Apple Weekly Project Reporting calendar week 19 05/07/2015

Upload: amaranath-medavarapu

Post on 10-Nov-2015

217 views

Category:

Documents


0 download

DESCRIPTION

project

TRANSCRIPT

Apple Weekly Project Reporting calendar week 01 01/08/2015

Apple Weekly Project Reportingcalendar week 1905/07/2015

ACSAUAT started on 4/28 with the accounts teamRegression testing started on 4/28Snapshot CR got approved with minor adjustmentsSchedule an onsite workshop with middleware and SAP teamsRemaining requirements to be delivered by 5/7Other incoming project will influence Apple project05/07/2015Overall Project Statuson schedulein budgetin scope25% over budgetlarge scope changeOverallTimelineResourcesBudgetScopen/a

Key accomplishments last weekPlanned activities that did not occur?Activities for upcoming weekRisks/Problems/Help wantedWeek:Continue Sprint 6 Development (Regression Bug fixes / ABP Requirements)ACSA Tools Feature complete 04/24/2015Account Team Demo went well 04/28/2015Regression Testing ongoing 04/27/2015 04/30/2015 Germany Dev Kickoff / US Germany sync up call Continue working on ABP Requirements / Backlog creation

Planned ACSA Tools Feature complete postponed to 04/24/2015 due to environment issues / bugs Account team demo postponed to 4/27/2015 due to environment issues / bugsRegression Testing postponed to 04/27/2015 04/30/2015 due to environment issues / bugs

Content Freeze starting 5/6/2015 Regression bug fix ends 5/6/2015Targeted Regression 5/7/2015UAT Environment Prep 5/8/2015Formal UAT Signoff by Frontend IT (PM / QA) 5/8/2015Account Team Signoff (5/12/2015)

Missing Wireframes for ABP - Potential waste of resources / Potential Rework All remaining ABP Requirements by 5/1/2015 Onboard additional 3 Developers by 4/6/2015

05/07/2015Frontend ITon schedulein budgetin scope25% over budgetlarge scope changeOverallTimelineResourcesBudgetScopeKey accomplishments last weekPlanned activities that did not occur?Activities for upcoming weekRisks/Problems/Help wantedWeek:Copy Neptune (Tested for high load)Change Neptune to AppleOne Project is openPMG is again part of the project

n/a

Get the mapping from Frank?Start developer testSharepoint access for Christian

05/07/2015Middlewareon schedulein budgetin scope25% over budgetlarge scope changeOverallTimelineResourcesBudgetScopeKey accomplishments last weekPlanned activities that did not occur?Activities for upcoming weekRisks/Problems/Help wantedWeek:Completed ACSA testing for APPLE CareInterface s for ABP are not ready as per the planARS/NSO Design and requirements gathering

New September timeline for SAP Brazil migration ABP Workpackages are not completed as per project plan05/07/2015SAPon schedulein budgetin scope25% over budgetlarge scope changeOverallTimelineResourcesBudgetScopeKey accomplishments last weekPlanned activities that did not occur?Activities for upcoming weekRisks/Problems/Help wantedWeek:n/an/a

Help needed: Forecast from account management for upcoming projects.

03/05/2015Design Phaseon schedulein budgetin scope25% over budgetlarge scope changeOverallTimelineResourcesBudgetScopeFeedback from AM regarding NSO

Key accomplishments last weekPlanned activities that did not occur?Activities for upcoming weekRisks/Problems/Help wantedWeek: