XI-1-83-54Rt XI-1-86-21R Section XI - Interpretations No. 26 Interpretation: XI-1 -83-541 Subject: Section XI, Division 1, IWA-4400, IWA-4600, and IWA-7400; Hydrostatic Testing (I 977 Edition and Later Editions and Addenda Through the 1987 Addenda) Date Issued: September 19, 1989 File: BC84-321* Question: If the Owner performs a pipe replacement in accordance with Section XI, Division 1, IWA-7000, what hydrotesting is required? Reply: The hydrostatic test requirements of IWA-4600 shall be met, except for the items listed under IWA-7400 and IWA-4400. Interpretation: XI-1 -86-21 R Subject: Section XI, Division 1, Table IWB-2500-1, IWP and IWV; Defect Removal Without Welding (1977 Edition With Addenda Through Summer 1978, and Subsequent Ad- denda Through Winter 1985) Date Issued: September 19, 1989 File: IN86-004* Question (I): When maintenance is performed which does not involve welding or does not involve metal removal, do the requirements of-Section XI apply? Reply (I): No; however, Table IWB-2500-1 applies. Question (2): When maintenance such as removal and reinstallation of the same bolting ma- terial, tightening of fasteners, and replacement of gaskets, packing, and seals, where such mainte- nance does not require welding or removal or replacement of pressure retaining material, do the rules of Section XI apply? Reply (2): No, except for the retest requirements of IWV and IWP. 186 COPYRIGHT American Society of Mechanical Engineers Licensed by Information Handling Services COPYRIGHT American Society of Mechanical Engineers Licensed by Information Handling Services

Upload: nguyengiadinh1980

Post on 27-Jan-2016

285 views

Category:

Documents


5 download

DESCRIPTION

Asme Sec Xi-1 Int [1986]

TRANSCRIPT

Page 1: Asme Sec Xi-1 Int [1986]

XI-1-83-54Rt XI-1-86-21R Section XI - Interpretations No. 26

Interpretation: XI-1 -83-541

Subject: Section XI, Division 1, IWA-4400, IWA-4600, and IWA-7400; Hydrostatic Testing (I 977 Edition and Later Editions and Addenda Through the 1987 Addenda)

Date Issued: September 19, 1989

File: BC84-321*

Question: If the Owner performs a pipe replacement in accordance with Section XI, Division 1, IWA-7000, what hydrotesting is required?

Reply: The hydrostatic test requirements of IWA-4600 shall be met, except for the items listed under IWA-7400 and IWA-4400.

Interpretation: XI-1 -86-21 R

Subject: Section XI, Division 1, Table IWB-2500-1, IWP and I W V ; Defect Removal Without Welding (1977 Edition With Addenda Through Summer 1978, and Subsequent Ad- denda Through Winter 1985)

Date Issued: September 19, 1989

File: IN86-004*

Question (I): When maintenance is performed which does not involve welding or does not involve metal removal, do the requirements of-Section XI apply?

Reply (I): No; however, Table IWB-2500-1 applies.

Question (2): When maintenance such as removal and reinstallation of the same bolting ma- terial, tightening of fasteners, and replacement of gaskets, packing, and seals, where such mainte- nance does not require welding or removal or replacement of pressure retaining material, do the rules of Section XI apply?

Reply (2): No, except for the retest requirements of I W V and IWP.

186

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 2: Asme Sec Xi-1 Int [1986]

Section XI - Interpretations No. .26 X1-1-86-27Rt XI-1 -116-52R

Interpretation: XI-1 -86-27R

Subject: Section XI, Division 1, IWA-5214, IWC/lWD-4000, and IWC/IWD-7000; Pressure Testing After Disassembly and Reassembly of Class 2 and 3 Mechanical Joints (I 980 Edition With Addenda Through Winter 1981)

Date Issued: September 19, -1 989

File: lN86-007"

Question: Does Section XI, Division 1, IWA-5214(e) apply to the disassembly and reassembly of mechanical joints in Class 2 and 3 systems only when such is performed in the course of a Section XI, Division 1, IWC-4000 and IWD-4000 repair or. IWC-7000 and IWD-7000 replacement?

Reply: Yes.

Interpretation: Xi-1 -86-52R

Subject: Section XI, Division 1, IWA-3400, IWB-3000, IWB-3500, IWX-2500 and Table I W X - 2500-1; Flaw Evaluations and Indications (1980 Edition With Addenda Through Winter 1981 1

Date Issued: November 22, 1989

File: BC85-524*

Question (1): In accordance with Section XI, Division I, may -linear flaws addressed in IWA- .3400, and linear indications detected by surface examinations required by IWB-3500, be defined in accordance with Section I l l , 1980 Edition with Addenda through Winter 1981, NX-5341 (c) and NX- 5351 (c)?

Reply (1): No, The acceptance criteria shall be as stated in IWB-3500.

Question (2): In accordance with Section XI, Division 1, are nonlinear indications detected by surface examinations specified in IWX-2500 which exceed the acceptance criteria specified h t h e Construction Code unacceptable, unless found acceptable by subsequent volumetric examinations?

Reply (2): IWX-2500 requires that components be examined and tested as specified in Table IWX-2500-1. If the indication exceeds the acceptance standards of IWB-3000, it is classified as a flaw. The flaw must be either analyzed to the requirements of IWB-3600 or repaired. For preservice examinations, analysis is not permitted.

187

COPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling ServicesCOPYRIGHT American Society of Mechanical EngineersLicensed by Information Handling Services

Page 3: Asme Sec Xi-1 Int [1986]

Section XI - Interpretations No. 29 XI-1-86-13R, XI-1-89-46R

Interpretation: XI-1-86-13R

Subject: Section XI, IWA-5211, IWA-5214, IWA-4000, and IWA-7000; System Pressure Tests - Disassembly and Reassembly

Date Issued: June 10, 1991

File: BC85-111*

Question (1): In Section XI (1983 Edition), IWA-5214 is titled “Repairs and Replacements.” Does this paragraph apply only to activities conducted under the IWX-4000, “Repair Procedures” (except IWP), and IWX-7000, “Replacements” articles in other than Class 1 systems?

Reply (1): Yes.

Question (2): When using Section XI, (1977 Edition with Addenda through Summer 1978, and later Editions and Addenda through the 1983 Edition), is a system pressure test (IWA-5000) re- quired whenever the pressure boundary is opened and closed (e.g., replacing a valve bonnet gasket)?

Reply (2): No. A Section XI pressure test is required only when the pressure boundary is opened and closed in the course of a Section XI repair or replacement, with the exception of those items exempt under JWA-4000/7000, (see Interpretation XI-1-89-08).

Interpretation: XI-1-89-46R

Subject: Section XI, IWA-7210; Section VI11 as The Construction Code Edition)

Date Issued: April 15, 1991

File: IN90-008*

Edition of (1989

Question (1): Does Section XI, IWA-7210, allow the installation of existing pressure vessels constructed in accordance with other than the current Edition and Addenda of Section VI11 for use in a nuclear power plant application?

Reply (1): Yes.

Question (2): Does Section XI, IWA-7210, allow the construction of a Section VI11 pressure vessel to other than the current Section VI11 Edition and Addenda when used in a nuclear power plant application?

Reply (2): Section XI requires the Section VI11 requirements to be met.