environmentclearance.nic.inenvironmentclearance.nic.in/writereaddata/modification/previoustor… ·...
TRANSCRIPT
AMENDMENT IN ENVIRONMENTAL CLEARANCE
(No.J.11011/365/2006-IA.II (I) dated 22-2-2007
and amendment dated 14-11-2008)
FOR
CHANGE IN STEEL MAKING PROCESS TECHNOLOGY
&
CHANGE IN PLANT LAYOUT
AT KERJANG, DISTRICT ANGUL, ORISSA
JINDAL STEEL & POWER LIMITED
FEBRUARY 2013
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 2
CONTENTS
Contents
Page Number
1.0 Background Information 3
2.0 Suggested Changes / Amendments in EC 4
2.1 Changes in Steel Making Technology 5
2.1.1 Justification for Changes in Steel Making Technology 5
2.2 Changes in Plant Layout 6
2.2.1 Justification for Changes in Plant Layout 9
3.0 BOF Convertor Process of Steel Making 10
3.1 Pollution Control System 27
3.2 Gas Recovery System 37
3.3 Material Balance 39
4.0 Water Balance and Management Scheme 40
5.0 Air Emission Control and Load Calculations 40
6.0 Solid Waste Generation and Load Calculation 43
7.0 Pollution Load Statement 45
8.0 Conclusion 47
Appendix 1 Copy of EC Letter obtained from MOEF 48
Appendix 2 Plant Layout Submitted to MOEF in July 2011 Back Pouch
Appendix 3 Now Proposed Revised Plant Layout Back Pouch
Appendix 4 Proposed Layout of SMS Back Pouch
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 3
1.0 Background Information
Jindal Steel & Power Limited (JSPL) is constructing a 6.0 MTPA Integrated Steel
Plant and 1142 MW Captive Power Plant at village Kerjang, District Angul in
Orissa. Environmental Clearance for the project was granted by the Ministry of
Environment & Forests, Government of India (MoEF) vide letter
No.J.11011/365/2006-IA.II (I) dated 22-2-2007 and amendment dated 14-11-
2008. [copy of the EC letter is given in Appendix 1)
The name of the units for which EC has been obtained from Industry Committee
and proposed amendment is shown in Table below:
Name of the Unit
Name of Product
Unit Capacity as mentioned in EC
Amendment Sought from MOEF
1 Pellet Plant Iron ore pellets MTPA 5.0 -- 2 Coal Gassifiers Coal gas Nm3/year 4000 x 106 -- 3 DRI Plant
(Gas based) Sponge iron MTPA 4.0 --
4 Blast Furnace Pig Iron MTPA 3.2 -- 5 Coke Oven &
Byproduct Plant Coke MTPA 2.0 --
6 Sinter Plant Sinter MTPA 4.0 -- 7 Steel Melting
Shop Steel MTPA 6.0 3.0 MTPA based
on EAF route 3.0 MTPA based on BOF route
8 Rolling Mill Steel Product MTPA 6.0 -- 9 Ferroalloy Plant Ferroalloys MTPA 0.08 -- 10 Lime-dolime
Plant Lime / Dolime TPD 3000 --
11 Process Gas/ Pressure Recovery Turbine*
Electricity MW 62 --
12 Coal based Power Plant
Electricity MW 1080 (8x135 MW)
--
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 4
Note: i) In addition to above main units, 7200 TPD Oxygen Plant was also
proposed in Form 1 Application and EIA, which remains unchanged.
ii) For meeting the process steam, 3 x 180 TPH coal based steam boilers
were also proposed in Form 1 Application and EIA, which remains
unchanged.
*iii) 2 x 15 MW mixed gas based turbines, 14 MW blast furnace top gas
pressure recovery turbines and 2 x 9 MW coal gas pressure recovery
turbines
In addition to above, JSPL has taken the Environmental Clearance for 6.5
MTPA coal washery inside the same premises vide letter no. J-
11015/1015/2007-IA.II (M) dated 13th October 2009 (From Coal Mining
Committee). This unit remains unchanged.
JSPL has also submitted application to establish 4 MTPA coking coal
washery and 6.5 MTPA non-coking coal washery inside the same
premises and obtained TOR for conducting the EIA study (From Coal
Mining Committee). This proposal remains unchanged.
2.0 Suggested Changes / Amendments
Following changes are proposed for approval of the Expert Appraisal Committee
(Industry) of MOEF
1. Change in Steel Making Technology, keeping the steel production same.
Also to modify the configuration of casters and rolling mills, while capacity
keeping same at 6 Mtpa each.
2. Change in Plant Layout keeping the total plant area same. .
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 5
2.1 Change in Steel Making Technology
The 6 MTPA SMS process was entirely based on Electric Arc Furnace Route,
comprising 3 x 200 tons capacity EAF (2 vessels in each Conarc type furnace,
totaling to 6 vessels) and 6 x 200 tons capacity Laddle Refining Furnace (LRF)
and 2 x 200 tons RH-TOP for production of special quality slabs has been
proposed. Conventional slab casting technology comprising 3 x 1 strands and 1 x
1 strand casters has been proposed.
Now the 6 MTPA SMS process has been bifurcated into Electric Arc Furnace
Route and Basic Oxygen Furnace Route. 2 x 250 tons capacity EAF shall be
established to produce 3 MTPA Steel. 2 x 250 tons capacity BOF shall be
established to produce 3 MTPA Steel. The capacity of LRF, RH-TOP and Slab
Caster have also been updated accordingly to suit the heat size of 250 tons.
Regarding the Casters, a total of 4 Slab casters (all single strand) were planned
earlier with a total output of 6 Mtpa. Now also the no. of casters will remain same
at 4 with 6 Mtpa output. Configuration will be:
a) One Slab Caster (1 strand)
b) Two Thin Slab Casters (1 strand each)
c) One Billet Caster (8 strand)
The Plate Mill shall also have facilities for the heat treatment with total capcity
of325000 TPA and cold leveller to produce plates of high quality. Two heat
treatment furnaces shall use the clean syn gas produced at coal gasification
plant as a fuel and the exhaust will be vented through the stacks of atleast 30 m
height. As for Rolling Mills, the existing clearance is for 6 Mtpa with a
configuration of one Plate Mill with a capacity of 1.5 Mtpa capacity and One Hot
strip mill with the balance capacity. New Capacity shall remain 6 Mtpa and the
configuration shall be:
a) One Plate Mill of 1.5 Mtpa capacity
b) One Hot Strip Mill (Compact Strip Type) of 3.1 Mtpa capacity
c) One Bar Mill of 1.4 Mtpa capacity
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 6
It may be mentioned here that, change in configuration has been done keeping
the capacity same as the existing EC and the emission levels for solid, liquid and
gaseous wastes will not exceed the emission levels w.r.t. existing configuration of
Casters and Rolling Mills.
2.1.1 Justification for Change in Steel Making Technology
Steel making using the Electric Arc Furnace route is economically viable when
plenty of cheap scrap is available in the market. This scrap is mixed with Hot
Metal and Sponge Iron in EAF to produce steel. Since more scrap and sponge
iron is used in EAF, the electricity consumption is significant.
In the present scenario at JSPL Angul, the Hot Metal availability from Blast
Furnace is more than sufficient to mix some sponge iron and produce steel using
the BOF route. Oxygen lancing in BOF will generate gases having high calorific
value due to suppressed combustion. Power consumption is about 85% lower in
BOF compared to EAF. This ensures production of steel at low cost.
In EAF route the exhaust gases coming out of the furnace are discharged into
the atmosphere after capturing it using hood and cleaning in Bag Filter. In the
BOF Route the exhaust gases have very high Carbon Monoxide (upto 50%),
resulting in very high calorific value (about 2000 kcal/Nm3) of gas, which could be
suitably used in the Reheating Furnaces, thereby reducing the Furnace Oil
consumption. The flue gas of BOF convertor shall be treated using Dry Process
through Electrostatic Precipitators. Any unutilized portion of the BOF Gas shall
be flared using suitably designed flare stack, ensuring soot less flare.
Environmental Benefits of BOF : Low air pollution because of higher content of
hot metal as input, low slag generation (11.8% in BOF compared to about 22% in
EAF because of lower content of sponge iron as input) and possibility of energy
recovery from exhaust gas (because of use of higher oxygen lancing and
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 7
resultant suppressed combustion). The yield of liquid steel from metallics using
BOF route is about 90% compared to about 85% using EAF Route.
2.2 Change in Plant Layout
As per the MOU signed between JSPL and the Govt of Orissa, about 6000
acres land has been identified to establish the project. As per the MOU,
IDCO would purchase the land and hand over to JSPL. The break-up of
the land as given in the EIA Report (August 2008) is as follows.
S.No Name of the Unit
Land requirement as given in the EIA Report 2008
(in hectares) 1 Coal Gasification Unit 159.41 2 Steel Plant 639.19 3 Power Plant 253.99 4 Common Facility 112.12 5 Ash Pond & Dump Yard 245.5 6 Water Reservoir 101.17 7 Approach Roads 21.63 8 Railway Yard 105.04 9 Green Belt 368.66
10 Mics Uses 153.675
TOTAL 2160.385 ha
(5338.341 Acres)
Subsequently, during the detailed engineering, the land requirement has
been further optimized to 2016.787 ha. The same has been communicated
to the MoEF along with the layout map showing 33% green belt as per the
EC condition vide JSPL letter dated 10th January 2011. The break-up of
the revised land requirement as submitted to MOEF on 10-1-2011 is as
follows:
Name of the Unit Land requirement in ha A PLANT AREA
Coal Gasification Unit 89.279 Steel Plant 608.753 Power Plant 197.454
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 8
Common Facility 85.231 Ash Pond & Dump Yard 183.669 Water Reservoir 84.617 Green Belt 621.041 Sub Total (A) 1870.044 B OUTSIDE PLANT AREA Land requirement in ha
Approach Roads 20.627 Railway Yard 105.04 Water Pipe Line 21.076
Sub Total (B) 146.743
TOTAL2016.787 ha (4983.48 ac)
Meanwhile the High Level Clearance Committee of Government of Orissa
further optimized the land requirement of the project to 1753.3 ha, which
includes 1416.4 ha for core plant area, 128.7 ha for township, 35.8 ha for
offsite facilities like intake water pump house, water pipeline and coal
conveyor corridor and 157.5 ha for developing the railway siding.
Based on this the core plant layout has been again optimized to 1416.4
ha. This has been has been communicated to the MoEF vide letter dated
26th July 2011 along with the revised Layout Plan.
The Plant Layout submitted to MOEF on 26th July 2011 is shown in Appendix 2 .
JSPL received the lease document of the entire 1416.4 ha land. As on date
physical possession of 867 ha land is available with JSPL where the project
construction work is going on. Considering the fact that physical possession of
the balance land will take more time than anticipated and therefore to meet the
scheduled commissioning target, revision of plant layout has become inevitable.
However the total land for setting up the core plant will remain1416.4 ha, as
already furnished to MOEF.
The now proposed revised land break-up is shown below:
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 9
Name of the Unit
Land Requirement (in hectares)
Now Proposed A PLANT AREA
Coal Gasification Unit 63.7 Steel Plant 415.7 Power Plant 116.8 Common Facility 90.4 Ash Pond & Dump Yard 183.7 Water Reservoir 78.8 Green Belt 467.3
Sub Total (A)1416.4 ha
(3500 acres) B OUTSIDE PLANT AREA
Approach Roads & Water Pipe Line 35.8 Railway Yard 157.4
Sub Total (B) 193.2 ha
TOTAL1563.043 ha
(3860.7 acres)
The now proposed revised Plant Layout based on above Table is shown in
Appendix 3.
2.2.1 Justification for Change in Plant Layout
1.2 MTPA Plate Mill and 4 x 135 MW Captive Power Plant is already
commissioned. Coal washery and lime plant shall be ready for commissioning
soon. Coal Gasification Plant, Gas based DRI Plant and Steel Making Shop (EAF
Route) are ready for commissioning in March 2013. The following Table shows
the various stages of construction of the Integrated Steel Plant:
Sl. No
Plant Status
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 10
1 Power Plant
(8 x 135 MW)
4 units are already commissioned. 2 Units are in advance stage of construction.
2 Coal Gasification Plant
(14 Gassifiers)
7 Gassifiers are in advance stage of construction and will be ready by March 2013.
4 DRI (gas based)
(2 x 2 MTPA)
1 unit of 1.8 MTPA capacity is in advance stage of construction and will be ready by March 2013.
5 Oxygen plant
1200 TPD plant is in advance stage of construction and will be ready by March 2013.
6 Lime and dolime plant
1000 TPD is in advance stage of construction and will be ready by February 2013.
7 SMS 1.5 MTPA SMS is in construction and will be ready by March 2013.
8 Plate mill 1.2 MTPA Plate Mill commissioned and started commercial production based on the steel slabs brought from Raigarh Plant of JSPL
9 Structural Beam Plant
A structural beam making plant based on automatic welding machines have been installed to produce 7000 MT of structural steel to meet the internal need of the project construction work
10 Automatic plant for making fly ash based construction product
An imported fly ash based construction materials plant has been commissioned to produce fly ash bricks, concrete panels, kerbstones, etc
11 Raw material handling section
Raw material handling system for the power plant has been commissioned.
RMH Yard for the steel plant is under advance stage of construction and will be ready by March 2013.
12 Process steam boiler One unit of 180 TPH process boiler is ready for commissioning
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 11
JSPL decided to shift the blast furnace, pellet plant, coke oven and sinter plant
from the west side to east side and shift the ash pond from east side to west side
of the plant layout. This will enable JSPL to immediately start constructing the
remaining units and synchronize them with the units that are ready for
commissioning.
3.0 BOF Pro cess of Steel Making
Hot Metal Handling
Hot Metal will be delivered to the BOF shop via Torpedo Ladles. Re-ladling into
the hot metal charging ladles takes place at the reladling pits while charging
ladles are brought via transfer cars. The ladle will then be picked up by EOT
crane and placed on the transfer cars at HMDS for pre-treatment of hot metal in
the desulphurisation station. For accurate weighing of the hot metal being
charged into the ladle from the torpedoes, weighing arrangement is provided in
the charging ladle transfer cars as well as in the EOT cranes.
Hot Metal Desulphurisation Process Description
To meet the increasingly stringent demand for higher quality steels, it is the
intention of JSPL to install hot metal desulphurisation facilities to treat the liquid
hot metal between the blast furnace and the BOF Convertor. The hot metal will
be desulphurised by the deep injection of a combination of desulphurization
agents.
The layout for phase 1 will consist of one twin unit (1 x twin station). The powder
system will be serviced by its own powder storage facility. Future provision for
ECO injection with lime will be allowed for in the layout. Each station will be
equipped with deslagging and fume extraction facilities.
Hot metal is desulphurised in the transfer ladle by the injection of a mixture of
calcium carbide and magnesium, through a refractory coated immersed lance.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 12
There are two possible injection combinations of the desulphurisation reagents
including calcium carbide on its own (mono-injection) and calcium carbide and
magnesium in combination (co-injection).
Prior to treatment, the weighed hot metal transfer ladle is placed on a ladle
transfer car (with a combined tilting frame) by the overhead ladle handling crane.
The ladle car is driven inside the refractory faced enclosures, which are sealed
when the ladle is inside the enclosure by a wall mounted on the car.
A sample taken from the transfer ladle prior to treatment is analysed, and the
result is used to calculate the amount of lime, calcium carbide and magnesium
required to achieve the necessary amount of desulphurisation. The calculation is
done automatically by the control system, once the initial and required final
sulphur levels are known. The injection lance, which is a thick walled steel tube
inside a refractory coating, is positioned above the ladle, and then lowered
through a port in the enclosure cover.
Co-injection proceeds as follows:
Before the tip of the lance enters the hot metal surface, the powder transport gas
is switched on, and then the calcium carbide powder begins to flow though the
lance. Once powder flow is established, the lance is driven down into the hot
metal to a predetermined position above the refractory bottom of the ladle.
During injection the actual rate of injection is measured by the load cells on which
the powder injection dispensers are mounted, and calculated by the control
system. The actual achieved injection rate is compared with the required rate on
a continuous basis. Any difference between the measured rate and the required
rate is used to drive the material flow control valves below the dispensers. These
valves open or close automatically to increase or decrease the actual rate of
injection in order to maintain the preset rate.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 13
When the lance has reached its fully immersed position, magnesium is
introduced into the powder stream. As the magnesium begins to be injected, the
rate of calcium carbide injection is automatically reduced, so that the total rate of
material injection remains constant.
When all the required magnesium has been injected, the rate of calcium carbide
injection increases again, back to the original figure. When all the calcium
carbide to be injected approaches its end figure, the lance begins to retract and
leaves the surface of the hot metal as the last of the powder is being blown.
Powder flow is established before the lance enters the hot metal and maintained
until the lance leaves the hot metal to prevent blockage of the lance tip.
All the required measured values are displayed on the VDUs in the control room.
Control of the injection process is automatic once initiated by the operator.
When all the powder has been discharged from the lance, the transport gas
continues to flow for a short period of time, to ensure the powder line is clear,
and then shuts off.
The lance is retracted to its top position, and the lance port in the fume enclosure
hood is sealed by an actuated sealing flap. The lance unit also incorporates an
automatic sampler, which can be used to take a temperature measurement, or a
two in one type chemical and temperature sample, through the port in the fume
enclosure hood.
When injection is complete, the carry-over slag plus the slag formed on top of the
ladle during injection is removed by a slag skimming machine.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 14
This is done by rotating the ladle in its tilting frame on the transfer car. To
achieve this movement, a pair of hydraulic cylinders lift the tilting frame at one
side tilting the ladle over the slag pot.
The angle of ladle rotation is variable, depending on the ladle freeboard. Slag is
removed from the hot metal surface over the rear lip of the ladle by a slag
skimming machine. Each treatment station has its own slag skimming machine.
Slag is collected in slag pots placed on the slag pot transfer car within the
enclosure. Once a slag pot is filled up a slag pot car will transfer the same to the
slag yard where the filled-up slag pot will be emptied and an empty slag pot will
be picked up for transport to the deslagging position.
At the end of the deslagging process the ladle is rotated back to its vertical
position by the hydraulic cylinders.
Throughout the injection and deslagging process fume generated is removed
from the enclosures by extraction ducting connected back to the secondary fume
system.
After injection and deslagging, a sample is taken from the ladle. The ladle
transfer car is then driven to its parked position and the ladle removed by the
overhead crane and transferred to the furnace.
Each station is equipped with independent injection dispensers, one for calcium
carbide and one for magnesium. These dispensers are refilled between
treatments. Refilling can be done automatically, or by operator selection. In either
case the process is as follows.
First the dispenser is depressurised. Powder material, calcium carbide or
magnesium as required, is then pneumatically transferred from the transport
dispensers below the three main storage silos to the injection dispensers.
Material is transferred in fixed batches, and refilling continues until the injection
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 15
dispenser contents reach a preset high level, or the operator overrides the
process.
Control and monitoring of the injection and refill process is from the central
control room.
Scrap Handling
The scrap mix to be charged as a coolant into the converter shall consist of
return scrap. The above shall be handled in the scrap yard where a scrap loading
crane is available for loading scrap from the storage boxes into one of the scrap
chutes. The chutes shall be placed on mobile scrap chute transfer car. After
transfer to the charging bay, the scrap will be charged into the converter by
cranes.
Material Handling System
Flux Charging System
Flux material for converters will be taken over at the top of flux bunkers within the
steel making plant for further distribution into the different bins.
Charging System for Fluxes and Coolants
From the high level bin system including vibrating feeders, weighing hoppers,
chutes etc. the material is charged into the converters, mainly fluxes such as
burnt lime, raw dolomite, burnt dolomite as well as iron ore and / or DRI for
cooling purpose.
Ferro Alloy Charging System
Ferro alloys shall be transferred from outside the plant to the storage bins for
tapping additions by means of conveyor system. From here the ferro alloys will
be fed into the ladle by means of vibrating feeders, weigh hoppers, belt
conveyors etc. The addition system for daily storage of alloys to be charged into
each ladle during tapping is designed for the main amount of additions (approx.
80 – 90 %).
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 16
BOF Converter Plant
The 2 BOF converters will be designed including all facilities (e.g. oxygen
blowing equipment, off gas system, bin system etc.) for parallel operation of 2
converters. Downtimes have to be considered for relining. During relining,
production can be performed by single vessel operation.
Two water cooled lances (one operating and one standby) will be provided for
each converter. The bottom will be equipped with an inert gas stirring system.
The converters will operate with slag free tapping systems. Self propelled steel
transfer cars as well as slag pot transfer cars have to handle the liquid material.
The above conditions require a hot metal input of about 80%, cooling will be
provided by mainly scrap charged via scrap chute as well as DRI / iron ore
feeding via bin system. The required fluxes for slag formation will mainly consist
of burnt lime and burnt dolomite. The combined blowing practice will be
favourable for handling the increased phosphorous content of the hot metal and
allows blowing with only one slag.
The converter will be operated with a top lance for oxygen blowing and with
bottom stirring of inert gases. The typical advantage of such combined blowing
technique will be the close approach to the equilibrium of metallurgical reactions
and the resulting smooth blowing process and benefits of material yield.
The liquid steel will be tapped slag free from the BOF, in order to eliminate the
negative influence of the furnace slag (FeO, MnO) during further processing and
casting of the steel. The required deoxidation materials, the slag forming
additions as well as deoxidation agents and ferro alloy additions (approx. 90 % of
the required amount) will be added during tapping. The ladle is stirred during and
after tapping for homogenisation purposes. For this 2 nos. on-line Argon Rinsing
Stations (ARS) are installed.
The ladle will be transferred to the Ladle Furnace Stations and will be positioned
into one of the Ladle Transfer Cars.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 17
Ladle Furnaces
The Ladle Furnaces (LF) are designed as a single station furnaces.
Description of LF Process
Main features of the LF process are:
• Ladle with liquid steel is placed onto the ladle transfer car.
• Bottom purging system gets automatically connected by means of auto
couplers and purging started.
• Transfer car with ladle is positioned below ladle roof (after necessary
interlocks are satisfied).
• Ladle roof is lowered
• Steel temperature is measured and sampling done by means of
automatic or manual lance through the opening in the ladle roof.
• Arcing is started in lower taps
• Necessary quantity of calcined lime is added through the FAFA system
• Trimming alloys are added as per grade and sample analysis requirement
• Sample is taken for final analysis
• Arcing is shifted to higher taps and done as per final aim temperature
• Wire feeding is done as per requirements
• Arcing is stopped, roof lifted and ladle transferred out from treatment
position and lifted by EOT crane
General Description of Ladle Furnace plant
The Ladle furnace plant is designed for three-phase connection to the high-
voltage power supply. The furnace transformer with upstream high-voltage
switchgear plant, the hydraulic station and the low-voltage switchgear cabinet
with control cubicle are arranged near the furnace i.e., in the immediate vicinity of
the furnace.
The furnace is equipped with a roof, which has provision for lifting and lowering
by 3 brackets actuated by hydraulic cylinders. For automatic / manual
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 18
temperature measurement, sampling and visual inspection / manual additions the
roof has a sliding working door which can be opened / closed by means of a
pneumatic cylinder.
The electrodes move up and down by means of hydraulically actuated
mechanism. The electrodes are clamped by clamping devices provided in the
electrode arms, which are in turn supported by electrode columns. The electrode
columns are guided by means of electrode guiding system consisting of a set of
rollers. This guiding system ensures proper vertical movement of the electrodes
through the openings in the roof.
A central control panel is provided in the control room of the furnace. All
necessary controls (Level 1) are provided in the main control room.
Level 2 Technological Process Control System for LF
A level 2 process automation computer system is supplied.
The system is implemented in a manner that in case of computer failure or Level
1 - Level 2 link failure the ladle furnace operations can be continued with the
Level I system. All equipment and software will conform to internationally
accepted standards.
Major Safety features of Ladle Furnace
1. The PLC system does not allow arcing to take place unless the hydraulic
system, cooling water system & the fume extraction system is in healthy
and running condition
2. The Ladle placed on LF station for treatment cannot be taken out unless:
a) Electrodes are fully raised.
b) Temperature & Sampling lance is fully retracted
c) Roof is raised
3 In case of power failure or pumps ceasing to work, emergency water
system is provided to cool the LF roof for approx 30 mins.
4 In case of power failure following operations can be carried out with the
help of accumulator provided in the hydraulic system :
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 19
a) Electrode lifting
b) Roof lifting
5 Various protection relays have been provided in the HT systems to take
care of the fault conditions.
6 Various protection relays have been provided in the transformer for
protection against:
a) Oil surges
b) Gas formation
c) Over temperature winding, oil and water.
7. All the individual system i.e., FAFA system, wire feeder etc are interlocked
through software for safe sequential operation.
RH process
The basis of the recirculatory process is as follows:
A refractory lined vacuum vessel is equipped with two refractory lined nozzles,
attached to the bottom of the vessel.
Prior to the treatment, the vessel is lowered until the nozzles are immersed in the
molten steel to a predetermined depth in the ladle. The vacuum vessel is then
evacuated by a set of powerful vacuum pumps.
The atmospheric pressure on the surface of the liquid metal in the ladle forces
columns of liquid metal up the nozzles. Atmospheric pressure is capable of
supporting a column of liquid steel 1.4m in height.
To achieve the required movement of metal from the ladle into the vacuum
vessel and then back to the ladle, argon is used. The argon is injected through
small bore pipes into one of the two nozzles attached to the vessel bottom. The
effect of the argon is to lower the bulk density of the resulting mixture. This
causes an increase in the height of the liquid steel column local to the so called
`up leg’. The effect of this, plus the lift imparted to the steel by the rising argon
bubbles, is to produce a movement of liquid metal up the `up leg’, across the
hearth of the vacuum vessel, and down the `down leg’, back to the ladle. The
rate of metal recirculation is dependent on geometric factors such as the inner
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 20
diameter of the nozzles, and also the rate of argon injection. In practice,
recirculation rates of 100 tonnes/minute or more are achieved.
As the metal enters the vessel it is exposed to the low-pressure conditions within
the vessel. This encourages reactions that are pressure dependent, such as the
carbon-oxygen reaction. At lower pressures hydrogen is removed by diffusion
from the metal surface.
Alloying elements added under vacuum via the vacuum lock give high and
consistent recoveries due to the absence of atmospheric oxygen and the fact
that the metal surface within the JSPL Ltd. vessel is slag free. Additions made to
the vessel are dissolved and washed across the bath, down the `down leg’ and
back into the ladle. Homogenisation of the ladle contents can be achieved in less
than three minutes.
A colour TV camera is provided, mounted on the alloy addition chute flange to
enable the reaction in the vessel, and the alloys falling through the alloy port to
be observed. This also serves to monitor the start of any possible blockage in the
alloy chute.
To minimise temperature losses during treatment, the vessel refractory
temperature is maintained at 1350oc - 1450oc throughout the campaign. This is
done by the multi function lanceunit which passes through a port in the hot off-
take. The vessel refractory temperature is continuously monitored. A high vessel
temperature is important to prevent skulling.
The proposed unit will be a duplex installation, i.e. there will be two treatment
stations, with the vacuum system, the alloy addition system and vessel handling
& relining facilities being common to both. Each treatment station will have its
own transfer car, vacuum vessel with hot off-take & gas cooler, vacuum lock
arrangement, top lance, , etc.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 21
This configuration will help cut down the net cycle time of the overall unit to the
treatment time only, with all other activities of one treatment station like ladle
transfer & positioning, temperature measurement and sampling, calcium
treatment, etc. falling within the shadow of the degassing time of the other
treatment station.
Metallurgical
The major benefits of the vacuum treatment of un-killed steels are as follows:
By subjecting the liquid steel to a vacuum, the carbon-oxygen reaction is
encouraged to proceed further than it could possibly do at atmospheric pressure.
This is because the reaction is pressure dependent, and the product, carbon
monoxide, is continuously removed from the system. The oxygen content of the
steel is therefore reduced, prior to the addition of deoxidants. The lower initial
level of oxygen in the liquid steel means that less de-oxidants are required, and
fewer non-metallics are formed by reaction with residual oxygen.
The addition of de-oxidants such as aluminium in vacuum eliminates the
possibility of atmospheric oxidation, or immediate contact with slag. These
factors lead to a higher, and perhaps more important, more consistent recovery
of aluminium. The consequence is tighter control of aluminium content and the
confidence to aim for the lower end of the specification, both important
advantages in subsequent continuous casting.
Vacuum degassing is, in addition, an extremely efficient means of mixing and
homogenizing the ladle contents. Vigorous mixing promotes the agglomeration
and flotation of non-metallic inclusions, particularly alumina. Homogenisation of
he ladle contents produces very uniform Tundish temperatures, another
important advantage during continuous casting.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 22
The practice of vacuum decarburisation or vacuum carbon deoxidation, followed
by the addition of aluminium leads to a number of other benefits.
Low silicon levels can be achieved since the intimate mixing of aluminium and
ladle slag, which takes place during ladle additions at tap, is avoided. High
carbon ferro manganese can be added at tap, rather than the more expensive
low carbon grade.
The ability to produce low carbon or ultra low carbon grades by vacuum
decarburization takes an excessive wear load from the convertor, and opens up
new potential markets for extra deep drawing, single coat enamel, pearlite free
grades, etc. Ultra low carbon grades (if) cannot be produced without vacuum
degassing facilities.
Multi function top lance system
The multi function top lance system was developed by SMS Mevac. It offers a
much greater flexibility to the RH degassing process, and consists of a lance unit
which is located in a port in the hot off-take above the vessel, on the vertical
centre line of the vessel. The central bore of the lance ends in a specially
designed copper nozzle, designed to blow oxygen onto the steel in the vessel
during vacuum treatment. Oxygen blowing can be used for a variety of
metallurgical reasons, including increased decarburisation from higher initial
carbon levels, accelerated rates of decarburisation from normal initial carbon
levels and steel reheating in combination with aluminium. In this case, steel
reheat rates of more than 4oC/min net are easily achieved.
The inner oxygen blowing lance is surrounded by a water cooled outer jacket.
Between treatments, the fuel gas is blown down the inner oxygen tube and
combustion oxygen is blown down the annular gap between the oxygen tube and
the outer water cooled jacket. Oxygen and fuel gas mix at the lance tip to
produce an intense flame which maintains the vessel refractories at high
temperature.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 23
Gas flow rates are monitored and controlled to achieve preset rates of heating or
preset plateau temperatures.
The lance unit is located in a port in the hot offtake which incorporates a vacuum
tight seal. During normal operation the lance remains entered into the hot offtake
port, but is designed to be removed during hot offtake changing.
Procedure
There are two basic process routes, namely the so-called light treatment practice
and the full vacuum degassing practice. The operational procedure is similar in
both cases, but differs in detail.
The basic procedure is as follows:
The converter or furnace is tapped into a well preheated ladle (preheat 1000oc or
more). Although not extremely critical, the ladle slag depth should be limited, if
possible. During tap, additions of high carbon ferro manganese can be made, if
required, prior to light treatment. A sample is taken after tap.
The ladle is then transferred by the converter ladle car and shop crane to the
degassing unit transfer car. When the ladle arrives, the ladle freeboard is
measured and temperature and chemical sample taken with an automatic
sampler.
With the ladle positioned under the vacuum vessel, the vessel is then lowered
until the nozzles are immersed to a predetermined depth in the steel. This depth
is known from the freeboard measurement previously taken.
Before the vessel is lowered, the gas supply to the `up leg’ of the vessel is
switched from nitrogen to argon (nitrogen is used between treatments for
economic reasons). This is done automatically.
The argon flow is controlled at a predetermined rate. With the nozzles fully
immersed, and the argon being introduced into the `up leg’ at the predetermined
rate, the vacuum system is switched on. The pressure within the vessel begins to
fall, and is continuously monitored in the control room. A tv camera looking down
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 24
the alloy chute gives a picture of the metal flow through the vessel on a colour
monitor in the control room.
The degree of vacuum achieved depends on the length of the treatment, and the
combination of vacuum pumps selected. For a light treatment for example, a final
vacuum level of 50 mbar or more is adequate. This pressure can be achieved, if
required, by using only part of the full steam ejector vacuum system. The vacuum
level gradually falls as the gas is removed from the steel.
For low carbon steels, or for full degassing purposes, the various stages of the
steam ejector can be preselected and then switched in automatically at their
optimum preset operating pressures.
In the case of the light treatment practice, an oxy-temperature measurement is
normally taken from the ladle after a pre-set degassing time (about 3 minutes).
Aluminium is then added, based on the measured free oxygen content of the
steel. The required aluminium addition is composed of two components, one to
remove the remaining oxygen on a stochiometric basis, and the other to bring the
aluminium content within the analysis range.
Having added the aluminium, a second check oxy-temperature measurement is
taken after about 3-4 minutes mixing.
Any required carbon or ferro manganese addition will already be known from the
tap analysis, displayed in the control room.
In the cases where the temperature is too high for casting, coolant scrap can be
added during vacuum treatment as a rapid way of reducing temperature. The
scrap size must be the same as the ferro alloys, since it is added through the
same system. Coolant scrap should also be free of volatiles such as zinc.
At the completion of alloying, the vacuum vessel is flooded back to atmospheric
pressure. The vessel is then raised from the ladle, final samples are then taken,
before the ladle is transferred to the wire feeding station. At the wire feeding
station cored ca wire will be fed through a wire feeder along with soft argon
purging of the steel through the porous plug. Thereafter the ladle will be
transferred to the caster. The wirefeeder station will be provided with a fixed type
fume collection hood which will be connected to the shop dedusting system.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 25
For ultra low carbon grades, the full vacuum system is required to achieve final
vacuum levels of 1 mbar. In this case the treatment time is extended, and
deoxidants are not added until the vacuum pressure trace has levelled out,
indicating that the carbon-oxygen reaction is complete. During treatment the co
and CO2 content of the exhaust gases is monitored. The progress of
decarburisation can be assessed from the co content of the exhaust gases.
The procedure after vacuum decarburisation however, is similar to that for light
treatment.
Start conditions:
For self decarburization
Initial tap carbon levels up to 0.050% are acceptable for final carbon levels down
to 0.015%. For ultra low carbon levels tap carbons in the range 0.025 - 0.035%
are normally required. Higher start carbon levels are made possible by the use of
the oxygen lance for forced decarburisation. For light treatment practice, only
part of the full vacuum system is required. For full decarburization to produce
ultra low carbon grades the full steam ejector system is required.
Multi function lance practice
Decarburisation
Using the oxygen lance raises the upper limit on tap carbon. In this case it will be
possible to present steel to the degassing unit with carbon content for example of
0.060%, and, by using the oxygen lance under vacuum, reduce the carbon
content to, for example, 0.030%. From this point, a normal light treatment
practice would follow, as previously described, resulting in a final carbon level
down to 0.015%, or any intermediate value as required.
For ultra low carbon steels, the procedure would be in principle similar, except
the carbon content would be reduced by oxygen blowing in the vacuum vessel
down to about 0.020%. Full decarburisation practice would then proceed as
described previously, using the full vacuum system.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 26
The oxygen blow facility can also be used to accelerate the rate of
decarburisation from normal initial carbon levels.
Reheating
After deoxidation the steel can be reheated, if required, by using the oxygen
lance. The operator selects the required amount of reheat, which could be 10oc,
20oc, 30oc etc. The plc then automatically calculates the amount of oxygen and
aluminium required to achieve the requested reheat. Oxygen is blown at a
controlled, preset rate and aluminium is added during the oxygen blow. The steel
is then reheated by the exothermic reaction between oxygen and aluminium.
Reheat rates of 4oc per minute or more are achieved. After the required amount
of oxygen has been blown, and the required amount of aluminium added, the
PLC automatically stops the reheat process. The operator can then take a check
measurement for temperature and aluminium content (Celox sample) after
allowing a couple of minutes mixing to homogenize the ladle contents.
The ability to reheat the steel gives the RH process a much greater degree of
flexibility and versatility.
Hydrogen Removal
In certain grades of steel such as HIC plate steels, rail steels, high carbon steels
etc hydrogen levels are critical. The RH process is an extremely effective method
of removing hydrogen.
Hydrogen is removed during degassing by diffusion from the surface of the metal
to the low pressure atmosphere in the vacuum vessel. The effective removal of
hydrogen therefore requires, apart from low pressure conditions, a high surface
area between the metal and the vacuum.
In the case of the RH, the metal within the vessel is slag free, the depth of metal
is low, and the argon bubbles greatly enhance the surface area exposed. All
these factors, plus the high rate of recirculation of the RH process, produce a
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 27
very high surface area to volume ratio, and result in the fact that the RH is a very
effective method for removing hydrogen.
The design is the so-called rocker system. In this design the vacuum vessel, hot
off take and gas cooler are all located on a platform which is supported at one
end of a double lever arm arrangement. The lever arms are pivoted about a
centre point and counterweighted at the other side of the pivot point. Movement
is achieved by a hydraulic ram attached to the counterweight box. Since the
counterweight is slightly heavier than the vessel and platform, the system is fail-
safe, in that the platform can be raised by bleeding the ram, in the event of total
power failure.
Ladles are presented to the degassing unit by a ladle transfer car which also
serves to remove the used vacuum vessel and replace it with the relined and
preheated replacement vessel.
The steam ejector vacuum system and the ferroalloy addition system are both
supported and enclosed by freestanding structures.
Ancillary equipment such as vessel wrecking, rebricking and preheating stations
can be located adjacent to the operating unit or in some adjoining bay.
Control and monitoring of the process is done from a control room local to the
unit.
Liquid Material Handling
After tapping, the steel ladle will be transported to the teeming bay by a steel
transfer car. Further transportation to the Ladle treatment and caster will be
provided by crane.
The empty ladle returning from the caster will be prepared for the next heat as
follows:
• tilting to remove the remaining steel and slag
• � teeming nozzle inspection/replacement
• � stirring plug inspection/replacement
• � preheating up to about 1,200 °C
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 28
Ladle inspection and repair stand as well as ladle preheating station will be
provided for the above activities.
Slag Handling
The slag from the converter shall be transported in slag pots placed on the rail
bound slag transfer cars to the slag handling area. The slag pots will be handled
by overhead cranes for dumping into the slag pits. After that the slag pots will be
lime coated for reuse and transferred back.
3.1 Pollution Control System
BOF – Gas Cleaning Plant (DRY System)
Primary Gas Cooling Systems: The lower hood of the cooling stack and the
cooling stack will be designed for the gas flow rates, based on a reacting oxygen
shown below and a combustion factor of n = 0.1. In order to minimize skull build
up on the membrane wall, a round conical shape has been selected in the lower
section of the hood with an inside diameter shown below. The waste gas leaving
the converter is collected in the attached hood cooling system above the
converter. At the hood inlet an adjustable skirt is installed to close the opening
between converter mouth and hood inlet during the blowing process. This will
limit the access of ambient air to the gas and the combustion of the primary
converter gas will be kept below 10 %. At the outlet of the Gas Cooling System
the gases are cooled down to approx. 900°C.
The flow rate of primary gas and therefore also the total flow rate of LD-gas
during the blowing period is not constant but fluctuates over a wide range. To
assure a good capture efficiency and high LD-gas quality, the flow of LD-gas
through the system has to be carefully and accurately controlled. This is assured
by continuously adjusting the flow rate in such way, that the pressure at the
cooling stack inlet varies only insignificantly around zero (P0). SMS Siemag
favours a cascade control concept based on a radial type ID fan (IDF) equipped
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 29
with an inlet guide van damper (IGVD). Small adjustments of the gas flow rate
will be controlled by the IGVD, larger fluctuations will be controlled by the
revolution speed of the IDF by means of a VVVF-control unit (Frequency
converter).
Due to this minimized waste gas quantity, the SMS Siemag Dry type System with
a pressurized close loop hot water system will be reduced to a minimum of
operating costs.
Description:
The cooling water is forced by cooling water circulation pumps through the
cooling hood tubes of the different hood sections. From the outlet it is passed
through a fin-fan heat exchanger to remove the heat to the atmosphere. The
design parameters of the heat exchanger are calculated to use the time between
the blowing cycles for cooling of the water back to the initial starting temperature.
This will ensure the most economical size of the equipment.
From the heat exchanger the cooled water is returned into a pressurized storage
tank and picked up by the pumps for the next circulation cycle. The storage tank
is designed to contain a water volume for two complete cycles during one
blowing period. Nitrogen is used to pressurize the storage tank. The pressure is
maintained at approx. 11 to 14 bar (g) and nitrogen is added if necessary through
an automatic control valve. The pressure is designed to prevent the water in the
system from boiling during the heat. The advantage of this system is the easy
operation and almost no feeding water requirement.
Primary Gas Cleaning System (Dry System)
The BOF waste gas cleaning system is designed as a dry-type cleaning system
for high efficiency.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 30
cleaning and further cooling of the LD-gas. The system is designed for
subsequent converter gas recovery. This type of Cleaning System is a technical
solution to comply with today’s most stringent environmental requirements.
The Gas Cleaning System is only in operation with full capacity during blowing
time. After passing through the cooling stack (CS), within that the gas
temperature is reduced, the LD gas enters the adjacent gas conditioning tower
(GCT) with a temperature of max. 1000°C. The gas is heavily laden with dust
particles from the converter process, mainly with iron, iron oxide but also other
particles from slag, flux charges (lime and others) and hot metal. The range of
particles sizes vary from approx. 0.1 micron up to some mm.
In the GCT, connected gastight via a special designed high temperature
compensator, the LD gas is being cooled and conditioned by evaporation of
injected water. Coarse dust particles are separated in dry state and transported
to the coarse dust silo. The conditioned LD gas exits the GCT at about 200°C.
By means of the following horizontal 2nd generation dry-type electrostatic
precipitator (ESP) the remaining fine dust load is further reduced to the
requested clean gas dust content. The dust is also collected in dry state and
transported to the fine dust silo.
The gas is transported through the Gas Cleaning system by means of an induced
draft fan (IDF). Depending on the actual CO content a switch-over station will
direct the gas either to the Flare Stack (FS) or with sufficient CO content to the
gas holder (GH) (not within the scope of supplies of this specification).
A subsequent Gas Cooler (GK) installed in the gas duct to the GH further cools
down the LD Gas to temperatures in the range of 60-70° appropriate for the
gasholder operation. The gas will then be fully saturated.
_____
_____
The
GK)
The
Clea
coole
(SOS
The
• • • • • • •
_____________
_____________
system is
down to 10
graphic be
ning Syste
er (GK) s
S).(Location
Gas Cleani
� Evapor
� � Roun
� � Dust
� � Dust
� � I.D. F
� � Gas c
� � Flare
____________
____________
capable of
0 mg/Nm3 (
elow depics
em for LD-
shall be
n of gas coo
ing System
ration Coole
nd Electrost
Transport s
Storage Sy
Fan (IDF)
cooler (GK)
stack (FS)
_____________
_____________
f reducing t
(dry).
s and name
Gas. In th
installed
oler can be
m consists o
er (= Gas C
tatic Precip
system (DT
ystem (DSS
)
)
Amend
____________
____________
the dust co
es the main
e following
downstrea
e discussed
of the follow
Conditioning
itator (ESP
TS
S)
dment in EC ofVillage
J_____________
_____________
ontent of th
n compone
g specificat
m of the
d)
wing main co
g Tower (G
)
f Integrated Stee-Kerjang, DisJindal Steel and_____________
_____________
he clean ga
ents of a d
tion howev
e switch-o
omponents
GCT))
eel Plant & CPst-Angul, Odishd Power Limite____________
___________3
as (after th
ry type Ga
ver, the ga
over statio
s:
P ha ed __
31
he
as
as
on
_____
_____
Evap
In th
orde
distri
of th
acco
GCT
The
the g
For a
Eithe
The
requ
evap
preci
by a
A fee
outle
_____________
_____________
poration Co
e water co
r to assure
ibution is ac
he cone. T
ording to the
T flow simul
cooling in t
gas. Nozzle
atomisation
er Steam or
water drop
ired diame
poration zon
ipitated at t
dust extrac
ed forward
et of the coo
____________
____________
ooler ( Gas
ooled inlet c
e an optim
chieved by
The detail
e actual des
ation – with
the conditio
es lances ar
n of the inj
r Nitrogen w
plet sizes ar
eter and h
ne, all wate
the hopper
ction system
control co
oling tower
_____________
_____________
Conditionin
cone of the
ized gas fl
means of w
arrangeme
sign of the
h gas distrib
oning tower
re located d
jected wate
will be used
re taken int
height of th
er is compl
of the cond
m.
oncept, whic
as well the
Amend
____________
____________
ng Tower =
e GCT the
ow over th
water coole
ent of this
cooling sta
bution inter
r is perform
directly belo
er so-called
d as atomiza
to consider
he conditio
etely evapo
ditioning tow
ch process
e gas flow a
dment in EC ofVillage
J_____________
_____________
GCT)
entering ga
he entire G
ed internals
s gas distr
ack.
rnals
med by direc
ow the the i
d dual flow
ation media
ration for th
oning towe
orated. The
wer can be
ses the tem
and other p
f Integrated Stee-Kerjang, DisJindal Steel and_____________
_____________
as is first d
GCT cross
s arranged
ribution is
ctly injectin
inlet cone.
w nozzles
a.
he determin
er. At the
e coarse d
captured in
mperatures
process dat
eel Plant & CPst-Angul, Odishd Power Limite____________
___________3
distributed i
section Th
in two level
customize
ng water int
are applied
nation of th
end of th
ust particle
n a dry stat
at inlet an
ta, is applie
P ha ed __
32
in
he
ls
ed
to
d.
he
he
es
te
nd
ed
_____
_____
to co
varia
the b
The
with
humi
Roun
Due
mono
clean
prote
In or
preve
way
_____________
_____________
ontrol the w
ations in the
beginning a
treatment o
that the ga
idity. The h
nd Electros
to the su
oxide and
ning system
ection of the
rder to pre
ent any de
that the flo
____________
____________
water flow in
e temperatu
nd at the e
of the gases
as volume
igher the h
tatic Precip
uppressed
gas contai
m. When h
e entire pla
vent the fo
eflagrations
ow of the e
_____________
_____________
n order to o
ure and in
nd of each
s in the GC
to be hand
umidity, the
pitator (Dry-
combustio
ning oxyge
handling th
nt are of pa
ormation of
, the waste
entire gas r
Amend
____________
____________
overcome t
the gas qu
blowing int
CT not only
dled in the
e better the
-Type)
on process
en alternate
his waste g
articular imp
f combustib
e gas clea
route has t
dment in EC ofVillage
J_____________
_____________
he very sud
uantity, whic
terval.
reduces th
ESP, but a
e ESP sepa
s, waste g
ely pass th
gas, the sa
portance.
ble gas mix
ning plant
the form of
f Integrated Stee-Kerjang, DisJindal Steel and_____________
_____________
dden and c
ch particula
he gas temp
also increa
aration effici
gas contain
hrough the
afe operat
xtures and
is designe
f a piston. T
eel Plant & CPst-Angul, Odishd Power Limite____________
___________3
considerabl
arly occur a
perature an
ases the ga
iency.
ning carbo
cooling an
ion and th
d in order t
ed in such
Thereby th
P ha ed __
33
le
at
nd
as
on
nd
he
to
a
he
_____
_____
mixtu
are s
The
mean
inlet
Insid
sepa
elect
high-
the c
The
perm
disch
colle
beco
partic
The
mean
roun
open
The
therm
_____________
_____________
ures of gas
suppressed
gases to b
ns of distrib
transition.
de the ESP
aration field
trodes are
-voltage sy
collecting pl
patented d
mits optimu
harge elect
cting plate
ome negati
cles move t
collecting p
ns of rapp
d casing. A
nings into a
patented S
mal dilatatio
____________
____________
ses of differ
d.
be cleaned
bution baffl
P discharge
s. The colle
fixed in the
ystem the d
lates are ea
design of SM
m corona
trode into t
s. As the
ively charg
to the colle
plates as w
ing devices
A dust scr
drag chain
SMS ELEX
on of each
_____________
_____________
rent compo
are evenly
les and pe
electrodes
ecting plate
e centre lin
discharge e
arthed.
MS ELEX d
discharge
the gas flo
electrons a
ged. Force
cting plates
ell as the d
s. The dus
aper extrac
n conveying
X collecting
h plate and
Amend
____________
____________
ositions due
distributed
rforated pla
s and colle
es form par
e of each
electrodes
discharge e
behaviour.
ow. These
accumulate
ed by the
s where the
discharge s
st falls dow
cts the dus
g device.
plate syste
d easy rap
dment in EC ofVillage
J_____________
_____________
e to the cha
d over the w
ates, which
cting plates
rallel passa
passage. B
are negativ
electrodes
. Electrons
electrons m
e on the du
electric fie
ey are depo
ystem are
wn into the
st from the
em is desi
pping. The
f Integrated Stee-Kerjang, DisJindal Steel and_____________
_____________
anging proc
whole cross
h are place
s are arran
ages and th
Being conn
vely charge
– known a
s are emitte
migrate to
ust particle
eld the ch
osited.
periodically
bottom se
e ESP thro
gned in or
plates are
eel Plant & CPst-Angul, Odishd Power Limite____________
___________3
cess phase
s section b
ed inside th
nged in dus
he discharg
ected to th
ed, wherea
s RS-type
ed from th
the earthe
es, the latte
harged dus
y cleaned b
ection of th
ough bottom
rder to allow
split in th
P ha ed __
34
es
by
he
st
ge
he
as
–
he
ed
er
st
by
he
m
w
he
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 35
center of the ESP into individually suspended hanging and standing plates. In the
center all plates of one plate wall are guided by the rapping bar which transfers
the rapping impulse into each plate individually.
This unique design facilitates the opportunity to spread the passages for inside
passages maintenance access up to 700mm at rapping bar level. The collecting
plate material for the first field is 1.7335 (13CrMo4-5), thickness is 2mm. The
fields 2-4 are of material 1.0116 (St37-3G), thickness is 1,25mm. The patented
SMS ELEX discharge electrode frame is also designed to allow thermal dilatation
of the electrodes. The tubular electrodes are fixed at one bar of the frame only.
The other two bars at the top and the bottom of the frame are meant for guidance
only. Hence, mechanical stress and consequential damage to the electrodes can
be avoided.
For the first field the discharge electrodes are fabricated of special material to
resist high temperature which may occur due to glowing dust. The material of the
tubular part is of 1.7335 (13CrMo4-5) material with 2mm thickness, the spraying
tips of heat and scale resistant 1.4742 (X10CrAlSi18) material with 3mm
thickness. The discharge electrodes of fields 2-4 are fabricated of 1.0338 (St4
K40), both tubular part (thickness 0.6mm) and spraying tips (thickness 1mm). In
order to prevent the casing and the ESP internals of any damage caused by
deflagrations the ESP is equipped with sufficient number of SMS ELEX pressure
vent valves (certified according to directive 94/9/EC).
Each field is equipped with one high-voltage rectifier located either at the top of
the ESP casingor in an electrical room, and is controlled by a special control
cabinet with automatic oltage control.
All auxiliary equipment such as rapping systems, dust scraper, dust conveyor are
controlled by an additional low-voltage switch-gear cabinet.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 36
Scraper bearings inside the ESP are grease lubricated. In order to avoid coking
of high temperature lubrication grease the lubrication pipes and bearings are
cooled by Nitrogen rinsing.
The ESP is provided with necessary access and maintenance platforms.
The ESP casing is provided with thermal insulation as per the technical
requirement
Dust Transport and Storage System (DTS and DSS)
There will be two independent dust transportation and storage systems at each
BOF. One for the coarse dust from the conditioning tower and one for the fine
dust from the ESP.
The transport to the dust silos is carried out depending on the layout by a
mechanical or pneumatic transportation system.
ID Fan (IDF)
Downstream of the ESP the radial type ID fan is located.
Flare Stack (FS)
The flare stack is provided with a flare tip and with a flare ignition device with
blower in order to make sure that no CO-containing gas is released into the
atmosphere without having been passed through the high-temperature reaction
zone provided by the pilot burner for ignition purposes..
For example, natural gas or coke oven gas may be used as lighting-up gas for
the pilot burner. The ignition burners which are located at the flare tip will be
supplied with gas and combustion air by means of the separate pipes.
In case of power failure or ID fan failure the flare stack will be purged by means
of a Nitrogen injector.
LD Gas Duct (LGD)
The LGD connects the various elements of the gas cleaning system, such as
GCT, ESP, IDF, GK and SOS with the FS on one end and the Main Recovery
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 37
duct on the other hand. The LGD consists of various elements/segments with
different diameter (as a contribute to the temperature and pressure regime) and
length (to allow a convenient positioning of the a. m. equipments within the layout
of the steel plant).
Secondary Emission Control Systems
The secondary fume collection system will be designed to collect the fumes from
the following emission sources:
• � Torpedo car re-ladling
• � Injection & de-slagging in Twin desulphurisation station
• � Converter charging, blowing (secondary fumes only) and tapping
• � Flux and alloy charging system at the BOF Converters
• � Ladle Furnaces with their material handling system
• � Wire Feeding & Material handling system at the RH
• � Argon Rinsing Station
• � Ladle breakout stand
• � Tundish breakout stand
Plant description
The fumes are collected in specially designed hoods, arranged as close as
possible at the emission source. In the suction ducts of each hood there are
motor operated dampers installed for appropriate on/off operation and
intermediate positions.
The fumes are then guided to a gas mixer where the gases are homogeneously
mixed and subsequently to a Bag Filter system where the dusty gas get filtrated
and released to the atmosphere by self supported chimney at a certain height in
line with the local pollution norm.
The suction of gas from various source as explained above through the duct,
mixer and Bag Filter is created by four number (three in working condition + one
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 38
in standby condition) ID fans located at the out let of the Bag Filter. The dust
disposed of below the gas mixer and Bag Filter will be pneumatically conveyed to
the dust storage silo suitable for 24 hours capacity. The dust will be unloaded
from the storage silo at regular intervals by trucks.
3.2 Gas Recovery System
The LD-Gas Recovery System mainly consists of:
• Switch over Station (SOS)
• Gas cooler (GK) with re-cooling-system
• Gasholder (GH)
• Gas export Station (BFS)
• Nitrogen injection system (NI-System)
• Switch-over Station (SOS)
For switching-over the gas from flare stack operation to gas recovery operation
and vice versa, a switch-over station is used. This gas switch-over station mainly
consists of two bell shaped valves (cup valves) which are adjusted hydraulically
and separately from each other. By means of this station, the system can be
switched over without any pressure surge. The signal for switching over the
system is given by PLC based on interlocks and process variables. The signal for
switching over the system is given by the CO and O2-analysis. The system is
controlled by means of the differential pressure measurement. For the control,
the pressure is measured at two representative points of the system and is set
against the preset values.
During switching-over, the valve closes the direct way to the flare gas stack.
During pressure compensation the cup valve with control contour opens the way
to the gas holder. At blowing end, first the way to the gas holder starts closing
and then simultaneously the direct way to the clean gas stack is opened fully. In
case of emergency both cup-valves move into fail safe position.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 39
In the ducts of the switch-over station several connections for injection of
nitrogen are arranged in order to purge the ducts during the switch-over
sequence and to flush the system free from gas and / or air pockets.
The main recovery duct interconnects the switch-over stations of the individual
converters with the inlet of the gas holder. The dimensions follow the
requirements of Converter Operation Pattern.
Gas Cooler (GK)
A Gas Cooler (GK) is installed in the duct after the SOS to reduce the waste gas
temperature from approx. 150°C - 200° C inlet temperature to a level of 60 – 70°
C. This is vital for a long lifetime of the gasholder sealing. As a side effect, the
cooling reduces the gas volume.
The GK is designed as a counter-flow cooler, which means the gases enter the
cooler in the lower part and leave at the top. The cooling water is injected
through nozzle-banks with several individual nozzles. The cooling water is
internally circulated by pumps. At least one pump is in operation, while one is
always in stand-by mode.
In order to keep the dust concentration in the re-circulated water on the desired
level, a small amount of water will be continuously exchanged. Losses due to
exchange are compensated by feeding fresh make-up water.
A Goggle Valve (GV) and a gastight shutoff-damper are installed at the inlet of
the GK. A U-Seal valve along with a double excentric butterfly valve will be
installed before the interconnection to the recovery duct. This provides a
complete separation of the individual recovery installation of the Converter from
the common Recovery System.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 40
3.3 Material Balance of EAF and BOF
Material Balance of EAF Route of Steel Making (6 MTPA, from EIA Report August 2008 Input Quantity, TPA Output Quantity, TPA 1 DRI
(@ 0.64 t/t) 3,840,000 Steel Slabs 6,000,000
2 Hot Metal (@ 0.494 t/t)
2,964,000 Slag 1,080,000
3 Cold Pig (@ 0.005 t/t)
29,400 Cut ends, rejects (scrap) 348,000
4 Lime (calcined) (@ 0.072 t/t)
431,800 LOI 54,300
5 Dolomite (calcined) (@ 0.0103 t/t)
61,800 Flue dust 296,880
6 Fluorspar (@ 0.00213 t/t)
12,780
7 Return scrap (@ 0.058 t/t)
348,000
8 Ferroalloys (@ 0.0152 t/t)
91,400
Total 7,779,180 7,779,180
Material Balance of EAF Route of Steel Making (3 MTPA, as proposed) Input Quantity, TPA Output Quantity, TPA 1 DRI
(@ 1.1328 t/t) 3,398,400 Steel Slabs 3,000,000
2 Hot Metal (@ 0.0988 t/t)
296,400 Slag 647,040
3 Cold Pig (@ 0.001 t/t)
2,940 Cut ends, rejects (scrap) 174,000
4 Lime (calcined) (@ 0.072 t/t)
215,900 LOI 27,150
5 Dolomite (calcined) (@ 0.0103 t/t)
30,900 Flue dust 148,440
6 Fluorspar (@ 0.00213 t/t)
6,390
7 Ferroalloys (@ 0.0152 t/t)
45,700
Total 3,996,630 3,996,630 Requirement of oxygen is 42 Nm3/ton of steel produced
Requirement of power is 490 KW per ton steel produced
PM emissions limit is 20 mg/Nm3.
Solid waste generation is 265 kg/ton of steel produced
Water consumption: 1 m3/ton steel produced
Material Balance of BOF Route of Steel Making (3 MTPA as proposed now) Input Quantity, TPA Output Quantity, TPA 1 DRI
(@ 0.1067 t/t) 320,000 Steel Slabs 3,000,000
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 41
2 Hot Metal (@ 0.8883 t/t)
2,665,000 Slag 354,000
3 Return scrap (@ 0.116 t/t)
348,000 Return scrap 174,000
4 Lime (calcined) (@ 0.050 t/t)
150,000 LOI 5,000
5 Dolomite (calcined) (@ 0.01 t/t)
30,000 Flue dust 25,000
6 Ferroalloys (@ 0.015 t/t)
45,000
Total 3,558,000 3,558,000 Requirement of oxygen is 54Nm3/ton of steel produced
Requirement of power is 46 KW per ton steel produced
PM emissions limit is 20 mg/Nm3.
Solid waste generation is 126 kg/ton of steel produced
Water consumption: 1 m3/ton steel produced
4.0 Water Balance and Management Scheme
The consumptive water requirement of the existing SMS (EAF Route) is 2033
kl/hour. The wastewater generation is 650 kl/hour. There will be no change in the
consumptive water requirement of the SMS and wastewater generation after
changing to BOF Route. The wastewater shall be taken to the Oil and Grease
Separator and Settling Tank and after treatment the water will be recycled. No
wastewater shall be discharged outside the premises.
5.0 Air Emissions and Load Calculations The nature of emissions from the Integrated Steel Plant and Power Plant,
including the emission inventory is shown in Table below. The air pollution load
will decrease by using BOF Route.
Source of Emissions
Description of Source
Pollutants
Stack height M
Stack dia m
Gas Temp (K)
Flow Rate (Nm3/hr)
World Bank Standard (mg/Nm3)
Design Limit (mg/Nm3)
Exit Velocity m/s
Emission Load g/s
Power Plant Flue of
each 135 MW units, Total 8 flues
PM 275 3.5 421 392270 (each flue)
50 40 16 35.2 SOx 2000 1720 1499.2
NOx 750 750 653.6
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 42
Pellet Plant Single stack
attached to ESP
PM 70 3.0 388 263850 50 50 13.5 3.6 SOx 2000 30 2.2 NOx 320 320 23.5
Three stacks attached to Venturi Scrubber
PM 30 1.0 m 298 22620 (each flue)
50 50 8.0 0.9
Four Stacks attached to 4 bag houses
PM 30 1.0 m 298 14140 (each flue)
50 30 5.0
0.8
DRI Plant Two Stacks
attached to gas heater
PM 40 3.0 326 23260 (each flue)
50 10 15 1.0
SOx 2000 350 28.2
NOx 320 320 57
Blast Furnace One Stack
attached to Stoves
PM 65 3.6 473 196230 50 10 8.5 0.6
NOx 750 750 41
F 5 5 0.27
Two Stacks for Cast House Dedusting
PM 45 4.0 353 286430 (each flue)
50 50 7.5 8.0
One Stack for Stock House dedusting
PM 45 3.0 333 204950 50 50 9.0 2.9
SMS Three
Stacks attached to 3 Bagfilters
PM 70 6.1 403 622380 (each flue)
20 50 8.0 25.8 SOx 2000 50 25.8 NOx 750 320 165.9
Coke Oven Two Stacks
attached to 4 batteries
PM 135 2.0 553 45710 (each flue)
50 50 7.5 1.2 VOC 20 20 0.25 Benzene
5 5 0.06
SO2 800 60 1.6 NOx 500 500 12.8
Coal Gasifiers Two Stacks
attached to 2x 7 sets of gasifiers
PM 40
2.0 553 42660 (each flue)
50 50 7.0 1.2 VOC 20 20 0.24 Benzene
5 5 0.06
SO2 800 50 1.2 NOx 500 500 11.8
Plate Mill One Stack
attached to Reheating furnace
PM 80 3.3 693 105925
50 50 8
1.5 SO2 2000 1400 41.2 NOx 460 460 13.5
Hot Strip Mill Two Stacks
attached to 2 Reheating furnaces
PM 80 3.3 693 145645 (each flue)
50 50 11 4.0
SO2 2000 1400 113.2 NOx 460 460 37.2
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 43
Lime-dolo Plant Six Stacks
attached to Kilns
PM 50 2.2 383 74535 (each flue)
50 50 7.0 1.2 SO2 600 10 2.4 NOx 400 200 6.0
Two Stacks attached to dedusting units
PM 50 2.0 323 57390 (each flue)
50 50 5.5 1.6
Ferroalloy Plant Two Stacks
attached to Furnace
PM 45 3.0 393
135070
50 50 7.0
3.8 SO2 2000 300 22.6 NOx 320 320 24
Two Stack attached to dedusting Unit
PM 30 2.0 298 56550
50 50 5.0 1.6
Sinter Plant Stack
attached to ESP
PM 85 5.5 408 624700 50 50 10.0 8.7 SO2 500 100 17.4 NOx 320 200 34.7 F 5 5 0.9
Stack attached to Dedusting Unit
PM 85 3.0 408 139400 50 50 7.5 1.9
Process Steam Boilers Two twin-
flues Stacks attached to 4 x 180 TPH Boilers
PM 105 2.6 421 202940 (each flue)
50 40 15 4.6
SOx 2000 1260 184 NOx 750 750 169.2
In the EIA Report, 3 EAF, 6 LRF and 2 RH TOP were proposed. The emissions
from these EAF, LRF and RH-Top would be captured using Fume Extraction
System and taken to three Bag Filters for treatment. The outlet of Bag Filters
would be discharged using three numbers of 70 m tall stacks. The emission
inventory of SMS is shown in Table below:
Stack height, m
Stack diameter m
Exit Velocity m/s
Exit Gas Temp oK
Exit gas volume Nm3/Hr
Emission Limit, mg/Nm3
Emission Load, g/s
70 m 3 Nos.
6.1 8.0 403 622380 x 3 Nos
PM- 50 SO2- 50 NOx- 320
PM- 25.8 SO2-25.8 NOx-166
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 44
In the proposed change, 2 EAF (250 tons), 2 BOF (250 tons), 6 LRF and 2 RH-
Top shall be established.
Stack height, m
Stack diameter m
Exit Velocity m/s
Exit Gas Temp oK
Exit gas volume Nm3/Hr
Emission Limit, mg/Nm3
Emission Load, g/s
70 m 2 Nos.
6.1 8.0 403 622380 x 2 Nos.
PM- 25 SO2- 50 NOx- 320
PM- 17.3 SO2-17.3 NOx-111
70 m 2 Nos.
3.6 8.0 403 216770 x 2 Nos.
PM- 25 SO2- 50 NOx- 320
PM- 3.0 SO2-3.0 NOx-38.5
6.0 Solid Waste Generation and Load Calculations
The inventory of solid wastes load from the Integrated Steel Plant and Power
Plant is shown below. The solid waste load will decrease by using BOF Route.
Name of the Unit Type of solid Waste
Quantity (TPA)
Utilization/ Disposal
1 Coal Gasification
Plant
Coal Ash 1584000 Used in land filling and road making. Unutilized portion of coal ash will be disposed in abandoned coal mines
2 Pellet Plant
Dust 81750 Dust will be reused in Pellet Plant. 100 % reused
3 DRI Plant
Dust Sludge
1982000
Dust and sludge will be used in Sinter Plant. 100 % reused
4 Sinter Plant
Dust 52000 Reused back for sinter making. 100 % reused
5 Blast Furnace
Slag Sludge & Flue Dust
854400 1176035
Granulated Slag will be sold for cement making. Sludge and flue dust will be 100% used in Sinter Plant.
6 Coke Oven &
Byproduct Plant
Bio sludge 50200 Bio-sludge is mixed with coal and reused in coke oven. 100 % reused
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 45
7 Steel Melting Shop
& Rolling Mills
Slag Flue dust
1080000 50200
Slag will be given for metal recovery. Dust will be reused in sinter plant
8 Lime-dolime Plant Dust 746000 100% reused in sinter plant . .
9 Captive Power Plant
Fly Ash Bottom Ash
2134000 533000
Used in cement making, brick making, block making, wasteland filling and road making. Unutilized portion of coal ash will be disposed in abandoned coal mines
10 Ferroalloy plant,
Slag Dust
50000 67000
100% slag will be used in road making. 100% flue dust will be recycled
The solid wastes generation from 6 MTPA and 3 MTPA SMS based on EAF
Route is given below: The solid waste generated from 3 MTPA BOF is given
below (in tons per annum):
Name of solid wastes
Generation from 6 MTPA SMS based on EAF
Generation from 3 MTPA SMS based on EAF
Generation from 3 MTPA SMS based on BOF Route
Generation from 3 MTPA SMS based on EAF and 3 MTPA SMS based on BOF
SMS Slag 1,080,000 647,040 354,000 1,001,040
Flue Dust 296,880 148,440 25,000 173,440
There will be significant reduction in solid wastes generation due to change in
SMS process technology. About 7% in SMS Slag and 42% Flue dust.
7.0 Pollution Load Statement
Component Existing Pollution Load
with EAF Route
Pollution Load after
Change to BOF Route
1 Land 1563.043 ha
(3860.7 acres)
No change in land area,
except that Plant Layout
has been revised
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 46
2 Water
Consumption
9700 kl/hr 9700 kl/hr
(No change)
3 Wastewater
Generation
100% reuse within plant
premises
No change in quality of
wastewater generation.
100% reuse within plant
premises
3 Air Pollution Load
PM
SO2
NOx
In g/s
PM- 25.8
SO2-25.8
NOx-166
In g/s
PM- 20.3
SO2-20.3
NOx-149.5
4 Solid Wastes
Generation
SMS Slag: 1,080,000 TPA
Flue dust: 296,880 TPA
SMS Slag: 1001040 TPA
Flue dust: 173440 TPA
5 Energy
Consumption
Approx. 700 MW Approx.600 MW
8.0 Conclusion
Jindal Steel & Power Limited (JSPL) is constructing a 6.0 MTPA Integrated Steel
Plant and 1142 MW Captive Power Plant at village Kerjang, District Angul in
Orissa. Environmental Clearance for the project was granted by the Ministry of
Environment & Forests, Government of India (MoEF) vide letter
No.J.11011/365/2006-IA.II (I) dated 22-2-2007 and amendment dated 14-11-
2008.
Following changes are proposed for approval of the Expert Appraisal Committee
(Industry) of MOEF
1. Change in Steel Making Technology, keeping the steel production same.
2. Change in Plant Layout keeping the total plant area same.
The earlier 6 MTPA SMS process was based on Electric Arc Furnace Route,
comprising 3 x 200 tons capacity EAF (Conarc type furnace) and 6 x 200 tons
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 47
capacity Laddle Refining Furnace (LRF) and 2 x 200 tons RH-TOP for production
of special quality slabs has been proposed. Conventional slab casting technology
comprising 3 x 1 strand and 1 x 1 strand caster has been proposed.
Now the 6 MTPA SMS process has been bifurcated into Electric Arc Furnace
Route and Basic Oxygen Furnace Route. 2 x 250 tons capacity EAF shall be
established to produce 3 MTPA Steel. 3 x 250 tons capacity BOF shall be
established to produce 3 MTPA Steel. The capacity of LRF, RH-TOP and Slab
Casters are also updated accordingly due to change in heat size..
Environmental Benefits of BOF are low air pollution because of higher content of
hot metal as input, low slag generation and possibility of energy recovery from
exhaust gas (because of use of higher oxygen lancing and resultant suppressed
combustion). The metal recovery using BOF route is about 90%, compared to
about 85% using EAF Route. The electricity consumption is also lower in BOF
than the EAF Route.
The core plant layout has been optimized to 1416.4 ha. This has been has
been communicated to the MoEF vide JSPL letter dated 26th July 2011
along with the revised layout plan of the Integrated steel plant. JSPL
received the lease document of the entire 1416.4 ha land (3500 acres). As
on date physical possession of 867 ha land (2141.5 acres) is available
with JSPL where the project construction work is going on. Considering
the fact that physical possession of the balance land will take more time
than anticipated and therefore to meet the scheduled commissioning
target, revision of plant layout has become inevitable. Because of land
acquisition issues an adjustment of 23.5 ha (58 acres) land was done.
However the total land for setting up the core plant will remain1416.4 ha
(3500 acres), as already furnished to MOEF.
Amendment in EC of Integrated Steel Plant & CPP Village-Kerjang, Dist-Angul, Odisha
Jindal Steel and Power Limited ______________________________________________________________________________________
____________________________________________________________________________________ 48
JSPL decided to shift the blast furnace, pellet plant, coke oven and sinter plant
from the west side to east side and shift the ash pond from east side to west side
of the plant layout. This will enable JSPL to immediately start constructing the
remaining units and synchronize them with the units that are ready for
commissioning.
There will be net reduction in Pollution Load due to change in SMS process
technology. Water consumption and wastewater generation will remain same.
Entire wastewater generated from SMS shall be treated and recycled. The air
pollution load from the SMS will decrease after the change in process
technology. The solid waste generation from the SMS will also decrease after the
change in process technology. The land requirement for the SMS however
remains unchanged.
ENVIRONMENTAL CLEARANCE ‐NEW
(Steel & Power Plant)
F. No. J-11011/365/2006-IA II (I) Government of India
Ministry of Environment and Forests (I.A. Division)
Paryavaran Bhawan CGO Complex, Lodhi Road
New Delhi - 110 003
To, / ,.,fhe Executive Director
E-mail: [email protected] Telefax: 011: 24367668
Dated 14th November, 2008
Mis Jindal Steel & Power Limited 'Jindal Centre', 12 Bikaji Cama Place New Delhi 110 066
E-mail: [email protected]/[email protected] Fax No.: 011- 26161271
Subject: Integrated Steel Plant (6.0 MTPA) and Captive Power Plant (1,080 MW) at Kerjang, Angul, Orissa by Mis Jindal Steel & Power Ltd. - Amendment in environment clearance reg.
Ref. Your letter no. JSPLIANGULIMOEFIVRK dated 25 th January, 2008, 30th April, 2008, 10th June, 2008, 1st July, 2008, 15th July, 2008 and 19th August, 2008 3rd
September, 2008 and 22"d September, 2008. Sir,
Kindly refer above mentioned letters dated 25th January, 2008, 30 th April, 2008, 10th
June, 2008, 1st July, 2008, 15th July, 2008 and 19th August, 2008 3rd September, 2008 and 22"d September, 2008 wherein you have requested for the amendment in environment clearance accorded by the Ministry vide even no. letter dated 22"d February, 2007 for Integrated Steel Plant (6.0 MTPA) with Captive Power Plant (1,000 MW) at Angul, Orissa by Mis Jindal Steel & Power Ltd. as per the following configuration:
S. N. 1 2 3 4 5
6 7 8
2.0
Product (s)
Iron Ore Pellets (MT Coal Gas (Nm 3/yr)
. MMMMセBMN@
セ@
-i . Phase-I
1 x 3.5 5120 セwウ@
Sponge Iron (MTPA Pig Iron (MTPA)
) -----_ ...
Steel Products (Sla Rods, Plates and S
bs, Billets, Bars, trip) (MTPA)
Ferro Allo s TPA) e (TPD) Calcined Lime Dolim
Thermal Power Pia nt (MW) -----
2 x 1.7 1 x 0.35
3
.-1 x 50,000
2 x 350 -_ .. -----2 x 250
.. Phase-II Total Capacity
_ .. 1 x 3.5 7.0
2560 x 106 7680 X 106 MセN@
1 x 1.7 5.1 -- 0.35 3 6
1 x 30,000 80,000 3 x 350 1750
-----
2x 250 4 x 250
Now, you have proposed for revised configuration in the environment clearance accorded. The final configuration of the proposed project will be as follows:
2
I I I
----Proposed Final l Name of Units Product As per EC Proposed
I dated 22"d deletions additions Capacity Feb., 2007 ----,.
Pellet Plant Iron Ore Pellets 7.0 2.0 I -- I 501 Coal Gasifier Coal Gas 76S0 x 106 36S0 X 106 -- 4000 X 106
Nm3/year Nm3/year Nm3/year I DRI Plant Sponge Iron 5.1 1.1 -- 4.0
--
Blast Furnace Pig Irem MMセ@ -- 2.S5 3.2 Coke Oven & Coke -- -- 2.0 2.0
セケーイッ、オ」エ@ plant - - --Sinter Plant Sinter 4.0 4.0 , -- , --
--
SMS Steel 6 -- -- 61 ---_. . --.. Zセ@ ---- セNMNMMM .. MMMLセMセNMMMBBMM
Rolling Mill Steel Products 6 _ . -- 6 .. -
Ferro alloy Plant Ferro Alloys O.OS -- -- O.OS Lime Dolime Plant Lime 1 Dolime 1 1750 TPD -- 1250 TPD 3000 TPD
- -- MMMNMLLMMNセLMMM - ----- , .. ----"-Process gas 1 l Electricity -- -- 62MW I 62MW I , pressure recovery I turbines ,
I
Coal based Power Electricity 1000 MW -- -- 1080 MW Plant I (4x250 MW , (Sx135 MW -'------------
Total cost of the project will be Rs. 21,000 Crares instead of Rs. 15.000.00 Crores earlier proposed.
3.0 The matter has been examined in the Ministry. Based on the revised proposal and EIA/EMP report submitted incorporating increase in capacity of certain plants and installation of new plants, following additional specific conditions shall be included in the environmental clearance letter accorded by the Ministry vide letter no J-11 011/365/2006- IA II (I) dated 22nd
February, 2007:
i)
ii)
iii)
iv)
Continuous stack monitoring facilities for all the major stacks and adequate air pollution control systems shall be provided to control air emissions within 50 mg/Nm 3
and reports for ambient air, stack emissions and fugitive emissions submitted to the Ministry's Regional Office at Bhubaneswar, OSPCB & CPCB regularly.
The emission standards issued by the Ministry in May, 200S for the sponge plants shall be followed.
Total requirement of the water River Brahmani 1 Samil Barrage shall not exceed 14,700 m3/hr and prior 'Permission' should be obtained from the concerned department and a copy submitted to the Ministry's Regional Office at Bhubaneswar within 3 months of issue of this letter.
Proper and full utilization of coke oven gases in power plant using heat recovery steam generators (WHRB) shall be ensured and no flue gas shall be discharged into the air. Tar, NH3 should be cleaned in the process and H2S recovery from the coke oven shall be ensured. Coal tar, elemental Sulphur and crude Benzol shall be recovered from coke oven gas.
v) Wet quenching shall be adopted within one year of installation of coke oven and all the treated wastewater shall be used for wet quenching.
o .,
vi) The prescribed emission standards for coke oven plants as notified vide notification no. GSR 46 (E) dated 3'd February. 2006 shall be complied with.
vii) Biochemical treatment of phenolic wastewater shall be should be treated in BOD plant and used for quenching of hot coke to control emissions, dust suppression and green belt development. Cyanide as CN shall be controlled within 0.2 mg/litre and Ammonical Nitrogen within 50 mg/litre as per the standards notified under the E(P) Act. Elluent analysis reports shall be submitted to the Ministry's Regional Office at Bhubaneswar, OSPCB & CPCB regularly.
viii) Coal and coke fines shall be recycled and reused in the process.
ix) All the recommendations made in the Charter on Corporate Responsibility for Environment Protection (CREP) for the Coke Oven Plants shall be implemented.
x) 'Consent for Establishment' for the revised Integrated Steel Plant (6.0 MTPA) and Captive Power Plant (1,156 MW) shall be obtained from the Orissa State Pollution Control Board and a copy submitted to the Ministry's Regional Office at Bhubaneswar.
4.0 This letter may be kept with the original letter.
5.0 All the other terms and conditions shall remain same.
6.0 This has been issued with prior approval from the Competent Authority in the Ministry.
セ@(Dr. P. B. Rastogi)
Director Copy to:-
1. The Secretary, State Department of Environment, Govt. of Orissa, Bhubaneswar, Orissa.
2. Chairman, Central Pollution Control Board, Parivesh Bhavan, CBD-cum-Office Complex, East Arjun Nagar, New Delhi - 110 032.
3. Chairman, Orissa Bengal Pollution Control Board, Parivesh Bhavan, A/11S, Neelkanthhanagar, Unit-S, Bhuvaneswar - 751 012, Orissa.
4. The Chief Conservator of Forests (Eastern), Regional Office (EZ), N3, Chandrasekharpur, Bhuvaneswar - 751 023, Orissa.
5. Adviser (IA II-I), Ministry of Environment and Forests, Paryavaran Bhavan, CGO Complex, New Delhi.
6. Monitoring Cell, Ministry of Environment and Forests, Paryavaran Bhavan, CGO Complex, New Delhi.
7. Monitoring Cell S. Guard File. 9. Record File.
セセ@(Dr. P. B. Rastogi)
Director
ENVIRONMENTAL CLEARANCE –OLD
(Steel & Power Plant)
F. nセ N@ J·l1011138SI2006· IA II (I) . . Government of IndlR Ministry of Environment end For.sts
JI.A. Division) Plryavaran Shawan
CGO Campi •• , Ladhl ROld New Oelhl -l10 003
e.rnall : pb,rI.toa lft nlc.ln Tolef .. : 011 : 2436 7688 Dated 22'" FebnJary. 2007
To, / . oShri Anand Goyal
Deputy Managing Director Mis Jindal St., 1 & Pewsr Umited Jindal Centre . 12 Bika ji Cerna Place New DelhlttO 068
FIX No.: 011· 2818 12Tl E-mail : [email protected]/ [email protected]
Subject : Integrated Steel Plant (8.0 MTPA) and Captive Powlr Planl (1,000 MW) al kGセャョァ L@ Angul, Orl ... by MIl Jlndll Stell & Power セi、N@
Sir This has reference to your letter no. JSPUEMD/CORf'06.07101 daled 14" October.
2008 alongwith application and EIAIEMP and sub.equent clarifiea'on. furnl.had by you \lid. your Jett er dated 23'" November . 2006 and 20'" December , 2006 for env ironmental ・ャ・セャイ。ョ」・@on the above mentioned project. The Ministry of Environm ent and Forests has examined your application. Il ls noted that Mia. Jindal St.el & Power Ltd. have propo.ed for Integrated Sloe! Plant (6.0 MTPA) and Captive Power Plant (1000 MW) .t k・セ。ョァN@ Angul. Ori •••. No キゥ ャ 、 ャ セ・@
sanctuary , elephant corridOC' , eeo1ogicalfy sansltlv, area, notified archaeolog lca l afte or criUc any polluted area e>data within 25 km area of the site. Ph.'o-wia. details for the procuellon of 6.0 MTPA .te.1 will be as follows :
Coal wi ll be sou rced from captive coa l mIn' and enVIronmenta l dearance Is yet to 。セッ イ 、・、@ 9Y the Minlatry. Total land requirement will be 2.160.365 Including le8.232 h • . forest land which Is SUbmitted to tha St.t. Forest dLー。イエュ・ョセ@ Oris.o on 22'" November. 2006 for approval. The
proposal also Involves dIsplacement of pe rso ns and oustee! have to be rehablHlated . R & R Act iO" Plan Ii prepared and subm itt ed to the Stale Govt for Dpproval
2.0 Bag filters , rume extra ct ion system, cyclon e. ventury scrubber, Electr ost at\c Prec ipit ators (ESPs), waler spray ing fac ili ties elc . will be pro vi ded to contro l the fugitiv e/gaseous emissions below 100 mgINm'. Totel waler requirement Irom River Brahmanll Saml1 8arrege will be 14,700 mllhr . The wastewater will be treated in ETP and WIll be , 00% recycled and reused in the process , cosl dust suppress ion and gardening . No wastElwater will be re leased outs ide the plan t prem ises . SF slag will be so ld to ceme nt manufactu rers Dust from SF & SMS sludge ; ETP 81udge of ORI plant : coal ash from power plant & gas ifi er etc , will be used for backfilling captive coa t mines . Oust from li me do lomi te plant will be reused In lad le coating and wastewater treatment. SMS slag and olag and dust Irom lerro·alloy plant will be used lor road maKing. Mill sealo. will be sold to 51eel plants. He.rth layer and APCD dust from pellet plant will be reu,ed in Pell et plant. No char and accretions will be generated , Out of to lal fottd waste generated , 46.6''; win be reuti lized and 53.3% will bo disposed off In abandoned coal mines.
3.0 Public heering meeting was held on 21· Morch, 2006. 'Conoent lor Establishment' hs, been accorded by the Orissa Stote Pollution Control Board vide letter nO.220901Ind·Ii·NDC· 4103 dated 7" September. 2000. Total cosl oft/1e project is Rs. 15,000.00 Cror.s.
4.0. The Mini stry 01 Environment and Forests hereby accords environmental clearance to the above project under the pro vi sions or EIA Notification dated 14111 September, 2006 sub ject to strict compliance of the following spec ifi c and general cond iti ons:
A,
i)
/I)
III)
SPECIFIC CONOITIONS :
The gaseous emiss ions from various process units sha ll conform to the lo ad/mass b.sed .tandardS notified by thl. Mlnl.1ly on 19" May, 1993 Nセ、@ standard. prescribed flom time 10 time. The stale Board may specify more" &lrlngenl otandard. lor the relevant parameters keepIng In vIew the nature of the Industry and Its size and location. At no time, the emission level .hall go beyond the p",.cribed slandards. On· li ne continuous stac k emis sion. monitoring for all the major atacks will be car ned out and reports oubmltted to the DSPCB & CPCB. The emission /evels from all the sburces shall be Kept below 100 mglNm'. InterlocKing lacilffi •• ';hall be provided so'
lnat process can be automat ically stopped In eaee emission level exceeds the limIt.
ContlnuoLls on-line amb ient air quaUty monllor ing slat ions shall be setup al three location. oround the project oit. and ",porta submitted 10 the OSPCB & cpce.
In-plant control measures for checkIng fug itiv e emissions from aU the vulnerable sources shall be pro vided . Fume and duet extraction system wlth bag filters shall be provided In aleel melting shop , Electrfc Arc Furnac e and Lad le Refining Furnace , Coke oven (non-recovery type) .haJl be opera ted at negative pressure with no fug itive emissions. Bag filters shall b. provided to Pellel plant, DR plant, Lime kiln, Power plant, SMS, SAF, Cast house, raw materiel stock house 01 BF, raw malerial mixing section of SMS and malerlal transler point. 01 lime 、ッャッュセ・@ plant. ESP shall be provided to DRI Kilns and fime dolomilo plant. Gas cleaning plant shall be provided 10 BF. Cyclone 101l0wed by ventury scrubber ,/10/1 be provided 10 the BF. Further speciflc ュ・。ウオイ・セ@ lik e wate r sprinkling shall be carried out at the coal yard, キウァッセ@tfpp ler and エイオセ@ tipp ler elc . Fugitive emissions sha ll be controlled, regularly mon itored and records mainta ined .
Iv)
v)
vi)
J
The power pl.nt Installed shall be b.,ed on con .... ntion.1 セオャカN イゥ N・、@ fuel technology. COBI shell be sourced from captive coal mines and pri or env ironmental clearance from tho Mlnl,try sholl be obtained. ESP shall b. In.talled to keop SPM le\lol. below 100 mgfNm1 , Wastewater generated from coo ling lower blow down sha ll be used for ash handling and disposal. Fly ash shall be backfilled In captive coal mines.
Total requ irement of th e water River Brahman ! I Samil Barrage sha ll not exceed 14,700 m'lhr . 'Perm iss ion ' has been iiilceorded for the drawl of 7.000 m'lhr water for Phase I by the Depar tment Of Water Resources, Govt. of Ori SSi vide leiter dated 11 11 Dec., 2006 and 'Perm iss ion ' for phase II shall be Obta ined . The wastewater from scrubbera In OR Plant and Blast fumace sha ll be trested in ETP and reused ror duet scrubbing . Ha .... leve' , wastewater from SMS and Oxygen plant shan be uiWd for slag granulation; from elilet and Sieb ca.ter. Soft waler plant, DM water plant etc. in pellet making and CooJ ing water for re-(: ircu lation. The wastewater (rom power plan t sha n be used for ash sli Cing and coa l dust suppress ion . All the treated waslewalBr ShaH be recycled & reused either In the process or for green belt deve lopment. No effluent sha ll be discha rged outside th e premises end 'Zero ' dtscharge sha ll be adopted , Domestic wlstes . hell be treated In Sewage Treatment Pllnt (STP)
Ground water monHoring around Ihe solid waste disposal site I .ecvred landfill (SLF) shall be earned out regularly and イ・ーッセ@ sUbmlHed to the Ministry's Regional Office at ehuvane.hwar, epee and opce.
vU) Dust from pellet plant In Pe llet plant; from Lime dolomlle plant In ladle co.Hng snd wastewater Ireatment; from eF & SMS, sludge from GCP of SF, ETP Sludge of DRI pl.nt, coal ash from power plant, coal a.h from ga.ifler. sludge from eTP etc for backfilling captive coal mine.; SMS . 'ag and slag duat from ferro-alloy plant . hall be used for road makin g. SF slag shall be sold to ceme nt manufac tu rers . Mill scales of casting mach ine and ro ili ng mill shall be sold to steel pfa,nts. Fly ash and granu lated sla g shall be used In cement pl.nls . No char and accre tions will be generated . Used oil , hall be so ld to イ・」ケ」ャ・イセ@ and prep rocessors .
viii) POSSibiliti es sha ll be explored regardIng use of coa l ash by lhe cement manufac tunn g units. Sottom ash . hall be disposed off in a suitably de.lgned landfill a. per epes gu idell nes to prevenl leach lng to the sub -soil and underground aqu ifer.
Ixl The company sha ll 、・セッー@ rain water harvest ing, structures .to harvest the rain water for utilization In the lean aeason besIdes recharg in g the groun d water table .
x) Green belt shall be developed In at I .. ,t 33 ' .. area within and around the plant premis •• a. per the epes gUideline. In consultation with DFO.
xl) Occupat !onal Health Surv enlanca of the workers sha ll be done on a regular bas is and records maintained as per the FactorieS Act.
xii) Recommendations made in the CREP guide lines issued fo r the stee l plants shall be Implemented.
xm) No commencement or opera tion of the cement plant shall be carried out without obta ining prior environmenta l clearance for the cap!lve coal mine nom the MinIstry ,
B.
l
n.
liL
Iv.
v.
VI.
vII.
xiv) Comment. and recommendations of the Chief WIldlife Warden (CWLW), GoV!. of Orlss8 regard ing imp act or the proposed plant on the nearb y rese rv e and prote ct ed fores ts sha ll be obta in ed and suggest ions, if any , sha ll be implemen ted 10 3 time bound manne r,
xv) AI the .ffected peraons ,hall be .ultably compensatAd 。 セ 、@ イ ・ィ。「ャ ャセ 。ャ N ・、@ as per the norma and gu ide lines issued by the state GovemmeOi In co ll aborat ion With State Government .
xv ij No construct ion activity at the pro ject she sha ll be Init iated till the approva l for the '";88.232' h. forest land I. obtained セョ、・イ@ the Fore.t (Conservallon) Act, 1980 & subsequent amendments (rom the Stale I Centra l Government
GENERAL CONOITlONS:
The project authorities must strictly adhere to the st ipu lat ions made by the Ori ssa PoMlon Control Board (OS PCB) and Ihe State Government.
No further expansion Of modlficslion. in tho plont should be carried out without prfor approval of the Ministry of Environment and FOfO.t • .
At least four ambient air qualijy monitoring $lations shall be establl.had in the downward direction 8S well 8S where maximum ground level concentrat ion of SPM, SO: and NOx are anHelpated In consultalion wiln Ihe OSPCB. Data on ambient air quality and stack emi,slon should be regularly .ubmitled to thl. Ministry inctudfng セ 。@ Regional OffICe at Bhopel and Ine OSPCBICPCB once In .Ix months. •
Industria l wastewa ter sha ll be properly co llected , treated 10 'as to conform to the .tandarda pre.cribed under GSR 422 (El dal.d l e· May, 1993 and 31· December, 1993 or as amended form time to time . The trealed wBs tewater shall be utilized for plantation purpose.
The overall noiae levela In and around the plant area ,h,U be kepi well wijhln Ihe atandards (85 dBA) by' providing nol.e conlrol measure. Including acoustic hood" silencers , enc losures etc. on all sources of no ise generat ion . The ambient nOrS! levels should conform to the atandard. prescribed under EPA Rule" 1989 viz. 75 dBA H、。ケエゥュセI@ and 70 dBA (nighttima).
The pro ject proponent sha ll also comply with all the environmenta l protect ion measures and .,feguard. recomm.nded In the EIA I EMP report. Further, the company mu.t undertake socio·economlc d ..... lopm.nt ,ctMtie. In the surrounding yillages Uk. community development programmes, educational programmes, drinking water aupply and heaitt1 care etc.
Aa menUoned In the EIAIEMP, R., 2,000.00 Crore. and Ra. 100.00 Crore. eamarked toward. the capital coat and racun1ng cosVannum for enVironmental pollution oontrol me •• ure. shall be Judlclou,ly uliliud to Implement Ine condilion •• tipulated by Ihe Mlnlatry of Env ironment and Forests as well as the State Governme nt The funds so crovlded sha ll not be divt!rled (or .nv /'Ilh-.r /'UJrf'\I"Ica
5
viii The Reglonsl Office of this Mioistry Rt Rh,lV.nA.hw., I cpca l OSPCB will ュm セ ッ イ@ the stipu lated cond itions A six monthly comp li ance repo rt and the mon itored dala along with statistica ll nterprelat ion sha ll be subm Hted to them regu larly .
Ix. The Project Proponent shall Inform the public that the project has beeo eccorded envlronmental clearance by the Ministry and cop ies of the cfearance letter are 8ve l!able with the OSPCB/Commnte. and may elsa be seen at Web.rte of the Ministry of Environment aod Forest. al httpJenvtor n!C.in. This ahali be adve,tlsad within .even days from the date of issue ot the clearanco letter , at leilst in twQ local newspapers that are widely circu lated in the region of which one sha ll be in the vernacular language of the locality concerned Elnd a copy of the same shall be forwar ded to the Reg iona l office .
x. Project authorit ies sho uld Inform the Reg iona l Offi ce as weU 36 the MInistry , the date of tlnanc ial closure and tinal approval oJ the project by the concerned authorit ies end the date of commenc ing the land deve lopment work .
5.0. The Ministry may revoke or suspend the clearance , If Implementa Uon of any of the above conditions Is not satisfactory .
6.0. The Miolstry reserves Ihe right to lIIipulet. additiMal 」ッョ、 セャ ッョウ@ if found necessary. Till! Company In a time bound manner wlllimplernent these co(,!d iti ona .
7.0. The above condrtlons will be enforced, Inter-ella under the provisions of the Water (Prevention & Conlrol of Pollution) Act, 1974, the Air (Prevenllon & Cootrol of Pollution) Act, 1981. the Environment (Prot.ctloo) Act, 1986, Huardous Wast •• (Management and Hendling) Rulea, 2003 and the Public (Insurance) UBbility a」セ@ 1991 along with their amendments and rules セ@ ..
Copy to:-
(Dr. P. B. RIIlogl) Additiof1i11 Director
1. The Secretary, State Department of Env ironment , Govt . Of Orissa , Bhubaneswar . OrIssa .
2. Chairman, Central Pollution Control Board. Parivesh Bhavan. CBD-eum-Ofnce Complex, EastMun Nagar, New Delhi - flO 032.
3. Chairman, Orls.a Bengal Pollution Control Board, Parivesh Bhavan, N1 16, セ・・ ャ ォ。ョエィィNョNァNイ L N uョ ゥ エMXL@ Bhuvane.war - 751 012, Orissa,
4. v'rhe Chief Conservator of Forests (Eastem), Regional Ofnce (El), Al3. ChandrasekharptJr , Bhuvaneswar - 751 023, Orissa .
5. Joint Secretary (CCI-I), Minlalry of Envlronmonl and Forests, Paryavar.n Bhavan, CGO Complex, New Delhi.
8. Monitoring Cell, Ministry of Env iro nment and Forests , Paryavaran Shavan , eGO Complex, New Delhi.
7. mッョセッイャョァ@ Cell 8. Guard File, セNNNゥッjGQ@Q RACOrd File . V'.!o I
(Dr. p , B. Rastogi) Add itional Director