area development projects zero draft

92
Administrative Staff College of India Hyderabad Sector Specific Guidance Manual for Townships & Area Development Projects Rajasthan State Pollution Control Board Zero Draft Prepared by

Upload: siddharth-nain

Post on 27-Nov-2014

151 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Area Development Projects Zero Draft

Administrative Staff College of India Hyderabad

Sector Specific Guidance Manual for

Townships & Area Development Projects

Rajasthan State Pollution Control Board

Zero DraftPrepared by

Page 2: Area Development Projects Zero Draft

==============================================================SECTOR SPECIFIC GUIDANCE MANUAL

FOR TOWNSHIPS AND AREA DEVELOPMENT PROJECTS

==============================================================

Page 3: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 1

Contents

Chapter No. Title Page No. Foreword Acknowledgements Team

List of Annexures About the Manual

Chapter 1 Introduction 1.0 About RPCB

1.1 Townships and area development projects- Classification by RPCB for Consent Management purpose 1.2 Townships and area development projects- Classification by MoEF for EC applicability

Chapter 2 Environmental Acts and Legal Requirements

2.0 Legal requirements under the provisions of the Water (Prevention & Control Pollution) Act, 1974 as amended 2.1 Requirement under the provisions of Air (Prevention & Control Pollution) Act, 1981 as amended 2.2 Requirement under the provisions of the Environmental (Protection) Act, 1986 and as amended 2.3 Requirement for ground water extraction 2.4 Notification for the integrated township dated 29.03.07

Urban development & Local Self Department, Government of Rajasthan

2.5 Requirements under the Notification No. S.O. 319 (E) dated 7th May 1992 and S.O. 1189 (E) dated 29th November 1999-

Restriction of certain activities in specified area of Aravalli Range 2.6 Requirements under the Notification No. S.O. 1545 dated 25th June 2009-Mount Abu Eco-sensitive Zone

Chapter 3 Statutory Clearance Process

3.0 Environmental Clearance Process 3.1 Public Consultation 3.2 Validity of Environmental Clearance 3.3 Post Environmental Clearance Monitoring 3.4 Transferability of Environmental Clearance 3.5 Criteria for EIA consultants 3.6 Authorized signatory 3.7 Participation of the project proponent during the EAC meeting 3.8 Projects requiring recommendation of the Chief Wildlife Warden 3.9 Consent management system – RPCB

Chapter 4 Environmental Aspects and Guidance

4.0 Environmental Checklist 4.1 Environmental norms 4.2 Guidance for the project developer

Page 4: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 2

Chapter 5 Guidelines for sector specific projects

5.0 Guidelines for stipulating sector specific condition in the CTE order

Chapter 6 Environmental Management Plan

6.0 General 6.1 Components of EMP

Page 5: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 3

Foreword

(To be given by RPCB)

Page 6: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 4

Acknowledgements

(To be given latter by ASCI)

Page 7: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 5

Project Team

Page 8: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 6

Annexures

1. FORM 1 (EIA Notification dated 14th September 2006 as amended 1st December 2009) 2. FORM-1 A (only for construction projects listed under item 8 of the Schedule of EIA

Notification) 3. Application for Consent To Establish 4. Application for Consent To Establish 5. Consent Fee Under the Provisions of Water Act 6. Consent Fee Under the Provisions of Air Act 7. Areas as identified by CGWA as – safe areas, semi – critical areas, critical areas & over

exploited areas 8. General Standards for Discharge of Effluents 9. National Ambient Air Quality Standards (NAAQS) 10. Noise Ambient Air Quality Standards 11. Noise Limits for Generator Sets run with Diesel 12. Effluent Standards for Hotel Industry notified under E (P) Act, 1986 13. Estimation of Water Demand 14. Code of Practices for Parking Requirements 15. BIS Code of Practices 16. Ground Water Scenario of Rajasthan 17. Rain Water Harvesting Structures 18. Water Quality Inlets 19. Availability of Rain Water Through Roof Top Rain Water Harvesting 20. Wind Towers 21. Checklist - Construction Phase

Page 9: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 7

About the Manual

The purpose of developing sector specific guidance manual for Township and Area Development projects is to provide clear and concise information to all the stakeholders i.e project proponent, environmental consultant, Rajasthan State Pollution Control Board officials and the public to have a better understanding on the relevant environmental aspects in the initial stage itself. This manual covers the legal requirements, clearance process, environmental standards and maintenance of statutory records. The manual will also covers the environmental aspects due the Township and Area Development projects. The project proponent may use this manual to ensure that all the aspects of the environment due to the project are addressed and adequate mitigation measures are planned in the proposed environmental management plan and he will be fully aware of the environmental process and requirements. The consultants will have similar understanding of the sector and the procedures involved, so that the quality EIA or EMP reports will be improved. The reviewers across the board may have same understanding about the sector and helps them in the process of review and appraisal. Public who are concerned about a new or expansion project, will have information about the environmental aspects, standards, regulatory requirements etc., and have a better understanding about the developmental project. To ensure effective utilization by different stakeholders this manual is divided into the following chapters: The preparation of sector specific guidance manual by Rajasthan State Pollution Control Board is in line with National Environmental Policy 2006, which emphasizes on:

- Formulate and periodically update, codes of good practices for environment for different category of industries

- Ensure faster decision making with greater transparency and access to information, together with necessary capacity building

The manual is meant to serve as a guidance purpose. In case of interpretation of any question related to law, the provisions of the original law and the rules made thereunder with various government directions/resolutions will have to be read and followed. In case of amendment to the original Act/Rules/Notifications made thereunder, the provisions as amended from time to time shall be applicable.

Page 10: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 8

CHAPTER I Introduction

1.0 About RSPCB The Rajasthan State Pollution Control Board (RPCB) is a statutory authority entrusted to implement environmental laws & rules within the jurisdiction of the State of Rajasthan. The Board ensures proper implementation of the statues, judicial and legislative pronouncements related to environmental protection within the state. The Board was established in the year 1975 under the provisions of Water (P&C of Pollution) Act 1974. Over the years, RSPCB was entrusted with various responsibilities under different enactments made. Currently RSPCB is responsible completely or partially for the implementation of following Acts and rules: • The Water (Prevention & Control of Pollution) Act, 1974 and Rules made there off • The Air (Prevention & Control of Pollution) Act, 1981 and Rules made there off • The Water (Prevention & Control of Pollution) Cess Act 1976 and Rules made there off • The Public Liability Insurance Act, 1991 and Rules made there off • The Environmental Protection Act, 1986 and Rules made there off

‐ Hazardous Wastes (Management, Handling & Transboundary Movement) Rules 2008

‐ Manufacture, Storage and Import of Hazardous Chemical Rules, 1989 as amended ‐ Municipal Solid Waste (Management and Handling) Rules, 2000 ‐ Bio Medical Waste (Management and Handling) Rules, 1998 as amended ‐ Ozone Depleting Substances (Regulation) Rules, 2000 ‐ The Batteries (Management and Handling) Rules, 2001 ‐ Fly Ash Notification as amended S.0. 2804(E) dated 3rd November 2009 ‐ Environmental Impact Assessment Notification, 2006 as amended ‐ The Chemical Accidents (Emergency Planning, Preparedness and Response) Rules,

1996 ‐ The Recycled plastic (Manufacture and Usage) Rules, 1999 as amended ‐ The Manufacture, Use, Import, Export and Storage of Hazardous Micro Organisms,

Genetically Engineered Organism or Cells Rules, 1989 ‐ Notification No. S.O. 319 (E) dated 7th May 1992 (Restricting certain activities in

special specified area of Aravalli Range) ‐ Notification No. S.O. 1545 (E) dated 25th June 2009 declaring Mount Abu Eco

Sensitive Zone ‐ The Noise Pollution (Regulation and Control) Rules, 2000 ‐ The EIA Notification S.O. 1533 dated 14th September 2006 as amended 1st December

2009

Page 11: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 9

1.1 Townships and Area Development projects - Classification by RPCB for consent management purpose The RPCB had categorized based on pollution causing potential, the Township and Area Development projects for consent management purpose as follows:

No. Project Description Red category

S.No.30 of Red category

Building/construction projects having built up area equal to or more than 20,000 Sq. meters

S.No.31 of Red category

Township projects of more than or equal to 50 ha

S.No.37 of Red category

Hotels: - Having capacity of 100 beds and above - Hotels and all tourism projects irrespective of their capacity which is amidst in any water body or which are located within 200 meters of HFL of any lake, reservoir, river or water body

S.No.43 of Red category

Hospitals (50 or more beds)

Orange category S.No.11 of Orange category

Hotels having capacity from 51 to 99 beds

S.No.30 of Orange category

Hospitals (less than 50 beds)

S.No.35 of Orange category

Water Treatment Plants of capacity more than 4.0 MLD

S.No.36 of Orange category

Multiplexes or building/construction projects having built up area less than 20, 000 sq. meters but more than or equal to 2500 sq. meters

Other category S.No. A of Other category

- All other industries which are not covered under the ‘Red’ or ‘Orange’ categories and are discharging waste, water and/or air emissions - All mines not included in Red & Orange categories and having area less than 1.0 - Water Treatment Plants of capacity up to 4.0 MLD - Hotel having capacity up to 50 beds - Fixed D.G sets with total capacity of more than or equal to 200 KVA

Reference: RPCB office order dated 03.04.2008 1.2 Townships and Area Development projects – Classification by MoEF for EC applicability Environmental Impact Assessment Notification S.O.1533 (E) of 14th September 2006 as amended in 2009 has made it mandatory to obtain prior environmental clearance for scheduled development projects. As per these notifications, Townships and Area

Page 12: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 10

Development projects are classified as category B projects. The following is the categorization made for the applicability of EIA Notification:

Category with threshold Project or activity Category A Category B

Conditions

8 (a)

Building and Construction projects

--- ≥20, 000 sq. meters and < 1,50,000 sq. meters of built-up area#

# Built up area for covered construction; in case of facilities open to the sky, it will be the activity area

8 (b)

Townships and Area Development projects

--- Covering an area ≥50 ha and or built up area ≥1, 50,000 sq. meters ++

++ All projects under item 8(b) shall be appraised as Category B1

7(c) Industrial estates/parks/complexes/areas, export processing zones (EPZs), special economic zones (SEZs), Biotech parks, Leather complexes

If at least one industry in the proposed industrial estate falls under the Category A, entire industrial area shall be treated as Category A, irrespective of the area Industrial estates with area greater than 500ha. and housing at least one Category B industry

Industrial estates housing at least one Category B industry and area <500ha Industrial estates of area >500ha. and not housing any industry belonging to Category A or B

Special conditions shall apply Note: Industrial estate of area below 500ha. and not housing any industry of Category ‘A’ or ‘B’ does not require clearance If the area is less than 500ha. but contains building and construction projects >20,000 sq.mtr and or development area more than 50ha it will be treated as activity listed at serial no. 8(a) or 8(b) in the Schedule, as the case may be

Reference: EIA Notification S.O 1533 dated 14th September 2006 and amended Notification S.O 3067 (E) dated 1st December 2009

Page 13: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 11

CHAPTER 2 Environmental Acts and Legal requirements

2.0 Legal requirements under the provisions of the Water (Prevention & Control of

Pollution Act) 1974 as amended

The Water (Prevention & Control of Pollution) Act, 1974 and as amended Section 25 (1) Restrictions on new outlets and discharges

Subject to the provisions of this section, no person shall, without the previous consent of the State Board a. Establish or take any steps to establish any industry, operation or process, or any treatment and disposal system or an extension or addition thereto, which is likely to discharge sewage or trade effluent into a stream or well or sewer or on land (such discharge being hereafter in this section referred to as discharge of sewage); or b. Bring into use any new or altered outlets for the discharge of sewage; or c. Begin to make any new discharge of sewage

Section 44 Penalty of contravention of section 25

Whoever contravenes the provision of section 25 shall be punishable with imprisonment for a term which shall not be less than two years but which may extend to six years and with fine

2.1 Requirements under the provisions of the Air (Prevention & Control of Pollution Act) 1981 as amended

The Air (Prevention & Control of pollution) Act, 1981 and as amended Section 21 (1) Restrictions on use of certain industrial plants

Subject to the provisions of this section, no person shall, without the previous consent of the State Board, establish or operate any industrial plant in an air pollution control area

Section 37 (1) Penalty of contravention of Section 21

Whoever fails to comply with the provisions of section 21, be punishable with imprisonment for a term which shall not be less than one year and six months but which may extend to six years and with fine

2.2 Requirements under the provisions of the Environment (Protection) Act, 1986 and as amended

S.O. 1533 dated 14th September 2006

Projects listed in the schedule shall obtain prior environmental clearance from the concerned regulatory authority.

Section 15 of E (P) Act 1986

Punishable with imprisonment up to 5 years with fine up to one lakh or with both

Section 16 of E When a company has committed offence under E (P) Act, and it is

Page 14: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 12

(P) Act 1986 proved that the offence has been committed with the consent or connivance of, or neglect on the part by any director, manager, secretary or other officials shall be deemed to be guilty and shall be liable for punishment.

2.3 Requirements for Ground Water Extraction Keeping in view of the requirements stated in the Policy guidelines for clearance of ground water abstraction for various uses issued by the Central Ground Water Authority, Ministry of Water Resources, GoI vide their letter dated 14.10.2009, the following guidelines regarding the requirement of NOC from CGWA for abstraction of ground water by any industry/ infrastructure project/ mine (proposed/existing) are being followed:

S. No Guidelines 1. NOC from CGWA shall not be required for abstraction of ground water in the

following cases: • In case of over-exploited areas abstraction<25m3/day • In case of critical areas abstraction <50 m3/day • In case of semi critical areas abstraction <100 m3/day

2. The exemption shall not be applicable to industries, which are using water as raw material such as packaged drinking water industries, distilleries and breweries

3. Industry/infrastructure project/time (proposed/existing) located in safe category areas, are required to obtain NOC from CGWA if ground water abstraction exceeds 1000 m3/day for hard rock areas and 2000 m3/day for alluvial areas

4. For the industry/infrastructure project/mine which proposed to abstract ground water more than the exempted quantity referred above, the Consent to Establish application will be considered only after submission of NOC from CGWA

5. The following conditions shall be imposed while issuing Consent to Establish • The artificial recharge proposal shall be vetted by the component authority

viz. Regional Director, Central Ground Water Board (WR), Jaipur/State Ground Water Department, Jaipur

• Industry shall undertake artificial recharge measures • Recycled and /or treated water shall not be used for recharge to ground

water • Industry shall provide suitable meter system and maintain proper record of

the daily abstraction of ground water 6. A copy of consent letter containing will be endorsed to Regional Director,

Central Ground Water Board (WR), 6A, Jhalana Institutional Area, Jaipur for their information and necessary action by RPCB

Please refer RPCB Circular dated 08.01.2010 for further information 2.4 Notification for Integrated Township dated 29.03.2007, Urban Development & Local Self Department, Government of Rajasthan The Government of Rajasthan had issued certain directions in their order dated 29.03.2007 to promote integrated development in future growth of the urban areas of the Rajasthan and to encourage private sector investment/foreign direct investment (FDI) in real estate sector.

Page 15: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 13

These directions were issued under Section 297 of the Rajasthan Municipal Act 1959, Section 90 of the Jaipur Development Authority Act 1982, Section 60 of the Raj Housing Board Act, 1970 and Rule 31 of the Rajasthan Urban Improvement (Disposal of urban lands) Rules 1974. Some of the provisions of this notification are listed below:

A. Integrated Township Schemes of Private Developers 1. Minimum area for integrated township shall be 10 hectares in Jaipur, 6 hectares in

Divisional Headquarters and 4 hectares in other Municipal Towns and District Head quarters

9 (a). The following land use distribution shall be ensured at scheme level

Residential Up to 50% Plotted apartments (of the scheme area 7.5% land be reserved for EWS and 0.5% land shall be reserved under “Jan Sathi” scheme/informal sector in the scheme

Commercial Up to 5% Available to developer for disposal Institutional (Educational /Medical etc)

Up to 10% Available to developer for disposal

Facilities (Roads, parks & open spaces)

Not less than 35% (including sector level roads)

To be developed as per approved planning. At least 10% area for parks & open spaces shall be reserved. This entire area under roads, parks & open spaces to be surrendered to local authority after development. The Local authority would ensure reservation of adequate land for games and sports facilities

9 (b). Local authorities would develop sector parks on the lines of sector roads as per zonal plans

10. No road shall be less than 40ft. and all the roads shall provide for standard street lighting and essential street furniture. Road connectivity shall be ensured by the developer

12. Gross residential density shall be prescribed on the basis of level of available external development infrastructure. Configuration of plotted/Group housing shall be developer’s option

14. Separate Building Regulations shall be framed for integrated township projects. Suggested points for inclusion in the Building Regulations are as under. The Local Authority shall prepare/amend Building Regulations accordingly: (i). Group housing projects to be encouraged in which all provisions for a decent communities living would be ensure, such securities arrangements, power/water backing backup shops for daily needs, provisions for service class, space for communities gathering, gyms, health club etc (ii). All public areas to have provisions for physically handicapped (iii). Rain water harvesting provisions will be compulsory in all group housing projects and township schemes (iv). Separate regulations for Group housing/malls to be proposed. The regulations so prepared shall provide for the provisions of parking and open spaces which shall be surrendered in favor of the Local Authority

15. In township schemes “community water harvesting strictures” will be constructed by local authority and all water outlets and drainages will be connected to this structure. This shall be strictly enforced by the local authority

21. An “Eco-cess” at the rate of Rs. 1/- per sq.yd. shall be charged by the local bodies for

Page 16: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 14

the lands to be developed under this scheme which shall be utilized for greening the city

22. The design of the township shall aim at water and energy conservation. This would mean

7. Proper orientation of building blocks ii. Use of appropriate building material iii. Use of non conventional energy sources, particularly solar energy iv. Recycling of waste water and water harvesting

23. The FAR of the entire gross area of township shall be 1.0. this would encourage proper mix of plotted development and group housing and would also encourage vertical development

B. Township Schemes of Local Authorities 1. The Jaipur Development Authority in case of Jaipur and local authority in consultation

with Town Planning Department of the State for other towns of Rajasthan shall declare a well-defined area in appropriate zone as “Town Planning Scheme”. The master plans would be suitably amended to accommodate such schemes

3. Sector plans shall be prepared indicating the sector road network and sector level uses 6. After deducting area of sector road, commercial strips, developer’s land and FDI

pockets from the project area, the redistribution of the available area shall be done in the following manner

Use Percentage Detailed Break up Residential/Plotted

63% 35% To be made available to khatedar in his own land or in the vicinity 15% To be retained by local authority towards cost of Internal Development 5% To be retained by local authority towards external development / augmentation of infrastructure 7.5% To be developed by local authority for EWS/LIG housing 0.5% Would be reserved for convenient shopping/kiosks/informal sector under “Jan Sathi” scheme

Internal Roads 20% Sectoral facilities 7% Local/level facilities/open spaces/parks

10%

C. General Conditions

3.i. Local authority would issue NOC to the developers as per provisions of Master plan and land use plan

3.iii. Conversion of land would be allowed according to master plan provisions. Wherever required, change in land use would be first ensured before conversion is permitted

5. Pollution Control Board norms for townships with respect to provisions of Environmental Clearance as required under Ministry of Environment and Forests (GoI) Notifications shall be applicable

7. The provisions will also apply in the entire NCR Region of Rajasthan state App If in case of individual khatedar schemes, the entire internal development will be done

Page 17: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 15

endix - 1

by the local authority for which plots of equal value would be handed over by the khatedar developer to the local authority

Appendix - 1

Time limit foe completion of project

Type Time period from date of sanction Land development with respect to roads, drains, sewerage, power & water supply etc

Up to 10 ha - 3 years 25% development by the end of the I year 50% development by the end of the II year 100% development by the end of III Year For more than 10 ha - one additional year for each additional 10 ha

Land development & construction works (minimum of 25% on every earmarked plot)

Up to 10 ha - 4 years 33% development by the end of the II year 66% development by the end of the III year 100% development by the end of IV Year For more than 10 ha - one additional year for each additional 10 ha

Please refer to the Notification dated 29.03.2007 for details 2.5 Requirements under the Notification No. S.O.319 (E) dated 7th May 1992 and S.O. 1189 (E) dated 29th November 1999 – Restriction of certain activities in specified area of Aravalli range: The MoEF, GoI had stipulated restrictions on certain activities in specified area of Aravalli Range vide Notification No. S.O. 319 (E) dated 7th May 1992 and as amended. As per the Notification the Central Government prohibits the carrying on the following processes and operations, except with its prior permission, in the specified area. Processes and activities which require prior permission

• Location of new industry including expansion/modernization • A. All new mining operations including renewals of mining lease

B. Existing mining leases in sanctuaries/national park and areas covered under Project Tiger and/or C. Mining is being done without permission of the competent authority

• Cutting of trees • Construction of any clusters of dwelling units, farms houses,

sheds, community centres, information centres and any other activity connected with such construction (including roads a part of any infrastructure relating thereto)

• Electrification (laying of new transmission lines) Areas covered under the Notification

• All reserved forests, protected forests or any other area shown as “forest in the land records maintained by the State Government as on the date of this notification in relation to Gurgaon District of the State of Haryana and the Alwar District of the State of Rajasthan

• All areas shown as

Page 18: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 16

a. Gair Mumkin Pahar, or b. Gair Mumkin Rada, or c. Gair Mumkin Behed, or d. Banjad Beed, or e. Rundh

In the land records maintained by the State Government as on the date of this notification in relation to Gurgaon district of the State of Haryana and the Alwar district of the State of Rajasthan • All areas covered by notifications issued under Section 4 and 5 of the

Punjab Land Preservation Act, 1900, as applicable to the State of Haryana in the district of Gurgaon up to the date of this notification

• All areas of Sariska National Park and Sariska Sanctuary notified under the Wildlife (Protection) Act, 1972 (53 of 1972)

Clearance process

Any person desirous of undertaking any of the activities mentioned in the Notification No. 319 (E) dated 7th May 1992 shall submit an application to the Secretary, Department of Environment of the Government of Haryana/Rajasthan, as the case may be. The applicant shall also furnish environment impact statement and an environment management plan and such other information as may be prescribed by such State Governments. The application after due scrutiny shall be placed before the Expert Committee for its recommendations. Based on the recommendations of the Expert Committee, the Department of Environment in the State Government concerned shall take a final decision and convey the same to the applicant within the three months from the date of receipt of application or when further information has been asked for from the applicant within three moths from the date of receipt of such information

Monitoring mechanism

Monitoring Committee, under the Chairmanship of District Collector concerned (Gurgaon in Haryana and Alwar in Rajasthan) shall inter alia monitor the compliance of the conditions stipulated while according Environmental Clearance by State Government The District collectors of Gurgaon in Haryana and Alwar in Rajasthan shall be authorized by the respective State Governments to take necessary action under section 5 of the said Act in respect of cases where the project proponents fail to implement the conditions

Appeal provision

The MoEF retains appellate power against rejection of any proposal and the National Environmental Appellate Authority constituted under the National Environment Appellate Authority Act, 1997 (22 of 1997) shall continue as an Appellate Authority against approval

Note: Refer the Notification for details 2.6 Requirements under the Notification No. S.O. 1545 dated 25th June 2009 – Mount Abu Eco Sensitive Zone Mount Abu area has significant ecological importance comprising of tropical dry deciduous forests at lower altitude and evergreen forests at higher altitude and the flora and fauna of the region comprise of several endemic and rare species; besides Mount Abu has natural heritage such as Nakki Lake and man-made heritage like Dilwara temples and other

Page 19: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 17

heritage buildings and structures. To conserve and protect the area from ecological and environmental point of view, the MoEF had issued Notification No. S.O. 1545 dated 25th June 2009 regulating certain activities in the eco-sensitive zone Regulated Activities

Pending the preparation of the Zonal Master Plan for Eco-sensitive zone and approval thereof by the Central Government in the MoEF, there shall be no increase in the existing parameters of permissible floor area ratio, permissible ground coverage, maximum number of floors and maximum height and all new constructions shall be allowed only after the proposals are scrutinized and approved by Monitoring Committee and all other development activities including additions, alterations, demolitions, repairs, renovations and restorations of buildings shall require prior approval of the Monitoring Committee provided that these do not involve structural changes and are on the existing authorized plinth areas in the Mount Abu Municipal Limits and there shall be no consequential reduction in Tribal area, Forest area, Green area and Agricultural area

Boundaries of the eco-sensitive zone

a. The said eco-sensitive zone is situated in the southern area of Rajasthan in Sirohi District between 240 33’42’’ and 240 39’ 00’’ North latitude and between 720 41’ 36’’ and 720 48’ 06’’ East longitude and the configuration of land is hilly and rugged with high altitudinal variation ranging from 300 meter to 1727 meter. Gurushikar, the highest peak of the Aravalli, is the highest peak between the Himalayas and the Nilgiris. The boundaries of the said eco-sensitive zone comprise North - Southern boundary of Abu Forest Block No.3 South - Northern Boundary of Abu Forest Block No. 1 East - Western and Southern Boundary of Abu Forest Block No.2 West - Eastern boundary of Abu Forest Block No. 3 b. The Eco-sensitive zone covers the entire area of Notified Urban Area Limit, including Mount Abu Municipal Limits adjoining Forest Block Areas. c. The list of the villages in the eco-sensitive zone – Sanigaon, Machgaon, Goagaon, Delwara, Oriya, Jawal, Achalgarh, Salgaon, Torna, Dudhai, Hetamji, Ama d. All activities in the Forest Block Areas (both within and outside Municipal Areas) shall be governed by the provisions of the Rajasthan Forest Act, 1953 and the Forests (Conservation) Act, 1980 (69 of 1980) and all the activities in the Protected Areas (Sanctuary) shall be governed by the provisions of the Wildlife (Protection) Act, 1972 (53 of 1972)

Trees There shall be no felling of trees whether on Forest, Government, Revenue or Private lands within the Eco-sensitive zone without the prior permission of the State Government in case of forest land and the respective District Collector in case of Government, Revenue and Private land as per the procedure which shall be laid down by the State Government

Tourism The tourism activities shall be as per the Tourism Master Plan to be prepared by the Department of Tourism of the Rajasthan State Government

Water • All future and existing buildings, where possible, in the Municipal Are shall provide roof-top rain water harvesting structures with plinth area

Page 20: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 18

and the Institutional and commercial buildings shall not draw water from existing water supply schemes in a manner that adversely affects water supply especially to local villages or settlements

• In Non-Municipal Areas rain water harvesting shall be undertaken through such structures as percolation tanks and storage tanks and only other means. Ground water aquifer recharge structures shall be constructed wherever such structures do not lead to slope instabilities

• The rain water collected through storm water drains shall be used to recharge the ground water or to clean the waste disposal drains and sewers

• The extraction of ground water shall be permitted only for the bona-fide agricultural and domestic consumption of the occupier of the ply and the extraction of ground water for industrial or commercial or residential estates or complexes shall require prior written permission, including of the amount that can be extracted, from the State Ground Water Department. However, the areas rich in ground water may not be delivered for construction activities

Use of Plastics

No person shall use plastic carry bags within the notified area

Development on and protection of hill slopes

• The zonal Master Plan shall indicate areas o hill slopes where development shall not be permitted

• No development shall be undertaken in areas having a steep slope or areas which fall in fault or hazard zones or areas falling on the spring lines and first order streams or slopes with a high degree of erosion as identified by the State Government on the basis of available scientific evidence

• No development on existing steep hill slopes or slopes with a high degree of erosion shall be permitted

Discharge of sewage and effluents

No untreated sewage or effluent shall be permitted to be discharged into any water body or forests within the eco-sensitive zone and the local authority shall provide proper drainage and treatment system for collection, treatment and disposal of untreated/and treated effluent in accordance with the provisions of the Water (Prevention and Control of Pollution) Act, 1974. Moreover, the treated sewage and treated effluent shall be disposed only at or into a point(s) identified and approved by the local authorities and the Monitoring Committee

Monitoring Committee

Under the provisions of sub-section (3) of Section 3 of the Environment (Protection) Act, 1986 (29 of 1986), the Central Government shall constitute a committee to be called the Monitoring Committee to monitor the compliance of the provisions of this notification In case of activities requiring prior permission on environmental clearance, such activities shall be referred to the State Level Environmental Impact Assessment Authority, which shall be the Competent Authority for grant of such clearances

Note: Refer the Notification for complete details

Page 21: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 19

CHAPTER 3 Statutory Clearance Process

3.0 Environmental Clearance process The Township and Area Development project covering an area ≥50 ha and or built up area ≥1, 50,000 sq. meters, attracts the provisions of EIA Notification dated 14th September 2006 and amended in 2009. All such projects are categorized as B1 projects. The process of environmental clearance involves submission of Form I (Annexure 1), Form IA (Annexure 2), copy of the conceptual plan along with proposed TOR to the State Environmental Impact Assessment Authority (SEIAA). Figure 3.1 shows process involved in the prior environmental clearance for Township and Area Development projects.

Page 22: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 20

* The proponent should apply for CRZ clearance, as per applicability

Figure 3.1 Prior Environmental clearance process for category B projects

Project Concept and Site selection*

Draft EIA report to SPCB/UTPCC by project

proponent

EC- rejected by SEIAA on the recommendation of SEAC

TOR approved by SEAC

Rejected Approved

Post EC monitoring Submission of half yearly compliance report to SEIAA

Display of compliance report on SEIAA

website

Approval by SEIAA

Appraisal and recommendation by SEAC

Referred back to SEAC under communication to

the project proponent

Display on the SPCB/UTPCC website & project proponent website

Scoping by SEAC (site visit by sub group of SEAC, if necessary)

Form 1, Form 1 A, conceptual plan with proposed TOR to SEAC

Clarifications by SEAC /Modifications by project proponent

Display on the SEIAA website

Page 23: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 21

3.1 Public Consultation

As per Para No 7 (i) (III) (d) of EIA Notification dated 14th September 2006 as amended 1st December 2009, all building/construction projects/area development projects and townships are not required to undertake public consultation process. 3.2 Validity of Environmental Clearance The prior environmental clearance granted is valid for a period of five years. The regulatory authority concerned may extend this validity period by a maximum period of five years. However, in the case of Area development projects and Townships [item 8(b)], the validity period shall be limited only to such activities as may be the responsibility of the applicant as a developer. This validity period may be extended by the regulatory authority concerned by a maximum period of 5 years provided an application is made to the regulatory authority by the applicant within the validity period, together with an updated Form I, and supplementary Form IA, for construction projects or activities. 3.3 Post Environmental Clearance Monitoring The project proponent shall prominently advertise in the newspapers indicating the project has been accorded environmental clearance and the details of regulatory authority website where it is displayed. To the regulatory authority concerned all such reports shall be public documents. The latest such compliance report shall also be displayed on the website of the concerned regulatory. 3.4 Transferability of Environmental Clearance A prior Environmental Clearance granted for a specific project or activity to an applicant may be transferred during its validity to another legal person entitled to undertake the project or activity on application by the transferor or the transferee with a written “no objection” by the transferor, to, and by the regulatory authority concerned, on the same terms and conditions under which the prior environmental clearance was initially granted, and for the same validity period. 3.5 Criteria for EIA consultants The MoEF, GoI had stipulated certain criteria for EIA consultants as per the Ministry’s office memorandum dated 2nd December 2009, and the same is kept in the public domain of Ministry’s website (www.envfor.nic.in). Accordingly, the EIA consultants shall have accreditation with Quality Control of India (QCI)/National Accreditation Board of Education and Training (NABET). The consultants shall include the copy of the accreditation certificate and that provided by the other organizations/laboratories including their status of approvals etc. the EIA/EMP reports prepared by the consultants who are not registered with NABET/QCI shall not be considered by the Ministry after 30th June 2010. 3.6 Authorized Signatory All correspondence with the regulatory authority including submission of application for TOR/Environmental Clearance, subsequent clarifications, as may be required from time to

Page 24: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 22

time, participation in the EAC Meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory shall also submit a document in support of his claim of being an authorized signatory for the specific project (EIA amendment Notification dated 1st December 2009). 3.7 Participation of the project proponent during the EAC meetings As per the office memorandum dated 25th February 2010 of MoEF, the authorized representative of the project proponent shall only attend the EAC meetings. The authorized representative of the project proponent should be a reasonably senior officer / executive duly authorized in writing. In case, a consultant is to be nominated as the authorized representative, it should be through a irrevocable power of attorney executed and formally registered with the Sub-Registrar concerned. A copy of the authorization / registered power of attorney, as the case may be should be submitted to the ministry for record. The authorized representative, so nominated should only participate in the EAC meetings on behalf of the project proponent. The consultant (s) and other experts may, however, assist the authorized representative during the meeting. In the absence of the authorized representative, the proposal will not be considered by the EAC. 3.8 Projects requiring recommendation of the Chief Wildlife Warden If the project is located within 10 km radial distance from the national parks, sanctuaries, biosphere reserves, migratory corridors of wild animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations or comments of the Chief Wildlife Warden thereon at the stage of EC (EIA amendment Notification dated 1st December 2009). 3.9 Consent Management System – RPCB

The project proponent is required to obtain consent of the Board, before start of the project. The consent management process adopted at RPCB is explained below in the form of different questions and answers to facilitate better understanding for the project proponent as well as other stakeholders.

Page 25: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 23

01. What projects are required to apply for CTE?

Township and Area Development Projects covering all or any of the following shall apply for CTE:

Red category Building/construction projects having built up area equal to or more than 20,000 Sq. meters Township projects of more than or equal to 50 ha

Hotels: • Having capacity of 100 beds and above • Hotels and all tourism projects irrespective of their capacity

which is amidst in any water body or which are located within 200 meters of HFL of any lake, reservoir, river or water body

Hospitals (50 or more beds) Orange category • Hotels having capacity from 51 to 99 beds • Hospitals (less than 50 beds) • Water Treatment Plants of capacity more than 4.0 MLD • Multiplexes or building/construction projects having built up

area less than 20, 000 sq. meters but more than or equal to 2500 sq. meters

Other category • Water Treatment Plants of capacity up to 4.0 MLD • Hotel having capacity up to 50 beds • Fixed D.G sets with total capacity of more than or equal to

200 KVA 02. What to apply? The project proponent shall apply in the prescribed CTE

application form along with requisite enclosures, CTE fee and data. The CTE application is as given in Annexure 3 & 4. It can be downloaded from RPCB web also (www.rpcb.nic.in)

03. What is the fee to be submitted?

CTE fee is to be paid along with CTE application as notified by the DoE, Government of Rajasthan under section 64 of the Water (P&CP) Act, 1974 as amended and under section 54 of the Air (P&CP) Act, 1981 as amended (Annexure 5 & 6). The CTE fee is to be paid on the following basis as per the Notification dated 25th May 2009. • Capital investment • Categorization of the project • Whether the project attracts the provision of the Hazardous

Waste (Management & Handling) Rules, 1989? If yes, then fee equal to one and half times fee prescribed in the schedule of the Notification shall be paid

• Whether the project requires environmental clearance under the provisions of E (P) Act, 1986? If yes, shall pay an extra amount of Rs 15,000/-, as one time consent fee to establish in addition to the fee mentioned in the schedule under the

Page 26: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 24

provisions of Water Act & Air Act Points for discussion Whether HW Rules 1989 or HW Rules 2008 are to be considered for fee purpose?

04. What is meant by capital investment of the industry?

For calculating the investment in plant and machinery, the cost of pollution control, research & development, industrial safety devices and such other items as may be specified by the notification, shall be excluded (RSPCB office order amendment dated 18.12.2008). Points for discussion with Core Team of RPCB: • What type of documents, the project proponent shall

submit in support of the capital investment mentioned in the CTE application?

• Incase of expansion, whether the capital investment of the expansion only to be considered for arriving applicable fee slab

• Whether the Land cost component is to be added or not? • Whether the depreciation should be considered or not while

calculating the capital investment 05. What is the mode of payment of CTE fee?

Instrument : Infavour of : Online payment : (Inputs requested from RPCB)

06. Whom to submit the CTE application?

Inputs requested from RPCB

07. Is there any provision to apply CTE application on-line?

Inputs requested from RPCB

08. What is the procedure to apply on line?

Inputs requested from RPCB

09. Who will issue acknowledgment towards receipt of the application?

Inputs requested from RPCB

Page 27: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 25

10. Whether NOC from CGWA is a pre-requisite for processing CTE application?

Yes, in the following cases: • If the abstraction of ground water is ≥ 25 m3/day, in case of

over exploited areas • If the abstraction of ground water is ≥ 50 m3/day, in case of

critical areas • If the abstraction of ground water is ≥ 100 m3/day, in case of

semi critical areas • The exemption shall not be applicable to industries, which are

using water as raw material such as packaged drinking water industries, distilleries and breweries

• Industry/infrastructure project/mine (proposed/existing) located in safe category areas, are also required to obtain NOC from CGWA if ground water abstractions exceeds 1000m3/day for hard rock areas and 2000m3/day for alluvial areas

• CTE application will be considered by RPCB only after submission of NOC from CGWA in above cases

(Please refer RPCB Circular Guidelines dated 08.01.2010) Points for discussion: As per the circular dated 30.04.2008, CTE for the units, which propose to extract ground water more than 200 KLD, the CTE application will be considered only after submission of NOC from CGWA…whether this circular instruction is still in practice in view of the latest circular dated 08.01.2010 on the subject matter or not?

11. What are the areas as identified by CGWA as – safe areas, semi – critical areas, critical areas & over exploited areas?

The details are given in Annexure 7

12. Whether prior environmental clearance is a pre- requisite to submit the CTE application?

Inputs requested from RPCB

13. Whether NOC from Local authority is a pre – requisite to submit CTE application?

Inputs requested from RPCB

14. Whether conversion of land, wherever required, is a pre – requisite to submit CTE application?

Inputs requested from RPCB

15. Who will process the CTE application?

Inputs requested from RPCB

Page 28: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 26

16. Who is the authority to accord the CTE application?

Red Category projects Chairperson Orange category Regional officer Other category Assistant Environmental

Engineer* *As per RPCB office order dated 18.12.2009

The consent to the units covered by the Aravalli Notification will be dealt at Head Office level and not at R.O level Points for discussion: Whether AE at RO level or AE at HO level are authorized to accord CTE

17. What is the maximum time period to process the CTE application?

Statutory time limit: Section 25(7) of Water (P&CP) Act, 1974 as amended: Four months on submission of application, complete in all aspects Section 21(4) of Air (P&CP) Act, 1981 as amended: Four months after receipt of the application Administrative time limits of RPCB:

Red category projects 6 weeks Orange category projects 4 weeks Other category projects 4 weeks

18. Is there any deemed provision?

YES, there is provision under the Water Act Section 25 (7) of the Water (P&CP) Act, 1974 as amended: Deemed to have been given unconditionally on the expiry of four months of making of an application complete in all respects to the Board AIR ACT ….to be discussed with RPCB

19. What is the mode of communication of the approval / rejection order of CTE?

RPCB to confirm the following: Hard copy: By RPAD Soft copy: By mail Down loads: From RPCB web

20. Is there any appeal mechanism?

Section 28 (1) of Water (P&CP) Act, 1974 as amended: Any person aggrieved by the order made by the State Board under section 25, 26 and 27 may within 30 days from the date on which is communicated to him, prefer an appeal before Appellate Authority constituted by the State Government. The appellate authority may entertain the appeal after the expiry of the said period of thirty days, if such authority is satisfied that the appellant was prevented by sufficient cause from filing the appeal in time Section 31 (1) of Air (P&CP) Act, 1981 as amended: Any person aggrieved by an order made by the State Board under this Act may, within thirty day from the date on which the order is communicated to him, prefer an appeal to Appellate Authority

Page 29: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 27

constituted by the State Government The appellate authority may entertain the appeal after the expiry of the said period of thirty days if such authority is satisfied that the appellant was prevented by sufficient cause from filing the appeal in time

21. Whether the CTE obtained from the board can be transferred to any other person?

Section 21 (7) of the Air (P&CP) Act, 1981 as amended: Where a person to whom consent has been granted by the State Board under section 21 (4) transfers his interest in the industry to nay other person, such consent shall be deemed to have been granted to such other person and he shall be bound to comply with all the conditions subject to which it was granted as if the consent was granted to him originally Points for discussion under the provisions of the Water Act

22. What is the validity period for CTE?

CTE will be valid for a period of three years or till the commissioning of the unit (RPCB Office order dated. 10.08.2001)

23. What is the procedure for extension of CTE?

For inputs from RPCB

24. Is there any criterion for consultant for preparation of EIA/EMP?

For inputs from RPCB

25. Are there any standards notified for discharge of wastewater?

The MoEF, GoI vide Notification No.G.S.R 422 (E) dated 19.05.1993 and G.S.R 801 dated 31.12.1993 had notified general standards for discharge of effluents (Annexure 8)

26. Are there are any specific noise standards applicable to D.G. Sets?

Notification No. 371(E) dated 27.05.2002 - E (P) Act, 1986: Noise limit for Diesel Generator Sets (up to 1000 KVA) manufacture on or after the 1st July, 2003 • The maximum permissible sound pressure level for new diesel

generator (DG) sets with rated capacity up to 1000 KVA, manufactured on or after the 1st July, 2003 shall be 75 dB (A) at 1 meter from the enclosure surface

• The diesel generator sets should be provided with integral acoustic enclosure at the manufacturing stage itself

Noise limit for DG sets not covered above Noise from the DG set should be controlled by providing an acoustic enclosure on by treating the room acoustically, at the users end The acoustic enclosure or acoustic treatment of the room shall be designed for minimum 25 dB (A). Insertion Loss or for meeting the

Page 30: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 28

ambient noise standards, whichever is on the higher side (if the actual ambient noise is on the higher side, it may not be possible to check the performance of the acoustic enclosure/acoustic treatment. Under such circumstances the performance may be checked for noise reduction up to actual ambient noise level, preferably, in the nighttime. The measurement for Insertion Loss may be done at different points at 0.5m from the acoustic enclosure/room, and then averaged The DG set shall be provided with proper exhaust muffler with Insertion Loss of minimum 25 dB (A) Requirement of certification Every manufacturer or importer of DG set to which these regulations apply must have valid certificates of type approval and also valid certificates of conformity of production for each year, for all the product models being manufactured or imported from 1st July 2003 with the noise limit specified in the Notification. The conformance label must contain the following information a. Name and address of the supplier (if the address is described in the owner’s manual, it may not be included in the label) b. Statement “This product confirms to the Environment (Protection) Rules, 1986” c. Noise limit viz. 75 dB (A) at 1m d. Type approval certificate number e. Date of manufacture of the product Notification No. S.O. 50(E) dated 11th January 2010 – E (P) Act 1986: A loud speaker or a public address system r any sound producing instrument or a musical instrument or sound amplifier shall not be used at night time (10.00 pm to 6.00 am) except in closed premises for communication within, like auditoria, conference rooms, community halls, banquet halls or during public emergency

27. Is there any guideline to calculate the minimum requirement of the stack of D.G set?

The CPCB had evolved the minimum height of the stack to be provided to the DG set and published in Emission Regulations Part IV: COINDS/26/1986-87. H= h+0.2 x ÖKVA

H Total height of stack in meter h Height of the building in meters where the

generator set is installed KVA Total generator capacity of the set in KVA

Based on the above formula the minimum stack height to be provided with different range of generator sets may be categorized as follows:

Page 31: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 29

For generator Sets Total height of stack in meter 50 KVA Ht. of the building +1.5 meter 50-100 KVA Ht. of the building +2.0 meter 100-150 KVA Ht. of the building +2.5 meter 150-200 KVA Ht. of the building +3.0 meter 200-250 KVA Ht. of the building +3.5 meter 250-300 KVA Ht. of the building +3.5 meter

28. Is there any standards notified for ambient noise level?

CPCB notified National Ambient Air Quality Standards dated 18th November 2009 (Annexure 9)

29. Where shall the ambient noise levels be monitored for compliance?

The ambient air quality standards in respect of noise as notified under E (P) Act, 1986 shall be monitored at the boundary of the project for compliance

30. Whether any procedures notified for handling solid waste?

MoEF had notified procedures and standards for handling municipal solid waste vide Municipal Solid Waste (Handling &Management) Rules, 2000

31. What are the post project monitoring requirements after obtaining CTE?

Inputs requested from RPCB

32. Whether Township and Area Development Projects are required to apply for Consent To Operate?

Inputs requested from RPCB

33. Whether Township and Area Development Projects are required to apply for Hazardous Waste Authorization?

Inputs requested from RPCB

34. Whether Township and Area Development Projects are required to file water cess returns?

Inputs requested from RPCB

Page 32: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 30

CHAPTER 4

Environmental Aspects and Guidance 4.0 Environmental checklist The project proponent, reviewer and the public to have a better understanding on the environmental aspects, can use the following checklist: S. No Description Yes No Remarks

Land Environment 01. Whether the proposed project is in conformity with the

approved master plan / development plan of the area?

02. Whether the proposed project requires change of land use and if so, the status in obtaining statutory approval from the competent authority?

03. Whether the existing land use will be significantly altered due to the proposed project activity?

04. Whether the proposed project disturbs sites with heritage and cultural values such as protected monuments?

05. Whether topsoil management is prepared for storing and using the topsoil excavated during the construction work?

06. Whether any natural stream is passing through the project area? If yes, whether it will be blocked?

07. Whether the natural drainage system will be altered? 08. Whether it is proposed to construct any compound wall

along the project boundary? If yes, whether any storm water management plan is prepared?

Water Environment 09. Whether estimation of water demand for peak and

ultimate project requirement is assesses as per the norms?

10. Whether reliable source of water for peak and ultimate demand has been identified?

11. Whether the stress, if any, on the ground water/surface water availability has been assessed and to see there is no pressure on the existing users of the water?

12. Whether the quality of the water is assessed, in case of own arrangements by the project developer i.e. the source of water supply is not by the local authority?

13. Whether any on-site water treatment facility is proposed? 14. Whether adequate safe drinking water facility and

proper sanitary facilities are planned for the construction workers?

Page 33: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 31

S. No Description Yes No Remarks 15. Whether dual plumbing system for using treated

wastewater for flushing the toilets or any other usage is explored?

16. Whether it is proposed to have on-site sewerage treatment plant with reuse/disposal for green belt?

17. Whether construction of internal sewerage network is proposed as a part of the project?

18. Whether sewerage network with treatment system already exists in the area? If yes, any assessment is made on the adequacy of the sewer network and STP to handle the additional domestic liquid waste from the proposed development?

Solid Waste 19. Whether a plan has been prepared for proper disposal of

construction debris and waste?

20. Whether estimation of solid waste generation for the peak and ultimate project stage is assessed as per the norms?

21. Whether segregation of solid waste is planned? 22. Whether the possibility of providing on-site treatment of

organic waste to convert the biodegradable waste into manure, is examined?

23. Whether final disposal point for municipal solid waste is identified? Incase, if it proposed to dispose at secured landfill maintained by the local authority, whether details of the secured landfill such as authorization obtained from the Board, distance from the project area, mode of disposal, responsibility for transportation and disposal are furnished?

Air Environment 24. Whether dust generation during excavation, blasting

and construction is addressed and planned with mitigation measures?

25. Whether dust generated during the transportation and storage of the raw materials is addressed and planned with mitigation measures?

26. Whether mitigation of automobile air emissions is planned?

Noise Environment 27. Whether noise due to blasting of the rocks at project site

and due to operation of equipments such as DG sets is addressed?

Biological Environment 28. Whether the project involves cutting of trees? 29. Whether green belt plan is prepared along with

implementation schedule and responsibility for maintenance?

Page 34: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 32

S. No Description Yes No Remarks 30. Whether any forest area is covered in the proposed

project site?

31. Whether there is any threat to bio diversity due to the project?

Planning 32. Whether road connectivity to the project site is planned

as a part of the development project?

33. Whether diverse use facilities needed in layout development have been assessed?

34. Whether the land use distribution at scheme level is planned as per the norms?

35. Whether parking requirements is assessed and provision made for the peak and ultimate project stage as per the norms? What are the norms followed?

36. In case of provision of community halls, stadiums, theatres etc., where huge gathering is expected, whether assessment on parking requirement and adequacy of the road network is made or not?

37. Whether fire fighting installations are planned as recommended in the code of practice i.e. National Building Code of India 2005, BIS

38. Whether construction of internal roads is proposed as a part of the project?

39. Whether construction of internal storm water drains is proposed as a part of the project?

40. Whether the project area likely to have moderate to high intensity of earthquake, or cyclonic storm, or significant flood flow or inundation, or land slides / mud flows / avalanches, or one or more of hazards? If yes, whether appropriate safety measures are incorporated in the project?

Natural Resources 41. Whether provision for rainwater harvesting is

proposed?

42. Whether provision to collect the rooftop is explored? 43. Whether the possibility of providing solar heating

system for water heating, cooking etc, is examined?

44. Whether the possibility of providing solar lighting for streetlights and timer based lighting management in common area, is assessed?

45. Whether the usage of glasses at external portion of the building is kept at optimal to reduce the electricity consumption and load on air – conditioning system? Whether the use of double glass with special reflective coating is examined?

46. Whether the usage of thermal insulation for the rooftop is examined to reduce the energy requirement?

Page 35: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 33

47. Whether the usage of fly ash or alternate building materials is explored?

4.1 Environmental Norms S. No Description of the norms Notification

01 General Standards for Discharge of Effluents

Notification No. G.S.R 422 (E) dated 19.05.1993 and G.S.R 801 (E) dated 31.12.1993 issued under the provisions of E (P) Act 1986 (Annexure 8)

02 National Ambient Air Quality Standards

CPCB Notification No. B-29016/20/90/PCI-I dated 18th November 2009 (Annexure 9)

03 National Noise Ambient Air Quality Standards

The Noise Pollution (Regulation & Control) Rules, 2000 – S.O. 123 (E) dated 14th February 2000 and as amended in S.O. 1046 (E) dated 22.11.2000 (Annexure 10)

04 Noise Limit for Generator Sets Run With Diesel

Notification No. G.S.R 371 (E) dated 17th May, 2002 (Annexure 11)

05 Standards for discharge of effluents for hotel industry

Notification No G.S.R 794 (E) dated 4th November, 2009 (Annexure 12)

06 The Ozone Depleting Substances The Ozone Depleting Substances (Regulation & Control) Rules, 2000 – S.O. 670 (E) dated 19.07.2000

4.2 Guidelines for the project developer

The project developer is advised to refer to the following documents:

• EIA guidance manual for Building construction, Townships and Area Development of

MoEF • National Building Code of India 2005 • Development Control Rules – Town and Country Planning

Design layout should ensure adequate solar access and ventilation Depending upon the geographical latitude and sky conditions a precise analysis of the local climate; surroundings, urban development and surrounding terrain in relation to solar access, daylight availability and predominant air movement should be carried out. This would control minimum distances to be kept between the built up volume and open spaces. The design of the layout should allow for wind protection and solar access in winter, and at the same time provide adequate sun protection and ventilation in summer months. The size and density of the layout should provide desired comfort levels maximum from natural resources. Solar path analysis and wind pattern assessment should be carried out in the design stage that would help developers decide upon the alternatives for the type of layout and the proportion of the built volume and open space in the layout.

Page 36: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 34

The submittals should be provided only to indicate the optimized layout of buildings on the site with respect to sun path and optimized solar access and availability of wind for natural ventilation. Following are the factors, may be considered during the lay out design. Open spaces

The proportion of open space and its built-up edges should be designed such that it ensures winter solar access and summer ventilation. Vegetation may provide as shading and promote evaporative cooling. In hot dry climates, evaporative cooling through appropriately sized wet surfaces or fountains have a desirable effect. Design layout should ensure the following

• Area allotted for Sewage Treatment plant • Area allotted for of Garbage Segregation • Area allotted for of DG Sets • Parking requirement should meet the local body requirements • Area for visitors parking • Area for green belt and lawns

Sustainable site planning Site planning is a vital component of any type of development activity and is the first step. However, ideally the design team should be involved in site selection and should assess the appropriateness of the site relative to the proposed development. Analysis and assessment of the site characteristics in terms of its capacity to provide natural resources inside the building such as light, air and water without damaging the natural environment should be carried out during site selection and analysis process Sustainable site planning is a critical phase of the green design process. When selecting a potential site, you should look to eliminate or minimize the disruption of the existing environment as much as possible. Using the topography of the site is paramount. This allows for detailed planning that outline the existing and proposed design concepts to include the home location, vegetation, land slope, setbacks, and other crucial factors Cut and fill: Preserve natural slopes to aid natural drainage. The amount of excavation should be minimized as far as possible. Removing or importing soil (also known as cut and fill) adds to environmental emissions via the transporting of the soil. Furthermore, rearranging the landscape may disturb the flow of water being directed away from the project. This may affects the original contours of the surrounding areas

Landscaping: Preserve natural landscaping whereever possible and use vegetation of native to the environment. Layout and form of the project must conform to the landscape of the area without unduly affecting the scenic features of that place.

Land use distribution at scheme level: Land use distribution at scheme level shall be planned while designing the project lay out.

Page 37: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 35

Ambient environment quality in the region: Levels of air, noise and water pollution should be surveyed and considered carefully before implementing the building design. For example: High level of air, noise and water pollution and location near pollution sources such as heavy traffic roadways should be considered carefully to implement developing the area. Availability of infrastructure: Infrastructure requirement should be properly assessed such as: Development of Roads Development of Drainage Providing Water supply Providing Power and Telecom facilities Planting trees along with roads Storm water management and Rain water Harvesting System Street lights

Site Location: Urban infrastructure and facilities, public transport, infrastructure for power, water supply to meet the estimated requirement, sewage system network should be available nearby or should be made available with minimum environment impact. The following information may help in assessing requirements of infrastructure: Distance from Highway Distance from Municipal road Width of Road adjacent to the site Nearest Bus Stop and Railway Station Distance from facilities like post office, police station, fire station Distance from nearest bank, school, college, market etc.

Onsite management of waste: The following requirements are very important from environmental consideration Land acquired should be minimum but sufficient to provide for a green belt wherein the

treated wastewater, if possible/ suitable, could be utilized from wastewater treatment systems.

Adequate space may be provided for storing solid wastes. The space and the waste can be made available for possible reuse in future.

Adequate space shall be provided for construction of STP Diverse Use Facilities in the layout development: The diverse use facilities such as Bank, Community /civic center, Convenience store, Hair care, Hardware store, Health club or outdoor recreation facility, Laundry/dry cleaner Library, Medical/dental office, Pharmacy (stand-alone), Place of worship, Police/fire station, Restaurant, School, Supermarket, Theater, Over Head Tank, Sewage treatment plant, Garbage segregation point should be assessed

Estimation of water demand: The water demand should be estimated by adopting the WHO guideline of minimum water requirement of 135 LPCD for a family of 5 for each dwelling. Care must be taken to adopt maximum possible number of dwellings in a plot.

Page 38: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 36

The water requirements for different types of buildings should be estimated as given in Annexure 13 Estimation of solid waste generation The garbage quantity needs to be estimated by adopting 0.5 kg/head for residential areas and 0.3 kg/head for commercial areas. Other solid wastes anticipated are STP sludge, waste oils, batteries, bio medical wastes. Construction Phase: The following should be considered during the construction stage:

Road construction Storm water drainage construction Other infrastructure Material requirement and lead distances Cut and fill quantities (excavation) Disposal of excess cut material and or source of fill materials including lead distances. Walkable streets Street network Access to surrounding vicinity Heat island reduction Water recycling Composting of garbage and use of manure Use of solar lighting and street lighting Use of solar heating

Page 39: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 37

CHAPTER 5

Guidelines for Sector Specific Projects

5.0 Guidelines for stipulating sector specific conditions in the CTE order

Mandatory EMP requirements Provision of rain water harvesting structure/ground water recharge pits Storm water

Management Storm water drains along the internal roads should be provided and the same should be clearly marked in the project lay out plan Should submit water availability certificate / letter from the concerned authority, if the source of water is from the local authority NOC from Central Ground Water Authority, if the source of water is ground water and as per the applicable norms Provision of water meters to record the water consumption

Dual plumbing system for collection of grey and other effluent

Design details of the Sewerage Treatment System, if on site STP is proposed and norms as per the final disposal point shall comply the general standards for discharge of effluent notified under the provisions of E (P) Act, 1986 Provision of energy meter for STP, to assess the continuous operation of STP Standard Operation Practice (SOP) of STP shall be submitted as and when finalized Provision of stand by power for continuous operation of the STP

Reuse of treated waste water for flushing and or land application

Incase, the final disposal is through local area sewer net work, the permission letter from the concerned authority clearly stating the quantity, standards for receiving and compliance mechanism

Water Management

Provision for common toilets Garbage segregation area should be provided with in the site Garbage collections bins green and blue bins for biodegradable and non-biodegradable wastes respectively shall be provided

Solid Waste

Final disposal point and permission letter from the concerned, in case, if it is proposed to dispose in the off site secured landfill Provision of integral acoustic enclosure or treating the room acoustically as per the G.S.R 371 (E) dated 17th May 2002 as amended Provision of minimum stack as per the CPCB guidelines

DG Sets

To comply the requirement of certification and requirement of conformance labeling as per G.S.R 371 (E) dated 17th May 2002 as amended. Details shall be submitted to RPCB after installing the D.G set Use of solar energy for hot water or as submitted in the EMP Timer based lighting management in Common areas Solar lighting for street lights (1 in 3)

Energy

Roof should meet regulatory requirement as per Energy Conservation Building Code by using appropriate thermal insulation material

Use of glass should be optimal to reduce the electricity consumption and load on air conditioning in community buildings

Page 40: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 38

Adequate provision for parking Adequate provision for visitors parking

Parking Requirement

In case of provision of community halls, stadiums, theatres etc., where huge gathering is expected, adequate parking and strengthening road infrastructure To be developed as per approved plan Adequate area for parks & green area shall be reserved The entire area under roads, parks and open spaces should to be surrendered to local Authority after development No road shall be less than 40 ft. and all roads shall provide for standard street lighting and essential street furniture The area earmarked for the parking shall be used for parking only. No other activity shall be permitted in this area The area earmarked as green area shall be used only for greenbelt and shall not be altered for any other purpose Traffic congestion near the entry and exit points on the roads adjoining the proposed project site must be avoided

Land and Site Lay Out

Road connectivity to the site shall be ensured by the developer Ozone Depleting Substances

Ozone Depleting Substances (Regulation & Control) Rules shall be followed while designing the air conditioning system of the project

Sediment control during construction Avoiding stockpiles of materials near natural drains All transport vehicles should have valid PUC

Construction Management

Provision of toilets for site workers connected to septic tank followed by soak pit The guidelines of RPCB shall be followed for hotels Hotels The standards notified by MoEF vide G.S.R 794 (E) dated 4th November 2009 shall be complied

Hospitals Biomedical wastes generating from the hospital if any, shall be disposed as per the Bio-medical Wastes (Management and Handling Rules), 1998 amended from time to time

Suggestive EMP requirements

Rain water harvesting pond/water body may be provided subject to site availability and suitability Roof top rain water collection system and reuse after pre treatment Roof top rain water may also be diverted to a bore well

Storm water Management

The drainage in the area may be planned in accordance with the natural slopes as per the contour plan without much disturbing the contour levels Install low-volume toilets and sensors Water Management Use low water consuming taps and sensors

Solid Waste Management

Onsite treatment of organic waste and to generate manure

CFL in common areas Energy Use of solar energy for room heating, cooking etc Cut and fill operation to be done during non-monsoon season Land and Site Lay Out

Development Water sprinkling on the roads to control the road dust

Page 41: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 39

CHAPTER 6

Environmental Management Plan 6.0 General

The objective of Environmental Management Plan is to: • Ensure the identified mitigation measures are implemented • Establish systems and procedures for this purpose • Monitor the effectiveness of the mitigation measures and • Take necessary action when unforeseen impacts occur 6.1 Components of EMP The EMP should contain: • Summary of potential impacts and proposed mitigation measures • An independent expert should certify the installation of the Sewage Treatment Plant

(STP) and a report in this regard should be submitted to RPCB before the project is commissioned for operation

• Water conservation measures proposed in the project • Provision of adequate parking facilities • Usage of solar energy in the project development • Energy efficient practices proposed in the project • Usage of alternative building materials such as fly ash bricks, PPC etc., • Allocation of budgetary resources • Details of environment cell

Page 42: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 40

ANNEXURES

Page 43: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 41

Annexure 1

FORM 1 (EIA Notification dated 14th September 2006 as amended 1st December 2009) (I) Basic Information S. No Item Details 1. Name of the project/s 2. S. No in the schedule 3. Proposed capacity/area/length/tonnage to be

handled/command area/lease area/number of wells to be drilled

4. New/expansion/modernization 5. Existing capacity/area etc 6. Category of project i.e. ‘A’ or ‘B’ 7. Does it attract the general condition? If yes, please

specify

8. Does it attract the specific condition? If yes, please specify

Location Plot/survey/khasra No Village Tehsil District

9.

State 10. Nearest railway station/airport along with distance

in kms

11. Nearest town, city, district head quarters along with distance in kms

12. Village Panchayats, Zilla Parishad, Municipal Corporation, Local body (complete postal addresses with telephone no.s to be given)

13. Name of the applicant 14. Registered address

Address for correspondence: Name Designation (Owner/partner/CEO) Address Pin code E-mail Telephone No.

15.

Fax No. 16. Details of alternative sites examined, if any. Location

of these sites should be shown on a topo sheet Village-District-State 1. 2. 3.

17. Interlinked projects 18. Whether separate application of interlinked project

has been submitted?

Page 44: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 42

19. If yes, date of submission 20. If no, reason 21. Whether the proposal involves approval/clearance

under: if yes, details of the same and their status to be given

a. The Forest (Conservation) Act, 1980? b. The Wildlife (Protection) Act, 1972? c. The CRZ Notification, 1991?

22. Whether there is any Government order/policy relevant/relating to the site?

23. Forest land involved (hectares) 24. Whether there is any litigation pending against the

project and/or land in which the project is propose to be set up?

a. Name of the Court b. Case No. c. Orders/directions of the Court, if any and its

relevance with the proposed project

(II) Activity 1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan)

1.2 Clearance of existing land, vegetation and buildings?

1.3 Creation of new land uses? 1.4 Pre-construction investigations e.g.

bore houses, soil testing?

1.5 Construction works? 1.6 Demolition works? 1.7 Temporary sites used for construction

works or housing of construction workers?

1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations

1.9 Underground works including mining or tunneling?

1.10 Reclamation works?

Page 45: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 43

1.11 Dredging? 1.12 Offshore structures? 1.13 Production and manufacturing

processes?

1.14 Facilities for storage of goods or materials?

1.15 Facilities for treatment or disposal of solid waste or liquid effluents?

1.16 Facilities for long term housing of operational workers?

1.17 New road, rail or sea traffic during construction or operation?

1.18 New road, rail, air waterborne or other transport infrastructure including new or altered routes and stations, ports, airports etc?

1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements?

1.20 New or diverted transmission lines or pipelines?

1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers?

1.22 Stream crossings? 1.23 Abstraction or transfers of water form

ground or surface waters?

1.24 Changes in water bodies or the land surface affecting drainage or run-off?

1.25 Transport of personnel or materials for construction, operation or decommissioning?

1.26 Long-term dismantling or decommissioning or restoration works?

1.27 Ongoing activity during decommissioning which could have an impact on the environment?

1.28 Influx of people to an area in either temporarily or permanently?

1.29 Introduction of alien species? 1.30 Loss of native species or genetic

diversity?

1.31 Any other actions?

Page 46: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 44

2. Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

2.1 Land especially undeveloped or agricultural land (ha)

2.2 Water (expected source & competing users) unit: KLD

2.3 Minerals (MT) 2.4 Construction material – stone,

aggregates, sand / soil (expected source – MT)

2.5 Forests and timber (source – MT) 2.6 Energy including electricity and fuels

(source, competing users) Unit: fuel (MT), energy (MW)

2.7 Any other natural resources (use appropriate standard units)

3. Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health. S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies)

3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases)

3.3 Affect the welfare of people e.g. by changing living conditions?

3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc.,

3.5 Any other causes

Page 47: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 45

4. Production of solid wastes during construction or operation or decommissioning (MT/month) S.No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

4.1 Spoil, overburden or mine wastes 4.2 Municipal waste (domestic and or

commercial wastes)

4.3 Hazardous wastes (as per Hazardous Waste Management Rules)

4.4 Other industrial process wastes 4.5 Surplus product 4.6 Sewage sludge or other sludge from

effluent treatment

4.7 Construction or demolition wastes 4.8 Redundant machinery or equipment 4.9 Contaminated soils or other materials 4.10 Agricultural wastes 4.11 Other solid wastes 5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr) S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

5.1 Emissions from combustion of fossil fuels from stationary or mobile sources

5.2 Emissions from production processes 5.3 Emissions from materials handling

including storage or transport

5.4 Emissions from construction activities including plant and equipment

5.5 Dust or odours from handling of materials including construction materials, sewage and waste

5.6 Emissions from incineration of waste 5.7 Emissions from burning of waste in

open air (e.g. slash materials, construction debris)

5.8 Emissions from any other sources

Page 48: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 46

6. Generation of Noise and Vibration, and Emissions of Light and Heat: S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

6.1 From operation of equipment e.g. engines, ventilation plant, crushers

6.2 From industrial or similar processes 6.3 From construction or demolition 6.4 From blasting or piling 6.5 From construction or operational traffic 6.6 From lighting or cooling systems 6.7 From any other sources 7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

7.1 From handling, storage, use or spillage of hazardous materials

7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge)

7.3 By deposition of pollutants emitted to air into the land or into water

7.4 From any other sources 7.5 Is there a risk of long term build up of

pollutants in the environment from these sources?

8. Risk of accidents during construction or operation of the Project, which could affect human health or the environment S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances

8.2 From any other causes 8.3 Could the project be affected by natural

disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)?

Page 49: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 47

9. Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality S. No. Information/Checklist confirmation Yes/No Details thereof (with Approximate

quantities /rates, wherever possible) with source of information data

9.1 Lead to development of supporting. lities, ancillary development or development stimulated by the project which could have impact on the environment e.g. • Supporting infrastructure (roads, power supply, waste or waste water treatment, etc.) • Housing development • Extractive industries • Supply industries • Other

9.2 Lead to after-use of the site, which could havean impact on the environment

9.3 Set a precedent for later developments 9.4 Have cumulative effects due to

proximity to other existing or planned projects with similar effects

(III) Environmental Sensitivity S. No. Areas Name/

Identity Aerial distance (within 15 km.) Proposed project location boundary

1 Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value

2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests

3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration

4 Inland, coastal, marine or underground waters

Page 50: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 48

5 State, National boundaries 6 Routes or facilities used by the public

for access to recreation or other tourist, pilgrim areas

7 Defence installations 8 Densely populated or built-up area 9 Areas occupied by sensitive man-made

land uses (hospitals, schools, places of worship, community facilities)

10 Areas containing important, high quality or scarce resources (ground water resources, surface resources, forestry, agriculture, fisheries, tourism, minerals)

11 Areas already subjected to pollution or environmental damage. (Those where existing legal environmental standards are exceeded)

12 Areas susceptible to natural hazard which could cause the project to present environmental problems (Earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions)

(IV). Proposed Terms of Reference for EIA studies ………………………………………………………………………………………………………………………………………………………………………………………………………………………… I hereby given undertaking that the data and information given in the application and enclosures are true to the best of my knowledge and belief and I am aware that if any part of the data and information submitted id found to be false or misleading at any stage, the project will be rejected and clearance give, if any to the project will be revoked at our risk and cost: Date: __________________ Place: _________________

Signature of the applicant With Name and Full Address

(Project proponent/Authorized signatory) Note: 1. The projects involving clearance under Coastal Regulation Zone Notification, 1991 shall submit with the application a CRZ map duly demarcated by one of the authorized agencies, showing the project activities, w.r.t CRZ (at the stage of TOR) and the recommendations of the State Coastal Zone Management Authority (at the stage of EC).

Page 51: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 49

Simultaneous action shall also be taken to obtain the requisite clearance under the provisions of the CRZ Notification, 1991 for the activities to be located in the CRZ 2. The projects to be located within 10km of the National Parks, Sanctuaries, Biosphere Reserves, Migratory corridors of the Wild animals, the project proponent shall submit the map duly authenticated by Chief Wildlife Warden showing these features vis-à-vis the project location and the recommendations of comments of the Chief Wildlife Warden thereon (at the stage of EC) 3. All correspondence with the Ministry of Environment & Forests including submission of application for TOR/Environmental Clearance, subsequent clarifications, as may be required from time to time, participation in the EAC meeting on behalf of the project proponent shall be made by the authorized signatory only. The authorized signatory should also submit a document in support of his claim of being an authorized signatory for the specific project.”

Page 52: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 50

Annexure 2

FORM-1 A (only for construction projects listed under item 8 of the Schedule of EIA

Notification) Check List of Environmental Impacts (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme) 1. Land Environment (Attach panoramic view of the project site and the vicinity) 1.1. Will the existing landuse get significantly altered from the project that is not consistent with the surroundings? (Proposed landuse must conform to the approved Master Plan /Development Plan of the area. Change of landuse if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. 1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc. 1.3. What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing landuse, and disturbance to the local ecology). 1.4. Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given). 1.5. Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site) 1.6. What are the quantities of earthwork involved in the construction activity-cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site etc.) 1.7. Give details regarding water supply, waste handling etc during the construction period 1.8. Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity) 1.9. Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

Page 53: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 51

2. Water Environment 2.1. Give the total quantity of water requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement. 2.2. What is the capacity (dependable flow or yield) of the proposed source of water? 2.3. What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality) 2.4. How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage) 2.5. Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption) 2.6. What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity) 2.7. Give details of the water requirements met from water harvesting? Furnish details of the facilities created. 2.8. What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate the problems of flooding or water logging in any way? 2.9. What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any) 2.10. What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts) 2.11. How is the storm water from within the site managed?(State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels) 2.12. Will the deployment of construction labourers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation) 2.13. What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal) 2.14. Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use.

Page 54: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 52

3. Vegetation 3.1. Is there any threat of the project to the biodiversity? (Give a description of the local ecosystem with it’s unique features, if any) 3.2. Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project) 3.3. What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale) 4. Fauna 4.1. Is there likely to be any displacement of fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details. 4.2. Any direct or indirect impacts on the avifauna of the area? Provide details. 4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna 5. Air Environment 5.1. Will the project increase atmospheric concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions) 5.2. What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters. 5.3. Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site. 5.4. Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category. 5.5. Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above. 5.6. What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details. 6. Aesthetics 6.1. Will the proposed constructions in any way result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

Page 55: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 53

6.2. Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account? 6.3. Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out. 6.4. Are there any anthropological or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered. 7. Socio-Economic Aspects 7.1. Will the proposal result in any changes to the demographic structure of local population? Provide the details. 7.2. Give details of the existing social infrastructure around the proposed project 7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed? 8. Building Materials 8.1. May involve the use of building materials with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency) 8.2. Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts? 8.3. Are recycled materials used in roads and structures? State the extent of savings achieved? 8.4. Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project. 9. Energy Conservation 9.1. Give details of the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption? 9.2. What type of, and capacity of, power back-up to you plan to provide? 9.3. What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation? 9.4. What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project.

Page 56: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 54

9.5. Does the layout of streets & buildings maximise the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details. 9.6. Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected? 9.7. Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air-conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications. 9.8. What are the likely effects of the building activity in altering the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects? 9.9. What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components. 9.10. What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans. 9.11. If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics. 9.12. What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration. 9.13. To what extent the non-conventional energy technologies are utilised in the overall energy consumption? Provide details of the renewable energy technologies used. 10. Environment Management Plan The Environment Management Plan would consist of all mitigation measures for each item wise activity to be undertaken during the construction, operation and the entire life cycle to minimize adverse environmental impacts as a result of the activities of the project. It would also delineate the environmental monitoring plan for compliance of various environmental regulations. It will state the steps to be taken in case of emergency such as accidents at the site including fire.

Page 57: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 55

Annexure 3

FORM I APPLICATION FOR CONSENT TO ESTABLISH

Application for consent to establish industry, operation or process any treatment and

disposal system under Section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974

(TO BE SUBMITTED IN TRIPLICATE)

(See Rule 29)

From: …………………………………………….. Dated:………………………………… …………………………………………….. To: ……………………………………………. ……………………………………………. Sir, I/we hereby apply for consent under section 25/26 of the Water (Prevention and control of pollution) Act, 1974 (No. 6 of 1974) for establishing or taking any steps for establishment of industry/operation/process or any other treatment/disposal system on land/premises owned by……………………………………………………………………………………………….. …………………………………………………………………………………………………………… The relevant details are as below: Part-I, General a. Name of the industry ……………………………………………… b. Address ………………………………………………

……………………………………………… c. Location (also enclose copy of land allotment ……………………………………………… /land conversion order and site map) d. Category of industry (Red/Orange/Others) ……………………………………………… e. Scale of industry (Large/Medium/Small) ……………………………………………… f. Whether the unit would generate hazardous waste (s) …………………………………….. as defined in the Hazardous Waste (Management and Handling) Rules, 1989. If so, the Category No …………………………………….. Part-II, Surrounding Details a. Area of the land proposed to be acquired (in square meter) ……………………………. b. Which of the following features exist within 25kms of the site ……………………………. i. Human settlement (specify population) …………………………….

Page 58: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 56

ii. Forest/sanctuary/national park/Hill resort/ ……………………………. National monument iii. Nallah/Stream/River/Pond/Dam/ …………………………….

any other water body iv. Industries, specify ……………………………..

Part-III, Process Details a. Manufacturing process with flow diagram ……………………………………….. b. Details of raw materials, products, by products ……………………………………….. and their storage capacity S.No Particulars Name Nature Quantity

(Unit/Day) i. Raw materials ii. Products iii. By products iv. Hazardous chemicals c. Energy consumption d. Details of fuel

S.No

1

Plant/Auxillary machines where fuel is used

2

Name and Quantity (TPD) Coal, Diesel, other (specify)

3 i. ii. iii. iv. v.

Part-IV, Water Pollution (Process-wise) a. Water consumption per day …………………………………… i. Boiler/Cooling/Industrial spray/Mining …………………………………… ii. Domestic …………………………………… iii. Industrial Process …………………………………… b. Total waste water generation per day …………………………………… c. Total waste water discharge per day …………………………………… d. Water balance …………………………………… e. Indicate wastewater and sludge characteristics, before …………………………………… And after treatment – (physical/chemical) f. Type of treatment proposed to be adopted …………………………………… (enclose details, design and schematic diagram) g. How do you propose to discharge the waste water …………………………………… (specify mode of disposal) h. What method do you propose to adopt for treatment …………………………………… Handling & disposal of sludge

Page 59: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 57

Part-V, Details of Air Pollution

Stack details S. No Stack attached to plant Temp

(0C) Dia (m)

Ht (m)

Volume (NM3/hr)

Pollution concentration SPM/others (Mg/NM3)

i. ii. iii. iv. v.

Note: Enclose lay out plan indicating location of each stack Part-VI, Sludge/Solid Wastes/Hazardous Wastes (Process-wise) and their proposed treatment a. Total quantity of wastes (kg/day) …………………………………………………. b. Nature of wastes …………………………………………………. c. Method proposed for treatment & disposal …………………………………………………. Part-VII, Other type of Pollution a. Is your industry likely to cause noise pollution? …………………………………………. If so, what measures are proposed to be taken? b. Is your industry likely to cause any other pollution?…………………………………………. If so, what measure are proposed to be taken? Part-VIII, Management of Pollution Control a. Give details of the organizational setup proposed for …………………………………………. Pollution control & monitoring Part-IX, Cost of Pollution Control Measures a. Total capital expenditure proposed for pollution control ………………………………… b. Annual recurring expenditure ………………………………… c. Has any financial outlay been proposed in the project? ………………………………… Report for pollution control measures? If so, mention the cost 1. I/We declare that the information furnished above is correct to the best of/my/our knowledge 2. I/We undertake to furnish any other information within one month of its being called by the State Board I/We enclose herewith Bank Draft No…………………………..Dated………………………for Rs………………..(Rs. in words………………………………………………………………… in favor of the Member Secretary, Rajasthan Pollution Control Board, Payable under section 25/26 of the Act.

Page 60: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 58

(In support of amount paid as fee, document on capital investment on the industry must be enclosed)

Yours faithfully,

Signature…………………………….

Name………………………………..

Designation…………………………

Applicant Note: i. In case information required to be furnished is lengthy, separate sheet can be used & attached ii. Consent fee: Each consent application (under Air Act, 1981 or Water Act, 1974) must be accompanied by the fees as given in schedule below. An application not accompanied with the prescribed fee shall not be entertained by the Board iii. Consent fees shall be paid through Bank Draft payable in favor of the Member Secretary, Rajasthan State Pollution Control Board

Page 61: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 59

Annexure 4

FORM I APPLICATION FOR CONSENT TO ESTABLISH

Application for consent to establish industrial plant under Section 21

of the Air (Prevention & Control of Pollution) Act, 1981

(TO BE SUBMITTED IN TRIPLICATE)

(See Rule 4) From: …………………………………………….. Dated:………………………………… …………………………………………….. To: ……………………………………………. ……………………………………………. Sir, I/we hereby apply for consent under section 21 of the Air (Prevention and control of pollution) Act, 1981 for establishing the industrial plant owned by…………………………………………………………………………………………………………………………………………………………………………………………………………………… The relevant details are as follows: Part-I, General c. Name of the industry ……………………………………………… d. Address ………………………………………………

……………………………………………… c. Location (also enclose copy of land allotment ……………………………………………… /land conversion order and site map) d. Category of industry (Red/Orange/Others) ……………………………………………… e. Scale of industry (Large/Medium/Small) ……………………………………………… Part-II, Surrounding Details a. Area of the land proposed to be acquired (in square meter) ……………………………. b. Which of the following features exist within 25kms of the site ……………………………. i. Human settlement (specify population) ……………………………. ii. Forest/sanctuary/national park/Hill resort/ ……………………………. National monument iii. Nallah/Stream/River/Pond/Dam/ …………………………….

any other water body iv. Industries, specify ……………………………..

Page 62: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 60

Part-III, Process Details a. Manufacturing process with flow diagram …..………………………………. b. Details of raw materials, products, by products …………………………………… and their storage capacity S.No Particulars Name Nature Quantity

(Unit/Day) i. Raw materials ii. Products iii. By products iv. Hazardous chemicals c. Energy consumption d. Details of fuel

S.No

1

Plant/Auxillary machines where fuel is used

2

Name and Quantity (TPD) Coal, Diesel, other (specify)

3 i. ii. iii. iv. v.

Part-IV, Water Pollution (Process-wise) a. Water consumption per day …………………………………… i. Boiler/Cooling/Industrial spray/Mining …………………………………… ii. Domestic …………………………………… iii. Industrial Process …………………………………… b. Total waste water generation per day …………………………………… c. Total waste water discharge per day …………………………………… d. Water balance …………………………………… e. Indicate waste water and sludge characteristics, before …………………………………… And after treatment – (physical/chemical) f. Type of treatment proposed to be adopted …………………………………… (enclose details, design and schematic diagram) g. How do you propose to discharge the wastewater …………………………………… (specify mode of disposal) h. What method do you propose to adopt for treatment …………………………………… Handling & disposal of sludge

Page 63: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 61

Part-V, Details of Air Pollution

Stack details S. No Stack attached to plant Temp

(0C) Dia (m)

Ht (m)

Volume (NM3/hr)

Pollution concentration SPM/others (Mg/NM3)

i. ii. iii. iv. v.

Note: Enclose lay out plan indicating location of each stack Part-VI, Sludge/Solid Wastes/Hazardous Wastes (Process-wise) and their proposed treatment a. Total quantity of wastes (kg/day) …………………………………………………. b. Nature of wastes …………………………………………………. c. Method proposed for treatment & disposal…………………………………………………. Part-VII, Other type of Pollution a. Is your industry likely to cause noise pollution? …………………………………………. If so, what measures are proposed to be taken? b. Is your industry likely to cause any other pollution?…………………………………………. If so, what measure are proposed to be taken? Part-VIII, Management of Pollution Control a. Give details of the organizational setup proposed for…………………………………………. Pollution control & monitoring Part-IX, Cost of Pollution Control Measures a. Total capital expenditure proposed for pollution control ………………………………… b. Annual recurring expenditure ………………………………… c. Has any financial outlay been proposed in the project? ………………………………… Report for pollution control measures? If so, mention the cost 1. I/We declare that the information furnished above is correct to the best of/my/our knowledge 2. I/We undertake to furnish any other information within one month of its being called by the State Board

Page 64: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 62

I/We enclose herewith Bank Draft No…………………………..Dated………………………for Rs………………..(Rs. in words……………………………………………………………………… in favor of the Member Secretary, Rajasthan Pollution Control Board, Payable under section 25/26 of the Act. (In support of amount paid as fee, document on capital investment on the industry must be enclosed)

Yours faithfully,

Signature…………………………….

Name………………………………..

Designation…………………………

Applicant Note: i. In case information required to be furnished is lengthy, separate sheet can be used & attached ii. Consent fee: Each consent application (under Air Act, 1981 or Water Act, 1974) must be accompanied by the fees as given in schedule below. An application not accompanied with the prescribed fee shall not be entertained by the Board iii. Consent fees shall be paid through Bank Draft payable in favor of the Member Secretary, Rajasthan State Pollution Control Board

Page 65: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 63

Annexure 5

Consent Fee Under the Provisions of Water Act SCHEDULE IV (See rule 29) Part I Fee for Industries other than Mining Units

S. No

Capital Investment of the Industry

One Time Consent Fee to Establish (in Rs)

Annual Consent Fee to Operate (in Rs.)

(in Rs.) Red Orange Other Red Orange Other 1 Upto 5 Lacs 3,000 2,000 1,000 1,400 1,200 1,000

2 More than 5 Lacs upto 10 Lacs 4,500 3,000 1,500 2,100 4,800 1,500

3 More than 10 Lacs upto 25 Lacs 6,000 4,000 2,000 2,800 2,400 2,000

4 More than 25 Lacs upto 50 Lacs 9,000 6,000 3,000 4,000 3,500 3,000

5 More than 50 Lacs upto 1 Crore 15,000 10,000 5,000 4,800 4,200 3,600

6 More than 1 Crore upto 5 Crore 18,000 12,000 6,000 6,400 5,600 4,800

7 More than 5 Crore upto 10 Crore 24,000 16,000 8,000 8,000 7,000 6,000

8 More than 10 Crore upto 25 Crore 30,000 20,000 10,000 9,600 8,400 7,200

9 More than 25 Crore upto 50 Crore 37,500 25,000 12,500 12,000 10,500 9,000

10 More than 50 Crore upto 100 Crore 45,000 30,000 15,000 22,000 19,000 15,000

11 More than 100 Crore upto 250 Crore 1,05,000 70,000 35,000 31,000 26,000 21,000

12 More than 250 Crore upto 500 Crore 1,27,500 85,000 42,500 44,000 38,000 30,000

13 More than 500 Crore upto 750 Crore 1,50,000 1,00,000 50,000 53,000 45,000 36,000

14 More than 750 Crore upto 100 Crore 1,87,500 1,25,000 62,500 57,000 49,000 39,000

15 Above 1000 Crore 2,25,000 1,50,000 1,50,000 75,000 53,000 42,000 Note: 1. The categorization of the industries / mining units into Red, Orange and Other categories shall be as specified by the State Board. 2. All industries and mining units requiring environmental clearance under the Environmental (Protection) Act, 1986 shall pay an extra amount of Rs. 15,000/- as one time consent fee to establish in addition to that mentioned in Schedule IV. 3. Provided that where a person who is establishing or carrying on any industry, operation or process and is generating hazardous waste as defined under the Hazardous Wastes (Management & Handling) Rules, 1989; and requiring authorization thereunder; the application for consent shall be accompanied with a fee equal to one and half times of the amount of fee prescribed under Schedule IV. (Please refer Notification dated 25th May 2007 of Dept. of Environment, Govt. of Rajasthan)

Page 66: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 64

Annexure 6

Consent Fee Under the Provisions of Air Act SCHEDULE (See rule 5) Part I Fee for Industries other than Mining Units

S. No

Capital Investment of the Industry

One Time Consent Fee to Establish (in Rs)

Annual Consent Fee to Operate (in Rs.)

(in Rs.) Red Orange Other Red Orange Other 1 Upto 5 Lacs 3,000 2,000 1,000 1,400 1,200 1,000

2 More than 5 Lacs upto 10 Lacs 4,500 3,000 1,500 2,100 4,800 1,500

3 More than 10 Lacs upto 25 Lacs 6,000 4,000 2,000 2,800 2,400 2,000

4 More than 25 Lacs upto 50 Lacs 9,000 6,000 3,000 4,000 3,500 3,000

5 More than 50 Lacs upto 1 Crore 15,000 10,000 5,000 4,800 4,200 3,600

6 More than 1 Crore upto 5 Crore 18,000 12,000 6,000 6,400 5,600 4,800

7 More than 5 Crore upto 10 Crore 24,000 16,000 8,000 8,000 7,000 6,000

8 More than 10 Crore upto 25 Crore 30,000 20,000 10,000 9,600 8,400 7,200

9 More than 25 Crore upto 50 Crore 37,500 25,000 12,500 12,000 10,500 9,000

10 More than 50 Crore upto 100 Crore 45,000 30,000 15,000 22,000 19,000 15,000

11 More than 100 Crore upto 250 Crore 1,05,000 70,000 35,000 31,000 26,000 21,000

12 More than 250 Crore upto 500 Crore 1,27,500 85,000 42,500 44,000 38,000 30,000

13 More than 500 Crore upto 750 Crore 1,50,000 1,00,000 50,000 53,000 45,000 36,000

14 More than 750 Crore upto 100 Crore 1,87,500 1,25,000 62,500 57,000 49,000 39,000

15 Above 1000 Crore 2,25,000 1,50,000 1,50,000 75,000 53,000 42,000 Note: 1. The categorization of the industries / mining units into Red, Orange and Other categories shall be as specified by the State Board. 2. All industries and mining units requiring environmental clearance under the Environmental (Protection) Act, 1986 shall pay an extra amount of Rs. 15,000/- as one time consent fee to establish in addition to that mentioned in Schedule IV. 3. Provided that where a person who is establishing or carrying on any industry, operation or process and is generating hazardous waste as defined under the Hazardous Wastes (Management & Handling) Rules, 1989; and requiring authorization thereunder; the application for consent shall be accompanied with a fee equal to one and half times of the amount of fee prescribed under Schedule IV. (Please refer Notification dated 25th May 2007 of Dept. of Environment, Govt. of Rajasthan)

Page 67: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 65

Annexure 7

Areas as identified by CGWA as – safe areas, semi – critical areas, critical areas & over exploited areas

S.No District No of Blocks Safe Semi-Critical Critical Over-Exploited

1 2 3 4 5 6 7 8

Bikaner

5

1. Lunkaransar 2. Kolayat

- -

1. Dungargarh

9

Bundi

4

-

1. Kesorai Patan 2. Talera

1. Bikaner 2. Nokha 1. Hindoli 2. Nainwa

10

Chittorgarh

14

-

1. Bhainsrorgarh

-

1. Amod 2. Bari Sadri 3. Begun 4. Bhadesar 5. Bhopalsagar 6. Chhotisadri 7. Chittorgarh 8. Dungla 9. Gangrar 10. Kapasan 11. Nimbahera 12. Pratapgarh 13. Rashmi

11

Churu

6

1. Churu 2. Atangarh 3. Sardarshahar

-

1. Sujangarh

1. Rajgarh

12

Dausa

5

1. Bandikui 2. Dausa 3. Lalsot 4. Mahua 5. Sirai

13

Dholpur

4

1. Bari

1. Baseri

1. Dholpur 2. Rajakhera

14

Dungarpur

5

1. Aspur

1. Bichhiwara 2. Dungarpur

1. Sagwara 2. Simalwara

15

Ganganagar

7

1. Anupgarh 2. Ganganagar 3. Karanpur 4. Padampur 5. Raisingh nagar 6. Sadulshahar 7. Suratgarh

Page 68: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 66

16

Hanumangarh

3

1. Bhadra 2. Hanumangarh 3. Nohar

17

Jaipur

13

1. Dudu 2. Phagi

1. Amer 2. Bairath 3. Bassi 4. Chaksu 5. Govindgarh 6. Jamwa Ramgarh 7. Jhotwara 8. Kotputli 9. Sambher 10. Sanganer 11. Shahpura

18

Jaisalmer

3

1. Sam

1. Jaisalmer 2. Sankra

19

Jalore

7

1. Ahore 2. Bhinmal 3. Jalore 4. Jaswantpura 5. Raniwara 6. Sanchore 7. Sayla

20

Jhalawar

6

1. Bakani 2. Dag 3. Jhalra Patan 4. Khanpur

1. Manoha Thana 2. Pirawa

21

Jhunjhunu

8

1. Alsisar

1. Bhuhana 2. Chirawa 3. Jhunjhunu 4. Khetri 5. Nawalgarh 6. Surajgarh 7. Udaipurwati

22

Jodhpur

9

1. Bap

1. Phalodi

1. Luni 2. Shergarh

1. Balesar 2. Bhopalgarh 3. Bilara 4. Mandore 5. Osaian

23

Karauli

5

1. Nadauti

1. Sapotra

1. Hindaun 2. Karauli 3. Todabhim

24

Kota

5

1. Sultanpur

1. Itawa 2. Khairabad 3. Ladpura 4. Sangod

Page 69: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 67

25

Nagaur

11

1. Nagaur

1. Ladnu

1. Jayal 2. Makrana

1. Degana 2. Didwana 3. Kuchaman 4. Merla 5. Mundwa 6. Parbaisar 7. Riyan

26

Pali

10

1. Bali 2. Desuri 3. Pali 4. Raipur 5. Rohit

1. Jaitaran 2. Kharchi 3. Rani 4. Sojat 5. Sumerpur

27

Rajsamand

7

1. Railmagra 2. Rajsamand

1. Amet 2. Bhim 3. Deogarh 4. Khamnor 5. Kumbhalgarh

28

Sawaimadhopur

5

1. Bamanwas 2. Bonli 3. Khandar

1. Gangapur 2. Sawai Madhopur

29

Sikar

8

1. Fatehpur

1. Danta Ramgarh 2. Dhod 3. Khandella 4. Lachhmangarh 5. Neem Ka Thana 6. Piprali 7. Sri Madhopur

30

Sirohi

5

1. Abu Road 2. Pindwara 3. Sirohi

1. Reodar 2. Sheoganj

31

Tonk

6

1. Deoli 2. Malpura 3. Newai 4. Toda Rai Singh 5. Tonk

1. Untara

32

Udaipur

11

1. Kherwara 2. Kotra 3. Sarada

1. Badgaon 2. Bhinder 3. Dhariawad 4. Girwa 5. Gogunda 6. Jhadot 7. Mavli 8. Salumber

Total 237 32 14 50 140 (Source: CGWA No: 21-4/Guidelines/CGWA/2009-832 dated 14.10. 2009)

Page 70: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 68

Annexure 8

General Standards for Discharge of Effluents Standards

Inland surface water

Public sewers Land for irrigation

Marine coastal areas

S. No

Parameter

(a) (b) (c) (d) 1 Color & odour * ------- * * 2 Suspended solids

mg/l, Max 100 600 200 1. For process waste

water-100 2. For cooling water effluent 10% above total suspended matter of influent

3 Particle size of suspended solids

Shall pass 850 Micron IS sieve

-- -- 1. Floatable solids max. 3 mm 2. Settleable solids max. 850 microns

4 pH Value 5.5 to 9.0 5.5 to 9.0 5.5 to 9.0 5.5 to 9.0 5 Temperature Shall not exceed 50

C above the receiving water temperature

-- -- Shall not exceed 50 C above the receiving water temperature

6 Oil and grease mg/l Max.

10 20 10 20

7 Total residual chlorine mg/l Max.

1.0 -- -- 1.0

8 Ammonical Nitrogen (as N), mg/l Max.

50 50 -- 50

9 Total Kjeldahl nitrogen (as NH3), mg/l Max.

100 -- -- 100

10 Free ammonia (as NH3), mg/l Max.

5.0 -- -- 5.0

11 Bio-chemical oxygen demand (3 days at 270 C), mg/l max.

30 350 100 100

12 Chemical oxygen demand, mg/l max.

250 -- -- 250

13 Arsenic (as As), mg/l max.

0.2 0.2 0.2 0.2

14 Mercury (as Hg), mg/l max.

0.01 0.01 -- 0.01

15 Lead (as Pb), mg/l max.

0.1 1.0 -- 2.0

16 Cadmium (as Cd), mg/l max.

2.0 1.0 -- 2.0

17 Hexavalent chromium (as Cr +6), mg/l max.

0.1 2.0 -- 1.0

Page 71: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 69

18 Total chromium (as Cr), mg/l max.

2.0 2.0 -- 2.0

19 Copper (as Cu), mg/l max.

3.0 3.0 -- 3.0

20 Zinc (as Zn), mg/l max.

5.0 15 -- 15

21 Selenium (as Se), mg/l max.

0.05 0.05 -- 0.05

22 Nickel (as Ni), mg/l max.

3.0 3.0 -- 5.0

23 Cyanide (as CN), mg/l max.

0.2 2.0 0.2 0.2

24 Fluoride (as F), mg/l max.

2.0 15 -- 15

25 Dissolved phosphates (as P), mg/l max.

5.0 -- -- --

26 Sulphide (as S), mg/l max.

2.0 -- -- 5.0

27 Phenolic compounds (as C6H5OH), mg/l max.

1.0 5.0 -- 5.0

28 Radio active materials: a. Alpha emitter

micro curie/ml 10-7 10-7 10-8 10-7

b. Beta emitter micro curie/ml

10-6 10-6 10-7 10-6

29 Bio-assay test 90% survival of fish after 96 hours in 100% effluent

90% survival of fish after 96 hours in 100% effluent

90% survival of fish after 96 hours in 100% effluent

90% survival of fish after 96 hours in 100% effluent

30 Manganese (as Mn), mg/l

2 2 -- 2

31 Iron (as Fe), mg/l 3 3 -- 3 32 Vanadium (as V),

mg/l 0.2 0.2 -- 0.2

33 Nitrate nitrogen, mg/l

10 -- -- 20

* All efforts should be made to remove colour and unpleasant odour as far as practicable These standards shall be applicable for industries, operations or processes other than those industries, operations or process for which standards have been specified of the Environment Protection Rules, 1989 Source: G.S.R 422 (E) dated 19.05.1993 and G.S.R 801 (E) dated 31.12.1993 issued under the provisions of E (P) Act 1986

Page 72: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 70

Annexure 9

National Ambient Air Quality Standards (NAAQS)

Concentration in Ambient Air S. No

Pollutant Time Weighted Average

Industrial, Residential, Rural and other areas

Ecologically sensitive area (notified by

central government)

Methods of measurement

(1) (2) (3) (4) (5) (6) 1 Sulphur dioxide

(SO2), μg/m3 Annual* 24 hours**

50 80

20 80

-Improved West & Gaeke -Ultraviolet fluorescence

2 Nitrogen Dioxide (NO2), μg/m3

Annual* 24 hours**

40 80

30 80

-Modified Jacob & Hochheiser (Na- arsenite) -Chemiluminescence

3 Particulate Matter (Size less than 10μm) or PM10μg/m3

Annual* 24 hours**

60 100

60 100

- Gravimetric - TOEM - Beta attenuation

4 Particulate Matter (Size less than 2.5μm) or PM2.5μg/m3

Annual* 24 hours**

40 60

40 60

- Gravimetric - TOEM - Beta attenuation

5 Ozone (O3) μg/m3

8 hours** 1 hour**

100 180

100 180

- UV photometric - Chemiluminescence - Chemical method

6 Lead (Pb) μg/m3 Annual* 24 hours**

0.50 1.0

0.50 1.0

-AAS/ICP method after sampling on EPM 2000 or equivalent filter paper -ED-XRF using Teflon filter

7 Carbon Monoxide (CO) mg/ m3

8 hours** 1 hour**

02 04

02 04

-Non Dispersive Infra Red (NDIR) spectroscopy

8 Ammonia (NH3) μg/m3

Annual* 24 hours**

100 400

100 400

- Chemiluminescence - Indophenol blue method

9 Benzene (C6H6) μg/m3

Annual* 05 05 -Gas chromatography based continuous analyzer -Adsorption and Desorption followed by GC analysis

10 Benzo(a)Pyrene (BaP) – particulate phase

Annual* 01 01 -Solvent extraction followed by HPLC/GC analysis

Page 73: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 71

only, ng/m3 11 Arsenic (As)

ng/m3 Annual* 06 06 -AAS/ICP method after

sampling on EPM 2000 or equivalent filter paper

12 Nickel (Ni) ng/m3

Annual* 20 20 -AAS/ICP method after sampling on EPM 2000 or equivalent filter paper

* Annual arithmetic mean of minimum 104 measurements in a year at a particular site taken twice a week 24 hourly at uniform intervals ** 24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be complied with 98% of the time in a year. 2% of the time, they may exceed the limits but not on two consecutive days of monitoring. Note: Whenever and wherever monitoring results on two consecutive days of monitoring exceed the limits specified above for the respective category, it shall be considered adequate reason to institute regular or continuous monitoring and further investigation (Source: National Ambient Air Quality Standards, CPCB Notification dated 18th November 2009)

Page 74: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 72

Annexure 10

Noise Ambient Air Quality Standards

Limits in db (A) Leq Area code Category of area Day time Night time

A Industrial area 75 70 B Commercial area 65 55 C Residential area 55 45 D Silence zone 50 40

Note: 1. Day time shall mean from 6.00 a.m. to 10.00 p.m. 2. Night time shall mean from 10.00 p.m. to 6.00 a.m. 3. Silence zone is an area comprising not less than 100 meters around hospitals, educational institutions, courts, religious places or any other area, which is declared as such by the competent authority. 4. Mixed categories of areas may be declared as one of the four above-mentioned categories by the competent authority. * dB(A) Leq denotes the time weighted average of the level of sound in decibels on scale A which is relatable to human hearing. A “decibel” is a unit in which noise is measured. “A”, in dB(A) Leq, denotes the frequency weighting in the measurement of noise and corresponds to frequency response characteristics of the human ear. Leq: It is an energy mean of the noise level over a specified period. (Source: Noise pollution (Regulation and control) Rules, 2000)

Page 75: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 73

Annexure 11

Noise Limits for Generator Sets run with Diesel 1. Noise limit for diesel generator sets (up to 1000 KVA) manufacture on or after the 1st July 2003 The maximum permissible sound pressure level for new diesel generator (DG) sets with rated capacity up to 1000 KVA, manufactured on or after the 1st July, 2003 shall be 75 dB (A) at 1 meter from the enclosure surface The diesel generator sets should be provided with integral acoustic enclosure at the manufacturing stage itself The implementation of noise limit for these diesel generator sets shall be regulated as given in paragraph 3 below 2. Noise limit for DG sets not covered by paragraph 1 Noise limits for diesel generator sets not covered by paragraph 1, shall be as follows: 2.1 Noise from DG set shall be controlled by providing an acoustic enclosure or by treating the room acoustically, at the users end 2.2 The acoustic enclosure or acoustic treatment of the room shall be designed for minimum 25 dB (A) insertion loss or for meeting the ambient noise standards, whichever is on the higher side (if the actual ambient noise is on the higher side, it may not be possible to check the performance of the acoustic enclosure/acoustic treatment. Under such circumstances the performance may be checked for noise reduction up to actual ambient noise level, preferably, in the nighttime). The measurement for insertion loss may be done at different points at 0.5m from the acoustic enclosure/room, and then averaged 2.3 The DG set shall be provided with proper exhaust muffler with insertion loss of minimum 25 dB (A) 2.4 these limits shall be regulated by the State Pollution Control Boards and the State Pollution Control Committees 2.5 Guidelines for the manufacturers/users of Diesel Generator sets shall be as under:

01 The manufacturer shall offer to the user a standard acoustic enclosure of 25 dB (A) insertion loss and also a suitable exhaust muffler with insertion loss of 25 dB(A) 02 The user shall make efforts to bring down the noise levels due to the DG set; outside hid premises, within the ambient noise requirements by proper siting and control measures 03 Installation of a DG set must be strictly in compliance with the recommendations of the DG set manufacturer

Page 76: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 74

04 A proper routine and preventive maintenance procedure for the DG set should be set and followed in consultation with the DG set manufacturer which would help prevent noise levels of the DG set from deteriorating with use

3. Limits of noise for DG Sets (Up to 1000 KVA) Manufactured on or after the 1st July 2003 3.1 Applicability

01. These Rules apply to DG sets up to 1000 KVA rated output, manufactures of imported in India, on or after 1st July 2003

02. These rules shall not apply to

a. DG sets manufactures or imported for the purpose of exports outside India; and

b. DG sets intended for the purpose of sample and not for sale in India (Please refer Notification No. G.S.R. 371 (E) dated 17th May, 2002 for details)

Page 77: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 75

Annexure 12

Effluent Standards for Hotel Industry notified under E (P) Act, 1986

S. No Industry Parameter Standards

1 2 3 4 Effluent standards

i. Hotel with at least 20 bedrooms Limiting concentration in mg/l except for pH Inland surface water On land for irrigation PH 5.5-9.0 5.5-9.0 BOD 3 days 270C 30 100 Total suspended solids 50 100 Oil & grease 10 10 Phosphates as P 1.0 - ii. Hotel with less than 20 bed rooms or a Banquet Hall with minimum floor area of 100m2 or a Restaurant with a minimum seating capacity of 36 PH 5.5-9.0 5.5-9.0 BOD 3 days 270C 100 100 Total suspended solids 100 100 Oil & Grease 10 10 Note: i. Hotels, banquet halls, restaurants etc., located in coastal area shall also comply with the provisions of the Coastal Regulation Zone, as applicable

39 Hotel industry

ii. If the effluent is discharged into a municipal sewer leading to a Sewage Treatment Plant, the hotel or restaurant or banquet hall, as the case may be, shall provide a proper Oil and Grease trap for effluent arising from its kitchen and laundry and shall have to comply with the ‘General standards for discharge of environmental pollutants Part A effluents’ notified under Schedule VI

(Source: G.S.R. 749 (E) under Environmental (Protection) Act dated 4th November 2009 - MoEF, GoI)

Page 78: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 76

Annexure 13

Estimation of Water Demand

S. No Type of Building Consumption liters/day

1. Factories with bath rooms 45 per head

2. Factories without bath rooms 30 per head

3. Hospital (including laundry):

4. a) Number of beds not exceeding 100 340 per head

5. b) Number of beds exceeding 100 450 per head

6. Nurses’ homes and medical quarters 135 per head

7. Hostels 135 per head

8. Hotel (up to 4 star) 180 per head

9. Hotel (5 star and above) 320 per head

10. Offices 45 per head

11. Restaurants 70 per seat

12. Cinemas, concert halls and theaters 15 per seat

13. Schools

14. a) Day schools 45 per head

15. b) Boarding schools 135 per head

In addition, water demand of visitors to these building is considered as 15 LPCD Source: Manual on norms and standards for environment clearance of large construction projects,MoEF

Page 79: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 77

Annexure 14

Code of Practices for Parking Requirements Area Requirements for Parking in Different Types of Cities

One Car Parking Space for Every

Sl. No Occupancy Population

less than 50,000

Population between 50,000 to 2,00,000

Population between

2,00,000 to 10,00,000

Population between

10,00,000 to 50,00,000

Population above

50,00,000

(1) (2) (3) (4) (5) (6) (7) a) Residential ---- ---- 2 tenements

having built-up area 101 to 200 m2

1 tenement of 100 m2 built up area

1 tenement of 75 m2 built up area

1 b) Lodging establishments, tourist homes and hotels, with lodging accommodation

12 guest rooms 8 guest rooms

4 guest rooms

3 guest rooms 2 guest rooms

2 Educational

70 m2 area or fraction thereof of the administrative office area and public service areas

50 m2 area or fraction thereof of the administrative office area and public service areas

35 m2 area or fraction thereof of the administrative office area and public service areas

20 beds (Private)

15 beds (Private)

10 beds (Private)

5 beds (Private)

2 beds (Private)

30 beds (Public)

25 beds (Public)

15 beds (Public)

10 beds (Public) 5 beds (Public) 3 Institutional (Medical)

a) Assembly Halls, Cinema Theatres

20 seats 80 seats 25 seats 15 seats 10 seats

b) Restaurants 60 seats 40 seats 20 seats 10 seats 5 seats c) Marriage Halls, Community Halls

600 m2 plot area

400 m2 plot area

200 m2 plot area

50 m2 plot area 25 m2 plot area 4

d) Stadia and Exhibition Center

240 Seats 160 seats 50 seats 30 seats 20 seats

a) Business Offices and Firms for Private Business

300 m2 area or fraction thereof

200 m2 area or fraction thereof

100 m2 area or fraction thereof

50 m2 area or fraction thereof

25 m2 area or fraction thereof 5 b) Public or semi-

public Offices 500 m2 area or fraction thereof

300 m2 area or fraction thereof

200 m2 area or fraction thereof

100 m2 area or fraction thereof

50 m2 area or fraction thereof

6 Mercantile (See Note 2)

300 m2 area or fraction thereof

200 m2 area or fraction thereof

100 m2 area or fraction thereof

50 m2 area or fraction thereof

25 m2 area or fraction thereof

7 Industrial 400 m2 area or

fraction thereof 300 m2 area or fraction thereof

200 m2 area or fraction thereof

100 m2 area or fraction thereof

50 m2 area or fraction thereof

Page 80: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 78

8 Storage ---- ---- 500 m2 area

or fraction thereof

250 m2 area or fraction thereof

125 m2 area or fraction thereof

Area requirements for different types of parking

Vehicle type Area required for parking (m) Clear height (m) Car 2.5x5 2.2 Scooter cycle 3x1.4 2.2 Trucks 3.75x10 4.75

Parking requirements for per Car space is as per the floor type

Basement 35 sq.m Stilts 30 sq.m Open 25 sq.m

(Source: National Building Code of India, 2005)

Page 81: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 79

Annexure 15

BIS Code of Practices

S. No BIS Code Description

Genera Structural Safety 1 IS: 456:2000 Code of Practice for Plain and Reinforced Concrete 2 IS: 800-1984 Code of Practice for General Construction in Steel

3 IS: 801-1975 Code of Practice for Use of Cold Formal Light Gauge Steel Structual Members in General Building Construction

Members in General Building Construction

4 IS: 875 (Part 2): 1987

Design loads (other than earthquake) for buildings and structures Part 2 Imposed Loads

5 IS: 875 (Part 3): 1987

Design loads (Other than earthquake) for buildings and structures Part 3 Wind Loads

6 IS: 875 (Part 4): 1987

Design loads (Other than earthquake) for buildings and structures Part 4 Snow Loads

7 IS: 875 (Part 5): 1987

Design loads (Other than earthquake) for buildings and structures Part 5 Special loads and load combination

8 IS: 883: 1966 Code of Practice for Design for Structural Timber in Building 9 IS: 1904: 1987 Code of Practice for Structural Safety of Buildings: Foundation

10 IS: 1905: 1987 Code of Practice for Structural Safety of Buildings: Masonry Walls IS: 2911 (Part 1) Section 1: 1979

Code of Practice for Design and Construction of Pile Foundation Section1

Part 1: Section 2 Based Cast-in-situ Piles Part 1: Section 3 Driven Precast Concrete Piles Part 1: Section 4 Based precast Concrete Piles Part 2: Timber Piles Part 3 Under Reamed Piles

11

Part 4 Load Test on Piles Cyclone/Wind Storm Protection

12 IS: 875 (3)-1987 Code of Practice for Design Loads (other than Earthquake) for Buildings and Structures, Part 3, Wind Loads

13 IS: IS Guidelines for improving the Cyclonic resistance of Low rise houses ad other building

Earthquake Protection 14 IS: 1893-2002 Criteria for Earthquake Resistant Design of Structures (Fifth Revision)

15 IS: 13920-1993 Ductile Detailing of Reinforced Concrete Structures subjected to Seismic Forces – Code of Practice

16 IS: 4326-1993 Earthquake Resistant Design and Construction of Buildings – Code of Practice (Second Revision)

17 IS: 13828-1993 Improving Earthquake Resistance of Low Strength Masonry Buildings – Guidelines

18 IS: 13827-1993 Improving Earthquake Resistance of Earthen Buildings – Guidelines 19 IS: 13935-1993 Repair and Seismic Strengthening of Buildings - Guidelines

Protection of Landslide Hazard

20 IS: 14458 (Part 1): 1998

Guidelines for retaining wall for hill area: Part I Selection of type of wall

Page 82: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 80

21 IS: 14458 (Part 2): 1997

Guidelines for retaining wall for hill area: Part 2 Design of retaining / Breast walls

22 IS: 14458 (Part 3): 1998

Guidelines for retaining wall for hill area: Part 3 Construction of dry stone walls

23 IS: 14496 (Part 2): 1998

Guidelines for preparation of landslide – Hazard zonation maps in mountainous terrains: Part 2 Macro-zonation.

Note: 1: Whenever an Indian Standard including those referred in the National Building Code or the National Building Code is referred, the latest revision of the same shall be followed except specific criteria, if any, mentioned above against that code. 2. Codal Provisions/Guidelines Pertaining to Protection for Cyclone or Landslide Hazard cam be omitted whenever not applicable

Page 83: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 81

Annexure 16

Ground Water Scenario of Rajasthan Hydrogeology

The State can be divided into three hydrogeological units namely, unconsolidated sediments, semi-consolidated sediments and consolidated rocks. The unconsolidated sediments are of two types- alluvial sediments and aeoline deposits. The Alluvial deposits are confined to Barmer, Jalore and Jodhpur district, consisting of sand, clay, gravel and cobbles. Valley fills have been reported from Jhunjhunu, Ajmer, Bhilwara and Udaipur district. The Aeoline sediments constitute one of the major aquifers east of major fault, east of Bikaner. It occupies an area of 1400 sq.k m. The aquifer thickness is 40 to 80 m. The yield of wells ranges from 100 to 150 m3/hr. Semi-consolidated formations include sandstones, limestones and Aur beds, covering Jaisalmer and Barmer districts. The dugwells in Jaisalmer limestones yield 13 to 68 m3/day. The yield of wells in Lathi sandstone varies from 50-150 m3/hr. The consolidated rocks includes gneiss, granites, schist, phyllites, marble and Vindhyan sandstones, limestone, quartzite and basaltic flows, mostly restricted to eastern part of the State. The yield prospect is limited unless the well is located near major lineaments or any other weak planes. The ground water quality is in general poor (brackish to saline) at deeper levels.

Ground Water Exploration/Sources Findings Dynamic Resources Annual Replenishable Ground water Resource

11.56 BCM

Net Annual Ground Water Availability 10.38 BCM Annual Ground Water Draft 12.99 BCM Stage of Ground Water Development 125 % Developmental Monitoring Over Exploited 140 Blocks Critical 50 Blocks Semi- critical 14 Blocks Exploratory Tube wells Constructed (as on 31.03.2009)

1383

No. of ground water observation wells 1373 Ground Water User Maps 32 districts Ground Water Quality Problems Contaminants Districts affected (in part) Salinity (EC > 3000 µS/cm at 25 ° C) Ajmer, Alwar, Barmer, Bharatpur, Bhilwara,

Bundi, Bikaner, Churu, Chittaurgarh, Dhaulpur, Dausa, Ganganagar, Hanumangarh, Jaipur, Jaisalmer, Jalor,Jhunjhunun, Karoli, Nagaur, Neemuch, Raja Samand, Sirohi, Sikar, Swai Madhopur, Tonk, Udaipur

Fluoride (>1.5 mg/l) Ajmer, Alwar, Banaswara, Barmer, Bharatpur, Bhilwara, Bikaner, Bundi, Chittaurgarh, Churu, Dausa, Dhaulpur, Dungarpur, Ganganagar, Hanumangarh, Jaipur, Jaisalmer,

Page 84: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 82

Jalor,Jhunjhunu, Jodhpur, Karauli, Kota, Nagaur, Pali, Rajasamand, Sirohi, Sikar, SawaiMadhopur, Tonk, Udaipur

Chloride (> 1000 mg/l) Barmer, Bharatpur, Bikaner, Churu, Ganganagar, Hanumangarh, Jaipur, Jaisalmer, Jalor, Jhunjhunun, Jodhpur Nagaur, Sirohi, Nagaur, Sikar, Tonk

Iron (>1.0 mg/l) Ajmer, Alwar, Banswara, Baran, Bharatpur, Bhilwara, Bikaner, Chittaurgarh, Churu, Dausa, Dhaulpur, Dungarpur, Ganganagar, Hanumangarh, Jaipur, Jaisalmer, Jhalawar, Jhunjhunu, Jodhpur, Karauli, Kota, Nagaur, Pali, Rajasamand, Sikar, Sawai Madhopur, Tonk, Udaipur

Nitrate (>45 mg/l) Ajmer, Alwar, Banaswara, Baran, Barmer, Bharatpur, Bhilwara, Bikaner, Chittaurgarh, Churu, Dausa, Dhaulpur, Dungarpur, Ganganagar, Hanumangarh, Jaipur, Jaisalmer, Jalor, Jhalawar, Jhunjhunu, Jodhpur, Karauli, Kota, Nagaur, Pali, Partapgarh, Rajasamand, Sirohi, Sikar, Swai Madhopur, Tonk, Udaipur

Inclusion of Roof Top Rain Water Harvesting (RTRWH) in building by laws

Roof Top RWH has been made mandatory in state owned buildings of plot size more than 300 sq.m with effect from 03.01.2006. For violation of building bye-laws, punitive measures, viz. disconnection of water supply, has also been made. The Govt. has made provision of compulsory installation of rainwater harvesting system in all newly and existing construction building and Govt. offices vide order dated 31.05.2000 and 12.12.2005. The State Government is also considering to modify Municipal Corporation Act making provisions of RWH.

Areas Notified for Regulation of ground water development

Jhotwara block of Jaipur district Pushkar Valley, Ajmer district Jalore block, Jalore district Raniwara block, Jalore district Budhana block, Jhunjunu district Chirawa block, Jhunjunu district Mundwa block, Nagaur district Behror block, Alwar district Bhinmal block, Jalore district Surajgarh block, Jhunjunu district Dhod block, Sikar district Shri Madhopur block, Sikar district

Source: http://cgwb.gov.in down loaded on 10th March 2010

Page 85: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 83

Annexure 17

Rain Water Harvesting Structures Rainwater available from rooftops of buildings, paved and unpaved areas goes waste. This water can be recharged to aquifer and can be utilized gainfully at the time of need. The rainwater harvesting system needs to be designed in a way that it does not occupy large space for collection and recharge system. A few techniques of roof top rainwater harvesting in urban areas are described below. Roof Top Rain Water Harvesting Through Recharge Pit • In alluvial areas where permeable rocks are exposed on the land surface or at very

shallow depth, roof top rainwater harvesting can be done through recharge pits. • The technique is suitable for buildings having a roof area of 100 sq.m. and are

constructed for recharging the shallow aquifers. • Recharge Pits may be of any shape and size and are generally constructed 1.0 to 2.0 m.

wide and 2.0 to 3.0 deep, which are back filled with boulders (5 - 20 cm), gravels (5 – 10 mm) and coarse sand (1.5 - 2.0 mm) in graded form. Boulders at the bottom, gravels in between and coarse sand at the top so that the silt content that will come with runoff will be deposited on the top of the coarse sand layer and can easily be removed. For smaller roof area, pit may be filled with broken bricks/ cobbles.

• A mesh should be provided at the roof so that leaves or any other solid waste / debris is prevented from entering the pit and a desilting /collection chamber may also be provided at the ground to arrest the flow of finer particles to the recharge pit.

• The top layer of sand should be cleaned periodically to maintain the recharge rate. • By-pass arrangement be provided before the collection chamber to reject the first

showers.

Page 86: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 84

Roof Top Rain Water Harvesting Through Recharge Trench • Recharge trenches are suitable for buildings having roof area of 200-300 sq. m. and

where a permeable stratum is available at shallow depths • Trench may be 0.5 to 1.0 m wide, 1.0 to 1.5 m deep and 10 to 20 m. long depending upon

availability of water to be recharge • These are back filled with boulders (5-20cm), gravel (5-10 mm) and coarse sand (1.5-2.0

mm) in graded form – boulders at the bottom, gravel in between and coarse sand at the top so that the silt content that will come with runoff will be coarse sand at the top of the sand layer and can easily be removed

• A mesh should be provided at the roof so that leaves or any other solid waste/debris is prevented from entering the trenches and a desilting/collection chamber may also be provided on ground to arrest the flow of finer particles to the trench

• By-pass arrangement be provided before the collection chamber to reject the first showers

• The top layer of sand should be cleaned periodically to maintain the recharge rate

Page 87: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 85

Roof Top Rain Water Harvesting Through Existing Tube wells • In areas where the shallow aquifers have dried up and existing tube wells are tapping

deeper aquifer, roof to rain water harvesting through existing tube well can be adopted to recharge the deeper aquifers

• PVC pipes of 10 cm dia are connected to roof drains to collect rainwater. The first roof runoff is let off through the bottom of drainpipe. After closing the bottom pipe, the rainwater of subsequent rain showers is taken through a T to an online PVC filter. The filter may be provided before water enters the tube wells. The filter is 1 –1.2 m. in length and is made up of PVC pipe. It’s diameter should vary depending on the area of roof, 15 cm if roof area is less than 150 sq m and 20 cm if the roof area is more. The filter is provided with a reducer of 6.25 cm on both the sides. Filter is divided into three chambers by PVC screens so that filter material is not mixed up. The first chamber is filled up with gravel (6-10mm), middle chamber with pebbles (12-20 mm) and last chamber with bigger pebbles (20-40 mm)

• If the roof area is more, a filter pit may be provided. Rainwater from roofs is taken to collection/desilting chambers located on ground. These collection chambers are interconnected as well as connected to the filter pit through pipes having a slop of 1:15. The filter pit may vary in shape and size depending upon available runoff and are back-filled with graded material, boulder at the bottom, gravel in the middle and sand at the top with varying thickness (0.30- 0.50m) and may be separated by screen. The pit is divided into two chambers, filter material in one chamber and other chamber is kept empty to accommodate excess filtered water and to monitor the quality of filtered water. A connecting pipe with recharge well is provided at the bottom of the pit for recharging of filtered water through well

Page 88: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 86

Roof Top Rain Water Harvesting Through Trench With Recharge Well • In areas where the surface soil is impervious and large quantities of roof water or surface

runoff is available within a very short period of heavy rainfall, the use of trench/ pits is made to store the water in a filter media and subsequently recharge to ground water through specially constructed recharge wells

• This techniques is ideally suited for area where permeable horizon is within 3m below ground level

• Recharge well of 100-300 diameter is constructed to a depth of at least 3.0 to 5.0 m below the water level. Based on the lithology of the area well assembly is designed with slotted pipe against the shallow and deeper aquifer

• A lateral trench of 1.5-to 3.0 m width and 10 to 30 m length, depending upon the availability of water is constructed with the recharge well in the centre

• The number of recharge wells in the trench can be decided on the basis of water availability and local vertical permeability of the rocks

• The trench is backfilled with boulders, gravels and coarse sand to act as a filter media for the recharge wells

• If the aquifer is available at greater depth say more than 20 m, a shallow shaft of 2.0 to 5.0 m diameter and 3.0 –5.0 meters deep may be constructed depending upon availability of runoff. Inside the shaft a recharge well of 100-300 mm dia is constructed for recharging the available water to the deeper aquifers. At the bottom of the shaft a filter media is provided to avoid choking of recharge well

(Source: Rainwater Harvesting Techniques to Augment Ground Water - 2003, Central Ground Water Board)

Page 89: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 87

Annexure 18

Water Quality Inlets Water quality inlets (WQIs), also commonly called oil/grit separators or oil/water separators, consist of a series of chambers that promote sedimentation of coarse materials and separation of free oil (as opposed to emulsified or dissolved oil) from storm water. Most WQIs also contain screens to help retain larger or floating debris, and many of the newer designs also include a coalescing unit that helps to promote oil/water separation. WQIs typically capture only the first portion of runoff for treatment and are generally used for pretreatment before discharging to other best management practices (BMPs). A typical WQI, as shown in following Figure, consists of a sedimentation chamber, an oil separation chamber, and a discharge chamber. The basic WQI design is often modified to improve performance.

Advantages and Disadvantages WQIs can effectively trap trash, debris, oil and grease, and other floatables that would otherwise be discharged to surface waters (Schueler, 1992). In addition, a properly esigned and maintained WQI can serve as an effective BMP for reducing hydrocarbon contamination in receiving water sediments. While WQIs are effective in removing heavy sediments and floating oil and grease, they have demonstrated limited ability to separate dissolved or emulsified oil from runoff. WQIs are also not very effective at removing pollutants such as nutrients or metals, except where the metals removal is directly related to sediment removal.

Page 90: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 88

Annexure 19

Availability of Rain Water Through Roof Top Rain Water Harvesting

Rainfall

(mm) 100 200 300 400 500 600 800 1000

Roof Top Area (Sq.m) Harvested Water from Roof Top (Cum) 20 1.6 3.2 4.8 6.4 8 9.6 12.8 16 30 2.4 4.8 7.2 9.6 12 14.4 19.2 24 40 3.2 6.4 9.6 12.8 16 19.2 25.6 32 50 4 8 12 16 20 24 32 40 60 4.8 9.6 14.4 19.2 24 28.8 38.4 48 70 5.6 11.2 16.8 22.4 28 33.6 44.8 56 80 6.4 12.8 19.2 25.6 32 38.4 51.2 64 90 7.2 14.4 21.6 28.8 36 43.2 57.6 72

100 8 16 24 32 40 48 64 80 150 12 24 36 48 60 72 96 120 200 16 32 48 64 80 96 128 160 250 20 40 60 80 100 120 160 200 300 24 48 72 96 120 144 192 240 400 32 64 96 128 160 192 256 320 500 40 80 120 160 200 240 320 400

1000 80 160 240 320 400 480 640 800 2000 160 320 480 640 800 960 1280 1600 3000 240 480 720 960 1200 1440 1920 2400

(Source: Rainwater Harvesting Techniques to Augment Ground Water - 2003, Central Ground Water Board)

Page 91: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 89

Annexure 20

Wind Towers Wind towers are generally used in hot and dry climates for cooling. Wind towers operate in many ways depending on the time of day wind availability. Wind towers work on the principle of changing air density in and around the tower. During daytime, hot ambient air comes into contact with the cool, top part of the tower and gets cooled. Cool, dense air sinks through the tower and into living species (through vents and openings). Increased wind velocity improves the performance of wind towers. During the night the reverse takes place. Cool air comes in contact with the warm inner surface of the tower. This air in turn gets warmed up, rises and is exhausted through openings. The pressure difference thus created pulls the cool night air through the doors and windows into the building. Due to small storage capacities, sensible cooling may stop after several hours of operation on hot summer days. In order to improve the efficiency of its operation, evaporating cooling is used in conjunction with sensible cooling. Wind towers can bring about a difference of 10-150C in arid climates. Wind towers can be combined with ground cooling to give better performance and have been used effectively in several buildings in the Middle East and West Asia. It may be noted that wind towers are used only for summer cooling. Proper care should be taken to close the vents and openings during the winter. (Source: Manual on norms and standards for environment clearance of large construction projects, MoEF)

Page 92: Area Development Projects Zero Draft

 

TOWNSHIPS & AREA DEVELOPMENT PROJECTS 90

Annexure 21

Checklist - Construction Phase 1. First Aid facility should be provided. Adequate drinking water and sanitary facilities

should be provided for construction workers. The safe disposal of wastewater and solid wastes generated during the construction phase should be ensured.

2. Topsoil excavated during construction activities should be stored for use in

horticulture/landscape development within the project site. 3. Disposal of debris /muck during construction phase should not create any adverse

effect on the neighboring communities and be disposed taking the necessary precautions for general safety and health aspects of people, only in approved sites with the approval of competent authority.

4. Soil and ground water samples should be tested to ascertain that there is no threat to

ground water quality by leaching of heavy metals and other toxic contaminants from the site

5. Any hazardous waste including biomedical waste should be disposed of as per

applicable Rules & norms with necessary approvals of the Pollution Control Board 6. The diesel generator sets to be used during construction phase should be low sulphur

diesel type and should conform to E (P) Rules prescribed for air and noise emission standards.

7. Vehicles hired for bringing construction material to the site should be in good condition

and should conform to applicable emission standards 8. Storm water control and its re-use as per CGWA and BIS standards for various

applications should be planned 9. Separation of grey and black water should be done by the use of dual plumbing line.

Treatment of grey water by decentralized treatment 10. Fixtures for showers, toilet flushing and drinking should be of low flow either by use of

aerators or pressure-reducing devices of sensor based control. 11. Optimal use of glass to reduce the electricity consumption and load on air-conditioning.

If necessary, use high quality double glass with special reflective coating in window should be planned

12. Roof should meet prescriptive requirement as per Energy Conservation Building Code

by using appropriate thermal insulation material to fulfill requirement. 13. Adequate measures to reduce air and noise pollution during construction keeping in

view of MoEF/CPCB norms 14. Rain water harvesting for roof run-off and surface run-off, as plan submitted should be

implemented