april 25, 2011 otpcindia new delhi

18
2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India April 25, 2011 www.otpcindia.in New Delhi

Upload: esma

Post on 14-Jan-2016

30 views

Category:

Documents


1 download

DESCRIPTION

2 X 363.3 Combined Cycle Gas Power Project Palatana, Tripura Presentation at Ministry of Development of North Eastern Region, Government of India. April 25, 2011 www.otpcindia.in New Delhi. Contents. Background Project Highlight Power Allocation - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: April 25, 2011                                        otpcindia New Delhi

2 X 363.3 Combined Cycle Gas Power Project

Palatana, Tripura

Presentation

atMinistry of Development of

North Eastern Region,Government of India

April 25, 2011 www.otpcindia.inNew Delhi

Page 2: April 25, 2011                                        otpcindia New Delhi

Contents

Background Project Highlight Power Allocation Project Location Gas Supply Network of ONGC Project Status : Clearances & Permits Project Status : Supply and Construction Project Status : Erection Logistics Status of Inputs Areas of Concern Assistance Required

Page 3: April 25, 2011                                        otpcindia New Delhi

October 29, 2005

LAYING OF FOUNDATION STONE

Page 4: April 25, 2011                                        otpcindia New Delhi

Source of Inspiration

Page 5: April 25, 2011                                        otpcindia New Delhi

Project Highlight

Capacity: 2 x 363.3 MW

Type: Gas Based Combined Cycle

Location: Palatana, Tripura

Project Cost: Rs 3,429 Crore

Source of Fuel: ONGC’s Gas Field in Tripura

Type of Fuel: Natural Gas

Quantity of Fuel: 2.65 MMSCMD

Source of Water: River Gumti

Quantity of Water: 125 MLD

Promoters: ONGC (50%), IL&FS (26%), GOT (0.5%).

Page 6: April 25, 2011                                        otpcindia New Delhi

Project Highlight …… Contd

EPC Contractor: Bharat Heavy Electricals Limited (BHEL)

Award of Contract: 23-Jun-08

Commissioning: Unit-1: 22-Dec-11,

Unit-2: 22-Mar-12

Evacuation: 650 KM 400 KV D/C Palatana – Bongaigaon Line

Page 7: April 25, 2011                                        otpcindia New Delhi

Power Allocation

Power Allocation by MoP

Beneficiary State Pro-rata allocation in MW based on actual capacity of 726.6 MW

Tripura 196

Assam 240

Arunachal Pradesh 22

Nagaland 27

Mizoram 22

Manipur 42

Meghalaya 79

Power allocated to OTPC 98

Page 8: April 25, 2011                                        otpcindia New Delhi

Project Location

650 kms 400 kV D/C line

Byrnihat S/S

Ajara S/S

Silchar S/S

Page 9: April 25, 2011                                        otpcindia New Delhi

Konaban GGSKunjaban Manifold

Nimbutali

Sonamura GGS

Agartala Dome GGS(ADB)

Palatana

Sundalbari Manifold

16” 12km Pipeline

(Sector–II)

8” 19.5km Pipeline

(Sector-IV)

6” 19.5km Pipeline

(Sector-V)

20” 41km Pipeline (Sector-I)

20” 12km Pipeline

(Sector –I)

8” 12.5km Pipeline

(Sector –VI)6” 12.5km

Pipeline(Sector-VII)

16” 22km Pipeline

(Sector – III)

BagabasaSectionalizing Valve Station

F1A : Facility F1 (Early)F1B : Facility F1 (as per NOA)F 2 : Facility F2

Gas Supply from ONGC – Tripura Asset

F1A

F1A

F1B

F2F2

F2

Page 10: April 25, 2011                                        otpcindia New Delhi

Project Status: Clearances and Agreements

Clearance received from MOEF, TSPCB, AAI, MOD

State Support Agreement Signed

206 Acres of Land Acquired for the project

Shareholders Agreement, Gas Sale & Purchase Agreement and Power

Purchase Agreement signed.

Long Term Service Agreement signed with OEM (GE) for Gas Turbine

Page 11: April 25, 2011                                        otpcindia New Delhi

Project Status : Supply & Construction

SUPPLIES

All ODC to be transported through Bangladesh dispatched from BHEL works. Transportation of ODC from Kolkata to Ashuganj in Bangladesh started in February’11 and last consignment expected to reach Bangladesh in May’11.

Supplies of non-ODCs to be transported via Gauhati started in Mar-10 and last dispatch from BHEL works for Unit-1 & Unit-2 is expected by Jun-11 and Sep-11 respectively.

CIVIL CONSTRUCTION

Piling and foundation of major buildings for Unit-1 completed and main plant equipment erection started in Jan-11.

Major structures for Unit-2 are likely to be ready for erection by Jun-11.

Work for Cooling Tower and Water Treatment System has commenced. CT-1 is likely to be commissioned in Sep-11 and Water Treatment System is likely to be commissioned in Jul-11

Construction of River Water Intake Pump house and pipeline has commenced and likely to be commissioned by Jul-11.

Page 12: April 25, 2011                                        otpcindia New Delhi

Project Status : Erection

ERECTION

Main Plant equipment erection started in Jan-11

Milestone Target Date

UNIT-1

Mechanical Completion Sep-11

Hydro test Completion Nov-11

Readiness for commissioning Dec-11

UNIT-2

Mechanical Completion Dec-11

Hydro test Completion Feb-12

Readiness for commissioning Mar-12

Page 13: April 25, 2011                                        otpcindia New Delhi

Routes: Kolkata – Ashuganj – Palatana Kolkata – Karimgunj - Palatana

Page 14: April 25, 2011                                        otpcindia New Delhi

Routes for transportation of ODCs from Kolkata: There are two routes available for transportation of ODCs to Palatana site:

Via Karimganj: 1318 KM (river) + 320 KM (road - India)

Via Ashuganj (Bangladesh): 856 KM (river) + 115 KM (road – India + B’dsh)

Ashuganj route has been selected because river route is navigable through out the year and road route passes through generally plain land leading to less risk in transportation.

Hon’ble Prime Minister of Bangladesh during her visit to India in Jan-10 agreed to allow movement of ODC through Ashuganj in Bangladesh. Since then, Ashuganj has been included in Indo-Bangla Water Transport Proto-call and MOU has been signed with GOB on 29th November 2010 formally allowing movement of ODCs through Bangladesh territory.

90 ODCs shall be transported through Bangladesh. Construction of bypasses in between Ashuganj (Bangladesh) and Palatana (Tripura) has breen completed.

13 ODCs have reached site, 2 are likely to reach site within 2-3 days and balance ODCs are expected to reach site progressively by Jun-11.

Logistics – Overview

Page 15: April 25, 2011                                        otpcindia New Delhi

PROJECT – STATUS OF INPUTS

Commissioning Gas Start-up Power Evacuation System

Responsible agency ONGC TSECLNETCL / POWERGRID /

NER STATES

Latest required – to meet commissioning schedule

August ’11 May’11 November’11

Current StatusConstruction has

started

Contract for line construction awarded

Slow progress

Construction started but moving at tardy

pace.

OTPC assessment No delay Delay of 3 Months

Delay of 3 months (up to Silchar)

Delay of 6-9 months (up to Bongaigaon)

Impact on unit#1 No impact Delay of 3 monthsLikely delay of 3

months

Impact on Unit#2 No impact No impactLikely delay of 6/9

months

Page 16: April 25, 2011                                        otpcindia New Delhi

SILCHAR – BONGAIGAON TRANSMISSION LINE

Delay in Forest Clearance in Meghalaya (25 KM) and Assam (22 KM) – NETCL

EVACUATION CONSTRAINT: PALATANA – BONGAIGAON

Delay in construction of Azara, Byrnihat and Surajmaninangar sub-station – Assam / Meghalaya / Tripura

Delay in construction of 400 kV Silchar sub-station – POWERGRID

Delay in construction of Palatana – Silchar Line – NETCL / POWERGRID

DOWNSTREAM NETWORK BY BENEFICIARY STATES

Work yet to commence by States i.e. Assam, Tripura, Mizoram etc for absorption of power. Unit-1 commissioning may be delayed on this account. – NER States

States to absorb Unit-1 power:

Assam : 120 MW Meghalaya: 40 MW

Tripura: 98 MW Manipur: 21 MW

Mizoram: 11 MW Nagaland: 14 MW

Arunachal: 11 MW

AREAS OF CONCERN

Page 17: April 25, 2011                                        otpcindia New Delhi

Immediate Forest Clearance in Assam (22 KM), Meghalaya (25 KM) and Tripura (4 KM) required.

State governments to expedite development of Azara (Assam), Byrnihat (Meghalaya) and Surajmaninagar (Tripura) sub-station and downstream network to match Unit-1 commissioning in Dec-11

States to advise POWERGRID to install series-compensation facility at Bongaigaon sub-station.

Government of Tripura to expedite construction of 132 KV line and provide startup power by May-11

POWERGRID to expedite construction of 400 kV Silchar substation to match with Unit-1 commissioning in Dec-11.

NETC and POWERGRID to expedite construction of 400 kV D/C Palatana – Silchar Line

ASSISTANCE REQUIRED

Page 18: April 25, 2011                                        otpcindia New Delhi

April 25, 2011New Delhi