approaches to historic bridge rehabilitation case study #2
DESCRIPTION
Approaches to Historic Bridge Rehabilitation Case Study #2. Lake Park North Lion Bridge Rehabilitation Milwaukee, Wisconsin Darrell Berry, PE, SE. Case Study #2. Lake Park North Lion Bridge. Steel arch with concrete deck Originally built in 1896, narrowed in the 1960s - PowerPoint PPT PresentationTRANSCRIPT
Lake Park North Lion Bridge RehabilitationMilwaukee, Wisconsin
Darrell Berry, PE, SE
Approaches to Historic Bridge Rehabilitation
Case Study #2
1
Lake Park North Lion Bridge Steel arch with concrete deck
Originally built in 1896, narrowed in the 1960s
Length: 90 feet; Width: 10 feet clear Single span steel arch Design Live Load: 85 psf or 15,000 lb.
vehicle
Case Study #2
North Lion Bridge
Lake Michigan
2Milwaukee, Wisconsin
Lake Park North Lion Bridge Rehabilitation
Owner: Milwaukee County Department of Parks, Recreation and Culture
Design Engineer: Mead & Hunt, Inc.
General Contractor: Vista Design & Construction, LLC
Project Cost: $1.6 Million
Project dates: started Feb 2009,
completed Oct 2009.
Case Study #2
3
Significant Issues Associated With Project
Case Study #2
4
1. Arch Structure
2. Railing
3. Stone Facing on Abutments
4. Lion Statues
1. Steel arch structure, including bearings & concrete deck
5
How Arch Issue Was Resolved
Case Study #2
6
Deteriorated structural steel was removed and replaced, with details matching original.
Bearings were removed and replaced.
Concrete deck was removed and replaced Precast concrete panels Cast-in-place concrete surface
2. Metal Railings
Case Study #2
7
How Railing Issue Was Resolved
Case Study #2
Railings were removed from bridge and delivered to a fabrication shop.
New finials were added and made larger to fill the openings.
Edges were welded to uprights.
Railings were painted and reinstalled.
8
3. Stone facing on abutments
Case Study #2
9
How Stone Facing Issue Was Resolved
Case Study #2
Missing stones were replaced with matching stones.
Entire abutments were tuckpointed, with color to match existing.
All surfaces were gently cleaned to remove moss and dirt.
10
4. Lion Statues
Case Study #2
11
How Lion Statue Issue Was Resolved
Case Study #2
110 year old statues were in good condition with minimal graffiti.
Cleaning used a gentle process with water and light power wash.
Digital 3D image will be prepared in near future.
12
Lessons Learned/Conclusions Rehabilitated bridge is part of beloved, historic park.
Bridge and lion statues are enduring symbols of a celebrated Milwaukee landmark.
Cooperation and collaboration between all parties lead to an extremely successful, award-winning project.
Case Study #2
13