art gallery of nsw expansion - sydney modern

23
2302897U ART GALLERY OF NSW EXPANSION PROJECT - SYDNEY MODERN SEARS ESD SSDA REPORT 1 NOVEMBER 2017

Upload: others

Post on 22-Jan-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

2302897U

ART GALLERY OF NSW EXPANSION PROJECT - SYDNEY MODERN SEARS ESD SSDA REPORT

1 NOVEMBER 2017

``

ART GALLERY OF NSW EXPANSION PROJECT- SYDNEY MODERN Prepared for Art Gallery NSW Art Gallery Rd The Domain Sydney NSW 2000

Project: 2302897U Date: 1/11/2017

WSP Australia Pty Ltd Level 27, 680 George Street Sydney NSW 2000

Phone: 02 9272 5100 www.wsp.com

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

Q U A L I T Y M A N A G E M E N T S I G N A T U R E S

PREPARED BY

Sean Holmes, Senior Sustainability Consultant – WSP | Parsons Brinckerhoff

REVIEWED BY

Richard Palmer,

Associate Director – WSP | Parsons Brinckerhoff

Paul Stoller Director – atelier ten

ISSUE/REVISIO

N

FOR ISSUE FOR ISSUE FOR ISSUE FOR ISSUE FOR ISSUE FOR ISSUE

Remarks Draft DA Report Revised Draft DA

Report

Revised Draft DA

Report

Revised Draft DA

Report

Final DA Report Final DA Report

(updated figures)

Date 18/04/2016 02/06/2016 21/06/2016 20/09/2017 11/10/2017 1/11/2017

Prepared by SNH SNH SNH GVH GVH GVH

Checked by RNP / PDS RNP / PDS RNP / PDS RNP / PDS RNP / PDS RNP / PDS

Authorised by RNP RNP RNP RNP RNP RNP

Project

number

SYD1508900 SYD1508900 SYD1508900 2302897U 2302897U 2302897U

Report number 01 02 02 03 04 05

File reference J:\projects\SYD1

528900\0 -

General\2 -

Project Reports

J:\projects\SYD15

28900\0 -

General\2 - Project

Reports

J:\projects\SYD15

28900\0 -

General\2 - Project

Reports

\\corp.pbwan.net\A

NZ-

DFS\Data\Sustain

ability\Projects\230

2897U - Sydney

Modern\0 -

General\2 - Project

Reports

\\corp.pbwan.net\A

NZ-

DFS\Data\Sustain

ability\Projects\230

2897U - Sydney

Modern\0 -

General\2 - Project

Reports

\\corp.pbwan.net\A

NZ-

DFS\Data\Sustain

ability\Projects\230

2897U - Sydney

Modern\0 -

General\2 - Project

Reports

ii

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

TABLE OF CONTENTS ART GALLERY OF NSW EXPANSION PROJECT -

SYDNEY MODERN ......................................... 1

1 INTRODUCTION ............................................. 2

1.1 PURPOSE OF REPORT .................................... 2

1.2 PROJECT BRIEF .............................................. 2

1.3 PROJECT DESCRIPTION ................................. 3

1.4 SEARS REQUIREMENTS ................................. 3

1.5 BIZOT REPORT ................................................ 3

1.6 LIMITATIONS .................................................... 3

2 ESD PRINCIPLES AND PERFORMANCE ..... 4

2.1 SITE, LANDSCAPE AND URBAN ECOLOGY .. 4

2.2 INDOOR ENVIRONMENTAL QUALITY AND CONDITION CONTROL ............................................... 5

2.3 RESOURCE EFFICIENCY | ENERGY AND CARBON ..................................................................... 6

2.4 RESOURCE EFFIENCY | WASTE AND MATERIALS ................................................................ 7

2.5 RESOURCE EFFICIENCY | WATER ................. 8

2.6 EMISSIONS AND POLLUTION ......................... 9

2.7 TRANSPORT AND MOBILITY .......................... 9

2.8 CONSTRUCTION AND OPERATIONAL MANAGEMENT ........................................................... 9

2.9 RESILIENCE ..................................................... 9

3 GREEN STAR ASSURANCE AND CERTIFICATION ............................................ 10

3.1 GREEN STAR DESIGN AND AS-BUILT ......... 10

4 CONCLUSION ................................................. 1

4.1 SUMMARY OF RESPONSES TO SEARS ........ 1

APPENDIX 1: GREEN STAR D&AB 5 STAR SCORECARD ............................................................ 11

1

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

E X E C U T I V E S U M M A R Y

This report describes the ESD strategy for the Art Gallery of NSW Expansion Project – Sydney Modern, here on in referred to as the Sydney Modern Project, for the purposes of the State Significant Development Application (SSDA).

This report identifies the project goals for sustainable performance, the key principles that underpin sustainability and the initiatives by which it is embedded in both the design and the proposed operation of the Gallery.

The Art Gallery of New South Wales (AGNSW) is also driving the following initiatives:

Conservation of art collection

Integration and multi-functionalism

Green Walls and Roofs.

Fittings and Fixtures

Water Efficiency / Harvesting

Passive and active design

Whole of Life Objectives

The principles of ecologically sustainable development (ESD) have been embedded in each of the major components of the Sydney Modern Project.

The site selection has embodied the precautionary principle by selecting substantially disturbed land for the building location – partially straddling a motorway and embedded within historic fuel bunkers.

In this way, the serious environmental impacts of green field development are avoided and the ecological value of the precinct is enhanced. High value trees have been retained as much as possible, further mitigating site impacts.

The native landscaping strategy further conserves and enhances the bio-diversity and ecological integrity of the precinct.

The built form and services support a resource-efficient strategy to enhance the whole of life resource consumption of the project. The consideration of zero-carbon energy, low-impact materials, operational waste strategy to embed zero-waste principles and making use of alternative water sources have been primary design drivers for the project.

The project embeds principles for inter-generational equity, by curating, storing and enhancing the cultural environment and rehabilitating the ecological environment for the benefit of future generations.

The headline ESD initiatives are identified in the adjacent diagram.

Source: ESD Concept Design Report, Atelier ten | WSP

Source: Concept Landscape Design, McGregor Coxall Source: Preliminary Energy Analysis Report, Atelier ten | WSP

2

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

1 INTRODUCTION

1.1 PURPOSE OF REPORT

This report describes the ESD strategy for the Sydney Modern Project (SMP) at the Art Gallery NSW (AGNSW) for the purposes of the State Significant Development Application (SSDA).

This report identifies the project goals for sustainable performance, the key principles that underpin sustainability and the initiatives by which it is embedded in both the design and the proposed operation of the Gallery.

1.2 PROJECT BRIEF

The Sydney Modern Project at the Art Gallery of New South Wales has the following vision:

From its base in Sydney, the Art Gallery of New South Wales is dedicated to serving the widest possible audiences a centre of excellence for the collection, preservation, documentation, interpretation and display of Australian and international art, and as a forum for scholarship, art education and the exchange of ideas.

The Art Gallery of New South Wales (AGNSW) is also driving the following initiatives:

Conservation of art collection— incorporating a design which allows an area to provide excellent indoor environment quality to suit the art in the space at any point in time.

Integration and multi-functionalism—A holistic and integrated approach which builds on increased awareness of site opportunities, form and function to address a broad range of sustainability objectives.

Green Walls and Roofs—the integration of landscape onto walls and roofs to offer a diverse range of spatial and microclimatic opportunities, giving consideration to the risks associated with water features above Gallery spaces.

Fittings and Fixtures—to be selected and utilised to reduce energy and resource costs, including in manufacture, operations and in recycling at end of life.

Water Efficiency / Harvesting—Integration of water capture and reuse systems into design.

Passive and active design —the design will explore ways to integrate innovative solutions to the following:

Spatial innovation to minimise energy, achieve display conditions without compromising display flexibility.

Increased energy efficiency.

Daylight harvesting for improved indoor environment quality and reduced reliance on electric lighting.

Utilising renewable energy.

Efficient use of reused and potable water.

Reduce or eliminate toxic and harmful substances on the site.

Improved interior and exterior working environments for increased productivity and health.

Maintain visual amenity

Use of natural resources efficiently.

Selection of materials, systems and products based on lifecycle environmental impacts

Increased use of materials and products with recycled content.

Reduce harmful waste products throughout construction.

Use maintenance and operations practices that reduce or minimise harmful effects on people and the environment.

Provision of cardboard, glass and paper recycling spaces.

Whole of Life Objectives —the design will consider whole of life factors in the design development and decision making on the project.

Figure 1: Sydney Modern Project Landscape Plan (top), source: Concept Landscape Design, McGregor Coxall and

Thermal 3D Model (bottom), source: ESD Preliminary Energy Analysis Report, Atelier ten | WSP

3

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

1.3 PROJECT DESCRIPTION

Detailed description of works:

The Art Gallery of NSW proposes to undertake a major expansion of the existing art gallery in the eastern part of the Royal Botanic Gardens and Domain. The expansion is located north of the existing gallery, partly extending over the Eastern Distributor land bridge and includes a disused Navy fuel bunker located to the north east of this land bridge.

The new expansion, known as the Sydney Modern Project, comprises a new entry plaza, new exhibition spaces, shop, food and beverage facilities, visitor amenities, art research and education spaces, new roof terraces and landscaping and associated site works and infrastructure, including loading and service areas, services infrastructure and an ancillary seawater heat exchange system.

Development consent is sought for:

Site preparation works, including:

Site clearing, including: demolition of former substation, part of road surfaces, kerbs and traffic islands, pedestrian crossings, foot paths, retaining walls, stairs, and part of disused underground former Navy fuel bunkers;

Tree removal;

Excavation and site earthworks;

Remediation works;

Construction of the Sydney Modern Project comprising:

Covered public plaza;

Entry pavilion and five building levels following the site topography down to Lincoln Crescent;

Retention of part of existing disused underground former Navy fuel bunker for use as gallery space and support spaces;

Art gallery spaces;

Outdoor terraces;

Shop, café and restaurant;

Multipurpose space;

Education spaces;

Ground level loading dock (accessed via Lincoln Crescent) with associated workshops, service parking, plant, and storage areas.

New open staff and administration visitor carpark to rear of art gallery building;

Landscaping and public domain improvements including:

Continuation of the east-west pedestrian link between the Domain and Woolloomooloo Bay, including dedicated lift structure for disability access;

Hard and soft landscaping to roof terraces;

Planter beds and new pathways;

Increased landscaped area to forecourt of existing Art Gallery building;

Relocation of selected trees to the south-eastern corner of the site;

Sound barrier to edge of land bridge;

Upgrade works to part of Art Gallery Road, Cowper Wharf Road, Mrs Macquaries Road, and Lincoln Crescent, including new pedestrian crossings;

Provision of vehicle drop off points including a taxi stand, private vehicle drop off and bus/coach drop off, at Art Gallery Road;

Installation of an ancillary seawater heat exchange system to act as the new building’s cooling system, adjacent to and within Woolloomooloo Bay;

Diversion, extension and augmentation of physical infrastructure and utilities as required.

1.4 SEARS REQUIREMENTS

The most recent Secretary’s Environmental Assessment Requirements (SEARS) were provided on 8 June 2016 for the Sydney Project. Refer to Table 1 for a list of the requirements relating to Ecological Sustainable Development and a cross reference of where they are addressed in this report.

1.5 BIZOT REPORT

The BIZOT Report is an assessment of environmental standards for the conservation of art developed in 2014.

In the absence of a shared global standard on environmental sustainability for museums, it represents the current best practice in balancing environmental sustainability and conservation priorities for galleries and museums.

Specifically, it identifies a range of internal conditions that are wider than previous international practice and proposed as acceptable for inter-intuition lending.

Furthermore, it identifies a range of energy intensity benchmarks against which the SMP will be assessed.

1.6 LIMITATIONS

This analysis is based on the best available information at the time of assessment.

The Green Star targets do not imply that certification has been achieved. The project is registered for a Green Star rating, but final certification depends on third party assessment of Design and As-built Documentation.

Final performance of the building and its systems will depend on its final design, implementation and operation.

Table 1 SEARS Requirements

Secretary’s Environmental Assessment RequirementsReference in SEARS ESD

Report

Relevant Green Star

Categories

Detail how ESD principles (as defined in clause 7(40 of Schedule 2 of the EP&A Regulation

2000) w ill be incorporated in the design, construction and ongoing phases of the development.

The principles of ecologically sustainable development are as follow s:

(a) the precautionary principle, namely, that if there are threats of serious or irreversible

environmental damage, lack of full scientif ic certainty should not be used as a reason for

postponing measures to prevent environmental degradation. In the application of the

precautionary principle, public and private decisions should be guided by:

(i) careful evaluation to avoid, w herever practicable, serious or irreversible damage to the

environment, and

(ii) an assessment of the risk-w eighted consequences of various options.

Executive Summary and

Section 2.1 and Section 2.9

Land Use and Ecology,

Management

(b) inter-generational equity, namely, that the present generation should ensure that the health,

diversity and productivity of the environment are maintained or enhanced for the benefit of

future generations.

Section 2 All categories

(c) conservation of biological diversity and ecological integrity, namely, that conservation of

biological diversity and ecological integrity should be a fundamental consideration.Section 2.1 Land Use and Ecology

(d) improved valuation, pricing and incentive mechanisms, namely, that environmental factors

should be included in the valuation of assets and services, such as:

(i) polluter pays, that is, those w ho generate pollution and w aste should bear the cost of

containment, avoidance or abatement,

(ii) the users of goods and services should pay prices based on the full life cycle of costs of

providing goods and services, including the use of natural resources and assets and the

ultimate disposal of any w aste,

(iii) environmental goals, having been established, should be pursued in the most cost effective

w ay, by establishing incentive structures, including market mechanisms, that enable those best

placed to maximise benefits or minimise costs to develop their ow n solutions and responses to

environmental problems.

Section 2.3 and Section 2.5 Energy, Water, Management

Outline resource, energy and w ater initiatives, including the use of sustainable technologies

and/or renew able energy

Resource – Section 2.3,

Section 2.4 and Section 2.5

Energy – Section 2.3

Water – Secton 2.5

Sustainable Technologies/

Renew able Energy –

Section 2.3

Resource – Water,

Materials, Energy,

Management

Energy – Energy

Water – Water

Sustainable Technologies/

Renew able Energy – Energy

Provide an integrated Water Management Plan including alternative w ater supply, proposed

end uses of potable and non-potable w ater, w ater sensitive urban design and w ater

conservation measures

Section 2.5 Water

4

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

2 ESD PRINCIPLES AND PERFORMANCE

2.1 SITE, LANDSCAPE AND URBAN ECOLOGY

The site selection for the Sydney Modern Project is a foundational contributor to the sustainability strategy. The new project is situated on:

Partially over the land bridge partially over the Eastern Distributor Highway; and

Completely over former WWII fuel bunker adjacent to Lincoln Crescent.

Both elements are covered by a thin layer of soil and a mono culture of lawn with a few trees.

The new gallery spaces are embedded within a structured mostly native landscape supporting a biodiversity node with diverse botanical species selection. The integration of green infrastructure with the landscape provides micro-habitats for a broad range of fauna and supports the broader biodiversity of the Domain in a manner that the existing lawn is unable to.

Green infrastructure is the engineered approach to landscape that provides communities with effective storm-water management systems – regulating both the quantity and quality of overland flows while also providing high amenity public space and local ecology hotspots. Green infrastructure – also referred to as water-sensitive urban design (WSUD) – is composed of a wide range of urban water management practices:

Erosion & sediment control

Rainwater tanks

Swales

Green roofs

Constructed wetlands, infiltration systems

Water harvesting and reuse schemes

The location of the new gallery on existing infrastructure and enhancement of local ecological value play to Precautionary Principle and support the climate resilience strategy for the Sydney Modern Project.

Land Bridge Fuel Bunkers

New intensive native landscape Concept design green roof elements New intensive native landscape

Figure 2: Existing site for the Sydney Modern Project (top), source: google earth mark up and Sydney Modern Project Landscape Plan (bottom), source: Concept Landscape Design, McGregor Coxall

5

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

2.2 INDOOR ENVIRONMENTAL QUALITY AND CONDITION CONTROL

HEALTHY FOR ART

The provision of an exceptional indoor environment for the storage and exhibition of art is of primary importance for the Gallery.

Achieving a design that meets the lending criteria of the world’s leading art institutions, while also embedded energy efficiency and natural light into the gallery are important considerations for the SMP.

There are three over-riding indoor environmental quality considerations including:

Natural light | Providing natural light, while mitigating the impact of light on art

Temperature Control | thermal stability and conditioning

Humidity Control | hydroscopic stability and conditioning

DESIGN PRINCIPLES

The design principles for providing an indoor environment that is healthy for people and meets the requirements for art conservation are:

Façade that balances natural light admission and control

HVAC system and controls to provide sufficient fresh air and stable climate conditions

Lighting strategy that is integrated with the natural light approach.

Provision of thermal mass to surround close control galleries

Insulation in addition to minimum code requirements

The design is underpinned by the outcomes of the BIZOT report, which identify how flexibility can be introduced into spaces for art.

The BIZOT report also provides for a global benchmarking framework for the combination of condition control and energy efficiency.

DESIGN CONSIDERATIONS:

The key design considerations which inform the indoor environment are:

Glazing selection (recommended VLT < 50%) or secondary screening if glazing has VLT > 50%

Provision of blinds to control direct sunlight

Provision of gauze curtains to manage daylight

Space planning, embedding close control zones within broader control zones rather than direct exposure to the external environment

Dual mode conditioning which is able to provide close control when required, and broader control when not required

Partitioning to separate close control zones from broader control zones for night-time fresh air set-back

The proper control of fresh air in gallery spaces and associated condition and humidity risk that it brings.

HEALTHY FOR PEOPLE

Beside the requirements for art, the SMP is also a space for people. There are a number of critical considerations for how the experience and health of visitors and employees is supported through the design:

Visual and physical connection to the outside environment;

Thermal comfort in both naturally ventilated and air-conditioned spaces through excellent solar control;

Low-pollutant finishes (VOCs & formaldehyde);

Visitor spaces with high air quality;

Transition from the outside environment through thresholds of increasing climate control to fully controlled;

Careful spatial transitions to maintain visual comfort without suddenly exposing visitors to bright light;

VLT 70

VLT50

Mixed mode: natural ventilation or comfort conditioning (20-25° with no humidity control)

Gallery set-back conditioning (broader set-pots TBC)

Gallery close control (Temp 21° ±1°; RH 50% ±5%)

Comfort Conditioning: 20-25°

Figure 3: Daylight analysis exploring balancing daylight for art conservation and

comfortable viewing, source Concept Daylight Analysis, Atelier ten | WSP Figure 4 Diagram of stepped climate control strategy to increase thermal comfort of visitors and reduce gallery energy use

for space conditioning, source: Concept Mechanical Model, Steensen Varming

6

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

2.3 RESOURCE EFFICIENCY | ENERGY AND CARBON

DESIGN PRINCIPLES

The energy performance for the SMP has been benchmarked against the existing gallery performance, a global peer group of galleries and the findings of the BIZOT report into gallery conditioning and energy efficiency.

The energy efficiency and carbon emissions reduction strategy for the SMP is underpinned by a number of primary principles:

High performance building fabric – insulation, thermal mass and glazing

Natural light and daylight harvesting

Set-back air-conditioning for all spaces to avoid over-conditioning when not required

Efficient HVAC and lighting equipment selections

Thermal hierarchy spatial planning - layering tightly controlled spaces within less closely controlled spaces.

In spaces where conditioned control is not required, natural ventilation and mixed mode systems have been allowed for.

CONCEPT DESIGN PERFORMANCE

The initial analysis of the energy performance has been undertaken in conjunction with the NCC section J JV-3 methodology. Analysis has shown substantial sensitivity to the amount of fresh air supplied to the galleries. Design analysis has been undertaken to show the energy benefit of supplying fresh air according to an international ventilation standard specific for gallery spaces (ASHRAE 62.1) rather than the conventional Australian ventilation practice (AS1168).

The energy performance of the baseline model (DTS faced and services); compliance model (Proposed Façade and DTS Services) and the Design model are identified in the adjacent figure.

All are referenced against the BIZOT performance averages and the existing gallery performance.

SUMMARY

The proposed building facade and services are shown to comply with the performance requirements of the NCC Section J by the JV-3 methodology.

The proposed gallery achieves an energy efficiency improvement of approximately 20% compared to the ASHRAE 62 reference building.

The modelled performance corresponds with the median BIZOT performance benchmark and substantially reduces the energy intensity benchmark of the current gallery.

Further improvement is likely with design opportunities in optimising heat recovery and the treatment of the substantial fresh air load.

The energy analysis to date does not take account of on-site generation, which is dealt with in following sections.

Figure 5 Predicted Energy Consumption, source: ESD Concept Design Report and Preliminary Energy Analysis, Atelier ten | WSP

7

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

RENEWABLE ENERGY AND GREEN POWER

On-site renewable energy and the procurement of low-carbon electricity is a priority for the Gallery.

A range of options have been considered, including:

Building Integrated PV integrated with some of the SMP pavilion roofs

Procurement of Green power.

A benchmarking study has been undertaken and referenced against the existing gallery energy consumption data for the following options.

A mix of conventional PV and Building Integrated PV (providing in the order of 250kW, 1000m2)

Purchase of zero-carbon power (GreenPower equivalent to conventional PV output)

The cost-benefit analysis indicates that conventional PV provides the best whole-of-life performance; BIPV provides the best aesthetic solution and the purchase of GreenPower provides the greatest scope for deep carbon emissions reduction, but at the highest cost.

ENERGY EFFICIENCY OPPORTUNITIES

Many further energy efficiency measures (EEMs) have been loosely or actively considered for the SMP.

The analysis work to date has identified several EEMs that have a high potential to significantly reduce energy use or increase thermal comfort and the stability of internal conditions.

The EEMs that are now under further study are:

Architecture

Enhanced architectural shading (broader overhangs, lower SHGC glazing)

Heating, Ventilation and Air-Conditioning

Ventilation heat recovery (sensible and enthalpy for further dehumidification)

Heat recovery cooling plant

Labyrinth thermal storage and OA pre-treatment

Controls

Gallery night setback of supply air volume

Gallery climate conditions loosened for a portion of the year.

2.3.1

2.4 RESOURCE EFFIENCY | WASTE AND MATERIALS

DESIGN PRINCIPLES

The design principles for waste and materials at the SMP are:

Reducing the resource and climate intensity of the major building fabric materials;

Reducing toxicity in building materials and finishes for a healthier indoor environment and mitigating disposal pollution risks;

Avoiding the use of materials that deplete non-renewable resources;

Supporting a whole-of-life or chain-of-custody approach to material procurement.

DESIGN CONSIDERATIONS:

The key waste and materials considerations which inform the design are:

Use on non-cementitious materials in concrete

Increased recycled content in steel

FSC-certified timber

Avoidance of PVC where possible, and use of PVC complying with best practice standards where it must be used.

The Gallery is exploring a range of operational materials and waste considerations for managing the substantial material consumption associated with exhibitions.

Considerations include:

Cradle-to-grave or cradle-to-cradle stewardship requirements in materials procurement; and

Durability requirements for temporary gallery walls to allow for greater in-house re-use.

Other opportunities for closed-loop approaches to waste include:

Food-waste to compost for landscaping

Environmental Product Declarations for fit-out and finishes; and

Local sourcing.

Approximately 1000 m² PV Array

Figure 6 Concept PV provision, source: Concept Architectural Design, SANAA | Architectus

8

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

Rooftop Collection for Re-use in

Existing Cooling Towers

Harbour Heat Rejection in Woolloomooloo

Bay replacing new cooling towers

2.5 RESOURCE EFFICIENCY | WATER

DESIGN PRINCIPLES

The design principles for the integrated management of water for the SMP are:

Water consumption is reduced as far as possible through efficient equipment, fitting and fixture selections;

The majority of non-potable water demand (existing gallery cooling towers) to be met through captured rain- and storm-water and/or recycled water;

Harbour heat rejection allows for no new cooling towers being installed, saving 6.3ML/year.

The landscape to provide local ecological hot-spot through regenerative native landscaping that integrates with the water cycle; and

DESIGN CONSIDERATIONS:

The key design considerations which inform the integrated water cycle management plan are:

Best practice fittings, fixtures & appliances (low-flow fittings, dual flush toilets);

Rainwater capture from all rooftops for re-use in existing cooling towers;

200kL rainwater storage tank for use in existing cooling towers;

150KL rainwater storage tank and 150KL stormwater detention tank for onsite irrigation;

Harbour heat rejection in lieu of evaporative cooling towers for the Sydney Modern Project conditioning systems to reduce to reduce water demand for the new gallery spaces – potentially reducing 6.3ML/year.

Future considerations include collaboration with other institutions to assess the feasibility of resource sharing. Specific opportunities include The Royal Botanical Gardens, Eastern Distributor storm-water management (RMS), State Library, NSW Parliament House and other neighbouring State Government agencies.

FIXTURES AND FITTINGS

A simple way to reduce potable and recycled water consumption is through the use of efficient fixtures and fittings. The design team anticipates specifying fixtures with the following Water Efficiency Labelling and Standards Scheme (WELS) performance levels:

Showers – 3 Star WELS rating, 6.0L/min

Taps – 6 Star WELS rating, 4.5L/min

Pans – 5 Star WELS rating, 3.0L/flush

Urinals – 6 star WELS, ,0.8L/flush

Dishwashers – 6 Star WELS rating, 9.8L/cycle

STORMWATER QUALITY

There is an opportunity to address the quality of the storm water entering the public infrastructure. An efficient filtration system including landscape elements is being designed and implemented to ensure that the water is of a high quality and will not cause adverse environmental impacts downstream. Typical pollutants present in storm-water vary depending on the run off surface.

The target pollutant reduction for the SMP is:

Total Suspended Solids to 90%

Gross Pollutants to 95%

Total Nitrogen to 60%

Total Phosphorus to 70%

Total Petroleum Hydrocarbons to 90%

Free Oils to 98%.

Figure 7: Water Strategy: Rainwater Harvesting and Harbour Heat Rejection, source: Concept Landscape Design, McGregor Coxall (mark up by Atelier ten | WSP)

9

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

2.6 EMISSIONS AND POLLUTION

DESIGN PRINCIPLES

Reducing the polluting emissions from the SMP are a priority. The direct emissions from the site have an impact on the ecosystems of Woolloomooloo Bay and the local ecosystems in the Domain and Royal Botanic Gardens, including extensive nocturnal avi-fauna (bats and birds).

The principles for pollution reduction respond directly to these sensitive ecosystems and are:

Stormwater quantity and quality management with water sensitive urban design and collection tanks;

No artificial light directed into the night sky;

No new cooling towers due to harbour heat rejection, so reduced legionella risk.

2.7 TRANSPORT AND MOBILITY

DESIGN PRINCIPLES

The SMP includes provision for improved public access and reduced reliance on cars for staff and visitors alike.

The key principles for mobility are:

Effectively connecting Woolloomooloo to the city;

Providing minimal car parking;

Providing extensive bicycle storage for visitors and staff; and

Providing end-of-trip facilities for staff.

The project is well connected to the CBD by key pedestrian links, with good walkability to Martin Place and St James stations.

Disabled access through and across the site is of particular importance and the SMP plays a crucial role in providing equitable access to the galleries as well as across the site.

2.8 CONSTRUCTION AND OPERATIONAL MANAGEMENT

CONSTRUCTION MANAGEMENT

There are a number of important considerations in the construction management for the SMP. While the procurement of a building contractor is yet to commence, there will be a number of core requirements embedded within the procurement documentation:

Environmental management (ISO14001 and a compliant EMS)

Best practice commissioning and building tuning

Contractor Education for sub-contractors

Detailed metering and monitoring systems (during construction and operation)

INSTITUTIONAL SUSTAINABILITY

Furthermore, the Gallery is exploring institutional opportunities to further embed sustainability principles in the operational management of the SMP:

Financial Transparency – disclosure of the sustainability costs for the project to the Green Building Council of Australia to inform industry development

Institutional commitment to operational and end-of-life waste performance

Culture, Heritage and Identity – embedding interpretation of contemporary and indigenous culture, heritage and identify within the SMP project;

Local Procurement

2.9 RESILIENCE

CLIMATE CHANGE

Climate change is a critical consideration for long-term projects, especially in coastal areas.

Key climate considerations include:

Flood thresholds at Lincoln Crescent to take account of the 2100 climate change sea level rise projections (passive and active mitigation options are available).

Location of critical electrical infrastructure and emergency generation to above 2100 flood levels to maintain systems in the event of substantial flooding events;

Passive building performance to provide thermal stability for artwork in the event of elevated temperatures or utilities disruptions.

Furthermore, the detailed design of the pavilion roofs will take the potential for higher-then-usual wind loading in line with predicted climate change impacts.

A detailed climate adaptation plan will be undertaken in subsequent design phases to identify the detailed design considerations to mitigate these key climate risks.

10

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

3 GREEN STAR ASSURANCE AND CERTIFICATION

3.1 GREEN STAR DESIGN AND AS-BUILT

Green Star Design and As-built is an industry tool for benchmarking sustainability performance for the built environment.

The SMP is registered for a Green Star rating with the Green Building Council of Australia. The project is seeking a 5-star rating through a mix of design and construction sustainability initiatives.

Furthermore, the options to exceed the 5 star rating are being considered through the procurement of low-impact goods and low-carbon energy.

The 5-star strategy is noted in the scorecard in Appendix A and summarised in Table 2 below.

Table 2 Summary of Green Star Scorecard

Category Points Available

5 Star D&AB

Management 14 14

Indoor Environmental Quality

17 11

Energy 22 9

Transport 10 7

Water 12 6

Materials 14 6

Land Use & Ecology

6 4

Emissions 5 4

Innovation 10 10

Total 100 71

11

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

4 CONCLUSION

The principles of ecologically sustainable development have been embedded in each of the major components of the Sydney Modern Project.

The site selection has embodied the precautionary principle by selecting substantially disturbed land for the building location – partially straddling a motorway and embedded within historic fuel bunkers.

In this way, the serious environmental impacts of green field development are avoided and the ecological value of the precinct is enhanced. High value trees have been retained, further mitigating site impacts.

The native landscaping strategy further conserves and enhances the bio-diversity and ecological integrity of the precinct.

The built form and services support a resource-efficient strategy to enhance the whole of life resource consumption of the project. The consideration of zero-carbon energy, low-impact materials, operational waste strategy to embed zero-waste principles and making use of alternative water sources have been primary design drivers for the project.

The project embeds principles for inter-generational equity, by curating, storing and enhancing the cultural environment and rehabilitating the ecological environment for the benefit of future generations.

The headline ESD initiatives are identified in the adjacent diagram.

Figure 8 ESD Summary Section, source: ESD Concept Design Report, Atelier ten | WSP

12

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

4.1 SUMMARY OF RESPONSES TO SEARS

.

Secretary’s Environmental Assessment RequirementsReference in SEARS ESD

Report

Relevant Green Star

Categories

Detail how ESD principles (as defined in clause 7(40 of Schedule 2 of the EP&A Regulation

2000) w ill be incorporated in the design, construction and ongoing phases of the development.

The principles of ecologically sustainable development are as follow s:

(a) the precautionary principle, namely, that if there are threats of serious or irreversible

environmental damage, lack of full scientif ic certainty should not be used as a reason for

postponing measures to prevent environmental degradation. In the application of the

precautionary principle, public and private decisions should be guided by:

(i) careful evaluation to avoid, w herever practicable, serious or irreversible damage to the

environment, and

(ii) an assessment of the risk-w eighted consequences of various options.

Executive Summary and

Section 2.1 and Section 2.9

Land Use and Ecology,

Management

(b) inter-generational equity, namely, that the present generation should ensure that the health,

diversity and productivity of the environment are maintained or enhanced for the benefit of

future generations.

Section 2 All categories

(c) conservation of biological diversity and ecological integrity, namely, that conservation of

biological diversity and ecological integrity should be a fundamental consideration.Section 2.1 Land Use and Ecology

(d) improved valuation, pricing and incentive mechanisms, namely, that environmental factors

should be included in the valuation of assets and services, such as:

(i) polluter pays, that is, those w ho generate pollution and w aste should bear the cost of

containment, avoidance or abatement,

(ii) the users of goods and services should pay prices based on the full life cycle of costs of

providing goods and services, including the use of natural resources and assets and the

ultimate disposal of any w aste,

(iii) environmental goals, having been established, should be pursued in the most cost effective

w ay, by establishing incentive structures, including market mechanisms, that enable those best

placed to maximise benefits or minimise costs to develop their ow n solutions and responses to

environmental problems.

Section 2.3 and Section 2.5 Energy, Water, Management

Outline resource, energy and w ater initiatives, including the use of sustainable technologies

and/or renew able energy

Resource – Section 2.3,

Section 2.4 and Section 2.5

Energy – Section 2.3

Water – Secton 2.5

Sustainable Technologies/

Renew able Energy –

Section 2.3

Resource – Water,

Materials, Energy,

Management

Energy – Energy

Water – Water

Sustainable Technologies/

Renew able Energy – Energy

Provide an integrated Water Management Plan including alternative w ater supply, proposed

end uses of potable and non-potable w ater, w ater sensitive urban design and w ater

conservation measures

Section 2.5 Water

Art Gallery of NSW Expansion - Sydney Modern WSP | Parsons Brinckerhoff Art Gallery NSW SYD1508900 01/11/2017

APPENDIX 1: GREEN STAR D&AB 5 STAR SCORECARD

Project:Core Points

Available

Total Score

Targeted

Total Points

Awarded

Total Points

TBC

Targeted Rating: 100 71.0 0.0 0.0

CATEGORY / CREDIT AIM OF THE CREDIT / SELECTION CODE CREDIT CRITERIAPOINTS

AVAILABLE

POINTS

TARGETED

POINTS

AWARDED

POINTS

TBCOUTCOME ASSESSMENT COMMENTS

Management 14

Green Star Accredited

Professional

To recognise the appointment and active involvement of a

Green Star Accredited Professional in order to ensure that

the rating tool is applied effectively and as intended.

1.0 Accredited Professional 1 1

2.0 Environmental Performance Targets - Complies

2.1 Services and Maintainability Review 1 1

2.2 Building Commissioning 1 1

2.3 Building Systems Tuning 1 1

2.4 Independent Commissioning Agent 1 1

Adaptation and ResilienceTo encourage and recognise projects that are resilient to

the impacts of a changing climate and natural disasters.3.1 Implementation of a Climate Adaptation Plan 2 2

4.1 Building Operations and Maintenance Information 1 1

4.2 Building User Information 1 1

5.1 Environmental Building Performance 1 1

5.2 End of Life Waste Performance 1 1

6.0 Metering - Complies

6.1 Monitoring Systems 1 1

7.0 Environmental Management Plan - Complies

7.1 Formalised Environmental Management System 1 1

8A Performance Pathway - Specialist Plan 1 1

8B Prescriptive Pathway - Facilities -

Total 14 14 0 0

17

Commitment to

Performance

To recognise practices that encourage building owners,

building occupants and facilities management teams to set

targets and monitor environmental performance in a

collaborative way.

Metering and MonitoringTo recognise the implementation of effective energy and

water metering and monitoring systems.

Construction

Environmental

Management

To reward projects that use best practice formal

environmental management procedures during

construction.

Indoor Environment Quality

Operational Waste Performance Pathway

Building Information

To recognise the development and provision of building

information that facilitates understanding of a building's

systems, operation and maintenance requirements, and

environmental targets to enable the optimised performance.

Green Star - Design & As Built Scorecard

Sydney Modern Project

5 Star - Australian Excellence

Commissioning and

Tuning

To encourage and recognise commissioning, handover and

tuning initiatives that ensure all building services operate to

their full potential.

9.1 Ventilation System Attributes 1 1

9.2 Provision of Outdoor Air 2

9.3 Exhaust or Elimination of Pollutants 1

10.1 Internal Noise Levels 1 1

10.2 Reverberation 1

10.3 Acoustic Separation 1 1

11.0 Minimum Lighting Comfort - Complies

11.1 General Illuminance and Glare Reduction 1 1

11.2 Surface Illuminance 1 1

11.3 Localised Lighting Control 1 1

12.0 Glare Reduction - Complies

12.1 Daylight 2 1

12.2 Views 1 1

13.1 Paints, Adhesives, Sealants and Carpets 1 1

13.2 Engineered Wood Products 1 1

14.1 Thermal Comfort 1 1

14.2 Advanced Thermal Comfort 1 0

Total 17 11 0 0

22

15A.0 Conditional Requirement: Prescriptive Pathway -

15A.1 Building Envelope -

15A.2 Glazing -

15A.3 Lighting -

15A.4 Ventilation and Air-conditioning -

Energy

Greenhouse Gas

EmissionsE. Modelled Performance Pathway

Visual ComfortTo recognise the delivery of well-lit spaces that provide high

levels of visual comfort to building occupants.

Indoor PollutantsTo recognise projects that safeguard occupant health

through the reduction in internal air pollutant levels.

Thermal ComfortTo encourage and recognise projects that achieve high

levels of thermal comfort.

Lighting ComfortTo encourage and recognise well-lit spaces that provide a

high degree of comfort to users.

Indoor Air QualityTo recognise projects that provide high air quality to

occupants.

Acoustic ComfortTo reward projects that provide appropriate and comfortable

acoustic conditions for occupants.

15A.5 Domestic Hot Water Systems -

15A.6 Building Sealing -

15A.7 Accredited GreenPower -

15B.0 Conditional Requirement: NatHERS Pathway -

15B.1 NatHERS Pathway -

15C.0 Conditional Requirement: BASIX Pathway -

15C.1 BASIX Pathway -

15D.0 Conditional Requirement: NABERS Pathway -

15D.1 NABERS Energy Commitment Agreement Pathway -

15E.0Conditional Requirement: Reference Building

Pathway- Complies

15E.1 Comparison to a Reference Building Pathway 20 8

16A Prescriptive Pathway - On-site Energy Generation -

16B Performance Pathway - Reference Building 2 1

Total 22 9 0 0

Transport 10

17A.1 Performance Pathway 0

17B.1 Access by Public Transport 3 3

17B.2 Reduced Car Parking Provision 1 1

17B.3 Low Emission Vehicle Infrastructure 1 1

17B.4 Active Transport Facilities 1 1

17B.5 Walkable Neighbourhoods 1 1

Total 7 7 0 0

Water 12

Sustainable Transport Prescriptive Pathway

Greenhouse Gas

EmissionsE. Modelled Performance Pathway

Peak Electricity Demand

ReductionPerformance Pathway

18A.1 Potable Water - Performance Pathway 0 0

18B.1 Sanitary Fixture Efficiency 1 1

18B.2 Rainwater Reuse 1 1

18B.3 Heat Rejection 2 2

18B.4 Landscape Irrigation 1 1

18B.5 Fire System Test Water 1 1

Total 6 6 0 0

Materials 14

19A.1 Comparative Life Cycle Assessment 0 0

19A.2 Additional Life Cycle Impact Reporting 0 0

19B.1 Concrete 3 1

19B.2 Steel 1 1

19B.3 Building Reuse 4 0

20.1 Structural and Reinforcing Steel 1 1

20.2 Timber Products 1 1

20.3Permanent Formwork, Pipes, Flooring, Blinds and

Cables1 1

Sustainable ProductsTo encourage sustainability and transparency in product

specification. 21.1 Product Transparency and Sustainability 3 0

22A Fixed Benchmark -

22B Percentage Benchmark 1 1

Total 12 6 0 0

6

23.0 Endangered, Threatened or Vulnerable Species - Complies

23.1 Ecological Value 3 1

Ecological ValueTo reward projects that improve the ecological value of their

site.

Responsible Building

Materials

To reward projects that include materials that are

responsibly sourced or have a sustainable supply chain.

Land Use & Ecology

Potable Water Prescriptive Pathway

Life Cycle Impacts Prescriptive Pathway - Life Cycle Impacts

Construction and

Demolition WastePercentage Benchmark

24.0 Conditional Requirement - Complies

24.1 Reuse of Land 1 1

24.2 Contamination and Hazardous Materials 1 1

Heat Island EffectTo encourage and recognise projects that reduce the

contribution of the project site to the heat island effect.25.0 Heat Island Effect Reduction 1 1

Total 6 4 0 0

5

26.1 Reduced Peak Discharge 1 1

26.2 Reduced Pollution Targets 1 1

27.0 Light Pollution to Neighbouring Bodies - Complies

27.1 Light Pollution to Night Sky 1 1

Microbial Control

To recognise projects that implement systems to minimise

the impacts associated with harmful microbes in building

systems.

28.0 Legionella Impacts from Cooling Systems 1 1

Refrigerant ImpactsTo encourage operational practices that minimise the

environmental impacts of refrigeration equipment.29.0 Refrigerants Impacts 1

Total 5 4 0 0

10

Innovative Technology or

Process

The project meets the aims of an existing credit using a

technology or process that is considered innovative in

Australia or the world.

30A Innovative Technology or Process

Market Transformation

The project has undertaken a sustainability initiative that

substantially contributes to the broader market

transformation towards sustainable development in

Australia or in the world.

30B Market Transformation

Improving on Green Star

Benchmarks

The project has achieved full points in a Green Star credit

and demonstrates a substantial improvement on the

benchmark required to achieve full points.

30C Improving on Green Star Benchmarks

Innovation Challenge

Where the project addresses an sustainability issue not

included within any of the Credits in the existing Green Star

rating tools.

30D Innovation Challenge 10

Global Sustainability

Project teams may adopt an approved credit from a Global

Green Building Rating tool that addresses a sustainability

issue that is currently outside the scope of this Green Star

rating tools.

30E Global Sustainability

Total 10 10 0 0

TOTALS AVAILABLE TARGETED AWARDED TBC

CORE POINTS 100 61.0 0.0 0.0

Light Pollution To reward projects that minimise light pollution.

Innovation

10

Sustainable Sites

To reward projects that choose to develop sites that have

limited ecological value, re-use previously developed land

and remediate contaminate land.

Emissions

StormwaterTo reward projects that minimise peak stormwater flows

and reduce pollutants entering public sewer infrastructure.

CATEGORY PERCENTAGE SCORE 61.0

INNOVATION POINTS 10 10.0

TOTAL SCORE TARGETED 71.0