appendix - ii - welcome to...

9
Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects listed under item 8 of the Schedule) CHECK LIST OF ENVIRONMENTAL IMPACTS (Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and submit along with proposed environmental management plan & monitoring programme) 1. LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity) 1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed landuse must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans. The land use of project area is Integrated Township area. Proposed development is in line with Development Plan of Pune. Following documents are attached as supporting documents. 1. Master plan layout attached as Annexure I \1.2 List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs, etc. Details Area Unit Details Area m 2 1) Total plot area 5,41,012.8 m 2 2) Garden Area 27,335 m 2 3) Play Ground Area 41,003 m 2 4) FSI area 5,46,704 m 2 5) Non-FSI area 6,43,63 m 2 Total construction area 11,90,339 m 2 Water consumption Total water consumption 5753 m 3 /day Energy requirement Maximum demand 13125 kW Connected load 43130 kW Parking details Car 9924 No. Scooter 12886 No. Cycle 9149 No. Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 1

Upload: phungnhu

Post on 14-May-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

APPENDIX - II (See paragraph 6)

FORM-1 A

(only for construction projects listed under item 8 of the Schedule)

CHECK LIST OF ENVIRONMENTAL IMPACTS

(Project proponents are required to provide full information and wherever necessary attach explanatory notes with the Form and

submit along with proposed environmental management plan & monitoring programme)

1. LAND ENVIRONMENT

(Attach panoramic view of the project site and the vicinity)

1.1 Will the existing land use get significantly altered from the project that is not consistent with the surroundings? (Proposed landuse must conform to the approved Master Plan / Development Plan of the area. Change of land use if any and the statutory approval from the competent authority be submitted). Attach Maps of (i) site location, (ii) surrounding features of the proposed site (within 500 meters) and (iii) the site (indicating levels & contours) to appropriate scales. If not available attach only conceptual plans.

The land use of project area is Integrated Township area. Proposed development is in line with Development Plan of Pune. Following documents are attached as supporting documents.

1. Master plan layout attached as Annexure I

\1.2 List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs, etc.

Details Area Unit

Details Area m2

1) Total plot area 5,41,012.8

m2

2) Garden Area 27,335 m2

3) Play Ground Area 41,003 m2

4) FSI area 5,46,704 m2

5) Non-FSI area 6,43,63

m2

Total construction area 11,90,339 m2

Water consumption

Total water consumption 5753 m3/day

Energy requirement

Maximum demand 13125 kW

Connected load 43130 kW

Parking details

Car 9924 No.

Scooter 12886 No.

Cycle 9149 No.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 1

Page 2: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

Connectivity Railway: Pune Railway Station: 16.5 km from the Project site. Airway: Lohgaon Airport : 24 km from the Project site. Roadway: Pune-Mumbai Highway : 3.5 km. Annexure III

1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to the proposed site? (Such as open spaces, community facilities, details of the existing land use, disturbance to the local ecology).

The project being a well-planned activity will result in organized open spaces and green areas. The biodiversity in the area will increase due to proposed green areas. Community cum recreational facilities will be developed hence no stress on the existing facility is anticipated.

1.4. Will there be any significant land disturbance resulting in erosion, subsidence & instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc may be given).

The main reasons for erosion are overexploitation of groundwater, instable slopes, landslides etc. The proposed construction will involve cutting and filling operations. The project will involve construction of roads and development of green areas, which would reduce the chances of erosion and subsidence. Subsidence is not anticipated as ground water would not be used as a source of water supply. As per seismic-zoning map of India, the project site falls under zone III. Structural design requirements will be as per zone III.

1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a contour map showing the natural drainage near the proposed project site)

The proposed development is planned in such a manner that it will not alter the existing drainage pattern of the area.

1.6 What are the quantities of earthwork involved in the construction activity- cutting, filling, reclamation etc. (Give details of the quantities of earthwork involved, transport of fill materials from outside the site, etc.)

The project area will require minor cutting and filling work. Excavation for foundation and road construction work is prominent activity. The debris and excavated soil removed would be used as filling material for levelling and for road construction.

1.7 Give details regarding water supply, waste handling etc during the construction period.

Supply Source: Water supply during construction phase will be from water tanker Storage: Water for construction will be stored in a tank constructed temporarily at site Waste handling: Sanitation facilities like toilet blocks and bathrooms will be provide for the construction workers and site staff and the sewage generated will be collected and treated in a septic tank. It will be then disposed off into existing sewer line through closed pipeline.

1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity)

No wet lands and low-lying areas on the site.

1.9 Whether construction debris & waste during construction cause health hazard? (Give quantities of various types of wastes generated during construction including the construction labour and the means of disposal)

No health hazard. Minor quantity of construction debris will be generated which will be sent out side. Construction waste will be used for road and as fill material for levelling and road, pathway construction.

2. WATER ENVIRONMENT 2.1 Give the total quantity of water

requirement for the proposed project with the breakup of requirements for various uses. How will the water requirement met? State the sources & quantities and furnish a water balance statement.

Detailed water utilization chart Enclosed as Annexure IV

2.2 What is the capacity (dependable flow or yield) of the proposed source of water?

The proposed water demand will be met from Varve Grampanchayat

2.3 What is the quality of water required, in case, the supply is not from a municipal source? (Provide physical, chemical, biological characteristics with class of water quality)

Sr. Parameters Unit Drinking water

1. pH - 6.5-8.7

2. Colour (unit on Platinum Cobalt scale)

- 5

3. Odour - Unobjectionable

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 22

Page 3: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

4. Turbidity NTU 5

5. Total Hardness (as CaCO3 )

mg/l 300

6. Chlorides mg/l 250

7. Sulphates mg/l 200

8. Fluorides mg/l 1

9. Nitrates mg/l 45

10. Lead mg/l 0.05

11. Arsenic mg/l 0.01

2.4 How much of the water requirement can be met from the recycling of treated wastewater? (Give the details of quantities, sources and usage)

Treated water from Sewage treatment plant will be used for flushing in toilet and gardening purpose.

Total sewage generated 4691 m3/day

Total STP capacity 4925 m3/day

Treated water recycled for flushing 1831 m3/day

Treated water recycled for gardening 541 m3/day

Treated water recycled for vehicle washing 40 m3/day

Sludge generation 469 m3/day

Excess treated water 2084 m3/day

2.5 Will there be diversion of water from other users? (Please assess the impacts of the project on other existing uses and quantities of consumption)

No diversion is anticipated.

2.6 What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity)

The total sewage of about 5000 m3/day will be generated from both Residential & commercial building. We will be provided two separate STP to The composition of waste water is given in the table indicating the quality of raw waste water before treatment

Parameters Values Units

pH 7-8 mg/l

BOD 250-300 mg/l

COD 450-600 mg/l

O & G/ ABS 10-20 mg/l

TSS 100-200 mg/l

Mitigation measures: Domestic Effluent will be treated in the Sewage Treatment plant of capcity 5000 m3/day.

2.7 Give details of the water requirements met from water harvesting? Furnish details of the facilities created.

Recharge pits with bore wells will be provided for rainwater harvesting within project area.

2.8. What would be the impact of the land use changes occurring due to the proposed project on the runoff characteristics (quantitative as well as qualitative) of the area in the post construction phase on a long term basis? Would it aggravate the problems of flooding or water logging in any way?

The project will have proper storm water drainage facility as per Strom Water Drain Remarks by concerned authority. So there will be no problem of water logging due to this project.

2.9 What are the impacts of the proposal on the ground water? (Will there be tapping of ground water; give the details of ground water table, recharging capacity, and approvals obtained from competent authority, if any)

In the proposed development there will be no tapping of groundwater. Water demand for the construction shall be met from Tanker water whereas during operational phase will be met from Irrigation Department.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 33

Page 4: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

2.10 What precautions/measures are taken to prevent the run-off from construction activities polluting land & aquifers? (Give details of quantities and the measures taken to avoid the adverse impacts)

To prevent degradation and maintain the quality of water source, adequate control measures have been proposed to check the surface run-off, as well as uncontrolled flow of water into any water body.

• Avoid excavation during monsoon season. • Rainwater harvesting can serve as a solution to water problem in worst case scenario.

Following methods can increase efficiency of rainwater harvesting and recharging groundwater.

• Catch drainage all along the periphery of plot to prevent surface runoff.

• Reduce and filter surface runoff. • Use vegetated swales and depressions to reduce runoff.

2.11 How is the storm water from within the site managed?(State the provisions made to avoid flooding of the area, details of the drainage facilities provided along with a site layout indication contour levels)

During rainy season, after the rainfall some part of the rainwater percolates into the ground and joins ground water table, a part is retained as soil moisture, some part is lost in evapotranspiration and the remaining part overflows as storm water runoff. The quantity of runoff reaching the sewers or drains is considerable as compared with sanitary sewage The project will have proper storm water drainage facility as per Strom Water Drain Remarks by concerned authority. So there will be no problem of water logging due to this project.

2.12 Will the deployment of construction labourers particularly in the peak period lead to unsanitary conditions around the project site (Justify with proper explanation)

No, the deployment of construction labourers will not lead to any unsanitary condition. The construction labourers will be provided with temporary shelter shades within the project premises. Labour camp will be provided with drinking water and sanitary facilities. Housekeeping will be done in labour camp on regular basis.

2.13 What on-site facilities are provided for the collection, treatment & safe disposal of sewage? (Give details of the quantities of wastewater generation, treatment capacities with technology & facilities for recycling and disposal)

The Sewage Treatment Plant (STP) is designed to treat the raw waste water generated from project STP details are attached as Annexure V

2.14 Give details of dual plumbing system if treated waste used is used for flushing of toilets or any other use.

Not Applicable

3. VEGETATION 3.1 Is there any threat of the project to the

biodiversity? (Give a description of the local ecosystem with it’s unique features, if any)

There is no sensitive ecosystem present at site that will be disturbed by the project, as existing land use in surrounding area is Residential

3.2 Will the construction involve extensive clearing or modification of vegetation? (Provide a detailed account of the trees & vegetation affected by the project)

No. There is very scanty vegetation of trees, grasses and shrubs along with very common fauna prevalent elsewhere in the area.

3.3 What are the measures proposed to be taken to minimize the likely impacts on important site features (Give details of proposal for tree plantation, landscaping, creation of water bodies etc along with a layout plan to an appropriate scale)

About 90,230 m2 areas are provided for the development of Green belt for both sale & rehab building. The green belt will be developed for control of pollution and aesthetic view of the complex

4. FAUNA 4.1 Is there likely to be any displacement of

fauna- both terrestrial and aquatic or creation of barriers for their movement? Provide the details.

No. The proposed site and its surroundings do not support any habitat for any group of wild animals

4.2 Any direct or indirect impacts on the avifauna of the area? Provide details.

No. There will be no direct or indirect impact on the avifauna of the area.

4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna

Since the proposed project would not have any adverse impact on fauna hence mitigation measure not relevant

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 44

Page 5: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

5. AIR ENVIRONMENT 5.1 Will the project increase atmospheric

concentration of gases & result in heat islands? (Give details of background air quality levels with predicted values based on dispersion models taking into account the increased traffic generation as a result of the proposed constructions)

The Project will result in negligible increase in the atmospheric concentrations of gases due to D.G. operations (backup power only) and the increased traffic. The proposed activity will not result in the formation of any heat islands, as it does not involve any significant change in the land use pattern or the concreting of areas.

5.2 What are the impacts on generation of dust, smoke, odorous fumes or other hazardous gases? Give details in relation to all the meteorological parameters.

Diesel generator sets operated for back-up power supply are identified as the only major sources of gaseous and particulate emission. Impact of vehicular is not significant. SO2 , SPM, NOX

and CO emissions are expected due to fuel combustion in generator sets.

5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of the present level of transport infrastructure and measures proposed for improvement including the traffic management at the entry & exit to the project site.

Car 9924 No.

Scooter 12886 No.

Cycle 9149 No.

5.4 Provide details of the movement patterns with internal roads, bicycle tracks, pedestrian pathways, footpaths etc., with areas under each category.

Internal roads, footpaths/ pedestrian pathways have been planned within the residential project.

5.5 Will there be significant increase in traffic noise & vibrations? Give details of the sources and the measures proposed for mitigation of the above.

Considering the addition of vehicles due to the proposed project with the existing roads and vehicles plying on them, there will be marginal increase in the noise levels but will not result in an impact.

5.6 What will be the impact of DG sets & other equipment on noise levels & vibration in & ambient air quality around the project site? Provide details.

DG set will be used in construction and operation phase only in case of power failure. The DG Sets shall be as per the guide lines laid down by EPR for specific noise emission standards. Measures shall be taken for reduction of noise by using acoustic enclosures. Noise emissions are expected from various construction equipment and machinery but will not result in an impact.

6. AESTHETICS 6.1 Will the proposed constructions in any way

result in the obstruction of a view, scenic amenity or landscapes? Are these considerations taken into account by the proponents?

The proposed land use of the site would be mainly residential and commercial. The proposed development will not result in obstruction of view, scenic amenity or landscape. However, the buildings will be planned in such a way that the organised open areas and landscaped areas are at the centre so that all can enjoy the green areas.

6.2 Will there be any adverse impacts from new constructions on the existing structures? What are the considerations taken into account?

Internal roads, footpaths/ pedestrian pathways have been planned within the proposed township.

6.3 Whether there are any local considerations of urban form & urban design influencing the design criteria? They may be explicitly spelt out.

The Project has been designed as per the department of town planning, Government of Maharashtra.

6.4 Are there any anthropological or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered.

No anthropological or archaeological sites or artefacts are found near the site area.

7. SOCIO-ECONOMIC ASPECTS 7.1 Will the proposal result in any changes to

the demographic structure of local population? Provide the details.

No. Majority of the labour will be recruited locally and only minimal skilled workers would be from outside, which is anticipated to be very small and will not alter the existing demographic profile of the area.

7.2 Give details of the existing social infrastructure around the proposed project.

The Project comes in Residential area and has all basic infrastructural facilities as schools, medical establishments, shops, etc.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 55

Page 6: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

7.3 Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?

No. The Project will have positive impact on local communities. Employment opportunities for skilled and unskilled workers will be provided within project area.

8. BUILDING MATERIALS 8.1 May involve the use of building materials

with high-embodied energy. Are the construction materials produced with energy efficient processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency)

The buildings will have Sewage Treatment Plant, Rainwater harvesting systems, Solar hot water system, Solar lighting in common areas and RG.

8.2 Transport and handling of materials during construction may result in pollution, noise & public nuisance. What measures are taken to minimize the impacts?

Adequate mitigation measures will be adopted. Construction equipment with idling control technologies will be used. Regular maintenance of the equipment’s will be carried out. The construction activities will be carried out during the daytime only. The workers exposed to high noise generating would be provided with earplugs earmuffs. As per Environmental Management Plan.

8.3 Are recycled materials used in roads and structures? State the extent of savings achieved?

Fly ash in cement concrete. Typically 20-25 % of fly ash is substituted in cement.

8.4 Give details of the methods of collection, segregation & disposal of the garbage generated during the operation phases of the project.

The bio-degradable and non-bio degradable waste will be segregated at source of waste generation. Solid waste generated: 15,218 kg/day

9. ENERGY CONSERVATION 9.1 Give details of the power requirements,

source of supply, backup source etc. What is the energy consumption assumed per square foot of built-up area? How have you tried to minimize energy consumption?

Source of power supply: MSEDCL DG Set will be provided as emergency backup.

Residential & Commercial 13125 kW

9.2 What type of, and capacity of, power back- up to you plan to provide?

DG Set will be provided as emergency backup for lighting in common areas, one lift per building and fire pump in each building.

9.3 What are the characteristics of the glass you plan to use? Provide specifications of its characteristics related to both short wave and long wave radiation?

Single glazed with light tented glass we will be provided for residential project.

9.4 What passive solar architectural features are being used in the building? Illustrate the applications made in the proposed project.

The building structure will be designed in such a way that solar water heating can be utilised maximum for day time.

9.5 Does the layout of streets & buildings maximise the potential for solar energy devices? Have you considered the use of street lighting, emergency lighting and solar hot water systems for use in the building complex? Substantiate with details.

We will be provided hot water systems and solar lights.

9.6 Is shading effectively used to reduce cooling/heating loads? What principles have been used to maximize the shading of Walls on the East and the West and the Roof? How much energy saving has been effected?

Yes. Shading has been effectively used to reduce the cooling loads.

9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical systems? Provide technical details. Provide details of the transformers and motor efficiencies, lighting intensity and air- conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.

Yes rooms will be so dimensioned that effective air conditioning can be carried out. Public areas will be cooled by natural ventilation. The design of the building will be such that maximum use of natural ventilation can be achieved. The walls, roofs and openings will be so designed that influx of heat is minimum.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 66

Page 7: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

9.8. What are the likely effects of the building activity in altering the micro-climates? Provide a self assessment on the likely impacts of the proposed construction on creation of heat island & inversion effects?

Heat emission from the proposed construction can be from the following sources: Heat absorbed from the concrete structures, heat generated from equipments/ appliances, and due to increased population in the proposed development. However the heat generated will not be significant and will be dissipated in the lush greens and open areas provided within. Hence it can be concluded that the heat island effect shall not be a concern for the proposed project.

9.9. What are the thermal characteristics of the building envelope? (a) roof; (b) external walls; and (c) fenestration? Give details of the material used and the U-values or the R values of the individual components.

U value in Watts/hr/m2/ C

Roof 0.409 Watts/hr/m2/

Wall 0.352 Watts/hr/m2/

9.10 What precautions & safety measures are proposed against fire hazards? Furnish details of emergency plans.

The fire fighting system shall compromise of hydrant system and portable extinguishers. Smoke detectors will be provided along with manual call points. External yard hydrants shall be installed around all buildings in the complex in galvanized steel fire hose cabinet (weather proof). All external yard hydrants shall be at one meter height from finished ground level as per National Building Code. External fire hydrants shall be located such that no portion of any building is more than 40 m from a hydrant, and the external hydrants are not vulnerable to mechanical or vehicular damage.

9.11 If you are using glass as wall material provides details and specifications including emissivity and thermal characteristics.

Not Applicable

9.12 What is the rate of air infiltration into the building? Provide details of how you are mitigating the effects of infiltration.

The following measures will be adopted to mitigate the effects of infiltration: • Aluminium windows with rubber gasket, so that the

windows are sealed, will be provided. • Summer cross section ventilation will be maximum.

9.13 To what extent the non-conventional energy technologies are utilised in the overall energy consumption? Provide details of the renewable energy technologies used.

Non-conventional energy system will be provided.

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 77

Page 8: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

Master Plan

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 22

Page 9: APPENDIX - II - Welcome to Environmentenvironmentclearance.nic.in/writereaddata/online/EC/08042017UH4MOR... · APPENDIX - II (See paragraph 6) FORM-1 A (only for construction projects

Application form for Environmental Clearance Project Name: Kaleidoscope Integrated Township project at Bhugaon, Pune

Ministry of Environment & Forests, New Delhi. Prior Environmental Clearance Notification 14.09.2006 310