apqp with flow of process
TRANSCRIPT
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008
Page No.: 1 of 8
PURPOSE1 ) To define procedures for new process development ,
2 ) To Develop a cost effective Process to meet Customer timing requirements.
3 ) To direct company's resources to meet customer requirements
4 ) To identify problems too early, so that late changes are avoided
SCOPEApplicable to new process development
Applicable to significant process change & significant design modification
(If new tooling required or supplied by customer)
DEFINITIONS
The Cross functional Team for new Process Development and for design process changes is fixed .
appointed through an IOM.
Development Team will consist of the following functions at the minimum.
Engineering : Programme Manager
Quality Assurance : Team Member
Production : Team Leader ( CFT Leader)
Maintenance : Team Member
Purchase : Team Member
Marketing : Team Member
Amtek group functions and Customer's Representative ( when required by Customer ) will be invited for CFT meeting
as and when necessary
The person to liaise with Customer and to represent Customer in internal functions will also be identified .
CFT Leader can co-ordinate with any other member as and when necessary.
As and when necessary , operator will be involved during development.( Ex. C.P. , W.I. )
Record
1 ) APQP File
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008
Page No.: 2 of 8
Primary Secondary Process Owner : Engineering
pro
d
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt PROCESS CHART Related Document
Receive New Product Enquiry with Enquiry register
Drawing and or sample.
Quotation
No
Yes
Formation of CFT Team for project CFT form
Yes
Process flow
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Assign Request for Quotation No. to each Drawing and Update RFQ Tracking Sheet.
Refer TGW/TGR record of previous project, Product history for necessary proactive action
Prepare Preliminary BOM , Preliminary Process Flow Chart, Risk Analysis , Manufacturing Team Feasibility, Special Product and
Process Characteristics Identified based on Drawing or CRT agreement, Feasibility Review, identify opportunity for Mistake
proofing and Review for need of sub supplier
Start
Business decision toprocess enquiry
Customer / productinformation &
standards given for product adequate ?
Regret offer
Clarify with customer
A
NO
Prepared by Approved by Master copy Controlled copy
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008
Page No.: 3 of 8
Primary Secondary Process Owner : Engineering
pro
d
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt PROCESS CHART Related Document
Send to Approval Costing sheet
Approval
No
Yes
P.O.
APQP Review Meeting ( Gate 1) Review Record
Part Drawing
Check list
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Prepare " Product Costing Sheet", Tooling Costing Sheet.
Quote to Customer along with Standard Terms Conditions
Negotiate & Resolve with Customer.
P.O/Tooling Order from Customer
1) Notify customer for
any slippage in PSW Timing
plan 2) Initiate recovery action to
improve Red point
Prepare APQP Timing Plan & ensure for adherence.
Receive new drawings & Quality documents from customer
List of customer drawing
Review and check customer data as per check list(AAL/D/CH/01)
Review of DFMEA , Product history, Quality rating, Drawing Dimns.
Clarifications..
Review for Clarification required from customer if any
Discuss with customer & get clarification , resolve issue if any.
A
Acceptable
B
Identify & development of sub supplier
NO YES
Need of sub -supplier
H
Start APQP activity of sub supplier as per doc.no AAL/CFT/F/07 . ( Sub supplier APQP Gate Ways )
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008
Page No.: 4 of 8
Primary Secondary Process Owner : Engineering
pro
d
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt
Prepare Amtek Drawing Amtek Drawing
Issue Register
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Get approval from customer & maintain as a Master copy
Master copy drawing file
Track Five Gateway timing plan & Update GYR Status
Put controlled copy stamp & issue to concern dept.
Prepare Simulation data for analysis
CAD data for tooling preparation
Make changes
OK
Release Tooling Design to concern dept with necessary controls
OK
Not Ok
B
C
Pass all drawing specification,significant,characteristics(CC,SC,PTC,HIC details to supplier for child part development
Sample submit to Amtek
OKREJ
PPAP from sub- supplier as per level 3 requirement.
K
H
Convey rejected points to sub supplier & take corrective action if any.
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008
Page No.: 5 of 8
Primary Secondary Process Owner : Engineering
pro
d
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt PROCESS CHART Related Document
Review New Equipment, Tooling & Facilities
Identify Special Characteristic Special char. sheet
APQP Review Meeting ( Gate 2)
No
Yes
Customer approval
Prepare Process parameters sheet Process Para. sheet
Review Process Flow Chart Flow chart
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Develop Prototype Control Plan & Proto samples.
Validation of samples for appearance & dimensional aspects ( reliability requirement,
if any) & submit to customer.
C
Any Prototyperequirements ?
D
1) Notify customer for any slippage in PSW Timing plan 2) Initiate recovery action to improve Red point
Use PPAP approved part from sub- supplier
K
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008Page No.: 6 of 8
Primary Secondary Process Owner : Engineering
Pro
d
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt PROCESS CHART Related Document
Prepare floor plan Floor plan
Review PFMEA
Develop Pre-launch / production Control Plan Control plan
Develop process Quality instructions /Work instruction
Operator instructions
Review Record
Make corrections if any.
Inspection by QA
APQP Review Meeting ( Gate 3)
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Sampling Trial for casting & machining ( if involved. )
1) Notify customer for
any slippage in PSW Timing
plan 2) Initiate recovery action to
improve Red pointValidation of samples (product & process) ,
confirm parts are meeting dimensional , functional (& reliability requirement, with sub
supplier part if any) .
E
D
Doc.No. : PR/ENGG/01
Rev.No. : 02
Rev. dt : 04.07.2008
Page No.: 7 of 8
Primary Secondary Process Owner : Engineering
Pro
d
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt PROCESS CHART Related Document
Lay out Inspection by QA
No
Yes
Develop SPC study Plan Spc study plan
No
Yes
Develop MSA study Plan MSA Plan
Dimensional Verification
Validation record
APQP Review Meeting ( Gate 4)
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
Sample Submission to customer ( With sub supplier part if any )
1) Notify customer for any slippage in PSW Timing plan 2) Initiate recovery action to improve Red
E
Any SPCrequirements
Are New MSAstudies required
Any ProductionTrial requirements
of Customers
F
Doc.No. : PR/ENGG/01
Rev.No. : 02Rev. dt : 04.07.2008
Page No.: 8 of 8
Primary Secondary Process Owner : Engineering
Desi
gn
M.R
.
Pu
r
Eng
i
Q.A
.
Mkt PROCESS CHART Related Document
Customer feedback
Corrections if any.
PPAP File
Product quality planning summary & sign-off Sign off sheet
APQP Review Meeting ( Gate 5) Review sheet
Track 5000 components or 3 months
Prod. Record supplies (whichever is earlier ) for any Concern
No
Yes
Control plan
ECN
Prepared by Approved by Master copy Controlled copy
ADVANCED PRODUCT QUALITY PLANNING - NEW PRODUCTS
PPAP Submission with all applicable documents. (Default level 3 & min. 300 parts unless specified.)
1) Notify customer for
any slippage in PSW Timing
plan 2) Initiate recovery action to
improve Red point
Develop, Track Action Plan & review FMEA for high RPN.
Any improvement or modification in process after PPAP approval must inform to internal
Quality for approval
F
Any concerns
Stop