as on 02.12.2016. - mines
TRANSCRIPT
The cases where, required documents have been submitted by Project Proponent but pending for processing / decision by the State
Governments- as on 02.12.2016.
State S.
No
.
Name of the
Applicant
Mineral Area
(Hect.)
Village and Dist. Date of Approval under
5(1) , if scheduled
mineral
Letter of Intent issued, if
non-scheduled mineral
Action required and
Timeline agreed.
Andhra
Pradesh
1
M/s. Chettinad
Cement
Corporation
Limited
Limestone 377.523
Kesanupalli &
Pedagarlapadu
Villages of Dachepalli
& Karempudi
Mandals, Guntur
District
-
PL granted vide
G.O.Ms.No.37,
dt.07.05.2013. Letter of
intent given vide memo
No.19749/M.IV (2)/2013-1,
dt.18.01.2014.
Lease Executed on
24.08.2016.
(A1)
2 M/s The KCP Ltd Limestone 20.046
Mandadi R.F. Block
No.2, Polepalli
Village, Durgi
Mandal, Guntur
District
-
Government Memo
No.16354/M.IV(2)/2012-1,
dt.06.12.2013
Lease Executed on
18.06.2016
(A1)
3 M/s The KCP Ltd Limestone 4.274 Mandadi Village,
Guntur District -
Government Memo
No.14276/M.IV(2)/2012-1,
dt.06.12.2013
Lease Executed on
18.06.2016
(A1)
4 Ultratech Cement Limestone 29.70 Petnikota, Kurnool 19.05.2007
All clearances
complete. Only the
6(1)(b) general
relaxation needs to be
sought by the State
Government by Sep,
2016
(A3)
5 Ultratech Cement Limestone 90.52 Bandarlapally,
Kurnool, 20.7.2007
All clearances
complete. Only the
6(1)(b) general
relaxation needs to be
sought by the State
Government by Sep,
2016
(A3)
6 Ultratech Cement Limestone 114.37 Tummalapenta,
Kurnool 19.05.2007
All clearances
complete. Only the
6(1)(b) general
relaxation needs to be
sought by the State
Government by Sep,
2016
(A3)
7 M/s APMDC
Ltd. Beach Sand 3618
B/w Bendi to
Donkur, Srikakilam
Dist.
1.02.2010 -
TOR approved in
Jan, 2016 but now
MoEF insisting on
reduction of
protected forest
area. The state Govt.
need to expedite
decision, if required
in consultation with
the Central
Government. (B2)
8 M/s My Home
Industries Ltd Limestone 374.58
Gamalapadu
Village, Dachepalli
Mandal, Guntur
District
-
Govt. Memo
No.14722/M.III(2)/2012
-4, dt.16.04.2013.
EC has been
Granted. State
Government may
expedtie. (A2)
Proposal submitted
to the Government,
dated. 11.10.2016
for grant of Mining
Lease.
9 Shree Jai Jyoti
Cement Limestone 149.39 Palkur village, 23.11.2012
EC has been
Granted. State
Government may
expedite. (A2)
10 M/s. Shree
Cement Ltd Limestone 283.59
Kachavaram &
Inuparajupalli
Villages of
Karempudi Mandal,
Guntur District
Govt. Memo
No.14499/M.II(2)/2009
-3, dt.19.05.2010.
Proposal submitted
to the Government,
dated. 26.11.2016 for
grant of Mining
Lease. (A2)
11 M/s. The Ramco
Cements Ltd Limestone
267.30
Acres
Sy.No.193,194/1,2
etc., and Sy.No.
171 of
Jayanthipuram (V)
Jaggayyapeta (M)
Krishna Dist
-
Recommended to
Government for
relaxation of
maximum area under
section 6(i)(b) of
MMDR Act, 1957.
(A3)
Chhattisgar
h
1 Kamlibai Kashyap
Limestone 4.09 Badhaji, Jagdalpur - 31.03.2011 03.05.2012 State Govt. has sorted
out the complaint in the
matter and given a
grant order on
22.08.2016. MDPA
model format is to be
given by the Central
Government. Lease
Execution to be
expedited by the State
Government. (A2)
2 M/s Pushp Steel &
Mining, Delhi
Iron ore 215
Hahaladi, Kanker - - High court has given
final order in July,
2016.The SG has
sought legal opinion
from Law Dept. The
lease may be executed
after the same, as rest
all clearances are
already obtained. (B2)
3 M/s J.K. Laksami
Cement Pvt Ltd.
Limestone 281-339 Semriya & Nandni
Khundani
Durg
- 07.02.2011 Regarding Govt. Grass
Land. State Govt. to
expedite decision by
16.08.2016. (A4)
4 M/s Ultratech
Cement Ltd. Raipur
Limestone 689.048 Mohrenga, Murra, Raipur - 19.04.12 EC granted on
09.08.2016. Not
pending on part of
MoEFCC.
NOC of Water
resources Department
of the State is to be
revised after resolution
of dam catchment
issue. Revised report
submitted by the
applicant. State
Government may be
asked to expedite
decision by15.09.2016.
EC has been
Granted. (A2)
5 M/s Ultratech
Cement Ltd. Raipur
Limestone 157.122 Guma, Balodabazar - 17.11.2009 EC has been
Granted. (A2)
6 CMDC/ NMDC Iron Ore 646.596
Deposit No. 4,
Dantewada
30.11.11
-
Goa 1
M/s Gomantak
Investment Pvt.
Ltd
FE 29.8700 Pissurlem, Sattari --- --- Matter is Subjudice
before Hon’ble
Supreme Court. (B2)
2
M/s A.H. Jaffar &
Sons
FE 100 Dharbandora, --- --- DGPS plan approved
and Regional control
of Mines informed
regarding
Environmental
clearance quantum,
which is required for
MP. (A2)
Gujarat 1 M/s Nirma Ltd Limestone 911.41.45 Patan Dist:- Jamnagar -- Dt.09.05.2007 All formalities
complete. The District
Administration may be
asked to expedite lease
execution. State has
also requested to give
model MDPA for non-
auction cases under
Rule 8(3) of MCR,
2016. (A2)
2 M/s Ambuja
Cement
Limestone 591.13 Lodhva, Girisomnath 20.09.2013
3 Indo Rama
Cement Ltd
(Heidelberg
Cement India
Ltd)
Limestone,
Marl
891.71.85 Rohina, Balana,
Vadhera Dist:-
Amreli
-- 08.02.2006 The decision in
regard to change of
name is to be taken
by SG for further
processing of EC.
The State may
expedite by31.08.2016.
(B2)
4 UltraTech
Cement Ltd
Limestone,
Marl
14.20.45 Babarkot Dist:-
Amreli
-- 04.02.2012 Pending for seeking
relaxation under
Section 6(1) (b) for
which a general
proposal needs to be
sent by the SG to the
CG by Aug 2016.
(A3)
5 UltraTech
Cement Ltd
Limestone,
Marl
49.84.54 Babarkot Dist:-
Amreli
-- 04.02.2012
6 M/s Nirma Ltd. Limestone 616.7254 Padhiyarka &
Doliya, Dist:
Bhavnagar
-- 15.02.2008 Proposal considered
by EAC in August,
2016. EAC deferred
the proposal due to
involvement of
Agriculture land.
Minutes of EAC
already put on
website. (B4)
7 M/s Nirma Ltd. Limestone 1225.855
3
Vangar& Madhiya,
Dist: Bhavnagar
-- 15.02.2008
8 M/s Nirma Ltd. Limestone 1489.470
1
Gujarda &
Dudheri, Dist:
Bhavnagar
-- 15.02.2008
9 Shree Digvijay
Cement Co. Ltd.
Limestone 6.64.89 Survey No. 51,
Mokhan Ta.
Bhanvad, Dist.
Jamnagar.
--- Included in the list
of saved cases
compiled by MoM
on the request of
State Government.
May please
expedite.. (A2) 10 Shree Digvijay
Cement Co. Ltd.
Limestone 18.03.88 Survey No.78,
Village:-
Pachhatardi, Ta.
Bhanvad, Dist.
Jamnagar.
11 Shree Digvijay
Cement Co. Ltd.
Limestone 67.17.37 Survey No. 166 and
138, Vill.:- Dheber
and Bhavaneshwar,
Ta. Bhanvad, Dist.
Jamnagar.
Jharkhand
1 M/s ACC Ltd Limestone 115.38 Ha. Ranjka, Kondwa &
Dakatta (W.
Singhbum)
19.02.2006(MMDR Act
1957), Sec 6(1)(b)
2204/M.Dated 14.10.2014 GR, EC, Not submitted
by Applicant. State
Govt. to expedite
decision by
16.08.2016. (B1)
2 Omiyo Ranjan
Jaiswal
Bauxite 111.63
Ha.
Kujam Dokapaat(
Gumla)
Nov,89 __ SG to verify mining
plan approval, FC
approval. Application
for EC is to be
expedited. (A4)
3 Omiyo Ranjan
Jaiswal
Bauxite 85.13 Ha. Bahagarah(Gumla) Nov,89 __ Queries of SG replied
by applicant on
16.03.2016. Pending
for decision by State
Government which
needs to be expedited
by 15 Sep, 2016. (A4)
Karnataka
1 M/s. Bellary Steel
and Alloys Ltd.
Iron Ore,
Manganese
Ore
121.41 Jaisingpur Approved
10/11/1997
Govt. conducted
meeting on 24.05.2016
to finalize draft orders.
Govt has passed
proceedings on
27.08.2016. Applicant
has to submit
complaince to the
Govt. DMG addressed
CEC on 07.10.2016 to
issue directions to
ICFRE to prepare
R&R plan of the
considered area.
Simultaneously ICFRE
has been informed vide
letter dated:
10.11.2016 that
expenses would be
borne by the respective
applicants. (A4)
2 Shri Vonti
Shivappa
Manganese
Ore 18.8 Acre Yeshwanthanagar
Approved
dt :3 /7 /2009
Pending with DC patta
land. Clarification
from DC with regard to
present status of land is
sought. Reply awaited.
Case is pending in DC
office Bellary
regarding the present
land status of the land.
State DMG office may
write to DC to expedite
the matter in 15 days.
(B2)
3 Shri D. Ramesh Iron Ore 14.59 Acre Ramgad Approved
dt :3 /6 /2008
Govt. is conducting
hearing on the proposal
sent to GoI as patta
land and now the status
of land has become
forest. Presently the
matter is pending with
the Hon'ble Minister,
GOK. The final
decision may be taken
within 15 days. State
Govt. recommended
for withdrawl of 5(1).
4 M/s. Mineral
Syndicate
Iron Ore,
Manganese
Ore
20.23 Hect. in NER Range
Approved
dt :25/7 /2005
MP & FC approved.
Overlaping found with
non FC area of M/s
MML area. Held up
for ascertaining the
same. Report is being
verified by Drawing
Branch. State DMG
has to forward its
comment to GOK as
applied area is
overlapping with the
non forest area of M/s
MML within 10 days.
(B1)
5 M/s. Kumar
Enterprises Iron Ore 7.69 Hect. Ramadurg Range
Approved
dt :18/7 /2006
Mines Tribunal
quashed the 5(1)
approval in favour of
this applicant.
Presently pedning with
law officer. WP
15700/2011/05.07.201
6 direction to conduct
hearing of all
applicants. State DMG
may process the matter
as per court orders and
take decision within 15
days. (B2)
6 Shri V.
Venkateshulu Iron Ore 40 Acre NEB Range Bavihalli
Approved
dt :14/6 /2006
GOK has requested to
revoke the grant
notification as no free
area is available and
nobody is present in
behalf of the lessee.
May be finalized
within 15 days. (B2)
7
Shri N.
Mohammed Imam
Niazi
Iron Ore 16.19 Hect. Sankalapura Approved
dt :27/2 /2009
In process. Addressed
a letter to DC Bellary
and report awaited.
Case is pending in DC
office Bellary
regarding the present
land status of the land.
State DMG office may
write to DC to expedite
the matter in 15 days.
(B2)
8 Smt. B.L. Rani
Samyuktha Iron Ore 79 Acre Rajapur etc.
Approved
dt :4 /7 /2008
At present Pending
with drawing branch
of DMG for opinion
and status. The
matter for survey and
demarcation may
kindly be expedited to
be completed in 10
days. (B2)
9 Ms. Kumar
Enterprises Iron Ore 165 Acre Ramgad
Approved
dt :20/8 /2008
Matter is pending
before the court of law.
(B3)
10
M/s Upendra and
Company
Iron ore &
Manganese
ore
121.41 Ha Yarrekatte
Tumkur
Approved on 21-04-2006 Grantee has submitted
all clearances except
FC. Pending with
lessee.
But the considered area
is notified area for
Manganese and this
applicant company is a
sole applicant, without
conducting hearing
recommended this
application for grant.
The SG to take
decision within 15
days. (B1)
11
M/s Goa Minerals
Pvt.Ltd
Iron ore &
Manganese
ore
116.55Ha Yarrekatte
Tumkur
Approved on 09-03-
2006.
11 cases involved in the
overlapping issue.
WPs’ in High Court
Pending. Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of Hon'ble
High Court. To resolve
the boundary dispute.
(B2)
12
M/s Dhruvdesh
Meta Steel
PVt.Ltd.,
Iron ore &
Manganese
ore
116.55 Ha Katarkihalli
Tumkur
Approved on 01-06-
2006.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
13
Shri R.N.Ashok Iron ore &
Manganese
ore
178.3 acres Gollarahalli
Tumkur
Approved on 17-12-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute.
14
Shri R.Praveen
Chandra
Iron ore &
Manganese
ore
178.3 acres Gollarahalli
Tumkur
Approved on 17-03-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
15
M/s Milan
Minerals
Iron ore &
Manganese
ore
178.3 acres Gollarahalli
Tumkur
Approved on 04-03-
2008.
Advertised area.
No details are available
regrarding grant
notification. To be
checked at Govt.
At the time of
conducting S&D,
inherent defects found
in the adjacent original
village maps of
Hombalaghatta,
Kathrikehal &
Yarrekatte. To resolve
the boundary dispute, a
meeting was held on
16.10.2015 under the
Chairmanship of
Secretary, C&I.
Revenue Department
and the Department of
Survey Settlement &
Land Records have
been directed to
resurvey the village
boundaries and revise
the revenue documents
accordingly within
three months.Awaiting
for revised village
maps from the
Revenue Dept.
Presently the case is
pending with GOK to
demarcate the village/
lease boundary after
re-survey as per the
direction of Hon'ble
High Court. (B2)
16
M/s Mineral
Enterprises
Pvt.Ltd.,
Iron ore &
Manganese
ore
178.3 acres Gollarahalli
Tumkur
Approved on 17-03-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
17
M/s Banashankari
Mining Corpn.
Iron ore &
Manganese
ore
178.3 acres Gollarahalli
Tumkur
Approved on 17-12-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
18
Shri M.Babanna Iron ore &
Manganese
ore
383.5
Acres
Aravatti
Tumkur
Approved on 17-12-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
19
M/s Kudremukha
Iron ore Co.Ltd.,
Iron ore &
Manganese
ore
116.55 Ha Hombalagatta
Tumkur
Approved on 12-06-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
20
Smt.Prema
Channappa
Iron ore &
Manganese
ore
60.00 Ha Hombalagatta
Tumkur
Approved on 02-06-
2008.
Overlapping issue.
WPs’ in High Court
Pending.Presently the
case is pending with
GOK to demarcate the
village/ lease boundary
after re-survey as per
the direction of
Hon'ble High Court To
resolve the boundary
dispute. (B2)
21
Mariam Md.
Siddique Patel
Iron ore &
Manganese
4.86 Ha Kenkeri
Chitradurga
Approved on
24-12-2008
Applicant has
produced statutory
clearances such as
technical report, NOC
from DC, CFE from
KSPCB, EC and
mining plan approved
by IBM. NA
conversion not
produced. Govt. yet to
issue grant notification.
Pending with Govt.
Matter is pending with
GOK for notification
of ML. May expedite
decision within 15
days. (A4)
Madhya
Pradesh
1 Lalaji Mineral Manganese 4.99 Negariya/ Jhabua 13.07.2011 All clearances
obtained. SG will issue
Grant orders by
September. (A2)
2 Khatri Mineral Iron ore,
Yellow Ocre
4.56 Silua, Jhasi/ Jabalpur 30.11.2015 All clearances
obtained. SG will issue
Grant orders by
September. (A2)
3 M/s Vandana
Energy and Steel
Ltd.
Manganese 9.915 Miragpur, Balaghat 26.07.2007 SG to examine the
matter in the light of
the recent decision of
the High Court. MP
approved. (B3)
4 Shri Harish
Khandelwal
Limestone 4.502 Sitapuri/ Dhar 22.12.2014 SG will issue Grant
orders by September.
(A2)
5 M/s Mescow
OMC Mining
Corporation
Limestone
and
Dolomite
522.436 Tedi,
Manehra,Shahpur/
Katni
7.05.2015 EC pending, but the
State Government has
intimated about
executing the lease.
(A2)
6. M/s Nirmala
Minerals
Iron,
Manganese
Ore, Bauxite
23.491 Ghughari Kalan/
Jabal Pur
26.10.2007 Pending in MoM for
reduction of area.
(A3)
7. M/s Anand
Mining
Corporation
Iron,
Manganese
Ore, Bauxite
30.756 Ghughari Kalan/
Jabalpur
02.01.2008
8. Shri Ajay
Knandelwal
Manganese
Ore
22.498 Lodhikheda
Chhindwara
29.09.2008
Maharashtra
1 M/s. Y &M
Cement (India)
Pvt. Ltd.
Limestone 252.00 Devalmari/
Katepalli, Dist.
Gadchiroli
------ 12/08/2008 Common boundary
dispute with Ambuja to
be resolved by the
State Govt. (B2)
2 M/s. Jagadamba
Power and
Alloys Ltd.
Manganese
Ore
90.95 Bhandarbodi, Dist.
Nagpur
14/12/2005 --- Area is being revised
to 14.65 , which needs
to be processed by the
State Government
(B1)
3 M/s. Nilesh Mines
Corporation
Bauxite 70.07 Karivane, Dist.
Raigad
23/05/2008 All approvals granted.
Lease to be executed.
Processing at state
govt. level. State Govt.
to expedite decision by
30.08.2016. (A2)
4 M/s. Prachi Mines Bauxite 73.22 Adi M Khadi, Dist.
Raigad
23/05/2008 All approvals granted.
Lease to be executed.
Processing at state
govt. level State Govt.
to expedite decision by
30.08.2016.. (A2)
5 M/s. Ex-
ServicemenWelfar
e Association
Bauxite 90.60 Girgaon Dist.
Kolhapur
14/10/2014 --- 5 (1) approval obtained
but Revised LOI not
issued by the State
Govt. (Applied area is
reduce excluding forest
area) State Govt. to
expedite decision by
30.08.2016. (B2)
6 Shri. Haroon
Ahamed Fazlani
Bauxite 139.05 Mandivali, Dist.
Ratnagiri
18/06/2007 --- Issue regarding Legal
Heir. SG may take
appropriate action by
30.08.2016. EC
approved , but put on
hold due to Eco
sensitive notification
but now cleared. EC
final order to be issued.
(B4)
8 M/s. Deccan
Minerals
Bauxite 369.96 Gargoti block, Dist.
Kolhapur
10/07/2009 --- Applicant has been
asked by MoEF to
reduce the area for
which the applicant is
seeking the State
Government approval
9 Smt. Nila V.
Dempo
&Shrivinas V.
Dempo
Iron Ore 263.82 Zolambe, Dist.
Sindhudurg
01/08/2008 --- Pending with MoEF
for EC and FC.
MoEF may take
final decision by
Aug. 2016. Public
hearing has deferred
by SPCB on account
of moratorium
imposed in the
region by MoEF for
grant of EC for
Project falling in
Western Ghat.
(Ratnagiri and
Sindhudug). MoEF
to expedite
by16.08.2016. Decided
not give EC in the
wake of Moratorium.
(B4)
10 Shri. Shrivinas
V. Dempo
Iron Ore 437.93 Asaniye, Dist.
Sindhudurg
29/03/2007 --- Pending with MoEF
for EC and FC.
MoEf may take final
decision. Public
hearing has been
conducted on
22.04.2010 but
deffered by SPCB
on account of
moratorium
imposed in the
region by MoEF on
16.08.2010 for grant
of EC for Project
falling in Western
Ghat. (Ratnagiri and
Sindhudug) MoEF to
expedite by16.08.2016.
Decided not give EC in
the wake of
Moratorium. (B4)
11 M/s. Ex-
ServicemenWelfar
e Association
Bauxite 90.60 Girgaon Dist.
Kolhapur
14/10/2014 --- The proposal was
recommended by
EAC in meeting of
EAC held during
June 22,23, 2016.
File is under
submission. EC
rejected. (B4)
Odisha
1 J. N.Pattnaik Iron 4.916 Bhanjapali,
Sundergarh
19.12.2001 - Pending for
disposal at Govt.
level. State Govt.
to expedite
decision by Sep
.2016 taking the
implications of
Rule 12(5) of
minimum area of
5 ha for grant of a
mining lease
under the new
rules. (A3)
2 M/s. OMC Ltd. Iron &
Manganes
e
5091.84 Malangtoli,
Keonjhar &
Sundergarh
20.12.2000 - MP approved on
08.03.1996 over
5226.03 hects. of
the applied area.
EC & FC not
applied. LoI not
issued by Govt.
The prior approval
mandates
tripartite
agreement of
OMC, NMDC &
Rio Tinto. Which is
notmade
operational by the
State Govt.
Matter in court
also. FC under
section 2(iii) is
being applied by
OMC. (B3)
3 M/s. OMC Ltd. Iron &
Manganes
e
1011.5 SGBK, Keonjhar 13.12.1993 - MP & EC
approved. FC not
applied. LoI not
issued by Govt.
The issue of state
mining agent to
be converted to
mining lease is
pending for
decision of policy
section of the
Ministry of Mines
which needs to be
expedited by Sep,
2016. (A3)
4 M/s. Orissa
Sponge Iron
Ltd.
Iron 459 Garjantoli &
Kadamdihi,
Keonjhar
17.07.2002 - The diversion
proposal has been
accorded stage-I
(In Principle)
approval for
173.02 hect.
Against originally
proposed
269.1698 hect.
Further an extent
34.00 hect. Of non
forest land has
been considered
as forest land by
the Ministry
during their site
inspection for
which GOI, MOEF
has sought for
separate diversion
proposal and then
modification of
Stage-I approval
order. The user
agency has filed
the D.P. for 34.00
hect. which is
under scrutinity at
the field level.
Issue of captive
use condition is
also bein
contemplated by
the State Govt, in
line with the
guidelines of the
Ministry dt.
19.09.2012.
State Govt. to
expedite decision
by 16.08.2016.
(B2)
5 M/s. OMC Ltd. Bauxite 721.323 Lanjigarh
(Niyamgiri R.F)
Kalahandi &
Rayagada
13.09.2004 - Stage-I approval
has been
accorded for
660.449 hect.
Stage-I
compliance
awaited. Not
being processed.
FC withdrawn by
Supreme Court.
(B3)
6 Sri M.R. Dash Iron 68.63 Bhulbera
(Khuntapani)
Keonjhar
27.03.1986 - MP, EC & FC not
applied. The
applicant
requested for
deletion of Forest
area and retaining
the balance area
of 65.299 hects.
which is pending
with Govt. since
01.05.2008.
Complinace of
Rule 8 submitted
on 25.5.2016.
State Govt. to
expedite decision
by 30.09.2016 and
to be considered
in the Screening
committee
meeting of
24.09.2016. (B2)
7 Sri J.N.
Pattanaik
Iron &
Manganes
e
57.5 Unchabali
&Nayagarh,
Keonjhar
24.10.03 Granted GP No.
18/SM dt.04.01.2005
MP approved over
the entire area
over 57.50 hects.
EC & FC not
obtained. The
applicant
preferred
reduction of the
area to 30.642
hects. delating the
forest area but
Govt. decision in
this regard is
awaited. To be
considered in the
HLC meeting of
the State. Entire
area is DLC for
which FC would
be required. (B2)
8 M/s. Balasore
Alloys Ltd.
Chromite 35.6 Kaliapani, Jajpur 16.04.99 - Prior approval
was for 100 ha.
Part of it has been
executed as lease.
but left over area
is beinf processed.
MP & EC
approved, FC
approved for
35.285 hects. out
of total fores area
of 35.60 hects.
Applicant has
moved application
for clearation U/s-
2(iii) of FC Act,
1980 which is
pending with
MoEF, Govt. of
India. The
requirement of
prior approval for
bifurcation of the
area may be
borne in mind as
per letter dated
31.5.2012. for
expediting the
csase. (A4)
9 M/s. Koustuv
Mining &
Smelting (P)
Ltd.
Tin 19.0 Kamarpalli No.1
Malkangiri
- 9767/SM dt.
22.11.2004
MP approved, EC
is not a condition
of LoI, hence not
applied for the
same. FC not
required. The case
is Pending for
disposal at Govt
level. Compliance
of Rule 8(1)
submitted. The SG
may expedite the
case by 15 Oct,
2016 (A2)
10 Shri. Bijay Ku
Bansal
Garnet 33.532 Ghatapada,
Kalahandi
- 7543/SM
dt.13.06.2001
MP approved, EC
is not a condition
of LoI, hence not
applied for the
same. FC not
required. The
execution of the
ML has not
materialised since
the matter is sub-
judice before
Hon'ble High
Court, Odisha.
(B3)
11 Shri Om
Prakash Jain
Garnet 33.532 Ghatapada,
Kalahandi
- 7546/SM
dt.13.06.2001
MP approved, EC
is not a condition
of LoI, hence not
applied for the
same. FC not
required. The
execution of the
ML has not
materialised since
the matter is sub-
judice before
Hon'ble High
Court, Odisha.
(B3)
12 Shri. Bijay Ku
Bansal
Gemstone 41.485 Paikadakulguda,
Rayagada
- LoI 11915/SM dt.
15.10.2001 & GP No-
9246/SM
dt.12.11.2007
This case not
subjudice. Only
order to be issued
by State Govt. The
applicant was
asked to submit
the compliance of
Rule 8(1) within 3
days time to the
SG and SG to
expedite lease
execution by 15
Oct, 2016. (A2)
13 Shri. Bajrang
Lal Gupta
Semi-
precious
stone
41.485 Paikadakulguda
&
Kandhadakulgud
a
- LoI 11910/SM
dt.15.10.2001 &
Granted vide GP No.
9366/SM
dt.17.11.2007
Grant order
already issued.
Report from
collector received.
The SG to
expedite lease
execution by 15
Oct, 2016. (A2)
14 M/s.
Manikeswari
Minerals
Quartz &
Gemstone
21.092 Bankia,
Subarnapur
- LoI 9701/SM
dt.18.09.03 &
Granted vide GP No.
18239/SM
dt.22.07.2006
The applicant was
asked to submit
the compliance of
Rule 8(1) within 3
days time to the
SG and SG to
expedite lease
execution by 15
Oct, 2016 (A2)
15 M/s.
Manikeswari
Minerals
Quartz &
Gemstone
19.692 Manikpur,
Subarnapur
- LoI 9656/SM
dt.17.09.03 &
Granted vide GP No.
17692/SM
dt.07.12.2006
The applicant was
asked to submit
the compliance of
Rule 8(1) within 3
days time to the
SG and SG to
expedite lease
execution by 15
Oct, 2016 (A2)
16 M/s.
Manikeswari
Minerals
Quartz &
Gemstone
25.504 Bahalpadar,
Subarnapur
- LoI 4102/SM
dt.07.06.2004 &
Granted vide GP No.
3471/SM
dt.16.02.2006
The applicant was
asked to submit
the compliance of
Rule 8(1) within 3
days time to the
SG and SG to
expedite lease
execution by 15
Oct, 2016 (A2)
17 M/s. Sanjukta
Gems
Cat's eye 17.122 Pipal Padar &
Sarigipali Dist-
Kalahandi
- Granted vide GP
7496/SM Dt.
02.07.05
The applicant was
asked to submit
the compliance of
Rule 8(1) within 3
days time to the
SG and SG to
expedite lease
execution by 15
Oct, 2016 (A2)
18 Sri M.R. Dash Graphite 49.96 Dudukamal,
Bolangir
- LoI 11866/MG dt.
01.11.85 & Granted
vide
G.P No.4605/MG
dt.04.04.86
The applicant was
asked to submit
the compliance of
Rule 8(1) within 3
days time to the
SG and SG to
expedite lease
execution by 15
Oct, 2016
19 M/s. Mesco
Ltd.
Iron 1519.98 Kadakala,
Luhakala,
Pidapokhari and
Sundra Keonjhar
07.01.1999 Granted GP No.
2327/SM
dt.17.03.1999
Moved to HC for
execution of the
Lease. Counter
filed by the SG.
The SG has replied
to MESCO query
of the Central
Govt whch needs
to be finalised by
the Central Govt
by Sep, 2016 (B3)
20 M/s. Shiva
Cement Ltd.
Limestone
& Dolomite
63.956 Kutra,
Sundergarh
- Granted vide
G.P. No. 5919/MG
dt.22.05.92
MP appvd in
1989. FC
Application
pending with the
Collector for DLC
land of 4.09 ha.
The district
administration
may be asked to
expedite the same
by Sep, 2016 (B4)
21 M/s.
Sulakshani
Mines &
minearls (P)
Ltd.
Ruby 15.666 Karanga,
Kalahandi
- LoI 7920/SM dt.
27.06.01
Granted vide
G.P No.3435/SM
dt.28.03.03
FC (stage-II
approved only
14.836 hects.
Balance forest
area not
approved) Issue of
Stanp duty with
District
Administration
which may be
asked to expedite
by Sep, 2016. (A2)
22 M/s. Bharat
Precious Stone
& Minerals
(P) Ltd.
Semi-
precious
stone
70.553 Karlaghati,
Litakabaoli,
Pidilpodga,
Rayagada
- LoI 9085/SM dt.
23.08.2003 Granted
vide GP No. 3423/SM
dt.03.04.2007
The grant order
issued. Pending
for execution of
Lease for want of
approval of survey
maps. May be
done by Sep, 2016
(A2)
23 M/s. Deepak
Steel & Power
Ltd.
Iron &
Manganes
e
38.687 Khandabandh &
Baitarni R.F.
Keonjhar
NA
However LoI issued
on 20.08.2007
- Grant order was
revoked due to
illegal mining
issues. The same
was quashed by
RA but State has
escalated the
matter to HC. So
cant be decided
till the decision is
given by the HC.
MP & EC
approved. FC not
obtained but
compliance of
Stage-I clearance
submitted and
NPV paid over
total forest land.
(B3)
Rajasthan
1
M/s. Grasim
Industries Ltd.
Limestone 532.8585 Sundo ki
dadi/Jhunjhunu
Not required 02-04-03 Matter is pending at
Govt. level regarding
demerger of Grasim
Industries Ltd. in M/s.
Samridhi Cement Ltd.
and further
amalgamation of M/s.
Samridhi Cement Ltd.
in M/s. Ultratech
Cement Ltd. State
Govt. to expedite
decision for S. No. 4 to
5. Applicantion will be
required to submit
revised mining plan
because company has
reduced the area from
34.612 sq. km. to
532.8585 ha (A4)
2
M/s. Grasim
Industries Ltd.
Limestone 1153.4 Bsawa/ Jhunjhunu Not required 16-03-02 State Govt. to expedite
decision at the earliest..
(A2)
3
M/s. Grasim
Industries Ltd.
Limestone 318.78 Mohanpura
jodhpura/Kotputali
Not required 10-10-07 State Govt. to expedite
decision at the earliest.
(A2)
4 M/s Rashtgriya
Ispat Nigam Ltd.
Iron ore 945.8575 Baneda, Sultangarh,
Baran/ Bhilwara
19.03.2013 31.05.2013 Pending with State for
final sanction order.
State Govt. to expedite
decision by 16.08.2016.
On the request of
applicant GoR issued
sanction for further
prospecting in the area
by the applicant. (A2)
5 M/s Shree Cement
Ltd.
Limestone 532.8585 Sundo Ki dadi/
Jhunjunu
23.08.2007 Proposal has been sent
to the Government on
13.10.2016. (A2)
Tamilnadu
1
Tvl Ultratech
Cement Ltd
Limestone 24.63.5 Kairulabad, Ariyalur 22.02.2012 AMP & EC submitted
also obtained in 2015.
Section 6(1)(b)
relaxation is required
from GOI, which is to
be finalized within 10
days. Pending lease
grant order by CGM,
State Govt. and lease
execution by DC.
Applicants to submit
compliance under rule
8(1) within 1 week.
Lease grant to be
expedited by the SG by
Oct, 2016. (A3)
2
Tvl Ultra
techCement Ltd
Limestone 74.38.0 Ottakovil Ariyalur 22.02.2012
3
Tvl Ultra
techCement Ltd
Limestone 54.68.0 Varagupadi
Perambalur
23.02.2012 AMP & EC submitted
also obtained in 2015.
Section 6(1)(b)
relaxation is required
from GOI, which is to
be finalized within 10
days. Pending lease
grant order by
Secretariat of State
Govt. and lease
execution by DC.
Applicants to submit
compliance under rule
8(1) within 1 week.
Lease grant to be
expedited by the SG by
Oct, 2016. (A3)
4 Tvl Dalmia
Cement (B) Ltd
Limestone 15.48.0 Ariyalur,
Periyanagalur and
Kairulabad
12.07.2005 AMP
& EC obtained in 2006
& 2007, respectively.
Section 6(1)(b)
relaxation from GOI
obtained in 2007. The
area earlier given
administrative for PSU
to start purchase of
land, but later
administratively
cancelled these areas
as the PSU had not
started any land
procurement process
which was even
mentioned to the
Central govt for
obtaining 6(1)(b)
relaxation. Now,
Pending decision of
State Govt., for which
they were advised to
form a committee of
officials from CGM,
State Secretariat, IBM
& PSU representatives
if required. The CGM
officials informed that
final decision will be
expedited in this case
within 15 days. In the
meanwhile, applicants
to submit compliance
under rule 8(1) within
1 week. Lease grant to
be done by the SG by
Oct, 2016. (A3)
5 Tvl Dalmia
Cement (B) Ltd
Limestone 26.94.0 Ariyalur,
Periyanagalur
Ameenabad and
Kairulabad
12.07.2005
6. Chhetinad Cement
Corporation ltd.
Limestone 26.145 Karuppur, senapati,
Ariyalur
4.7.2012 Approved MP & EC
submitted in 2015. The
Grant order to be
passed by State
Government and lease
execution to be
expedited by Oct,
2016. In the
meanwhile, applicants
to submit compliance
under rule 8(1) within
1 week. (A2)
7. Tvl. Chettinad
Cement
Corporation
Limestone 32.29.5 Periyathirukonam,
Ariyalur
17.07.2012
8.
Tvl. The Ramco
Cements Ltd.
Limestone 16.22.5 Virudhunagar,
Srupukkottai,
Amanakunatham
11.09.2012 To be considered after
general relaxation for
Limestone for TN.
Section 6(1)(b)
relaxation is required
from GOI, which is to
be finalized within 10
days. The applicant to
give application of MP
& EC subsequent to
Feasibility by Sep,
2016 end. (A3)
Telangana
1
M/s Pioneer
Torsteel Mills Pvt.
Ltd
Limestone,
Iron Ore and
Dolomite
22.460 Nawabpet, Chityal
Mandal, Warangal
24.10.2008 Pending with SG, to be
expedited decision by
15 Sep, 2016. (B4)
2
M/s My Home
Industries Ltd
Limestone 156.586 Choutapally,
Mattampally,
Mandal, Nalgonda
1.11.2013 Pending with MoEF
for final orders to be
issued. Presentation
and
recommendation
already done on
22.03.2016. May be
expedited by 15Sep,
2016. EC Granted
14.10.2016 (A2)