Mgt 2070 Assignment #9 Answers
Mgt 2070 Assignment #9 Answers
14.11Given the product structure, master production schedule, and inventory status
a) Develop a gross requirements plan for Item C.
To develop a Gross Requirements Plan for item C, we note from the diagram that one of item C is used in Assembly A and another is used in Assembly H. Note that existing inventories arent taken into account in a gross requirements plan. Our plan should thus show requirements for all three components:
Item123456789101112
AGross Req10050150
Order Rel10050150
HGross Req10050
Order Rel10050
CGross Req1001005050150
Order Rel1001005050150
b) A net requirements plan for Item C.
Our net requirements plan does taken into account existing inventories and provides us with some more detailed quantities. Once again, it should show items A, H, and C:
Item123456789101112
AGross Req10050150
On Hand
Net Req10050150
Planned Receipt10050150
Planned Release10050150
HGross Req10050
On Hand
Net Req10050
Planned Receipt10050
Planned Release10050
CGross Req1001005050150
On Hand5050505050505000000
Net Req501005050150
Planned Receipt501005050150
Planned Release501005050150
14.13Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each fan consists of a housing assembly, two grills, a fan assembly, and an electrical unit. The housing assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub and five blades. The electrical unit consists of a motor, a switch and a knob. The table on the top of page 607 gives lead times, on-hand inventory, and scheduled receipts.
a)Construct a product structure.The product structure diagram is:
b) The time-phased product structure is:
Frame
SupportHousing
Handle
GrillsFan
Hub
Fan Assembly
Blades
Motor
SwitchElec
Knobs
1234567
c) The net material requirements plan is:
Lot SizeLead TimeOn HandItem ID1234567
110020 FanGross Requirements1000
Projected On Hand100
Net Requirements900
Planned Order Receipts900
Planned Order Releases900
1100HousingGross Requirements900
Projected On Hand100
Net Requirements800
Planned Order Receipts800
Planned Order Releases800
2200GrillsGross Requirements1800
Projected On Hand200
Net Requirements1600
Planned Order Receipts1600
Planned Order Releases1600
3150Fan
AssemblyGross Requirements900
Projected On Hand150
Net Requirements750
Planned Order Receipts750
Planned Order Releases750
1Electrical
UnitGross Requirements900
Projected On Hand
Net Requirements900
Planned Order Receipts900
Planned Order Releases900
2FrameGross Requirements800
Projected On Hand
Net Requirements800
Planned Order Receipts800
Planned Order Releases800
Lot SizeLead TimeOn HandItem ID1234567
150SupportsGross Requirements1600
Projected On Hand50
Net Requirements1550
Planned Order Receipts1550
Planned Order Releases1550
1400HandleGross Requirements800
Projected On Hand400
Net Requirements400
Planned Order Receipts400
Planned Order Releases400
1HubGross Requirements750
Projected On Hand
Net Requirements750
Planned Order Receipts750
Planned Order Releases750
1002BladesGross Requirements3750
Projected On Hand50505050
Net Requirements3750
Planned Order Receipts3800
Planned Order Releases3800
1MotorGross Requirements900
Projected On Hand
Net Requirements900
Planned Order Receipts900
Planned Order Releases900
12120SwitchGross Requirements900
Projected On Hand208
Net Requirements880
Planned Order Receipts888
Planned Order Releases888
Lot SizeLead TimeOn HandItem ID1234567
251KnobGross Requirements900
Scheduled Receipt200
Projected On Hand200200200
Net Requirements700
Planned Order Receipts700
Planned Order Releases700
15.13The following jobs are waiting to be processed at a small machine center:
JobDue DateDuration (days)
01026030
02025816
0302608
04027020
05027510
In what sequence would the jobs be ranked according to the following decision rules: (1) FCFS, (2) EDD, (3) SPT, (4) LPT? All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 210. Which is the best decision rule?
a)FCFS because all jobs arrived on day 210, and presumably in the order given, the FCFS sequence is:
010, 020, 030, 040, 050
b)EDD
Job SequenceDue Date
020258
010260
030260
040270
050275
Note that longest processing time was used to choose between jobs 010 and 030.
c)SPT
Job SequenceProc Time
0308
05010
02016
04020
01030
d)LPT
Job SequenceProc Time
01030
04020
02016
05010
0308
Scheduling RuleAverage TardinessAverage Flow TimeAverage # Jobs in System
FCFS7.457.63.4
EDD7.454.83.3
SPT6.639.62.4
LPT12.061.23.6
20 Fan
Switch
Motor
Blades (5)
Hub
Handle
Knob
Supports (2)
Frame
Electrical
Housing
Grills (2)
Fan Assembly