apple weekly project reporting 04.23.2015

5
Apple Weekly Project Reporting calendar week 17 04/23/2015

Upload: amaranath-medavarapu

Post on 15-Jan-2016

18 views

Category:

Documents


0 download

DESCRIPTION

status

TRANSCRIPT

Page 1: Apple Weekly Project Reporting 04.23.2015

Apple Weekly Project Reportingcalendar week 1704/23/2015

Page 2: Apple Weekly Project Reporting 04.23.2015

Key accomplishments last week

Planned activities that did not occur?

Activities for upcoming week

Risks/Problems/Help wanted

Week:

ABP design session to validate user flow, to identify risks/gaps, etc.

Continuing to prepare ABP Sprint 1 and 2 Finished all items of ACSA Sprint 5 (last sprint) Account Demo of ACSA on 04/22 Onboarding new contractors Onboarding new QA resources

ABP project kick off ABP epic creation/estimation for available

business requirements Start ABP development

Content work is done by IT team instead of account/business team

Identify and onboard Designer Onboard 3 Developers by 4/6/2015 Other incoming project might influence Apple project Snapshot approval Design/architectural questions/items from ABP design session

04/23/2015

Overall Project Status- on schedule- in budget- in scope

- <10% off schedule - <25% over budget - slight scope change

- >10% off schedule- >25% over budget- large scope change

Overall Timeline Resources Budget Scope

n/a

Page 3: Apple Weekly Project Reporting 04.23.2015

Key accomplishments last week

Planned activities that did not occur?

Activities for upcoming week

Risks/Problems/Help wanted

Week:

Sprint 5 Development in progress / ABP Project Setup in progress

Initial discussion between Dev Leads in US and Germany in regards to project setup and next steps

Continue ABP requirement review and clarification

ACSA Admin Tools Go-Live planned and scheduled 05/18/2015

n/a

Continue and finish Sprint 5 Development.

Planned ACSA Tools Feature complete 04/17/2015

Schedule ABP design session to clarify ABP requirements 04/17/2015

Scheduled ABP kickoff meeting 04/20/2015

Account team demo prep 04/21/2015

Planned Regression 04/20/2015 – 04/23/2015

ABP Backlog creation

Sprint 5 Demo and Retrospective for Team Avengers and Aperture

Sprint 6 planning

Necessary unexpected PBI’s added mid Sprint – Risk Potential delay in Go-Live

Onboard additional 3 Developers by 4/6/2015

Onboard Resource for Support / Operational Activities

QA ramp up / challenges with new automation process (Currently mitigated by manual testing)

New incoming projects / Estimate Requests / Change Requests taking away Dev Resources - Risk Potential Delay in Go-Live

Missing Wireframes for ABP / Snapshot Approval

Major UI rework approved and added mid sprint – Risk potential UI bugs

04/23/2015

Frontend IT- on schedule- in budget- in scope

- <10% off schedule - <25% over budget - slight scope change

- >10% off schedule- >25% over budget- large scope change

Overall Timeline Resources Budget Scope

Page 4: Apple Weekly Project Reporting 04.23.2015

Key accomplishments last week

Planned activities that did not occur?

Activities for upcoming week

Risks/Problems/Help wanted

Week:

EDI Order throttle solution testing- 12k+ orders submitted

Christian Bittner identified as responsible BizTalk person

Christian has provide a quote for ABP BizTalk implementation

n/a

Finalizing testing order throttle solution Go for ABP Biztalk implementation Move “Apple Shop” to integration box

“GTLBMLBIZ0020”

Sharepoint access for Christian (alstechnology account to be created)

Pending approval from the Control Board for Seeburger to Biztalk migration for ACSA and change to Biztalk for ABP

04/23/2015

Middleware- on schedule- in budget- in scope

- <10% off schedule - <25% over budget - slight scope change

- >10% off schedule- >25% over budget- large scope change

Overall Timeline Resources Budget Scope

Page 5: Apple Weekly Project Reporting 04.23.2015

Key accomplishments last week

Planned activities that did not occur?

Activities for upcoming week

Risks/Problems/Help wanted

Week:

Quote for RAE migration from seeburger to Biztalk

n/a

ARS/NSO Design and requirements gathering (upcoming activity, not immediately)

Quote for Seeburger to Biztalk migration

New September timeline for SAP Brazil migration

04/23/2015

SAP- on schedule- in budget- in scope

- <10% off schedule - <25% over budget - slight scope change

- >10% off schedule- >25% over budget- large scope change

Overall Timeline Resources Budget Scope