arpa-e transmission planning dale...co-optimization generation forecast and transmission • three...
TRANSCRIPT
ARPA-ETransmission Planning
Dale OsbornSeptember 29,2016
Road Map
MISO Transmission Expansion Plan (MTEP)Value Base Planning Process
Carbon and Other EffluentsMax Renewables Optimal Economic Generation Mix Forecastin lieu of Integrated Resource Plans
Location of Generation-Renewable Energy Zones input in lieu of exact site informationValue of Optimal Transmission Optimal Inter MISO Regional Transmission
Road MAP Scope
Definition of the future(s) with variable and alternatives, Existing MISO inter regional power transfer capability Generation alternativesTransmission alternativesSolution Constraints
1 Yr.
6 Yrs.
Transmission approved for constructionGeneration Adequacy ( LOLP) Informational studies answering pertinent questions
Balancing the mix of renewable siting and transmission build-out
3
• RGOS found there is a balance between siting renewables in resource rich areas and building transmission to deliver them.
• MISO’s mid-term analysis uses a new co-optimization technique to reevaluate this conclusion given current resource trends.
– Transmission interface capacity between the MISO Local Resource Zones (LRZ) is examined.
Results for MISO’s Mid-Term Analysis of EPA's Final Clean Power Plan (Mar. 16, 2016)
MISO’s Local Resource Zones
Co-optimization Generation Forecast and Transmission
• Three carbon dioxide reduction levels since 2005 were used– 30% by 2030– 50% by 2036– 80 % by 2050
• Optimal mixes of gas, wind and solar generation were sited for each carbon dioxide reduction level
• Cost of future energy was calculated-50% carbon reduction was the least cost scenario
• Inter-MISO regional transmission was identified
Results shown are from the load matching optimization which does not consider economics.
Study finding: an increase in transmission allows for more renewables to be built-out, while minimizing thermal generation
5
*RGOS = Regional Generator Outlet Study, see https://www.misoenergy.org/Planning/Pages/RegionalGenerationOutletStudy.aspx
Model not allowed to pick transmission as an expansion alternative
2050 CapacityNG = 182 GWCoal = 0 GW
Wind = 161 GWSolar = 119 GW
2050 Generation NG = 233 TWHCoal = 0 TWH
Wind & Solar = 648 TWHOther = 111 TWHLosses = 31 TWJ
Curtailments = 57 TWH
Model allowed to pick transmission as an expansion alternative
2050 CapacityNG = 182 GWCoal = 0 GW
Wind = 217 GWSolar = 125 GW
2050 Generation NG = 123 TWHCoal = 0 TWH
Wind & Solar = 861 TWHOther = 104 TWH
Losses = 185 TWHCurtailments = 0 TWH
Results for MISO’s Mid-Term Analysis of EPA's Final Clean Power Plan (Mar. 16, 2016)
This study identified cumulative potential for wind and solar build-out in MISO, which represents the upper limit of renewable expansion
6
Constraining transmission expansion (left) drives a more distributed solar build-out; allowing transmission expansion (right) shifts renewable build-out to MISO North and replaces some solar expansion with wind.
Both maps shows results of the load-matching optimization which does not consider economics.
*RGOS = Regional Generator Outlet Study, see https://www.misoenergy.org/Planning/Pages/RegionalGenerationOutletStudy.aspx
Model allowed to pick transmission as an
expansion alternative
Results for MISO’s Mid-Term Analysis of EPA's Final Clean Power Plan (Mar. 16, 2016)
Future Substation LocationsLinked by TransmissionFor the 2010 Road Map
-20
-10
0
10
20
30
40
50
Zone 1 Zone 2 Zone 3 Zone 4 Zone 5 Zone 6 Zone 7 North toSouth
Zone 8 Zone 9 Zone 10
Inte
rfac
e Tr
ansf
er C
apac
ity (G
W)
2016 2030 2036 2050
MISO North Hub MISO South Hub
(80%)
Results for MISO’s Mid-Term Analysis of EPA's Final Clean Power Plan (Mar. 16, 2016) 7
Study finding: High levels of wind build-out in Zone 1 by 2050 are facilitated by a large increase in export capacity
(30%)
Export to hub
Import from hub
(50%)
Load Forecast
• Utility bus by hour for the year• Wind pattern matching the load pattern for a
year• Solar pattern matching the load pattern for a
year• Demand Response hourly for a year
EGEAS Generation Forecast
• Establish futures- 4• Optimal selection of generation using a set of
the road map alternatives• Output is and input to the PROMOD
production cost simulation program
Top Congested Flowgates in PROMOD Run*
11
* Based on 2017 and 2022 BAU future PROMOD simulation** Historically congested flowgates
Flowgate NameMonitored Element
Area (From - To)
2017 BAU 2022 BAU 2017 and 2022 BAU Combined
Binding Hours
Shadow Price
(k$/MWh)
Congestion Cost
($)
Binding Hours
Shadow Price
(k$/MWh)
Congestion Cost
($)
Binding Hours
Shadow Price
(k$/MWh)
Congestion Cost
($)
10NTVL13 253581 SIGE 10NTVL16 253580 SIGE ** SIGE 3857 368.23 64,808 4443 493.26 86,814 8300 861.49 151,622 10802288 253552 SIGE 10ELOT13 253526 SIGE SIGE 1051 85.95 24,667 962 82.35 23,633 2013 168.30 48,300 4NASON P 348835 AMIL 4INA 347280 AMIL AMIL 843 134.19 21,335 636 101.12 16,078 1479 235.31 37,413 7JOPPA T 347325 AMIL 5JOPPA T 351003 EEI AMIL-EEI 693 30.96 18,577 568 29.55 17,731 1261 60.52 36,308 16PETE 254529 IPL YBUS702 99296 IPL IPL 631 47.70 14,310 596 47.00 14,100 1227 94.70 28,410 08WHITST 249529 DUK-IN 16GUION 254523 IPL ** DEI-IPL 151 6.54 6,251 463 22.75 21,750 614 29.29 28,001 10ABBRWN 253505 SIGE 10ABB345 253620 SIGE ** SIGE 1386 20.32 9,552 1559 30.15 14,170 2945 50.48 23,722
Market Efficiency Planning Study 3rd TRG October 30, 2012
Summary of Historically Congested Flowgates
12
Flowgate Common NameMonitored Element
Area(From - To)
Day-Ahead Real-TimePROMOD Simulation
2017 BAU 2022 BAU
Binding Hours
Ranking
Shadow Price
Ranking
Binding Hours
Ranking
Shadow Price
Ranking
Binding Hours
Shadow Price
(k$/MWh)
Binding Hours
Shadow Price
(k$/MWh)
AB Brown 138/345KV Xfmr FLO Gibson-Francisco 345KV SIGE 27 73 117 623 1386 20.32 1559 30.15
Adams 161/69kV Xfmr FLO Adams-Beaver Creek-Harmony/Rice 161kV ALTW 14 24 76 21 2 0.06
Baldwin-Mt Vernon 345KV FLO St. Francois-Lutesville 345KV AMIL 19 107 19 220 382 4.41 247 3.34
Benton Harbor-Palisades 345KV FLO Cook-Palisades 345KV AEP 18 132 43 61 1 -
Bunsonville-Eugene 345KV FLO Casey-Breed 345 KV AEP-AMIL 9 58 32 213 989 12.65 77 1.07
Crete-East Frankfort 345kV FLO Dumont-Wilton Center 765kV CE 172 410 4 51 201 0.94
Crete-St Johns Tap 345kV FLO Dumont-Wilton Center 765kV NIPS-CE 155 313 3 15 125 0.57 191 2.46
Market Efficiency Planning Study 3rd TRG October 30, 2012
Difference of Constrained and Unconstrained Production Cost Cases
• Potential production cost savings– By area– MISO and neighboring areas
Market Efficiency Planning Study 3rd TRG October 30, 2012 14
15
Energy Sources and Sinks MISO – using Ventyx, Velocity Suite © 2012
Market Efficiency Planning Study 3rd TRG October 30, 2012
West to East Interface Flows OH-PA
0
5000
10000
15000
20000
25000
0 720 1440 2160 2880 3600 4320 5040 5760 6480 7200 7920 8640
Hour of the Year
MW
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Transmission Overlay Design WorkshopExample Interface Duration CurveInterface Flow
-2000
-1500
-1000
-500
0
500
1000
1500
2000
2500
3000
3500
1
245
489
733
977
1221
1465
1709
1953
2197
2441
2685
2929
3173
3417
3661
3905
4149
4393
4637
4881
5125
5369
5613
5857
6101
6345
6589
6833
7077
7321
7565
7809
8053
8297
8541
Hours
MW
Flo
w
WAPA-MINN
Transmission Capacity designed to deliver 80% of desired energy flow
Transmission and Substation Costs per Mw-mile by Transmission Voltage And Type of Construction
0400800
1,2001,6002,0002,4002,8003,2003,6004,000
345 kVSteel
WoodedAreas
2-345kkVon Steel
500 kV 765 kV 765 HSIL 800 kV GIL 1200 mile-800kVHVDC
$/M
w-M
ile
Lowest cost options
600 1200 1300 2600 5400 5300 6400
345 kV - 765 kv Delivery Capacitywith a 5% voltage drop
on a losseles line
0
0.5
1
1.5
2
2.5
3
3.5
0 50 100 150 200 250 300 350Miles
PU S
IL
21
Power Transfer Breakover by Voltage
$0
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
$14,000,000
$16,000,000
200
1,20
02,
200
3,20
04,
200
5,20
06,
200
7,20
08,
200
9,20
010
,200
11,2
0012
,200
13,2
00Power Transfer MW
Cos
t/Mile
345 kV AC+600 Mw1-765kV AC1-800 kV HVDC345 kV AC+1000 Mw
22
Interface Contour: Annual Energy DifferenceUnconstrained Case Minus Constrained Case
MISO – using Ventyx, Velocity Suite © 2012Market Efficiency Planning Study 3rd TRG October 30, 2012
Interface AC Flows without an OverlayInterface Flows with an Overlayincluding HVDC
Loop Flow Patterns
Benefit Components
Market Efficiency Planning Study 3rd TRG October 30, 2012 24
Robust Transmission Plan
• Then tested for reliability• Cost allocated• Sent to Board of Directors for Approval
Average LMPs for Base, 765kv Overlay, and WIND
$30
$35
$40
$45
$50
$55
ON
HY
NY
PP
SU
NC VP
PJM
EV
AC
AR
WP
SC
PJM
SM
IDW
WE
PLK
PJM
WC
EC
STH
RN
DE
TED FE
LBW
LS
OLA
ES
PP
WA
EP
SO
LAW
DP
&L
SA
SK
CG
ELG
&E
EM
DE
DQ
ED
PC
AR
LMH
EC
IP&
LP
SI
TVA
SP
CIU
TW
RI
NIP
SB
RE
CM
GE
GR
ES
MM
PH
UC
WP
LS
IGE
WP
PI
NS
PM
PC
AS
EC
IND
NA
LWS
TC
OE
DK
CP
LM
IPU
WP
SK
AC
YW
EP
MP
WO
TPM
PL
MID
AM
CIL
EE
IN
WP
SIL
PC
SIP
CM
HS
PC
IPS
WA
BN
IS
PR
ILW
AB
DA
UE
PM
DU
NP
PD
LES
OP
PD
Avg LMP - 765kV Overlay Avg LMP - Base Case Avg LMP - WIND
MISO26%
SERC21%PJM
Interconnection
16%
Southwest Power Pool
13%
Entergy8%
TVA6%
New York4%
MRO4%
TVA -Other
1%
IESO (Ontario)1%
Chart Title
MISO Pays 100%, 34% Benefits For MISO Central to Entergy Transmission
Without Overlay
With AC Overlay
With HVDC Overlay
PRI
CE
Distance
GenRevenueDifference
LoadSavings
Capacity Diversity
• Between Balancing Areas• Time zone differences is the main driver• North-South load pattern differences is a
secondary driver• Study
– Determine the economic potential• Generation displacement• Energy payment and market product premium
displacements– Design a transmission system to capture the value for
a targeted benefit/cost ratio
31
5.9 GW
7.9 GW
3.8 GW
5.6 GW
4.6 GW
7.5 GW
Load Diversity Between Areas
Total = 35 GWof load diversity Valued at $700k/MW of
displaced capacity
Frequency Response
• Sharing frequency response reserves through interregional secure power transmission– ~950 MW of local reserve, ~2750 total reserves– 2x900 MW of secure transmission– Net benefit 5400 MW of displaced capacity (3x1800 MW)
• Approximately 1 in 30 years there will be an outage in two regions simultaneously
32
900MW
900MW
900MW Zone Reserves (MW)
East 4500
MISO+ 2900
WECC 2740
ERCOT 2750
MISO+(1100MW)
ERCOT(950MW)
WECC(940MW)
Frequency Response (cont.)• Improved frequency response performance
– Current governor control responds in 3-5 seconds– VSCs allow for response in 0.1 seconds– Raises frequency event nadir
33
Time
Nadir(w/ HVDC)
Nadir(w/out HVDC)
Freq
uenc
y Frequency Response Event
900MW
900MW
900MW MISO+(1100 MW)
ERCOT(950 MW)
WECC(940 MW)
HVDC Network Concept
Wind Energy Benefits for WECC
35
Reduced peak ramp rate
2011: x2.0
• Add all wind generation across MISO, ERCOT, and WECC• Re-distribute wind based on peak capacity
• Benefits– Reduced ramp rate– Reduced variability (and thereby potentially increased capacity credit)
Effect on Capacity Credit: TBD
Costs allocated by % of benefits
36
Example:
SERC Load Cap. Cost = $36.2B * 9% = $3.3B
SERC Freq Reg Cost = 36.2B * 3% = $1.1B
Value Drivers
Load diversity 46%
Frequency response 22%
Wind diversity 5%
Other Energy Based Products
27%
37
High Solar Generation Impact
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Load
/Net
Loa
d (M
W)
Hours
Southern California Edison and HVDC load and net loadfor off-peak day: 11/25/2012
SoCalEd Normalized Load
SoCalEd Normalized Net Load
HVDC Normalized Load
HVDC Normalized Net Load
SoCalEd Reduced Ramp
S. CA Edison peak load: 22,400 MWHVDC Network peak load: 316,000 MW
HVDC Network Conceptwith Some Gas Fields
Cost to Deliver Wind Energy with the Macro Grid is 25% of the cost of individual HVDC lines proposed currently because of sharing the cost
and more fully utilizing the lines.
Questions
• Dale Osborn• MISO Policy and Economic Studies• Phone 651-632-8471• Email [email protected]