OUTLINE
Pre-Discovery Pilot Project
• Goals & Actions‒ Pre-Discovery Data Prep
‒ Watershed Prioritization
• Current Status & Findings
• Lessons Learned
ARKANSAS
“THE NATURAL STATE”
ARKANSAS’S
WATERSHEDS
57 Watersheds
touch AR /
38 Watersheds
primarily in AR
(>50% Land Area)
5 watersheds
deployed, 3
watersheds in
progress
49 TO GO
AR CTP’S CHALLENGE
AR CTP’S CHALLENGE
• Effectively / Efficiently perform
Discovery on remaining 49
Watersheds (in Mike’s lifetime)
• Identify / Prioritize Watersheds for
Discovery
– Must perform Discovery to move on to
Risk MAP (“deploy” watershed)
STATEWIDE PRE-DISCOVER
PILOT PROJECT
• Awarded a FEMA Grant for 1-year
Statewide Pre-Discovery Pilot Project
• Objective is to “deploy” watersheds
faster and cheaper
• Develop automated (and fluid)
watershed prioritization scheme
• Collect data as with normal
Discovery but statewide
• Draw heavily from the State’s Hazard
Mitigation Plan
• Mini-Discovery
─ workshops, conferences, CAVs, CACs,
and other venues
STATEWIDE PRE-DISCOVER
PILOT PROJECT
Provided in
pdf fillable
form
EXAMPLES
EXAMPLES
Washington County (May 25, 2015) http://5newsonline.com/2015/05/25/roads-closed-due-to-
heavy-rain-and-flooding/
Stone Bridge is flooded and impassable
Mount Olive Road, just east of Elkins, is flooded and impassable
Billings is flooded and impassable
Dye Creek Road in West Fork is flooded and impassable
Sprinston Ford is flooded but is passable
Goose Creek Road is flooded but is passable
Ball Street in Johnson is flooded and impassable
The intersection of Highways 59 and 62 is flooded but passable
Kinver Road is flooded and impassableApr 2011
EXAMPLES
EXAMPLES
OUR MOST FREQUENT RESPONSE
Engagement Plan / Pre-Discovery
Report
─AR CTP / Region 6 Report
Template
─Developed Standardized
Figures
─Local HMP Reviews
─ Input from Questionnaires
STATEWIDE PRE-DISCOVER
PILOT PROJECT
• Established
process to update
and process
datasets
• Discovery
template (*.mxd)
set up with
relative paths
STATEWIDE PRE-DISCOVER
PILOT PROJECT
Watershed Prioritization
• Utilize pre-Discovery data collected
to develop prioritization plan for
future Discovery
STATEWIDE PRE-DISCOVER
PILOT PROJECT
OBVIOUS PRIORITIES
Criteria that will influence Watershed
Selection for Discovery:
• Good Topography / Elevation Data
• Flood Losses / Claims
• NFIP Participation
• Population
ARKANSAS’S DRAFT
PRIORITIZATION SCHEME
EXAMPLES OF RESULTS
EXAMPLES OF RESULTS
EXAMPLES OF RESULTS
EXAMPLES OF RESULTS
EXAMPLE RANKING PRIORITIES
CTP PRIORITY WATERSHEDS
(CURRENT)
HUC-8 Watershed Current Priority Draft Rank
Lower Arkansas-Maumelle* 1 2
Boeuf* 2 19
Lake O' The Cherokees* 3 52
Upper Saline* 4 7
Bayou Meto* 5 3
Illinois* 6 5
Lower Black* 7 33
Lake Conway-Point Remove* 8 6
L'Anguille 9 9
Lower St. Francis 10 1
Big 11 21
Cache 12 4
Dardanelle Reservoir 13 28
Lower Arkansas 14 27
Bayou Bartholomew 15 11
*Discovery completed or in progress
• Next Steps
–Finalize & Review Priority Datasets
–Assign the Weights
–Establish the Statewide Priority Map• Include in 2016 Business Plan
–Update routinely
– Initiate our Discovery tools
STATEWIDE PRE-DISCOVER
PILOT PROJECT
LESSONS LEARNED
• QUESTIONAIRES
– NOT ALL INPUT IS EFFECTIVE
• MINI DISCOVERY
– SPREADING THE WORD
• ABOVE ALL ELSE
– TOPO MATTERS
– PARTNERSHIPS / LEVERAGE MATTER
– FEMA STILL HAS THE HAMMER
IN CONCLUSION
• The Pre-Discovery Pilot Project is
expected to establish priority watersheds
based on AR’s priorities and will be part of
the annual Business Plan
• Ongoing updates will allow for rapid
re-prioritization (i.e. flood events, partner
opportunities)
• Discovery will be performed quicker and at
less cost