Sta

biliz

ati

on

Ordered Growth

Conflictive Growth

Grey Green

Dominance of

Fossil Sources

Green

Globalization

Hegemony of

Traditional Oil Producers Decline of Oil

Page 86: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

72

Scenario 1: Green Globalization

In this scenario, relative geopolitical stability favours economic growth and trade cooperation

between countries. With high demand, new alternative sources of energy, finally economically viable,

would add to the supply of conventional fuels. It is a scenario in which ordered growth in the geopolitical

axis and a green future in the axis of competitiveness between energy sources predominate.

The investment in the CCS industry, taking this scenario, is encouraged by the green requirement

of energy sources. As so, if the O&G industry want a share in the global energy matrix, they must

develop systems that change the intrinsic grey character of their fuels. And for that Carbon Capture and

Storage, as seen, is very well placed.

Scenario 2: Decline of Oil

Here, we would see a decline in the importance of oil in the global energy matrix. It would be a

world in which alternative energy sources would gain impetus, with a lower demand for oil due to lower

economic growth, combined with technological innovations and advances in alternative sources. The

preponderance on the geopolitical axis would be at the conflictive stagnation end, maintaining the green

hypothesis on the competitiveness of energy sources axis.

Once more, CCS implementation may be fostered by environmental requirements of energy

sources. Nevertheless, the demand of oil will suffer an implacable cut if the O&G industry doesn’t move

to a greener and fashionable level, which may stimulate the oil producers to adopt carbon mitigation

measures. However, if policies and regulations are not adopted there is the risk of a huge deceleration

in investments which may bring down the chances of CCS.

Scenario 3: Hegemony of traditional producers

Politically, this scenario is similar to that of number 2: political tensions in several corners of the

world would not decline and emerging countries would continue to stagnate, which would contribute to

a fall in global energy demand. The difference would be that the countries that today dominate the oil

and gas market would continue to exercise power, with oil firm and strong in the global energy matrix. It

would be a scenario in which the hypothesis of conflictive stagnation would combine with the grey

competitiveness of energy sources.

Hegemony of traditional oil producers allied with geopolitical confusion will not contribute to the

development of regulatory requirements in the energy world, thus not encouraging new investments in

technology development. Focus will be in a cheaper production, without carrying about environmental

problems.

Scenario 4: Dominance of fossil fuels

In the fourth scenario, the geopolitical axis would again tend toward ordered growth, with

competitiveness of energy sources leaning toward the grey end. Alternative energy vectors would not

be established as viable options and natural gas would not be commercialized through a global market.

With this, sources of fossil origin would multiply, which would combine with conventional oil and gas

exploration to supply growing demand from the emerging economies.

Page 87: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

73

As the world would be dominated by fossil fuels, investment in CCS systems will be only possible

if governments take advantage of the geopolitical stabilization and launch together environmental

requirements to make this sources cleaner and less dangerous to the environment. Here, Enhanced Oil

Recovery projects may be often used for competitiveness purposes between the players, enhancing as

well the investment in CCS systems.

These identified and described scenarios are merely particular developments which may arise

from the actual conjuncture in the O&G industry. However, taking into consideration the present context

of growing global uncertainty in an energy transition era, no scenario may be determinant by itself. The

future of the energy sector might find a mix of two or more of these situations, where no specific scenario

will materialize itself completely and where uncertainty and systemic risks will play an ever growing role.

Actual Panorama

In order to better realize what the future might reserve, is essential to clearly understand where

is located the present energetic panorama in the referential shown in figure 4.5. In the horizontal axis,

energy source competitiveness, we are leaning to the left: grey energy sources. In the next years, it

seems that fossil fuels will continue to meet most of the world demand, particularly natural gas. Due to

improved efficiencies of the technology, such as cars, demand of oil will not grow exponentially anymore.

Instead, demand will stabilize or grow slowly, forcing moderation of the supply and levelling off the

growth of US shale oil. Alternatives that avoid oil consumption, such as electric cars, are becoming a

reality as initial investments become less expensive. However, current oil crisis puts some pressure on

renewable energy sources, which become less competitive as the oil price goes down.

The falling price of the oil barrel is explained from tensions between the Organization of Petroleum

Exporting Countries (OPEC) and the US. OPEC is keeping high production levels in spite of the reduced

demand. The objective is to maintain the oil price in lower levels, which drives the US shale-oil boom to

a halt, since the production cost of it is much higher than the production cost of the most oriental

countries. Thus, in the geopolitical situation measured in the vertical axis we are closer to the conflictive

situation (bottom).

Balancing the two axis, one may see that nowadays we are moving towards the scenario 3 – a

hegemony of oil producers. Conflictive geopolitical situation moves the attention of the governments

from environmental problems to the economical field. In short term, they are more concerned about the

economic viability of the country thus decelerating the investment in renewables or in systems that

mitigate impact of the fossil fuels.

Matching with CCS

Based on the case studies elaborated along this thesis, one may conclude that technologies such

as Carbon Capture and Storage would benefit much more of an ordered growth, where there is space

and time to discuss and implement regulation. It was the case, for example, of Norway or EOR projects

(refer to case study 3 and 4).

Regarding the competitiveness between energy sources, the answer is not so easy. Dominance

of fossil sources (scenario 4) widens the opportunities to apply carbon mitigation technologies: there are

more producers and they may adopt those systems if stimulated by national/international regulation or

Page 88: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

74

even for EOR purposes. It happened in the case study 3 and 4, where investments were made to

withdraw bigger quantities of oil from the reservoir or to avoid emission taxes.

On the other hand, if energy sources get greener (scenario 1), it means that the oil will lose a big

part of its share, thus losing capacity to invest in technology development. Moreover, the mentality and

the regulation in this panorama will be much tighter in environmental terms. Consequently, the traditional

oil producers that resist to this agitation will be forced to adopt procedures to mitigate the ecological

footprint.

One may create the figure 4.6, illustrating the interconnection, differences and possible bridges

between the different scenarios from the one that we are living now (scenario 3), relatively identifying

the possible importance of CCS for each one. Case studies are positioned in the most similar scenario

where they were developed, in a specie of micro-panorama conditions.

Figure 4.6 – CCS importance and case studies positioning in emergent scenarios of the Oil&Gas industry.

Case study 1 and 2 represent the overall current status of CCS development: demonstration

phase and pilot tests. In times of hegemony of traditional oil producers, as described by scenario 3, only

casual projects are going to arise, generally financed by the government. As it happened in this case

study, in the most cases these demonstration projects end without tangible results.

In the scenario 2, the demand of oil is very scarce and investments made by this sector will not

occur. Because of that, and observing that no case-study fits here, this scenario is perhaps the worst

for the CCS deployment.

Scenario 4 Scenario 1

Scenario 3 Scenario 2

Greener Sources

Ord

ere

d G

row

th a

nd

CC

S im

po

rta

nce

Path 2

Path 4

Path

3

Path

5

Case Study 4

Case Study 3

Case Study 1 Case Study 2

Page 89: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

75

Case study 3, and the most part of the EOR projects, is located in conditions similar to scenario

4. The dominance of fossil fuel sources reinforces the competition amongst the producers, which

incentives them to increase the oil extraction rates, thus indirectly investing in CCS. Furthermore,

through the right policies, such as the ones observed in the case study 4, CCS may become an

obligation, walking towards a sustainable globalization but where the O&G doesn’t lose importance or

market share.

Case study 4 is the upmost sustainable scenario and where grey industries have to adopt CCS,

thus giving to it a significant importance. The Norwegian government imposed carbon dioxide taxes,

moving the Oil&Gas sector towards a greener thinking, investing in Carbon Capture and Storage

research and taking advantage of it (EOR).

The best scenario for the CCS deployment may be, thus, a mix between a world of green

globalization and dominance of fossil fuels. It is needed a sustainable mentality to achieve carbon

mitigation measures and procedures, but it is essential to have revenue from the O&G sector to develop

those technologies.

One may describe, in the table 4.4, the strategy to foster the mentality’s shift from one scenario

to another, following the paths identified in the figure. Evidently that this shift is very hard to make, as it

relies on a huge number of variables that may be out of the control of the governments and industries.

Table 4.4 – Strategies plans to change global scenarios, following the paths identified in the figure 4.6.

Path Strategy

1 Impose strictly regulation, encouraging the investment in greener energy sources and reducing dependence on fossil fuels. This cannot be made without stimulating global cooperation between countries and economies.

2

Impose the same regulation than in path 1, but without considering the ordered growth and conflict between entities and countries. This will change the mentality regarding energy sources, but it will not allow the global share of knowledge and resources, which may decline the demand of oil.

3 If international collaboration between economies and industries is stimulated, fossil fuels will dominate as much as they dominate nowadays, but with reinforced strongholds. More producers may arise and competitiveness may healthfully grow.

4 After achieving scenario 4, scenario 1 may be reached through regulation and investment towards greener energy sources, such as renewables.

5 With the decline of oil presented after the path 2, scenario 1 may be found with stronger and viable relations between countries holding different resources regarding the energy market. A green globalization, where different economies play different strategic roles, may thus arise.

4.5.1. Energy Transitions: Risks and Challenges

Dynamism and challenges of the macro-economic environment is always increasing without any

apparent signs of easing. Risk management has been used to rapidly evolve tools to control and prepare

the present and the future. There is a much larger interconnectivity between the different risks and

nowadays companies are starting to handle risk management discipline as an enabler of sustainable

growth and innovation. As so, risk management capabilities must be prioritized and focused on the

things that matter for the organization.

Legal, Emerging, Business, Regulatory and Operational risks are, according to [80], the top five

risks expected to dominate the energy sector in the next years. The first ones refer to the cost and loss

of income caused by legal uncertainty, such as regulatory actions, disputes for or against the company

Page 90: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

76

or a failure to meet obligations. Emerging risks include uncertain, systemic and unexpected impacts

related to advancing science and technological innovation. Risks related to the possibility of inadequate

profits or even losses due to uncertainties, e.g. changes in consumption patterns or increased

competition, are contained in the business category. Regulatory risks are connected to restrictions,

licenses and laws applied by the government. Finally, operational risks are the ones resulting from

losses due to inadequate internal processes, people and systems or even from external events.

Even split and grouped into five categories, executives and boards may become lost in the risk

handling process, deeming the problem too large to be effectively managed. Hence, it is extremely

important to have solid frameworks, as the one proposed by the IRGC and used in this thesis, to provide

guidance in handling the risks even in situations of high complexity, uncertainty or ambiguity. In this way

is possible for the stakeholders to make a methodical approach, separating the credible and realistic

risks from the less relevant for their assets, even though recognizing that is not possible to anticipate or

prepare every conceivable risk.

Role of Industrial Policies

As seen, a technological trajectory is shaped by several external factors, ranging from social and

institutional to economic and environmental. The institutional part is particularly relevant due to its

transversal impact in the other categories, facilitating or restraining the use of new technologies such as

CCS. Hence, the role of the industrial policy and how it should be adapted to an uncertain and dynamic

period must be taken into consideration.

There is a great diversity of opinions regarding the role that industrial policies should perform.

The most adverse argument is that it is mainly created and developed by the strongest industries and

companies, thus distorting competition and exposing governments to their interests. However, this

argument is becoming out of context, as the international competition gained new silhouettes to

efficiently readapt to this era of energy transitions, characterized by extremely rapid innovations and

consequently falling prices, where knowledge and education is considered as a productive asset. In this

scenario, government interventions in the market may play a bigger and more positive role, facilitating

generation and spread of knowledge to all stakeholders.

In this context, the right industrial policy has to create and maintain strategic collaboration and

coordination between private and public sectors, enhancing the flow of information from the market to

the government, allowing it to take the most appropriate interventions [81]. The government has to adopt

a position of facilitator and coordinator in the knowledge generation, not being the driver as it was in

traditional industrial policies. Furthermore, the state should not adopt a policy where the firms are pre-

selected to be funded for knowledge investments. Instead, it should leave to the market forces to

naturally determine those firms. In short, the government should intervene in the market to facilitate risk

sharing and to establish relations among private entrepreneurs on different stages of the value chain

[82].

Taking the cases studies into the discussion, one may observe that Norwegian government was

the only one positively playing and encouraging CCS development. Thinking in environmental

improvements, it created a sustainable policy to reduce carbon emissions of oil related industries.

Further than requirements, the government provided solutions to achieve that goal. It created research

Page 91: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

77

poles based on universities, strengthening the relation industry-university and industry-science. It

implemented a learn-by-doing mentality, leaving room to the gradual acquire of knowledge and results.

As it happened in the Compostilla Project (Spain), the government said no to the project’s kick-off due

to the lack of regulation. Regulation can only be effectively made when there is sufficient knowledge

and experience, which is not the case about Carbon Capture and Storage. When this happens,

governments prefer to say no to prevent any possible incident, which is a comprehensible position.

However, this will not allow the development and deployment of the technology, holding it in a permanent

“demonstration phase”.

Engineering Contribution

Value-added engineering may very positively contribute to handle not only the growing

uncertainty but also the regulation issues described above. Essentially, engineering can reduce barriers

and deliver a good quality product/system doing the following:

Cost reductions through process optimization: focusing on efficiency improvements,

addressing product quality needs and eliminating redundancies. The overall goal of

process optimization is to reduce the cost of production, operation and maintenance;

Revenue generation through debottlenecking: identifying where revenue stream is being

constrained by improper or less than optimal designs;

Strategic site planning: engineers can develop plans for retrofit applications and new

builds, thus minimizing the cost of contribution and ongoing maintenance;

Pre-engineering to achieve flexibility design: stakeholders need to take careful steps to

cut capital expenditures and operating costs in the actual panorama, but always with an

eye toward the investment return in the future.

By considering these value-added strategies, engineering firms are well positioned to provide

these services with better efficiency, streamlining and cost-saving innovations. Now is the time to work

more effectively to extract maximum productivity from existing facilities by building value, maintaining

flexibility and improving efficiency [83].

The problem here with CCS is that is not modelled to be a revenue generation system. Its

utilization brings costs and not revenues, even though it can avoid emission taxes with larger weight.

Thus, the problem is a little upside-down but the principles are the same. It is of extremely importance

to achieve flexible and sustainable halts to be prepared for different scenarios that may result from the

combination of industrial policies and inevitable uncertainty.

4.6. Opportunities for Portugal

The panorama of the Portuguese industry is very scarce compared with the necessities of the

Oil&Gas industry. Whereas the lack of resources in Portugal did not motivate investment in this sector,

the small dimension of the economy hinder as well the ability to invest in a capital intensive industry as

the O&G is.

There is now, however, an opportunity for Portugal to enlarge and gain importance in this sector.

This opportunity results from several factors that are contributing for the increasing importance that this

Page 92: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

78

peripheral country may represent. The extension of the continental shelf, the predicted development of

the South Atlantic, mainly related with the exploration and production of hydrocarbons, and the

enlargement of the Panama Canal. Additionally, the industrial growth of the O&G sector in Brazil is being

followed by other Portuguese speaking oil-producing countries, as Angola and Mozambique are

example. All together bring prospects which must be characterized and framed into the Portuguese

industrial context and technological capacity.

Carbon Capture and Storage development, as mentioned, is very connected and dependent of

the knowledge of the O&G industry. Hence, Portugal must take the opportunity referred in the last

paragraph and progress in both industries at the same time. It is perhaps easier and more sustainable

to grow both together, assuring the most advanced technologies in a time that CCS cannot be decoupled

from the O&G as the mentality comes greener in terms of energy sources.

There is not much work produced in Portugal regarding CCS projects and opportunities. Even

universities are not very embraced in this mentality, preferring to focus almost all the resources in the

renewables. One collaboration between universities and entities was made to figure out the panorama

and capacities of Portugal in the present and in the future. The mapping of the Portuguese storage

capacity is represented in the figure 4.7:

Figure 4.7 – Location and description of potential storage areas and clusters for Portugal. Also showing the

economically viable pipeline routes from and between the main CO2 source regions. (Source: [84])

Different Portuguese stakeholders, from the industry to the academy, identify as main obstacle

the lack of knowledge, recommending financial incentives, a learn-by-doing strategy and the publication

of related information and studies already performed. They mentioned as well the huge impact that this

Cluster Setting Reservoirs Lithology Storage Capacity (Mt CO2)

S01 Offshore 5 Sandstones 1230

S02 Offshore 4 Sandstones,

conglomerates 870

S03 Offshore 5 Sandstones 2200

S04 Offshore 8 Sandstones,

conglomerates 1590

S05 Onshore 4 Sandstones,

conglomerates 340

S06 Offshore 4 Sandstones,

conglomerates 80

S07 Offshore 4 Limestones 410

S42 Offshore 2 Limestones and Sand

840

Page 93: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

79

industry may represent in terms of jobs creation, especially for young engineers that are nowadays

leaving the country without any challenging opportunities arising in Portugal.

Nevertheless, the dimension of a CCS project in this early stage demands a huge investment and

human resources. Thus, some stakeholders recognize that Portugal has no chances to enter in this

industry, only on an international point of view. Collaborations and cooperation are needed to employ

this technology due to the reduced size of the Portuguese energetic sector.

4.7. Concluding Remarks

Carbon Capture and Storage has been witnessing a huge improvement in terms of investment

and credibility. In times of energy transitions is difficult to understand what will be the real role and

importance that CCS may play in the near future, in terms of carbon mitigation.

Over the past five to ten years, interest in CCS technologies has been increasing rapidly in both

public and private sector, as governments, industry, and scientific community grapple with how to

reconcile energy demand with the need to reduce atmospheric carbon dioxide concentrations to mitigate

risks of climate change.

The assessment of transportation technologies, made in the second chapter, showed that this

stage of a Carbon Capture and Storage project benefited a lot from a learn-by-doing approach.

Nevertheless, and as it is revealed by the case study 1, there is a lot of phenomena to be analysed and

understood. Following the case study 2, was discussed the higher cost of offshore pipelines compared

to onshore facilities. The comparison between ships and sub-sea pipelines presented the potential

benefit from using ships for distances larger than 1000km between the coast and the offshore reservoir.

Case studies 3 and 4 reinforced the O&G significance in the development of CCS, through the

accumulated experience and similarities in storage mechanisms. Three main reasons fostered the

implementation in those situations: Enhanced Oil Recovery; Carbon excessive content or emission

taxes.

In this last chapter, different energetic scenarios were built changing the importance of the O&G

sector weight in the global energy matrix. The different case studies were framed into those global

scenarios and was concluded that a geopolitical stabilization, meaning an ordered growth, enhanced

systematically the investment in CCS. Case studies 3 and 4, where Statoil and EOR projects were

assessed, showed that this micro-climate of ordered growth and green globalization, without removing

completely the O&G importance, promoted the exploration and growth of this technological system.

However, seeing the challenging competition between technologies and environments one may

acknowledge that no scenario will be determinant by itself, but rather all of them will compete and coexist

with one other in different contexts. The analysis demonstrated as well the importance of flexibility in

engineering design to mitigate the growing uncertainty in global markets.

A successful innovation in CCS – which is a process towards a future where this technology is in

use as an important part of everyday industrial processes – still requires a lot of work to be done. Work

packages group all the milestones and progresses needed to be developed and improved, regarding

some specific matter. For the case of Carbon Capture and Storage projects, one may split the work to

be done in four packages:

Page 94: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

80

Perceived benefits: improve knowledge about real benefits in terms of climate change,

CO2 reduction and economy;

Safety concerns: reduce doubts about toxicity, fails, technology and incompatibility for

renewable energy;

Scientific worries: gain confidence in the determination of storage limits and sites, costs

and in a learn-by-doing mentality;

Risk perception: address and clarify the risks for the ecosystems, human health, drivers

and stakeholders.

4.8. Limitations and Further Work

This thesis presents two main ways for gathering scientific knowledge: literature review and

experts’ foresights. After an extensive literature review on all the topics addressed, not only the carbon

dioxide transportation and sequestration but also the Oil&Gas industry and the linkage between them,

the information was confirmed and completed through a large spectrum of interviews.

Besides the constraint of time inherent to a master thesis elaboration, other barriers to this work

were the lack of knowledge and receptivity about this disruptive approach to mitigate climacteric issues.

The differences in stakeholders’ mentality and, sometimes, the contradictory information provided by

them made this thesis even more challenging. Case studies elaboration was particularly difficult due to

the little readiness of individuals and groups to engage in interdisciplinary thinking and sharing valuable

insights, which made it harder to extract concise and valuable data.

Regarding the risk analysis, one may feel that the number of people interviewed should be larger

and wider, as more information as always found as new interviews were made. Drivers and stakeholders

are not always easily identified, due to the huge number of CCS related industries. As a result, the risks

management and recommendations provided might be also limited by those less sized but perhaps no

less important industries.

In terms of future work, the chapters related with transportation and storage may be further

addressed and analysed, particularly as new experiments and projects are activated. New trajectories

may arise and reshape the future global scenario, making the foresights developed in this last chapter

out of date and context. As part of the OIPG, this work is a first step in gathering knowledge on the

aforementioned topics and must be continuously updated, especially considering uncertainty and fast

paced technological evolution that characterize the dynamic transition era that energy industries are

facing nowadays. In parallel, a less technical approach to this theme should be also trailed, giving more

attention to the role of industrial policies, public perception or even to the development of solid

regulation.

Page 95: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

81

References

[1] International Energy Agency, “WORLD ENERGY OUTLOOK 2013,” 2013.

[2] E. Santoyo-Castelazo, L. Stamford, and A. Azapagic, “Environmental Implications of Decarbonising Electricity Supply in Large Economies: The case of Mexico,” Energy Conversion and Management, vol. 85, pp. 272–291, 2014.

[3] OECD/IEA, “CO2 Emissions From Fuel Combustion,” 2012.

[4] IPCC, “Carbon Dioxide Capture and Storage - Special Report,” 2007.

[5] International Energy Agency, “World Energy Outlook 2012,” 2012.

[6] CCSA, “Carbon Capture and Storage - Enabling a Low Carbon World,” pp. 1–20, 2009.

[7] A. S. Brouwer, M. Van Den Broek, A. Seebregts, and A. P. C. Faaij, “The flexibility requirements for power plants with CCS in a future energy system with a large share of intermittent renewable energy sources,” Energy Procedia, vol. 37, pp. 2657–2664, 2013.

[8] European Climate Foundation, “Roadmap 2050 - A Practical Guide to a Prosperous, Low-Carbon Europe,” 2010.

[9] P. Stevens, “The ‘Shale Gas Revolution’ : Developments and Changes,” Chatham House Briefing Paper, no. August, p. 12, 2012.

[10] H. Gerbelová, a. André, S. Casimiro, M. Melo, and P. Ferrão, “Assessment of carbon capture and storage opportunities: Portuguese case study,” Energy Procedia, vol. 4, no. 2011, pp. 6109–6116, 2011.

[11] J. Røyrvik, M. Schei Olsen, and T. M. B. Aasen, “Political rationality and CCS discourse,” Energy Procedia, vol. 23, no. 1876, pp. 284–295, 2012.

[12] OIPG, “The International Observatory Global Policies for the Sustainable Exploration of Atlantic,” 2014.

[13] IBM, “Meeting the challenges of today’s oil and gas exploration and production industry.,” On Demand Business - IBM, no. G510–3882–00, p. 8, 2004.

[14] A. T. Furtado, “Pré-sal , Desenvolvimento Industrial e Inovação Objetivo,” pp. 79–100.

[15] J. Koornneef, A. Ramírez, W. Turkenburg, and A. Faaij, “The environmental impact and risk assessment of CO2 capture, transport and storage - an evaluation of the knowledge base using the DPSIR framework,” Energy Procedia, vol. 4, pp. 2293–2300, 2011.

[16] “EC, Directive 2009/31/EC of the European Parliament and of the Council on the geological storage of carbon dioxide,” Office Journal of the European Union, no. June 2006, pp. 114–135, 2009.

[17] GLOBAL CCS INSTITUTE, “Large-Scale CCS Projects – Definitions.” [Online]. Available: http://www.globalccsinstitute.com/projects/large-scale-ccs-projects-definitions. [Accessed: 12-May-2015].

[18] CCSA, “What is CCS? Capture.” [Online]. Available: http://www.ccsassociation.org/what-is-ccs/capture/. [Accessed: 10-Apr-2015].

Page 96: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

82

[19] Carbon Sequestration Leadership Forum, “CO2 Capture - Does It Work?” 2009.

[20] GLOBAL CCS INSTITUTE, “CO2 Capture Technologies - Technology Options for CO2 Capture,” no. January, 2012.

[21] M. Gupta, I. Coyle, and K. Thambimuthu, “CO2 Capture Technologies and Opportunities in Canada,” Strawman Document for CO2 capture and Storage (CC&S) Technology Roadmap, no. September, pp. 1–15, 2003.

[22] International Energy Agency, “Technology roadmap - Carbon capture and Storage,” p. 59, 2013.

[23] CCSA, “What is CCS? Transport.” [Online]. Available: http://www.ccsassociation.org/what-is-ccs/transport/. [Accessed: 13-Apr-2015].

[24] UKCCS Research Centre, “CCS - Cross Cutting Issues - Transport.” [Online]. Available: https://ukccsrc.ac.uk/about/what-ccs/cross-cutting-issues/transport. [Accessed: 13-Apr-2015].

[25] A. Cosham and R. J. Eiber, “Fracture propagation in CO2 pipelines,” Journal of Pipeline Engineering, pp. 147–158, 2007.

[26] UKCCS Research Centre, “What is CCS Storage?” [Online]. Available: https://ukccsrc.ac.uk/about/what-ccs/storage. [Accessed: 14-Apr-2015].

[27] C. Fu and T. Gundersen, “Carbon Capture and Storage in the Power Industry: Challenges and Opportunities,” Energy Procedia, vol. 16, pp. 1806–1812, 2012.

[28] J. P. Barry, K. R. Buck, C. F. Lovera, L. Kuhnz, P. J. Whaling, E. T. Peltzer, P. Walz, and P. G. Brewer, “Effects of direct ocean CO2 injection on deep-sea meiofauna,” Journal of Oceanography, vol. 60, no. 4, pp. 759–766, 2004.

[29] CCSA, “What is CCS? Storage.” [Online]. Available: http://www.ccsassociation.org/what-is-ccs/storage/. [Accessed: 14-Apr-2015].

[30] M. E. Porter, “Competitive Advantage: Creating and Sustaining Superior Performance,” New York: The Free Press, 1985.

[31] C. O. H. Wolf, “The Petroleum Sector Value chain,” The World Bank Research Observer, no. June 2009, pp. 1–33, 2010.

[32] S. J. Gomes and B. F. Alves, Universo da Indústria Petrolífera: Da pesquisa à refinação. Fundação Calouste Gulbenkian, 2007.

[33] F. Jahn, M. Cook, and M. Graham, Hydrocarbon Exploration & Production. Elsevier, 2008.

[34] L. Vandebroek and J. Berghmans, “Safety aspects of the use of LNG for marine propulsion,” Procedia Engineering, vol. 45, pp. 21–26, 2012.

[35] A. Tugnoli, N. Paltrinieri, G. Landucci, and V. Cozzani, “LNG regasification terminals: Comparing the inherent safety performance of innovative technologies,” Chemical Engineering Transactions, vol. 19, pp. 391–396, 2010.

[36] N. Rosenberg, Inside the Black Box: Technology and Economics. Cambridge: Cambridge University Press, 1982.

Page 97: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

83

[37] C. Freeman and C. Perez, Structural crisis of adjustment, business cycles and investment behaviour. Pinter, London, 1988.

[38] A. De Oliveira, C. G. Ribeiro, and A. T. Furtado, “Competition between technological systems in pre-salt fields,” IAMOT, 2014.

[39] R. R. Nelson and S. G. Winter, “In search of a useful theory of innovations,” Research Policy, 1977.

[40] OECD, “The Oslo Manual: The Measurement of Scientific and Technical Activities,” Paris, 1992.

[41] G. Dosi, “The nature of the innovative process,” in Technical change and economic theory, London, Pinter, 1982, pp. 94–113.

[42] R. de Neufville and S. Stefan, Flexibility in Engineering Design. The MIT Press, 2011.

[43] J. K. Creswell, Qualitative inquiry and research design; choosing among five approaches, 3rd ed. Thousand Oaks: Sage, 2007.

[44] H. Simons, Case study research in practice. Los Angeles: Sage, 2009.

[45] M. Bassey, Case study research in educational settings. Maidenhead: Open University Press, 1999.

[46] R. E. Stake, The art of case study research. Thousand Oaks: Sage, 1995.

[47] N. J. Petty, O. P. Thomson, and G. Stew, “Ready for a paradigm shift? Part 2: Introducing qualitative research methodologies and methods,” Manual Therapy, vol. 17, no. 5, pp. 378–384, 2012.

[48] K. M. Eisenhardt, “Building Theories from Case Study Research,” Academy of Management Review, vol. 14, no. 4, pp. 532–550, 1989.

[49] J. Pfeffer, Organizations and organization theory. Marshfield, MA: Pitman, 1982.

[50] I. Miles, “The development of technology foresight: A review,” Technological Forecasting and Social Change, vol. 77, no. 9, pp. 1448–1456, 2010.

[51] IRGC, “Risk Governance Deficits: Analysis, illustration and recommendations,” pp. 1–24, 2010.

[52] IRGC, “Risk governance: Towards an integrative approach,” International Risk Governance Council, pp. 1–157, 2005.

[53] IRGC, “An introduction to the IRGC Risk Governance Framework,” International Risk Governance Council, pp. 1–24, 2008.

[54] OECD Reviews of Risk Management Policies, OECD (2011), Future Global Shocks: Improving Risk Governance. 2011.

[55] CO2 Europipe, “Towards a transport infrastructure for large-scale CCS in Europe Developing a European CO2 transport infrastructure,” Seventh Framework Programme, pp. 1–65, 2009.

[56] J. Morbee, J. Serpa, and E. Tzimas, “The evolution of the extent and the investment requirements of a trans-European CO2 transport network,” JRC Scientific an Technical Reports, 2010.

Page 98: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

84

[57] R. Doctor, A. Palmer, D. Coleman, J. Davison, C. Hendriks, O. Kaarstad, and M. Ozaki, “Transport of CO2,” in Special Report on Carbon dioxide Capture and Storage, IPCC, 2005.

[58] Energy Institute, “Good plant design and operation for onshore carbon capture installations and onshore pipelines,” p. 137, 2010.

[59] Det Norske Veritas, RECOMMENDED PRACTICE - Design and Operation of CO2 Pipelines, no. April. 2010.

[60] M. Mohitpour, H. Golshan, and A. Murray, Pipeline Design & Construction: A Practical Approach. ASME Press, New York, 2007.

[61] Canadian National Energy Board, PIPELINE REGULATION IN CANADA : A Guide for Landowners and the Public. 2010.

[62] R. Skagestad, N. Eldrup, H. Richard, S. Belfroid, A. Mathisen, A. Lach, H. A. Haugen, R. Skagestad, N. Eldrup, H. Ri-, S. Belfroid, and A. Mathi-, “Ship transport of CO2,” 2014.

[63] Global-CCS-Institute, “Preliminary Feasibility Study on CO2 Carrier for Ship-based CCS,” 2012.

[64] Y. Seo, D. Chang, J. Y. Jung, C. Huh, and S. G. Kang, “Economic evaluation of ship-based CCS with availability,” Energy Procedia, vol. 37, pp. 2511–2518, 2013.

[65] Lloyd’s List Intelligence, “Shipping just got smarter,” 2015. [Online]. Available: http://www.lloydslistintelligence.com/llint/index.htm.

[66] Zero Emission Platform, “The Costs of CO2 Transport Post-demonstration CCS in the EU,” 2010.

[67] N. Sacuta and K. Anderson, “Creating core CCS messages: Focus Group Testing and Peer Review of Questions and Answers from the IEAGHG Weyburn-midale CO2 Monitoring and Storage Project,” Energy Procedia, vol. 63, pp. 7061–7069, 2014.

[68] GHG and IEA, Weyburn CO2 monitoring & storage project. Summary report 2000-2004. 2004.

[69] APEC Energy Working Group Project EWG 03 / 2004T, “Building Capacity for CO2 Capture and Storage in the APEC Region - A Training Manual for Policy Makers and Practitioners,” no. March, 2005.

[70] M. Celia, B. Gunter, J. Ennis, and E. Lindeberg, Underground geological storage, vol. chapter 5. 2005.

[71] S. Bachu, “Screening and ranking of sedimentary basins for sequestration of CO2 in geological media in response to climate change,” Environmental Geology, vol. 44, pp. 277–289, 2003.

[72] J. B. Bradshaw, E. Bradshaw, G. Allinson, A. J. Rigg, V. Nguyen, and A. Spencer, “The potential for geological sequestration of CO2 in Australia: preliminary findings and implications to new gas field development,” Australian Petroleum Production and Exploration Association Journal, vol. 42, pp. 24–46, 2002.

[73] C. M. Gibson-Poole, “Site Characterisation for Geological Storage of Carbon Dioxide: Examples of Potential Sites from Northwest Australia,” The University of Adelaide, 2008.

[74] CO2CRC, “Researching Carbon Capture & Storage - Storing CO2,” p. 2, 2012.

Page 99: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

85

[75] S. E. Gasda, S. Bachu, and M. Celia, “The potential for CO2 leakage from storage sites in geological media: analysis of well distribution in mature sedimentary basins,” Environmental Geology, pp. 707–720, 2004.

[76] J. J. Heinrich, H. J. Herzog, and D. M. Reiner, “Environmental Assessment of Geological Storage of CO2,” in Second National Conference on Carbon Sequestration.

[77] NETL, “NETL - Carbon Capture and Storage Projects List 2015,” 2015.

[78] S. A. Benson, Geological Storage of CO2: Analogues and Risk Management. Pittsburgh PA, 2007.

[79] Delloite, “Vision 2040 - Global Scenarios for the Oil and Gas Industry: Understanding the next decades.”

[80] Accenture, “Risk management for an era of greater uncertainty,” 2013.

[81] D. Rodrik, “Normalizing Industrial Policy,” pp. 1–50, 2008.

[82] M. Yulek, Economic Planning and Industrial Policy in the Globalizing Economy: Concepts, Experience and Prospects. Springers, 2013.

[83] T. Hutchinson and P. Dickey, “Value-Added Engineering: A Solution to a Down Market,” Society of Petroleum Engineers, 2015.

[84] FCT, CGE, LNEG, Bellona, and REN, “CCS in Portugal - a bridge to a low carbon economy,” 2012.

Page 100: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations
Page 101: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

a

Annex A: Clusters for an effective Risk Assessment and Managing

(Source: [51])

Cluster A: Assessing Risks

Page 102: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

b

Cluster B: Managing Risks

Page 103: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

c

Annex B: Pipeline Design Flow Diagram

Source: [58]

Page 104: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

d

Annex C: Carbon Dioxide Phase Diagram

(Source: www.earthscience.com)

Page 105: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

e

Annex D: List of interviewed specialists

Interviewed Person Function Company/Institution URL

Richard De Neufville Professor Massachusetts Institute

of Technology (MIT)

https://esd.mit.edu/Faculty_Pages

/deneufville/deneufville.htm

Joaquim Neto Filipe CEO ProjectoDetalhe Group http://www.projectodetalhe.com/in

dex.php/grupo-projecto-detalhe-3/

Jorge Silva Chief Engineer ProjectoDetalhe Group https://pt.linkedin.com/pub/jorge-

gomes-da-silva/28/904/8

Lionel Loubeau New Markets

Responsible

Fundación Ciudad de la

Energía (CIUDEN) http://ciuden.es/index.php/en/

Marcelo Vindeirinho Claims Adjuster American Insurance

Group (AIG) http://www.aig.com.pt/

Ramiro Neves Professor Tecnico Lisbon, IST https://fenix.tecnico.ulisboa.pt/ho

mepage/ist11787

António Valle Director WW, Maritime Works

Consultant

http://www.appconsultores.org.pt/

associados/detalhes.php?id=152

Luís Medeiros Board Adviser ProjectoDetalhe Group http://www.projectodetalhe.com

Page 106: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

f

Annex E: Interviews Transcript

In this annex follows a transcript of some of the most relevant interviews for the context of this

thesis.

Interviewee: Richard de Neufville, Engineer

Occupation: Professor at Massachusetts Institute of Technology (MIT)

This interview was made to better understand the notion and requirements of a “Flexibility in

Engineering Design” approach to different projects, especially for Carbon Capture and Storage. Richard

de Neufville has strong ideas about the flexibility concept, which he believes is starting to be fundamental

for the sustainability of every product or project.

According to his experience throughout the past years, the biggest challenge is changing

perspectives of stakeholders. They think that the way they are doing is the optimal, because it always

gave profit without relevant problems. As so, they are very afraid of a change that, in their point of view,

might compromise results.

Richard de Neufville identifies five main problems which may arise during the implementation of

flexibility in engineering design on a certain product:

Engineers neither practised nor trained to consider uncertainties in non-technical areas;

Engineering models often so detailed that there is no time to simulate many scenarios;

Everything is uncertain? What should be the focus?

What options to develop and compare?

Multi-criteria evaluation. Many criteria for choice of concepts might difficult the results.

When asked about how may be analysed a more general case, instead of a specific product or

project, such as the sustainability of the energy sector, Richard de Neufville commented that should be

adopted a learn-by-doing methodology. Establishing short-time strategies and react to setbacks, like in

a chess game, is the best way to make things happen. Particularly for the CCS industry, they should

focus on real things and not being always in the research field. Build a project and see the difficulties

and results (basically, a learn-by-doing approach) is the best way to scale-up the industry.

Page 107: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

g

Interviewee: Jorge Silva, Engineer

Occupation: Chief Engineer at Projecto.Detalhe

Projecto.Detalhe was founded in 2000 and specializes in engineering and project management.

Is based in Quinta da Beloura (Sintra), which is near Lisbon. After consolidation in the national market,

Projecto.Detalhe focused on growth in new markets. Currently, under the strategy of internationalization,

has associate companies in Angola, Mozambique, Brazil, Cape Verde and Macau. Projecto.Detalhe is

also involved in Guinea, Swaziland, Cameroon, Ivory Coast, South Africa, Saudi Arabia and Qatar.

The focus is on projects EPC (Engineering, Procurement and Construction) in the sectors of Oil

& Gas, Energy, Environment, Infrastructures, Mining and Metallurgy and, finally, the Sea. Environment,

health and safety and regular activities of social responsibility are part of the sustainable development

of Projecto.Detalhe.

Jorge Silva believes that Projecto.Detalhe has capacity to face and resist to changes in paradigms

of the energy sector. They are investing in fresh graduate engineers to be more flexible and with new

ideas for the future, allying that to knowledge of more experienced employees.

Regarding Carbon Capture and Storage, especially transportation by pipelines, he recognizes the

lack of data of the phenomena behind the carbon dioxide behaviour. However, Jorge Silva thinks that

there is no reason to be much more concerned about CO2 than other fluids that engineers of

Projecto.Detalhe are used to deal with. As so, and defending that the excellence only may be achieved

with years of experience, he defends a more flexible regulatory regime.

Interviewee: António Valle, Engineer

Occupation: Director at WW – Maritime Consultancy SA

WW is a consultancy company of engineering specialized in the fields of Maritime Hydraulics,

Port and Shore Engineering. It develops its activity since 1981 in Portugal, including the Azores and

Madeira islands. Abroad, they are represented in Angola, Cape Verde, Spain, Morocco, Algeria, Malta

and Brazil.

António Valle is a Civil Engineer very experienced in maritime works, especially regarding coastal

issues. He defends that in the near future the shore will become saturated and offshore will start to play

a major role. There is plenty of space to explore in the sea, above and below the surface. That space

may be both used by the renewable energy sector (offshore wind farms) or the Oil&Gas (sub-sea

factories). However, António Valle recognizes the still embryonic stage of renewable energy, which are

not experiencing enough investment and effort to scale-up definitively.

When asked about the future of Carbon Capture and Storage, António Valle commented that the

major stakeholder responsible to improve CCS acceptance and deployment must be the O&G industry.

Only they have data that may be used, through appropriate knowledge transfer tools, to foster the

implementation of these technologies without beginning from scratch. However, he points out as biggest

barrier the substantial investments and costs, which should be balanced and stimulated through carbon

emissions penalties or benefits.

Page 108: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

h

Interviewee: Ramiro Neves, Engineer

Occupation: Professor at IST – Scientific Area of Environment and Energy, Mechanical Department

Ramiro Neves dedicated the last years to the study of Advanced Environmental Modelling. He

teaches environmental modelling following an interdisciplinary approach, putting into evidence the

importance of the physical processes for aquatic and terrestrial ecosystems, both directly through the

transport processes and indirectly through their implications on the energy cycle and on the differential

transport of particulate and dissolved matter.

This professor indicates as major drivers of modelling progression in the last decade the growing

necessity of forecast the future. The model is the reality and, sometimes, the data directly taken from

the several instruments is not. Modelling the past allows the identification of future problems and

consequent generation of solutions, supporting train and education. Is important to monitor large events

and, afterwards, downscale the data and results for the benefit of several industries, such as CCS. This

modelling reality should be fostered through public divulgation, while possible, of data and results

collected by different entities.

Interviewee: Marcelo Vindeirinho, Manager

Occupation: Claims Adjuster at American Insurance Group (AIG)

Marcelo Vindeirinho is the Manager of sinister related with the Maritime and Marine Industry. He

is in charge of several processes regarding oil platforms and ships.

He assumes the contribution that an insurance company may give to the development of an

industry, covering some controlled risks that may degenerate in serious accidents and compromise the

whole sector. Regarding the O&G industry, he referred that is always difficult to decide whether the fault

is on the company and out of the agreed terms of the contract. This industry has a lot of powerful

interests and tricks, making even more difficult the analysis and the decision of covering or not the

damages.

When asked about Carbon Capture and Storage, Marcelo Vindeirinho is not so confident in future

agreements because of the lack of knowledge and experience. The insurance company has to follow

strict regulations, based on strong and consolidated knowledge, to define the different terms of the

contract and to have a controlled management of the unknown risk. Thus, he identifies as first priority

the construction of regulatory policies to foster the development and attracting insurance companies to

join in.

Page 109: Assessing CCS technologies towards large-scale deployments · complemented with a risk analysis based on the IRGC risk governance framework, where drivers, stakeholders and recommendations

i

Interviewee: Lionel Loubeau, Engineer

Occupation: New Markets Responsible at Fundación Ciudad de la Energía (CIUDEN)

The Foundation was established in 2006, under the authority of the Government of Spain, to

implement R&D&I energy and environment programmes, and contribute to the economic development

in El Bierzo region. It is run by a board of governors with the participation of the ministries related to

Energy, Science and Environment. The energy model raises questions about the future and forces us

to do some hard thinking in order to achieve the future we desire. CIUDEN wants to be part of this

process. Open to the exchange of ideas, cooperation and innovation, with the participation of citizens,

enterprises, technology and thinking.

Lionel Loubeau defends the role of foundations as CIUDEN in the development of Carbon

Capture and Storage and related industries. He assumes that CCS is far from being generally accepted

and used, identifying as major challenges the changes in paradigms. Carbon Capture and Storage faces

the carbon dioxide in a different perspective of any other technology. Instead of reducing or annulling

completely carbon emissions, by improving the efficiency of the sources or investing in renewables,

CCS manages and stores the carbon emitted. In this way we are not mitigating the emissions but only

the damages that they may cause. It is not the smartest and cleanest way to lead with the problem, but

is not cleaver as well to waste all the fossil fuels potential. The energy matrix should have as much

entries (sources) as possible, without forgetting the damages and costs of each one.

Data and results made available to the public, allowing their engagement and education; flexible

regulations and risks frameworks; financial policies and harmonised monitoring, measurement and

verification standards are the key issues that, in his opinion, should be addressed to foster the

implementation of this technological system.