Asia Cell MPR Swap Project Prepared by :Ahmed Abdulqader Abdulla

Upload: ahmad-abdulqader

Post on 12-Apr-2017

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Asia Cell MPR Swap Project

Asia Cell MPR Swap ProjectPrepared by :Ahmed Abdulqader Abdulla

Page 2: Asia Cell MPR Swap Project

1-Project preparations

:2-Project scope

Project drama

Page 3: Asia Cell MPR Swap Project

>Customer training.>Customer Quality Installation Standard.

>Trail links.>The management skills & tools

>The coordinating.

:Project preparations

Page 4: Asia Cell MPR Swap Project

customer edifying about ALU products, solutions and new concepts.

>Customer training

Page 5: Asia Cell MPR Swap Project

Note: refer to Quality Installation Standard for Asiacell MW Swap.PDF

>Customer Quality Installation Standard

Page 6: Asia Cell MPR Swap Project

Prototype link installed under customer direct supervising.

>Trail links

Page 7: Asia Cell MPR Swap Project

*Study of the local market (sub-contractors qualifications).

*Study of local market (minor shortages of accessories materials ).

*Local environment(unstable security status of Iraq) . *Psychological study of customer and the regional

ALU employees. *Planning to next project and Future expansion .

*management office tools.

>The management skills & tools

Page 8: Asia Cell MPR Swap Project

M-Excel hyperlink with:

#Google Earth. #TSSR.

#LOS. #PAT documents .

*management office tools

Page 9: Asia Cell MPR Swap Project

Sites coordinates ,links paths, rings

#Google Earth

Page 10: Asia Cell MPR Swap Project

Elevations profile

#Google Earth

Page 11: Asia Cell MPR Swap Project

-dynamic charts M-Excel

Page 12: Asia Cell MPR Swap Project

Choosing smart and professional ALU coordinators specially with the customer.

>The coordinating

Page 13: Asia Cell MPR Swap Project

*TSSR: Technical Site Survey Report.*LOS: Line Of Sight.

*Logistic.*I & C : installation & Commissioning.

*PAT: Preliminary Acceptance.*PAT documents*Dismantlement.

:2-Project scope

Page 14: Asia Cell MPR Swap Project

Site info: site name,IDs,coordinates,access,delivery methods, contact person for accessing/Tel,site owner name/Tel,indoor(layout,photos and all the needed info),outdoor(layout,photos and all the needed info),Data of the required materials.

*TSSR: Technical Site Survey Report

Page 15: Asia Cell MPR Swap Project

All the needed Data for: (.LB(link budget) & MR(required materials

list

*LOS: Line Of Sight

Page 16: Asia Cell MPR Swap Project

>Delivering the required materials according to (the technical survey and on time(according to the plan deadlines).

>receiving signed MR from sub-contractors as(handover confirmation).

Logistic

Page 17: Asia Cell MPR Swap Project

According to:>The customer Quality Installation Standard

for (Asiacell MW Swap Projects.>ALU quality Standard.

I & C :installation & Commissioning

Page 18: Asia Cell MPR Swap Project

AsiaCell must be attendant.

PAT: Preliminary Acceptance

Page 19: Asia Cell MPR Swap Project

1-Link Budget2-Link Configuration

3-Link Performance4-Packet Drop

5-XPIC6-Interference test

7-ALU PAT Check List8-MPR TI Quality Checklist Phase-III B SWAP

PAT documents

Page 20: Asia Cell MPR Swap Project

the process should be fast, clean and according to the customer recommendations or form .

Dismantlement