appendix b. public involvementpontiaclivability.org/pdfs/draft_final_reports/appendix...suburban...
TRANSCRIPT
Prepared for by
Appendix B. Public InvolvementDowntown Pontiac Transportation Assessment
DRAFT • June 28, 2013
DRAFT • Appendix B • i
Table of Contents
APPENDIX B: PUBLIC INVOLVEMENT PLAN ................................................................... 3
1.0 PUBLIC INVOLVEMENT APPROACH ..................................................................... 3
1.1 Public Outreach Summary ..................................................................................... 5
1.2 Project Team Meetings ............................................................................................ 7
1.2.1 Project Advisory Team ............................................................................... 7
1.2.2 Community Advisory Group .................................................................... 7
1.2.3 Public Agency Meeting .............................................................................. 8
1.3 Public Meetings Summary ...................................................................................... 9
1.3.1 Community Workshop #1, March 17, 2012 ............................................. 9
1.3.2 Community Workshop #2, June 12, 2012 .............................................. 10
1.3.3 Community Workshop #3, September 26, 2012 .................................... 11
1.4 Online Survey and Comment Forms .................................................................. 11
2.0 URBAN DESIGN CHARRETTE REPORT ............................................................... 18
2.1 Introduction ............................................................................................................ 18
2.1.1 Why Is The Loop Wrong For The Future Of Pontiac? ......................... 18
2.1.2 Why Craft A Vision? ................................................................................ 19
2.2 Overview of Recommended Improvements ...................................................... 19
2.2.1 Specific Opportunities – A Neighborhood Approach ......................... 22
2.2.2 The Southern Gateway ............................................................................. 22
2.2.3 Parke Street ................................................................................................ 23
2.2.4 Lafayette Neighborhood .......................................................................... 24
2.2.5 Woodward Ave ......................................................................................... 25
2.3 Huron Street (M‐59) ............................................................................................... 26
2.4 Complete Street Design Components ................................................................. 27
2.4.1 What are Complete Streets? .................................................................... 28
2.4.2 Achieving State Complete Street Goals ................................................. 28
2.5 Kickstarting the Process ........................................................................................ 29
3.0 LIST OF REFERENCES ................................................................................................. 45
DRAFT • Appendix B • ii
List of Tables Table B‐1: Combined Questionnaire Results ........................................................................... 13
Table B‐2: Online Survey Questionnaire Results .................................................................... 14
Table B‐3: Community Workshop # 1, March 17, 2012 Questionnaire Results .................. 15
Table B‐4: Community Workshop # 2, June 12, 2012 Questionnaire Results ..................... 16
Table B‐5: Community Workshop # 3, September 26, 2012 Questionnaire Results........... 17
List of Figures Figure B‐1: Project Home Page .................................................................................................... 5
Figure B‐2: Idea Map .................................................................................................................... 9
Figure B‐3: Recommended Alternative .................................................................................... 21
Figure B‐4: Southern Gateway .................................................................................................. 23
Figure B‐5: Parke Street .............................................................................................................. 24
Figure B‐6: Lafayette Neighborhood ........................................................................................ 25
Figure B‐7: Woodward Avenue ................................................................................................ 26
Figure B‐8: Huron Street (M‐59) ................................................................................................ 27
Acronyms Used in this Document
DDA Downtown Development Authority
ADA American with Disabilities Act
ADT Average Daily Traffic
APTA American Public Transportation Association
FTA Federal Transit Administration
MDOT Michigan Department of Transportation
LID Low Impact Development
LOS Level of Service
SMART Suburban Mobility Authority for Regional Transit
SEMCOG Southeast Michigan Council of Governments
DRAFT • Appendix B • 3
Appendix B: Public Involvement Plan
The purpose of this study is to improve the connectivity between downtown Pontiac, the
adjacent neighborhoods, and the broader community by adapting the Woodward Loop
transportation network. This transportation network includes the street, sidewalk, and bike
path system. It is envisioned that adapting the network will improve livability and the long
term economic health of the downtown and surrounding neighborhoods. Oakland County
Planning & Economic Development Services, in partnership with the City of Pontiac, applied
for and was awarded a TIGER II program of the USDOT Grant in October 2010, from which this
study is funded.
Appendix C: Public Involvement Plan (PIP) (1) summarizes Oakland County’s and City of
Pontiac’s commitment to public involvement and (2) identifies the array of public involvement
activities focused on informing the broad range of stakeholders at specific stages during the
Downtown Pontiac Transportation Assessment Study. The plan defines the methods relied
upon to invite public inquiry and comment. A comprehensive outreach program was used to
inform residents and project stakeholders of the study’s progress and provide the forum to
receive questions and comments that were reviewed as part of the decision‐making process.
This material is based upon work supported by the FHWA under Cooperative Agreement No.
P‐27. Any opinions, findings, and conclusions or recommendations expressed in this
publication are those of the Author(s) and do not necessarily reflect the view of the FHWA.
1.0 Public Involvement Approach
Starting in November 2011, over 400 stakeholders including
residents and nearly 30 groups have participated in the
Project Advisory Team (PAT), Community Advisory Group
(CAG), community workshops, planning charrette and other
local meetings. Oakland County has presented the project
findings and recommended improvements to the Pontiac
City Council, Pontiac Downtown Business Association,
Pontiac Planning Commission and to numerous Pontiac
groups including, Golden Opportunity Club, Pastoral
Alliance and Rotary.
DRAFT • Appendix B • 4
The evaluation methodology in the Public Involvement Plan was divided into three evaluation
stages, with three community workshops:
Community Workshop #1, March 17, 2012 ‐ Explain the study and identify alternatives
for the Woodward Loop.
Community Workshop #2, June 11‐13, 2012 ‐ Three day charrette to refine the
alternatives.
Community Workshop #3, September 26, 2012 ‐ Present the recommended alternative to
the public.
Prior to the public meetings and at key stages in the project schedule, the Project Advisory
Team (PAT) held six meetings to brief Oakland County, MDOT, SEMCOG, and other agencies.
Additionally, Community Advisory Group (CAG) meetings were held open to the public seven
times at the CroFoot in downtown Pontiac. An agency meeting was held on September 26,
2012, in the morning prior to Public Workshop #3. Project updates and public meeting
presentations are posted at www.pontiaclivability.org.
Public survey and comment forms were provided at Public Meetings #1 and #2. The same
survey was also made available at other meetings and on the project web site. One hundred
and eighty six (186) surveys have been collected. Survey respondents supported the following
objectives:
Make it easier and safer for pedestrians to cross Woodward
Improve sidewalks and bike paths
Improve the connection between the neighborhoods and downtown
Improve transit
Convert the Loop to two‐way traffic
Connect Saginaw to the Loop
Objectives derived from meetings include:
Improve navigation for drivers into and out of downtown
Improve accessibility to the downtown, as the Loop serves the interest of pass through
drivers better than local drivers
Figure B.1 illustrates the project home page (http://www.pontiaclivability.org/).
DRAFT • Appendix B • 5
Figure B‐1: Project Home Page
1.1 Public Outreach Summary
Oakland County hosted three public meetings on March 17, 2012, June 12, 2012 and September
26, 2012 to present the findings and evaluation results at each stage of the study. Oakland
County placed advertisements to inform the community of the proposed project and upcoming
meetings through local community newspapers and distributed notices to churches, community
groups and other affected groups in Pontiac. The community newspapers included The
Oakland County Press, Detroit News and Detroit Free Press at least one and two weeks prior to
the public meetings.
DRAFT • Appendix B • 6
Prior to the public meetings and at key stages in project schedule, the Project Advisory Team
held six meetings to brief Oakland County, MDOT, SEMCOG and other agencies during the
study. Additionally, a Community Advisory Group meeting was held open to the public seven
times during the study at the Crofoot in downtown Pontiac.
Three public meetings were held in the study area at the Crofoot, March 17, 2012 from 9‐11 a.m.,
Bowen Senior Center June 12, 4‐7 p.m. and at the Bowen Center from September 26, 2012 from
5:00 – 7:00 p.m. Public comment forms were provided at each meeting.
Oakland County chose community meeting locations that met the following criteria: the facility
must be within the study area, free of charge, wheel chair accessible, accessible by transit and
can accommodate an audience of at least 100 people. Over 300 people attended the three public
meetings and provided contact information on a sign‐in sheet.
An open house meeting format with display boards, 15‐20 minute PowerPoint presentation, and
question and answer (Q&A) period was used. Oakland County staff, members of the Project
Advisory Team, Community Advisory Group and the consultant team attended each meeting.
Attendees were given the opportunity to talk independently with project team members,
participate in Q&A and/or submit a pre‐addressed comment card.
The presentation and meeting materials were made available on the project website within
three days after each of the three public meetings.
DRAFT • Appendix B • 7
1.2 Project Team Meetings
1.2.1 Project Advisory Team
A Project Advisory Team (PAT) was formed to provide guidance throughout the feasibility
study process and provide feedback on existing conditions, economic development
opportunities, and public participation. The PAT aided in the selection of the preferred
alternative. A total of six PAT meetings were held during the project approximately bi‐
monthly. Meetings were held in public location at the Oakland County offices on the following
days.
November 3, 2011 March 1, 2012 June 13, 2012
January 12, 2012 May 17, 2012 September 6, 2012
The PAT includes representatives from Oakland County, City of Pontiac, SEMCOG, and
MDOT:
Amtrak
City of Pontiac
Federal Highway Authority
Michigan Department of Transportation
Oakland County Office of the Water Resource Commissioner
Oakland County Parks & Recreation
Oakland County Planning & Economic Development Services
Pontiac Downtown Business Association
Southeast Michigan Council of Governments
Suburban Mobility and Regional Transit (SMART)
1.2.2 Community Advisory Group
A Community Advisory Group (CAG) was formed to provide guidance throughout the study
process and provide feedback on technical studies developed during the project. The CAG
aided in review of the Woodward Loop alternatives and the selection of the preferred
alternative. A total of seven CAG meetings were held open to the public at Crofoot at 1 South
Saginaw, Pontiac, MI on the following days.
December 1, 2011 March 8, 2012 June 13, 2012 September 6, 2012
January 19, 2012 May 24, 2012 July 26, 2012
The CAG includes stakeholders representing Churches, Community and Neighborhood
Groups, Schools, Local Agencies, business and property owners, and other groups from the
Pontiac community:
All Saints Episcopal Church
Baker College
Boʹs Smokehouse
CAO Arts & Technology Academy of Pontiac
DRAFT • Appendix B • 8
Crofoot
DeCook Government & Policy Strategies
Director of Community Services and Advocacy, St. Josephʹs Oakland
Doctors Hospital of Michigan
First Presbyterian Church
Future Help Designs
Genisys Credit Union
Goldner Walsh Nursery
Greater Pontiac Sesquicentennial Commission
Grace Gospel Fellowship
HAVEN
Henk Studio
JDʹs Dueling Pianos
K&R Architectural Design
Lighthouse of Oakland County
McClaren Hospital
Murphy House
OLHSA
Oakland Community College‐ Economic & Workforce Development
Oakland University
Pontiac Chamber of Commerce
Pontiac Creative Arts Center
Pontiac School of Excellence
St. Vincent DePaul Church
TDGA Architects
Thomas Duke Realty
Todd Enterprises
Transform Pontiac Now
Urban League Director
West Construction
1.2.3 Public Agency Meeting
A Downtown Pontiac Transportation Assessment Public Agency meeting was held on
September 26, 2012 at the Bowen Center. At this meeting, background information and project
recommendations were presented to representatives from eighteen agencies. Following the
presentation, project staff was available to discuss the project in more detail with agency
representatives. A final draft of the Executive Summary Report was posted on the project
website at http://www.pontiaclivability.org/ for agencies to review and provide comments to
Oakland County by November 2, 2012. The following agencies sent representatives to the
Agency meeting:
DRAFT • Appendix B • 9
Road Commission for OC
OC Parks & Recreation
OC Water Resources Commission
OC Sheriff’s Office
MDOT
MDCH
SEMCOG
SMART
MEDC
OC Board of Commissioners
MSHDA
Senator Stabenow’s Office
Representative Tim Greimel
Pontiac Library Board
Auburn Hills
Bloomfield Township
Waterford Township
OC Executive Office
1.3 Public Meetings Summary
1.3.1 Community Workshop #1, March 17, 2012
The first public meeting was held at the Crofoot on
March 17, 2012 from 9:00am to 11am. One hundred
and six (106) people attended the meeting. The
purpose of the public meeting was to gather and
consider community input on possible alternatives to
be studied during the project. The project study area
was defined and an overview of existing conditions
on the study area was presented. A project newsletter
was distributed approximately two‐weeks before the
public meeting via email and posted on the project
website.
The majority of participants said that making it easier for
pedestrians to cross the Woodward Loop was very important,
as was connecting neighborhoods with downtown and
improving transit along Woodward Avenue to connect Pontiac
with Detroit. Pedestrian safety, improved sidewalks and bike
paths also rated high. Restoring Saginaw Street as a through
street by connecting it to the Woodward Loop rated high as a
suggestion, along with more signalized pedestrian crossings
and the addition of bike lanes on certain streets. Many people
were also interested in the economic benefits the Downtown
would gain. Another common comment was on the project
timeline with people wanting the project to move forward more
rapidly.
Participants were given a printed 11x17 Idea Map (Figure B‐2)
of the study area and asked to provide comments and suggest
alternatives to be studied on the handout.
Ninety‐one (91) comment forms were collected and reviewed by
Figure B‐2: Idea Map
DRAFT • Appendix B • 10
Oakland County staff and responses were summarized in a Frequently Asked Questions (FAQ)
document and posted to the project website.
Once posted, participants received an email, phone call or letter notifying them that the
comments and responses were now available on‐line. A contact list was created to inform
attendees on project updates and notices of upcoming community workshops.
An online survey was made available on the project web site, between March 17, 2012 and
October 31, 2012. A total of 30 responses were submitted during this period. The Online
Survey Report results are available in Section 3.4.
1.3.2 Community Workshop #2, June 12, 2012
Community Workshop #2 was held in the study area at the Bowen Center, June 12, 4pm‐7pm.
Over seventy‐five people attended the workshop. This meeting was held during a three‐day
planning Charrette held at Bowen Center, June 11‐13. During the Charrette, the project team
worked on site, complete with drafting equipment, supplies, and computers, to develop and
refine the Woodward Loop roadway alternatives. Concept plans were developed and placed
on walls for public review during the workshop. Prior to the workshop, focus group meetings
were held for local agencies, Pontiac City Council and Planning Commission. For an overview
of Charrette process see Section 2.0.
Many of the alternatives were identified and developed
from the public comments received at the March 17, 2012
workshop. A project newsletter was distributed
approximately two‐weeks before the public meeting.
The workshop presentation and display boards focused
on eleven initial alternatives and the preliminary
evaluation of the alternatives. Three roadway
alternatives were identified for further detailed analysis
and a recommendation was given for the preferred
alternative. For further information on the alternatives
see Appendix B: Transportation Assessment.
The most common comments received were in regard to three indentified alternatives and the
concept vision developed during the Charrette process. There was a strong level of support
voiced for a recommended alternative that included the two‐way conversion of Woodward
Avenue, Saginaw Street to be reconnected, and “Local” and “Main” routes for the Loop.
Participants were given a printed 11x17 map of the study area and asked to provide comments
and suggest alternatives to be studied on the handout. Nine comment maps and sixty comment
forms were received and reviewed by the project team. A contact list was created to inform
attendees on project updates and notices of upcoming public meetings.
DRAFT • Appendix B • 11
1.3.3 Community Workshop #3, September 26, 2012
The final community workshop was held in the
study area at the Bowen Center, September 26,
7pm‐9pm. Thirty seven (37) people attended the
public meeting. The presentation and display
boards focused on the detailed evaluation of the
recommended alternative from workshop #2.
The most common comments received were in
regard to what happens next, how people can
help, recommended alternative costs and how
long it could take to be constructed.
Attendees were also encouraged to continue their support of the project and to continue to
submit comments. The comment period would remain open and draft executive summary
report was announced to be posted on the project web site. Five comment forms were collected.
A contact list was created to inform attendees on any future project updates.
1.4 Online Survey and Comment Forms
Three comment forms with survey questions were developed and made available at community
workshops during the study. An online survey was also made available on the project web site
between March 17, 2012 and October 31, 2012. After each community workshop and online, the
public was asked the following questions:
What is Important to you?
(Very Important, Important, Neutral/Not Sure, Not very Important, and Not Important At All)
Making it easier for pedestrians to cross the Woodward Loop
Slowing down traffic speeds along the Woodward Loop
Improving sidewalks and bike paths
Improving safety for pedestrians
Better connecting neighborhoods with downtown
Improving transit along Woodward to connect Pontiac with Detroit and places in
between
What do think of the ideas below?
(Prefer it, Worth Considering, Neutral/No opinion, I need convincing, and Oppose the idea)
Keep the Woodward Loop as is
Convert the Woodward Loop to 2‐way traffic
Reduce the number of traffic lanes in the Woodward Loop
Restore Saginaw as a through street by connecting it to the Woodward Loop
Add bike lanes to certain streets
Make all streets in downtown Pontiac for 2‐way traffic
Add more signalized pedestrian crossings along the Woodward Loop
Add more on‐street parking downtown
DRAFT • Appendix B • 12
A total of one hundred and fifty six (156) comment forms and thirty (30) survey responses were
submitted during the project. The responses to the above questions were reported at intervals
during the project and summarized in total, as shown in Table C‐1.
During the Community Workshop #2, the public was also asked to evaluate the three
recommended alternatives on the comment form:
What do you think of the 3 recommended Alternatives?
(Prefer it, Worth Considering, Neutral/No opinion, I need convincing, and Oppose the idea)
Alternative 5: Woodward Road Diet/Two Way, and Saginaw Reconnected
Alternative 7: Woodward Two Way and Saginaw Reconnected
Alternative 10: Woodward Two Way, Saginaw Reconnected, “Local” and “Main” Routes
During the Community Workshop #3, the public was asked to evaluate the recommended
alternative:
What do think of the Recommended Alternative?
(Prefer it, Worth Considering, Neutral/No opinion, I need convincing, and Oppose the idea)
Woodward Two Way with ʺLocalʺ and ʺMainʺ Routes Saginaw Reconnected
Tables B‐2 to B‐5 summarizes the public responses for the online survey and the comment forms
at the three community workshops.
DRAFT • Appendix B • 13
Table B‐1: Combined Questionnaire Results
Note: *No response indicates the questionnaire was blank
DRAFT • Appendix B • 14
Table B‐2: Online Survey Questionnaire Results
Note: *No response indicates the questionnaire was blank
DRAFT • Appendix B • 15
Table B‐3: Community Workshop # 1, March 17, 2012 Questionnaire Results
Note: *No response indicates the questionnaire was blank
DRAFT • Appendix B • 16
Table B‐4: Community Workshop # 2, June 12, 2012 Questionnaire Results
Note: *No response indicates the questionnaire was blank
DRAFT • Appendix B • 17
Table B‐5: Community Workshop # 3, September 26, 2012 Questionnaire Results
Note: *No response indicates the questionnaire was blank
DRAFT • Appendix B • 18
2.0 Urban Design Charrette Report
2.1 Introduction
From June 11th – 13th, 2012, a three‐day intensive
planning and design workshop was held at the
Bowen Senior Center in Pontiac, Michigan. The
purpose of the event was to develop and analyze
potential improvements for the Woodward Loop
in downtown Pontiac for improving connectivity,
enhancing livability and creating economic
opportunity. To that end, existing roadway
infrastructure and traffic patterns were examined
in an effort to identify solutions for reconfiguring
the Loop to improve the public realm and experience for all modes of travel and to create a
more conducive climate for attracting economic development into downtown Pontiac.
The workshop brought together planners, designers, transportation specialists, government
officials and engineers to collaborate on‐site with key stakeholders. Members of the public were
invited to participate throughout through meetings and open houses. An interactive dialogue
was cultivated and public input was factored into the design process as the team developed
visions for every quadrant of the downtown and for the project area as a whole.
2.1.1 Why Is The Loop Wrong For The Future Of Pontiac?
The rationale for constructing the Woodward Loop in the 1960’s Loop may well have been
warranted based the degree of growth expected in this region in the latter half of the 20th
Century. However, demographic and economic trends have changed, resulting in far lower
traffic volumes along this arterial than once projected. Today, rather than connecting Pontiac’s
neighborhoods and destinations, as a key transportation corridor should, the Loop segregates
Downtown Pontiac from surrounding neighborhoods and communities – choking economic
growth, cutting off the businesses from surrounding neighborhoods, and leaving small
residential pockets isolated from community context and amenities.
Early on in the Downtown Transportation Assessment, the Pontiac community identified the
Woodward Loop as a major barrier to both access and activity in Downtown Pontiac. The one‐
way four‐lane right‐of‐way promotes high‐speed travel, creating a formidable physical barrier
to pedestrians and motorists who want to access downtown.
Confusing or non‐existent connections to downtown streets result in a lack of connectivity to
downtown from surrounding areas. . The Loop consists of two one‐way pairs formed by
Woodward Avenue and the Woodward Loop Road (formerly Parke Street). These one‐way
arterials are very effective at moving traffic quickly around downtown Pontiac. The
configuration actually forces travelers to go out of their way or double‐back to get to
DRAFT • Appendix B • 19
downtown. A series of one‐way streets within the downtown and limited wayfinding further
hamper access. The result is a once vibrant economic center that has become an isolated island,
cut‐off from surrounding communities. Additionally, there are no clear or celebrated entrances
to downtown Pontiac on the Loop road; without prior knowledge, one might not even know
that a downtown Pontiac exists.
2.1.2 Why Craft A Vision?
In order to enhance livability in the vicinity of downtown Pontiac, this study seeks to improve
connections to downtown, neighborhoods and the broader community by readapting the Woodward Loop
and improving the street, sidewalk, public open space and bike path system.
Roads are a critical element in shaping the
character of any place. In that capacity, in
addition to carrying traffic, they should
emphasize their ability to access destinations;
make connections, enable community and
economic activities and serve as a vital
component of the public realm. The Woodward
Loop, while it functions effectively as a travel
through‐route for traffic, fails to achieve this goal
of enhancing a larger sense of place. By looking
at the road network as a component of the larger urban context, the workshop set out to
articulate and visualize what the proposed changes to the Loop could do to enliven downtown,
reconnect it to surrounding neighborhoods, foster pedestrian and bicycle movement and
catalyze economic development.
In crafting the vision, the team emphasized building upon past studies to set the stage for future
efforts, as well as community input over the course of the workshop.
2.2 Overview of Recommended Improvements
Multiple alternatives for changing the vehicular traffic patterns for the Loop road were
envisioned and analyzed. Of these, Alternative 10 emerged as the most effective approach to
the Loop over the course of the workshop. In June 2012, Alternative 10 was chosen as the
Recommended Alternative from the original 11 alternatives developed and shall be known as
‘the Recommended Alternative’ in the remainder of this appendix. The Recommended
Alternative is a balanced improvement that serves the needs of all; including Pontiac, the State,
surrounding communities, DBA, and neighborhoods. The Recommended Alternative consists
of:
A two‐way conversion of the entire Woodward Loop
o a four to five lane cross section on the west side serving as a through route and
retaining the name Woodward Avenue
DRAFT • Appendix B • 20
o a two to three lane cross section with parking (where appropriate) on the east
side serving as a local street named Parke Street. This type of facility fits the
downtown and neighborhood context and functions as a local street with an on‐
road cycle track and some on‐street parking.
Enhanced bicycle and pedestrian amenities
o completion of the sidewalk network
o two‐way on‐road cycle track on east side (Parke Street)
o two‐way shared use path on the west side (Woodward Avenue)
o addition of a narrow landscaped median where feasible
o rerouting the Clinton River Trail through downtown Pontiac using Pike Street
Connection of Wesson Street across Woodward Avenue
Creation of a “Gateway” at the southern end of the Woodward Loop
For further information on the Recommended Alternative see Appendix A: Transportation
Assessment.
DRAFT • Appendix B • 21
Figure B‐3: Recommended Alternative
DRAFT • Appendix B • 22
2.2.1 Specific Opportunities – A Neighborhood Approach
The Recommended Alternative allows the Loop flexibility in response to the different parts of
the City, adapting to surrounding contexts whether a corporate office area, mixed‐use
downtown, government area or residential community.
Currently, the area within the Loop, which is easily traversed by a ten minute walk, is
bifurcated into three distinct sections, the Southern gateway, downtown and the Lafayette
Neighborhood. Each distinct zone struggles to survive without the benefit of connections to the
surrounding community, or even to each other despite their close proximity. The proposed
changes to the traffic patterns, roadway design and streetscape for each of the areas can bring
these disparate communities together to operate as a single diversified economic engine and can
help catalyze the vision for development and public realm improvements for each area.
The sections in the following pages show how changes to the Loop road might catalyze larger
change for downtown. In addition to this visioning process, the team examined the Loop road
segment by segment, considering the desired design improvements in the context of the
anticipated vehicular traffic requirements based on the traffic analysis of the recommended
alternative. The following sections illustrate recommended conceptual designs for each distinct
segment of the Loop road.
2.2.2 The Southern Gateway
Due to the configuration of the Loop, local land uses and disconnected street patterns, the
southern end of downtown is completely cut‐off from the remainder of the City. Several
opportunities for developing the Southern gateway exist, including two large office buildings
that could become the core of the business district, a number of vacant and underutilized
parcels, and proximity to the newly renovated Amtrak Station. Long‐term plans to bring in Bus
rapid transit (BRT) at or near this location are currently being studied, potentially positioning
the Southern Gateway as a major regional transit‐ node. With improved access, visibility and a
stop for both rail and BRT, this area could become a strong gateway into Pontiac from the
South, supporting a Main Street oriented downtown with its own set of attractions.
DRAFT • Appendix B • 23
Figure B‐4: Southern Gateway
2.2.3 Parke Street
The main idea behind the Parke Street plan is to reduce the width of the road to better integrate
it into the surrounding neighborhoods. In this plan, the eastern side of the Loop has been
downsized to respond to the adjacent land uses and to integrate into the surrounding
community. Renamed Parke Street to correspond to the pre‐Loop road designation, this urban
boulevard concept would allow two‐way traffic, one lane in each direction, as opposed to the
current four lane one‐way condition. This segment passes by many current and past civic
destinations in Pontiac, including the library, the former city hall, and the complex of
government buildings which are perched on a grassy promontory adjacent to Parke Street.
Parke Street is also the proposed location for a critical connector the Clinton River Trail bicycle
route. Re‐envisioning the Clinton River in some form will help to integrate nature and
historical context and could serve as a significant park amenity that could be carried through
much of downtown. The presence of the trail, concentration of civic uses, and large amount of
underutilized land adjacent to the road (parking and vacant), make this a prime opportunity for
expanding Pontiac’s open space system and connecting a series of open spaces through Parke
Street. The Loop road is re‐envisioned as the central hub of this park corridor with bicycle and
pedestrian facilities and variety of parks and civic spaces along the route. The prime open space
DRAFT • Appendix B • 24
becomes a desirable front door to new development and a welcoming gateway to downtown
from the east.
Figure B‐5: Parke Street
2.2.4 Lafayette Neighborhood
The Lafayette neighborhood is sandwiched between M‐59 (Huron Street) and the northern
swing of the Loop. M‐59 (Huron Street) creates a barrier between the downtown and the
Lafayette Neighborhood. The northern section of the Loop cuts through a large, primarily
residential community that once fed the downtown, creating two isolated residential enclaves.
Cut‐off from schools, parks and other neighborhood amenities, these residential islands have
suffered abandonment and lost any sense of the larger community that they were once
connected to. Re‐envisioned as an urban Boulevard with a planted median, wide sidewalks, a
cycle track, enhanced crosswalks, and some on‐street parking, the Loop is transformed from an
barrier to a connector, providing neighborhoods with aesthetic and recreational amenities, and
opening up the northern end of downtown for residential and neighborhood‐oriented retail
development. Reconnecting Lafayette Street between the two isolated residential areas will help
to solidify the northern section of Pontiac as an emerging residential district and establish a
main east‐west connection through this part of town. There is ample room to create larger
DRAFT • Appendix B • 25
density residential developments in order to create a critical mass to support local retail,
restaurants and neighborhood‐scaled boutique shopping opportunities. The expansion of the
residential neighborhoods so close to the center of town will help to create a 24‐hour presence in
downtown and establish a market for neighborhood‐scale commercial development.
Figure B‐6: Lafayette Neighborhood
2.2.5 Woodward Ave
The western segment of the Loop will need to carry the bulk of through traffic and
accommodate connections to key east‐west corridors such as Huron Street. However, it can still
function as a complete street that enhances the overall connectivity of Pontiac’s downtown
street network. Creating safe, legible intersections for all road users (pedestrians and cyclists as
well as cars). Will be critical to enhancing the connectivity and encouraging development of
vacant parcels along Woodward Avenue. A legible street hierarchy can help prioritize
intersections for different modes of travel, with east‐west crossings for pedestrians being most
critical at the train and potential future BRT stations. An important consideration will be
connecting across downtown to tie together the neighborhoods east and west of the Loop.
DRAFT • Appendix B • 26
The properties located the internal eastern side of Woodward Avenue is a large parking lot (Lot
9) that has high potential for development. On the western side of Woodward Avenue, the land
area between Woodward Avenue and the Amtrak line serve minimal utility due to their
compromised lot depth, topographical issues and proximity to the rail.
However, one vision developed as part of the visioning exercise created a linear park space
along Woodward Avenue. A bus rapid transit intermodal terminal was also recommended a
possible alternative on west side of Woodward.
Figure B‐7: Woodward Avenue
2.3 Huron Street (M-59)
Like the vision for the Loop Road, the vision for Huron Street / M‐59 corridor is to make it a
route to downtown Pontiac while accommodating through traffic. While efficient through
vehicular traffic movement needs to be maintained as it is a key component of the local and
regional roadway network, the road needs to serve downtown Pontiac as well. Street and urban
design elements will be used to slow traffic within the Loop road and indicate to drivers their
arrival in downtown. The notion would be to provide cues along Huron Street as you enter,
traverse and exit Pontiac that clearly show that as a driver, you have entered a unique location
DRAFT • Appendix B • 27
or place within the longer corridor. Street furniture, landscaping, pavement treatments and the
introduction of on‐street parking can fundamentally change the experience for the driver
without altering roadway capacity and change the complexion of the area and the perception of
the driver. Improvements to the pedestrian realm and the redevelopment of strategic lots as
open space can signalize renewed public investment in Pontiac and provide physical
infrastructure to catalyze developer interest and investment in downtown.
Figure B‐8: Huron Street (M‐59)
2.4 Complete Street Design Components
A street redesign alone cannot generate the changes envisioned for downtown and its
surrounding neighborhoods – this will take action and investment of time and resources from
many partners. That being said, improvements to Pontiac’s transportation infrastructure can set
a strong framework and form the basis for future change. Investing in the infrastructure to
create a livable downtown can be a key catalyst for development and further reinvestment.
A key step in rethinking the Loop and opening up new opportunities for downtown will be the
actual design of the roadway corridor. In order to foster the development and livability
improvements envisioned for the neighborhoods surrounding it, the Loop road must become a
complete street.
DRAFT • Appendix B • 28
2.4.1 What are Complete Streets?
Complete streets are “…roadways planned, designed, and constructed to provide appropriate
access to all legal users in a manner that promotes safe and efficient movement of people and
goods whether by car, truck, transit, assistive device, foot, or bicycle” (Michigan Public Act 135).
Attention to the design of both the roadway and the streetscape, particularly the amenities
offered pedestrians, cyclists and motorists alike, will be critical in transforming the Loop into a
complete street and achieving the connectivity and use goals of the project. Key elements for the
redesign of the Loop road and downtown street network include:
Safe and comfortable pedestrian and bicycle facilities along the entire Loop road and
connect them to a city‐wide bicycle and pedestrian network
A street hierarchy for downtown that allows streets to be prioritized for different modes
of travel to assist in developing a better bicycle, pedestrian and transit network.
Intersections that are safe and accessible for all users by using a variety of techniques
including
Wide and well‐marked crosswalks,
Pedestrian‐friendly signal timing,
Enhancements at intersections that reduce crossing distances for pedestrians including
bump outs and refuge islands
Minimal curb radii for the local (Parke Street) area
Open space integration into the roadway corridor by using underutilized land within
the ROW as well as vacant adjacent parcels for parks, playgrounds and other public
uses.
Wayfinding that directs travelers on the Loop to destinations in downtown Pontiac
Incorporating these elements into roadway improvements will enable transportation
investments to catalyze a larger revitalization vision for downtown Pontiac. Keeping in mind
the Loop’s importance as a connector and a place that serves all modes of travel and provides
access to destinations in the city will help guide roadway design decisions to support the larger
vision for downtown.
2.4.2 Achieving State Complete Street Goals
On July 26, 2012, the State Transportation Commission approved Michigan’s new Complete
Streets Policy, which provides the Michigan Department of Transportation (MDOT) with
guidance for “the planning, design, and construction or reconstruction of roadways or other
transportation facilities in a manner that promotes complete streets as defined by the law, and
that is sensitive to the surrounding context” (State Transportation Policy on Complete Streets).
Under this new Policy, MDOT will need to “pursue a proactive and consistent approach to the
development of complete streets” and will be required to “consider complete street features for
DRAFT • Appendix B • 29
roadways and other transportation facility construction or reconstruction projects it
undertakes.”
As a state road, any changes or alterations to the Loop road will be subject to the requirements
of the Complete Streets Policy. So, in addition to helping Pontiac set the public realm
framework to achieve the development vision for downtown, the recommendations made in
this study will also help the state achieve its vision for complete streets, which includes:
A transportation network that is accessible, interconnected, and multimodal and that
safely and efficiently moves goods and people of all ages and abilities throughout the
State of Michigan.
A process that empowers partnerships to routinely plan, fund, design, construct,
maintain and operate complete streets that respect context and community values.
Outcomes that will improve economic prosperity, equity, accessibility, safety, and
environmental quality.
for the complete text of the state’s Complete Streets Policy see:
http://www.michigan.gov/documents/mdot/MDOT_CS_Policy_390790_7.pdf
For further information on complete streets see Appendix D: Complete Streets Best Practices
Report.
2.5 Kickstarting the Process
While big visions can take a long time to realize, and change in Downtown Pontiac may not
happen tomorrow, many of the opportunities identified during the workshop are projects that
can be implemented in stages, building to a sum that is greater than its parts. There was a
conscious effort during the workshop to identify improvements that might be made in the
short‐term with relatively minimal investment that can then be expanded or enhanced as
funding and permits become available, such as:
1. The proposed bicycle facilities on the Loop. On the east side of the Loop, the proposed
traffic reconfigurations and cycle track can be accommodated within the existing curb
dimensions of the roadway, through signal changes and restriping; no physical
reconstruction of curbs or roadbed would be required.
2. The cycle track (on the route of the existing greenway) could be separated from traffic by
a landscaped buffer and other enhancements made, improvements that could be phased
in over time while the basic amenities are put in place early on.
This strategy, of setting interim versions of the traffic and streetscape changes in place, while
the necessary resources are mobilized for more permanent improvements can help kickstart the
process in a more rapid time frame. Events and temporary projects that pilot more involved
transportation changes can also be effective strategies for engaging stakeholders, testing
interventions, and garnering support for more permanent interventions. By giving people a
sense of what changes can be like in real space, they can help make visions and planning ideas
more real and test the real‐world feasibility and suitability of proposed interventions.
DRAFT • Appendix B • 30
This approach can be applied to both the roadway and other public realm opportunities.
Relatively inexpensive suggestions that can be implanted in the short term but have the
potential include:
Reducing lanes and restriping segments of the Loop to include a bicycle path (two‐way
cycle track)
Hosting open street events on the Loop or downtown streets that close segments of
roadway for a day, or regularly over a season
Pop‐up parks in vacant or underutilized land along the Loop
Events, such as summer movies in underutilized parking areas of vacant sites
downtown and along the Loop
The following resources provide many examples and useful information about how to
implement your own pilot projects, tactical interventions, and events in the public right‐of‐way:
The Open Streets Project: Open streets initiatives temporarily close streets to automobile
traffic, so that people may use them for walking, bicycling, dancing, playing, and socializing.
With more than 80 documented initiatives in North America, open streets are increasingly
common in cities seeking innovative ways to achieve environmental, social, economic, and
public health goals. (http://openstreetsproject.org/)
Build a Better Block: Cities around the U.S. are looking for tools to help redevelop communities
that enable multi‐modal transportation while increasing economic development, and reducing
carbon emissions. The “Better Block” project is a demonstration tool that acts as a living
charrette so that communities can actively engage in the buildout process and provide feedback
in real time. (http://betterblock.org/)
Tactical Urbanism reader, volumes 1 & 2: Improving the livability of our towns and cities
commonly starts at the street, block, or building scale. While larger scale efforts do have their
place, incremental, small‐scale improvements are increasingly seen as a way to stage more
substantial investments. This approach allows a host of local actors to test new concepts before
making substantial political and financial commitments.
(http://issuu.com/streetplanscollaborative)
Building Communities through Transportation: The Project for Public Spaces provides
resources for how the planning and design of transportation networks and streets can be
reshaped to encourage economic vitality, civic engagement, human health, and environmental
sustainability, in addition to serving peoples’ mobility needs. (http://www.pps.org/reference‐
categories/building‐community‐through‐transportation/)
DRAFT • Appendix B • 45
3.0 List of References
City of Pontiac and the Downtown Development Group. 1962. Downtown Pontiac, Book I,
Dynamics: The Decisive Facts Program of Action for Rebuilding.
Southeast Michigan Council of Governments (SEMCOG). 1997. SEMCOG Traffic Safety Manual,
2nd Edition.
State of Michigan UD‐10 Traffic Crash Report Instruction Manual, revised in September 1994.
Transportation Research Board National Research Council. 2000. Highway Capacity Manual.
Michigan Traffic Crash Facts. 2012. State of Michigan Office of Highway Safety Planning.
<http://www.michigantrafficcrashfacts.org>