appendix d- geotechnical.pdf
TRANSCRIPT
20153715.001A/SAL15R12470 Page i of v January 15, 2015 © 2015 Kleinfelder
GEOTECHNICAL INVESTIGATION MONTEREY-SALINAS TRANSIT DISTRICT OPERATIONS AND MAINTENANCE FACILITY 1 RYAN RANCH ROAD MONTEREY, CALIFORNIA KLF PROJECT #20153715.001A
JANUARY 15, 2015
Copyright 2015 Kleinfelder
All Rights Reserved
ONLY THE CLIENT OR ITS DESIGNATED REPRESENTATIVES MAY USE THIS DOCUMENT AND ONLY FOR THE SPECIFIC PROJECT FOR WHICH THIS REPORT WAS PREPARED.
20153715.001A/SAL15R12470 Page ii of v January 15, 2015 © 2015 Kleinfelder
40 Clark Street, Unit J, Salinas, CA 93907 p | 831.755.7900 f | 831.755.7909
January 15, 2015 Project No. 20153715.001A AECOM 2101 Webster Street, Suite 1900 Oakland, California 94612 Attention: Mr. Rob McKie SUBJECT: Geotechnical Engineering Investigation for the Proposed Monterey-
Salinas Transit District Operations and Maintenance Facility Expansion in Monterey, California
Dear Mr. McKie: We are pleased to submit our geotechnical investigation report for the proposed Monterey Salinas Transit District Operations and Maintenance Facility Expansion to be located at 1 Ryan Ranch Road in Monterey, California. The accompanying report provides the results of our field investigation, laboratory testing, and engineering analyses. Geotechnical design recommendations are presented for site preparation, grading, engineered fill, surface drainage, utility trench backfill, foundations, retaining walls and seismic design parameters. In addition, we have provided the results of the percolation testing which was performed at the site. The primary geotechnical considerations at this site are the presence of moderately expansive near surface soils on portions of the site, collapse potential of saturated on-site soils used as engineered fill, erosion of cut and fill slopes, low subgrade support strength of on-site soils in the bus parking areas, and lower permeability of soils containing clayey fines and/or decomposed sandstone at depth. The moderately expansive soils will require a layer of “non-expansive” fill, or a thickened rock section under the proposed building additions and exterior concrete slabs-on-grade. The collapse potential of saturated on-site soils used as engineered fill will limit the use of the onsite soils for use as fill when subjected to a combination of high loads and potential saturation. Buried stormwater management systems will need to be located in areas that will not be subjected to high ground pressures that exist in areas such as foundation zones and to a lesser extent the bus parking areas. Such improvements will need to be located in light weight vehicle parking areas and landscape areas. Cut and fill slopes will need to protected from erosion. Additionally, animal burrows in the existing slopes could result in piping failures downslope of the buried stormwater management system. This will need to be mitigated by grading or site selection for the system. Low subgrade support strength of on-site soils in the bus parking areas will result in a slight increase in the asphalt concrete and baserock sections recommended for flexible pavements, and a slight increase in the baserock section for Portland cement concrete pavements. Finally, the lower permeability of deeper on-site soils containing clayey fines and/or
20153715.001A/SAL15R12470 Page iii of v January 15, 2015 © 2015 Kleinfelder
KLEINFELDER 40 Clark Street, Unit J, Salinas, CA 93907 p | 831.755.7900 f | 831.755.7909
decomposed sandstone will limit the total embedment depth of the buried stormwater management system. These items are discussed in the report. Based on the results of our investigation and from a geotechnical standpoint, we judge that the proposed improvements may be developed as planned provided the recommendations in the attached report including appendices are incorporated into the design and construction of the project. As noted in our report, Kleinfelder should be retained to review pre-final project plans and specifications prior to the start of construction, and to observe and test during earthwork and foundation construction. This will allow us to compare conditions exposed during construction with those encountered during our investigation and to present supplemental recommendations if warranted by different site conditions. We appreciate the opportunity of providing our services to you on this project. If any questions should arise regarding the interpretation of the contents of this report, please contact us at 831.755. 7900. Sincerely, KLEINFELDER, INC. Robert Hasseler, CE 58488 Brian O’Neill, PE, GE 2516 Project Engineer Principal Geotechnical Engineer Jeff Richmond, CEG 2425 Project Professional
20153715.001A/SAL15R12470 Page iv of v January 15, 2015 © 2015 Kleinfelder
GEOTECHNICAL INVESTIGATION MONTEREY-SALINAS TRANSIT DISTRICT
OPERATIONS AND MAINTENANCE FACILITY 1 RYAN RANCH ROAD
MONTEREY, CALIFORNIA
Table of Contents
1. INTRODUCTION ................................................................................................................ 1 1.1 PROJECT DESCRIPTION ......................................................................................... 1 1.2 PURPOSE AND SCOPE OF SERVICES ................................................................... 2
2. SITE INVESTIGATION ....................................................................................................... 3 2.1 SITE DESCRIPTION ................................................................................................. 3 2.2 SITE RECONNAISSANCE ........................................................................................ 3 2.3 SUBSURFACE INVESTIGATION .............................................................................. 5 2.4 PERCOLATION TESTING ......................................................................................... 5 2.5 GEOTECHNICAL LABORATORY TESTING ............................................................. 6 2.6 CORROSION POTENTIAL TESTING ........................................................................ 6 2.7 SUBSURFACE CONDITIONS ................................................................................... 7
3. GEOLOGY AND SEISMIC DESIGN .................................................................................. 8 3.1 REGIONAL GEOLOGY ............................................................................................. 8 3.2 SITE GEOLOGY ........................................................................................................ 9 3.3 FAULTING AND SEISMICITY .................................................................................... 9 3.4 SEISMIC DESIGN CRITERIA .................................................................................. 11 3.5 LIQUEFACTION POTENTIAL AND DYNAMIC COMPACTION ................................ 12
4. DISCUSSION AND CONCLUSIONS ............................................................................... 13 4.1 EARTHWORK ......................................................................................................... 13
4.1.1 Site Clearing and Stripping ......................................................................... 13 4.1.2 Grading and Subgrade Preparation ............................................................ 14 4.1.3 Concrete Slabs-on-Grade ........................................................................... 15 4.1.4 Material for Engineered Fill ......................................................................... 15 4.1.5 Fill Placement and Compaction .................................................................. 16 4.1.6 Excavations and Utility Trench Backfill ........................................................ 17 4.1.7 Surface Drainage ........................................................................................ 18 4.1.8 Seepage Control ......................................................................................... 19
4.1.8.1 Surface Infiltration Features ........................................................19 4.1.8.2 Buried Storm Water Management Systems ................................20
4.1.9 Wet Weather Construction .......................................................................... 20 4.1.10 Construction Observation ........................................................................... 21
4.2 BUILDING FOUNDATIONS AND SETTLEMENT ..................................................... 21 4.2.1 Shallow Footing Foundations ...................................................................... 21 4.2.2 Cast-In Drilled-Hole Pile Foundations (Drilled Piers) ................................... 23
4.3 RETAINING STRUCTURES .................................................................................... 26 4.4 VEHICLE PAVEMENTS .......................................................................................... 28
4.4.1 Flexible Asphalt Pavements ........................................................................ 28 4.4.2 Rigid Concrete Pavements ......................................................................... 30
4.5 PERCOLATION CHARACTERISTICS OF IN-SITU SOILS ...................................... 31
5. LIMITATIONS .................................................................................................................. 33
6. REFERENCES ................................................................................................................. 37
20153715.001A/SAL15R12470 Page v of v January 15, 2015 © 2015 Kleinfelder
GEOTECHNICAL INVESTIGATION MONTEREY-SALINAS TRANSIT DISTRICT
OPERATIONS AND MAINTENANCE FACILITY 1 RYAN RANCH ROAD
MONTEREY, CALIFORNIA
Table of Contents (Continued)
PLATES Plate 1 Site Vicinity Map Plate 2 Site Plan Plate 3 Proposed Improvements APPENDICES Appendix A Plate A-1 Graphics Key Plate A-2 Soil Description Key Plate A-3 to A-11 Boring Logs (B-1 to B-9) Appendix B Percolation Testing Results Appendix C Laboratory Testing Results Plate C-1 Laboratory Test Results Summary Plate C-2 Sieve Analysis Test Results Plate C-3 Atterberg Limits Test Results Plate C-4 Direct Shear Test Results Plate C-5 One Dimensional Swell Test Results Plates C-6 and C-7 R-Value Test Results Appendix D Corrosion Testing Laboratory Results Appendix E Summary of Compaction Recommendations Appendix F GBA Information Sheet
20153715.001A/SAL15R12470 Page 1 of 37 January 15, 2015 © 2015 Kleinfelder
GEOTECHNICAL INVESTIGATION MONTEREY-SALINAS TRANSIT DISTRICT
OPERATIONS AND MAINTENANCE FACILITY 1 RYAN RANCH ROAD
MONTEREY, CALIFORNIA
1. INTRODUCTION
This report presents the results of our geotechnical investigation for the proposed
Monterey Salinas Transit District Operations and Maintenance Facility Expansion to be
located at 1 Ryan Ranch Road in Monterey, California. The approximate location of the
project is shown on the Site Vicinity Map, Plate 1. The locations of our borings and
percolation tests are shown on the Site Plan, Plate 2. Proposed improvements are
shown on Plate 3. This geotechnical investigation was performed for AECOM and
Monterey Salinas Transit District.
The conclusions and recommendations presented in this report are based on the
subsurface soil conditions encountered at the locations of our exploration, and the
provisions and requirements outlined in the Limitations section of this report. The
findings, conclusions and recommendations presented herein should not be
extrapolated to other areas or be used for other projects without our review.
1.1 PROJECT DESCRIPTION
We understand that the project consists of an overhaul of the existing Monterey Salinas
Transit District Operations and Maintenance Facility. The improvements will include new
additions and renovations to the existing site buildings, bus wash renovation, and
enlargement of the existing fuel canopy, grading, pavements, retaining walls, on-site
storm water management and new buried utilities.
The new additions are anticipated to be tall one-story lightweight structures with
concrete slab-on-grade floors and conventional spread footing foundations. Specific
details regarding structure loading are not known at this time. It is anticipated that the
retaining walls will be supported on deepened conventional footing foundations or cast
in drilled hole piles (i.e. drilled piers). Canopy foundations would be either conventional
spread footings or pier foundations.
20153715.001A/SAL15R12470 Page 2 of 37 January 15, 2015 © 2015 Kleinfelder
1.2 PURPOSE AND SCOPE OF SERVICES
The purpose of this geotechnical investigation was to evaluate subsurface soil
conditions at the site of the proposed improvements; and to provide geotechnical
recommendations pertaining to earthwork and the foundation aspects of the project.
The scope of services performed for this geotechnical investigation consisted of a site
reconnaissance, subsurface exploration, laboratory testing, engineering analysis of field
and laboratory data, and preparation of this report. Percolation testing was also
performed as part of this investigation. The data obtained and analyses performed were
for the purpose of providing design and construction recommendations for site
preparation and grading, utility trench excavation and backfilling, building and canopy
foundations, retaining walls, and site drainage.
Environmental services such as evaluation and chemical analysis of the soil and
groundwater for hazardous materials were not included in our scope of services.
20153715.001A/SAL15R12470 Page 3 of 37 January 15, 2015 © 2015 Kleinfelder
2. SITE INVESTIGATION
2.1 SITE DESCRIPTION
The project site is located at 1 Ryan Ranch Road in Monterey, California. The location
of the site is shown on the Site Vicinity Map, Plate 1, in the Appendix. The site is
bounded to the west by Canyon Del Rey Road, to the south by Ryan Ranch Road, to
the north by Del Rey Gardens Drive and a parking lot (not part of the project site) to the
northeast, and to the east by undeveloped land. Site access is to the southeast towards
Ryan Ranch Road.
The irregularly shaped project site contains several buildings, a bus wash and fuel area,
conventional asphalt concrete parking lots and bus parking, sidewalks and landscaping
areas. The Site Plan, Plate 2 in the Appendix, shows the existing layout of the site and
the location of our exploratory borings and percolation test holes. The upper, developed
portion of the site is relatively level with only mild slopes. Between the upper developed
portion of the site and the bounding roads to the north, west and south, the ground
slopes moderately downwards. These areas are vegetated with trees, brush and grass.
To the northeast the ground slopes moderately upwards towards the bounding parking
lot to the northeast, and has similar vegetation. The eastern project site parking lot is
separated from the main developed part of the site by landscaping. The eastern parking
lot is slightly lower than the rest of the site. The perimeter of the eastern parking lot
consists of vegetated slopes which slope upwards to the north and west and
downwards to the south. Site drainage is generally to the southeast.
2.2 SITE RECONNAISSANCE
A Certified Engineering Geologist from our firm performed a site reconnaissance on
December 3, 2014 to observe the current site conditions. The focus of the
reconnaissance was to identify potential geologic hazards that could impact the
proposed improvements. The following section describes the potential geologic hazards
identified during the reconnaissance.
20153715.001A/SAL15R12470 Page 4 of 37 January 15, 2015 © 2015 Kleinfelder
Multiple landslides, landslide scars and erosion rills were identified on the cut slopes
adjacent to Canyon Del Rey Boulevard, indicating the slopes are currently in an over-
steepened configuration for the poorly to non-indurated deposits exposed. While no
evidence of incipient failure was observed above the hinge point of the slope, future up-
slope migration of the landslides should be anticipated as the slope attempts to reach its
angle of repose. The slopes are beyond the site property boundary, and the most
proximal slope is approximately 15 feet in height and currently 100 feet from the
proposed improvements. As such, future failure migration will not likely impact the site
or proposed improvements.
A broad colluvial swale exists along the southwest property line. A shallow landslide
previously occurred where the drainage intersects the Canyon Del Rey Boulevard cut
slope and is approximately 85 feet from the proposed improvements. The landslide was
previously investigated by Tharp (1993) and Weber-Hayes (1993), but remains largely
unmitigated. The drainage is configured at approximately 6.5H:1V (Horizontal:Vertical)
and has been locally disturbed by subsurface utility installation. While the existing
landslide and colluvial drainage do not necessarily represent a slope stability hazard,
thickened weak and/or porous soil should be anticipated within limits of the drainage.
Existing cut slopes throughout the site configured at 1H:1V exhibit accelerated erosion
and shallow failures, locally. Slopes which expose silty sand deposits appear most
susceptible. The existing slopes and any proposed slopes constructed in a similarly
over-steepened configuration will continue to fail, and require future maintenance and/or
stabilization.
Existing and proposed improvements constructed on or in close proximity to slopes are
susceptible to creep disturbance, particularly during periods of saturation. Disturbance
(settlement, lateral movement) of curb and gutter was noted on the site, particularly
along the south perimeter.
Abundant large animal burrows where observed throughout the slope located west of
the site entrance and directly down slope of percolation test P-2. During periods of
saturation, the burrows could potentially contribute to piping of perched groundwater
and contribute to slope instability in the area.
20153715.001A/SAL15R12470 Page 5 of 37 January 15, 2015 © 2015 Kleinfelder
Provided the recommendations in this report are incorporated into the design and
construction of the proposed improvements at the site, the conditions described above
should not adversely affect the project.
2.3 SUBSURFACE INVESTIGATION
Our field investigation consisted of a site reconnaissance and a subsurface exploration
program. On November 20 and 21, 2014, nine exploratory borings were drilled to
depths of between 5 feet and 30 feet below existing ground surface near the proposed
locations of the new facilities using a truck-mounted drill rig equipped with 8-inch
diameter hollow stem augers. The approximate locations of our borings are shown on
the Site Plan, Plate 2.
The soils encountered in the borings were visually classified in the field, and our
engineering staff recorded a log of each boring. Soil samples were obtained from the
borings by driving either a 2½ inch inside diameter California tube sampler, or a 13/8
inch inside diameter Standard Penetration (SPT) split-spoon sampler up to a depth of
18 inches into the underlying soil with a 140-pound hammer falling 30 inches. The
number of blows required to drive the sampler was recorded for each 6-inch penetration
interval. The borings were backfilled with drilling spoils and were capped with concrete
in pavement areas.
Our field engineering staff made visual classification of the soils encountered in our
exploratory borings in general accordance with the Unified Soil Classification System
(ASTM D2487 and D2488). Keys for the classification of the soil are presented in
Appendix A on the Graphics Key, Plate A-1 and the Soil Description Key, Plate A-2. The
logs of the borings are presented on Plates A-3 to A-11 in Appendix A.
2.4 PERCOLATION TESTING
On November 21, 2014 three percolation tests were completed to evaluate the average
percolation rates of the near-surface soils. The test holes were drilled on November 20
using a truck-mounted drill rig equipped with 8-inch diameter hollow stem augers to a
depth of approximately 15 feet below the existing ground surface. A section of 4-inch
diameter slotted PVC pipe was installed in the bottom 5 feet of each test hole and solid
PVC pipe was installed in the upper 10 feet of each hole. The bottom 6 feet of the hole
was backfilled with gravel and a 12 inch thick bentonite seal was installed above the
20153715.001A/SAL15R12470 Page 6 of 37 January 15, 2015 © 2015 Kleinfelder
gravel. The holes were then pre-saturated by filling the holes with water. The
percolation testing was performed on November 21, 2014 using a 10-minute
measurement interval. The locations of the percolation tests are shown as P-1 to P-3 on
the Site Plan, Plate 2. The results of the percolation testing are included in Appendix B.
2.5 GEOTECHNICAL LABORATORY TESTING
Representative soil samples were obtained from the exploratory borings at selected
depths. The samples were returned to our laboratory for further evaluation and testing.
Laboratory testing of selected soil samples from the borings was conducted to evaluate
the natural moisture content and density, grain size distribution, Atterberg limits, direct
shear strength, one dimensional swell/collapse potential, and R-value. Most of the
laboratory test results are presented on the individual boring logs. A summary of our
laboratory tests results is presented on Plate C-1. The results of the grain size
distribution test are shown on Plate C-2. The results of the Atterberg limits tests are
shown on Plate C-3. The results of the direct shear strength test are shown on Plate C-
4. The results of the one dimensional swell test are shown on Plate C-5, and the results
of the R-Value tests are shown on Plates C-6 and C-7.
2.6 CORROSION POTENTIAL TESTING
A representative near surface soil sample was sent to CERCO Analytical laboratory to
evaluate the potential corrosivity of onsite soils. Laboratory chloride concentration,
sulfate concentration, pH, oxidation reduction potential, and electrical resistivity tests
were performed for the selected soil sample. The results of the tests and a summary
letter from CERCO Analytical are attached in Appendix D. If fill materials will be
imported to the project site, similar corrosion potential laboratory testing should be
completed on the imported material.
Our scope of services does not include corrosion engineering and therefore a detailed
analysis of the corrosion test results is not included in this report. A qualified corrosion
engineer should be retained to review the test results and design protective systems
that may be required. Kleinfelder is able to provide those services if requested.
20153715.001A/SAL15R12470 Page 7 of 37 January 15, 2015 © 2015 Kleinfelder
2.7 SUBSURFACE CONDITIONS
Ground cover in the northern parking areas and bus parking areas (B-1 through B-3 and
B-8 and B-9) consisted of about 3½ to 6 inches thickness of asphalt concrete overlying
approximately 3 to 6 inches of aggregate base material. Pavement thickness in the
southern parking lot (B-6) was approximately 3 inches of asphalt concrete over 4 inches
of aggregate base material over silty sand with gravel fill to a depth of about 9 feet
below existing grade. Pavement thickness in the eastern parking lot (B-7) was
approximately 1½ inches of asphalt concrete over 2 inches of aggregate base material.
Boring B-4 was drilled on an asphalt covered fill pad on the west side of the site and
ground cover consisted of approximately 2 inches of asphalt concrete over 6 inches of
aggregate base material over silty sand fill to a depth of about 3½ feet below existing
grade. Boring B-5 was drilled in landscaping and consisted of about 2 inches of
aggregate base material.
Subsurface soils consisted primarily of silty sands and clayey sands with some poorly
graded sands. These soils extended to a depth of at least 30 feet in Borings B-2, B-3
and B-7. In Borings B-1, B-4, B-5 and B-6 the near surface soils overlaid decomposed
to highly weathered weak sandstone, which was encountered at a depth of
approximately 8, 3½, 1½ and 9 feet below existing grade, respectively. The coarse
grained soils underlying the site were typically medium dense to very dense except for
the silty sand fill layer to a depth of about 3½ feet at Boring B-4, which was loose.
Groundwater was not encountered in our borings or percolation test holes. However, it
must be noted that seasonal fluctuations in the groundwater level may occur due to
variations in rainfall, temperature, groundwater withdrawal, and possibly other factors
that were not evident at the time of our investigation. Due to the slow percolation rates
in the clayey sand layers below the silty sand layers in our percolation test holes, there
is a potential for seasonally perched groundwater at various depths.
The above is a general description of the subsurface conditions encountered in our
exploratory borings at the project site. Additional information is provided on the Logs of
Borings in Appendix A. Soil and groundwater conditions can deviate from those
conditions encountered at the boring locations. Should this be revealed during
construction, Kleinfelder should be notified immediately for possible revisions to the
recommendation that follow.
20153715.001A/SAL15R12470 Page 8 of 37 January 15, 2015 © 2015 Kleinfelder
3. GEOLOGY AND SEISMIC DESIGN
3.1 REGIONAL GEOLOGY
The site is located approximately 2.5 miles inland (southeast) of Monterey Bay, within
the Coast Ranges Geomorphic Province of Central California. This Province is
comprised of a discontinuous series of northwest-southeast trending mountain ranges,
ridges, and intervening valleys characterized by complex folding and faulting and the
dominant structural regime in the region. Geologic structure within the Coast Ranges
Province is generally controlled by the San Andreas fault system, which is a major
tectonic transform plate boundary. This right-lateral strike-slip fault system extends from
the Gulf of California in Mexico, to Cape Mendocino in northern California and forms a
portion of the boundary between two tectonic plates. In this portion of the Coast Ranges
Province, the Pacific plate (located west of the transform boundary) moves north
relative to the North American plate (located east of the transform boundary).
Deformation along this plate boundary occurs across a wide zone that is referred to as
the San Andreas fault system.
The site is located within the Salinian Block, which is one of the distinct continental
terranes of the central Coast Ranges. In the region, the Salinian Block is bounded by
the San Andreas fault on the east and the Sur-Nacimiento fault zone on the west (Page,
1966). This basement rock of this block is composed of Cretaceous age (about 140 to
65 million years old) granitic and high-grade metamorphic rocks. Major orogenic
features within the Salinian Block in the vicinity of the site include the Gabilan Range to
the east/northeast, the Sierra de Salinas to the southeast, and the Santa Lucia Range
to the southwest.
Overlying the granitic basement rocks of the Salinian block are Cretaceous and Tertiary
(about 65 to 1.8 million years old), marine and continental sedimentary rocks and
occasional Tertiary volcanic rocks. These Cretaceous and Tertiary age rocks are
typically folded and faulted into a series of generally northwest-southeast trending
blocks, largely as a result of stresses related to movement along the San Andreas fault
system. The inland valleys, including Salinas Valley, are filled with unconsolidated to
semi-consolidated alluvium (stream channel and over-bank deposits) of Quaternary age
(1.8 million years old to current). In the vicinity of the project site, the bedrock is overlain
by Quaternary age terrace deposits, eolian sands, and alluvium.
20153715.001A/SAL15R12470 Page 9 of 37 January 15, 2015 © 2015 Kleinfelder
3.2 SITE GEOLOGY
The geology of the site has been mapped by Dibblee and Minch (2007), Dupre (1990)
and Clark et al. (1997), among others. Dibblee and Minch (2007) map the site as
underlain by Quaternary age, dissected older alluvium. The reference indicates the
Canyon Del Rey Boulevard road cut southwest of the site exposes diatomite bedrock of
the Miocene age (23 to 5.3 million years old) Monterey Formation. Dupre (1990) and
Clark, Dupre and Rosenberg (1997) show the site to be underlain by Quaternary age
(Pleistocene) coastal terrace deposits, described as semi-consolidated, well sorted
marine sand, locally indurated and containing thin discontinuous gravel layers.
Comparable to Dibblee and Minch (2007), Dupre (1990) indicates the road cut exposes
undivided, pre-Quaternary bedrock. Clark et al. (1997) have also mapped the exposure
as Monterey formation diatomite bedrock, described as pale orange to white, punky and
locally silty. The reference indicates the terrace deposits and diatomite are in faulted
contact along the southwestern trace of the Chupines fault.
All three (3) references show the drainage within which Canyon Del Rey Boulevard and
the lower section of Ryan Ranch Road are located as being underlain by Holocene age
(11,000 years old to present). Dupre (1990) characterizes this deposit as highly
susceptible to liquefaction, while the terrace deposits and bedrock underlying the site
are characterized as having very low liquefaction susceptibility.
3.3 FAULTING AND SEISMICITY
According to the California Geological Survey (CGS, 2010), the site is not located within
an Alquist-Priolo Earthquake Fault Zone. The nearest zoned active fault is the creeping
section of the San Andreas fault, located approximately 24.3 miles northeast of the site,
which is capable of producing a maximum earthquake magnitude event of M8.05.
Moderate to major earthquakes generated on the San Andreas fault can be expected to
cause strong ground shaking at the site.
20153715.001A/SAL15R12470 Page 10 of 37 January 15, 2015 © 2015 Kleinfelder
The United States Geological Survey (USGS) Quaternary Fault and Fold Database
(available at: http://earthquake.usgs.gov/hazards/qfaults/map/) identifies several other
faults within the site vicinity. Table 3.1 below identifies the significant faults in the area
and their corresponding parameters. In addition, the database indicates the southwest
trace of the Chupines fault zone (Del Rey Oaks section) transects the site along its
southwest property line. The USGS characterizes this segment of the Chupines fault as
a “Late Quaternary active (rupture/deformation in the last 15,000 years) dextral-reverse
slip fault with generally up-on-north vertical component of displacement.” This segment
of the Chupines fault zone is not considered a potential source for seismic shaking by
the USGS, and has not been zoned as active by the CGS.
Table 3.1
Significant Faults
Fault Name Fault
Length (miles)
Closest Distance to
Site* (miles)
Magnitude of Characteristic Earthquake**
Slip Rate (millimeters
/year)
Monterey Bay-Tularcitos 51.6 1.6 7.3 0.5
Rinconada 118.7 7.3 7.5 1
San Gregorio Connected 109.4 9.7 7.5 5.5
Zayante-Vergales 36.0 19.8 7.0 0.1
San Andreas-SAS+SAP+SAN+SAO
293.3 24.3 8.05 17-24
Calaveras-CN+CC+CS 76.4 29.2 7.0 6-15
Hosgri 106.3 30.8 7.3 2.5
* Closest distance to the potential rupture.
** Moment magnitude: An estimate of an earthquake’s magnitude based on the seismic moment
(measure of an earthquake’s size utilizing rock rigidity, amount of slip, and area of rupture).
According to Petersen et al. (2008), characterization of the San Andreas, San Gregorio
and Calaveras faults are based on the following fault rupture segments and fault rupture
scenarios:
The San Gregorio Connected fault has been characterized by two segments and
three rupture scenarios, plus a floating earthquake. The two segments are San
Gregorio South (SGS) and San Gregorio North (SGN).
20153715.001A/SAL15R12470 Page 11 of 37 January 15, 2015 © 2015 Kleinfelder
The San Andreas Fault has been characterized by four segments and nine
rupture scenarios, plus a floating earthquake. The four segments are Santa Cruz
Mountains (SAS), Peninsula (SAP), North Coast (SAN), and Offshore (SAO).
The Calaveras fault includes three segments and six rupture scenarios, plus a
floating earthquake. The three segments are southern (CS), central (CC), and
northern (CN).
3.4 SEISMIC DESIGN CRITERIA
The table below presents the recommended seismic design parameters for the
proposed development.
Table 3.2 Recommended 2013 CBC (ASCE 7) Seismic Design Parameters
Design Parameter Symbol Recommended
Value
2013 CBC (ASCE 7)
Reference
Site Class -- C Table 20.3-1 (ASCE 7-10)
Mapped Spectral Acceleration for Short Periods
Ss 1.473 g Section 1613.3.1 (1)
Mapped Spectral Acceleration for a 1-Second Period
S1 0.535 g Section 1613.3.1 (2)
Site Coefficient Fa 1.0 Table 1613A.3.3 (1)
Site Coefficient Fv 1.3 Table 1613A.3.3 (2)
MCE* Spectral Response Acceleration for Short Periods
SMS 1.473 g Equation 16A-37
MCE* Spectral Response Acceleration at 1-Second Period
SM1 0.696 g Equation 16A-38
Design Spectral Response Acceleration (5% damped) at Short Periods
SDS 0.982 g Equation 16A-39
Design Spectral Response Acceleration (5% damped) at 1-Second Period
SD1 0.464 g Equation 16A-40
*Maximum Considered Earthquake
20153715.001A/SAL15R12470 Page 12 of 37 January 15, 2015 © 2015 Kleinfelder
3.5 LIQUEFACTION POTENTIAL AND DYNAMIC COMPACTION
Soil liquefaction is a condition where saturated, predominantly granular soils undergo a
substantial loss of strength and potential deformation due to pore pressure increase
resulting from cyclic stress application induced by earthquakes. In the process, the soil
acquires a mobility sufficient to permit both horizontal and vertical movements if the soil
mass is not confined. Soils most susceptible to liquefaction are saturated, loose, clean,
uniformly graded, fine sand deposits.
Near surface coarse grained soils were typically medium dense to very dense overlying
decomposed to highly weathered weak sandstone. No groundwater was encountered to
a depth of 30 feet below existing grade at the time of our subsurface exploration,
although perched groundwater could occur in unpaved or buried stormwater
management systems areas for a brief time after significant rains. Therefore, the
potential for liquefaction of the soils encountered in our borings is judged to be low.
Another type of seismically induced ground failure that can occur as a result of seismic
shaking is dynamic compaction or seismic settlement. Such phenomena typically occur
in unsaturated, loose granular material or uncompacted fill soils. In the event of a major
earthquake in the site vicinity, we estimate that less than ¼ inches of total and
differential settlement could occur as a result of dynamic compaction.
20153715.001A/SAL15R12470 Page 13 of 37 January 15, 2015 © 2015 Kleinfelder
4. DISCUSSION AND CONCLUSIONS
Based upon the data collected during this investigation and the results of our
engineering analysis, it is our opinion the site may be developed as proposed provided
our recommendations are incorporated in the design and construction of the project.
The opinions, conclusions and recommendations presented herein are based on our
field and office studies, the properties of the soils encountered in our borings, and the
results of our laboratory testing program. Geotechnical recommendations for site
preparation, grading, engineered fill, surface drainage, utility trench backfill, foundations,
and retaining walls are presented in the remaining portions of this report, along with the
results of the percolation testing.
4.1 EARTHWORK
The improvements will include new additions and renovations to the existing site
buildings, bus wash renovation, and enlargement of the existing fuel canopy, grading,
pavements, retaining walls, on-site storm water management and new buried utilities.
Earthwork is expected to be limited to that required for site clearing and leveling, cut
and fill slopes, and excavations for footings and drilled piers, the installation of
underground utilities, new fuel areas, and the buried stormwater management system.
Temporary construction slopes (if required) should be formed at no steeper than 1.5:1
(horizontal: vertical). Permanent cut slopes on the northeastern portion of the site
should be cut to no steeper than 1.5:1 (horizontal: vertical). However, we understand
that plans for the proposed improvement to the bus parking area include a 1:1 (H:V) cut
slope above the lot, to a maximum slope height of about 10 feet. As described in report
Section 2.2, cut slopes of 1:1 (H:V) are marginally stable and are expected to require
continuous erosion control and periodic maintenance for surficial sloughing. Fill slopes
should be constructed at 2:1 (Horizontal: Vertical) or flatter.
4.1.1 Site Clearing and Stripping
Prior to the start of construction, obstacles and deleterious material should be removed
from the construction areas. Active utilities to be reused should be carefully located and
protected during site clearing and construction.
20153715.001A/SAL15R12470 Page 14 of 37 January 15, 2015 © 2015 Kleinfelder
All abandoned or underground utilities designated for removal, any concrete slabs on
grade, foundations, and other obstacles and deleterious material encountered should be
removed from the construction areas. Excavations from removal of foundations,
underground utilities or other below ground obstructions should be cleaned of loose soil
and deleterious material, and backfilled with compacted engineered fill compacted to
the requirements given in the “Summary of Compaction Recommendations,” in Exhibit 1
of Appendix E. All clearing and backfill work should be performed under the observation
of a representative from Kleinfelder.
Surface vegetation present at the time of construction should be stripped together with
the organic-laden topsoil. Soils containing more than 3 percent of organic matter by
weight or excessive visible organics as determined by a representative of Kleinfelder
should be considered organic. The actual stripping depth should be determined at the
time of construction. For planning purposes, the average stripping depth may be
assumed to be approximately 3 inches in vegetated areas. Stripped material should be
removed from the site or stockpiled for use in landscaping areas if approved by the
project landscape architect.
4.1.2 Grading and Subgrade Preparation
Upon completion of site clearing and excavations, the exposed soil subgrades should
be properly prepared prior to placement of fill or other construction activities. In areas to
receive engineered fill or concrete slabs on grade, the upper 12 inches of soil should be
scarified, moisture conditioned and compacted as recommended in the “Summary of
Compaction Recommendations,” in Exhibit 1 of Appendix E. For the proposed buildings,
the areas to be processed should include the entire building pads, extending no less
than 5 feet beyond the limits of the buildings and any adjoining sidewalk areas unless
obstructed by improvements to remain. In exterior walkways not adjacent to building
areas, and in pavement areas, subgrade preparation should extend laterally no less
than 2 feet beyond the back of curb, or edge of pavements, and sidewalks unless
obstructed by improvements to remain. After the subgrades are properly prepared, the
areas may be raised to design grades by placement of engineered fill.
All loose or wet subgrade soil encountered during construction should be stabilized prior
to placement of new fill and further construction. The method of stabilization should be
evaluated by a representative of Kleinfelder at the time of construction depending on the
20153715.001A/SAL15R12470 Page 15 of 37 January 15, 2015 © 2015 Kleinfelder
exposed conditions. Moisture conditioning of subgrade and fill soils will consist of
adding water if the soils are too dry, and allowing the soils to dry if the soils are too wet.
4.1.3 Concrete Slabs-on-Grade
To reduce the effects of seasonal volume changes of the on-site expansive subgrade
soils, we recommend that interior concrete slabs-on-grade be constructed on a layer of
compacted “non-expansive” engineered fill at least 12 inches thick. Exterior concrete
slabs-on-grade should be constructed on a layer of compacted “non-expansive”
engineered fill at least 6 inches thick. Exterior concrete slabs-on-grade that will be
subject to vehicle traffic should be designed as Portland cement concrete pavements as
discussed in Section 4.4.2 “Rigid Concrete Pavements,” herein.
The non-expansive fill should extend laterally outward from the perimeter of the
structure and adjoining perimeter walkways a minimum of 5 feet on every side unless
obstructed by improvements to remain. In exterior walkways not adjacent to building
areas, and in pavement areas, the “non-expansive fill” should extend laterally no less
than 2 feet beyond the back of curb, or edge of pavements, and sidewalks unless
obstructed by improvements to remain. The “non-expansive” fill should meet the
requirements given in Section 4.1.4, “Material for Engineered Fill” and should be placed
and compacted in accordance with Section 4.1.5, “Fill Placement and Compaction.”
4.1.4 Material for Engineered Fill
Inorganic on-site soils approved by a representative of Kleinfelder may be used as
engineered fill, except in areas where “non-expansive” import fill is recommended.
Additionally, on-site soils should not be used as engineered fill in areas that will be
subject to a combination of heavy loading, such as from footing foundations combined
with saturated subsurface conditions. This condition is generally not expected to occur
at the site, provided the buried stormwater management system is located under light
weight vehicle parking areas and/or landscape areas. If heavily loaded and potentially
saturated areas are later determined to exist, import fill would be required for backfill in
those areas. In general, areas that are covered in pavements or concrete slabs-on-
grade, have proper surface drainage, and that do not store concentrations of water for
extended lengths of time, are not expected to become saturated. For example the bus
20153715.001A/SAL15R12470 Page 16 of 37 January 15, 2015 © 2015 Kleinfelder
wash area, if properly paved and drained of surface water, is not expected to become
saturated.
Inorganic soils may be defined as soils containing less than 3 percent of organic matter
by weight or free of visible organic matter deemed excessive by a representative of
Kleinfelder. In general, material for use as engineered fill should be free of deleterious
or oversized material, debris, or hazardous substances; should not contain rocks or
lumps larger than 3 inches in greatest dimension; should not contain more than 15
percent of material larger than 1½ inches; and should contain sufficient fines (8% to
40% fines) to allow excavations to be made without caving.
Imported soils should be “non-expansive” and meet the above requirements, should be
predominantly granular, and should have a plasticity index of 15 or less.
All proposed import fill must be approved by the project geotechnical engineer prior to
delivery to the site. At least five (5) working days prior to importing to the site, a
representative sample of the proposed import fill should be delivered to our laboratory
for evaluation and possible testing.
4.1.5 Fill Placement and Compaction
Fill materials should be placed and compacted in horizontal lifts, each not exceeding 8
inches in uncompacted thickness. Compaction of fill should be performed by
mechanical means only. Due to equipment limitations, thinner lifts may be necessary to
achieve the recommended level of compaction. Relative compaction or compaction is
defined as the in-place dry density of the compacted soil divided by the laboratory
compacted maximum dry density as determined by ASTM Test Method D 1557 (latest
edition), expressed as a percentage. A summary of our compaction recommendations is
included in table format in Appendix E.
Permanent cut slopes should be constructed no steeper than 1.5:1 (horizontal: vertical).
As previously discussed, we understand that plans include a 1:1 (H:V) cut slope above
the bus parking lot, to a maximum slope height of about 10 feet. Cut slopes of 1:1 (H:V)
are expected to require continuous erosion control and periodic maintenance for
surficial sloughing.
20153715.001A/SAL15R12470 Page 17 of 37 January 15, 2015 © 2015 Kleinfelder
Permanent fill slopes should be fully keyed and benched into the back slope. Fill slopes
should be keyed at least 8 feet width and 2 feet deep below adjacent grade. The bottom
of the keyway should be sloped at least 2 percent downwards back into the slope.
Benches should be level or slope back into the back slope and should be no more than
3 feet in vertical separation and wide enough to allow compaction equipment. All fill
slopes steeper than 3:1 (Horizontal:Vertical) should be compacted to at least 95 percent
relative compaction full height. Based on the results of our slope stability analysis,
compacted engineered fill for slopes shall have a minimum remolded cohesion of 100
pounds per square foot and a minimum remolded phi angle of 30 degrees. Fill slopes up
to 10 feet in height may be constructed at 2:1 (Horizontal: Vertical) or flatter.
If taller slopes are planned, Kleinfelder should be consulted for additional
recommendations. Some surficial slumping could occur; proper erosion control and
timely maintenance will need to be implemented. Setback distances are essential and
are generally based on slope height and the sensitivity of the structure (building or
road). Kleinfelder should perform a detailed review if the proximity of the structure (from
the improvement to the top of the slope) is less than the slope height.
Grading operations during the wet season or in areas where the soils are saturated may
require provisions for drying prior to compaction. If the project necessitates fill
placement and compaction in wet conditions, Kleinfelder can provide alternatives for
drying the soil. Conversely, additional moisture may be required during the dry months.
Water trucks should be available in sufficient number to provide adequate watering
during subgrade preparation, fill placement and compaction.
4.1.6 Excavations and Utility Trench Backfill
Excavations for utility trenches, fuel islands, buried stormwater management systems,
and foundations should be readily made with either a conventional backhoe or
excavator. The walls of temporary trenches less than 5 feet in height, in the medium
dense to very dense silty sand and clayey sand soils, should stand near vertical with
minimal bracing, provided proper soil moisture content is maintained. Deeper trenches,
or trenches into loose sands, must be properly shored and/or braced. Alternatively,
temporary trenches may be constructed using sloping trench sidewalls. Sloping trench
sidewalls should be constructed no steeper than 1:1 (horizontal: vertical). In addition,
excavations should be located so that no structures are located above a plane projected
20153715.001A/SAL15R12470 Page 18 of 37 January 15, 2015 © 2015 Kleinfelder
1.5 horizontal to 1 vertical upward from any point in an excavation, regardless of
whether it is shored or unshored. Trench stability should be evaluated prior to
occupation by construction personnel. All trenches should be constructed in accordance
with OSHA and Cal-OSHA Safety Standards. Safety in and around utility trenches is the
responsibility of the underground contractors.
Since groundwater is at least 30 feet below existing grade, we do not anticipate the
need for dewatering of excavations. Wet weather can impact construction, especially
where on-site soils have been compacted or where imported material is used. Refer to
Section 4.1.9 on “Wet Weather Construction.” If different soil or groundwater conditions
are encountered during construction than those encountered during our subsurface
exploration, Kleinfelder should be contacted to provide additional recommendations.
Utility trench pipe zone backfill, extending from the bottom of the trench to at least 1 foot
above the top of pipe, should consist of free-draining sand unless lean concrete is
specified. Above the pipe zone, underground utility trenches should be backfilled with
compacted engineered fill. Either approved on-site soil or imported sand may be used
for backfilling utility trenches. Trench backfill should be capped with at least 12 inches of
compacted, on-site soil similar to that of the adjoining subgrade. A summary of our
compaction recommendations is included in Appendix E. Compaction should be
performed by mechanical means only. Water-jetting or flooding to attain compaction of
backfill should not be permitted.
4.1.7 Surface Drainage
Final site grading should provide surface drainage away from existing and new
buildings, concrete slabs-on-grade and pavements to reduce the percolation of water
into the underlying soils. Ponding of surface water should not be allowed adjacent to
structures and on exterior flatwork and pavements. The ground surface should be
sloped away from the buildings a minimum of 4 percent in landscaped areas and 2
percent in paved areas. Rainwater collected on the roofs of buildings should be
transported through gutters, downspouts and closed pipes, which discharge on
pavements or lead directly to the site storm sewer system. If discharging onto the
pavement, safety of pedestrian traffic should be considered.
20153715.001A/SAL15R12470 Page 19 of 37 January 15, 2015 © 2015 Kleinfelder
On-site soils are highly erodible and should be planted with erosion resistant vegetation
as soon as practicable. The erosion control vegetation should be planted early enough
before the winter rainy season to allow the vegetation to take root before the rainy
season. Ground cover will require periodic maintenance and a maintenance schedule
should be developed. Specific details regarding erosion control should be determined
by the Civil Engineer.
4.1.8 Seepage Control
We do not anticipate any significant seepage problems due to the porous sandy nature
of the on-site near-surface soils, provided water is not allowed to pond near proposed
pavements, foundations and slabs-on-grade. Features that do not impound water for
extended periods of time, such as drainage swales or where water sheets over
embankments do not require setbacks from road areas provided they drain away from
the pavements and do not trap water adjacent to the pavements. However, water
erosion of such features will need to be addressed.
We also understand that storm water retention/infiltration features are planned for the
project. These may consist of surface features and buried improvements. These
features will act as impoundment areas for on-site storm water, and water will
concentrate in these areas for extended time periods.
4.1.8.1 Surface Infiltration Features
We recommend that surface infiltration features be located to minimize the impact of the
storm water on the nearby pavements and foundations. To minimize impact on
pavements, we recommend infiltration features be located with the pavement soil
subgrade elevation (i.e. bottom of the aggregate base layer, or the bottom of the asphalt
concrete layer where aggregate base is not used) located at least 2 feet above a plane
projected 5:1 (horizontal: vertical) downward from the highest retained water elevation
(design water surface) of the adjacent impoundment area. Assuming level ground we
anticipate that this would result in off sets of about 10 to 15 feet from the pavements, or
closer where the bottoms of the features are excavated or lowered below the adjacent
grade. To minimize impact on foundations, we recommend infiltration features be
located so that the bottoms of the footings are at least 1 footing width or at least 2 feet,
whichever is greater length, above a plane projected 5:1 (horizontal:vertical) downward
20153715.001A/SAL15R12470 Page 20 of 37 January 15, 2015 © 2015 Kleinfelder
from the highest retained water elevation (design water surface) of the adjacent
impoundment area.
In areas of the site where surface infiltration features must be located adjacent to areas
of extended flat pavements, such as in parking areas with bioswales, consideration
should be given to deepening curbs at the edges of the infiltration features to the bottom
of the drain rock layer. This will reduce the potential for rotation of the curb at the edge
of the feature due to infiltrating water softening the supporting soils.
4.1.8.2 Buried Storm Water Management Systems
Buried storm water management systems should be located in areas that will not be
subjected to high ground pressures that exist in areas such as foundation zones and
bus parking or traffic areas. Such improvements will need to be located in light weight
vehicle parking areas and landscape areas. Additionally, animal burrows in the existing
slopes could result in piping failures downslope of the buried storm water management
system. This will need to be mitigated by grading or site selection for the system. The
lower permeability of deeper on-site soils containing clayey fines and/or decomposed
sandstone will limit the total embedment depth of the buried storm water management
system. Our percolation test results are presented in Section 4.5, “Percolation
Characteristics of In-Situ Soils.” Bottoms of buried storm water management systems
should be located no closer than 30 feet horizontally from structures or the free face of a
slope and above a 2:1 (Horizontal:Vertical) slope projected downwards from the
bottoms of adjacent footings.
4.1.9 Wet Weather Construction
If site grading and construction is to be performed during the winter rainy months, the
owner and contractors should be fully aware of the potential impact of wet weather.
Rainstorms can cause delay to construction and damage to previously completed work,
such as saturating a compacted subgrade, or flooding an excavation. Runoff can also
cause erosion.
Earthwork during rainy months will require extra effort and caution by the contractors.
The soil may be too wet to compact which will require processing to dry the soil. The
grading contractor should be responsible to protect his work to avoid damage by
rainstorms, including smooth rolling to seal off a pad or subgrade surface to facilitate
20153715.001A/SAL15R12470 Page 21 of 37 January 15, 2015 © 2015 Kleinfelder
drainage and to reduce rain damage, and covering the trenches with plastic sheeting.
Ponding water should be pumped out immediately. Construction in wet weather should
be addressed in the project construction bid documents and/or specifications. We
recommend the grading contractor submit a wet weather construction plan outlining
procedures they will employ to protect their work and to minimize damage to their work
by rainstorms.
4.1.10 Construction Observation
Variations in soil types and conditions are possible and may be encountered during
construction. In order to permit correlation between the soil data obtained during this
investigation and the actual soil conditions encountered during construction, we
recommend that Kleinfelder be retained to provide observation and testing services
during site earthwork and foundation construction. This will allow us the opportunity to
compare actual conditions exposed during construction with those encountered in our
investigation and to expedite supplemental recommendations if warranted by the
exposed conditions. All earthwork should be performed in accordance with the
recommendations presented in this report, or as recommended by Kleinfelder during
construction. Kleinfelder should be notified at least 2 working days before the start of
construction, and before the time when observation and testing services are needed.
We also recommend that Kleinfelder be retained to review your pre-final foundation and
grading plans and specifications. It has been our experience that this review provides
an opportunity to detect misinterpretation or misunderstandings before the start of
construction.
4.2 BUILDING FOUNDATIONS AND SETTLEMENT
4.2.1 Shallow Footing Foundations
Based on our investigation, the loads for the proposed structures can be supported by
spread footings bearing on onsite soils. The foundation elements should be embedded
at least 18 inches below pad grade or lowest adjacent finished grade whichever
provides a deeper embedment. The recommended allowable soil bearing pressures,
depth of embedment, and width of footings are presented below.
20153715.001A/SAL15R12470 Page 22 of 37 January 15, 2015 © 2015 Kleinfelder
Table 4.1 Foundation Bearing Capacity Recommendations
Footing Type Allowable Bearing
Pressure (psf)* Minimum
Embedment (in)** Minimum Width
(in)
Continuous Footing 2,750 18 18
Isolated Footing 3,000 18 24
* Pounds per square foot, dead plus live load. Includes a factor of safety (FS) of 3.
** Below lowest adjacent grade defined as bottom of slab on the interior and finish grade at the exterior.
Allowable soil bearing pressures may be increased by one-third for transient loads such
as wind and seismic loads.
Lateral loads may be resisted by a combination of friction between the foundation
bottoms and the supporting subgrade, and by passive resistance acting against the
vertical faces of the foundations, including grade beams. An ultimate friction coefficient
of 0.35 between the foundation and supporting subgrade may be used. For passive
resistance, an ultimate equivalent fluid pressure of 350 pounds per cubic foot may be
used. Where ground slopes downwards away from the footings, such as may occur at
the proposed retaining wall, passive pressure should be neglected on the upper
portions of the footing within 5 feet horizontally of the slope face. (For example for a 5:1
horizontal: vertical slope downwards from the footing face, neglect the upper buried 1
foot of the footing for passive pressure resistance. For a 2:1 H:V slope, neglect the
upper buried 2½ feet of the footing.) Passive pressure should also be neglected in the
upper one foot unless the adjacent surface is confined by paving or flatwork. The friction
coefficient and passive resistance may be used concurrently.
Total estimated settlement of an individual spread foundation will vary depending on the
plan dimensions of the foundation and the actual load supported. Based on anticipated
foundation dimensions and loads, we estimate maximum settlement of foundations
designed and constructed in accordance with the preceding recommendations to be on
the order of 1 inch. Differential settlement between similarly loaded, adjacent footings is
expected to be less than ½ inch provided footings are founded on similar materials.
Settlement of all foundations is expected to occur rapidly and should be essentially
complete shortly after initial application of the loads. In the event of a major earthquake
in the site vicinity, we estimate that the additional total and differential ground settlement
as a result of dynamic compaction would be less than ¼ inch.
20153715.001A/SAL15R12470 Page 23 of 37 January 15, 2015 © 2015 Kleinfelder
Where footings are located adjacent to below-grade structures or near major
underground utilities, the footings should extend below a 1.5:1 (horizontal to vertical)
plane projected upward from the structure footing (or bottom if no footings) or the
bottom of the underground utility to avoid surcharging the below grade structure and
underground utility with building loads. Also, where utilities cross the perimeter footings
line, the trench backfill should consist of a vertical barrier of impervious type of material
or lean concrete. In addition, where utilities cross through or under exterior footings,
flexible waterproof caulking should be provided between the sleeve and the pipe. Utility
plans should be reviewed by Kleinfelder prior to trenching for conformance to these
requirements.
Concrete for footings should be placed neat against native soil or engineered fill. It is
critical that footing excavations not be allowed to dry before placing concrete. If
shrinkage cracks appear in the footing excavations, the excavations should be
thoroughly moistened to close all cracks prior to concrete placement. The footing
excavations should be monitored by a representative of Kleinfelder for compliance with
appropriate moisture control and to confirm the adequacy of the bearing materials. If
soft or loose materials are encountered at the bottom of the footing excavations, they
should be removed and replaced with lean concrete or engineered fill. Kleinfelder
should also be present during the excavation. If desired, unit prices for such excavation
and backfilling should be obtained during contractor bidding for this project.
4.2.2 Cast-In Drilled-Hole Pile Foundations (Drilled Piers)
The proposed retaining wall and fuel canopy structures may be supported on a cast-in-
drilled-hole (CIDH) pile (i.e. drilled pier) foundation system designed to derive support
from end bearing at the bottom of the pier (due to the low skin friction of the on-site
materials), and lateral resistance from passive soil pressure against the side of the pier.
The recommended allowable foundation loads presented in this section include a factor
of safety (FS) of 3.
Drilled pier embedment length may be controlled by various load cases in either axial
loading (compression or uplift) or lateral loading; however, drilled piers should be at
least 10 feet in depth and at least 18 inches in diameter. The drilled piers should be
located no closer together than three pier diameters on-center.
20153715.001A/SAL15R12470 Page 24 of 37 January 15, 2015 © 2015 Kleinfelder
The allowable end bearing capacity for drilled piers should be taken as 8,000 psf in the
native soil materials. The weight of the buried portion of the pier may be neglected when
calculating the downward axial loads on the pier. A one-third increase in the allowable
capacity may be used for consideration of transient loads such as wind or seismic.
For resistance to uplift of the foundation an ultimate skin friction of 3500 pounds total
per pier, plus the weight of the pier may be used. The skin friction assumes an 18 inch
diameter 10 foot deep pier. The skin friction may be scaled up proportionally to the
surface area of the pier due to increased width or depth.
For drilled shafts designed and constructed in accordance with the recommendations
presented in this report, total settlement of each drilled shaft is expected to be less than
about 1 inch, with differential settlement between adjacent supports of up to about 1/2
inch. The majority of the settlement should occur during and shortly after application of
the structure loads.
Pier foundation resistance to lateral loads will be provided by passive resistance of the
soil against shafts, pier caps, and grade beams (if present) and by the bending stiffness
of the pier shafts. The lateral resistance of a drilled pier is a function of the surrounding
soil strength and stiffness, size and stiffness of the pier, pier top connection, and
induced moments and forces at the top of the pier. For pier caps and grade beams, the
ultimate passive pressure available in undisturbed native soil or compacted engineered
fill may be taken as equivalent to the pressure exerted by a fluid weighing 350 pounds
per cubic foot (pcf) acting on two pier diameter for the portion of the pier foundation
embedded in firm soil. Where ground slopes downwards away from the pier foundation,
such as may occur at the proposed retaining wall, passive pressure should be
neglected on the upper portions of the pier (and grade beam) within 5 feet horizontally
of the slope face. (For example for a 5:1 horizontal: vertical slope downwards from the
downslope edge of the pier, neglect the upper buried 1 foot of the pier for passive
pressure resistance. For a 2:1 H:V slope, neglect the upper buried 2½ feet of the pier.)
This passive pressure value is an allowable value derived using an estimated shaft
head deflection of about ½ inch. We anticipate that there may be a variety of pier lateral
loading conditions due to the configuration of the proposed structure. The appropriate
factor of safety for lateral load resistance will depend on the design condition and
should be selected by the designer.
20153715.001A/SAL15R12470 Page 25 of 37 January 15, 2015 © 2015 Kleinfelder
The structural engineer should determine the actual embedded depth based on the
lateral loads transmitted to the foundations. Once the structural loading information is
available, if requested, Kleinfelder can assist in determining the shear, moments and
lateral displacement for the piers based on the design loads.
We note that attention must be given to the method of drilled pier construction to satisfy
the above recommendations. The need for slurry is not anticipated due to groundwater
being at least 30 feet below existing grade, and to allow inspection of the bottom of the
shaft. Sandy soils were encountered in our borings; therefore, casing should be
available onsite to facilitate supporting the excavations if needed. Highly weathered to
decomposed sandstone material was encountered in some of our borings; therefore,
rock augers or rock drilling buckets will likely be required. Steel reinforcement and
concrete should be placed within about 4 to 6 hours of completion of each drilled hole.
As a minimum, the holes should be poured the same day they are drilled. The bottom of
the drilled holes should be cleaned to remove as much loose soil as practical prior to
placement of concrete. A representative from Kleinfelder should be present to observe
drilled holes to confirm the soils encountered are capable of carrying the design loads
and that bottom conditions are satisfactory prior to placing steel reinforcement.
The steel reinforcement should be centered in the drilled hole. Concrete should be
discharged vertically with a tremie pipe from the shaft bottom upward at a rate in which
the tremie nozzle does not become separated from the placed concrete by more than
three feet. Under no circumstances should concrete be allowed to free-fall against either
the steel reinforcement or the sides of the excavation during construction. Sufficient
vibration should be performed while the concrete is tremied to minimize voids and
properly derive the frictional shaft surface to satisfy uplift design requirements.
Prior to mobilizing drilling equipment to the site, the foundation contractor should submit
to Kleinfelder a construction plan describing the procedures it intends to utilize in the
CIDH pile (drilled pier) construction process. Kleinfelder should review this plan and
confirm that the procedures conform to the recommendations provided herein.
20153715.001A/SAL15R12470 Page 26 of 37 January 15, 2015 © 2015 Kleinfelder
4.3 RETAINING STRUCTURES
A new retaining wall is planned on the western portion of the site above Canyon Del
Rey Boulevard. We understand that this wall will be approximately 10 feet in height, and
will primarily retain engineered fill and pavements areas.
Retaining walls may be supported on deepened continuous conventional footings or
CIDH piles (drilled piers) designed in accordance with our recommendations presented
above. Flexible walls that are free to deflect at the top may be designed for an active
lateral earth pressure calculated using an equivalent fluid weight of 40 pounds per cubic
foot where the backfill is level if the retaining wall is backfilled with on-site soil or
approved import fill material. Rigid walls that are constrained against movement at the
top should be designed for an "at-rest" lateral earth pressure calculated using an
equivalent fluid weight of 60 pounds per cubic foot where the backfill is level if the
retaining wall is backfilled with on-site soil or approved import fill material. The above
pressure values apply to horizontal backfill and do not include hydrostatic pressures that
might be caused by groundwater or water trapped behind the structure.
For seismic lateral surcharge loads, a design peak ground acceleration (PGA) of 0.57g
was used in the analysis which resulted in an additional seismic pressure of 15H
pounds per square foot (where H is the total height of the wall in feet) for flexible walls
that are free to defect at the top, and an additional seismic pressure of 33H pounds per
square foot for rigid walls that are constrained against movement at the top. This
additional seismic pressure should be applied as a rectangular distribution over the
entire depth of the wall.
In addition to lateral earth pressures and seismic surcharges, retaining walls must be
designed to resist horizontal pressures that may be generated by surcharge loads
applied at the ground surface such as from uniform loads or vehicle loads. For uniform
loads, such as floor live loads, an additional uniform lateral surcharge equal to 50
percent of the vertical live loads should be applied on the wall. For occasional fork-lift or
light vehicle loads, we recommend adding an additional uniform lateral surcharge
pressure of 50 pounds per square foot. Heavy vehicle loads, such as from busses or
heavy trucks is best evaluated once the position, type, magnitude and frequency of the
loads, is determined. Kleinfelder should be consulted to provide specific
recommendations for heavy vehicle loads once this information is available. For initial
20153715.001A/SAL15R12470 Page 27 of 37 January 15, 2015 © 2015 Kleinfelder
planning purposes, an estimated additional uniform lateral surcharge pressure of 250
pounds per square foot is recommended. For other loads, such as point or line loads,
the additional lateral surcharge will depend on the position, type and magnitude of the
loads, and Kleinfelder should be consulted to provide specific recommendations.
Retaining walls higher than 2 feet should be fully drained. Drainage may be provided by
a prefabricated drainage system, such as Mirafi Miradrain 6000/6200, or a 1 to 2 foot
wide zone of 3/4-inch by No. 4 crushed, clean rock wrapped in a layer of non-woven
geotextile filter fabric such as Mirafi 140NC or equivalent. Class 2 Permeable material
(Caltrans Standard Specifications, Section 68) may be used in lieu of the clean crushed
rock and filter fabric. The gravel drain should extend from the base of the wall to within
about one foot of the top of the wall. The upper one foot of the backfill should consist of
compacted native soil graded to direct surface water away from the walls. A 4-inch
diameter, rigid perforated pipe surrounded by the gravel drainage blanket should be
installed at the base of the wall to collect and transport the water away from the wall
toward a suitable discharge point. The pipe should be sloped to drain by gravity to
appropriate outlets. The pipe should be placed on approximately 4 inches of gravel
bedding with perforations placed down. The pipe should consist of solid walled pipe
where located away from the base of the wall. Similarly, a collector pipe will be required
where drainage panels are installed.
Where migration of moisture through the retaining wall would be detrimental or
undesirable, the retaining wall should be waterproofed as specified by the project
architect.
Backfill against wall structures should be properly compacted. Over-compaction should
be avoided because increased compaction can result in lateral pressures significantly
higher than those recommended above. Wall backfill should be spread in level lifts not
exceeding 6 inches in thickness. Each lift should be compacted to not less than 90
percent relative compaction, per ASTM D1557 latest edition, at over the optimum
moisture content. Retaining walls may be subjected to higher stress during placement of
wall backfill where large or heavy grading equipment is used. This should be considered
by the wall designer and contractor, and bracing during construction may be required.
Compaction of wall backfill within 5 feet of the wall should be performed by hand-
operated equipment.
20153715.001A/SAL15R12470 Page 28 of 37 January 15, 2015 © 2015 Kleinfelder
We recommend that design drawings of retaining walls showing height of wall, backfill
material type, drainage details and the earth pressures used in design be reviewed by
Kleinfelder for conformance to the recommendations given. Certain proprietary wall
systems, such as reinforced earth walls, segmental block walls, and criblock walls, are
design-built systems requiring close coordination with the Civil Engineer on drainage
outlets and connections. If any proprietary walls are planned, we strongly recommend
that we review the type of wall proposed and make alternate appropriate lateral earth
pressure recommendations for these walls. Furthermore, we recommend that
Kleinfelder be retained to review design plans prior to issuance for construction.
4.4 VEHICLE PAVEMENTS
Pavements for this project are anticipated to consist of parking and access areas for
passenger cars and light pickup trucks, and heavy traffic areas for busses and garbage
trucks. Traffic loading information for this project is based on our experience with similar
projects. Based on our experience, we suggest using a Traffic Index (TI) of at least 4.5
for automobile parking areas, a TI of at least 5.5 for automobile and light truck traffic
lanes, and a TI of at least 6.5 for garbage truck areas. We estimate that a Traffic Index
of 7.0 to 8.0 will be used for areas servicing busses. For heavy vehicle areas, a
minimum asphalt concrete section of 4½ inches is recommended. The anticipated traffic
and the alternate pavement sections presented should be reviewed by the project civil
engineer in consultation with the owner during the development of the final grading and
paving plans.
4.4.1 Flexible Asphalt Pavements
Bulk samples of the near surface soil were obtained from the site during our field
investigation. The results of our laboratory testing indicate R-Values of 7 and 57. The R-
value of 7 material was encountered in the bus parking area on the northern portion of
the site, on the flatter upper portion of the lot. The R-Value of 57 material was
encountered in the automobile parking lot on the south side of the site, near the south
slope. The recommended pavement sections are presented in the tables below. We
have made our pavement designs based on the pavement subgrade soil consisting of
existing on-site surface material (i.e. clayey sand and silty sand with gravel). If site
grading exposes soil other than that utilized in our analysis, we should perform
additional tests to confirm or revise the recommended pavement sections to reflect the
actual field conditions.
20153715.001A/SAL15R12470 Page 29 of 37 January 15, 2015 © 2015 Kleinfelder
Asphalt concrete should meet the requirements for 1/2- or 3/4-inch maximum, medium
Type A or Type B asphalt concrete as specified in Section 39 of the Caltrans Standard
Specifications. Class 2 aggregate base materials should conform to the requirements
presented in Section 26 of the Caltrans Standard Specifications. Class 2 aggregate
subbase materials should conform to the requirements presented in Section 25 of the
Caltrans Standard Specifications, with a minimum R-Value of 50. Asphalt concrete and
aggregate base, and preparation of the subgrade should conform to, and be placed in
accordance with, the California Department of Transportation Standard Specifications,
except as noted herein. ASTM Test procedures should be used to assess the percent
relative compaction of soils, aggregate base and asphalt concrete. Asphalt concrete
should be compacted to between 95 percent and 96 percent of the maximum
compacted unit weight.
Table 4.2 Flexible Asphalt Concrete Pavement Alternatives R-Value = 7
FLEXIBLE PAVEMENT SECTION ALTERNATIVES
R-Value = 7 (All areas except the existing southern parking lot containing Boring B-6)
Traffic Index Asphalt Concrete
(inches) Class 2 Aggregate
Base (inches) Class 2 Aggregate Subbase (inches)
4.5 2.5 9.0 -
2.5 4.5 5.0
5.0 2.5 10.5 -
2.5 5.0 6.0
5.5 3.0 11.5 -
3.0 5.5 6.5
6.0 3.0 13.0 -
3.0 6.5 7.5
6.5 3.5 14.5 -
3.5 6.5 8.5
7.0 4.0 15.0 -
4.0 6.5 9.5
7.5 4.5 16.0 -
4.5 7.0 10.0
8.0 4.5 17.5 -
4.5 8.0 10.5
*Note: AC = Type A or B Asphalt Concrete AB = Class 2 Aggregate Base (Minimum R-Value = 78) ASB = Class 2 Aggregate Subbase Minimum R-Value = 50
20153715.001A/SAL15R12470 Page 30 of 37 January 15, 2015 © 2015 Kleinfelder
Table 4.3 Flexible Asphalt Concrete Pavement Alternatives R-Value = 57
FLEXIBLE PAVEMENT SECTION ALTERNATIVES
R-Value = 57 (Southern parking lot containing Boring B-6)
Traffic Index Asphalt Concrete (inches) Class 2 Aggregate Base
(inches)
4.5 4.0 -
2.5 4.0
5.0 4.5 -
2.5 4.0
5.5 5.0 -
3.0 4.0
6.0 5.5 -
3.0 4.0
6.5 6.0 -
3.5 4.0
7.0 6.5 -
4.0 4.0
7.5 7.5 -
4.5 4.0
8.0 8.0 -
4.5 4.0
*Note: AC = Type A or B Asphalt Concrete AB = Class 2 Aggregate Base (Minimum R-Value = 78)
Parking areas should be sloped at a minimum of 2 percent and drainage gradients
maintained to carry all surface water off the site. Surface water ponding should not be
allowed anywhere on the site during or after construction. Seepage cut-offs should be
constructed as discussed previously in Section 4.1.
4.4.2 Rigid Concrete Pavements
Rigid pavements consisting of Portland cement concrete may also be considered. We
recommend that the pavement sections presented be reviewed by the project Civil
Engineer in consultation with AECOM and Monterey Salinas Transit District during the
development of the final grading plans.
20153715.001A/SAL15R12470 Page 31 of 37 January 15, 2015 © 2015 Kleinfelder
Portland cement concrete pavements should be constructed on a minimum 12-inch
thick layer of Class 2 Aggregate Base over the subgrade. Preparation of soil subgrade
and compaction of the aggregate base should follow the recommendations given above
in Section 4.1. The compacted subgrade and the aggregate base should be non-
yielding.
Using the above design parameters and the Portland Cement Association Simplified
Design Procedure, we recommend the use of a minimum concrete pavement thickness
of 4.5 inches for light vehicle areas and 6.5 inches in areas that will experience heavy
truck or bus traffic. Our design is based on a combined modulus of subgrade reaction of
approximately 130 pci at the top of the aggregate base, a concrete shoulder or curb
without doweled joints, and a modulus of rupture for the concrete of 600 pounds per
square inch. If a concrete shoulder or curb will not be used, then the above minimum
concrete pavement thicknesses should be increased by on inch. It should be noted that
the modulus of rupture for concrete is based on flexural strength, not compressive
strength, and should be specified accordingly. Our experience is that the compressive
strength will be on the order of 4,500 to 5,000 psi to achieve the required flexural
strength. Concrete with a compressive strength of 3,000 psi is not expected to provide
the desired flexural strength. Laboratory testing to evaluate the design strength is
recommended.
4.5 PERCOLATION CHARACTERISTICS OF IN-SITU SOILS
Presaturation of the percolation test holes was completed on November 20, 2014, 24
hours prior to percolation testing. Presaturation consisted of filling the prepared holes
with water.
Percolation testing was performed on the morning and afternoon of November 21, 2014.
For the percolation holes we generally used a 10-minute measurement interval. The
location of our exploratory borings and percolation test holes are presented on the Site
Plan, Plate 2. The results of the percolation testing are presented in Appendix B and
summarized in the table below. The raw stabilized rates are presented at the bottom of
the tables.
20153715.001A/SAL15R12470 Page 32 of 37 January 15, 2015 © 2015 Kleinfelder
Generally, percolation rates of the upper silty sand soils encountered above
approximately 9 to 13 feet bgs were measured to be about 3 to 6 minutes per inch raw
stabilized rate (i.e. percolation test holes P-1 to P-3). The percolation rates of the
deeper clayey sand soils encountered in P-1 to P-3 were too “slow” to accurately
measure over the given testing period. It should be noted that the rates presented are
raw stabilized rates. We have not applied any corrections for the hole diameter, pea
gravel, or slotted pipe.
Table 4.4 Percolation Test Results
Location Total Hole
Depth (feet) Soil Type
Percolation Rate
(min / inch)
Slow Percolation Below (feet)
P-1 13.4 SM/SC 5.6 10.4
P-2 13.5 SM/SC 2.7 13.1
P-3 13.2 SM/SC 3.6 8.9
Our scope-of-work was limited to testing, and excludes evaluation of the general
suitability of the sites for the infiltration system, evaluation of the storage capacity and
permeability of the in-situ soils, nor actual design of the infiltration system. The
proposed storm water management system design should be performed by the project
civil engineer.
20153715.001A/SAL15R12470 Page 33 of 37 January 15, 2015 © 2015 Kleinfelder
5. LIMITATIONS
This work was performed in a manner consistent with that level of care and skill
ordinarily exercised by other members of Kleinfelder’s profession practicing in the same
locality, under similar conditions and at the date the services are provided. Our
conclusions, opinions and recommendations are based on a limited number of
observations and data. It is possible that conditions could vary between or beyond the
data evaluated. Kleinfelder makes no other representation, guarantee or warranty,
express or implied, regarding the services, communication (oral or written), report,
opinion, or instrument of service provided.
This report may be used only by AECOM and Monterey Salinas Transit District and the
registered design professional in responsible charge and only for the purposes stated
for this specific engagement within a reasonable time from its issuance, but in no event
later than two (2) years from the date of the report.
The work performed was based on project information provided by AECOM and
Monterey Salinas Transit District. As part of our scope of services, Kleinfelder will be
performing a review of the pre-final plans and specifications for this project. Please
forward the pre-final plans and specifications to us when they are completed for our
review. If AECOM and Monterey Salinas Transit District does not retain Kleinfelder to
review any plans and specifications, including any revisions or modifications to the
plans and specifications, Kleinfelder assumes no responsibility for the suitability of our
recommendations. In addition, if there are any changes in the field to the plans and
specifications, AECOM and Monterey Salinas Transit District must obtain written
approval from Kleinfelder’s engineer that such changes do not affect our
recommendations. Failure to do so will vitiate Kleinfelder’s recommendations.
The scope of services was limited to nine borings, percolation testing, laboratory testing
of selected soil samples, engineering analysis, and preparation of this report. It should
be recognized that definition and evaluation of subsurface conditions are difficult.
Judgments leading to conclusions and recommendations are generally made with
incomplete knowledge of the subsurface conditions present due to the limitations of
data from field studies. The conclusions of this assessment are based on nine borings
to a maximum depth of about 30 feet below the existing ground surface, previous data
20153715.001A/SAL15R12470 Page 34 of 37 January 15, 2015 © 2015 Kleinfelder
collected by Kleinfelder on this site, laboratory testing of natural moisture content and
density, grain size distribution, plasticity, unconfined compression testing and
percolation testing of the site soils, and engineering analyses.
Kleinfelder offers various levels of investigative and engineering services to suit the
varying needs of different clients. Although risk can never be eliminated, more detailed
and extensive studies yield more information, which may help understand and manage
the level of risk. Since detailed study and analysis involves greater expense, our clients
participate in determining levels of service, which provide information for their purposes
at acceptable levels of risk. The client and key members of the design team should
discuss the issues covered in this report with Kleinfelder, so that the issues are
understood and applied in a manner consistent with the owner’s budget, tolerance of
risk and expectations for future performance and maintenance.
Recommendations contained in this report are based on our field observations and
subsurface explorations, limited laboratory tests, and our present knowledge of the
proposed construction. It is possible that soil, rock or groundwater conditions could vary
between or beyond the points explored. If soil, rock or groundwater conditions are
encountered during construction that differ from those described herein, the client is
responsible for ensuring that Kleinfelder is notified immediately so that we may
reevaluate the recommendations of this report. If the scope of the proposed
construction, including the estimated structural loads, and the design depths or
locations of the foundations, changes from that described in this report, the conclusions
and recommendations contained in this report are not considered valid unless the
changes are reviewed, and the conclusions of this report are modified or approved in
writing, by Kleinfelder.
As the geotechnical engineering firm that performed the geotechnical evaluation for this
project, Kleinfelder should be retained to confirm that the recommendations of this
report are properly incorporated in the design of this project, and properly implemented
during construction. This may avoid misinterpretation of the information by other parties
and will allow us to review and modify our recommendations if variations in the soil
conditions are encountered.
20153715.001A/SAL15R12470 Page 35 of 37 January 15, 2015 © 2015 Kleinfelder
As a minimum Kleinfelder should be retained to provide the following continuing
services for the project:
Review the project pre-final plans and specifications, including any revisions or
modifications;
Observe and evaluate the site earthwork operations to confirm subgrade soils
are suitable for construction and placement of engineered fill;
Observe and evaluate cut slope and fill slope construction;
Observe excavations and confirm that engineered fill and backfill for utilities and
other buried improvements are placed and compacted per the project
specifications;
Observe foundation excavations to confirm subsurface conditions are as
anticipated and to verify adequate geotechnical support for the proposed
improvements;
Observe retaining wall construction and backfill; and
Observe asphalt concrete and Portland cement concrete pavement construction.
The scope of services for this subsurface exploration and geotechnical report did not
include environmental assessments or evaluations regarding the presence or absence
of wetlands or hazardous substances in the soil, surface water, or groundwater at this
site.
Kleinfelder cannot be responsible for interpretation by others of this report or the
conditions encountered in the field. Kleinfelder must be retained so that all geotechnical
aspects of construction will be monitored on a full-time basis by a representative from
Kleinfelder, including site preparation, preparation of foundations, and placement of
engineered fill and trench backfill. These services provide Kleinfelder the opportunity to
observe the actual soil, rock and groundwater conditions encountered during
construction and to evaluate the applicability of the recommendations presented in this
report to the site conditions. If Kleinfelder is not retained to provide these services, we
will cease to be the geotechnical engineer of record for this project and will assume no
responsibility for any potential claim during or after construction on this project. If
changed site conditions affect the recommendations presented herein, Kleinfelder must
20153715.001A/SAL15R12470 Page 36 of 37 January 15, 2015 © 2015 Kleinfelder
also be retained to perform a supplemental evaluation and to issue a revision to our
original report.
This report, and any future addenda or reports regarding this site, may be made
available to bidders to supply them with only the data contained in the report regarding
subsurface conditions and laboratory test results at the point and time noted. Bidders
may not rely on interpretations, opinion, recommendations, or conclusions contained in
the report. Because of the limited nature of any subsurface study, the contractor may
encounter conditions during construction which differ from those presented in this
report. In such event, the contractor should promptly notify the owner so that
Kleinfelder’s geotechnical engineer can be contacted to confirm those conditions. We
recommend the contractor describe the nature and extent of the differing conditions in
writing and that the construction contract include provisions for dealing with differing
conditions. Contingency funds should be reserved for potential problems during
earthwork and foundation construction. Furthermore, the contractor should be prepared
to handle contamination conditions if encountered at this site, which may affect the
excavation, removal, or disposal of soil; dewatering of excavations; and health and
safety of workers.
20153715.001A/SAL15R12470 Page 37 of 37 January 15, 2015 © 2015 Kleinfelder
6. REFERENCES
California Geological Survey (2010), Digital Images of Official Maps of Alquist-Priolo
Earthquake Fault Zones of California; CD 2000-003; updated through December
2010 at: http://www.quake.ca.gov/gmaps/ap/ap_maps.htm.
Clark, J.C., Dupre, W.R., and Rosenberg, L.I., 1997, Geologic map of the Monterey and
Seaside 7.5-minute quadrangles, Monterey County, California: a digital database:
U.S. Geological Survey, Open-File Report OF-97-30, scale 1:24,000.
Dibblee, T.W. and Minch, J.A., 2007, Geologic map of the Monterey and Seaside
quadrangles, Monterey County, California: Dibblee Geological Foundation, Dibblee
Foundation Map DF-346, scale 1:24,000.
Dupre, W.R., 1990, Maps showing geology and liquefaction susceptibility of Quaternary
deposits in the Monterey, Seaside, Spreckels, and Carmel Valley quadrangles,
Monterey County, California: U.S. Geological Survey, Miscellaneous Field Studies
Map MF-2096, scale 1:24,000.
Petersen, Mark D., Frankel, Arthur D., Harmsen, Stephen C., Mueller, Charles S.,
Haller, Kathleen M., Wheeler, Russell L., Wesson, Robert L., Zeng, Yuehua, Boyd,
Oliver S., Perkins, David M., Luco, Nicolas, Field, Edward H., Wills, Chris J., and
Rukstales, Kenneth S. (2008), “Documentation for the 2008 Update of the United
States National Seismic Hazard Maps,” U.S. Geological Survey Open-File Report
2008–1128, 61 p.
Donald Tharp and Associates (1993), Soil and Foundation Investigation, Repair of
Small Slope Failure, Ryan Ranch Road and Highway 218, Monterey, California.
Weber Hayes and Associates (1993), Preliminary Geologic Letter Report for the
October 1993 Highway 218 Slope Failure, Monterey Salinas Transit, Monterey
County, California
PLATES
APPENDIX A
Field Explorations
PLATE
A-1MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
The report and graphics key are an integral part of these logs. Alldata and interpretations in this log are subject to the explanations andlimitations stated in the report.
Lines separating strata on the logs represent approximateboundaries only. Actual transitions may be gradual or differ fromthose shown.
No warranty is provided as to the continuity of soil or rockconditions between individual sample locations.
Logs represent general soil or rock conditions observed at thepoint of exploration on the date indicated.
In general, Unified Soil Classification System designationspresented on the logs were based on visual classification in the fieldand were modified where appropriate based on gradation and indexproperty testing.
Fine grained soils that plot within the hatched area on thePlasticity Chart, and coarse grained soils with between 5% and 12%passing the No. 200 sieve require dual USCS symbols, ie., GW-GM,GP-GM, GW-GC, GP-GC, GC-GM, SW-SM, SP-SM, SW-SC, SP-SC,SC-SM.
If sampler is not able to be driven at least 6 inches then 50/Xindicates number of blows required to drive the identified sampler Xinches with a 140 pound hammer falling 30 inches.
_
SILTY SANDS, SAND-GRAVEL-SILTMIXTURES
CLAYEY SANDS, SAND-GRAVEL-CLAYMIXTURES
SW-SM
CLAYEY SANDS, SAND-SILT-CLAYMIXTURES
CL
CL-ML
>
<
<
SANDSWITH5% TO12%
FINES
SANDSWITH >
12%FINES
SA
ND
S (
Mor
e th
an h
alf o
f coa
rse
frac
tion
is s
mal
ler
than
the
#4 s
ieve
)
WELL-GRADED SANDS, SAND-GRAVELMIXTURES WITH LITTLE FINES
Cu 4 and/or 1 Cc 3>
CLEANGRAVEL
WITH<5%
FINES
GRAVELSWITH5% TO12%
FINES
OL
CH
CLAYEY GRAVELS,GRAVEL-SAND-CLAY MIXTURES
GRAVELSWITH >
12%FINES
>
Cu 4 and1 Cc 3
>_
_
BULK SAMPLE
CALIFORNIA SAMPLER(3 in. (76.2 mm.) outer diameter)
STANDARD PENETRATION SPLIT SPOON SAMPLER(2 in. (50.8 mm.) outer diameter and 1-3/8 in. (34.9 mm.) innerdiameter)
_
GM
GC
GW
GP
GW-GM
GW-GC
_ _
_
INORGANIC CLAYS OF LOW TO MEDIUM PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS, LEAN CLAYS
GRAPHICS KEY
<
SAMPLE/SAMPLER TYPE GRAPHICS
>
<
<
>
CLEANSANDSWITH<5%
FINES
GR
AV
EL
S (
Mor
e th
an h
alf o
f coa
rse
frac
tion
is la
rger
than
the
#4 s
ieve
)
Cu 6 and/or 1 Cc 3
Cu 6 and/or 1 Cc 3
>
Cu 6 and1 Cc 3
SC-SM
Cu 4 and1 Cc 3
< _
ORGANIC SILTS & ORGANIC SILTY CLAYSOF LOW PLASTICITY
SILTS AND CLAYS(Liquid Limitless than 50)
SILTS AND CLAYS(Liquid Limit
greater than 50)
WELL-GRADED SANDS, SAND-GRAVELMIXTURES WITH LITTLE OR NO FINES
POORLY GRADED SANDS,SAND-GRAVEL MIXTURES WITHLITTLE OR NO FINES
MH
OH
ML
GC-GM
CO
AR
SE
GR
AIN
ED
SO
ILS
(M
ore
than
hal
f of m
ater
ial i
s la
rger
than
the
#200
sie
ve)
UNIFIED SOIL CLASSIFICATION SYSTEM (ASTM D 2487)
<
Cu 6 and1 Cc 3
GP-GM
GP-GC
_
_ _<
>
<
<
>
SP
SP-SM
SP-SC
SM
SC
< _<
>
WELL-GRADED GRAVELS,GRAVEL-SAND MIXTURES WITHLITTLE OR NO FINES
POORLY GRADED GRAVELS,GRAVEL-SAND MIXTURES WITHLITTLE OR NO FINES
WELL-GRADED GRAVELS,GRAVEL-SAND MIXTURES WITHLITTLE FINES
WELL-GRADED GRAVELS,GRAVEL-SAND MIXTURES WITHLITTLE CLAY FINES
POORLY GRADED GRAVELS,GRAVEL-SAND MIXTURES WITHLITTLE FINES
POORLY GRADED GRAVELS,GRAVEL-SAND MIXTURES WITHLITTLE CLAY FINES
SILTY GRAVELS, GRAVEL-SILT-SANDMIXTURES
CLAYEY GRAVELS,GRAVEL-SAND-CLAY-SILT MIXTURES
WELL-GRADED SANDS, SAND-GRAVELMIXTURES WITH LITTLE CLAY FINES
POORLY GRADED SANDS,SAND-GRAVEL MIXTURES WITHLITTLE CLAY FINES
SW
SW-SC
POORLY GRADED SANDS,SAND-GRAVEL MIXTURES WITHLITTLE FINES
Cu 4 and/or 1 Cc 3>
>
FIN
E G
RA
INE
D S
OIL
S(M
ore
than
hal
f of m
ater
ial
is s
mal
ler
than
the
#200
sie
ve)
INORGANIC SILTS AND VERY FINE SANDS, SILTY ORCLAYEY FINE SANDS, SILTS WITH SLIGHT PLASTICITY
ORGANIC CLAYS & ORGANIC SILTS OFMEDIUM-TO-HIGH PLASTICITY
INORGANIC CLAYS OF HIGH PLASTICITY,FAT CLAYS
INORGANIC SILTS, MICACEOUS ORDIATOMACEOUS FINE SAND OR SILT
INORGANIC CLAYS-SILTS OF LOW PLASTICITY, GRAVELLYCLAYS, SANDY CLAYS, SILTY CLAYS, LEAN CLAYS
GROUND WATER GRAPHICS
OBSERVED SEEPAGE
WATER LEVEL (level after exploration completion)
WATER LEVEL (level where first observed)
WATER LEVEL (additional levels after exploration)
NOTES
DRAWN BY: JDS
CHECKED BY: AB
DATE: 12/2/2014
REVISED: -
PLO
TT
ED
: 12
/05/
201
4 1
1:2
6 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: R
:KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
4.G
LB
[GE
O-L
EG
EN
D 1
(G
RA
PH
ICS
KE
Y)
WIT
H U
SC
S]
(# blows/ft) (# blows/ft)
PLATE
(# blows/ft)
A-2MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
The thread is easy to roll and not much time
5 - 12
A 1/8-in. (3 mm.) thread cannot be rolled at
5 - 15
15 - 4040 - 70
35 - 65
15 - 35
>70
Damp but no visible water
Visible free water, usually soil is below water table
Cohesive soil that can be broken down into small angular
DENSITY
0 - 15
crumbling when drier than the plastic limit
lumps which resist further breakdown
Fracture planes appear polished or glossy, sometimes striated
Breaks along definite planes of fracture with little resistance
APPARENT
10 - 3030 - 50
>50
less than 1/4-in. thick, note thickness
> 8000
Firm
Hard
Very Hard
Non-plastic
Low (L)
Medium (M)
High (H)
NOTE: AFTER TERZAGHI AND PECK, 1948
<4
65 - 85
Boulders
Green YellowGreen
Blue GreenBlue
Purple BluePurple
Red Purple
4000 - 8000
Weakly
Moderately
Strongly
FIELD TESTDESCRIPTION
It takes considerable time rolling and kneading
coarse
ABBR
R
YGYG
BG
RedYellow Red
Yellow
<5(%)
SAMPLER
or thread cannot be formed when drier than the
any water content.
The thread can barely be rolled and the lump
when drier than the plastic limit
FIELD TEST
Absence of moisture, dusty, dry to the touch
SubangularRounded Angular
CRITERIA
Very Soft
Soft
Subrounded
Gravel
Sand
Fines
Thumb will penetrate soil more than 1 in. (25 mm.)
Wet
fine
coarse
fine
#10 - #4
GRAINSIZE
>12 in. (304.8 mm.)
3/4 -3 in. (19 - 76.2 mm.)
0.19 - 0.75 in. (4.8 - 19 mm.)
< 1000
SOIL DESCRIPTION KEY
FIELD TESTDESCRIPTION
plastic limit.
the plastic limit. The lump or thread crumbles
limit. The lump or thread can be formed without
Same color and appearance throughout
DESCRIPTION
Inclusion of small pockets of different soils, such as small lenses
CRITERIA
Alternating layers of varying material or color with the layer
0.0029 - 0.017 in. (0.07 - 0.43 mm.)
0.017 - 0.079 in. (0.43 - 2 mm.)
to reach the plastic limit. The thread can be
Lensed
Blocky
Slickensided
Fissured
Laminated
Stratified
DESCRIPTION
None
Strong
Rounded
DESCRIPTION
Cobbles
Thumbnail will not indent soil
Thumb will penetrate soil about 1 in. (25 mm.)
CRITERIA
No visible reaction
Some reaction, with bubbles forming slowly
Violent reaction, with bubbles forming immediately
Weak
0.079 - 0.19 in. (2 - 4.9 mm.)
SPT-N60
Thumb will not indent soil but readily indented with thumbnail
Very DenseDense
Medium Dense
FIELD TEST
NP
< 30
> 50
<0.0029 in. (<0.07 mm.)
rerolled several times after reaching the plastic
SubroundedParticles have smoothly curved sides and no edges
Particles have nearly plane sides but havewell-rounded corners and edges
Particles are similar to angular description but have
of sand scattered through a mass of clay; note thickness
Thumb will indent soil about 1/4-in. (6 mm.)
to fracturing
Alternating layers of varying material or color with layers
Angular
Subangular
LL
30 - 50
Particles have sharp edges and relatively planesides with unpolished surfaces
rounded edges
at least 1/4-in. thick, note thickness
CONSISTENCY
medium
Loose
Very Loose
DENSITY
1000 - 2000
Homogeneous
DESCRIPTION
Dry
Moist
is required to reach the plastic limit.The thread cannot be rerolled after reaching
>6035 - 60
CALIFORNIA
4 - 10
NAME
YR
BPBP
RP
#40 - #10
#200 - #10
Passing #200
3 - 12 in. (76.2 - 304.8 mm.)
3/4 -3 in. (19 - 76.2 mm.)
#4 - 3/4 in. (#4 - 19 mm.)
SIEVESIZE
>12 in. (304.8 mm.)
3 - 12 in. (76.2 - 304.8 mm.)
Pea-sized to thumb-sized
Thumb-sized to fist-sized
Larger than basketball-sized
Fist-sized to basketball-sized
Flour-sized and smaller
Rock salt-sized to pea-sized
Sugar-sized to rock salt-sized
Flour-sized to sugar-sized
SIZEAPPROXIMATE
RELATIVE
85 - 100
<4
MODIFIED CASAMPLER
DESCRIPTION
12 - 35
Crumbles or breaks with handling or slight
Crumbles or breaks with considerable
Will not crumble or break with finger pressure
finger pressure
finger pressure
Black N
2000 - 4000
UNCONFINEDCOMPRESSIVE
STRENGTH (qu)(psf)
STRUCTURE
CONSISTENCY - FINE-GRAINED SOIL
MOISTURE CONTENT
APPARENT / RELATIVE DENSITY - COARSE-GRAINED SOIL
CEMENTATION
Munsell Color
PLASTICITY
REACTION WITH HYDROCHLORIC ACID
GRAIN SIZE
ANGULARITY
DRAWN BY: JDS
CHECKED BY: AB
DATE: 12/2/2014
REVISED: -
PLO
TT
ED
: 12
/05/
201
4 1
1:2
6 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: R
:KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
4.G
LB
[GE
O-L
EG
EN
D 2
(S
OIL
DE
SC
RIP
TIO
N K
EY
)]
approximate 6 inches of asphalt
approximate 6 inches of aggregate baserock
Poorly-graded SAND (SP): fine grained, lightgray, moist, medium dense, with some silt, withtrace fine sub-rounded gravel
Silty SAND (SM): fine to coarse grained, lightolive brown, moist, medium dense, trace finesub-rounded gravelfine grained at 4'
Decomposed to highly weathered Sandstone-as Clayey Sand (SC): fine to coarse grained,medium to high plasticity, dark brown, with palegray, moist, dense, with layers of orange-brownmottled pale gray sandstone
fine grained, low plasticity
medium plasticity, medium dense
low plasticity, dense
The exploration was terminated atapproximately 30 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 21, 2014.
1
2
3
4
5
6
7
12"
12"
28 4
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=111623
BC=141618
BC=141520
BC=211620
BC=162027
BC=8914
BC=121422
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-1
BORING LOG B-1 PLATE
A-3
Surface Condition: Asphalt
A. BordLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/21/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
4 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 5-1/2 inches of asphalt
approximate 3 inches of aggregate baserock
Clayey SAND (SC): fine to coarse grained,medium plasticity, brown, moist, very dense,with some fine to medium sub-rounded gravel
Silty SAND (SM): fine grained, low plasticity,gray brown, moist, dense, trace largesub-rounded gravel
Clayey SAND with Gravel (SC): fine grained,yellowish brown, moist, dense, fine sub-roundedgravel
Clayey SAND (SC): fine grained, mediumplasticity, light olive, moist, dense, trace finesub-rounded gravel
Silty SAND (SM): fine grained, low plasticity,light brown, moist, medium dense
dense
The exploration was terminated atapproximately 30 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 21, 2014.
1
2
3
4
5
6
7
12"
18"16.3 107.5
29
24
37 21
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=304239
BC=142132
BC=142124
BC=131418
BC=141727
BC=111113
BC=141927
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-2
BORING LOG B-2 PLATE
A-4
Surface Condition: Asphalt
A. BordLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/21/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
4 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 3-1/2 inches of asphalt
approximate 5 inches of aggregate baserock
Clayey SAND (SC): fine grained, low plasticity,reddish brown, moist, dense
Poorly-graded SAND with Silt (SP-SM): finegrained, low plasticity, yellowish brown, moist,very dense
Silty SAND (SM): fine grained, low plasticity,yellowish brown, moist, dense
Clayey SAND (SC): fine to coarse grained, lowplasticity, yellowish brown, moist, mediumdense
Silty SAND (SM): fine to medium grained, lowplasticity, yellowish brown, moist, dense
The exploration was terminated atapproximately 30 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 20, 2014.
1
2
3
4
5
6
7
15"
17"
18"
18"
18"
18"
18"
19.8 97.5
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=162430
BC=122650/6"
BC=141717
BC=161015
BC=141415
BC=232721
BC=121721
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-3
BORING LOG B-3 PLATE
A-5
Surface Condition: Asphalt
R. HasselerLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/20/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
5 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 2 inches of asphalt
approximate 6 inches of aggregate baserock
Silty SAND (SM): fine grained, low plasticity,light reddish brown, moist, loose, (FILL)
Decomposed to highly weathered Sandstone-as Silty Sand (SM): fine grained, low plasticity,pink, dry, medium dense
reddish yellow, very dense
The exploration was terminated atapproximately 29 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 20, 2014.
1
2
3
4
5
6
7
18"
18"
11"
12"
18"
12"
2"
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=644
BC=161521
BC=2850/5"
BC=4150/6"
BC=282935
BC=1950/6"
BC=50/2"
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-4
BORING LOG B-4 PLATE
A-6
Surface Condition: Asphalt
R. HasselerLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/20/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
5 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 2 inches of decorative aggregatebaserock
Silty SAND (SM): fine grained, low plasticity,dark brown, moist, medium dense
Decomposed to highly weathered Sandstone-as Sandy Silt (ML): fine grained, low plasticity,light yellowish brown, dry, very dense, withsome fine to coarse gravel and sandstonelenses
dense, with some fine to medium gravel
very dense
dense
The exploration was terminated atapproximately 30 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 21, 2014.
1
2
3
4
5
6
7
11"
3"
18"
12"
18"
18"
18"
100 67
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=1750/5.5"
BC=50/3"
BC=151923
BC=1850/5"
BC=131418
BC=162120
BC=131622
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-5
BORING LOG B-5 PLATE
A-7
Surface Condition: Gravel
A. BordLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/21/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
6 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 3 inches of asphalt
approximate 4 inches of aggregate baserock
Silty SAND with Gravel (SM): fine to mediumgrained, low plasticity, light brown & gray, dry,very dense, with some coarse sand, fine tomedium sub-rounded to angular gravel (FILL)
brown with gray
Decomposed to highly weathered Sandstone-as Silty Sand (SM): fine grained, low plasticity,light olive brown, dry, very dense
gravel band, 1.5 feet thick, fine to coarserounded gravel
The exploration was terminated atapproximately 30 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 21, 2014.
R-Value
Direct ShearC = 198 psfØ = 31°
difficult drilling - Sandstone
1
2
3
4
5
6
7
6"
5"
46
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=3650/4"
BC=50/4.5"
BC=273341
BC=111828
BC=111317
BC=3150/6"
BC=141925
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-6
BORING LOG B-6 PLATE
A-8
Surface Condition: Asphalt
A. BordLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/21/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
6 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 1-1/2 inches of asphalt
approximate 2 inches of aggregate baserock
Silty SAND (SM): fine grained, low plasticity,gray brown, moist, very dense
medium dense
Clayey SAND (SC): fine grained, low plasticity,reddish yellow to light reddish brown, moist,dense
Silty SAND (SM): fine to coarse grained, lowplasticity, reddish brown, moist, very densedense
The exploration was terminated atapproximately 29.5 ft. below ground surface.The exploration was backfilled with augercuttings and patched at surface on November20, 2014.
Swell/Collapse
1
2
3
4
5
6
7
6"
12"
18"
18"
17"
18"
12"
3.9 91.8
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
BC=50/5"
BC=2950/6"
BC=8811
BC=141722
BC=274150/5"
BC=142250/5.5"
BC=2650/5.5"
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-7
BORING LOG B-7 PLATE
A-9
Surface Condition: Asphalt
R. HasselerLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/20/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
7 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 5 inches of asphalt
approximate 3-1/2 inches of aggregatebaserock
Silty SAND (SM): fine grained, low plasticity,yellowish brown, moist
The exploration was terminated atapproximately 5 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 20, 2014.
1
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-8
BORING LOG B-8 PLATE
A-10
Surface Condition: Asphalt
R. HasselerLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/20/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
7 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
approximate 4 inches of asphalt
approximate 4 inches of aggregate baserock
Clayey SAND (SC): fine grained, low plasticity,reddish brown, moist
The exploration was terminated atapproximately 5 ft. below ground surface. Theexploration was backfilled with auger cuttingsand patched at surface on November 20, 2014.
R-Value2
GROUNDWATER LEVEL INFORMATION: Groundwater was not encountered during drilling or aftercompletion.GENERAL NOTES:
LABORATORY RESULTS
Lithologic Description
PAGE:
FIELD EXPLORATION
1 of 1
BORING LOG B-9
BORING LOG B-9 PLATE
A-11
Surface Condition: Asphalt
R. HasselerLogged By:
Date Begin - End:
Hor.-Vert. Datum:
Weather:
Drill Crew:
Hammer Type - Drop:Not Available B-53
J.R. & R.N.
Exploration Geoservices
140 lb. Sandline - 30 in.
-90 degreesPlunge:
Drilling Company:
Drilling Method:
Drilling Equipment:
11/20/2014
8 in. O.D.
Hollow Stem Auger /
Overcast Exploration Diameter:
Add
ition
al T
ests
/R
emar
ks
Dep
th (
feet
)
5
10
15
20
25
30
Gra
phi
cal L
og
Sam
ple
Num
ber
Rec
over
y(N
R=
No
Rec
over
y)
US
CS
Sym
bol
Wat
erC
onte
nt (
%)
Dry
Uni
t Wt.
(pcf
)
Pas
sing
#4
(%)
Pas
sing
#20
0 (%
)
Liqu
id L
imit
Pla
stic
ity In
dex
(NP
=N
onP
last
ic)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Blo
w C
ount
s(B
C)=
Unc
orr.
Blo
ws/
6 in
.
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_BO
RIN
G/T
ES
T P
IT S
OIL
LO
G]
PLO
TT
ED
: 01
/12/
201
5 0
7:3
8 A
M B
Y:
jsal
a
PROJECT NO.: 20153715
Sam
ple
Typ
e
APPENDIX B
Results of Percolation Testing
OWNER/APPLICANT: Monterey-Salinas Transit PROJECT: Monterey-Salinas Transit
SITE LOCATION: 1 Ryan Ranch Road, Monterey, CA PROJECT NUMBER:
CONTACT/TELEPHONE: DATE: 11/20/14 and 11/21/14
REHS:
HOLE #: P-1 PRESATURATE DATE/TIME: 8:45:00 AM 11/20/2014
DIAMETER: 8 inches PRESATURATE WATER DEPTH: 6.40 feet
HOLE DEPTH:15.00 feet HOLE DEPTH (Next Day) /TIME: 13.40 feet
SOIL TYPE: Silty Sand and Clayey Sand WATER DEPTH (Next Day): 10.39 feet
ELAPSED WATER
TIME FALL
READING DATE START FINISH START FINISH MIN. INCHES
1 11/21/2014 12:44 12:54 47.95 54.79 10 6.840
2 11/21/2014 12:54 1:04 54.79 58.15 10 3.360
3 11/21/2014 1:04 1:14 58.15 59.95 10 1.800
4 11/21/2014 1:14 1:24 59.95 61.75 10 1.800
5 11/21/2014 1:24 1:34 61.75 63.55 10 1.800
6 11/21/2014 1:34 1:44 63.55 65.47 10 1.920
7 11/21/2014 1:44 1:54 65.47 67.27 10 1.800
8 11/21/2014 1:54 2:04 67.27 69.07 10 1.800
9 11/21/2014 2:04 2:14 69.07 70.87 10 1.800
RATE: 5.6 min/in * Slow Percolation Below 10.4 feet bgs
HOLE #: P-2 PRESATURATE DATE/TIME: 9:15:00 AM 11/20/2014
DIAMETER: 8 inches PRESATURATE WATER DEPTH: 6.72 feet
HOLE DEPTH:15.00 feet HOLE DEPTH (Next Day) /TIME: 13.52 feet
SOIL TYPE: Silty Sand and Clayey Sand WATER DEPTH (Next Day): 13.05 feet
ELAPSED WATER
TIME FALL
READING DATE START FINISH START FINISH MIN. INCHES
1 11/21/2014 9:33 9:43 79.40 87.44 10 8.040
2 11/21/2014 9:43 9:53 87.44 92.48 10 5.040
3 11/21/2014 9:53 10:03 92.48 97.64 10 5.160
4 11/21/2014 10:03 10:13 97.64 100.76 10 3.120
5 11/21/2014 10:13 10:23 100.76 104.60 10 3.840
6 11/21/2014 10:23 10:33 104.60 108.44 10 3.840
7 11/21/2014 10:33 10:43 108.44 112.16 10 3.720
RATE: 2.7 min/in * Slow Percolation Below 13.1 feet bgs
PERCOLATION
SOIL PERCOLATION TEST RECORDED MEASUREMENTS
TIME
WATER LEVEL
RATE(in)
MINUTES/INCH*
TIME
PERCOLATION
RATE(in)
1.5
3.0
5.6
5.6
5.6
3.2
2.6
MINUTES/INCH*
WATER LEVEL
5.2
5.6
5.6
5.6
1.2
2.0
2.6
2.7
1.9
OWNER/APPLICANT: Monterey-Salinas Transit PROJECT: Monterey-Salinas Transit
SITE LOCATION: 1 Ryan Ranch Road, Monterey, CA PROJECT NUMBER:
CONTACT/TELEPHONE: DATE: 11/20/14 and 11/21/14
REHS:
HOLE #: P-3 PRESATURATE DATE/TIME: 9:45:00 AM 11/20/2014
DIAMETER: 8 inches PRESATURATE WATER DEPTH: 6.58 feet
HOLE DEPTH:15.00 feet HOLE DEPTH (Next Day) /TIME: 13.18 feet
SOIL TYPE: Silty Sand and Clayey Sand WATER DEPTH (Next Day): 8.86 feet
ELAPSED WATER
TIME FALL
READING DATE START FINISH START FINISH MIN. INCHES
1 11/21/2014 11:02 11:12 1.00 26.08 10 25.080
2 11/21/2014 11:12 11:22 26.08 33.88 10 7.800
3 11/21/2014 11:22 11:32 33.88 39.28 10 5.400
4 11/21/2014 11:32 11:42 39.28 44.08 10 4.800
5 11/21/2014 11:42 11:52 44.08 48.16 10 4.080
6 11/21/2014 11:52 12:02 48.16 51.04 10 2.880
7 11/21/2014 12:02 12:12 51.04 54.04 10 3.000
8 11/21/2014 12:12 12:22 54.04 56.80 10 2.760
9 11/21/2014 12:22 12:32 56.80 59.56 10 2.760
RATE: 3.6 min/in * Slow Percolation Below 8.9 feet bgs
3.5
3.3
3.6
3.6
MINUTES/INCH*
0.4
1.3
1.9
2.1
2.5
SOIL PERCOLATION TEST RECORDED MEASUREMENTS
WATER LEVEL PERCOLATION
TIME (in) RATE
APPENDIX C
Laboratory Testing Results
B-1 4.0 LIGHT OLIVE BROWN SILTY SAND (SM) 28 24 4
B-2 2.0 BROWN CLAYEY SAND (SC) 37 16 21
B-2 3.5 GRAY BROWN SILTY SAND (SM) 16.3 107.5
B-2 8.5 - 10.0 3 YELLOWISH BROWN CLAYEY SAND WITH GRAVEL (SC) 29
B-2 13.5 - 15.0 4 LIGHT OLIVE CLAYEY SAND (SC) 24
B-3 2.0 REDDISH BROWN CLAYEY SAND (SC) 19.8 97.5
B-5 8.5 - 10.0 3 LIGHT YELLOWISH BROWN SANDY SILT (ML) 100 67
B-6 0.0 - 5.0 LIGHT BROWN AND GRAY SILTY SAND WITH GRAVEL (SM) R-Value
B-6 1.5 - 3.5 LIGHT BROWN AND GRAY SILTY SAND WITH GRAVEL (SM) Direct Shear
C = 198 psf
Ø = 31°
B-6 13.5 - 15.0 4 LIGHT OLIVE BROWN SILTY SAND (SM) 46
B-7 1.0 1 GRAY GROWN SILTY SAND (SM) 3.9 91.8
B-7 4.0 Swell/Collapse
B-9 0.0 - 5.0 2 REDDISH BROWN CLAYEY SAND R-Value
Pas
sin
g 3
/4"
Sieve Analysis (%)
Pas
sin
g #
4
Pas
sin
g #
200
Atterberg Limits
Liq
uid
Lim
it
Sample Description
Pla
stic
Lim
it
Wat
er C
on
ten
t (%
)
Dry
Un
it W
t. (
pcf
)
ExplorationID Additional Tests
Refer to the Geotechnical Evaluation Report or thesupplemental plates for the method used for the testingperformed above.NP = NonPlasticNA = Not Available
TABLELABORATORY TESTRESULT SUMMARY
C-1
Pla
stic
ity
Ind
ex
SampleNo.
Depth(ft.)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
gINT FILE: L:\2014\14projects\20153715-Mst\20153715 Blogs.gpj
gINT TEMPLATE: PROJECTWISE: KLF_STANDARD_GINT_LIBRARY_2015.GLB [LAB SUMMARY TABLE - SOIL] PLOTTED: 01/12/2015 07:40 AM BY: jsala
CHECKED BY: AB
DRAWN BY: JDS
REVISED: 12/19/2014
DATE: 12/2/2014
PROJECT NO.: 20153715
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
0.0010.010.1110100
Sample Number Sample Description LL PL PI
%SiltCu %ClayCcExploration ID Depth (ft.)
PLATE
C-2
SIEVE ANALYSIS
50HYDROMETERU.S. SIEVE OPENING IN INCHES U.S. SIEVE NUMBERS
1403 4 20 40
BO
UL
DE
R
6 601.5 8 143/4 1/212 3/8 3 10024 16 301 2006 10
Sieve Analysis and Hydrometer Analysis testing performed in general accordance with ASTM D422.NP = NonplasticNA = Not AvailableNM = Not Measured
D60 D30 D10D100Passing
3/4"Passing
#4Passing
#200
NMNM NM3
NMNM NM8.5 - 10 100NM9.5 NMNM
Exploration ID Depth (ft.)
PE
RC
EN
T F
INE
R B
Y W
EIG
HT
GRAIN SIZE IN MILLIMETERS
medium fine
GRAVEL SANDCOBBLE
coarse coarseCLAYSILT
fine
Coefficients of Uniformity - Cu = D60 / D10
Coefficients of Curvature - CC = (D30)2 / D60 D10
D60 = Grain diameter at 60% passing
D30 = Grain diameter at 30% passing
D10 = Grain diameter at 10% passing
67
8.5 - 10B-5
B-5 NM
LIGHT YELLOWISH BROWN SANDY SILT (ML)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_SIE
VE
AN
ALY
SIS
]P
LOT
TE
D:
01/1
2/20
15
07
:28
AM
BY
: js
ala
PROJECT NO.: 20153715
0
10
20
30
40
50
60
0 10 20 30 40 50 60 70 80 90 100 110
ATTERBERG LIMITS
LL PL PIPassing#200
PLATE
C-3
Exploration ID Depth (ft.)
16
24
16
NM
NM
NA
NA
4
2
CL-ML
LIQUID LIMIT (LL)
PLA
ST
ICIT
Y IN
DE
X (
PI)
CL or OL
"U" L
INE
ML or OL4
7
MH or OH
"A" L
INE
CH or OH
Sample Number
Testing perfomed in general accordance with ASTM D4318.NP = NonplasticNA = Not AvailableNM = Not Measured
Sample Description
B-1
B-2
28
37
4
21
LIGHT OLIVE BROWN SILTY SAND (SM)
BROWN CLAYEY SAND (SC)
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Chart Reference: ASTM D2487
CHECKED BY: AB
DATE: 12/3/2014
DRAWN BY: JDS
REVISED: 12/19/2014
gIN
T F
ILE
: L:
\201
4\1
4pro
ject
s\20
1537
15-M
st\2
015
371
5 B
logs
.gpj
gIN
T T
EM
PLA
TE
: P
RO
JEC
TW
ISE
: KLF
_S
TA
ND
AR
D_G
INT
_LIB
RA
RY
_201
5.G
LB
[KLF
_AT
TE
RB
ER
G (
AS
TM
)]P
LOT
TE
D:
01/1
5/20
15
12
:30
PM
BY
: js
ala
PROJECT NO.: 20153715
For classification of fine-grained soilsand fine-grained fraction of coarse-grainedsoils.
1 2 4
7.5 7.5 na
107.5 107.9 na
36.9 37.3 na
0.538 0.532 na
2.42 2.42 na
1.00 1.00 na
18.6 18.2 na
108.4 110.0 na
93.9 96.1 na
0.526 0.503 na
2.42 2.42 na
0.989 0.979 na
After
18.6 18.2 na
767 1438 na
0.060 0.080 na
707 1318 na
LL: NM PL: NM PI: NM GS: 2.65 Assumed 0.300 0.300 na
Test Conditions: Undisturbed / Inundated 0.0060 0.0060 na
Description: Light Brown and Gray Silty Sand (SM) c, psf f, deg. na
Peak 198 30.9 na
Ultimate 78 32.0 na
Remarks: nm = not measured, na = not applicable
Project No:
Date:
Tested by:
Checked By:
File Name:
Vert
ical
Dis
pla
ce
men
t (I
n.)
7.4
107.8
36.5
2576
0.300
0.477
na
2576
4000
96.4
Horizontal Displacement (in.)
Specimen Number
0.300
0.0060
Sh
ea
r S
tres
s (
psf)
0.963
0.534
2.42
1.00
17.3Water Content, %
1.5-3.5
Test Date: 12/17/14
Boring:
Sample:
Depth, ft:
Plate
Tan f
0.62
20153715
1/12/15
CP
HL7396 2601 Barrington Ct Hayward, CA
1a&2a
Dry Density, pcf
Saturation, %
Sh
ear
Str
ess (
psf)
Water Content, %
Dry Density, pcf
MONTEREY-SALINAS TRANSIT DISTRICT
OPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROAD
MONTEREY, CALIFORNIA
C-4
DIRECT SHEAR TEST ASTM
D3080
Void Ratio
Normal Stress (psf)
Diameter, in
Height, in
Normal Stress, psf 1000 2000
RH
Initia
l
Horz. Displ. at Ultimate Shear Stress, in.
Ultimate Shear Stress, psf
Horz. Displ. at Peak Shear Stress, in.
Strain Rate, in./min.
Saturation, %
Peak Shear Stress, psf
Pre
shear
B-6
Water Content, % 17.6
2.42
Void Ratio
112.0
3
Diameter, in
Height, in
0.60
Horizontal Displacement (in.)
0
500
1000
1500
2000
2500
3000
3500
4000
0.000 0.050 0.100 0.150 0.200 0.250 0.300 0.350
Normal Stress=1000 psf
Normal Stress=2000 psf
Normal Stress=4000 psf
Peak Shear Stress
Ultimate Shear Stress
0
1000
2000
3000
4000
5000
6000
0 1000 2000 3000 4000 5000 6000
Peak
Ultimate
Peak
Ultimate
-0.010
-0.008
-0.006
-0.004
-0.002
0.000
0.002
0.004
0.006
0.008
0.010
0.012
0.00 0.05 0.10 0.15 0.20 0.25 0.30 0.35
Normal Stress=1000 psf
Normal Stress=2000 psf
Normal Stress=4000 psf
s
FINAL
SAMPLE DESCRIPTION
PLATE
SIZE AND % OF
OVERSIZED MATERIAL NA
WATER TYPE & SOURCE DEIONIZED, TAP
C-5Project No.: 20153715
MONTEREY-SALINAS TRANSIT DISTRICT
OPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROAD
MONTEREY, CALIFORNIA
Pursuant to 2006 IBC Section 1704, the results presented in this report are for the exclusive
use of the client and the registered design professional in responsible charge. The results
apply only to the samples tested. If changes to the specifications were made and not
communicated to Kleinfelder, Kleinfelder assumes no responsibility for pass/fail (meets/does
BORING NO. B-7
4
ONE DIMENSIONAL SWELL*
INITIAL
DRY DENSITY, psf
WATER CONTENT, %
SAMPLE HEIGHT, in.
92.6
4.1
*PERFORMED IN GENERAL ACCORDANCE WITH ASTM D 4546
1.0000
NET COLLAPSE (-)
/SWELL (+), %
102.0
17.9
0.8992
-0.4%
Brown Silty Sand (SM)
DEPTH, ft
% C
ON
SO
LID
AT
ION
-12.0
-10.0
-8.0
-6.0
-4.0
-2.0
0.0
0.01 0.10 1.00 10.00C
OL
LA
PS
E (
-) /
SW
EL
L (+
), %
PRESSURE (Ksf)
FLOOD
R-VALUE PLATE
C-6
PROJECT NO.: 20153715
CHECKED BY: RH
DATE: 1/12/2015
DRAWN BY: JDS
REVISED:
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Project Name: MONTEREY-SALINAS TRANSIT
Project No.: 20153715
Lab No.: HL7396
Sample Date:Sample No.: Bulk B-6
Sample Location: B-6 @ 0 - 5.0'
Material Description: Brown with Gravel
Report Date:
Briquette No. A B C
Moisture at Test, % 16.6 15.7 14.8
Dry Unit Weight at Test, pcf 108.2 108.3 109.7
Expansion Pressure, psf 4 13 22
Exudation Pressure, psi 200 289 425
Resistance Value 35 55 70
57
Reviewed By on 12/18/2014:
Laboratory Manager Aaron Kidd
Laboratory Test Report
R - Value at 300 psi Exudation Pressure:
Resistance R-Value and Expansion Pressure of Compacted Soils (ASTM D2844, CTM 301)
December 18, 2014
0
10
20
30
40
50
60
70
80
90
100
0100200300400500600700800
R-V
AL
UE
EXUDATION PRESSURE, psi
Limitations: Pursuant to applicable building codes, the results presented in this report are for the exclusive use of the client and the registered design professional in responsible charge. The results apply only to the samples tested. If changes to the specifications were made and not communicated to Kleinfelder, Kleinfelder assumes no responsibility for pass/fail statements (meets/did not meet), if provided.
R-VALUE PLATE
C-7
PROJECT NO.: 20153715
CHECKED BY: RH
DATE: 1/12/2015
DRAWN BY: JDS
REVISED:
MONTEREY - SALINAS TRANSIT DISTRICTOPERATION & MAINTENANCE FACILITY
1 RYAN RANCH ROADMONTEREY, CALIFORNIA
Project Name: MONTEREY-SALINAS TRANSIT
Project No.: 20153715
Lab No.: HL7396
Sample Date:Sample No.: Bulk B-9
Sample Location: B-9 @ 0 - 5.0'
Material Description: Brown Clay
Report Date:
Briquette No. A B C
Moisture at Test, % 17.4 16.5 15.4
Dry Unit Weight at Test, pcf 111.9 0.0 111.9
Expansion Pressure, psf 4 13 22
Exudation Pressure, psi 185 270 352
Resistance Value 3 6 7
7
Reviewed By on 12/18/2014:
Laboratory Manager Aaron Kidd
Laboratory Test Report
R - Value at 300 psi Exudation Pressure:
Resistance R-Value and Expansion Pressure of Compacted Soils (ASTM D2844, CTM 301)
December 18, 2014
0
10
20
30
40
50
60
70
80
90
100
0100200300400500600700800
R-V
AL
UE
EXUDATION PRESSURE, psi
Limitations: Pursuant to applicable building codes, the results presented in this report are for the exclusive use of the client and the registered design professional in responsible charge. The results apply only to the samples tested. If changes to the specifications were made and not communicated to Kleinfelder, Kleinfelder assumes no responsibility for pass/fail statements (meets/did not meet), if provided.
Appendix D
Corrosion Testing Laboratory Results
Appendix E
Summary of Compaction Recommendations
Exhibit 1
Summary of Compaction Recommendations
Area
Compaction Recommendation (1,2,3)
General Engineered Fill Compact to a minimum of 90 percent compaction at a moisture content above the optimum moisture content. Compact fill slopes steeper than 3:1 (Horizontal:Vertical) to a minimum of 95 percent compaction at a moisture content above the optimum moisture content.
Imported Fill (4) Compact to a minimum of 90 percent compaction at a moisture content above the optimum moisture content.
Trenches (5) Compact to a minimum of 90 percent compaction at a moisture content above the optimum moisture content.
Exterior Flatwork (6) Compact to a minimum of 90 percent compaction at a moisture content above the optimum moisture content. Compact baserock to a minimum of 95 percent compaction at near the optimum moisture content.
Parking and Access Driveways (6)
Compact to a minimum of 95 percent compaction at a moisture content above the optimum moisture content. Compact baserock to a minimum of 95 percent compaction at near the optimum moisture content.
Notes: 1. All compaction requirements refer to relative compaction as a percentage of the
laboratory standard described by ASTM D 1557. 2. All lifts to be compacted shall be a maximum of 8 inches loose thickness, unless
otherwise recommended. 3. All compacted surfaces should be firm, stable, and unyielding under compaction
equipment. 4. Includes building and/or equipment pads. 5. In landscaping areas, this percent compaction in trenches may be reduced to 85
percent. 6. Depths are below finished subgrade elevation.
APPENDIX F
GBA Information Sheet