appendix 11 kingswood playing field interpretation report...
TRANSCRIPT
Appendix 11
Kingswood Playing Field Interpretation
Report on Ground Investigation
63
Geotechnical Engineering Ltd Centurion House, Olympus Park Quedgeley, Gloucester. GL2 4NF 01452 527743 www.geoeng.co.uk
KINGSWOOD PLAYING FIELD
INTERPRETATIVE REPORT ON GROUND INVESTIGATION
Prepared for KINGSWOOD PARISH COUNCIL
Report Ref: 27979
64
Geotechnical Engineering Limited
www.geoeng.co.uk
2718
KINGSWOOD PLAYING FIELD
INTERPRETATIVE REPORT ON GROUND INVESTIGATION
Prepared for KINGSWOOD PARISH COUNCIL
Report Ref: 27979
PROJECT: Kingswood Playing Field
CONSULTANT: Complete Design Partnership VOLUME - VERSION STATUS ORIGINATOR CHECKER APPROVED DATE
1 of 1 – A DRAFT SCo CT - 19/06/2013
1 of 1 - A FINAL SCo CT CT 26/06/2013
ORIGINATOR APPROVER
Sophie Collins BSc (Hons) MSc CGeol EurGeol FGS Principal Geotechnical Engineer
Colin Thomas BSc PhD FGS Geotechnical Consultant
The report is not to be used for contractual or engineering purposes unless this sheet is signed and the
report designated “Final”. The report has been prepared for the sole use and reliance by Kingswood Parish Council. GEL accepts no
liability as a result of the use or reliance of this report by any other parties.
65
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page i
CONTENTS
REPORT PAGE
1. INTRODUCTION ............................................................................................................1
2. SITE LOCATION, DESCRIPTION AND GEOLOGY ............................................................2
3. PROPOSED WORKS ......................................................................................................3
4. GROUND INVESTIGATION ............................................................................................3
4.1 Fieldwork ..................................................................................................................3
4.2 Logging .....................................................................................................................5
4.3 Laboratory Testing ...................................................................................................5
5. DISCUSSION AND CONCLUSIONS .................................................................................7
5.1 Ground Conditions ...................................................................................................7
5.2 Geotechnical Appraisal ..........................................................................................10
5.2.1 Made Ground......................................................................................................10
5.2.2 Charmouth Mudstone ........................................................................................12
5.3 Excavations .............................................................................................................14
5.4 Pavement Design ....................................................................................................14
5.5 Soakaway Design ....................................................................................................15
5.6 Drainage Recommendations ......................................................................................16
6. REFERENCES ...............................................................................................................18
FIGURES Nos.
LOCATION PLAN 1
EXPLORATORY HOLE LOCATION PLAN 2
66
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page ii
APPENDICES
APPENDIX A FIELDWORK DATA
APPENDIX B LABORATORY TESTING
APPENDIX C GEOTECHNICAL DATA
67
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/07/12 JH Report Ref: 27979 Page 1
1. INTRODUCTION
It is proposed to undertake works to improve the drainage of existing playing fields and
construct a new car parking area at Kingswood Playing Fields, Kingswood, Wotton-under-
Edge. Geotechnical Engineering Limited (GEL) was instructed by Complete Design Partnership
acting on behalf of Kingswood Parish Council to carry out an investigation to determine the
ground conditions.
The scope of work and terms and conditions of appointment were defined in
correspondence by GEL, reference T16687 dated 21st February 2013.
This report describes the investigation, presents the findings and comments accordingly.
The comments given in this report and the opinions expressed assume that ground
conditions do not vary beyond the range revealed by this investigation. There may
however, be conditions at or adjacent to the site, which have not been disclosed by the
investigation and which, therefore, have not been considered in this report. Accordingly, a
careful watch should be maintained during any future ground works and the
recommendations of this report reviewed as necessary.
Many aspects of the proposed development have yet to be agreed/determined. The
comments given in this report should therefore be considered in the context of a general
overview of the site. It is recommended that the report is reviewed when the design is
finalised.
The recommendations given in this report should not be used for any other schemes on or
adjacent to this site without further reference to GEL.
68
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 2
2. SITE LOCATION, DESCRIPTION AND GEOLOGY
The site is situated at Kingswood Playing Fields, Wickwar Road, Wotton-under-Edge,
Gloucestershire and may be located by its National Grid co-ordinates ST 744 916. A site
location plan is provided as Figure 1.
A site walkover survey was undertaken on 11th April 2013.
At the time of the site walkover, the site was found to comprise a variety of playing field
areas (football and cricket pitches), a village hall, children’s playground areas and car
parking areas/areas of hardstanding (around the village hall – access road) of
approximately two to three hectares in total area. Several small buildings (pavillion and
observation huts) were noted around the main football pitch area. The site is accessed via
a dedicated driveway from Wickwar Road through a barrier. Topographical survey
information provided for the site indicates a slight sloping downwards to the west,
however visual observation would indicate that the site is essentially flat.
The site was found to be surrounded by open fields to the north, east and west, being
bordered by residential gardens to the south. Several mature trees were noted along the
site boundaries with the site being bounded by hedgerows of between 1.5 to 2.0m in
height.
No visual or olfactory signs of contamination were observed.
The site was found to be wet underfoot at the time of the walkover and drainage ditches
were noted along the site boundaries (noted to be partially full of water). It is assumed
(although no evidence was observed) that water from these drainage ditches drains into
the local surface water sewer drainage. Anecdotal evidence provided by the Client and
Complete Design Partnership indicates that the playing fields have a history of and
69
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 3
ongoing issue of waterlogging, at times causing parts of the pitches to be
unusable/unplayable.
British Geological Survey (BGS) England and Wales (Sheet No. 264, Bristol:) and the BGS
online geology (1:50,000) indicate the site is underlain by the Charmouth Mudstone
Formation (formerly Lower Lias Clay). Examination of the BGS 1:10 000 mapping for the area
(Sheet number ST 79 SW) confirms the above with additional detail/description given for the
site area of “Clay soil with limestone fragments”.
3. PROPOSED WORKS
Due to the ongoing issues of waterlogging and poor drainage of the existing sports
pitches, appropriate drainage solutions are required to remove excess water and to
ensure the pitches remain suitable for use at all times of the year. A proposed new car
parking area is also required on the site. At the time of preparing this report, details of
the likely remedial drainage solutions have not been agreed. This report will provide
ground investigation data and preliminary design parameters, together with
recommendations to enable the optimum selection and design of remedial drainage
option(s) and to facilitate the pavement design of the proposed car parking area.
4. GROUND INVESTIGATION
4.1 Fieldwork
The fieldwork was carried out in general accordance with BS5930:1999+A2:2010 on 29th April
2013 and comprised six machine dug trial pits, two soakaway tests and six dynamic cone
penetrometer (DCP) tests.
70
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 4
The exploratory holes locations were selected and set out by this Company and are shown
on Figure 2. The ground level and co-ordinates at each exploratory hole location were not
established.
The trial pits, referenced TP01 to TP06 (Appendix A), were formed by a wheeled excavator
with a 0.60m wide backactor bucket. Trial pit logs are presented in Appendix A.
The ground surface at TP01 to TP06 consisted of grassed (turf) areas. Breaking out prior to
excavation was not required.
Representative disturbed samples were taken and retained in sealed plastic bags and
airtight containers to retain moisture content.
Hand vane tests were carried out in suitable cohesive material. The results are presented
on the trial pit logs and tabulated in Appendix A.
Soakaway tests were carried out in trial pits TP03 and TP05 in general accordance with
BRE 365 (2007). The excavation sides were squared using the excavator bucket and the
dimensions recorded within the test section. The trial pit was partially filled with clean
water using a dedicated bowser with a 75mm diameter outlet and the fall in level
recorded against time. The test was undertaken only once in each pit due to the
extremely slow rate of infiltration observed. The results are presented in Appendix A.
On completion all trial pits were backfilled with arisings compacted in suitable layers by
the excavator bucket. The ground surface was left slightly proud to accommodate the
future inevitable settlement of the backfill.
Dynamic Cone Penetrometer tests (DCP), referenced DCP01 to DCP06 (Appendix A), were
carried out using a CNS Farnell A2465 dynamic cone penetrometer. Probe depths were
71
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 5
measured with respect to ground level and the number of blows for the penetration of
the probe was recorded. Equivalent CBR values have been calculated and presented with
the results in Appendix A.
On completion of fieldwork all samples were brought to this Company's laboratory for
testing and storage.
4.2 Logging
The logging of soils and rocks was carried out by an Engineering Geologist in general
accordance with BS5930:1999+A2:2010. A key to the exploratory hole logs is presented in
Appendix A.
Detailed descriptions of the samples are given in the trial pit logs, Appendix A, along with
details of sampling, in situ testing, groundwater ingress and relevant comments on drilling
techniques.
Hand vane tests were carried out on suitable samples. The results are summarised on the
trial pit logs and tabulated in Appendix A.
4.3 Laboratory Testing
A schedule of laboratory tests was prepared by this Company, the following tests being
carried out in accordance with BS1377:1990, unless stated otherwise. The number in
brackets refers to the test number given in that standard. The results are presented in
Appendix B.
72
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 6
The natural moisture content [Part 2:3.2] was determined on twenty two selected
samples.
Liquid limit, plastic limit and plasticity index tests [Part 2:4.3, 5.3 and 5.4] were carried out
on six selected samples. An Atterberg line plot has also been presented.
Particle size distributions were determined for two samples by wet sieving [Part 2:9.2].
The fine fractions of both of these samples were further analysed by sedimentation using
the pipette method [Part 2:9.4]. The results are presented as grading curves.
73
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 7
5. DISCUSSION AND CONCLUSIONS
5.1 Ground Conditions
The ground conditions revealed by the investigation generally confirm the strata indicated
by the geological records.
The ground conditions encountered in the exploratory holes are described in detail in the
exploratory hole logs presented in Appendix A. The general sequence of strata encountered
on the site is presented in Table 5.1 below.
Table 5.1 – Ground Summary
Stratum Age Stratum
Name
Typical Description(s) Approx depth to top
of stratum (m below
ground level (bgl))
Approx thickness
(m) 1, 2
Recent Made
Ground
(possibly
Topsoil)
Turf over firm SILT and CLAY (see
below and section 5.2 for detailed
descriptions)
Ground level Up to 0.85m (typically
0.15-0.30m, 0.85m in
TP03)
Jurassic Charmouth
Mudstone
Formation
(formerly
Lower Lias
Clay)
Stiff to very stiff (rarely firm)
CLAY (see below and section 5.2
for detailed descriptions)
0.15-0.20 (0.85m in
TP03)
Up to 2.2m encountered
(<2.2m)
Notes
1 thickness ranges based on data obtained from ground investigation, actual range of thicknesses may vary.
2 Base of stratum not proven
Made Ground (possibly Topsoil) was identified within all of the exploratory holes.
Encountered thicknesses typically ranged from 0.15-0.30m (0.85m observed in TP03).
74
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 8
The Made Ground comprised turf over firm, greyish brown slightly sandy, slightly gravelly silt
with frequent roots and rootlets and firm greyish brown mottled orangish brown and bluish
grey, slightly gravelly clay (below 0.3m in TP03 only). The gravel constituent was found to
consist of subangular and subrounded fine and medium quartzite, mudstone, sandstone and
rare brick fragments. Rare medium gravel sized pockets of yellowish brown coarse sand were
observed in TP06. A land drain consisting of a 60mm diameter orange clay pipe was observed
at 0.60m depth within the Made Ground encountered in TP03.
Material described as Charmouth Mudstone (formerly known as the Lower Lias Clay) was
identified within all of the exploratory holes. Encountered thicknesses ranged from 0.95m -
2.2m. The base of the Charmouth Mudstone was not proven in any of the exploratory holes.
The Charmouth Mudstone was found to comprise up to 2.2m of stiff (rarely firm) orangish
brown, becoming light grey mottled orangish brown, slightly sandy, silty stiff clay overlying
very stiff thinly laminated dark bluish grey and grey slightly sandy clay with frequent fine to
coarse gravel sized calcareous mudstone lithorelicts, rare to frequent fossil fragments and low
to high limestone cobble content. A band of light grey subangular limestone cobbles and
boulders was encountered between 1.40 and 1.53m bgl in TP01 is considered to represent a
weathered limestone band within the Charmouth Mudstone. The Charmouth Mudstone
typically contains bands and lenses of mudstone and limestone (may be laterally and vertically
impersistent). Each of the trial pits were terminated upon refusal on possible rock bands at
depth varying between 1.3 – 2.5m bgl.
Groundwater
Groundwater was not encountered in any of the trial pits, during the short period they
remained open.
75
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 9
Groundwater levels may vary seasonally, with significantly higher groundwater levels
expected in the winter/spring period or following periods of heavy rainfall, with levels in
summer or during periods of drought likely to be lower. The anecdotal evidence provided in
Section 2 of this report would suggest that significant waterlogging of the existing pitches
takes places, especially following heavy rainfall events. Groundwater levels may increase
following periods of heavy rainfall, however water may also pond at surface due to poor
infiltration characteristics of the relatively impermeable soils, inadequacy/poor function of
any existing land drainage and lack of a suitable gradient/fall across the existing pitches to
allow any excess surface water to drain away to the sides. The above should be taken into
account in the design of drainage measures.
76
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 10
5.2 Geotechnical Appraisal
The general sequence of strata encountered during the ground investigation, together with
encountered thicknesses and elevations is summarised in Section 5.1 above. The material
parameters and derivation of appropriate suggested preliminary design parameters is
discussed below.
5.2.1 Made Ground
The material parameters for the Made Ground are as given below together with the
derivation of appropriate design parameters.
Classification
Seven natural moisture content tests were carried out on samples of Made Ground, which
ranged from 26 to 59 %. The results are summarised in Appendix B and presented
graphically in Appendix C. Near surface results (with 0.15m depth) typically gave higher
moisture content values (40-59%), likely reflective of the surface wetness of the pitch as
observed during the site walkover.
No plasticity index tests were carried out on samples of Made Ground.
One particle size distribution test was carried out on a sample of the deeper Made Ground
from TP03. The results are presented in Table 5.2 below. Appendix B presents a grading
curve for this material.
Table 5.2. Summary of Particle Size Distribution Tests
% Clay % Silt %Sand % Gravel
% Cobbles/boulders
Laboratory classification
46 50 3 1 0 Brown slightly sandy silty CLAY with a little fine gravel
77
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 11
Bulk Unit Weight
No testing was undertaken on samples of Made Ground to obtain bulk density values,
however a value of 18kN/m3 is considered appropriate for the bulk unit weight of this
material.
Strength
One vane test was undertaken on a sample of Made Ground in TP03. This gave a value of
undrained shear strength of 44 KPa at 0.4m bgl (i.e. the deeper Made Ground).
An undrained shear strength in the range 40-50 kPa can be assumed for Made Ground on
the basis of the above result and material descriptions given on the exploratory hole log
(using typical strengths from BS8004, 1986).
Permeability
No data is available relating to the permeability of the Made Ground. Due to its cohesive
nature, the Made Ground is likely to be relatively impermeable, with a permeability in the
typical range for silts and clays (order of 10-5 m/s or less) (BS8004, 1986). The
permeability may vary both laterally and vertically with changes in the deposits (i.e. any
granular horizons may exhibit a higher permeability than cohesive).
78
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 12
5.2.2 Charmouth Mudstone
The material parameters for the Charmouth Mudstone are as given below together with
the derivation of appropriate design parameters.
Classification
Fifteen natural moisture content and six Atterberg limit tests were carried out on samples
of the Charmouth Mudstone, which ranged from 20 to 39 %. The results are summarised
and presented graphically in Appendix B.
The results shows that the Charmouth Mudstone soils typically fall within the boundary of
Group CH and CV with one result on the boundary of Group CV and CE) as defined in
BS5930 (1999) and therefore generally classify as clays of high to very high plasticity.
Based upon the modified plasticity indices, this material is considered to be of high
volume change potential in response to changes in moisture content (NHBC, 2011). The
desiccation parameters - moisture content, and moisture content/liquid limit ratio, would
infer the soil is currently slightly desiccated to around 1m depth. It should be noted
however, that with depth, the parameters may reflect the less weathered, more
overconsolidated nature of the Charmouth Mudstone. Desiccation parameter profiles,
plotted against depth, are presented in Appendix C.
Moisture content profiles are presented in Appendix C, for TP01 to TP06 inclusive. Based
on the shape of these profiles, moisture contents measured in the top 0.3m begl are
significantly higher than those at greater depths, likely indicative of the of the wet ground
surface observed. The moisture content profiles typically show an initial decrease in
moisture content to depths of 0.6m bgl followed by a slight increase. This would likely
indicate a slight desiccation of the soil to around 0.6m, with the observed slight increase
79
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 13
being indicative of the relatively high natural moisture content (undesiccated) of the
ground i.e. the initial observed decrease in moisture content is reflective of the near
surface desiccation. The observed pattern of moisture content with depth may also
possibly reflect the presence of existing land drains, which may be acting to partially drain
the site where present. A land drain was noted in TP 03 at 0.6m bgl.
Bulk Unit Weight
No specific testing was undertaken on samples of Charmouth Mudstone to obtain bulk
density values, however a value of 19kN/m3 is considered an appropriate design value for
the bulk unit weight of this material in accordance with the suggested range given for stiff
clays given in BS8002(1994).
Strength
Twelve vane tests were undertaken on samples of Charmouth Mudstone described as firm
and stiff. These gave values of undrained shear strength in the range 70-83 KPa. The
descriptions given on the exploratory hole logs would suggest a strength in the range 50-
150 kPa. For the purposes of preliminary design an undrained shear strength in the range
50-75 kPa (for firm clays), 75-150 kPa (for stiff clays), and 150 kPa or above (for very stiff
clays) can be assumed for the Charmouth Mudstone on the basis of the above results and
material descriptions given on the exploratory hole log (using typical strengths from
BS8004, 1986).
Rock bands encountered with the Charmouth Mudstone (limestone and mudstone) would
be expected to be of considerably higher strength.
A strength vs depth below ground level plot is presented in Appendix C based on the hand
vane results within the clay.
80
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 14
Permeability
No fieldwork data is available relating to the permeability of the Charmouth Mudstone,
however these deposits are likely to be relatively impermeable, with a permeability in the
typical range for clays (order of 10-7 m/s or less) BS8004, 1986) as demonstrated by the
soakaway tests carried out in TP03 and TP05. The permeability may vary both laterally
and vertically with changes in the deposits (i.e. granular horizons may exhibit a higher
permeability than cohesive).
5.3 Excavations
Excavations may be required to allow the installation of appropriate drainage measures.
The extent and dimensions of these are not determined at the time of writing this report.
Excavations should be within the scope of conventional backhoe excavators. Recourse to
hydraulic breakers may be required to break out any existing obstructions and rock bands.
Excavations should remain stable in the short term, although minor spalling of the
excavation sides may occur.
If potentially unstable excavations or any excavations deeper than 1.00m are to be
entered then the sides should be battered back and/or shoring methods and equipment
should be utilised in accordance with the relevant Health and Safety Acts.
5.4 Pavement Design
Six dynamic cone penetrometer tests were carried out in the vicinity of the proposed car
parking area. On the basis of the results, California Bearing Ration (CBR) values of 2.5%
and greater may be obtained on the basis of the correlation given in IAN 73/06 (2009).
Higher values are likely to represent localised higher strength materials within the soils.
81
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 15
An equilibrium subgrade California Bearing Ratio (CBR) value of 2% can be estimated from
plasticity indices based on table 5.1 of IAN 73/06 (2009). On the basis of the available
results, it is suggested that a CBR value of 2.5% be adopted for road and pavement design,
on the assumption that the formation subgrade for the car parking area will be within the
Charmouth Mudstone at a depth of at least 0.3m below ground level or greater.
The predominantly high plasticity nature of the soils indicates that these are relatively
unlikely to be frost susceptible. It is recommended that any material placed as sub
base/capping within 450mm depth of the proposed car park surface should be non-frost
susceptible in accordance with the Manual of Contract Documents for Highway Works,
Volume 1 Specification for Highway Works, Series 600 Earthworks, and tested according
to BS812: Part 124 (2009). Sub base and capping materials should be granular in nature
with a low fines content and not composed of any frost susceptible materials e.g
magnesian or oolitic limestones (as these are typically susceptible to frost heave).
The subgrade should be protected prior to placing sub base and capping materials in order
to protect the formation level from softening. In addition, adequate drainage should be
installed to ensure that water can be adequately drained from the area.
5.5 Soakaway Design
Soakaway tests were carried out in Trial Pits TP03 and TP05 in general accordance with
BRE 365 (2007). Due to the poor rate of infiltration observed (between 10 and 20mm
depth in three hours), it was not possible to calculate the soil infiltration rate.
Due to the poor infiltration observed, the use of soakaways to facilitate drainage on the
site is not considered to be appropriate.
82
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 16
5.6 Drainage Recommendations
The following drainage options may be considered for the site. Specialist advice should be
sought from a drainage designer/contractor/supplier to determine a suitable option and
design, suitable depths, spacing, layout, extent etc. The capacity of existing surface and
groundwater drainage systems (sewers etc) and ability to accept additional run-
off/drainage from the site and connection details to these should also be established and
taken into account in the selection and design of a suitable remedial option. Drainage
ditches (partially filled) were observed to the perimeter of the playing field, however it is
not clear whether existing drainage from the site currently routes into these, or what the
capacity of these existing ditches is to receive additional water from proposed drainage
systems.
Clay land drains
Anecdotal evidence provided by the Client and Complete Design Partnership, suggests
that there may be some existing drainage beneath the surface of the playing fields in the
form of land drains. A clay land drain was located in TP03 at 0.6m. The extent or layout of
the existing drains is not known. Use of land drains (either re-use of the existing or
construction of new drains) would not be recommended on their own as it is evident from
the waterlogging of the playing fields that the existing land drains are not functioning
correctly and/or are inadequate in size, number, layout etc to adequately drain the field.
Sand and gravel slit trenches
Drainage of waterlogged soils may possibly be achieved through the use of sand and
gravel slit trenches. These would typically consist of narrow trenches to shallow depths
(less than 1m) filled with sand and/or gravel. These are connected laterally via plastic
pipes (connector drains) and then routed onwards into the main drainage system. The
effectiveness of this type of drainage may be enhanced using geotextile wrapped
connector drains e.g. Hydraway Sportsdrain (Turfdry drainage system) by increasing the
83
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 17
surface area of the lateral connector drains and reducing the potential for clogging. Use
of this type of system may be effective for drainage of the site. Advice should be sought
from a specialist contractor/supplier for selection of an appropriate system, design and
installation.
Plastic pipe geocomposite systems
Drainage of waterlogged soils may possibly be achieved through the use of plastic pipe
drainage system geocomposites e.g Macaferri MacDrain or similar. These consist of a
HDPE drainage core attached to non-woven geotextile to prevent clogging one side or
both sides. These replace the function of traditional drainage materials such as sands and
gravels, meaning that they can be installed in narrow trenches without the addition of
surrounding imported filter materials (sand and gravel). These are then connected
laterally via connector drains and then routed onwards into the main drainage system.
Use of this type of system may be effective for drainage of the site. Advice should be
sought from a specialist contractor/supplier for selection of an appropriate system, design
and installation.
GEOTECHNICAL ENGINEERING LIMITED
84
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 18
6. REFERENCES
British Standards Institution (1999): Code of practice for site investigations. BS 5930
incorporating Amendments No. 1 & 2. Amendment 1 removes text superseded by BS EN ISO
14688-1:2002, BS EN ISO 14688-2:2004 and BS EN ISO 14689-1:2003, and makes reference to
the relevant standard for each affected sub clause. Amendment 2 removes text superseded
by BS EN 22475-1:2006 and makes reference to the relevant standard for each affected sub
clause.
British Standards Institution (1990): Methods of tests for soils for civil engineering purposes.
BS 1377 Parts 1-9.
British Standards Institution (1986): Code of Practice for Foundations. BS 8004:1986.
Superseded/withdrawn, replaced by BS EN 1997-1:2004.
British Standards Institution (1994): Code of Practice for Earth Retaining Structures. BS
8002:1994. Superseded/withdrawn, replaced by BS EN 1997-1:2004.
British Standards Institution (2009): Testing aggregates. Method for determination of frost
heave. BS 812-124:2009
Building Research Establishment (2007): Soakaway Design. BRE 365.
Highways Agency (2009): Design Guidance for Road and Pavement Foundations (Draft
HD25). Interim Advice Note (IAN) 73/06 Revision 1.
85
Geotechnical Engineering Limited
www.geoeng.co.uk
RT01 v09 18/01/13 JH Report Ref: 27979 Page 19
Highways Agency (1992, Amended 2009): Manual of Contract Documents for Highway
Works, Volume 1 Specification for Highway Works, Series 600 Earthworks. The Stationery
Office Ltd, (Amended 2009).
National House Building Council (2011): NHBC Standards. Chapter 4.2. Foundations:
Building near trees.
86
Geotechnical Engineering Limited
SITE LOCATION PLAN
CLIENT KINGSWOOD PARISH COUNCILSITE KINGSWOOD PLAYING FIELDSCALE NTS CONTRACT FIGURE
Reproduced from the Ordnance Survey 1:50,000 Map sheet 183, Yeovil and Frome, 1999. With the permission of Ordnance Survey on behalf of The Controller of Her Majesty's Stationary Office, Crown Copyright. Geotechnical Engineering Limited, Gloucester. AL100002447. 27979 1
N
SITE LOCATION
87
88
FIELDWORK DATA
2797
9
APPENDIX A
Geotechnical Engineering Limited
89
0.30
0.80
1.40
1.55
1.70
2.50
1
2
3
4
D*
B
B
B
H 79
H 74
0.15
0.30
0.35
0.75
1.00
1.80
- 0.50
- 1.20
- 2.00
Dry
Turf over firm greyish brown slightly sandy slightly gravelly SILT with frequentroots (up to 15mm diameter) and rare ash. Gravel is subangular and subroundedfine and medium quartzite. (MADE GROUND)
Stiff orangish brown and greyish brown slightly sandy silty CLAY.
Stiff light grey mottled orangish brown CLAY.
Light grey subangular limestone COBBLES and BOULDERS.
Stiff light grey mottled orangish brown CLAY.
Very stiff dark bluish grey and light grey slightly sandy CLAY with frequent fine tocoarse gravel sized calcareous mudstone lithorelicts and rare fine and mediumgravel sized fossil remains.
Trial pit completed at 2.50m.
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/06/
2013
10:
34:4
5 D
JO
End Date
KINGSWOOD PLAYING FIELD
depth level
(m)legend
CONTRACT CHECKED
Notes
TRIAL PIT LOG
(m)
Start Date
water
record
sample/test
TP01SITE
KINGSWOOD PARISH COUNCIL
2.50 m
27979EXPLORATORY HOLE LOGS SHOULD BE READ IN CONJUNCTION WITH KEY SHEETS
Sketch of Foundation - Not to scale. All dimensions in metres.
no/type
Trial pit excavated by JCB 3CX mechanical excavator.Groundwater not encountered.Trial pit sides remained stable and vertical.Trial pit dimensions 1.70x0.60x2.50m.Trial pit refused at 2.50m. Possible rock.On completion, the trial pit was backfilled with materials arising.
29 April 2013
29 April 2013
CLIENT
Geotechnical Engineering Limited
depth (m)description
Sheet 1 of 1
Scale 1 : 25
result
Depth
EW
90
0.20
0.60
0.80
1.30
1
2
3
4
D*
B
B
B
H 79
H 82
0.15
0.30
0.30
0.60
0.80
1.00
- 0.50
- 0.80
- 1.20
Dry
Turf over firm greyish brown slightly sandy slightly gravelly SILT with frequentrootlets. Gravel is subangular fine and medium quartzite. (MADE GROUND)
Stiff orangish brown and greyish brown slightly sandy silty CLAY with rare rootlets.
Stiff light grey mottled orangish brown CLAY.
Very stiff dark bluish grey and grey slightly sandy CLAY with frequent fine andmedium gravel sized fossil remains and a high limestone cobble content.
Trial pit completed at 1.30m.
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/06/
2013
10:
34:4
5 D
JO
End Date
KINGSWOOD PLAYING FIELD
depth level
(m)legend
CONTRACT CHECKED
Notes
TRIAL PIT LOG
(m)
Start Date
water
record
sample/test
TP02SITE
KINGSWOOD PARISH COUNCIL
1.30 m
27979EXPLORATORY HOLE LOGS SHOULD BE READ IN CONJUNCTION WITH KEY SHEETS
Sketch of Foundation - Not to scale. All dimensions in metres.
no/type
Trial pit excavated by JCB 3CX mechanical excavator.Groundwater not encountered.Trial pit sides remained stable and vertical.Trial pit dimensions 1.70x0.60x1.30m.Trial pit refused at 1.30m. Possible rock.On completion, the trial pit was backfilled with materials arising.
29 April 2013
29 April 2013
CLIENT
Geotechnical Engineering Limited
depth (m)description
Sheet 1 of 1
Scale 1 : 25
result
Depth
EW
91
0.30
0.85
1.50
1.80
1
2
3
D*
B
B
H 44
H 70
H 82
0.25
0.30
0.40
0.90
1.50
1.60
- 0.50
- 1.60
Dry
Turf over firm greyish brown slightly sandy slightly gravelly SILT with frequentrootlets and rare fine gravel sized brick fragments. Gravel is subangular andsubrounded mudstone. (MADE GROUND)
Firm greyish brown mottled orangish brown and bluish grey slightly gravellyCLAY. Gravel is subangular fine to coarse mudstone and quartzite. (MADEGROUND)
0.60m: 60mm diameter orange clay land drain.
Firm greyish brown mottled orangish brown and bluish grey slightly sandy CLAY.
Stiff thinly laminated dark bluish grey slightly sandy CLAY with frequent fine andmedium gravel sized fossil remains.
Trial pit completed at 1.80m.
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/06/
2013
10:
34:4
6 D
JO
End Date
KINGSWOOD PLAYING FIELD
depth level
(m)legend
CONTRACT CHECKED
Notes
TRIAL PIT LOG
(m)
Start Date
water
record
sample/test
TP03SITE
KINGSWOOD PARISH COUNCIL
1.80 m
27979EXPLORATORY HOLE LOGS SHOULD BE READ IN CONJUNCTION WITH KEY SHEETS
Sketch of Foundation - Not to scale. All dimensions in metres.
no/type
Trial pit excavated by JCB 3CX mechanical excavator.Groundwater not encountered.Trial pit sides remained stable and vertical.Trial pit dimensions 2.20x0.60x1.80m.Trial pit refused at 1.80m. Possible rock.On completion, the trial pit was backfilled with materials arising.
29 April 2013
29 April 2013
CLIENT
Geotechnical Engineering Limited
depth (m)description
Sheet 1 of 1
Scale 1 : 25
result
Depth
EW
92
0.20
0.90
1.40
1
2
3
D*
B
B
H 82
H 77
0.15
0.30
0.30
0.65
1.00
- 0.50
- 1.20
Dry
Turf over firm greyish brown slightly sandy SILT with frequent roots (up to 10mmdiameter) and rare brick fragments. (MADE GROUND)
Stiff orangish brown and light greyish brown slightly sandy silty CLAY with rarerootlets.
Stiff light grey rarely mottled orangish brown and bluish grey CLAY with a lowlimestone cobble content.
Trial pit completed at 1.40m.
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/06/
2013
10:
34:4
6 D
JO
End Date
KINGSWOOD PLAYING FIELD
depth level
(m)legend
CONTRACT CHECKED
Notes
TRIAL PIT LOG
(m)
Start Date
water
record
sample/test
TP04SITE
KINGSWOOD PARISH COUNCIL
1.40 m
27979EXPLORATORY HOLE LOGS SHOULD BE READ IN CONJUNCTION WITH KEY SHEETS
Sketch of Foundation - Not to scale. All dimensions in metres.
no/type
Trial pit excavated by JCB 3CX mechanical excavator.Groundwater not encountered.Trial pit sides remained stable and vertical.Trial pit dimensions 1.80x0.60x1.40m.Trial pit refused at 1.40m. Possible rock.On completion, the trial pit was backfilled with materials arising.
29 April 2013
29 April 2013
CLIENT
Geotechnical Engineering Limited
depth (m)description
Sheet 1 of 1
Scale 1 : 25
result
Depth
EW
93
0.15
1.30
1.50
1.70
1
2
3
4
D*
B
B
B
H 74
H 82
0.15
0.20
0.30
0.70
1.30
1.50
- 0.50
- 1.50
- 1.70
Dry
Turf over firm greyish brown slightly sandy slightly gravelly SILT with frequentrootlets and rare brick fragments. Gravel is subangular and subrounded fine andmedium quartzite. (MADE GROUND)
Stiff orangish brown and greyish brown slightly sandy silty CLAY with rare rootlets.
0.50m: With rare cobble sized pockets of stiff light grey slightly sandy clay.
Stiff light grey CLAY with a high limestone cobble and boulder content.
Very stiff dark bluish grey and light grey slightly sandy CLAY with frequent fine tocoarse gravel sized calcareous mudstone lithorelicts.
Trial pit completed at 1.70m.
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/06/
2013
10:
34:4
6 D
JO
End Date
KINGSWOOD PLAYING FIELD
depth level
(m)legend
CONTRACT CHECKED
Notes
TRIAL PIT LOG
(m)
Start Date
water
record
sample/test
TP05SITE
KINGSWOOD PARISH COUNCIL
1.70 m
27979EXPLORATORY HOLE LOGS SHOULD BE READ IN CONJUNCTION WITH KEY SHEETS
Sketch of Foundation - Not to scale. All dimensions in metres.
no/type
Trial pit excavated by JCB 3CX mechanical excavator.Groundwater not encountered.Trial pit sides remained stable and vertical.Trial pit dimensions 1.70x0.60x1.70m.Trial pit refused at 1.70m. Possible rock.On completion, the trial pit was backfilled with materials arising.
29 April 2013
29 April 2013
CLIENT
Geotechnical Engineering Limited
depth (m)description
Sheet 1 of 1
Scale 1 : 25
result
Depth
EW
94
0.15
0.60
1.40
1.70
1
2
3
4
D*
B
B
B
H 77
H 83
0.15
0.30
0.30
0.60
0.80
1.40
- 0.50
- 0.80
- 1.60
Dry
Turf over firm greyish brown slightly sandy slightly gravelly SILT with frequentrootlets and rare medium gravel sized pockets of yellowish brown coarse sand.Gravel is subangular and subrounded fine and medium sandstone and mudstone.(MADE GROUND)
Stiff orangish brown and greyish brown slightly sandy silty CLAY with rare rootlets.
Stiff light grey CLAY with a high limestone cobble and boulder content.
Very stiff dark bluish grey and light grey slightly sandy CLAY with frequent fine tocoarse gravel sized calcareous mudstone lithorelicts and rare fine and mediumgravel sized fossil remains.
Trial pit completed at 1.70m.
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/06/
2013
10:
34:4
7 D
JO
End Date
KINGSWOOD PLAYING FIELD
depth level
(m)legend
CONTRACT CHECKED
Notes
TRIAL PIT LOG
(m)
Start Date
water
record
sample/test
TP06SITE
KINGSWOOD PARISH COUNCIL
1.70 m
27979EXPLORATORY HOLE LOGS SHOULD BE READ IN CONJUNCTION WITH KEY SHEETS
Sketch of Foundation - Not to scale. All dimensions in metres.
no/type
Trial pit excavated by JCB 3CX mechanical excavator.Groundwater not encountered.Trial pit sides remained stable and vertical.Trial pit dimensions 1.80x0.60x1.70m.Trial pit refused at 1.70m. Possible rock.On completion, the trial pit was backfilled with materials arising.
29 April 2013
29 April 2013
CLIENT
Geotechnical Engineering Limited
depth (m)description
Sheet 1 of 1
Scale 1 : 25
result
Depth
EW
95
TP01 0.35 79 79
TP01 0.75 74 74
TP02 0.30 79 79
TP02 0.80 82 82
TP03 0.40 44 44
TP03 0.90 70 70
TP03 1.60 82 82
TP04 0.30 82 82
TP04 0.65 77 77
TP05 0.20 74 74
TP05 0.70 82 82
TP06 0.30 77 77
TP06 0.80 83 83
CONTRACT
SITE KINGSWOOD PLAYING FIELD
borehole
27979
depth(m)
CHECKED
remarks
*Average pocket penetrometer results reported as undrained shear strength.
averagepocket
penetrometer(kPa)*
CLIENT
no.
general remarks:
/trial pit
KINGSWOOD PARISH COUNCIL
Geotechnical Engineering Limited
averagehand vaneremoulded
(kPa)
hand vaneremoulded
(kPa)
averagehand vane
peak(kPa)
hand vanepeak(kPa)
IN-SITU HAND VANE/POCKET PENETROMETER
Hand vane test results reported as undrained shear strength.
pocketpenetrometer
(kg/cm2)
KINGSWOOD PARISH COUNCIL
/trial pit
general remarks:
no.
borehole
KINGSWOOD PLAYING FIELD
27979
Geotechnical Engineering Limited
CLIENT
SITE
CONTRACT CHECKED
EW
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
96
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.4
0 100 200 300
scalereading(mm)
CBR(%)
4.1
5.7
5.3
4.6
3.5
2.5
4.8
7.2
10.5
13.1
15.1
13.4
10.7
15.1
13.8
28.0
22.9
25.2
24.0
21.8
69.8
55.1
33.5
29.6
29.6
21.8
26.5
22.9
31.5
94.6
302.0
DCP(mm/blow)
59
43
46
53
69
93
50
35
24
20
17
19
24
17
19
10
12
11
11
12
4
5
8
9
9
12
10
12
9
3
1
depth bgl(m)
penetrationincrement
(mm)
59
85
92
105
137
185
100
69
48
39
34
38
47
34
37
19
23
21
22
24
8
10
16
18
18
24
20
23
17
6
1
64
149
241
346
483
668
768
837
885
924
958
996
1043
1077
1114
1133
1156
1177
1199
1223
1231
1241
1257
1275
1293
1317
1337
1360
1377
1383
1384
Remarks:
no. ofblows
Dep
th (
m)
Test carried out in accordance with operating instructions for the dynamic cone penetrometer Model A2465 byCNS Farnell Ltd.CBR correlation based on the relationship Log10 (CBR) = 2.48 - 1.057 * Log10 (mm/blow) developed by TRLtaken from The Highways Agency Interim Advice Note 73/06 - Design Guidance for Road Pavement Foundations(2009)
Initial scale reading (mm) 0
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
CBR (%)
DYNAMIC CONE PENETROMETER TESTING
Datum bgl (mm)5
0.06
0.14
0.24
0.34
0.48
0.66
0.76
0.83
0.88
0.92
0.95
0.99
1.04
1.07
1.11
1.13
1.15
1.17
1.19
1.22
1.23
1.24
1.25
1.27
1.29
1.31
1.33
1.36
1.37
1.38
1.38
Geotechnical Engineering Limited
CONTRACT CHECKED
DCP01CLIENT
SITE KINGSWOOD PLAYING FIELD
DATE 29 April 2013
27979 EW
KINGSWOOD PARISH COUNCIL
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
97
0
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
0 20 40 60 80 100
scalereading(mm)
CBR(%)
55.1
10.1
12.7
12.7
12.7
10.1
7.1
9.3
7.3
7.8
8.6
8.9
8.6
9.3
10.5
10.1
8.3
10.1
8.3
8.3
8.0
20.1
16.1
13.4
6.0
4.6
6.3
7.5
7.1
6.0
7.1
7.8
55.1
26.5
94.6
DCP(mm/blow)
5
25
20
20
20
25
35
27
34
32
29
28
29
27
24
25
30
25
30
30
31
13
16
19
41
52
39
33
35
41
35
32
5
10
3
depth bgl(m)
penetrationincrement
(mm)
5
25
20
20
20
25
35
27
34
32
29
28
29
27
24
25
30
25
30
30
31
13
16
19
41
52
39
33
35
41
35
32
5
10
3
60
85
105
125
145
170
205
232
266
298
327
355
384
411
435
460
490
515
545
575
606
619
635
654
695
747
786
819
854
895
930
962
967
977
980
Remarks:
no. ofblows
Dep
th (
m)
Test carried out in accordance with operating instructions for the dynamic cone penetrometer Model A2465 byCNS Farnell Ltd.CBR correlation based on the relationship Log10 (CBR) = 2.48 - 1.057 * Log10 (mm/blow) developed by TRLtaken from The Highways Agency Interim Advice Note 73/06 - Design Guidance for Road Pavement Foundations(2009)
Initial scale reading (mm) 0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
CBR (%)
DYNAMIC CONE PENETROMETER TESTING
Datum bgl (mm)55
0.01
0.03
0.05
0.07
0.09
0.12
0.15
0.18
0.21
0.24
0.27
0.30
0.33
0.36
0.38
0.41
0.44
0.46
0.49
0.52
0.55
0.56
0.58
0.60
0.64
0.69
0.73
0.76
0.80
0.84
0.88
0.91
0.91
0.92
0.93
Geotechnical Engineering Limited
CONTRACT CHECKED
DCP02CLIENT
SITE KINGSWOOD PLAYING FIELD
DATE 29 April 2013
27979 EW
KINGSWOOD PARISH COUNCIL
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
98
0
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
1.00
1.05
1.10
1.15
1.20
0 50 100 150
scalereading(mm)
CBR(%)
5.1
9.5
3.9
3.2
4.8
9.1
7.6
15.1
20.1
12.7
12.7
7.9
12.1
15.6
10.7
10.1
15.1
20.1
35.9
38.6
33.5
20.9
20.9
80.3
45.5
49.8
29.6
33.5
80.3
145.2
DCP(mm/blow)
48
27
61
74
50
28
33
17
13
20
20
32
21
17
24
25
17
13
8
7
8
13
13
4
6
6
9
8
4
2
depth bgl(m)
penetrationincrement
(mm)
48
53
122
147
100
55
65
34
26
40
40
63
42
33
47
50
34
26
15
14
16
25
25
7
12
11
18
16
7
2
53
106
228
375
475
530
595
629
655
695
735
798
840
873
920
970
1004
1030
1045
1059
1075
1100
1125
1132
1144
1155
1173
1189
1196
1198
Remarks:
no. ofblows
Dep
th (
m)
Test carried out in accordance with operating instructions for the dynamic cone penetrometer Model A2465 byCNS Farnell Ltd.CBR correlation based on the relationship Log10 (CBR) = 2.48 - 1.057 * Log10 (mm/blow) developed by TRLtaken from The Highways Agency Interim Advice Note 73/06 - Design Guidance for Road Pavement Foundations(2009)
Initial scale reading (mm) 0
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
CBR (%)
DYNAMIC CONE PENETROMETER TESTING
Datum bgl (mm)5
0.05
0.10
0.22
0.37
0.47
0.53
0.59
0.62
0.65
0.69
0.73
0.79
0.84
0.87
0.92
0.97
1.00
1.03
1.04
1.05
1.07
1.10
1.12
1.13
1.14
1.15
1.17
1.18
1.19
1.19
Geotechnical Engineering Limited
CONTRACT CHECKED
DCP03CLIENT
SITE KINGSWOOD PLAYING FIELD
DATE 29 April 2013
27979 EW
KINGSWOOD PARISH COUNCIL
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
99
0
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
0.85
0 20 40 60
scalereading(mm)
CBR(%)
5.3
5.3
7.1
7.5
7.1
5.4
5.2
5.7
6.1
6.5
6.6
8.3
8.0
7.3
8.3
9.7
10.5
9.7
29.6
26.5
14.2
15.1
10.1
26.5
17.3
17.3
12.7
55.1
55.1
55.1
DCP(mm/blow)
46
46
35
33
35
45
47
43
40
38
37
30
31
34
30
26
24
26
9
10
18
17
25
10
15
15
20
5
5
5
depth bgl(m)
penetrationincrement
(mm)
46
46
35
33
35
45
47
43
40
38
37
30
31
34
30
26
24
26
9
10
18
17
25
10
15
15
20
5
5
5
81
127
162
195
230
275
322
365
405
443
480
510
541
575
605
631
655
681
690
700
718
735
760
770
785
800
820
825
830
835
Remarks:
no. ofblows
Dep
th (
m)
Test carried out in accordance with operating instructions for the dynamic cone penetrometer Model A2465 byCNS Farnell Ltd.CBR correlation based on the relationship Log10 (CBR) = 2.48 - 1.057 * Log10 (mm/blow) developed by TRLtaken from The Highways Agency Interim Advice Note 73/06 - Design Guidance for Road Pavement Foundations(2009)
Initial scale reading (mm) 0
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
CBR (%)
DYNAMIC CONE PENETROMETER TESTING
Datum bgl (mm)35
0.05
0.09
0.13
0.16
0.20
0.24
0.29
0.33
0.37
0.41
0.45
0.48
0.51
0.54
0.57
0.60
0.62
0.65
0.66
0.67
0.68
0.70
0.73
0.74
0.75
0.77
0.79
0.79
0.80
0.80
Geotechnical Engineering Limited
CONTRACT CHECKED
DCP04CLIENT
SITE KINGSWOOD PLAYING FIELD
DATE 29 April 2013
27979 EW
KINGSWOOD PARISH COUNCIL
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
100
0
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
1.00
0 50 100 150
scalereading(mm)
CBR(%)
8.3
3.6
4.8
7.3
9.1
11.5
12.4
13.1
16.7
17.3
16.7
26.5
29.6
31.5
45.5
20.1
17.9
16.7
19.3
22.9
24.0
38.6
28.0
26.5
26.5
29.6
45.5
55.1
94.6
45.5
94.6
94.6
145.2
DCP(mm/blow)
30
66
51
34
28
22
21
20
16
15
16
10
9
9
6
13
15
16
14
12
11
7
10
10
10
9
6
5
3
6
3
3
2
depth bgl(m)
penetrationincrement
(mm)
30
132
101
68
55
44
41
39
31
30
31
20
18
17
12
26
29
31
27
23
22
14
19
20
20
18
12
10
6
12
6
6
2
30
162
263
331
386
430
471
510
541
571
602
622
640
657
669
695
724
755
782
805
827
841
860
880
900
918
930
940
946
958
964
970
972
Remarks:
no. ofblows
Dep
th (
m)
Test carried out in accordance with operating instructions for the dynamic cone penetrometer Model A2465 byCNS Farnell Ltd.CBR correlation based on the relationship Log10 (CBR) = 2.48 - 1.057 * Log10 (mm/blow) developed by TRLtaken from The Highways Agency Interim Advice Note 73/06 - Design Guidance for Road Pavement Foundations(2009)
Initial scale reading (mm) 0
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
CBR (%)
DYNAMIC CONE PENETROMETER TESTING
Datum bgl (mm)0
0.03
0.16
0.26
0.33
0.39
0.43
0.47
0.51
0.54
0.57
0.60
0.62
0.64
0.66
0.67
0.70
0.72
0.76
0.78
0.81
0.83
0.84
0.86
0.88
0.90
0.92
0.93
0.94
0.95
0.96
0.96
0.97
0.97
Geotechnical Engineering Limited
CONTRACT CHECKED
DCP05CLIENT
SITE KINGSWOOD PLAYING FIELD
DATE 29 April 2013
27979 EW
KINGSWOOD PARISH COUNCIL
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
101
0
0.05
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
0.85
0.90
0.95
1.00
1.05
1.10
0 50 100 150 200
scalereading(mm)
CBR(%)
2.9
5.7
6.4
6.5
6.4
7.4
8.9
8.9
8.9
8.6
8.0
11.8
94.6
145.2
114.7
196.7
80.3
55.1
35.9
26.5
12.7
12.7
49.8
49.8
45.5
49.8
20.9
9.1
94.6
DCP(mm/blow)
81
43
39
38
39
34
28
28
28
29
31
22
3
2
3
2
4
5
8
10
20
20
6
6
6
6
13
28
3
depth bgl(m)
penetrationincrement
(mm)
81
86
77
76
77
67
56
56
56
58
62
43
6
4
5
3
7
10
15
20
40
40
11
11
12
11
25
55
3
81
167
244
320
397
464
520
576
632
690
752
795
801
805
810
813
820
830
845
865
905
945
956
967
979
990
1015
1070
1073
Remarks:
no. ofblows
Dep
th (
m)
Test carried out in accordance with operating instructions for the dynamic cone penetrometer Model A2465 byCNS Farnell Ltd.CBR correlation based on the relationship Log10 (CBR) = 2.48 - 1.057 * Log10 (mm/blow) developed by TRLtaken from The Highways Agency Interim Advice Note 73/06 - Design Guidance for Road Pavement Foundations(2009)
Initial scale reading (mm) 0
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
1
CBR (%)
DYNAMIC CONE PENETROMETER TESTING
Datum bgl (mm)0
0.08
0.17
0.24
0.32
0.40
0.46
0.52
0.58
0.63
0.69
0.75
0.80
0.80
0.81
0.81
0.81
0.82
0.83
0.85
0.87
0.91
0.95
0.96
0.97
0.98
0.99
1.02
1.07
1.07
Geotechnical Engineering Limited
CONTRACT CHECKED
DCP06CLIENT
SITE KINGSWOOD PLAYING FIELD
DATE 29 April 2013
27979 EW
KINGSWOOD PARISH COUNCIL
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
102
LABORATORY TESTING
2797
9Geotechnical Engineering Limited
APPENDIX B
103
2718
GEOTECHNICAL ENGINEERING LTD
For the attention of Sophie Collins Date of IssuePage Number 1 of 6
PROJECT/SITE Kingswood Playing Field Samples received 08/05/2013GEL REPORT NUMBER 27979 Schedule received 08/05/2013Your ref/PO: Testing commenced 19/05/2013
QUANTITY ACCREDITEDTEST
22 YES6 YES2 YES2 YES
29 May 2013
TEST REPORT
SUMMARY OF RESULTS ATTACHED
TEST METHOD & DESCRIPTION
BS1377: Part 2: 1990:3.2, Moisture ContentBS1377: Part 2: 1990:4.2‐4.4&5.2‐5.4, Liquid & Plastic LimitsBS1377: Part 2: 1990:9.2, Particle Size Distribution ‐ Wet SieveBS1377 Part 2 1990 9 4 Particle Si e Distrib tion Pipette 2 YES
Remarks Approved Signatories:The report should not be reproduced except in full without R Ewens (Laboratory Business Manager) R Pratt (Client Manager)
written permission from this laboratory. W Jones (Laboratory Supervisor) J Hanson (Director) C Thomas (Consultant)
Doc TR01 Rev No. 5 Revision date 22/03/13 DC:JH
Geotechnical Engineering Ltd www.geoeng.co.ukCenturion House [email protected] Park, Quedgeley TEL: 01452 527743Gloucester GL2 4NF Fax: 01452 729314
Registered number: 00700739 Payments: Geotechnical Engineering Limited
VAT Number: 682 5857 89 Sort code: 30‐15‐99 Bank account: 00072116
BS1377: Part 2: 1990:9.4, Particle Size Distribution ‐ Pipette
104
TP01 1D* 0.15 0.15 46 E Brown slightly sandy CLAY with a little f-mgravel and rare rootlets
TP01 2B 0.30 0.30 39 BXE 2 78 29 49 Brown mottled orange-brown slightlysandy CLAY with a little fine gravel andrare rootlets
TP01 3B 1.00 1.00 27 BXE 12 67 23 44 Grey-brown slightly sandy CLAY with alittle f-m gravel
TP01 4B 1.80 1.80 28 BXE 5 71 29 42 Grey slightly sandy CLAY with a little f-mgravel
TP02 1D* 0.15 0.15 47 E Brown slightly sandy CLAY with rarerootlets
TP02 2B 0.30 0.30 39 BXE 3 90 33 57 Brown mottled orange-brown slightlysandy CLAY
TP02 3B 0.60 0.60 20 BXE 9 52 21 31 Light grey slightly sandy CLAY with a littlef-m gravel
TP02 4B 1.00 1.00 29 BXE 7 72 23 49 Grey-brown slightly sandy CLAY with alittle f-m gravel
TP03 1D* 0.25 0.25 35 E Brown slightly sandy silty CLAY with alittle f-m gravel and rare rootlets
TP03 2B 0.30 0.30 26 E Brown slightly sandy silty CLAY with alittle fine gravel
TP03 3B 1.50 1.50 35 E Grey mottled orange-brown slightly sandyCLAY
TP04 1D* 0.15 0.15 59 E Brown slightly sandy CLAY with frequentrootlets
TP04 2B 0.30 0.30 39 E Brown mottled orange-brown and greyslightly sandy CLAY with a little finegravel
TP04 3B 1.00 1.00 25 E Light grey mottled brown slightly sandyCLAY with a little fine gravel
TP05 1D* 0.15 0.15 40 E Brown slightly sandy CLAY with a little f-mgravel and rare rootlets
TP05 2B 0.30 0.30 38 E Brown slightly sandy CLAY with rarerootlets
TP05 3B 1.30 1.30 27 E Brown mottled grey slightly sandy CLAYwith a little fine gravel
TP05 4B 1.50 1.50 25 E Grey mottled orange-brown slightly sandyCLAY with a little f-m gravel
limit
(%)
moisture preparation
X - cone penetrometer (test 4.3)test method:
A - as receivedB - washed on 0.425mm sieve
specimen preparation:
BS.1377 : Part 2 : 1990 : 4 and 5
Z - Casagrande apparatus (test 4.5)Y - one point cone penetrometer (test 4.4)
C - air dried
NP denotes non-plastic
E - oven dried (105°C)F - not known
natural moisture content determined in accordance with BS1377 : Part 2 : 1990 : 3.2 (unless specified)
# denotes sample tested is smaller than that which is recommended in accordance with BS1377
D - oven dried (60°C)
LIQUID AND PLASTIC LIMITS
plastic
limit
(%)
plasticity
index
(%)
specimen
and
test method
natural
content
(%)
fraction
>0.425
mm
(%)
description and remarks
liquid
CLIENT
Geotechnical Engineering Limited
SITE
CONTRACT CHECKED
general remarks:
KINGSWOOD PLAYING FIELD
27979
KINGSWOOD PARISH COUNCIL
borehole
/trial pit
no. no./typedepth(m)
specimen
depth
(m)
sample
WJ
Geo
tech
nica
l Eng
inee
ring
Ltd,
Cen
turio
n H
ouse
, O
lym
pus
Par
k, Q
uedg
eley
, G
louc
este
r. G
L2 4
NF
. T
el. 0
1452
527
743
279
79.G
PJ
29/0
5/20
13 1
6:20
:27
105
TP06 1D* 0.15 0.15 47 E Brown slightly sandy CLAY with rarerootlets
TP06 2B 0.30 0.30 34 E Light brown mottled orange-brown slightlysandy CLAY with a little fine gravel
TP06 3B 0.60 0.60 27 E Light brown slightly sandy CLAY with alittle fine gravel
TP06 4B 1.40 1.40 31 E Grey mottled brown slightly sandy CLAYwith a little fine gravel
limit
(%)
moisture preparation
X - cone penetrometer (test 4.3)test method:
A - as receivedB - washed on 0.425mm sieve
specimen preparation:
BS.1377 : Part 2 : 1990 : 4 and 5
Z - Casagrande apparatus (test 4.5)Y - one point cone penetrometer (test 4.4)
C - air dried
NP denotes non-plastic
E - oven dried (105°C)F - not known
natural moisture content determined in accordance with BS1377 : Part 2 : 1990 : 3.2 (unless specified)
# denotes sample tested is smaller than that which is recommended in accordance with BS1377
D - oven dried (60°C)
LIQUID AND PLASTIC LIMITS
plastic
limit
(%)
plasticity
index
(%)
specimen
and
test method
natural
content
(%)
fraction
>0.425
mm
(%)
description and remarks
liquid
CLIENT
Geotechnical Engineering Limited
SITE
CONTRACT CHECKED
general remarks:
KINGSWOOD PLAYING FIELD
27979
KINGSWOOD PARISH COUNCIL
borehole
/trial pit
no. no./typedepth(m)
specimen
depth
(m)
sample
WJ
Geo
tech
nica
l Eng
inee
ring
Ltd,
Cen
turio
n H
ouse
, O
lym
pus
Par
k, Q
uedg
eley
, G
louc
este
r. G
L2 4
NF
. T
el. 0
1452
527
743
279
79.G
PJ
29/0
5/20
13 1
6:20
:28
106
0
10
20
30
40
50
60
0 10 20 30 40 50 60 70 80 90 100 110
49
44
42
57
31
49
remarks
CH
liquid limit - LL (%)
plas
ticity
inde
x -
PI (
%)
MV
0.30
1.00
1.80
0.30
0.60
1.00
MEMH
CE
ML MI
BH/TP No. PI
TP01
TP01
TP01
TP02
TP02
TP02
78
67
71
90
52
72
depth (m) PL
CV
LL
ATTERBERG LINE PLOT
CL CI
29
23
29
33
21
23
Geotechnical Engineering Limited
KINGSWOOD PARISH COUNCIL
KINGSWOOD PLAYING FIELD
CLIENT
SITE
CHECKEDCONTRACT
27979 WJ
Geo
tech
nica
l Eng
inee
ring
Ltd,
Cen
turio
n H
ouse
, O
lym
pus
Par
k, Q
uedg
eley
, G
louc
este
r. G
L2 4
NF
. T
el. 0
1452
527
743
279
79.G
PJ
29/0
5/20
13 1
6:20
:33
107
0
10
20
30
40
50
60
70
80
90
100
SPECIMEN DEPTH (m) 0.30
remarks:
20
6
2
89
76
63
# denotes sample tested is smaller than that which is recommended in accordance with BS1377
5
2
1.18
0.6
0.425
0.212
0.15
0.063
100
97
97
96
96
93
20
5
0.02 0.2
medium
test method(s)
passing
Brown mottled orange-brown slightly sandy CLAY
150
75
63
50
37.5
20
10
6.3
(mm)
%
passingsoil type
102
CLAY
37.5
SILT
% fraction
BS test sieve (mm)
63
coarse
0.063
20
SAND
6.3
BS test sieve
0.425
9.2 & 9.4
CLAY
SILT
SILT & CLAY
SAND
GRAVEL
COBBLE & BOULDER
test method:
9.2 - wet sieving
9.3 - dry sieving
9.4 - sedimentation by pipette
9.5 - sedimentation by hydrometer
coarse fine medium
( m)
BS.1377 : Part 2 : 1990 : 9
%
finer
BS test sieve
(mm)
0.6
mm 0.0063 0.063 0.63 6.3
0.15
1.18
particle size
fine medium coarse
0.002
50
63
PARTICLE SIZE DISTRIBUTION
75
%
GRAVELCOBBLE
DESCRIPTION
BOULDERfine
% p
assi
ng
2 200
0.212
63
30
93
7
0
0
SAMPLE DEPTH (m)
SAMPLE No./TYPE
Geotechnical Engineering Limited
BH/TP No. TP02KINGSWOOD PARISH COUNCILCLIENT
CHECKEDCONTRACT
27979 WJ
SITE KINGSWOOD PLAYING FIELD2B
0.30
Geo
tech
nica
l Eng
inee
ring
Ltd,
Cen
turio
n H
ouse
, O
lym
pus
Par
k, Q
uedg
eley
, G
louc
este
r. G
L2 4
NF
. T
el. 0
1452
527
743
279
79.G
PJ
29/0
5/20
13 1
6:20
:40
108
0
10
20
30
40
50
60
70
80
90
100
SPECIMEN DEPTH (m) 0.30
remarks:
20
6
2
89
58
46
# denotes sample tested is smaller than that which is recommended in accordance with BS1377
5
2
1.18
0.6
0.425
0.212
0.15
0.063
100
99
99
98
98
97
97
96
20
5
0.02 0.2
medium
test method(s)
passing
Brown slightly sandy silty CLAY with a little fine gravel
150
75
63
50
37.5
20
10
6.3
(mm)
%
passingsoil type
102
CLAY
37.5
SILT
% fraction
BS test sieve (mm)
63
coarse
0.063
20
SAND
6.3
BS test sieve
0.425
9.2 & 9.4
CLAY
SILT
SILT & CLAY
SAND
GRAVEL
COBBLE & BOULDER
test method:
9.2 - wet sieving
9.3 - dry sieving
9.4 - sedimentation by pipette
9.5 - sedimentation by hydrometer
coarse fine medium
( m)
BS.1377 : Part 2 : 1990 : 9
%
finer
BS test sieve
(mm)
0.6
mm 0.0063 0.063 0.63 6.3
0.15
1.18
particle size
fine medium coarse
0.002
50
63
PARTICLE SIZE DISTRIBUTION
75
%
GRAVELCOBBLE
DESCRIPTION
BOULDERfine
% p
assi
ng
2 200
0.212
46
50
96
3
1
0
SAMPLE DEPTH (m)
SAMPLE No./TYPE
Geotechnical Engineering Limited
BH/TP No. TP03KINGSWOOD PARISH COUNCILCLIENT
CHECKEDCONTRACT
27979 WJ
SITE KINGSWOOD PLAYING FIELD2B
0.30
Geo
tech
nica
l Eng
inee
ring
Ltd,
Cen
turio
n H
ouse
, O
lym
pus
Par
k, Q
uedg
eley
, G
louc
este
r. G
L2 4
NF
. T
el. 0
1452
527
743
279
79.G
PJ
29/0
5/20
13 1
6:20
:41
109
GEOTECHNICAL DATA
2797
9Geotechnical Engineering Limited
APPENDIX C
110
0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
0 5 10 15 20 25 30 35 40 45 50 55 60
27979
KINGSWOOD PLAYING FIELD
KINGSWOOD PARISH COUNCIL
Dep
th (
m)
Moisture Content (%)
Geotechnical Engineering Limited
CLIENT
SITE
CONTRACT CHECKED
MOISTURE CONTENT PLOT
TP01
TP02
TP03
TP04
TP05
TP06
EW
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
111
0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
0 0.2 0.4 0.6 0.8 1.0
Geotechnical Engineering Limited
CLIENT
KINGSWOOD PLAYING FIELD
27979
SITE
CONTRACT CHECKED
Dep
th (
m)
Moisture Content/Liquid Limit
TP01
TP02
KINGSWOOD PARISH COUNCIL
MOISTURE CONTENT/LIQUID LIMIT PLOT
EW
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
112
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.4
1.5
1.6
1.7
0 20 40 60 80 100
KINGSWOOD PLAYING FIELD
27979
KINGSWOOD PARISH COUNCILde
pth
(m)
STRENGTH v DEPTH PLOT
cohesion (kPa)
Geotechnical Engineering Limited
CLIENT
SITE
CONTRACT CHECKEDdenotes cohesion determined from triaxial test results
denotes cohesion determined from hand shear vane test results
denotes a cohesion determined from SPT results using a factor of 5kPa (Stroud,1974)
EW
Geo
tech
nica
l Eng
inee
ring
Ltd,
Tel
. 014
52 5
2774
3
27
979.
GP
J T
RIA
LJH
.GP
J G
EO
TE
CH
.GLB
18
/6/1
3
113
Appendix 12
Peer Review of Flood Risk Assessment
114
!
!
Peer review of Flood Risk Assessment and Drainage
Assessment
Document: 1 Version: Draft
Professional advice Re S.11/1839/FUL, Land at Chestnut Park, Kingswood
Stroud District Council
October / 21 / 2011
!
!!
!!
!!!
115
!
!
!
Authors!
!
Andy!McConkey!–!Principal!urban!water!consultant!
!
Rebecca!Bailey!"!Hydrologist
116
!
!
Halcrow Group Limited
Burderop Park, Swindon, Wiltshire SN4 0QD
tel 01793 812479 fax 01793 812089
halcrow.com
Halcrow Group Limited has prepared this report in accordance with
the instructions of client Stroud District Council for the client’s sole and specific use.
Any other persons who use any information contained herein do so at their own risk.
© Halcrow Group Limited 2011
!
Peer review of Flood Risk Assessment and Drainage
Assessment
Professional advice Re S.11/1839/FUL, Land at Chestnut Park, Kingswood
Stroud District Council
October / 21 / 2011
!
117
Peer review of Flood Risk Assessment and Drainage Assessment
!
!
Contents
1 Scope of review 51.1 Introduction 5
1.2 Scope 5
1.3 Site location 3
1.4 Ground conditions 6
1.5 Site assessment – sources, mechanisms and pathways of flooding 6
1.6 Surface water drainage strategy 7
1.7 Foul water drainage strategy 11
2 Conclusions and recommendations 12
!
!
!
118
Peer review of Flood Risk Assessment and Drainage Assessment
!
5!
1 Scope of review
1.1 Introduction
Halcrow!Group!Limited!have!been!commissioned!by!Stroud!District!Council!to!
review!the!Flood!Risk!Assessment!and!drainage!strategies!submitted!in!support!of!
Planning!Application!S.11/0812/FUL!for!27!houses!at!Chestnut!Park.!
The!review!has!been!requested!to!consider!5!key!questions:!
1.!Is!the!application!sufficiently!detailed?!
(a)!If!not,!what!additional!information!is!required?!
2.!Are!the!mitigation!measures!appropriate?!
3.!What,!if!any,!impact!would!the!proposed!development!have!on!flooding!both!on!
the!site!and!the!surrounding!area/displacement?!!
4.!Will!the!development!preserve!the!greenfield!run!off!values!of!the!existing!field?!
5.!Are!there!any!maintenance!concerns!or!arduous!regimes!required!to!ensure!the!
longevity!of!the!proposals?!
1.2 Scope
This!review!has!been!prepared!using!the!following!documents:!
Planning!Policy!Statement!25:!development!and!flood!risk;!March!2010!!
Planning!Policy!Statement!25:!development!and!flood!risk;!December!2009!
Sewers!for!Adoption!6th!Edition;!2006!
Flood!and!Water!Management!Act;!2010!
Environment!Agency!representation!13!October!2011!
Flood!Risk!Assessment,!Chestnut!Park,!BWB!consulting!for!Taylor!Wimpey,!
September!2011.!!!
Interpretive!Report!on!site!investigation,!Structural!Soils!Limited!for!Taylor!Wimpey,!
July!2010.!
Code!for!Sustainable!Homes!Version!2;!May!2009!
Code!for!Sustainable!Homes!Technical!Guide;!November!2010!
!
!
!
!
!
!
119
Peer review of Flood Risk Assessment and Drainage Assessment
!
6!
1.3 Review of ground conditions
The!bedrock!geology!is!Jurassic,!Lower!Lias!Mudstones.!!There!are!no!superficial!
deposits.!(Source:!http://www.bgs.ac.uk/GeoIndex/)!
Bedrock!Aquifer!designation!=!Secondary!undifferentiated!(This!has!been!assigned!in!
cases!where!it!has!not!been!possible!to!attribute!either!category!A!or!B!to!a!rock!type.!!
In!most!cases,!this!means!that!the!layer!in!question!has!previously!been!designated!as!
both!minor!and!non"aquifer!in!different!locations!due!to!the!variable!characteristics!of!
the!rock!type).!
Ground!investigations!are!detailed!in!the!interpretative!report!on!site!conditions.!!
These!confirm!that!the!soil!is!primarily!clay!with!intervening!limestone!strata,!and!
support!the!application!of!soil!type!WRAP!4!for!modelling!purposes.!!!
A!soakaway!test!was!undertaken!in!one!trial!pit!(TP7)!and!after!3!hours,!no!drop!in!
water!level!was!observed.!!The!report!concludes!that!no!infiltration!rate!could!be!
calculated!and!soakaways!are!unlikely!to!be!suitable!for!this!site.!!!
We!consider!that!this!conclusion!is!acceptable.!
1.4 Review of site assessment – sources, mechanisms and pathways of flooding
Fluvial!flood!risk!(flood!risk!from!rivers):!!The!FRA!and!drainage!strategy!concludes!
that!the!site!has!a!low!probability!of!flooding!from!river!(less!than!0.1%).!!We!have!
reviewed!the!Environment!Agency!Flood!Maps!and!used!our!local!knowledge!from!
preparing!the!Stroud!District!Council!Strategic!Flood!Risk!Assessment;!September!
2008!and!agree!with!this!assessment.!!!
We!find!no!fault!with!the!calculations!assessing!the!risk!of!flooding!from!the!
unnamed!drainage!ditch!on!the!north!west!boundary!of!the!site,!and!concur!that!the!
drainage!ditch!has!capacity!for!the!peak!flow!deriving!from!its!calculated!upstream!
catchment.!!This!is!subject!to!the!drainage!ditch!being!maintained!and!regularly!
cleared!such!that!there!are!no!obstructions!to!flow1.!!!!
Tidal!flood!risk:!(flood!risk!from!the!coast!or!tidal!waters)!–!The!FRA!and!drainage!
strategy!concludes!that!the!site!has!a!low!probability!of!flooding!from!coastal!or!tidal!
waters.!!We!have!reviewed!the!Environment!Agency!Flood!Maps!and!used!our!local!
knowledge!from!preparing!the!Stroud!District!Council!Strategic!Flood!Risk!
Assessment;!September!2008!and!agree!with!this!assessment.!!!
!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!
!
!
!
!
1!The!modelling!has!assumed!that!the!roughness!of!the!ditch! is!equivalent!to!rough!
grass.!!This!assumption!is!only!correct!if!the!bankside!vegetation!is!low"level!scrub!or!
uncut!grass.!!!!See!section!1.5.6!!for!more!information.!
120
Peer review of Flood Risk Assessment and Drainage Assessment
!
7!
Pluvial!flood!risk:!!Modelling!has!been!undertaken!to!assess!the!implications!of!
pluvial!flood!risk!and!mitigation!has!been!identified!to!manage!this!risk.!!We!agree!
that!the!site!is!at!risk!of!pluvial!flooding,!and!our!assessment!of!the!proposed!
mitigation!follows!in!section!1.5.6!
Groundwater!flooding:!Given!the!geological!characteristics,!the!risk!of!flooding!from!
groundwater!is!considered!low.!!This!agrees!with!the!assessment!made!in!section!2.1!
of!the!report.!!
Sewer!flooding:!!Flood!risk!to!the!site!from!surface!water!sewer!flooding!should!be!
prevented!through!good!design!of!the!drainage!system.!!!Our!comments!on!this!
follow!in!section!1.5.3.!
Foul!water:!!!Subject!to!foul!drainage!meeting!the!requirements!of!Sewers!for!
Adoption!6th!volume,!there!should!be!no!foul!flood!risk!to!the!site.!!!
No!assessment!has!been!made!of!the!impact!of!development!on!downstream!foul!
sewer!flooding.!!However!the!wastewater!and!sewerage!company!(Wessex!Water)!
have!implied!that!they!have!no!objections!to!the!development!in!their!letter!dated!30th!
September.!!!For!the!sake!of!completeness,!it!is!recommended!that!the!developer!seek!
a!letter!from!Wessex!Water!confirming!that!they!have!no!objections!to!the!
development,!and!confirming!that!they!have!capacity!in!their!foul!water!network!for!
this!development,!without!development!increasing!the!risk!of!downstream!foul!
flooding!or!overflows!from!combined!sewers.!
Surface!water.!!Subject!to!surface!water!drainage!meeting!the!requirements!of!PPS25,!
there!should!be!no!surface!water!sewer!flood!risk!to!the!site.!!Good!design!of!this!
system!should!prevent!any!change!in!risk!of!flooding!from!the!downstream!system.!!
We!consider!the!drainage!system!design!in!section!1.5.3.!
1.5 Review of surface water drainage strategy
1.5.1 Hierarchy of drainage
PPS25!and!the!SUDS!manual!require!developers!to!consider!the!following!hierarchy!
of!destination!of!surface!water:!
! Infiltration!
! Above!ground!river!system!
! Surface!water!sewer!
! Combined!sewer!
The!FRA!has!confirmed!that!infiltration!to!ground!is!not!suitable,!and!has!proposed!
that!a!conventional!below!ground!drainage!system!be!constructed!to!intercept!surface!
water!and!store!it!on!site,!with!a!controlled!discharge!via!the!existing!surface!water!
sewer!system!to!the!Ozleworth!Stream.!!!!!
There!is!a!more!proximate!drainage!ditch,!referenced!throughout!the!FRA,!that!has!
not!been!assessed!as!a!possible!destination!for!drainage!for!the!development.!!It!
would!be!expected!that!the!developer!should!confirm!that!that!ditch!is!unsuitable!for!
drainage!before!determining!to!discharge!into!an!existing!surface!water!sewer.!!
However,!in!general!terms,!the!philosophy!of!the!destination!of!drainage!hierarchy!
has!been!followed.!!!!
121
Peer review of Flood Risk Assessment and Drainage Assessment
!
8!
1.5.2 Greenfield runoff calculations
Peak!flow!discharge!rates!have!been!provided!based!on!Greenfield!runoff!
calculations!undertaken!in!WinDES.!!!The!ADAS!345!methodology!has!been!used!to!
determine!Greenfield!rates.!!Defra/EA!guidance!specifies!that!IH124,!not!ADAS!345!
should!be!used!to!determine!Greenfield!rates.!!There!is!merit!in!the!FRA!choosing!to!
use!ADAS!345!as!it!is!the!only!accepted!methodology!that!includes!a!gradient!factor.!!
In!the!case!of!this!development,!the!upstream!gradient!is!a!factor!for!concern.!!!!
However,!in!light!of!the!DEFRA/EA!guidance!that!specifies!IH124,!we!would!expect!
the!FRA!to!use!both!methodologies!and!provide!the!results!for!both!methodologies.!!
We!would!then!expect!the!FRA!to!conclude!which!method!they!were!using!and!how!
the!design!approach!put!forward!allows!or!mitigates!for!the!uncertainty!between!the!
two!methodologies.!!
Notwithstanding!the!above,!the!calculations!of!the!peak!flow!for!the!entire!fluvial!
catchment!(Table!3.1)!are!considered!acceptable.!!!
Notwithstanding!the!first!paragraph!above,!calculations!of!peak!flow!at!the!location!
of!the!proposed!highway!for!passage!of!water!through!the!culvert!are!considered!
acceptable.!!
Calculations!of!peak!flow!for!the!site!area!(Table!3.2)!are!considered!acceptable.!!!
1.5.3 Proposed drainage strategy
A!range!of!attenuation!storage!based!on!the!calculated!Greenfield!rates!have!been!
provided!(Table!4.2),!but!no!value!has!been!selected!for!use!in!the!drainage!system.!!
The!conclusion!that!a!positive!drainage!system!below!ground!is!required!partly!
because!of!the!number!of!trees!that!need!to!be!retained!seems!reasonable!and!fair.!!It!
is!noted!that!the!applicant!has!significant!holdings!of!land!outside!the!application!red!
line!boundary.!!However,!this!is!upgradient!of!the!application!site!therefore!not!
suitable!for!above!ground!SUDS!features!development.!!Therefore!the!philosophy!of!
providing!attenuation!storage!below!ground!is!acceptable.!!
The!volume!of!attenuation!storage!to!be!provided!has!not!been!confirmed.!!!The!
calculated!storage!provided!in!table!4.2!is!based!on!1!hour!storage!of!peak!flow!in!a!
range!of!return!period!rainfall!events.!!!Further!modelling!will!be!required!to!
determine!the!volume!of!storage!required.!!!!
This!additional!modelling!will!also!need!to!determine!the!long!term!storage!
requirement!that!will!be!required!to!mitigate!for!the!additional!volume!of!runoff!
being!generated!that!cannot!be!infiltrated.!!!
The!Code!for!Sustainable!Homes!technical!guide!(November!2010)!has!a!mandatory!
requirement!that!the!drainage!strategy!must!ensure!‘the!additional!predicted!volume!of!
runoff!for!the!100!year!6!hour!event!must!be!prevented!from!leaving!the!site!by!using!
infiltration!or!other!SuDS!techniques.’!(see!Figure!1_2!below).!The!applicant!has!shown!
that,!in!general,!infiltration!is!not!possible.!!They!have!also!identified!small!scale!
SUDS!features.!!However,!some!of!these!SUDS!features!are!deliberately!designed!to!
prevent!infiltration,!and!no!information!has!been!provided!to!quantify!or!manage!this!
additional!predicted!volume.!!!!It!is!essential!that!the!applicant!provide!further!detail!
regarding!the!long!term!storage!that!will!be!required,!and!how!the!volume!and!rate!
of!this!long!term!storage!will!be!managed!in!accordance!with!the!Code!for!
Sustainable!Homes!(see!Figure!1_2!below).!
122
Peer review of Flood Risk Assessment and Drainage Assessment
!
9!
With!respect!to!runoff!from!the!impermeable!area!of!the!site,!the!applicant!has!stated!
that!the!new!impermeable!area!will!generate!between!75l/s!and!100l/s!of!surface!
water!runoff!but!has!not!provided!any!modelling!evidence!or!calculations!to!support!
this!statement.!!We!consider!that!the!values!are!realistic,!but!for!the!sake!of!
completeness!an!FRA!would!be!expected!to!include!this!evidence.!The!applicant!has!
proposed!controlling!the!rate!of!discharge!from!the!new!development!impermeable!
area!(to!mitigate!for!the!75!–!100l/s)!at!the!point!of!discharge!downstream!of!the!
existing!development!to!68l/s!(which!includes!the!Greenfield!rate!of!the!existing!
development!and!the!Greenfield!rate!of!the!new!development.!!!This!in!principle!is!
acceptable.!!However,!it!is!unclear!if!a!flow!control!device!will!be!constructed!at!the!
downstream!end!of!the!new!development!drainage.!!!We!consider!that!flow!control!at!
this!point!is!required!to!ensure!that!Greenfield!rates!are!to!be!maintained.!!We!
therefore!would!recommend!that!a!staged!flow!control!device,!controlling!to!the!1!in!
5,!1!in!30!and!1!in!100!rates!is!constructed!at!the!point!marked!‘proposed!storm!water!
flow!control!manhole!in!drawing!number!02"100"01.!!!!
We!note!that!Drawing!02"21"01!suggests!a!flow!control!device!of!57l/s!will!be!applied!
at!this!point,!which!is!significantly!greater!than!the!Greenfield!1!in!100!year!rate!of!
39.8l/s.!!!!!
The!applicant!has!stated!several!times!that!the!downstream!surface!water!drainage!
system!was!designed!to!accommodate!predicted!flows!from!both!the!existing!and!
proposed!development,!but!has!not!provided!any!evidence!to!support!this!statement.!!
We!recommend!at!further!evidence!be!provided!to!support!this!statement.!
The!applicant!has!stated!that!the!flow!controlling!device!at!the!downstream!point!of!
discharge!into!the!Ozleworth!Stream!will!need!to!be!increased!to!allow!for!the!
additional!Greenfield!runoff!rate!from!the!proposed!development.!!This!change!will!
need!a!land!drainage!consent!from!the!EA,!and!we!recommend!that!any!permission!is!
conditional!on!this!consent!being!granted.!
No!allowance!appears!to!have!been!made!for!the!drainage!of!undeveloped!or!
permeable!areas!of!the!site.!!Runoff!from!permeable!areas!will!occur,!especially!
because!the!developer!has!advised!that!the!soil!type!is!generally!impermeable!clay!
like!materials.!!If!land!use!in!these!areas!is!not!changing,!then!the!runoff!rate!and!
volume!will!not!change!significantly!from!the!existing!Greenfield,!and!this!should!not!
affect!the!volume!of!storage!or!the!peak!rate!of!runoff!control.!!However,!any!
drainage!system!draining!the!site!must!be!able!to!drain!the!total!area!of!the!site!
effectually,!not!just!the!developed!area.!!The!developer!must!clarify!that!the!drainage!
system!proposed!has!capacity!for!100%!of!the!1.470ha!site!area!in!a!100year!+!climate!
change!rainfall!event.!
!
123
Peer review of Flood Risk Assessment and Drainage Assessment
!
10!
!
!
Figure 1-1 Extract for Code for Sustainable Homes Technical Guide November 2010
!
!
124
Peer review of Flood Risk Assessment and Drainage Assessment
!
11!
1.5.4 Drainage system adoption
The!FRA!and!drainage!strategy!has!proposed!that!the!positive!drainage!system!will!
be!adopted!by!Wessex!Water.!!!The!system!as!proposed!appears!to!have!been!
designed!to!meet!Wessex!Water!adoption!criteria!as!stated!in!their!latter!on!30th!
September.!
1.5.5 Drainage system failure
No!consideration!has!been!given!to!the!risk!of!flooding!following!failure!of!flow!
control!devices.!!It!is!expected!that!a!failure!mechanism!would!be!provided!to!ensure!
that!property!flooding!does!not!occur!even!following!failure!of!the!device.!!
1.5.6 Pluvial flooding mitigation
It!is!agreed!that!the!localised!topography!at!the!southern!boundary!currently!suggests!
that!the!natural!flow!path!of!runoff!would!be!through!the!site!rather!than!in!to!the!
pond!and!ditch!system!(section!3.11).!!!
The!construction!of!a!land!bund!along!the!southern!border!will!provide!protection!
from!fluvial!flooding!if!designed!correctly.!!!
In!its!current!location,!we!consider!that!the!bund!will!only!protect!plots!18!and!24!and!
those!downslope!of!these.!!Given!the!levels!presented!in!the!site!survey!drawing,!the!
bund!is!considered!to!provide!no!protection!to!the!properties!to!the!east!of!the!site,!
namely,!25,!26,!27,!1,!2,!3,!and!4.!!!
The!profile!of!the!ground!behind!the!bund!needs!to!be!such!that!the!water!drains!
towards!the!pond.!!The!topographic!survey!does!not!provide!enough!evidence!that!
this!will!occur!if!current!levels!are!maintained.!!!
The!calculations!for!the!capacity!of!the!drainage!ditch!are!acceptable,!subject!to!the!
ditch!being!kept!in!a!clear!and!well!maintained!state.!!The!modelling!of!the!ditch!has!
assumed!that!the!ditch!is!‘rough!grass’.!!If!the!state!of!the!ditch!is!overgrown,!or!
blocked!with!debris,!the!carrying!capacity!of!the!ditch!will!be!less!than!modelled,!and!
there!may!be!a!residual!risk!of!flooding!from!this!ditch.!
1.6 Review of foul water drainage strategy
Wessex!Water!has!stated!that!they!have!no!objection!to!the!proposal!subject!to!a!
separate!system!being!installed,!no!land!drainage!being!connected!to!the!system,!and!
no!surface!water!being!connected!to!the!surface!water!system.!!The!system!as!
designed!appears!to!comply!with!these!stipulations.!!
!
!
125
Peer review of Flood Risk Assessment and Drainage Assessment
!
12!
2 Conclusions and recommendations
2.1 Is the application sufficiently detailed, and if not, what additional information is required?
Further!information!would!be!expected!in!support!of!this!application.!!!If!the!
authority!is!minded!to!grant!permission,!we!would!recommend!conditional!
agreement!based!on!the!additional!information!below!being!provided,!and!a!detailed!
drainage!masterplan!being!agreed!with!the!planning!authority,!prior!to!construction.!!!
Critical:!!!!
Volume!of!attenuation!required!to!mitigate!to!Greenfield!rate!and!volume.!!Insufficient!
evidence!has!been!provided!regarding!the!volume!of!storage!that!will!be!provided.!!
Further!detail!regarding!the!volume!or!storage!provided,!including!the!need!to!
control!both!volume!and!rate!of!long!term!storage!must!be!provided.!!
No!allowance!appears!to!have!been!made!for!the!drainage!of!undeveloped!or!
permeable!areas!of!the!site.!!The!developer!must!clarify!that!the!drainage!system!
proposed!has!capacity!for!100%!of!the!1.470ha!site!area!in!a!100year!+!climate!change!
rainfall!event.!
Drainage!system!failure:!No!consideration!has!been!given!to!the!risk!of!flooding!
following!failure!of!flow!control!devices.!!It!is!expected!that!a!failure!mechanism!
would!be!provided!to!ensure!that!property!flooding!does!not!occur!even!following!
failure!of!the!device.!!
Pluvial!runoff!protection!bund:!!It!is!not!clear!from!information!provided!in!the!FRA!
that!the!bund!would!protect!all!properties!that!may!be!at!risk!of!pluvial!flooding.!!
The!applicant!needs!to!demonstrate!through!detailed!design!that!all!properties!at!risk!
are!protected,!and!that!the!profile!of!the!ground!behind!the!bund!ensures!water!
drains!towards!the!pond.!!!
Downstream!system!design:!The!applicant!has!stated!several!times!that!the!downstream!
surface!water!drainage!system!was!designed!to!accommodate!predicted!flows!from!
both!the!existing!and!proposed!development,!but!has!not!provided!any!evidence!to!
support!this!statement.!!We!recommend!further!evidence!be!provided!to!support!this!
statement.!
For!completeness:!!!
Foul!water:!For!the!sake!of!completeness,!it!is!recommended!that!the!developer!seek!a!
letter!from!Wessex!Water!confirming!that!they!have!no!objections!to!the!
development,!and!confirming!that!they!have!capacity!in!their!foul!water!network!for!
this!development,!without!development!increasing!the!risk!of!downstream!foul!
flooding!or!overflows!from!combined!sewers.!
Greenfield!runoff!calculations:!!The!assessment!is!not!fully!compliant!with!the!Defra/EA!
guidance.!Although!there!are!sound!technical!reasons!why!the!approach!chosen!has!
been!applied!in!light!of!the!variation!from!the!prescribed!approach,!we!would!expect!
the!FRA!to!use!both!methodologies!and!provide!the!results!for!both!methodologies.!!
We!would!then!expect!the!FRA!to!conclude!which!method!they!were!using!and!how!
the!design!approach!put!forward!allows!or!mitigates!for!the!uncertainty!between!the!
two!methodologies.!
126
Peer review of Flood Risk Assessment and Drainage Assessment
!
13!
2.2 Are the mitigation measures appropriate?
In!principle!yes,!subject!to!the!further!information!identified!above!being!provided!
and!agreed.!
2.3 What, if any, impact would the proposed development have on flooding both on the site and the surrounding area/displacement?
Mitigation!measures!appear!to!have!been!considered!in!principle.!!Subject!to!further!
information!required!being!provided!and!agreed!with!the!authority,!these!principles!
should!ensure!there!is!no!impact!on!flooding!on!the!site!or!surrounding!
area/displacement.!
The!calculations!for!the!capacity!of!the!drainage!ditch!are!acceptable!for!the!
conveyance!of!upstream!pluvial!runoff,!subject!to!the!ditch!being!kept!in!a!clear!and!
well!maintained!state.!!!If!the!state!of!the!ditch!is!overgrown,!or!blocked!with!debris,!
the!carrying!capacity!of!the!ditch!will!be!less!than!modelled,!and!there!may!be!a!risk!
of!flooding!from!this!ditch.!
2.4 Will the development preserve the greenfield run off values of the existing field?
In!principle!yes,!subject!to!the!further!information!identified!above!being!provided!
and!agreed.!
2.5 Are there any maintenance concerns or arduous regimes required to ensure the longevity of the proposals?
The!positive!drainage!system!has!been!designed!in!principle!to!meet!Wessex!Water’s!
adoptions!requirements.!
The!pluvial!runoff!mitigation!and!protection!system!will!require!maintenance.!!We!
recommend!that!the!developer!be!required!to!consider!the!operational,!management!
and!funding!requirements!to!ensure!that!maintenance!of!the!bund!and!ensure!the!
maintenance!and!regular!clearance!of!the!pond!and!drainage!ditch!from!debris!and!
plant!growth.!!!
!
!
!
!
!
!
127
Peer review of Flood Risk Assessment and Drainage Assessment
!
14!
!
128
!
!
!
For details of your nearest Halcrow office, visit our website halcrow.com
!
129