Construction UpdateDecember, 2011

Page 2: APS Construction Update Nov2011 [Read-Only]

Summary Completed New Construction

1. Atrisco Heritage Academy High School*(Phase I & II)2. Coronado Elementary School3. Desert Willow Family School4. G O’Keeffe Elementary School**5. Tierra Antigua Elementary School (Prototype 1)**6. Sunset View Elementary School (Prototype 2)**7. Tony Hillerman Middle School (Design/Build 1)**8. SR Marmon Elementary School **9. Helen Cordero Elementary School (K‐2)**10. Rudolfo Anaya Elementary School (Prototype 3)**11. Volcano Vista High School*12. Nex+Gen Academy High School13. E Academy High School14. John Baker Elementary School15. A. Montoya Elementary School16. Emerson Elementary School17. Kennedy Middle School18. Valley High School19. Bandelier Elementary School20. Alamosa Elementary School21. La Luz Elementary School22. Apache Elementary School23. Alvarado Elementary School24. Osuna Elementary School25. Eisenhower Middle School26. McCollum Elementary School27. Onate Elementary School

2

*Built partly with Legislative High Priority Project (HPP) awards

**Built partly with PSCOC awards

• Under Construction

1. Sandia High School2. Del Notre High School3. Truman Middle School Classrooms4. EG Ross Elementary School5. Atrisco Heritage Academy HS Final 

Phase6. Hoover Middle School7. APS Community Stadium (Bid)

Page 3: APS Construction Update Nov2011 [Read-Only]

SummarySince 2006, APS has undertaken a massive classroom (over 400) and educational space rebuild and remodel. These remodels add up to about 5 million sq.ft.A substantial portion of the above are kindergarten, fine arts, and music classrooms.In the same period APS has opened 11 new schools ( 3 HS, 2 Alternative,1 MS & 5 ES) that add up to about 4 million sq.ft.3 Elementary Schools were totally rebuiltAll new construction is being undertaken using sustainable materials and energy‐efficient principles.

3

Page 4: APS Construction Update Nov2011 [Read-Only]

New School Construction Schedule

4

Page 5: APS Construction Update Nov2011 [Read-Only]

2011 APS Construction Schedule

5

Grade Est. Date of 2008 2008 2008 2008 2009 2009 2009 2009 2010 2010 2010 2010 2011 2011 2011 2011 2012 2012 2012 2012 2013 2013 2013 2013Loc # Activity Address Levels Opening Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

576 Atrisco Heritage Academy HS10800 Dennis Chavez Blvd SWAlbuquerque, NM 87121

9-12

9th - Aug 20089-10th - Aug 20099-11th - Aug 2010 9-12th - Aug 2011

9th Grade 10th

Grade11thGrade

12thGrade

321 A Montoya Elementary School Kindergarten Wing Addition

24 Public School RoadTijeras, NM 87059

k-5 June 2011 School Opens

514 Del Norte High School Rebuild 5323 Montgomery NEAlbuquerque, NM 87109

9-12 Jan-12 School Opens

511 e Academy Alternative School 5300 Cutler NEAlbuquerque, NM 87110

9-12 Apr 2011 School Opens

219 E G Ross Elementary School Admin Expansion

6700 Palomas NE Albuquerque, NM 87109

k-5 Feb 2012 School Opens

217 John Baker Elementary School Classroom Addition

12015 B Tivoli NE Albuquerque, NM 87111

k-5 July 2011 School Opens

427 Kennedy Middle School Admin Addition and Renovation

721 Tomasita NE Albuquerque, NM 87123

6-8 July 2011 School Opens

516 Nex+Gen Academy High School 5323 Montgomery NEAlbuquerque, NM 87109

9-12 Aug 2010 School Opens

475 Truman Middle School Classroom Wing Addition

9400 Benavides Rd SWAlbuquerque, NM 87121

6-8 Dec 2011 School Opens

560 Valley High School Shop/Fine Arts Addition

1505 Candalaria NWAlbuquerque, NM 87107

9-12 Mar 2011 School Opens

Albuquerque Community Stadium 1601 Arroyo Vista Blvd NWAlbuquerque, NM 87120

Apr 2013 Open

*Timelines are only tentative. The exact date of opening will be contingent upon there being no unforeseen circumstances during the design and construction.Q = Quarter (3 months)SLA = Special Legislative Appropriation

New School Construction Schedule (as of Dec,2011)

Boundary Done

Complete

Complete

Complete

Complete

Complete

Complete

Page 6: APS Construction Update Nov2011 [Read-Only]

Current Projects

6

Page 7: APS Construction Update Nov2011 [Read-Only]

Atrisco Heritage Academy High School Address: 10800 Dennis Chavez Blvd SW

Square Footage: 463,000

Est. Date of Opening: Aug 2008 for 9th grade Aug 2009 for 10th grade Aug 2010 for 11th grade Aug 2012 for 12th grade

Budget: $132,000,000

Architect: Fanning Bard Tatum Architects/ Perkins & Will

General Contractor: Phase 1: Gerald Martin‐COMPLETE Phase 2: Bradbury‐Stamm‐COMPLETE Phase 3: McCarthy‐May 2012

2009 NSBA Exhibition of School Architecture Grand Prize Winner

7

This school was constructed to relieve primarily West Mesa High School and the future growth areas of Rio Grande High School.

Page 8: APS Construction Update Nov2011 [Read-Only]

Truman Middle School Address:  9400 Benavides SW

Square Footage: 88,269

Year Opened: 1975

Current Projects:

Classroom Addition

Drop off /Parking Improvements 

Drainage upgrades

Est. Date of Completion: Dec 2011

Budget: $7,268,941

Architect: Fanning Brad Tatum

General Contractor: TA Cole & Sons

2011 Strategy Projects:

Additional funds for Classroom Addition &Parent Drop‐off/Pick‐up

Drainage Upgrades

Budget: $4,026,329

Architect: Fanning Bard Tatum

General Contractor: TBD

8

Page 9: APS Construction Update Nov2011 [Read-Only]

9

Del Norte High School Address: 5323 Montgomery NE 

Square Footage: 280,744

Year Opened: 1964‐65

Current Project: Rebuild the school in 3 phases

Phase 1 Construct new classroom building (Phase 1a) Demolish a portion of 100 Building Construct new administration building (Phase 1b) Date of Completion:  Aug 2011 Architect: Dekker/ Perich, Greg T. Hicks O/E, & 

Allison Eng. O/E General Contractor: TBD

Phase 2 Construct new classroom building Demolish rest of 100 Building and 500 Building Remove portables Est. Date of Completion: Jan 2012

Phase 3 Construct Phase 3 classrooms Demolish 300, 400 and 500 buildings Finish student commons Est. Date of Completion: Aug 2014

Total Budget: $58,911,244

Page 10: APS Construction Update Nov2011 [Read-Only]

10

EG Ross Elementary School Address: 6700 Palomas NE Square Footage: 63,608 Year Opened: 1983 Current Projects: Administration Expansion  Loop Road Improvements  Electrical / Lighting Upgrade Site Health & Safety Projects 

Est. Date of Completion: Feb 2012 Budget: $1,237,354   Architect: Westwork General Contractor: CC Construction

Page 11: APS Construction Update Nov2011 [Read-Only]

11

Hoover Middle School Address: 12015 Tivoli NE 87111

Square Footage: 10,0122 

Year Opened: 1966 

Current Projects: Cafeteria Kitchen Renovation and 

Addition Gym and Locker room upgrades HVAC improvements

Est. Date of Completion: Jan 2012

Budget: $1,202,464

Architect/Eng: DWL

General Contractor: CC Construction

2011 Strategy Projects: Supplement for Cafeteria/Kitchen 

renovation and Gym locker upgrades Site improvements Budget: $2,391,855 

Page 12: APS Construction Update Nov2011 [Read-Only]

12

Albuquerque Public Schools Community Stadium

Address: 1601 Arroyo Vista Blvd NW

Current Projects:  Football Stadium

Track and Field

Softball court

Tennis court

Est. Date of Completion: Apr 2013

Budget:  $36,361,300

Architect: SMPC

General Contractor: TBD

Page 13: APS Construction Update Nov2011 [Read-Only]

Recently Completed Projects

Page 14: APS Construction Update Nov2011 [Read-Only]

14

A. Montoya Elementary School Address: 24 Public School Rd, Tijeras

Square Footage: 64,002

Year Opened: 1990

Current Project :

Kindergarten  and Computer Lab Addition

Electrical Upgrade

Date of Completion: June 2011

Budget: $2,809,999

Architect: Design Plus

2011 Strategy

Supplemental Funds for Kindergarten and Health and Safety Projects

Budget: $1,848,825

Page 15: APS Construction Update Nov2011 [Read-Only]

15

John Baker Elementary School

Address: 12015‐B Tivoli Ave NE

Square Footage: 44,601

Year Opened: 1970

Current Projects:

Classroom addition

Art room

Playground Improvements

Restroom Renovations

Date of Completion: July 2011

Budget: $3,468,620 

Architect: Greg T. Hicks O/E

General Contractor: TBD

2011 Strategy Projects:

Health & Safety

Supplemental to Classroom Addition

Budget: $7,020,251

Page 16: APS Construction Update Nov2011 [Read-Only]

e Academy Alternative School

Address: 5200 Cutler Ave NE  Square Footage: 44,369  sq. ft. Year Opened: 1915  Current Project Administration/Classroom Building 

LEED Date of Completion: April 2011 Budget: $8,262,423 Architect: Integrated Design & 

Architecture General Contractor: Longhorn 2011 Strategy Project: Supplemental Funding Budget: $6,475,344 Architect & General Contractor: 

TBD

16

Page 17: APS Construction Update Nov2011 [Read-Only]

17

Valley High School Address: 1505 Candelaria NW  Square Footage: 341,710  Year Opened: 1954‐55  Current Projects:

HVAC in Gym Shop/Fine Arts Addition & Police Facility 

Remodel Pool Locker Rooms

Date of Completion: Mar 2011 Budget:  $10,760,888 Architect/Eng: NCA, Allison Engineers General Contractor: Shumate 2011 Strategy Projects:

Renovate Building Construction of New Classroom & Soccer 

Field Relocate Tennis Courts and Police 

Station Budget: $ 8,151,554

Page 18: APS Construction Update Nov2011 [Read-Only]

Kennedy Middle School Address: 721 Tomasita NE 87123 Square Footage: 84,416 Year Opened: 1965 Current Projects:

HVAC Improvements

Admin Addition and Refurbish

Date of Completion:  July 2011 Budget:  $2,406,547 Architect/Eng:WH Pacific General Contractor: Michael S. Rich 2011 Strategy Projects:

Supplemental Admin addition

Upgrade science area

Music area renovation

Budget: $2,320,147 

18

Page 19: APS Construction Update Nov2011 [Read-Only]

19

Emerson Elementary School Address: 620 Georgia St SE  Square Footage: 58,500 Year Opened: 1952 Current Projects:  Kindergarten Addition Site Work ‐ LEED  Art Room  Refurbish Restrooms  Playground Improvements 

Date of Completion: Jan 2011 Budget: $2,938,667 Architect: AECOM   General Contractor: Vigil

Page 20: APS Construction Update Nov2011 [Read-Only]

20

Zuni Elementary School Address: 6300 Claremont NE 

Square Footage: 53,058

Year Opened: 1960

Current Projects: Cafeteria Kitchen Additions & 

Renovations  Site improvements Electrical upgrades

Date of Completion: Aug 2011

Budget: $1,613,624

Architect: Greg T. Hicks

General Contractor: Jim Sena Const. Co Inc.

Page 21: APS Construction Update Nov2011 [Read-Only]

21

Sandia High School Address: 7801 Candelaria NE 

Square Footage: 330,699

Year Opened: 1958

Current Projects: Main Bldg./ Music Area/ PAC Additions 

& Renovations  Addition & Remodel to Gymnasium 

Complex  Electrical Fund Restroom Renovations to Gym, Shops 

and Music ADA upgrades and Improvements –Gym 

Date of Completion: Sep 2010

Budget: $12,988,481

Architect: Mahlman Studio 

General Contractor: T.A. Cole & Sons

Page 22: APS Construction Update Nov2011 [Read-Only]

Alamosa Elementary School Address: 6500 Sunset Gardens SW

Square Footage: 55,067

Date of Opening: 1959

Current Projects: Phase 2a Kindergarten Wing New Staff Parking Lot Reroofing

Budget:  $6,769,688

Date of Completion: March 2010

Architects: PA Architects, High Mesa O/E, Greg T. Hicks O/E

General Contractor:  Lockwood

22

Page 23: APS Construction Update Nov2011 [Read-Only]

La Luz Elementary School Address: 225 Griegos Rd NW

Square Footage: 38,102

Year Opened: 1995

Projects: Admin Addition and Renovation Kitchen/Cafeteria Addition Phase II

Date of Completion: March 2010

Budget: $1,555,226

Architect: Design Plus O/E General Contractor: BZ Ent., 

AnchorBuilt

23

Page 24: APS Construction Update Nov2011 [Read-Only]

24

Apache Elementary School Address: 12800 Copper NE

Square Footage: 46,637

Year Opened: 1967

Projects: Kindergarten Addition/ Renovation  Restroom Improvements  Dumpster Enclosure Electrical Fund‐LEED Drainage and electrical 

improvements

Date of Completion: Feb 2010

Budget: $1,018,084

Architect: Huitt‐Zollars

General Contractor:  ESA Construction

Page 25: APS Construction Update Nov2011 [Read-Only]

Alvarado Elementary School Address: 1100 Solar NW

Square Footage: 38,424

Year Opened: 1952

Projects:  Kindergarten Addition Playground/Basketball Court 

Improvements

Date of Completion: March 2010

Budget: $2,046,214

Architect: G. Donald Dudley General Contractor: Famco 2011 Strategy Projects:

Kitchen/Cafeteria Addition + Renovation Entry Court/Administration/Media Center 

Addition Restroom Renovation Upgrade Security Budget: $3,122,269

25

Page 26: APS Construction Update Nov2011 [Read-Only]

For Additional Information

APS Facilities Design & Construction

http://www.apsfacilities.org/facilities/

APS Capital Master Plan

http://www.apsfacilities.org/capital/

26