Apple Weekly Project Reportingcalendar week 1704/23/2015
Key accomplishments last week
Planned activities that did not occur?
Activities for upcoming week
Risks/Problems/Help wanted
Week:
ABP design session to validate user flow, to identify risks/gaps, etc.
Continuing to prepare ABP Sprint 1 and 2 Finished all items of ACSA Sprint 5 (last sprint) Account Demo of ACSA on 04/22 Onboarding new contractors Onboarding new QA resources
ABP project kick off ABP epic creation/estimation for available
business requirements Start ABP development
Content work is done by IT team instead of account/business team
Identify and onboard Designer Onboard 3 Developers by 4/6/2015 Other incoming project might influence Apple project Snapshot approval Design/architectural questions/items from ABP design session
04/23/2015
Overall Project Status- on schedule- in budget- in scope
- <10% off schedule - <25% over budget - slight scope change
- >10% off schedule- >25% over budget- large scope change
Overall Timeline Resources Budget Scope
n/a
Key accomplishments last week
Planned activities that did not occur?
Activities for upcoming week
Risks/Problems/Help wanted
Week:
Sprint 5 Development in progress / ABP Project Setup in progress
Initial discussion between Dev Leads in US and Germany in regards to project setup and next steps
Continue ABP requirement review and clarification
ACSA Admin Tools Go-Live planned and scheduled 05/18/2015
n/a
Continue and finish Sprint 5 Development.
Planned ACSA Tools Feature complete 04/17/2015
Schedule ABP design session to clarify ABP requirements 04/17/2015
Scheduled ABP kickoff meeting 04/20/2015
Account team demo prep 04/21/2015
Planned Regression 04/20/2015 – 04/23/2015
ABP Backlog creation
Sprint 5 Demo and Retrospective for Team Avengers and Aperture
Sprint 6 planning
Necessary unexpected PBI’s added mid Sprint – Risk Potential delay in Go-Live
Onboard additional 3 Developers by 4/6/2015
Onboard Resource for Support / Operational Activities
QA ramp up / challenges with new automation process (Currently mitigated by manual testing)
New incoming projects / Estimate Requests / Change Requests taking away Dev Resources - Risk Potential Delay in Go-Live
Missing Wireframes for ABP / Snapshot Approval
Major UI rework approved and added mid sprint – Risk potential UI bugs
04/23/2015
Frontend IT- on schedule- in budget- in scope
- <10% off schedule - <25% over budget - slight scope change
- >10% off schedule- >25% over budget- large scope change
Overall Timeline Resources Budget Scope
Key accomplishments last week
Planned activities that did not occur?
Activities for upcoming week
Risks/Problems/Help wanted
Week:
EDI Order throttle solution testing- 12k+ orders submitted
Christian Bittner identified as responsible BizTalk person
Christian has provide a quote for ABP BizTalk implementation
n/a
Finalizing testing order throttle solution Go for ABP Biztalk implementation Move “Apple Shop” to integration box
“GTLBMLBIZ0020”
Sharepoint access for Christian (alstechnology account to be created)
Pending approval from the Control Board for Seeburger to Biztalk migration for ACSA and change to Biztalk for ABP
04/23/2015
Middleware- on schedule- in budget- in scope
- <10% off schedule - <25% over budget - slight scope change
- >10% off schedule- >25% over budget- large scope change
Overall Timeline Resources Budget Scope
Key accomplishments last week
Planned activities that did not occur?
Activities for upcoming week
Risks/Problems/Help wanted
Week:
Quote for RAE migration from seeburger to Biztalk
n/a
ARS/NSO Design and requirements gathering (upcoming activity, not immediately)
Quote for Seeburger to Biztalk migration
New September timeline for SAP Brazil migration
04/23/2015
SAP- on schedule- in budget- in scope
- <10% off schedule - <25% over budget - slight scope change
- >10% off schedule- >25% over budget- large scope change
Overall Timeline Resources Budget Scope