appendix q fiona harte regional earthworks report... · 2018. 6. 24. · environmental effects of...
TRANSCRIPT
-
APPENDIX Q
FIONA HARTE
REGIONAL EARTHWORKS REPORT
-
Consent: LUC60318373 (BUN60318372) America’s Cup 1
Technical Memo – Specialist Unit
To: Nicola Broadbent – Team Leader, North West Resource Consenting Unit, Auckland
Council
From: Fiona Harte – Specialist (Earth and Stream Works), Specialist Unit, Auckland Council
Date: 13 June 2018
1.0 APPLICATION DESCRIPTION
Application and property details
Applicant's Name: Panuku Development Auckland
Application numbers: LUC60318373 (BUN60318372)
Activity types: Earthworks
Purpose description: Earthworks to facilitate the construction of infrastructure
associated with the America’s Cup 36.
Site addresses:
11-99 Brigham Street, Brigham Street (legal road), Hamer Street(legal road), Jellicoe Street (legal road), 1 Brigham Street, 9Brigham Street, 8-34 Brigham Street / 8 Hamer Street, 36-54Brigham Street, 51E Brigham Street, 58 Brigham Street, 90Brigham Street, 49-63 Jellicoe Street, 65-75 Jellicoe Street / 2-8,12 Hamer Street, 37-55 Madden Street, North Wharf Section 5,Section 3 and Section 1, 141-177 Halsey Street, 155-161 HalseyStreet, Te Wero Island, 220 Quay Street, 149-159 & 161-173Quay Street, 149 Quay Street.
2.0 PROPOSAL, SITE AND LOCALITY DESCRIPTION
2.1 Proposal relevant to this consent only
2.2 This report provides an earthworks review / assessment of the America’s Cup resource
consent application, which I refer to in this memo as the “AC36 Application” or simply the
“application”. It is noted that the specific contaminated land aspects of the proposal that
are closely related to the earthworks are addressed in separate reports from Rob van de
Munckhof and Marija Jukic for the Council.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 2
2.3 The applicant is seeking resource consent for earthworks in relation to the construction of
infrastructure associated with the America’s Cup 36 event. A full description of the proposal
is provided in the Assessment of Environmental Effects (AEE) for the application prepared by
UNIO Environmental Limited (UNIO) and dated 13 April 2018.
2.4 The following application documents are particularly relevant to this report and the
earthworks consent required:
(a) Reports:
- ‘America’s Cup Wynyard Hobson Application for Resource Consent: Assessment of
Environmental Effects’, prepared by UNIO and dated 13 April 2018 (AEE)
(Application Document 4);
- The applicant’s Proposed Conditions of Consent (Application Document 7);
- ‘America’s Cup Physical Infrastructure Technical Report for Resource Consent
Application, Wynyard Hobson’, prepared by Beca Ltd and dated 11 April 2018 (the
Infrastructure Report, Application Document 9);
- ‘Outline Erosion and Sediment Control Plan’, prepared by Beca Ltd and dated 11
April 2018 (Appendix C to the Infrastructure Report);
- ‘America’s Cup Preliminary Site Investigation (Contamination) for Resource Consent
Application, Wynyard Hobson’, prepared by Beca Ltd and dated 11 April 2018 (the
PSI Report, Application Document 27);
- A draft ‘Remediation Action Plan’, prepared by Beca Ltd and dated April 2018 (Appendix
F to the PSI Report).
(b) Plans:
- ‘America’s Cup, Engineering Concept Drawings for Resource Consent Application, Wynyard Hobson’, Application Documents DS5.1, DS5.2 and DS5.3, drawing package prepared by Beca Ltd and dated April 2018.
2.2 In brief:
(a) Earthworks are required over approximately 25,400m2.1
(b) Earthworks will involve excavations for ground improvements and construction of new
services, piling, creation of building platforms and re-paving.
2.5 Site Description
2.6 The applicant provides a description of the site in section 8 of the AEE. The proposed earthworks
are to be undertaken in Wynyard Quarter, Auckland City Centre. The area is flat and almost
completely impervious apart from areas which have been recently upgraded to create public
1 Area of earthworks as provided in the Outline Erosion and Sediment Control Plan.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 3
space and infrastructure upgrades such as rain gardens. The area is well known for soil
contamination due to historical land use and reclamation of the costal marine area. The
immediate receiving environment is the adjacent coastal marine area (CMA) and the existing
stormwater network. The stormwater network discharges directly into the CMA being the
Waitemata Harbour and ultimately the Hauraki Gulf.
3.0 REASON FOR CONSENT – EARTHWORKS
3.1 Regional land use consent for earthworks is required under the provisions of Chapter E.11
Land Disturbance – Regional, of the Auckland Unitary Plan (Operative in Part) (AUP). Activity
(A9) in Activity table E.11.4.1 provides that general earthworks in the City Centre Zone and
on roads, greater than 2,500m2 within the Sediment Control Protection Area2 are to be
assessed as a restricted discretionary activity. The AC36 Application requires earthworks
over an area of 25,400m2. As such, the application requires regional consent with the
proposed earthworks assessed as restricted discretionary activity.
4.0 TECHNICAL ASSESSMENT OF EFFECTS
Assessment of effects on the environment
4.1 The applicant identifies and assesses the effects of the proposed earthworks activities on the
environment that are likely to arise and any mitigating factors in section 10.17 of the AEE
(section entitled “Land Disturbance & Contamination Effects”). The potential adverse
environmental effects of the proposed earthworks activities are in relation to potential
sediment discharges.
Earthworks
4.2 In order to manage the effects related to the potential sediment discharges associated with
the earthworks, the applicant has provided an Infrastructure Report including an “Outline
Erosion and Sediment Control Plan” (Outline ESCP) at Appendix C, and a draft “Remediation
Action Plan” (draft RAP) as Appendix F to the PSI Report. The applicant’s reports propose a
variety of controls to be established across the site to minimise the potential for erosion to
occur and for sediment to be discharged during the earthworks operation. The applicant has
also proposed to undertake the earthworks in accordance with Auckland Council’s Erosion
and Sediment Control Guide for Land Disturbing Activities in the Auckland Region, June 2016,
Guideline Document 2016/005 (GD05).
4.3 The Outline ESCP in conjunction with the draft RAP provides an overview of the erosion and
sediment controls to be used during the proposed earthworks. The applicant has not
provided a set of detailed erosion and sediment control drawings to complement the plans
and has advised that detailed drawings in the form of final site specific Erosion and Sediment
Control Plans, showing the location and specifications of controls for the respective
earthworks areas, will be submitted by the nominated earthworks contractor following issue
of consents and prior to earthworks commencing. Due to the contaminated nature of soils
2 With reference to Note 1 below E11.4.1 Activity table in the AUP, the site is located in a Sediment Control Protection
Area being within 100m landward of the coastal marine area.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 4
within the proposed earthworks area, standard control of potentially sediment laden water
prior to its discharge will not suffice when dealing with contaminants such as hydrocarbons.
The applicant has proposed where possible to allow dirty water to infiltrate back into the
excavation area or be pumped to a dedicated sump within the site where it will be managed
as discussed below. Where this cannot be achieved, dewatering to the sewer has been
outlined as a possibility in the Outline ESCP and the draft RAP. Retention devices (i.e., a
dedicated sump, treatment tank or similar) and flocculation of these devices has also been
proposed as a possibility to reduce total suspended solids (TSS) to meet the relevant water
quality standards to discharge to the sewer network. The applicant has proposed that
specific details of the chosen dewatering and treatment methodology be included in the
contractor’s site specific Erosion and Sediment Control Plans. As these details (including
copies of any relevant trade waste permits) are required prior to earthworks commencing, a
requirement for final details regarding dewatering and water treatment has been included
below. This is to ensure the final methodology is appropriate and consistent with the options
noted in the Outline ESCP and draft RAP. If trade waste permits cannot be obtained to
discharge to the sewer, intensive onsite treatment of runoff generated during excavations
will need to be undertaken and it is expected that details of this treatment would be
included in the site specific erosion and sediment control plans.
4.4 It is recommended that a final set of erosion and sediment control plans (including site
drawings) be provided to Council for approval prior to earthworks commencing. This is to
ensure that the plans detail the specifications and location of controls to be used and will
also ensure that the plan has been drafted in conjunction with the final Remediation Action
Plan for contaminated soil to avoid discrepancies. Further recommendations within this
assessment can also be incorporated into the finalised plans for completeness.
4.5 In the Outline ESCP, stabilised construction entrances are proposed to ensure the entrances
to the site at Hamer Street and Brigham Street, reducing the risk of construction vehicles
tracking sediment out onto the public roads. The applicant identifies that wheel washes may
be used at the stabilised construction entrances to further prevent tracking onto the public
roads. The wheel washes are proposed to be drained or pumped to an approved sediment
retention device or dewatering device and the applicant has proposed that details in this
regard will be included in the contractor’s site specific Erosion and Sediment Control Plans
prior to earthworks commencing. Based on the nature and type of earthworks proposed, I
consider this to be an acceptable method to minimise the potential sediment related effects
of the earthworks.
4.6 Controlling the amount of clean water entering the site with clean water diversion bunds has
also been proposed. This will ensure surface water is directed around the respective
earthworks areas to prevent clean water from entering the area and contributing to the
amount of water that needs to be treated on the site. The applicant has envisaged that the
existing road kerb and gutter will act as clean water diversion for many of the required
earthworks areas and that specific concrete/asphalt bunds will be required in some
locations. Concrete and asphalt bunds are also proposed where conveyance of dirty water is
proposed to ensure dirty water does not flow offsite and can be directed to the excavations
-
Consent: LUC60318373 (BUN60318372) America’s Cup 5
or dewatered to an approved treatment device.
4.7 The applicant has proposed to protect adjacent stormwater cesspits with geotextile filter
cloth and silt socks. Generally speaking, contaminants bind to soil and the filtration provided
by the cesspit protection may aid in reducing some contaminants from being discharged into
the stormwater system, however, it is highlighted that this is a contingency measure only
and that the focus should be on avoidance of sediment discharges, in particular to the
reticulated system. In some scenarios, capping of the existing stormwater infrastructure may
be more appropriate, especially where existing cesspits are located within the areas
proposed to be excavated. It is recommended that any cesspits proposed to be protected or
blocked off during the works be detailed in the finalised set of erosion and sediment control
plans.
4.8 The need for stockpiling of soil has been identified within the Outline ESCP. Stockpiles are
proposed to be covered with polythene and bunded to prevent ingress of rain water which
could lead to erosion. The applicant has acknowledged that any proposed stockpile areas will
be detailed in the contractor’s site specific Erosion and Sediment Control Plan and will align
with the procedures to be detailed in the final Remediation Action Plan. The draft RAP also
notes that stockpiles are to be minimised and kept to a height no greater than 3m and shall
not be placed in an area where runoff cannot be controlled. I concur with the applicant’s
proposed measures in this regard.
4.9 A seasonal restriction has not been recommended for the proposed earthworks due to the
nature and type of earthworks to be undertaken. The sites are flat and although some of the
proposed earthworks areas border the CMA, the earthworks to be undertaken are generally
below ground excavations where dirty water has limited potential to flow directly to the
CMA. Water can be contained within excavations where necessary and soak back into the
ground or be pumped to a containment and treatment device before being discharged.
4.10 Progressive stabilisation is proposed to limit the exposed area of earthworks at any one
time, however no detail has been provided in this regard. The applicant has stated that they
will endeavour to complete the earthworks during the Auckland Council earthworks season
(1st April – 30th April) however have also stated that works may occur outside of these
months, during winter. Although a seasonal restriction has not been recommended (as
above), it is recommended that details of staging and open areas be included in the
Construction Environmental Management Plan for Council approval, prior to works
commencing.
4.11 There are some works proposed at the interface between land and CMA. This includes
ground improvement and shoreline remediation. The applicant has envisioned that the use
of a coffer dam or temporary seawall will be used to retain any sediment laden runoff from
land within a dry area. I concur with this approach and note that a coffer dam was
successfully used to create a dry working area and avoid sediment discharges while
constructing a stormwater outfall into the CMA off Halsey Street during the Halsey and Daldy
Street upgrade and infrastructure works. It is recommended that final details and
specifications of the cofferdam/ temporary seawall be provided for Council approval prior to
-
Consent: LUC60318373 (BUN60318372) America’s Cup 6
works commencing.
Conclusion
4.12 Although detailed erosion and sediment control drawings have not been provided with the
application, the detail within the Outline ESCP and draft RAP is deemed sufficient to
demonstrate that the applicant can appropriately manage the effects relating to potential
sediment discharges resulting from the proposed earthworks.
4.13 For the proposed earthworks, provided the erosion and sediment controls are installed,
constructed and maintained in accordance with the AEE, supporting documentation, the
recommendations above and any additional requirements as deemed necessary by the
guidance outlined in GD05, I consider the resulting effects on the environment from
sediment discharges during the earthworks will be appropriately managed.
4.14 I accept the applicant’s proposed consent conditions in Application Document 7 relating to
erosion and sediment control including the incorporation of finalised site-specific Erosion
and Sediment Control Plans to be provided within an overarching Construction
Environmental Management Plan. However, I have suggested some minor amendments to
the applicant’s proposed wording. These have been incorporated into my recommendations
in section 6 below.
4.15 Affected parties
4.16 Due to the nature of the effects considered in this memo, and for the reasons set out above,
it is considered that no persons are adversely affected by the proposed earthworks activities.
5.0 STATUTORY CONSIDERATIONS
Objectives and Policies of the AUP
5.1 The relevant regional land disturbance objectives and policies are found in sections E11.2
and E11.3 of the AUP (Objectives 1-3 and Policies 1-8). These objectives and policies seek to
ensure that earthworks are undertaken in a manner that protects people and the
environment, does not exacerbate natural hazards and minimises sediment generation.
Other Statutory documents
5.2 The following statutory documents are considered relevant to the planner’s assessment of
the application:
AUP Regional Policy Statement (AUP RPS)
a. Chapter B7, Natural Resources of the AUP RPS is considered relevant as the objectives
and policies in section B7.4 seek to ensure the progressive improvement of degraded
coastal water, the quality of good or excellent coastal water is maintained and that
any adverse effects are avoided, remedied or mitigated.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 7
New Zealand Coastal Policy Statement 2010 (NZCPS)
b. As the ultimate receiving environment of the proposed activity is the CMA and the
Hauraki Gulf, the NZCPS is considered relevant to this application. The NZCPS seeks to
protect the coastal environment and its special values and states that adverse effects
of development should, as far as practicable, be avoided. As potential discharges from
the development will ultimately reach the CMA, this statutory document is considered
relevant.
Hauraki Gulf Marine Park Act (HGMPA) 2000
c. As the ultimate receiving environment includes the Hauraki Gulf, the HGMPA is
considered relevant to this application. The HGMPA seeks to recognise the national
significance and life-supporting capacity of the Hauraki Gulf along with enhancing its
natural, historic and physical resources where appropriate.
The assessment of objectives and policies is a matter for the Council’s reporting planner,
however I have read the provisions referred to above, and from a technical perspective,
subject to implementation of the recommended conditions of consent, I consider the
proposal to be consistent with them.
6.0 RECOMMENDATION AND CONDITIONS
Adequacy of information
6.1 The above assessment is based on the information submitted as part of the AC36
Application. It is considered that the information submitted is sufficient to enable the
consideration of the above matters on an informed basis:
a. The level of information provides a reasonable understanding of the nature and scope
of the proposed activities as they relate to the relevant planning documents.
b. The extent and scale of any potential adverse effects on the environment are able to
be understood and assessed, however detail around the final works approach is
incomplete and further recommendations have been made to bridge the information
gaps.
Recommendation
6.2 The assessment in this memo does not identify any reasons to withhold consent, and the
aspects of the proposal considered by this memo relating to earthworks could be granted
consent, subject to recommended conditions, for the following reasons:
a. The sensitivity of the receiving environment to the potential adverse effects of
sediment discharge will not be compromised given the expected level of discharge,
suitable control technologies and appropriate on-site management techniques.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 8
b. Subject to the imposition of suitable consent conditions, it is considered that the
potential effects on the receiving environment will be appropriately managed.
Conditions
6.3 The applicant has provided a set of proposed conditions that are consistent with Council’s
standard earthworks conditions and have subsequently been incorporated into my
recommended conditions below. However, some minor wording changes have been made
to ensure the conditions are clear and enforceable and also to incorporate the addition of
extra detail for the site-specific Erosion and Sediment Control Plan requirements. It is also
considered appropriate to recommend consent conditions regarding progressive
stabilisation during the works and permanent stabilisation of the site on completion or
abandonment of works. The inclusion of these conditions is consistent with similar
earthworks operations for which consent has been granted in the Auckland Region, and the
wider site, and will ensure that the effects of the proposed earthworks will be appropriately
managed.
General conditions
6.4 I recommenced that a number of general conditions are imposed covering:
• Access to the site (I note that proposed condition 9 addresses this); and
• Works undertaken in accordance with the plans (I note that proposed condition 13
requires the construction of physical infrastructure to be undertaken “in general
accordance with the drawings provided in Document DS5”. I suggest that this be
amended to read “in accordance with”. I understand that the Council’s planner,
Nicola Broadbent, is recommending a number of other improvements to this
condition).
6.5 The following conditions or amendments to conditions are recommended:
Pre-commencement meeting
6.5 I recommend the following minor amendments to proposed condition 40:
Within 15 working days prior to Commencement of Construction, the Consent Holder shall arrange and conduct a pre-start meeting that:
a) Is located on the subject site;
b) Is scheduled not less than five days before the anticipated Commencement of Construction;
c) Includes Council Compliance Monitoring representatives;
d) Includes representation from the contractors who will undertake the works; and
e) Includes an invitation to Mana Whenua.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 9
6.6 A minor amendment to the advice note following condition 44 is proposed as follows:
Advice Note: To arrange the pre-start meeting please contact the Team Leader –
Central Monitoring Compliance Monitoring - Central to arrange this meeting on
[email protected], or 09 301 01 01. The conditions of consent
should be discussed at this meeting. All additional information required by the
Council should be provided no later than 2 days prior to the meeting.
Construction Environmental Management Plan
6.7 I recommend that condition 32(b) be amended as follows:
b) Construction works programming, including:
(i) an outline construction programme;
(ii) confirmation of the proposed staging and sequence of construction;
(iii) the open area of earthworks throughout construction;
(iv) the indicative timing of the submission of Site Specific Erosion and Sediment Control Plans to be submitted to Council for approval for each stage.
Erosion and Sediment Control
6.8 The applicant’s proposed erosion and sediment control conditions are split between
conditions 70 to 74 (controls generally) and conditions 75 to 84 (relating to erosion and
sediment control plans). There is some repetition and overlap. In my amended set of
conditions below, I have endeavoured to minimise repetition. Specifically:
a. The applicant’s proposed condition 70 is very similar to condition 83. I have
merged the two conditions as a new condition 77.
b. Similarly, condition 71 is very similar to condition 82, and I again
recommend merging the two conditions as a new condition 76.
c. I have relocated conditions 72 and 73 relating to inspection / maintenance
and progressive stabilisation to conditions 78 and 79 respectively.
d. I have relocated condition 74 (concerning notification of completion of
earthworks).
6.9 The proposed set of re-organised and amended conditions is set out below:
Erosion and Sediment Control
70. During construction, the Consent Holder shall take all practicable
measures to minimise erosion and prevent the discharge of sediment
beyond the boundaries of the site of earthworks on land. This includes
mailto:[email protected]
-
Consent: LUC60318373 (BUN60318372) America’s Cup 10
deposition of mud or other debris on any road or footpath beyond the
boundary of the site resulting from earthworks activity on the subject site.
In the event that such deposition does occur, it shall immediately be
removed.
71. Erosion and sediment control measures shall be implemented throughout
land-based Construction Works. They shall be constructed and maintained
so as to operate and perform in accordance with Auckland Council
GD2016/005: Erosion Sediment Control Guide for Land Disturbing
Activities in the Auckland Region and any amendments to this document,
except where a higher standard is detailed in the conditions below in
which case the higher standard shall apply.
Advice note: Standard E26.7.5.1 of the Auckland Unitary Plan (Operative in Part)
outlines the Accidental Discovery Rule in relation to Land Disturbance for
infrastructure. Except as authorised by this consent and provided for in Condition 45,
this standard must be complied with at all times, and should these requirements be
unable to be complied with, a further resource consent may be required.
7570. At least 10 working days pPrior to Commencement of Construction for each
stage of the Project, an Site-Specific Erosion and Sediment Control Plan
(SSESCP), shall be prepared by a suitably qualified person in general
accordance with Auckland Council Guideline GD05, Erosion and Sediment
Control Guide for Land Disturbing Activities in the Auckland Region. The
SSESCP shall be submitted to the Team Leader Compliance Monitoring -
Central for certification in terms of the matters in Condition 72. No
earthworks activity on the subject site shall commence until written
approval for the relevant SSESCP is received from the Team Leader
Compliance Monitoring - Central.
7671. The purpose of the SSESCP is to set out the measures to be implemented
during construction to minimise erosion and the discharge of sediment
beyond the boundaries of the site.
7772. The SSESCPs shall include, but not be limited to, the following information
as appropriate to the scale, location and type of earthworks:
a) Drawings showing location and quantities of earthworks and any mudcrete placement on land, contour information, catchment boundaries and erosion and sediment controls (location, dimensions, capacity);
b) Supporting calculations for erosion and sediment controls;
c) Catchment boundaries and contour information;
d) Reference to details of measures for contaminated land;
e) Details of construction methods to be employed, including timing and duration;
-
Consent: LUC60318373 (BUN60318372) America’s Cup 11
f) Dewatering and pumping methodology (if applicable);
g) Details of the proposed water treatment measures, devices and appropriate trade waste permits (if applicable);
h) Specific location of stockpile areas (if applicable);
i) Detail of adjacent cesspits to be protected or capped (if applicable);
j) Final details and specifications of the coffer dam or temporary seawall;
k) A programme for managing exposed areas, including progressive stabilisation considerations;
l) Roles and responsibilities under the SSESCP and identification of those holding roles including the suitably qualified person; and
m) Monitoring, maintenance and record-keeping requirements.
7873. Prior to any earthworks commencing, a certificate signed by an
appropriately qualified and experienced person shall be submitted to the
Team Leader Compliance Monitoring - Central, to certify that the erosion
and sediment controls have been constructed in accordance with the
approved SSESCPs erosion and sediment control plans and Auckland
Council Guideline GD05.
7974. Certified controls shall include but not be limited to the dewatering and
treatment devices, stabilised construction entrances, cesspit protection and
clean and dirty water diversions. The certification for these and any
subsequent measures shall be supplied immediately upon completion of
construction of those measures. Information supplied if applicable, shall
include:
ma) Contributing catchment area;
b) Treatment capabilities and capacities;
nc) Shape and capacity of structure (dimensions of structure);
od) Position of inlets/outlets;
pe) Stabilisation of the structure; and
qf) A statement regarding the appropriateness of the device with respect to Auckland Council Guideline GD05.
80. At least 10 working days prior to commencement of construction
associated with each stage of the Project, the consent holder shall submit
the ESCP to the Team Leader – Central Monitoring for certification in terms
of the matters in Condition 77. No earthworks activity on the subject site
shall commence until written certification for the relevant ESCP is received
from the Team Leader – Central Monitoring.
8175. The operational effectiveness and efficiency of all erosion and sediment
control measures required by the ESCP SSESCPs shall be maintained
throughout the duration of earthworks activity, or until the site is
-
Consent: LUC60318373 (BUN60318372) America’s Cup 12
permanently stabilised against erosion.
8276. Erosion and sediment control measures shall be constructed and
maintained in general accordance with Auckland Council Guideline GD05
GD2016/005: Erosion Sediment Control Guide for Land Disturbing Activities
in the Auckland Region and any amendments to this document, except
where a higher standard is detailed in the conditions of this consent or in
the SSESCP documents referred to the ESCP, in which case the higher
standard shall apply.
8377. Earthworks shall be managed to avoid There shall be no deposition of
earth, mud, dirt or other debris on any road or footpath beyond the subject
site resulting from earthworks activity on the subject site. In the event that
any deposition does occur, it shall immediately be removed. In no instance
shall roads or footpaths be washed down with water without appropriate
erosion and sediment control measures in place to prevent contamination
of the stormwater drainage system, watercourses or receiving waters.
Advice Note: In order to prevent sediment laden water entering waterways from the
road, the following methods may be adopted to prevent or address discharges should
they occur:
• Provision of a stabilised entry and exit(s) point for vehicles;
• Provision of wheel wash facilities;
• Ceasing of vehicle movement until materials are removed;
• Cleaning of road surfaces using street-sweepers;
• Silt and sediment traps; and
• Catchpit protection.
In no circumstances should the washing of deposited materials into drains be advised
or otherwise condoned.
It is recommended that the consent holder discusses any potential measures with the
Council’s monitoring officer who may be able to provide further guidance on the most
appropriate approach to take. Please contact the Team Leader – Central Monitoring
Compliance Monitoring - Central for more details. Alternatively, please refer to
Auckland Council Guideline GD05, Erosion and Sediment Control Guide for Land
Disturbing Activities in the Auckland Region.
7278. The sediment and erosion controls at the site of the works shall be
constructed and maintained in accordance with the approved SSESCP and
shall be inspected on a regular basis and within 24 hours of each rainstorm
-
Consent: LUC60318373 (BUN60318372) America’s Cup 13
event that is likely to impair the function or performance of the controls. A
record shall be kept of the date, time and any maintenance undertaken in
association with this condition, and shall be forwarded to the Team Leader
– Central Monitoring Compliance Monitoring - Central on request.
7379. The site shall be progressively stabilised against erosion at all stages of the
earthwork activity and shall be sequenced to minimise the discharge of
sediment to surface water. The site shall be stabilised against erosion as
soon as practicable, and in a progressive manner, as earthworks are
finished over the sites. Areas of earthworks not actively worked for a period
of two weeks shall be stabilised until such time as further earthworks occur
in a specific area.
Advice Note: Earthworks shall be progressively stabilised against erosion during all
stages of the earthwork activity. Interim stabilisation measures may include:
• The use of waterproof covers, geotextiles, or mulching;
• Top-soiling and grassing of otherwise bare areas of earth; and
• Aggregate or vegetative cover that has obtained a density of more than 80% of
a normal pasture sward.
It is recommended that the consent holder discusses any potential measures with the
Council’s monitoring officer who may be able to provide further guidance on the most
appropriate approach to take. Please contact the Team Leader – Central Monitoring
Compliance Monitoring - Central for more details. Alternatively, please refer to
Auckland Council Guideline GD05, Erosion and Sediment Control Guide for Land
Disturbing Activities in the Auckland Region.
80. Upon completion or abandonment of earthworks on the subject site all
areas of bare earth shall be permanently stabilised against erosion to the
satisfaction of the Team Leader Compliance Monitoring - Central.
Advice Note: Should the earthworks be completed or abandoned, bare areas of earth
shall be permanently stabilised against erosion. Measures may include:
• The use of mulching;
• Top-soiling, grassing and mulching of otherwise bare areas of earth;
• Aggregate or vegetative cover that has obtained a density of more than 80%
of a normal pasture sward; and
The on-going monitoring of these measures is the responsibility of the consent
holder. It is recommended that the consent holder discusses any potential measures
with the Council’s monitoring officer who will guide you on the most appropriate
-
Consent: LUC60318373 (BUN60318372) America’s Cup 14
approach to take. Please contact the Team Leader – Central Monitoring Compliance
Monitoring - Central for more details. Alternatively, please refer to Auckland Council
Guideline GD05, Erosion and Sediment Control Guide for Land Disturbing Activities in
the Auckland Region.
84. The Consent Holder shall carry out monitoring in accordance with the ESCP
and shall keep records detailing:
a) The monitoring undertaken;
b) The erosion and sediment controls that required maintenance;
c) The time when the maintenance was completed; and
d) Areas of non-compliance with the erosion and sediment control
monitoring plan (if any) and the reasons for the non-compliance.
This information shall be made available to the Team Leader – Central
Monitoring upon request.
7482. Written nNotification shall be given to the Team Leader – Central
Monitoring Compliance Monitoring - Central within 20 working days of
completion of earthworks.
-
Consent: LUC60318373 (BUN60318372) America’s Cup 15
7.0 REVIEW
Memo prepared by:
Fiona Harte
Specialist - Earth and Stream works
Specialist Unit, Resource Consents
Date: 13 June 2018
Matt Byrne
Earthworks, Streamworks & Sediment Management Consultant
Specialist Unit, Resource Consents
Date: 13 June 2018
Technical memo reviewed and approved for release by:
David Hampson
Team Leader – Earth, Streams and Trees
Specialist Unit, Resource Consents
Date: 13 June 2018