asl 11 kv fcl for the ce electric grid, newcastle, uk low...
TRANSCRIPT
1
ASL 11 kV FCL for the CE Electric Grid, Newcastle, UK
Low-Carbon Network Fund Program Update
EPRI Superconductivity Conference
Tallahassee, Florida
October 12, 2011
Albert Nelson – [email protected]
Franco Moriconi – [email protected]
2
Overview
Brief Background of the Project
Initial Test Results
Bushing Failure and Corrective Action
Recovery and Repair Effort
Successful Retest and Acceptance
3
Saturable Iron Core MFCL
Operating Principle
Picture-Frame Iron-Cores
AC CoilAC Coil
Boost Buck
Configuration for single
phase FCL
BoostBuck
4
Evolution of the Product
SPIDER
2.5x2.5 m footprint
Effective core 300 cm2
Rectangular COMPACT
2.0x1.3 m footprint
Effective core 860 cm2
Prototype AC coils and magnets
ROUND COMPACT
1.8m OD footprint
Effective core 750 cm2
Commercial product
FROM
DEMONSTRATORTO
PROTOTYPE
TO
PRODUCT
5
Installation Late 2011
Specifications:Voltage: 11.3 kV
Current: 1250 A
Prospective Fault: 17 kA peak
Fault Reduction: 22%
Fault Duration: 3 seconds
CE Electric UK and Applied Superconductor Ltd(11 kV)
6
ASL MFCL Assembly – Major Components
7
ASL 11 kV MFCL Assembly – T&R Electric
8
ASL 11 kV MFCL Assembly – T&R Electric
9
ASL 11 kV MFCL Factory Tests
• Windings Resistance
• Windings Reactance
• From Insertion Impedance Voltage Drop
• Insulation Resistance
• Temperature Rise
• AC Withstand Voltage
10
ASL 11 kV MFCL First Test Protocol
(Factory Tests Highlighted)
Document Section Test Name Specification Clarification Test Location
a) At Reduced Voltage a) Factory
b) At Full Voltage b) High Power Lab
a) At Reduced Voltage a) Factory
b) At Full Voltage b) High Power Lab
Factory and High
Voltage Lab
4.1.6 Temperature Rise
IEC 60076 Part-6,
Clause 8.9.11
&60076 Part2
At Reduced Voltage. Test at 1250A until
steady state, then 15 min at 1600A, longer if
limit not reached Factory
4.1.7 Partial Discharge IEC 60270
Each phase in turn, remaining phases and
frame earthed High Power Lab
4.1.8 Inter-turns Insulation
IEC 60076-6,
Clause 8.9.9
Test@95kV Peak. Nom. 1.2x50. Each phase
in turn, remaining phases and frame
earthed. 15+ve, 15-ve pulses on each
phase High Voltage Lab
4.1.9 BIL (Lightning Impulse)
60076-6,
Clause 8.9.12&
IEC 60076-4,
Clause 7
Test@95kV Peak. Nom. 1.2x50. Each phase
in turn, remaining phases and frame
earthed. 15+ve, 15-ve pulses on each
phase High Voltage Lab
4.1.2 Insulation Resistance
IEEE Std. 62-
1995, Clause
6.1.5 Coil manufacturer dielectric test Factory
(1) Prosp. Asym.=17kA peak,
(2) Prosp. Sym.= 6.2kArms
(1) Limited Asym. < 13.25 kA peak,
(2)Limited Sym. < 5kArms
Loss Measurement
IEC 60076 Part-6,
Clause 8.9.7
4.1.5 AC Withstand Voltage
IEC 60076-6
Clause 8.9,8
& IEC 60076-3,
28kV for 1-minute each phase in turn,
remaining phases and frame earthed
SP
EC
IAL
TE
ST
S
4.3.1
Faulting with FCL bypassed at
rated voltage (11.3kV) to verify for
IEC 60076 Part-5,
Clauses 4.2.2 to
RO
UT
INE
TE
ST
S
4.1.3 Insertion Impedance (Voltage Drop)
IEC 60076 Part-6,
Clause 8.9.5
4.1.4
High Power Lab
4.3.2
Faulting with FCL in the circuit at
rated voltage (11.3kV). Test at 17
IEC 60076 Part-5,
Clauses 4.2.2 to High Power Lab
11
ASL 11 kV MFCL Factory Testing Inductance Measurements
ASL 11 kV - Terminal Inductance at Full Load 1250 Arms vs. DC Magnetization
Measured at 60Hz - Calculated at 50Hz
160
170
180
190
200
210
220
230
240
250
260
270
280
290
300
310
320
330
340
350
360
370
380
360 370 380 390 400 410 420 430 440 450 460 470 480 490 500 510 520
DC Magnetization [kAT]
Term
inal
Ind
uct
ance
[m
icro
H]
0.6
0.65
0.7
0.75
0.8
0.85
0.9
0.95
1
1.05
1.1
1.15
1.2
1.25
1.3
1.35
1.4
1.45
1.5
1.55
1.6
1.65
1.7
1.75
1.8
Equ
ival
ent
Rel
ativ
e P
erm
eab
ility
Mu
r
MeasuredTerminalInductance
ANSYS CalculatedTerminalInductance
Inductance limitfor 100VrmsVoltage Drop255 microH
Measured Air-CoreTerminal Inductance189 microH
Minimum DC Magnetization450 kAT
EquivalentRelativePermeability
12
ASL 11 kV MFCL Factory Testing – Temperature Rise
• 17 hours at full load 1250 A rms
• Top Radiator Oil temperature
from 26 C to 73 C
• Bottom Radiator Oil temperature
from 19 C to 40 C
• Average Temperature Rise 34 C
AC Current 1250 Arms
Top Radiator Oil Temp [C]
Bottom Radiator Oil Temp [C]
13
ASL 11 kV MFCL Factory Testing – Voltage Withstand
• Over-voltage is applied to verify external insulation and dielectric strength
• 28 kV voltage was applied for 60 seconds
• The FCL successfully endured the voltage withstand test of 28 kV ph-ph for 1 minute, as per Table 2 of IEC
60076-3, without voltage collapse
14
ASL 11 kV MFCL Factory Testing
AC Voltage Drop Versus DC Current
DC vs. AC
0
50
100
150
200
250
300
350
400
450
500
550
600
650
700
750
800
850
900
950
1000
1050
1100
1150
1200
1250
1300
1/7/
11 5
:02
PM
1/7/
11 5
:16
PM
1/7/
11 5
:31
PM
1/7/
11 5
:45
PM
1/7/
11 6
:00
PM
1/7/
11 6
:14
PM
1/7/
11 6
:28
PM
1/7/
11 6
:43
PM
1/7/
11 6
:57
PM
1/7/
11 7
:12
PM
1/7/
11 7
:26
PM
1/7/
11 7
:40
PM
1/7/
11 7
:55
PM
1/7/
11 8
:09
PM
1/7/
11 8
:24
PM
1/7/
11 8
:38
PM
1/7/
11 8
:52
PM
1/7/
11 9
:07
PM
1/7/
11 9
:21
PM
1/7/
11 9
:36
PM
Date and Time
AC
Cu
rren
t [A
rms]
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
DC
Cu
rren
t [A
]
AC
Vo
ltag
e D
rop
[V
rms]
ASL-12kV.ASL_AcInfo.PhaseACurrent
ASL-12kV.ASL_HtsCoil1.Current
ASL-12kV.ASL_AcInfo.PhaseAVoltage
15
ASL 11 kV FCL Factory Testing
Typical HTS Coil Temperature Rise
HTS COIL 2 - BOTTOM FCL
15
16
17
18
19
20
21
22
23
24
25
1/7/
11 5
:02
PM
1/7/
11 7
:26
PM
1/7/
11 9
:50
PM
1/8/
11 1
2:14
AM
1/8/
11 2
:38
AM
1/8/
11 5
:02
AM
1/8/
11 7
:26
AM
1/8/
11 9
:50
AM
1/8/
11 1
2:14
PM
1/8/
11 2
:38
PM
1/8/
11 5
:02
PM
Date and Time
Cry
og
enic
s T
emp
erat
ure
s [k
]
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
Cu
rrre
nt
and
Vo
ltag
e [A
rms,
Vrm
s]
ASL-12kV.ASL_HtsCoil2.LsTemp1
ASL-12kV.ASL_HtsCoil2.LsTemp2
ASL-12kV.ASL_HtsCoil2.LsTemp3
ASL-12kV.ASL_HtsCoil2.LsTemp4
ASL-12kV.ASL_HtsCoil2.LsTemp5
ASL-12kV.ASL_HtsCoil2.LsTemp6
ASL-12kV.ASL_HtsCoil2.LsTemp7
ASL-12kV.ASL_HtsCoil2.LsTemp8
ASL-12kV.ASL_AcInfo.PhaseACurrent
ASL-12kV.ASL_HtsCoil1.Current
ASL-12kV.ASL_AcInfo.PhaseAVoltage
16
ASL 11 kV MFCL Factory Testing
AC Coil Temperature Rise
AC Windings and Oil Temperature Rise
0
20
40
60
80
100
120
140
1/7
/11
2:2
4 P
M
1/7
/11
7:1
2 P
M
1/8
/11
12
:00
AM
1/8
/11
4:4
8 A
M
1/8
/11
9:3
6 A
M
1/8
/11
2:2
4 P
M
1/8
/11
7:1
2 P
M
1/9
/11
12
:00
AM
1/9
/11
4:4
8 A
M
1/9
/11
9:3
6 A
M
Te
mp
era
ture
[C
]
ASL-12kV.ASL_AcTank.Temp1
ASL-12kV.ASL_AcTank.Temp10
ASL-12kV.ASL_AcTank.Temp2
ASL-12kV.ASL_AcTank.Temp3
ASL-12kV.ASL_AcTank.Temp4
ASL-12kV.ASL_AcTank.Temp5
ASL-12kV.ASL_AcTank.Temp7
ASL-12kV.ASL_AcTank.Temp9
17
High-Power Testing at KEMA Powertest, Chalfont, PA
18
First-Round Design and Special Acceptance Testing
Testing conducted 15-17 February 2011, KEMA Powertest, Chalfont, PA
One load circuit calibration shot
Seven fault circuit calibration shots
Six load through test device shots
Nine fault through test device shots
Varying DC bias currents, fault duration (12.5 cycles and 3 seconds – 150 cycles) and with and without load
current
Four additional transient recovery voltage tests were performed – two with the test device in the circuit and two
with equivalent three-phase air-core reactors in the circuit
Test results were mixed:
Outstanding HTS DC performance during three-second event
Satisfactory DC saturation and acceptable insertion impedance voltage drop at rated current
Generally acceptable fault limiting results – about 13.8 – 13.9 kA best performance due to bolted versus
grounded fault
Failed post-test HV testing – partial discharge detected on bushing during 28 kV voltage withstand test
19
Test Setup
11 kV MFCL Test Set-Up
MB Master Breaker
ABUB Auxiliary Back Up Breaker
MS Making Switch
AUX Auxiliary Breaker
20
-0.05 0 0.05 0.1 0.15 0.2 0.25 0.3
-15
-10
-5
0
5
10
15
TEST 16 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhA asymmetry
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
I prospective
Ia Limited
Ib Limited
Ic Limited
11 kV MFCL Test - Three-Phase Fault, 250 ms
-0.05 0 0.05 0.1 0.15 0.2 0.25 0.3
-5
0
5
10
15
TEST 16 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhA asymmetry
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
I prospective
I Limited - 90A DC Bias
21
Grounded versus Bolted Fault Limiting Performance
22
Test Results – 3 second fault
0 0.5 1 1.5 2 2.5 3-15
-10
-5
0
5
10
15TEST 22 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry - Reverse Polarity 3s
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
Ia 90A DC Bias
Ib 90A DC Bias
Ic 90A DC Bias
11 kV MFCL Test – Three-Phase Fault, 3 Seconds
23
Test Results – 3 second fault
0 0.5 1 1.5 2 2.5 380
90
100
110
120
130
140TEST 22 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry - Reverse Polarity 3s
Time [sec]
DC
CU
RR
EN
T [
A]
I HTS1 90A DC Bias
I HTS2 90A DC Bias
11 kV MFCL Test – DC Current During 3-Second Fault
24
Test Results – 3 second fault
0 0.5 1 1.5 2 2.5 3-6
-5
-4
-3
-2
-1
0
1
2TEST 22 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry - Reverse Polarity 3s
Time [sec]
DC
VO
LT
AG
E [
V]
V HTS1 90A DC Bias
V HTS2 90A DC Bias
V HTS Total 90A DC Bias
11 kV MFCL Test – DC Voltage During 3-Second Fault
HTS Voltage is 4 V during 3-second fault
25
B-Phase HV Bushing Failure
11 kV MFCL Test – AC Voltage Withstand Test
26
ASL 11 kV MFCL – Original Bus-Work Configuration
27
ASL 11 kV MFCL – Maximum Bus-Work Forces FEA
28
ASL 11 kV MFCL – Upgraded Bus-Work Concept
29
ASL 11 kV MFCL – Upgraded Bus-Work as Installed
30
ASL 11 kV MFCL – Detail of Flex Connectors
31
MFCL TRV Effects Testing
Analytical studies and full-power testing suggest that MFCLs have significantly lower impact on circuit-breaker TRV
compared to an equivalent air-core series reactor
Fast transient oscillations in the TRV due to a combination of low capacitance and high inductance are reduced
It should be possible to install MFCLs in circuits without incorporating TRV mitigation measures such as external
capacitors
32
ASL 11 kV MFCL Post-Repair Retest
Complete retest performed week of September 26, 2011
Acceptance and special test protocol modified to add additional, more rigorous tests
HV test regime performed before and after fault testing
Four Short Circuit Calibration tests performed (One per phase plus a three-second prospective)
Six Fault tests performed (Two per phase, maximum asymmetry on each phase, and reverse polarity)
Five 250 ms fault tests
One 3-second fault test
Verified pre-fault load current, insertion impedance, and post-fault recovery
All tests completed satisfactorily
Post-test inspection inside tank (lid-off) confirmed mechanical fastener and structural integrity
Voltage-drop, load, fault limiting and other tests were virtually identical to first-round test results
No change in voltage drop insertion impedance (100 V at 1.25 kA)
No change in fault limiting performance
33
Revised Test Protocol for Post-Repair Retest
34
Short Circuit Tests – Comparison Set 1 vs. Set 2
Set 1 - February 2011 Set 2 - September 2011
0 0.5 1 1.5 2 2.5 3-15
-10
-5
0
5
10
15TEST 22 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry - Reverse Polarity 3s
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
Ia 90A DC Bias
Ib 90A DC Bias
Ic 90A DC Bias
0 0.5 1 1.5 2 2.5 3-15
-10
-5
0
5
10
15TEST 13 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
Ia 110A DC Bias
Ib 110A DC Bias
Ic 110A DC Bias
-0.05 0 0.05 0.1 0.15 0.2 0.25 0.3
-5
0
5
10
15
TEST 16 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhA asymmetry
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
I prospective
I Limited - 90A DC Bias
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35
-5
0
5
10
15
TEST 8 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhA asymmetry
Time [sec]
LIN
E C
UR
RE
NT
[kA
]
Iprospective
Ia 110 DC Bias
35
0 0.5 1 1.5 2 2.5 3100
110
120
130
140
150TEST 13 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry
Time [sec]
DC
CU
RR
EN
T [A
]
I HTS1 110A DC Bias
I HTS2 110A DC Bias
0 0.5 1 1.5 2 2.5 380
90
100
110
120
130
140TEST 22 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry - Reverse Polarity 3s
Time [sec]
DC
CU
RR
EN
T [
A]
I HTS1 90A DC Bias
I HTS2 90A DC Bias
0 0.5 1 1.5 2 2.5 3-6
-5
-4
-3
-2
-1
0
1
2TEST 22 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry - Reverse Polarity 3s
Time [sec]
DC
VO
LT
AG
E [
V]
V HTS1 90A DC Bias
V HTS2 90A DC Bias
V HTS Total 90A DC Bias
0 0.5 1 1.5 2 2.5 3-5
-4
-3
-2
-1
0
1
2
3TEST 13 - ASL 11kV FCL - FAULT LEVEL 17 kApeak 6.2 kArms Prospective - PhC asymmetry
Time [sec]
DC
VO
LT
AG
E [V
]
V HTS1 110A DC Bias
V HTS2 110A DC Bias
V HTS Total 110A DC Bias
Short Circuit Tests – Comparison Set 1 vs. Set 2
Set 1 - February 2011 Set 2 - September 2011
36
Summary
Testing conducted 15-17 February 2011, KEMA Powertest, Chalfont, PA
Initial test results were generally satisfactory, but acceptance testing failed due to HV
retest failure (cracked bushing)
Bushing failure traced to excessive bus-work forces during faults
Rework of bus design to strengthen bus-work and isolate bushing terminations from loads
Retest 26-28 September 2011 successful – MFCL accepted by client