arborist associates ltd....o protect tree root systems from damage caused by runoff or spillage of...

1
A R B O R I S T A S S O C I A T E S L T D . 9 4 B A L L Y B A W N C O T T A G E S , E N N I S K E R R Y , C O . W I C K L O W T E L : 0 1 - 2 7 4 2 0 1 1 / 0 8 7 - 2 6 2 9 5 8 9 T I T L E : D A T E : S i t e : W o r k s S c h e d u l e S i t e M e e t i n g P r i o r t o a n y w o r k s c o m m e n c i n g . T r e e W o r k s F e l l i n g & P r u n i n g P r i o r t o a n y c o n s t r u c t i o n w o r k s c o m m e n c i n g . T r e e P r o t e c t i o n A f t e r t r e e r e m o v a l a n d p r u n i n g i s c o m p l e t e a n d p r i o r t o a n y c o n s t r u c t i o n w o r k s c o m m e n c i n g T h e e r e c t i o n a n d r e m o v a l o f t h e p r o t e c t i v e f e n c i n g i s t o b e s c h e d u l e d i n a c c o r d a n c e w i t h t h e p h a s i n g o f t h e c o n s t r u c t i o n w o r k s . S i t e M o n i t o r i n g O n g o i n g t h r o u g h o u t t h e c o n s t r u c t i o n w o r k s . R e m o v a l o f T r e e P r o t e c t i o n O n c e a l l t h e m a i n c o n s t r u c t i o n w o r k s a r e c o m p l e t e d a n d i n o r d e r t o i n c o r p o r a t e t h e a r e a i n t o t h e f i n i s h e d d e v e l o p m e n t . T r e e R e v i e w a n d C e r t i f i c a t i o n O n c e a l l w o r k s a r e c o m p l e t e . Tree Work Exclusion Zone Tree Protection Detail The following is a list of activities that are not allowed within the RPA or within the vicinity of the trees being retained. o Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials. o Protect root systems from ponding, eroding, or excessive wett ing caused during construction operations o Do not store construction materials, debris, or excavated material inside tree protection zones. When excavating, place excavated soil on opposite side of trench away from the tree. o Do not permit vehicles or foot traffic within tree protection zones; prevent soil compaction over root systems. o Do not allow fires under or adjacent to remaining trees or other plants. o Do not attach notice boards, cables or other services to any part of the tree. o Do not use neighbouring trees as anchor points. o Do not use high machinery such asTele porters, cranes or other equipment close to trees to avoid damage to the crown or any other parts. The tree protection fencing is to be erected enclosing the root protection areas around the trees being retained as shown on this drawing and appendix 1 In some areas, the site hoarding may be sufficient to act as the protective fencing if the tree and its root zone are positioned outside and no works are envisaged within the area outside the site hoarding. This will need to be discussed and agreed at the initial site meeting. Where tree protection fencing is needed, this will need to be 2.3m high and constructed in accordance with figure 2 of BS 5837 20 12 (see detail on drawing & appendix 1) using vertical and horizontal scaffold bars or similar well braced together with the verticals spaced out at a maximum of 3m centres. Onto this, weld mesh panels (harris fecne panels) are to be securely fixed with wire or scaffold clamps. Signs are to be attached to these fences warning people that this is a protective area and that the fencing must be maintained in good condition in accordance with the approved plans and drawings for this development. Once the protective fence line is erected, then the main construction works can commence on site.

Upload: others

Post on 26-Jan-2021

5 views

Category:

Documents


0 download

TRANSCRIPT

  • ARBORIST ASSOCIATES LTD.94 BALLYBAWN COTTAGES, ENNISKERRY, CO. WICKLOW

    TEL: 01-2742011 / 087-2629589

    TITLE :

    DATE:

    Site :

    Works Schedule

    Site Meeting Prior to any works commencing.

    Tree Works Felling &

    Pruning

    Prior to any construction works commencing.

    Tree Protection After tree removal and pruning is complete and prior to

    any construction works commencing The erection and

    removal of the protective fencing is to be scheduled in

    accordance with the phasing of the construction works.

    Site Monitoring Ongoing throughout the construction works.

    Removal of Tree P rotection Once all the main construction works are completed and

    in order to incorporate the area into the finished

    development.

    Tree Review and Certification Once all works are complete.

    Tree

    Work

    Exclusion Zone

    Tree Protection Detail

    The following is a list of activities that are not allowed within the RPA or within the vicinity of the trees being retained.

    o Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials.

    o Protect root systems from ponding, eroding, or excessive wetting caused during construction operations

    o Do not store construction materials, debris, or excavated material inside tree protection zones. When excavating, place excavated soil on opposite side of trench away from the tree.

    o Do not permit vehicles or foot traffic within tree protection zones; prevent soil

    compaction over root systems. o Do not allow fires under or adjacent to remaining trees or other plants.

    o Do not attach notice boards, cables or other services to any part of the tree.o Do not use neighbouring trees as anchor points.o Do not use high machinery such as Tele porters, cranes or other equipment

    close to trees to avoid damage to the crown or any other parts.

    The tree protection fencing is to be erected enclosing the root protection areas around the trees being retained as shown on this drawing and

    appendix 1 In some areas, the site hoarding may be sufficient to act as the protective fencing if the tree and its root zone are positioned outside and no works are envisaged within the area outside the site hoarding. This will need to be discussed and agreed at the initial site meeting.

    Where tree protection fencing is needed, this will need to be 2.3m high and constructed in accordance with figure 2 of BS 5837 2012(see detail on drawing & appendix 1) using vertical and horizontal scaffold bars or similar well braced together with the verticals spaced out at a maximum of 3m centres. Onto this, weld mesh panels (harris fecne panels) are to be securely fixed with wire or

    scaffold clamps.

    Signs are to be attached to these fences warning people that this is a protective area and that the fencing must be maintained in good condition in accordance with the approved plans and drawings for this development.

    Once the protective fence line is erected, then the main construction works can commence on site.