P r o c e s s of r e g i s t r a t i o n of B o i l e r / E c o n o m i s e r
Application along with fees
and documents
Fix date of inspection
Prescribed fees as Per Indian Boiler
Regulation, 1950
Within 7 days of owner intimating the Boiler
been prepared as per Regulation
Inspection of Boilers by
Inspector
Submit report to Deputy Chief
Inspector of Boilers (DCIB)
To be submitted by IB within 7 days of Inspection
Submit report to Chief
Inspector of Boilers(CIB)
Not Satisfactorv
Communicate to the
Owner the reason
Satisfactorv
Registration i.e issue of
Provisional order
Provsional orders for six month pending Steam Test for certification
Assign registry Number
Communicate to owner for engraving/Marking
Engrave/Mark Boiler Number on
Boiler by Owner
Owner intimates Inspector after
Engraving/Marking on Boiler
Page 1 of 6
Checklist
• Application on Letter Head stating Makers number, type of boiler, capacity and heating surface
area
• Boiler/Economiser maker Folder ( e.g. Form II, Form III, Form IV, Form IV-A, Approved Drawings)
• IBR certificates of Mountings And Fittings
• Work Completion Report of steam pipe line, if applicable
• Fees for Registration and Inspection by way of challan
Time Line:
Maximum Number of Days to complete : 30 days
Page 2 of 6
B. R e n e w a l of B o i l e r / E c o n o m l s e r C e r t i f i c a t e
Application with requisite fees
Fix date of inspection
Not Satisfartorv
Satisfactory
Submit certificate to DCIB
Within 7 days of owner intimating the Boiler has
been prepared as per Regulation
Communicate to the Owner the
reason
Obtain permission of CIS for
repairs
Issue repair order
Verification of repairs
y To be submitted by IB within 48 hours of
Inspection
Submit certificate to CIB for
Signature
Issue of Certificate for use of
Boiler
Checklist
• Application on Letter Head stating Boiler registration number
• Fees for Inspection by way of challan
Time Line:
Maximun Number of Days to complete : 15 days
Certificate for one year or Provisional
order for six months pending steam test
Page 3 of 6