april 14, 2004 architectural engineering senior thesis · pdf filekania som / brennan hall...
TRANSCRIPT
![Page 1: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/1.jpg)
April 14, 2004 Architectural Engineering Senior Thesis
![Page 2: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/2.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 3: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/3.jpg)
Kania SOM / Brennan HallProject Background
Introduction
Five-story office/classroom building
68,500 square feet
$12.3 million project
1st and 2nd floors primarily classrooms
3rd and 4th floors primarilyfaculty offices
5th floor executive board room and catering facilities
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 4: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/4.jpg)
Kania SOM / Brennan HallProject Background
Project Team
Owner – University of Scranton
Architects – Burkavage Design Associates
Structural Engineer – QproQ Engineering, Inc.
Geotechnical Consultant – Geo-Science Engineering
General Contractor – Sordoni Construction Services
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 5: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/5.jpg)
Kania SOM / Brennan HallProject Background
Construction
Started March 1999
Completed August 2000
CM at risk delivery method
Adjacent dorms constructed at same time
Subcontractor lump sum bids
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 6: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/6.jpg)
Kania SOM / Brennan HallProject Background
Structure
Structural steel framing
Fully rigid moments frames
Concrete-filled composite metal deck
Column spread and continuous wall footings
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 7: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/7.jpg)
Kania SOM / Brennan HallProject Background
Information Technology
Showcase instructional technologies and conference center flexibility
Touch screen control of lighting, computing, and audio/video components
Overhead projector, motorized screens, image visualizers, DVD & CD players
High-end video displays, theater like sound and video conferencing in executive conference center
Auditorium featuring theater like audio and video environments
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 8: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/8.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 9: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/9.jpg)
Kania SOM / Brennan HallStructural Depth Study
Loads
From AISC Manual of Steel Construction
Dead loadsRoof dead (no ballast) 16.7 psfRoof dead (with ballast) 26.7 psfFloor dead 100 psf
From ASCE 7-02
Live loadsCorridors 80 psfClassrooms 40 psfOffices 50 psf
Snow load 30 psf
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 10: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/10.jpg)
Kania SOM / Brennan HallStructural Depth Study
Loads
As Calculated by RAM Frame
Wind loads N-S E-WRoof level 12.2 kips 14.4 kipsFifth Floor 21.5 kips 22.9 kipsFourth Floor 20.5 kips 21.7 kipsThird Floor 21.7 kips 19.9 kipsSecond Floor 22.5 kips 18.3 kipsTotal 98.4 kips 97.2 kips
Seismic loadsTotal Building Weight 5690 kipsN-S Base Shear 246.7 kipsE-W Base Shear 284.5 kips
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 11: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/11.jpg)
Kania SOM / Brennan HallStructural Depth Study
Lateral System
Goals for proposed systemEliminate high cost of steel moment connectionsReduce steel erection time by eliminating steel
moment connections
Initially four shear wallsTwo located on each of
two opposing cornersVery rigid, very small
driftHigh lateral loads
caused overturning moment problems
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 12: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/12.jpg)
Kania SOM / Brennan HallStructural Depth Study
Lateral System
Combat overturning moments byAdding two additional shear walls
Decrease lateral load to each wallIncreasing wall thickness
Increase mass for resisting momentsIncreasing wall footing sizes
Increase mass for resisting moments
Wall Footings Thickness (ft) Width (ft) Length (ft)1 5 12 432 5 12 253 5 12 534 5 14 305 6 16 646 6 16 60
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 13: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/13.jpg)
Kania SOM / Brennan HallStructural Depth Study
Lateral SystemDesigned as deep cantilever beamsReinf. generally controlled by minimum steel areasExterior walls also designed for wind pressure
Frame Level thk (in) lw (ft) hw (ft) d (in) Mu (ft-k) Vu (k)Horiz. Web
Reinf.
Vert. Web Reinf.
Tensile Reinf.
+ Mu Reinf. - Mu Reinf. Shear Reinf.
Roof 12 31 14 366 360.73 25.77 (2) #3@6" (2) #3@12" (8) #9 #5 @ 12" #5 @ 12" N/A5 12 31 14 366 674.49 22.41 (2) #3@6" (2) #3@12" (8) #9 #5 @ 12" #5 @ 12" N/A4 12 31 14 366 1454.57 55.72 (2) #3@6" (2) #3@12" (8) #9 #5 @ 12" #5 @ 12" N/A3 12 31 14 366 2350.60 64.00 (2) #3@6" (2) #3@12" (8) #9 #5 @ 12" #5 @ 12" N/A2 12 31 14 366 3808.09 104.11 (2) #3@6" (2) #3@12" (8) #9 #5 @ 12" #5 @ 12" N/A
Roof 12 13 14 150 113.47 8.11 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A5 12 13 14 150 228.07 8.19 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A4 12 13 14 150 608.02 27.14 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A3 12 13 14 150 556.24 3.70 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A2 12 13 14 150 1211.14 46.78 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A
Roof 12 41 14 486 564.15 32.42 (2) #3@6" (2) #3@12" (10) #10 #5 @ 12" #5 @ 12" N/A5 12 41 14 486 1471.41 62.86 (2) #3@6" (2) #3@12" (10) #10 #5 @ 12" #5 @ 12" N/A4 12 41 14 486 2739.42 98.19 (2) #3@6" (2) #3@12" (10) #10 #5 @ 12" #5 @ 12" N/A3 12 41 14 486 3593.11 79.46 (2) #3@6" (2) #3@12" (10) #10 #5 @ 12" #5 @ 12" N/A2 12 41 14 486 4995.58 124.78 (2) #3@6" (2) #3@12" (10) #10 #5 @ 12" #5 @ 12" N/A
Roof 12 13 14 150 157.74 15.94 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A5 12 13 14 150 187.62 8.64 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A4 12 13 14 150 384.59 27.21 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A3 12 13 14 150 453.55 20.54 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A2 12 13 14 150 879.25 51.17 (2) #3@6" (2) #3@12" (6) #7 #5 @ 12" #5 @ 12" N/A5 12 33.5 14 396 1769.06 138.59 (2) #3@6" (2) #3@12" (8) #104 12 33.5 14 396 3901.29 178.69 (2) #3@6" (2) #3@12" (8) #103 12 49.17 14 584 3929.75 248.58 (2) #3@6" (2) #3@12" (10) #102 12 49.17 14 584 4265.37 233.47 (2) #3@6" (2) #3@12" (10) #105 12 19 14 222 1144.77 105.15 (2) #3@6" (2) #3@12" (8) #74 12 19 14 222 2489.67 144.75 (2) #3@6" (2) #3@12" (8) #73 12 40.5 14 480 2613.24 273.61 (2) #3@6" (2) #3@12" (10) #102 12 40.5 14 480 3128.11 227.42 (2) #3@6" (2) #3@12" (10) #10
6
2
3
4
5
Lateral Load Resisting Design Area Load Resisting Design
1
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 14: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/14.jpg)
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Goals for proposed systemReduce weight of floor systemImprove efficiency of floor system
Replace wide flange infill beams with open web steel joists
ConcernsFire ProtectionFloor Vibrations
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 15: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/15.jpg)
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Typical joist layout
Joists oriented to span long dimension of bay for economy
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 16: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/16.jpg)
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Fire ProtectionDifficult for spray-applied fireproofing to adhere
to joist webs
Design No. G708 from U.L. Fire Resistance Directory
2 hour fire rating
W8X28 min. beam sizeNormal weight concrete, f’c = 3500 psiForm deck with 2 ½” pitch, ½” corrugationsmin. 16K6 joists spaced at 3’-6” max.Spray-applied fire resistive materialMetal lath (optional)
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 17: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/17.jpg)
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Fire ProtectionDesign No. G708 from U.L. Fire Resistance
Directory
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 18: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/18.jpg)
Kania SOM / Brennan HallStructural Depth Study
Gravity System
Floor VibrationsCalculations based on AISC’s Design Guide 11
Applied loadsLive load 11 psfMisc. 4 psf
Floor stiffness evaluationCombined mode frequency 4.8 HzNot needed since less than 9 Hz
Walking evaluationPeak acceleration 0.43%gLess than office limit of 0.5%g
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 19: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/19.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 20: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/20.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Cost analysis to evaluate lateral system
Material Costs
Materials addedReinforced concrete shear wallsWall footings
Materials removedSpread footingsMoment connectionsSteel beamsSteel columns
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 21: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/21.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Material Costs
Shear WallsFrame thk (in) Avg lw (ft) hw (ft) vw (ft3) vw (CY) Cost ($/CY) Cost ($)
1 12 31 14 434 16.07 62 9972 12 13 14 182 6.74 62 4183 12 41 14 574 21.26 62 1,3184 12 13 14 182 6.74 62 4185 12 41.33 14 578.62 21.43 62 1,3296 12 29.75 14 416.5 15.43 62 956
Total Cost ($) 5,436
New Ftgs thk (ft) w idth (ft) length (ft) vw (ft3) vw (CY) Cost ($/CY) Cost ($)1 5 12 43 2580 95.56 59 5,6382 5 12 25 1500 55.56 59 3,2783 5 12 53 2400 88.89 59 5,2444 5 14 30 2100 77.78 59 4,5895 6 16 64 4664.16 172.75 59 10,1926 6 16 60 5760 213.33 59 12,587
Removed FtgsF50 1.33 5 5 33.25 1.23 59 -73F60 1.67 6 6 60.12 2.23 59 -131F66 1.83 6.5 6.5 77.3175 2.86 59 -169F70 1.83 7 7 89.67 3.32 59 -196
(3) F76 2 7.5 7.5 337.5 12.50 59 -738F80 2.17 8 8 138.88 5.14 59 -303
(3) F86 2.17 8.5 8.5 470.3475 17.42 59 -1,028F120 2.67 12 12 384.48 14.24 59 -840F136 2.17 13.5 13.5 395.4825 14.65 59 -864F5680 1.5 5.6 8 67.2 2.49 59 -147
Total Cost ($) 37,039
New wall footings and spread footings removed
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 22: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/22.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Material Costs Connections Cost ($/CY) Cost ($)Moment 280 -67,200Shear 70 16,800
Beams Qty Wt. (plf) length (ft) Wt. (lb) Wt. (Tons) Cost ($/Ton) Cost ($)W16x26 1 26 8.5 221 0.11 425 -47W16x26 5 26 11 1430 0.72 425 -304W16x26 1 26 13 338 0.17 425 -72W16x26 4 26 15.67 1629.68 0.81 425 -346W16x26 5 26 16.5 2145 1.07 425 -456W16x26 1 26 18.5 481 0.24 425 -102W16x26 1 26 21.5 559 0.28 425 -119W18x35 3 35 4 420 0.21 425 -89W18x35 4 35 13 1820 0.91 425 -387W18x35 4 35 19 2660 1.33 425 -565W18x35 4 35 21.5 3010 1.51 425 -640W18x35 1 35 27 945 0.47 425 -201W18x40 3 40 8.5 1020 0.51 425 -217W18x40 1 40 13 520 0.26 425 -111W18x40 4 40 18.5 2960 1.48 425 -629W18x40 1 40 21.5 860 0.43 425 -183W18x50 4 50 13 2600 1.30 425 -553W21x50 1 50 8.5 425 0.21 425 -90W21x50 1 50 21.5 1075 0.54 425 -228W21x62 1 62 21.5 1333 0.67 425 -283W24x55 1 55 4 220 0.11 425 -47W24x68 1 68 21.5 1462 0.73 425 -311W24x76 1 76 40.5 3078 1.54 425 -654W27x84 1 84 15.67 1316.28 0.66 425 -280W27x84 2 84 27 4536 2.27 425 -964W27x94 1 94 27 2538 1.27 425 -539
ColumnsW8x24 3 24 14 1008 0.50 425 -214W8x31 8 31 14 3472 1.74 425 -738W8x40 10 40 14 5600 2.80 425 -1,190W8x48 2 48 14 1344 0.67 425 -286W8x58 4 58 14 3248 1.62 425 -690W8x67 4 67 14 3752 1.88 425 -797W12x45 3 45 14 1890 0.95 425 -402W12x50 3 50 14 2100 1.05 425 -446W12x53 2 53 14 1484 0.74 425 -315W12x72 4 72 14 4032 2.02 425 -857W12x87 2 87 14 2436 1.22 425 -518W14x82 3 82 14 3444 1.72 425 -732
W14x176 2 176 14 4928 2.46 425 -1,047Total Cost ($) -67,047
Qty240240
Shear connections replacing moment connections
Steel beams and columns removed
Total material cost savings of nearly $25,000
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 23: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/23.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Construction Schedule
Sequencing shear wall constructionFormwork erectionConcrete placing and finishingStrip and rebuild forms
Time saved in steel erectionFewer steel membersNo moment connections
Sequencing with foundation construction
Time for concrete walls to reach 80% strengthSteel attached to concrete walls
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 24: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/24.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Detailed shear wall construction sequence
Two formwork crews
Sequence forming and placing
WeekDay S M T W R F S S M T W R F S S M T W R F S S M T W R F S S M T W R F S S M T W R F S
Steel Delivery
Steel Erection
Level 5 Walls
Form 1 & 2 - 1 Crew
Pour 1 & 2
Form 3 & 4 - 1 Crew
Pour 3 & 4
Level 4 Walls
Form 1 & 2 - 1 Crew
Pour 1 & 2
Form 3 & 4 - 1 Crew
Pour 3 & 4
Form 5 & 6 - 2 Crews
Pour 5 & 6
Level 3 Walls
Form 1 & 2 - 1 Crew
Pour 1 & 2
Form 3 & 4 - 1 Crew
Pour 3 & 4
Form 5 & 6 - 2 Crews
Pour 5 & 6
Level 2 Walls
Form 1 & 2 - 1 Crew
Pour 1 & 2
Form 3 & 4 - 1 Crew
Pour 3 & 4
Form 5 & 6 - 2 Crews
Pour 5 & 6
Level 1 Walls
Form 1 & 2 - 1 Crew
Pour 1 & 2
Form 3 & 4 - 1 Crew
Pour 3 & 4
Form 5 & 6 - 2 Crews
Pour 5 & 6
4: Oct. 31-Nov. 6 5: Nov. 7-13 6: Nov. 14-20
Foundation System
1: Oct. 10-16 2: Oct. 17-23 3: Oct. 24-30
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 25: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/25.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Construction ScheduleYearMonth
Original ScheduleSchedule with Shear Walls
Steel Delivery12/13
Steel Erection
11/15
11/15
Foundation System
Shear Wall Construction
8/2 11/15
10/11 11/12
12/17
1999July August September October November December
Qty Duration (hr or day) Cost ($/hr) Cost ($/day) Cost ($)Formwork Carpenters 8 184 38 55,936
Carp. Foreman 1 184 41 7,544Laborers 4 184 31 22,816
Labor Forman 1 184 43 7,912Pump 1 22 1200 26,400Crew 4 176 39 27,456
Total Cost ($) 148,064
Activity
(2 Crews)
Place & Finish
Qty Duration (day) Cost ($/day) Cost ($)Bms & Cols 107 2 5000 -10,000Connections 240 2 5000 -10,000
Total Cost ($) -20,000
ActivityErection
Total construction costs nearly $128,000
Shear wall construction costs
Steel erection costs
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 26: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/26.jpg)
Kania SOM / Brennan HallScheduling/Cost Breadth Study
Final Cost Figures
Combination of material and construction costs
Cost ($)Shear Walls 5,436
Footings 37,039Steel -67,047
Concrete 148,064Steel -20,000
Total Cost ($) 103,491Project Cost ($) 12,350,000
Percent Change (%) 0.84
ItemMaterials
Construction
Reinforced concrete shear walls result in nearly a $103,500 increase in total project cost
However, amounts to less than a 0.9% increase
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 27: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/27.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 28: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/28.jpg)
Kania SOM / Brennan HallWireless LAN Breadth Study
Wireless LAN
Goals for proposed systemLess wire and cable throughout buildingMore flexible systemReduce overhead costs caused by moves,
extensions to networks, adding connectionsCan serve as hot spot for students with laptopsCan connect other buildings to same network
Installing network in older buildings is easy
802.11aSelected over 802.11b & g standards64 users per access pointLower possibility of interferenceGood for; dormitories, computer labs,
conference rooms, VoIP
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 29: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/29.jpg)
Kania SOM / Brennan HallWireless LAN Breadth Study
Access Points
Analyzedlayout# of users
Determined # of AP’s AP
APAP
SC AP
APAP
AP
AP
SC
AP
AP
AP
AP
AP
AP
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 30: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/30.jpg)
Kania SOM / Brennan HallWireless LAN Breadth Study
Integrated IP Phone System
Wireless IP PhonesUsed by physical plant employees
Desktop IP PhonesConnected via Ethernet to wired
backboneLocated in secretary
and waiting areas
PC Based PhonesSoftware allowing computers
to be used as IP phonesEach individual’s extension
follows them to any computerTeleconferencing capabilities
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 31: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/31.jpg)
Kania SOM / Brennan HallWireless LAN Breadth Study
Interactive Whiteboards
Replaces chalkboard, overhead projector and screen
Can function simply as a whiteboardCan display computer imagesCan save handwritten notes to print
or post on course websites
Video Conferencing
Located in executive conference centerBuilt in conferencing with multiple video
and audio sitesDual LCD monitorsAdd a PC to the meetingSee live PC presentations and presenter
simultaneously
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 32: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/32.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 33: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/33.jpg)
Kania SOM / Brennan HallConclusions
Conclusions
Structural Depth Study – Lateral SystemLateral system consisting of six reinforced
concrete shear wallsVery rigid, little driftLarger wall footings needed for overturningWas a successful educational projectLearned how to design shear walls
Scheduling/Cost Breadth StudyAdditional crews and equipment needed for five
weeks to construct shear wallsSteel erection shortened four daysShear walls increased total project cost by
$103,500Less than a 0.9% increase
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 34: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/34.jpg)
Kania SOM / Brennan HallConclusions
Conclusions
Structural Depth Study – Gravity SystemEconomic joist layoutMore efficient floor framingTwo hour fire rated ceiling assemblyAdequate for floor excitation
Wireless LAN Breadth StudyMore flexible network solutionAccess points located throughout buildingIP telephony available from any networked
computerInstructional spaced equipped with interactive
whiteboardsSophisticated video conferencing units in
executive conference center
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 35: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/35.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 36: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/36.jpg)
Kania SOM / Brennan HallAcknowledgements
Douglas Wisniewski Architectural Engineering Senior Thesis
I would like to thank
James Devers, AIA, U of S Physical PlantDon Flynn, Burkavage Design AssociatesLinda Hanagan, PhD, PE, Penn State UniversityJames Kerns, PE, QproQ EngineeringFrancis Kranick, U of S Physical PlantM. Kevin Parfitt, Penn State UniversityAndrew Shedlock, Sordoni ConstructionRonald Skutnick, U of S Network ResourcesDavid Wilson, AIA, U of S Physical PlantDavid Wisniewski, Raytheon
For all of the time and information they have contributed to this project.
![Page 37: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/37.jpg)
Kania SOM / Brennan HallPresentation Outline
Project BackgroundIntroductionProject TeamConstructionStructureInformation Technology
Structural Depth StudyLoadsLateral SystemGravity System
Scheduling/Cost Breadth StudyMaterial CostsConstruction ScheduleFinal Cost Figures
Wireless LAN Breadth StudyWireless LANAccess PointsIP PhonesInteractive WhiteboardsVideo Conferencing
Conclusions
Acknowledgements
Questions
Douglas Wisniewski Architectural Engineering Senior Thesis
![Page 38: April 14, 2004 Architectural Engineering Senior Thesis · PDF fileKania SOM / Brennan Hall Project Background Introduction ¾Five-story office/classroom building ¾68,500 square feet](https://reader033.vdocuments.us/reader033/viewer/2022052710/5aa5cfff7f8b9a517d8dc0d7/html5/thumbnails/38.jpg)
Kania SOM / Brennan HallQuestions
Douglas Wisniewski Architectural Engineering Senior Thesis