[email protected] table 2. productivity concrete

3
Introduction There are several types of materials that are often used in designing the main structure of building construction as columns or beams. Currently, one of the most popular materials are IWF / H-Beam Steel and Reinforced Concrete. The selection of methods for the implementation of construction project work is very influential on quality, time and cost. Construction methods of steel structure work and reinforced concrete structures are very different. Each method has both advantages and disadvantages in terms of its nature or character, economic aspect and environmental aspects. The structure of residential buildings generally use reinforced concrete. However, recently steel structures have been used, especially in the column and beam structure, as in the object of the study which was reviewed, namely the Highland Nusa Dua Housing development project, Badung regency. The use of steel structures in the columns and beams will be composite using a mixture of plaster. Composite columns and beams using concrete are not formed a square profile as reinforced concrete, but only plastered by the IWF body part because the wing of the IWF has been aligned with a light brick. On the slab work is not used assembly reinforcement and plate formwork, because it usually uses factory reinforcement (wiremesh) as reinforcement plates and bondex as the support of wiremesh. The selection of the main structural material is not only considered in terms of strength, but the designer will consider the effectiveness in terms of time and cost of implementation. This research was conducted to determine the comparison of the two methods to the time and cost of implementation by using the Break-Even Point Method, therefore it can be analyzed how many volume between steel structure work and reinforced concrete structures effective to be used as the main structure of a residential are building. COMPARISON OF CONSTRUCTION METHOD BETWEEN TWO STOREY BUILDING STEEL STRUCTURE AND REINFORCED CONCRETE STRUCTURE REGARDING TIME AND COSTS IMPLEMENTATION A. Frederika and A. A. Wiranata [email protected] Research Methods The implementation of the research to be more clear and directed, is carried out by following the flow chart as in Figure 1. Results and Discussion Productivity, Unit Price, and Break Evan Point Observation results in volume, time, and number of labor of each column work, beam and floor slab structure in the implementation of the Highland Nusa Dua Housing project, type 120 residence (2 storeys), with steel structure and reinforced concrete methods, is calculated based on productivity for column work, beams and slabs. The results of productivity calculations are shown in Table 1 and Table 2. Based on the productivity resulted, the implementation costs of each method can be calculated as shown in Table 3 and Table 4. Then time and costs implementation was recapitulated (Table 5) to obtain Regression Equations and Correlation, hence the break-even point of the volume between the steel structure construction methods and reinforced concrete can be analyzed towards time and cost. Break-even point results are shown in Table 6. Table 1. Productivity Steel Structure Conclusion The conclusion of this research is : 1. Comparison of time and cost in implementation of building structures using steel structure and reinforced concrete structures is 158 hours (20 working days): 190 hours (24 working days) and Rp. 77,696,287.00: Rp. 72,224,407.00 respectively. The implementation time using steel structure method is 4 days faster, while the cost is Rp. 5,471,880.00 greater than reinforced concrete structure method. 2. The break-even point of volume between steel structural work and reinforced concrete structures towards time is in column volume, beam, and plate (74.44 m '; 69.84 m'; and 66.36 m2) with a total time of 190 hours (24 working days); volume towards cost in column volume, beam, and plate (86.4 m '; 67.2 m'; and 74.4 m2) with a total cost of Rp. 93,235,544.40. Therefore the break-even results provide a indication that starting at that volume point is more effective to use the steel structure method and vice versa. Acknowledgement This study was funded by the Udayana University PNBP DIPA FY 2018 with Conceler SK number. 435/UN 14/LT/2018 contract number: 1647 / UN 14.2.5.II / LT / 2018, March 29, 2018.. Bibliography Figure 1. Research Flow Chart Table 2. Productivity Concrete Structure Regarding a b c d e f = c*d g 1 Steel column work 1356.94 kg 14,718.00 19,971,442.92 29.64 Wire installation 61.2 m2 22,050.00 1,349,460.00 8 Formwork column 36.72 m2 184,284.00 6,766,908.48 16 Casting concrete 1.156 m3 2,218,685.00 2,564,799.86 28 Colomn work total 2 Steel beam work 1539.89 kg 15,600.00 24,022,284.00 41.95 Wire installation 36.5 m2 22,050.00 804,825.00 5 Formwork column 0.365 m3 3,688,685.00 1,346,370.03 12 Beam work total 3 Bondek floor (without ca 55.25 m2 259,947.00 14,362,071.75 9.5 4 Casting concrete 6.63 m3 981,695.00 6,508,637.85 8 Sub-Total 158.09 30,652,611.26 26,173,479.03 77,696,799.89 Duration (Hour) NO Job description VOL. UNIT UNIT PRICE (Rp) TOTAL PRICE (Rp) a b c d e f = c*e g 1 Structure column work Reinforcement 705.04 kg 11,225.00 7,914,074.00 64 Formwork column 55.08 m2 227,884.00 12,551,850.72 Casting concrete 2.754 m3 933,695.00 2,571,396.03 8 Total 72 2 Structure beam work Reinforcement 741.97 kg 12,450.00 9,237,526.50 48 Formwork column 52.33 m2 288,534.00 15,098,984.22 Casting concrete 2.61 m3 961,245.00 2,508,849.45 8 Total 56 3 Structure plate work Reinforcement 620 kg 9,380.00 5,815,600.00 8 Formwork column 55.25 m2 211,084.00 11,662,391.00 42 Casting concrete 6.63 m3 733,595.00 4,863,735.00 12 Total 62 Sub Total 190 23,037,320.75 26,845,360.17 22,341,726.00 72,224,406.92 No Job description Vol. Unit unit price (Rp) Total price (Rp) Duratio n (Hour) Table 3. The cost of carrying out steel structure work Table 4. The cost of carrying out concrete structure work Table 5. Recapitulation of time and cost of structural work Job description Total Unit Total Unit a b c d e f = c/e g 1 Column Structure Reinforcement 705.04 kg 64 11.01 kg/hour Formwork 55.08 m2 56 0.98 m2/hour Casting concrete 2.754 m3 8 0.344 m3/hour 128 2 Beam Structure Reinforcement 741.97 kg 48 15.46 kg/hour Formwork 52.33 m2 42 1.25 m2/hour Casting concrete 2.61 m3 8 0.33 m3/hour 98 3 Struktur Plat Lantai Reinforcement 620 kg 8 77.5 kg/hour Formwork 55.25 m2 42 1.31 m2/hour Casting concrete 6.63 m3 12 0.55 m3/hour 62 Total Duration of Concrete Structure work No Duration (Hour) Volume Productivity Total Duration Total Duration Total Duration 288 Hour or 36 day Job Description Total Unit Total Unit a b c d e f = c/e g 1 Column Structure Perforation 450 sheets 11.83 38.04 sheet/jam Catting 1920 cm 1.8 1066.67 cm/jam Painting 61.2 m' 0.51 120 m'/jam Welding and Asse 1356.94 kg 15.5 87.54 kg/jam 29.64 2 Struktur Balok Perforation 480 sheets 12.16 39.47 sheet/jam Catting 8377 cm 11 761.54 cm/jam Painting 58.15 m' 0.29 200.52 m'/jam Welding and Asse 1539.89 kg 18.5 83.24 kg/jam 41.95 3 Struktur Lantai Bondek installition 55.25 m2 4 13.81 m2/jam wiremesh Installit 310 m2 3 103.3 kg/jam Formwork Installi 36.5 m2 2.5 14.6 m'/jam Casting 6.63 m3 8 0.83 m3/jam 17.5 4 Wire Installition 59.91 m2 8 7.48 m2/jam Columns and Bea 1.589 m3 6 0.26 m3/jam 14 Duration Total Total Duration Total duration of Steel structure work 122 hour or 22 day Total Duration Total Duration Volume Produktivity No Duration (Hour) 1 Column Structure 61.2 m' 81.64 30,652,611.00 72 23,037,321.00 2 Beam Structure 58.2 m' 58.95 26,172,966.00 56 26,845,360.00 3 Plate Structure 55.3 m2 17.5 20,870,710.00 62 22,341,726.00 Total Comparison of construction meth 158 hour or 20 day 77,696,287.00 190 hour or 24 day 72,224,407.00 No Job Desctription Vol Unit STEEL CONCRETE Duration (Hour) Cost (Rp) Duration (Hour) Cost (Rp) unit X Y (jam) unit X (m3) Y(juta) 1 Column Structure m' 73.44 97.968 m' 86.4 36,783,133.20 2 Beam Structure m' 69.84 70.74 m' 67.2 31,407,559.20 3 Plate Structure m2 66.36 21 m2 74.4 25,044,852.00 189.708 93,235,544.40 Break Even point of Steel Structure and Concrete Structure Volume and Time Volume and Cost BEP Volume for Time and Cost No Job Description Table 6. Break Even Point Volume Asiyanto.2003.Construction Project Cost Management. PT Pradnya Paramita, Jakarta. Ervianto, W. I. 2007. Manajemen Proyek Konstruksi (Edisi Revisi). ANDI, Yogyakarta. Frederika, A. dan I.A.R. Widhiawati. 2017. Productivity and Break Even Point Analysis of Ready Mix Casting Method on tehe Beams Floor Slab Of Storey Buildings. Denpasar. Jurnal Spektran. Vol.5 No.1. Januari 2017. Hal. 1-87 Kartadiputra, R.H. 2012. Analisis Pemilihan Material Beton dan Material Baja Sebagai Alternatif Material Pengganti Kayu Ulin Untuk Kolom/Tiang. Banjarmasin. Jurnal Poros Teknik, Vol. 4. No.1 Juni 2012. Murdock, L. J., Brook, K. M., Hindarko, S., 1999. Bahan dan Praktek Beton. Erlangga, Jakarta. Peurifory, R. L., Ledbetter, W. B., Schexnayder, C. V. 1996. Construction Planing Equipment and Method, 5 th Edition McGraw-Hill.

Upload: others

Post on 15-May-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: arianyfrederikal@unud.ac.id Table 2. Productivity Concrete

Introduction

There are several types of materials that are often used in designing the main structure of

building construction as columns or beams. Currently, one of the most popular materials are

IWF / H-Beam Steel and Reinforced Concrete. The selection of methods for the implementation

of construction project work is very influential on quality, time and cost. Construction methods of

steel structure work and reinforced concrete structures are very different. Each method has both

advantages and disadvantages in terms of its nature or character, economic aspect and

environmental aspects.

The structure of residential buildings generally use reinforced concrete. However, recently steel

structures have been used, especially in the column and beam structure, as in the object of the

study which was reviewed, namely the Highland Nusa Dua Housing development project,

Badung regency. The use of steel structures in the columns and beams will be composite using a

mixture of plaster. Composite columns and beams using concrete are not formed a square profile

as reinforced concrete, but only plastered by the IWF body part because the wing of the IWF has

been aligned with a light brick. On the slab work is not used assembly reinforcement and plate

formwork, because it usually uses factory reinforcement (wiremesh) as reinforcement plates and

bondex as the support of wiremesh.

The selection of the main structural material is not only considered in terms of strength, but the

designer will consider the effectiveness in terms of time and cost of implementation. This

research was conducted to determine the comparison of the two methods to the time and cost of

implementation by using the Break-Even Point Method, therefore it can be analyzed how many

volume between steel structure work and reinforced concrete structures effective to be used as

the main structure of a residential are building.

COMPARISON OF CONSTRUCTION METHOD BETWEEN TWO STOREY

BUILDING STEEL STRUCTURE AND REINFORCED CONCRETE

STRUCTURE REGARDING TIME AND COSTS IMPLEMENTATION A. Frederika and A. A. Wiranata

[email protected]

Research Methods

The implementation of the research to be more clear and directed, is carried out by following the flow chart as in Figure 1.

Results and Discussion

Productivity, Unit Price, and Break Evan Point Observation results in volume, time, and number of labor of each column work, beam and floor

slab structure in the implementation of the Highland Nusa Dua Housing project, type 120

residence (2 storeys), with steel structure and reinforced concrete methods, is calculated based

on productivity for column work, beams and slabs. The results of productivity calculations are

shown in Table 1 and Table 2. Based on the productivity resulted, the implementation costs of

each method can be calculated as shown in Table 3 and Table 4. Then time and costs

implementation was recapitulated (Table 5) to obtain Regression Equations and Correlation,

hence the break-even point of the volume between the steel structure construction methods

and reinforced concrete can be analyzed towards time and cost. Break-even point results are

shown in Table 6.

Table 1. Productivity Steel Structure

Conclusion The conclusion of this research is :

1. Comparison of time and cost in implementation of building structures using steel

structure and reinforced concrete structures is 158 hours (20 working days): 190 hours

(24 working days) and Rp. 77,696,287.00: Rp. 72,224,407.00 respectively. The

implementation time using steel structure method is 4 days faster, while the cost is Rp.

5,471,880.00 greater than reinforced concrete structure method.

2. The break-even point of volume between steel structural work and reinforced concrete

structures towards time is in column volume, beam, and plate (74.44 m '; 69.84 m'; and

66.36 m2) with a total time of 190 hours (24 working days); volume towards cost in

column volume, beam, and plate (86.4 m '; 67.2 m'; and 74.4 m2) with a total cost of Rp.

93,235,544.40. Therefore the break-even results provide a indication that starting at that

volume point is more effective to use the steel structure method and vice versa.

Acknowledgement This study was funded by the Udayana University PNBP DIPA FY 2018 with Conceler SK number.

435/UN 14/LT/2018 contract number: 1647 / UN 14.2.5.II / LT / 2018, March 29, 2018..

Bibliography

Figure 1. Research Flow Chart

Table 2. Productivity Concrete Structure

Regarding

a b c d e f = c*d g

1 Steel column work 1356.94 kg 14,718.00 19,971,442.92 29.64

Wire installation 61.2 m2 22,050.00 1,349,460.00 8

Formwork column 36.72 m2 184,284.00 6,766,908.48 16

Casting concrete 1.156 m3 2,218,685.00 2,564,799.86 28

Colomn work total

2 Steel beam work 1539.89 kg 15,600.00 24,022,284.00 41.95

Wire installation 36.5 m2 22,050.00 804,825.00 5

Formwork column 0.365 m3 3,688,685.00 1,346,370.03 12

Beam work total

3 Bondek floor (without cast) 55.25 m2 259,947.00 14,362,071.75 9.5

4 Casting concrete 6.63 m3 981,695.00 6,508,637.85 8

Sub-Total 158.09

30,652,611.26

26,173,479.03

77,696,799.89

Duration

(Hour)NO Job description VOL. UNIT

UNIT PRICE

(Rp)

TOTAL PRICE

(Rp)

a b c d e f = c*e g

1 Structure column work

Reinforcement 705.04 kg 11,225.00 7,914,074.00 64

Formwork column 55.08 m2 227,884.00 12,551,850.72

Casting concrete 2.754 m3 933,695.00 2,571,396.03 8

Total 72

2 Structure beam work

Reinforcement 741.97 kg 12,450.00 9,237,526.50 48

Formwork column 52.33 m2 288,534.00 15,098,984.22

Casting concrete 2.61 m3 961,245.00 2,508,849.45 8

Total 56

3 Structure plate work

Reinforcement 620 kg 9,380.00 5,815,600.00 8

Formwork column 55.25 m2 211,084.00 11,662,391.00 42

Casting concrete 6.63 m3 733,595.00 4,863,735.00 12

Total 62

Sub Total 190

23,037,320.75

26,845,360.17

22,341,726.00

72,224,406.92

No Job description Vol. Unitunit price

(Rp)

Total price

(Rp)

Duratio

n

(Hour)

Table 3. The cost of carrying out steel structure work Table 4. The cost of carrying out concrete

structure work

Table 5. Recapitulation of time and cost of structural work

Job

description Total Unit Total Unit

a b c d e f = c/e g

1 Column Structure

Reinforcement 705.04 kg 64 11.01 kg/hour

Formwork 55.08 m2 56 0.98 m2/hour

Casting concrete 2.754 m3 8 0.344 m3/hour

128

2 Beam Structure

Reinforcement 741.97 kg 48 15.46 kg/hour

Formwork 52.33 m2 42 1.25 m2/hour

Casting concrete 2.61 m3 8 0.33 m3/hour

98

3 Struktur Plat Lantai

Reinforcement 620 kg 8 77.5 kg/hour

Formwork 55.25 m2 42 1.31 m2/hour

Casting concrete 6.63 m3 12 0.55 m3/hour

62

Total Duration of Concrete Structure work

NoDuration

(Hour)

Volume Productivity

Total Duration

Total Duration

Total Duration

288 Hour or 36 day

Job

Description Total Unit Total Unit

a b c d e f = c/e g

1 Column Structure

Perforation 450 sheets 11.83 38.04 sheet/jam

Catting 1920 cm 1.8 1066.67 cm/jam

Painting 61.2 m' 0.51 120 m'/jam

Welding and Assembly1356.94 kg 15.5 87.54 kg/jam

29.64

2 Struktur Balok

Perforation 480 sheets 12.16 39.47 sheet/jam

Catting 8377 cm 11 761.54 cm/jam

Painting 58.15 m' 0.29 200.52 m'/jam

Welding and Assembly1539.89 kg 18.5 83.24 kg/jam

41.95

3 Struktur Lantai

Bondek installition 55.25 m2 4 13.81 m2/jam

wiremesh Installition 310 m2 3 103.3 kg/jam

Formwork Installition36.5 m2 2.5 14.6 m'/jam

Casting 6.63 m3 8 0.83 m3/jam

17.5

4 Wire Installition 59.91 m2 8 7.48 m2/jam

Columns and Beams plastering1.589 m3 6 0.26 m3/jam

14

Duration Total

Total Duration

Total duration of Steel structure work 122 hour or 22 day

Total Duration

Total Duration

Volume ProduktivityNo

Duration

(Hour)

1 Column Structure 61.2 m' 81.64 30,652,611.00 72 23,037,321.00

2 Beam Structure 58.2 m' 58.95 26,172,966.00 56 26,845,360.00

3 Plate Structure 55.3 m2 17.5 20,870,710.00 62 22,341,726.00

Total Comparison of construction method 158 hour or 20 day 77,696,287.00 190 hour or 24 day 72,224,407.00

No Job Desctription Vol Unit

STEEL CONCRETE

Duration (Hour) Cost (Rp) Duration (Hour) Cost (Rp)unit X Y (jam) unit X (m3) Y(juta)

1 Column Structure m' 73.44 97.968 m' 86.4 36,783,133.20

2 Beam Structure m' 69.84 70.74 m' 67.2 31,407,559.20

3 Plate Structure m2 66.36 21 m2 74.4 25,044,852.00

189.708 93,235,544.40

Break Even point of Steel Structure and Concrete Structure

Volume and Time Volume and Cost

BEP Volume for Time and Cost

No Job Description

Table 6. Break Even Point Volume

Asiyanto.2003.Construction Project Cost Management. PT Pradnya Paramita, Jakarta.

Ervianto, W. I. 2007. Manajemen Proyek Konstruksi (Edisi Revisi). ANDI, Yogyakarta.

Frederika, A. dan I.A.R. Widhiawati. 2017. Productivity and Break Even Point Analysis of Ready Mix

Casting Method on tehe Beams Floor Slab Of Storey Buildings. Denpasar. Jurnal Spektran. Vol.5 No.1.

Januari 2017. Hal. 1-87

Kartadiputra, R.H. 2012. Analisis Pemilihan Material Beton dan Material Baja Sebagai Alternatif Material

Pengganti Kayu Ulin Untuk Kolom/Tiang. Banjarmasin. Jurnal Poros Teknik, Vol. 4. No.1 Juni 2012.

Murdock, L. J., Brook, K. M., Hindarko, S., 1999. Bahan dan Praktek Beton. Erlangga, Jakarta.

Peurifory, R. L., Ledbetter, W. B., Schexnayder, C. V. 1996. Construction Planing Equipment and Method,

5th Edition McGraw-Hill.

Page 2: arianyfrederikal@unud.ac.id Table 2. Productivity Concrete
Page 3: arianyfrederikal@unud.ac.id Table 2. Productivity Concrete