ansi c29.17 prototype test report - hubbellcdn · engineering report subject ansi c29.17 prototype...

27
ANSI C29.17 Quadri*Sil Repor Section Prototype Tests I. Tests on Interfaces II. Core Load - Time T III. Tensile Load Test IV. Housing Tracking a V. Aging or Weathering VI. Dye Penetration Te VII. Water Diffusion Tes VIII. Flammability Tests 7 Prototype Test R 300 Line Post Insulato rt Number: R12-11-03 Table of Contents ANSI Clause and Connections of End Fittings 7.1 Test 7.2.1 7.2.2 and Erosion Tests 7.3.1 g Test 7.3.2 est 7.4.1 st 7.4.2 7.5 Design Test R Report ors Page 3 11 13 17 20 21 24 25 Report EU-1603

Upload: votuyen

Post on 26-Apr-2018

232 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ANSI C29.17 Prototype Quadri*Sil 300 Line Post

Report Number:

Section Prototype Tests I. Tests on Interfaces and Connections of End Fittings

II. Core Load - Time Test III. Tensile Load Test

IV. Housing Tracking and Erosion Tests

V. Aging or Weathering Test

VI. Dye Penetration Test VII. Water Diffusion Test

VIII. Flammability Tests

C29.17 Prototype Test Report

Quadri*Sil 300 Line Post InsulatorsReport Number: R12-11-03

Table of Contents

ANSI Clause

Tests on Interfaces and Connections of End Fittings 7.1

Time Test 7.2.1

7.2.2

g and Erosion Tests 7.3.1

athering Test 7.3.2

ation Test 7.4.1

usion Test 7.4.2

7.5

Design Test Report EU

Test Report nsulators

Page

3

11

13

17

20

21

24

25

Design Test Report EU-1603

Page 2: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 2 Test Requests:

Introduction:

Sample insulators were evaluated according to the protocols established within ANSI C29.1

tested varied in length to match the requirements of the standard. The polymer weathersheds were

composed of 1800-120V silicone rubber. The coupling agent employed between the fiberglass rod and the

polymer was Chemlok 608. The fiberglass

(Electrical grade – Corrosion Resistant Direct Draw) glass fibers and pultruded in the Centralia, Missouri

or Aiken, South Carolina facility.

Details:

A summary of the tests performed and their

Test Name

Tests on interfaces and connection of end fittings

Core time-load test

Tensile load test

Housing tracking and erosion tests

Aging or weathering test

Dye penetration test

Water diffusion test

Flammability test

Discussion:

All of the tests were successfully completed.

Conclusions:

The Quadri*Sil Series 300 line post met all of the requirements of the ANSI C29.17 prototype tests.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Prototype Testing

ANSI C29.17

Quadri*Sil Series 300 Line Posts

Sample insulators were evaluated according to the protocols established within ANSI C29.17

tested varied in length to match the requirements of the standard. The polymer weathersheds were

120V silicone rubber. The coupling agent employed between the fiberglass rod and the

polymer was Chemlok 608. The fiberglass rod was an HPS epoxy resin system reinforced with E

Corrosion Resistant Direct Draw) glass fibers and pultruded in the Centralia, Missouri

A summary of the tests performed and their results is contained in table 1.

Standard/Clause Request Number

Tests on interfaces and connection of end fittings ANSI C29.17/7.1 E11

ANSI C29.17/7.2.1 M12

ANSI C29.17/7.2.2 M11

ANSI C29.17/7.3.1 E12

ANSI C29.17/7.3.2 M05

ANSI C29.17/7.4.1 M11

ANSI C29.17/7.4.2 E11

ANSI C29.17/7.5 R02

Table 1

All of the tests were successfully completed.

The Quadri*Sil Series 300 line post met all of the requirements of the ANSI C29.17 prototype tests.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

7. The samples

tested varied in length to match the requirements of the standard. The polymer weathersheds were

120V silicone rubber. The coupling agent employed between the fiberglass rod and the

rod was an HPS epoxy resin system reinforced with E-CR DD

Corrosion Resistant Direct Draw) glass fibers and pultruded in the Centralia, Missouri

Request Number

E11-10-19

M12-10-05

M11-10-12

E12-02-18

M05-04-07

M11-10-13

E11-10-18

R02-11-02

The Quadri*Sil Series 300 line post met all of the requirements of the ANSI C29.17 prototype tests.

Page 3: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 3 Test Requests:

Tests on Interf

Introduction:

The tests on interfaces and connections of end fittings were performed on samples of Quadri*Sil Series

300 line posts. The procedure emp

of the test was performed at PowerTech Labs. The insulators tested were catalog number P300046S0040.

The samples were manufactured with 1800

and Chemlok 608 coupling agent.

Test Protocol:

The insulators were subjected to the test protocol that follows.

7.1 Tests on interfaces and connection of end fittings

7.1.1 Test specimens

Four insulators, representative of the production pro

shall be reserved as a reference for the power frequency voltage test in 7.1.3.3. The insulator length

(metal-to-metal) will be at least 15 times the core diameter. If shorter insulators are tested, the

results are valid only for insulators up to the length tested.

The insulators shall be subjected to the routine mechanical test, per section 10.

7.1.2 Pre-stressing

The following tests (7.1.2.1, 7.1.2.2) shall be carried out on three test insulators in the s

indicated below.

7.1.2.1 Thermal-mechanical test

The three insulators will be loaded in cantilever and subjected to the temperature cycle described

in Figure 2. The load shall be selected so as to produce the same bending moment at the base of

the insulator as is exerted by 50% of the SCL in normal application.

Each 24 hour cycle has a minimum of 8 hours at both +50ºC and

shall be run twice, with the direction of the load reversed after the first cycle.

The test may be interrupted for the load direction reversal and for maintenance of the test

equipment for a total duration of 2 hours.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

ANSI C29.17 - Clause 7.1

Tests on Interfaces and Connections of End Fittings

Quadri*Sil Series 300 Post

Catalog Number P300046S0040

E11-10-19

The tests on interfaces and connections of end fittings were performed on samples of Quadri*Sil Series

300 line posts. The procedure employed was as defined by ANSI C29.17. The thermal-mechanical portion

of the test was performed at PowerTech Labs. The insulators tested were catalog number P300046S0040.

The samples were manufactured with 1800-120V silicone rubber, Chance epoxy E-CR DD fiberglass rod

The insulators were subjected to the test protocol that follows.

Tests on interfaces and connection of end fittings

Four insulators, representative of the production process and design, shall be selected. One of these

shall be reserved as a reference for the power frequency voltage test in 7.1.3.3. The insulator length

metal) will be at least 15 times the core diameter. If shorter insulators are tested, the

sults are valid only for insulators up to the length tested.

The insulators shall be subjected to the routine mechanical test, per section 10.

The following tests (7.1.2.1, 7.1.2.2) shall be carried out on three test insulators in the s

mechanical test

The three insulators will be loaded in cantilever and subjected to the temperature cycle described

in Figure 2. The load shall be selected so as to produce the same bending moment at the base of

sulator as is exerted by 50% of the SCL in normal application.

Each 24 hour cycle has a minimum of 8 hours at both +50ºC and -35ºC ±5K. The 24 hour cycle

shall be run twice, with the direction of the load reversed after the first cycle.

interrupted for the load direction reversal and for maintenance of the test

equipment for a total duration of 2 hours.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

The tests on interfaces and connections of end fittings were performed on samples of Quadri*Sil Series

mechanical portion

of the test was performed at PowerTech Labs. The insulators tested were catalog number P300046S0040.

fiberglass rod

cess and design, shall be selected. One of these

shall be reserved as a reference for the power frequency voltage test in 7.1.3.3. The insulator length

metal) will be at least 15 times the core diameter. If shorter insulators are tested, the

The following tests (7.1.2.1, 7.1.2.2) shall be carried out on three test insulators in the sequence

The three insulators will be loaded in cantilever and subjected to the temperature cycle described

in Figure 2. The load shall be selected so as to produce the same bending moment at the base of

35ºC ±5K. The 24 hour cycle

interrupted for the load direction reversal and for maintenance of the test

Page 4: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 4 Test Requests:

7.1.2.2 Water immersion test

The three test insulators will be immersed in boiling water for 42 continuous hours (de

water with 0.1% NaCl or tap water adjusted to a conductivity of 1650 µS/cm ±50 µS/cm at 20º C

25ºC). After the 42 hour boiling period, the insulators will remain in the vessel until the water

cools to approximately 50ºC. This temperature will be maintained until the

started.

7.1.3 Verification tests

The following verification tests (7.1.3.1, 7.1.3.2, 7.1.3.3) shall be completed within 48 hours

following the removal of the insulators from the water.

7.1.3.1 Visual examination

The housing shall be inspec

are permitted.

7.1.3.2 Steep-front impulse test

The three test specimens will be fitted with a sharp edged electrode, consisting of a clip made of

copper strip approximately 20mm wide and le

firmly on the housing or sheath between the weathersheds, forming two sections of 500 mm or

smaller axial length. If the test specimens have an insulating length that is less than or equal to

500mm, the voltage will be applied between the end fittings (no clip is necessary).

An impulse voltage with a steepness of at least 1000 kV/µs will be applied to each test section.

Each section will be stressed with 25 impulses of positive polarity and 25 impulses of

polarity. Each impulse shall cause an external flashover of the test section. No punctures of any

part of the insulator shall occur.

The electrodes used to form the test sections will be removed prior to the power frequency voltage

test.

7.1.3.3 Power frequency voltage test

The dry power frequency flashover voltage will be determined by averaging five flashover

voltages on each insulator per ANSI/IEEE 4. The flashover voltage will be reached within 1

minutes by increasing the voltage linearly fro

insulator will be determined using the same procedure.

The average flashover voltage for each test insulator will be at least 90% of the flashover voltage

of the reference insulator.

The three test insulators and the reference insulator will be allowed to reach thermal equilibrium

with the surrounding atmosphere. All four insulator will then be subjected to 80% of the reference

insulator flashover voltage for 30 minutes. No puncture of any part of the in

and the temperature of the shank (measured immediately after the test) will not be more than 20ºC

above the ambient temperature.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Water immersion test

The three test insulators will be immersed in boiling water for 42 continuous hours (de

% NaCl or tap water adjusted to a conductivity of 1650 µS/cm ±50 µS/cm at 20º C

25ºC). After the 42 hour boiling period, the insulators will remain in the vessel until the water

cools to approximately 50ºC. This temperature will be maintained until the verification tests are

The following verification tests (7.1.3.1, 7.1.3.2, 7.1.3.3) shall be completed within 48 hours

following the removal of the insulators from the water.

Visual examination

The housing shall be inspected visually. No cracks or crazing of the elastomeric shed or housing

front impulse test

The three test specimens will be fitted with a sharp edged electrode, consisting of a clip made of

copper strip approximately 20mm wide and less than 1mm in thickness. The electrode will

firmly on the housing or sheath between the weathersheds, forming two sections of 500 mm or

smaller axial length. If the test specimens have an insulating length that is less than or equal to

tage will be applied between the end fittings (no clip is necessary).

An impulse voltage with a steepness of at least 1000 kV/µs will be applied to each test section.

Each section will be stressed with 25 impulses of positive polarity and 25 impulses of

polarity. Each impulse shall cause an external flashover of the test section. No punctures of any

part of the insulator shall occur.

The electrodes used to form the test sections will be removed prior to the power frequency voltage

ower frequency voltage test

The dry power frequency flashover voltage will be determined by averaging five flashover

voltages on each insulator per ANSI/IEEE 4. The flashover voltage will be reached within 1

minutes by increasing the voltage linearly from zero. The flashover voltage of the reference

insulator will be determined using the same procedure.

The average flashover voltage for each test insulator will be at least 90% of the flashover voltage

of the reference insulator.

tors and the reference insulator will be allowed to reach thermal equilibrium

with the surrounding atmosphere. All four insulator will then be subjected to 80% of the reference

insulator flashover voltage for 30 minutes. No puncture of any part of the insulator shall occur,

and the temperature of the shank (measured immediately after the test) will not be more than 20ºC

above the ambient temperature.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

The three test insulators will be immersed in boiling water for 42 continuous hours (de-ionized

% NaCl or tap water adjusted to a conductivity of 1650 µS/cm ±50 µS/cm at 20º C -

25ºC). After the 42 hour boiling period, the insulators will remain in the vessel until the water

verification tests are

The following verification tests (7.1.3.1, 7.1.3.2, 7.1.3.3) shall be completed within 48 hours

ted visually. No cracks or crazing of the elastomeric shed or housing

The three test specimens will be fitted with a sharp edged electrode, consisting of a clip made of

ss than 1mm in thickness. The electrode will be

firmly on the housing or sheath between the weathersheds, forming two sections of 500 mm or

smaller axial length. If the test specimens have an insulating length that is less than or equal to

An impulse voltage with a steepness of at least 1000 kV/µs will be applied to each test section.

Each section will be stressed with 25 impulses of positive polarity and 25 impulses of negative

polarity. Each impulse shall cause an external flashover of the test section. No punctures of any

The electrodes used to form the test sections will be removed prior to the power frequency voltage

The dry power frequency flashover voltage will be determined by averaging five flashover

voltages on each insulator per ANSI/IEEE 4. The flashover voltage will be reached within 1

m zero. The flashover voltage of the reference

The average flashover voltage for each test insulator will be at least 90% of the flashover voltage

tors and the reference insulator will be allowed to reach thermal equilibrium

with the surrounding atmosphere. All four insulator will then be subjected to 80% of the reference

sulator shall occur,

and the temperature of the shank (measured immediately after the test) will not be more than 20ºC

Page 5: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 5 Test Requests:

Test Results:

Clause 7.1.1 – Test specimens:

The samples evaluated were catalog number P300046S0040 w

of the sales drawing is included as figure 1.

Clause 7.1.2.1 – Thermal-

The thermal-mechanical portion of the test was performed at

load profile is shown as figure 2.

PowerTech’s report stated, “No breakage of the end fittings or visible deformation or pullout of

the core rod occurred.”

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Test specimens:

The samples evaluated were catalog number P300046S0040 with an S.C.L. of 5400 lbf. A copy

of the sales drawing is included as figure 1.

Figure 1

-mechanical Test:

mechanical portion of the test was performed at PowerTech Labs. A typical thermal

load profile is shown as figure 2.

PowerTech’s report stated, “No breakage of the end fittings or visible deformation or pullout of

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

ith an S.C.L. of 5400 lbf. A copy

PowerTech Labs. A typical thermal-

PowerTech’s report stated, “No breakage of the end fittings or visible deformation or pullout of

Page 6: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 6 Test Requests:

Clause 7.1.2.2 – Water Immersion Test:

The samples were immersed in boiling water in accordance with the standard.

Clause 7.1.3.1 – Visual examination:

Each of the insulators was examined. No cracks were found.

Clause 7.1.3.2 – Steep-front impulse voltage test:

Each of the insulators was subjected to a steep

insulators into sections shorter than 500 mm. All flashovers were external. The data is contained

in tables 1 2and 3.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Water Immersion Test:

mersed in boiling water in accordance with the standard.

Figure 2

Visual examination:

Each of the insulators was examined. No cracks were found.

front impulse voltage test:

of the insulators was subjected to a steep-front impulse voltage by sub-dividing the

insulators into sections shorter than 500 mm. All flashovers were external. The data is contained

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

dividing the

insulators into sections shorter than 500 mm. All flashovers were external. The data is contained

Page 7: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 7 Test Requests:

Sample

Line 9 sheds

End/Pol. Top/+ Top/-

1 399 368

2 396 366

3 399 366

4 394 366

5 394 368

6 394 368

7 394 366

8 394 366

9 394 366

10 396 368

11 394 366

12 394 366

13 391 366

14 394 366

15 391 366

16 396 366

17 396 366

18 394 368

19 391 366

20 399 366

21 391 366

22 391 366

23 394 368

24 391 366

25 394 366

Pass Pass

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Table 1

Sample #1

Line Mid 10 sheds Ground Mid 10 sheds Ground 9 sheds

- Mid/+ Mid/- Mid/+ Mid/- Grd./+

368 362 370 401 370 384

366 362 373 404 370 384

366 362 375 401 370 387

366 365 373 404 368 384

368 362 373 404 368 387

368 362 373 404 368 387

366 365 373 404 370 384

366 362 373 404 368 387

366 365 373 401 368 387

368 360 373 404 368 387

366 362 370 404 370 387

366 362 373 408 370 387

366 365 373 404 368 387

366 365 373 405 370 381

366 365 370 401 366 384

366 365 373 404 370 384

366 362 375 401 368 384

368 365 373 404 370 384

366 365 373 399 370 384

366 362 370 401 368 384

366 362 370 404 370 384

366 362 373 404 368 384

368 362 373 404 370 384

366 365 370 404 368 384

366 365 370 408 370 384

Pass Pass Pass Pass Pass Pass

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

Ground 9 sheds

Grd./-

368

368

361

370

370

370

370

370

370

370

370

370

370

368

370

370

370

368

370

370

370

366

368

370

370

Pass

Page 8: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 8 Test Requests:

Sample

Line 9 sheds

End/Pol. Top/+ Top/-

1 394 375

2 399 375

3 391 370

4 391 370

5 394 373

6 391 373

7 399 370

8 391 373

9 394 373

10 394 373

11 391 370

12 394 373

13 394 370

14 391 370

15 394 370

16 391 373

17 396 370

18 394 370

19 394 370

20 394 370

21 396 375

22 394 370

23 394 370

24 394 370

25 394 370

Pass Pass

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Table 2

Sample #2 Line Mid 10 sheds Ground Mid 10 sheds Ground 9 sheds

- Mid/+ Mid/- Mid/+ Mid/- Grd./+

375 401 366 396 368 384

375 404 370 399 368 387

370 405 370 396 368 384

370 404 370 399 366 381

373 410 368 399 370 387

373 405 370 396 370 387

370 404 366 399 370 384

373 401 370 399 366 387

373 404 368 401 368 384

373 404 370 399 370 381

370 404 373 401 368 384

373 408 370 401 368 384

370 401 370 399 370 384

370 408 373 399 368 384

370 401 370 399 370 384

373 399 370 399 368 384

370 401 370 401 370 384

370 404 370 399 370 384

370 404 370 399 368 381

370 404 368 399 368 384

375 404 370 399 368 381

370 404 368 399 368 384

370 404 368 399 370 384

370 404 366 399 368 384

370 404 368 399 370 387

Pass Pass Pass Pass Pass Pass

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

Ground 9 sheds

Grd./-

370

373

373

375

373

375

375

373

375

373

370

370

373

373

370

370

370

373

370

373

370

370

370

370

370

Pass

Page 9: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 9 Test Requests:

Clause 7.1.3.3 – Dry power frequency voltage test:

The 3 sample insulators were tested for dry flas

was performed. Data is contained in tables 4 and 5. All corrections are in accordance with ANSI

C29.1

Reference

Bar (cmHg) 73.4

Temp dry (ºC) 23.05

Rel. Hum. 17.7

Sample

Line 9 sheds

End/Pol. Top/+ Top/-

1 391 375

2 391 375

3 391 373

4 390 373

5 396 373

6 391 375

7 394 375

8 394 373

9 394 370

10 394 373

11 391 373

12 396 373

13 394 373

14 391 373

15 391 373

16 391 373

17 394 373

18 394 373

19 391 375

20 391 373

21 394 370

22 394 373

23 394 375

24 394 373

25 391 373

Pass Pass

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Table 3

Dry power frequency voltage test:

The 3 sample insulators were tested for dry flashover values and a 30-minute, 80% withstand test

was performed. Data is contained in tables 4 and 5. All corrections are in accordance with ANSI

Reference Unit 1 Unit 2 Unit 3

73.4 73.4 73.4

23.05 23.5 23.5 23.0

17.6 17.3 17.7

Table 4

Sample #3 Line Mid 10 sheds Ground Mid 10 sheds Ground 9 sheds

- Mid/+ Mid/- Mid/+ Mid/- Grd./+

375 401 375 399 370 384

375 401 378 401 370 389

373 405 378 404 370 391

373 404 378 404 370 391

373 404 375 401 370 391

375 405 375 404 370 391

375 404 373 408 370 391

373 408 373 404 370 391

370 404 370 401 370 390

373 408 375 404 370 387

373 405 375 404 370 387

373 404 375 401 370 387

373 401 378 404 380 391

373 404 375 404 302 391

373 401 375 401 382 391

373 401 375 404 382 391

373 401 375 401 382 390

373 401 375 404 382 390

375 404 375 404 382 390

373 405 375 405 382 391

370 401 375 405 382 391

373 405 375 405 382 391

375 399 375 401 382 390

373 404 378 401 382 391

373 401 370 401 380 391

Pass Pass Pass Pass Pass Pass

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

minute, 80% withstand test

was performed. Data is contained in tables 4 and 5. All corrections are in accordance with ANSI

Ground 9 sheds

Grd./-

378

380

380

380

382

382

382

382

382

382

382

380

382

380

382

380

382

380

380

380

378

382

378

380

378

Pass

Page 10: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 10 Test Requests:

Corrected Flashovers

Flashover No. Reference

1 491

2 491

3 485

4 497

5 504

6 504

7 479

8 491

9 479

10 479

Average

Flashover 490

30 Minute Withstand Test

Start Withstand

End Withstand

Temperature Differential

Differential from Ambient

Conclusions:

The samples of the Quadri*Sil Series 300 Line Post insulators manufactured with Chance Epoxy Series 300

E-CR DD rod and 1800-120V silicone rubber met all of the requirements of the test proto

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Reference Unit 1 Unit 2 Unit 3

491 498 497

479 480 497

473 498 497

461 498 491

479 498 497

473 498 497

479 480 497

461 504 491

473 480 479

473 480 497

474 491 494

30 Minute Withstand Test

kV ºC kV ºC kV ºC

392 18.7 392 17.5 392 17.5

392 21.8 392 23 392 21.7

Temperature Differential 3.1 5.5 4.2

ential from Ambient -1.7 -.5 -1.3

Table 5

The samples of the Quadri*Sil Series 300 Line Post insulators manufactured with Chance Epoxy Series 300

120V silicone rubber met all of the requirements of the test protocol.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

The samples of the Quadri*Sil Series 300 Line Post insulators manufactured with Chance Epoxy Series 300

col.

Page 11: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 11 Test Requests:

Introduction:

Three samples of Quadri*Sil, series 300 line post, catalog number P300053S0020 were used for the

performance of the core time-load test in accordance wit

manufactured without polymer on the core rod and employed Epoxy E

in Aiken.

Test Protocol:

The testing was performed in accordance with the following protocol.

7.2.1 Core time-load test

7.2.1.1 Test specimens

Three insulators manufactured on the production line using the standard end fittings shall be

selected. The section length (pole face to line attachment) shall be between 15 and 24 times the

diameter of the core, or the lon

7.2.1.2 Core time load test

Each insulator shall be gradually loaded to 40% of the SCL or the manufacturer’s RCL (whichever is

greater) at a temperature of 20ºC ± 10 K. The load shall be applied to the insulat

position, approximately perpendicular to the intended orientation of the conductor and

approximately perpendicular to the core of the insulator. The load shall be maintained for at least

96 hours.

7.2.1.3 Evaluation

7.2.1.3.1 Visual examination

After removal of the load, visually inspect the base end fitting for cracks or permanent

deformation. All threaded connections must be intact and usable.

7.2.1.3.2 Dissection and dye penetration

Cut each insulator 90º to the axis

the base end fitting longitudinally into two halves in the plane of the previously applied cantilever

load. The cut surfaces shall be smoothed by means of fine abrasive cloth (grain size 180

The cut halves shall be visually inspected for cracks and delamination. The presence of cracks or

delamination in the fiberglass rod shall constitute failure.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Core Time-Load Test

ANSI C29.17 – Clause 7.2.1

Catalog Number P300047S0040

Three samples of Quadri*Sil, series 300 line post, catalog number P300053S0020 were used for the

load test in accordance with ANSI C29.17, clause 7.2.1. The insulators were

manufactured without polymer on the core rod and employed Epoxy E-CR DD fiberglass rod manufactured

testing was performed in accordance with the following protocol.

Three insulators manufactured on the production line using the standard end fittings shall be

selected. The section length (pole face to line attachment) shall be between 15 and 24 times the

diameter of the core, or the longest length to be manufactured, whichever is less.

Each insulator shall be gradually loaded to 40% of the SCL or the manufacturer’s RCL (whichever is

greater) at a temperature of 20ºC ± 10 K. The load shall be applied to the insulator at the conductor

position, approximately perpendicular to the intended orientation of the conductor and

approximately perpendicular to the core of the insulator. The load shall be maintained for at least

mination

After removal of the load, visually inspect the base end fitting for cracks or permanent

deformation. All threaded connections must be intact and usable.

7.2.1.3.2 Dissection and dye penetration

Cut each insulator 90º to the axis of the core and about 50 mm from the base end fitting, then cut

the base end fitting longitudinally into two halves in the plane of the previously applied cantilever

load. The cut surfaces shall be smoothed by means of fine abrasive cloth (grain size 180

The cut halves shall be visually inspected for cracks and delamination. The presence of cracks or

delamination in the fiberglass rod shall constitute failure.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

Three samples of Quadri*Sil, series 300 line post, catalog number P300053S0020 were used for the

h ANSI C29.17, clause 7.2.1. The insulators were

CR DD fiberglass rod manufactured

Three insulators manufactured on the production line using the standard end fittings shall be

selected. The section length (pole face to line attachment) shall be between 15 and 24 times the

Each insulator shall be gradually loaded to 40% of the SCL or the manufacturer’s RCL (whichever is

or at the conductor

position, approximately perpendicular to the intended orientation of the conductor and

approximately perpendicular to the core of the insulator. The load shall be maintained for at least

After removal of the load, visually inspect the base end fitting for cracks or permanent

of the core and about 50 mm from the base end fitting, then cut

the base end fitting longitudinally into two halves in the plane of the previously applied cantilever

load. The cut surfaces shall be smoothed by means of fine abrasive cloth (grain size 180).

The cut halves shall be visually inspected for cracks and delamination. The presence of cracks or

Page 12: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 12 Test Requests:

A dye penetration test shall be performed on the cut surfaces in accordance with ISO 34

reveal cracks. The presence of cracks or delamination in the fiberglass rod shall constitute

failure.

Test Results:

The first two insulators were loaded in opposition to one another. A load cell was included in the

connecting link. The third sample was loaded against a reference insulator for which the data was not

included.

Sample No. Catalog No.

1R & 1L P300053S0020

1R & 1L P300053S0020

3R P300053S0020

3R P300053S0020

No failures occurred during the period of applied load. An examination of the bases and associated

hardware for each of the insulators found no damage.

The dye penetration test was performed on each of the samples. No dye penetration was found.

Conclusions:

The sample Quadri*Sil, series 300 line post insulators met the requirements of the test.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

A dye penetration test shall be performed on the cut surfaces in accordance with ISO 34

reveal cracks. The presence of cracks or delamination in the fiberglass rod shall constitute

The first two insulators were loaded in opposition to one another. A load cell was included in the

sample was loaded against a reference insulator for which the data was not

Date Time Load, lb

10/8/12 1200 2360

10/12/12 1200 2360

10/18/12 1130 2360

10/22/12 1130 2360

No failures occurred during the period of applied load. An examination of the bases and associated

for each of the insulators found no damage.

The dye penetration test was performed on each of the samples. No dye penetration was found.

The sample Quadri*Sil, series 300 line post insulators met the requirements of the test.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

A dye penetration test shall be performed on the cut surfaces in accordance with ISO 3452 to

reveal cracks. The presence of cracks or delamination in the fiberglass rod shall constitute

The first two insulators were loaded in opposition to one another. A load cell was included in the

sample was loaded against a reference insulator for which the data was not

Comments

Start of Test

End of Test

Start of Test

End of Test

No failures occurred during the period of applied load. An examination of the bases and associated

The dye penetration test was performed on each of the samples. No dye penetration was found.

Page 13: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 13 Test Requests:

Introduction:

The tensile load test was performed on samples of Quadri*Sil Series 300 line posts, catalog number

P300046S0360. These insulators were manufactured with Chance Ep

nominal diameter), 1800-120V silicone rubber and Chemlok 608 coupling agent. The test was performed in

accordance with ANSI C29.17, clause 7.2.2.

Test Protocol:

The test protocol is listed below.

7.2.2 Specified tensile load test

7.2.2.1 Test specimens

Three insulators manufactured on the production line using the standard end fittings shall be

selected.

7.2.2.2 Test procedures

A tensile load shall be applied to each insulator in line with the axis of the core of t

load shall be increased rapidly but smoothly from zero to 75% of the Specified Tensile Load (S.T.L.)

and shall then gradually increased in a time between 30 and 90 seconds until the STL is reached. If

the S.T.L. is reached in less than

90 seconds. At the conclusion of 90s, the load shall be removed.

7.2.2.3 Test evaluation

The test shall be regarded as passed if there is no evidence of:

• Pull out of the core from the end

• Breakage of the end fitting

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Tensile Load Test

ANSI C29.17 – Clause 7.2.2

Catalog Number P300046S0360

The tensile load test was performed on samples of Quadri*Sil Series 300 line posts, catalog number

These insulators were manufactured with Chance Epoxy E-CR DD fiberglass rod (3”

120V silicone rubber and Chemlok 608 coupling agent. The test was performed in

accordance with ANSI C29.17, clause 7.2.2.

load test

Three insulators manufactured on the production line using the standard end fittings shall be

A tensile load shall be applied to each insulator in line with the axis of the core of the insulator. The

load shall be increased rapidly but smoothly from zero to 75% of the Specified Tensile Load (S.T.L.)

and shall then gradually increased in a time between 30 and 90 seconds until the STL is reached. If

the S.T.L. is reached in less than 90 seconds, the load shall be maintained for the remainder of the

90 seconds. At the conclusion of 90s, the load shall be removed.

The test shall be regarded as passed if there is no evidence of:

Pull out of the core from the end fitting

Breakage of the end fitting

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

The tensile load test was performed on samples of Quadri*Sil Series 300 line posts, catalog number

CR DD fiberglass rod (3”

120V silicone rubber and Chemlok 608 coupling agent. The test was performed in

Three insulators manufactured on the production line using the standard end fittings shall be

he insulator. The

load shall be increased rapidly but smoothly from zero to 75% of the Specified Tensile Load (S.T.L.)

and shall then gradually increased in a time between 30 and 90 seconds until the STL is reached. If

90 seconds, the load shall be maintained for the remainder of the

Page 14: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 14 Test Requests:

Test Results:

The results of the test are contained in table 1.

Sample Number Catalog Number

1 P300046S0360

2 P300046S0360

3 P300046S0360

Analysis:

All three samples met the requirements of the test protocol.

Conclusions:

The Quadri*Sil Series 300 line post insulators manufactured with

tensile load test.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

The results of the test are contained in table 1.

Catalog Number STL (lbf) Sample Status

P300046S0360 33577 Crimp Slip

P300046S0360 40707 Crimp Slip

P300046S0360 41622 Crimp Sli

Table 1

All three samples met the requirements of the test protocol.

post insulators manufactured with Chance E-CR DD epoxy

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

Sample Status

Crimp Slip

Crimp Slip

Crimp Slip

CR DD epoxy rod passed the

Page 15: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 15 Test Requests:

0

5000

10000

15000

20000

25000

30000

0

Load

Pounds

Tested on 11-18-2011 TJW300,000 lb load calibrated 04-25-

0

5000

10000

15000

20000

25000

30000

35000

40000

0 30

Load

Pounds

Tested on 11-18-2011 TJW300,000 lb load cell calibrated 04

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Appendix:

30 60 90

TimeSeconds

M11-10-12 Sample 1 B Dual Eye Mounting

Load and Break

-2011

Max load - 33,578 Pounds

60 90 120 150

TimeSeconds

M11-10-12 Sample 2 Dual Eye Mounting

Load and Break

300,000 lb load cell calibrated 04-25-2011

Max load - 40,707 Pounds

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

180

Page 16: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 16 Test Requests:

0

5000

10000

15000

20000

25000

30000

35000

40000

0 30 60

Load

Pounds

Tested on 11-18-2011 TJW300,000 lb load calibrated 04-25-

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

90 120 150 180 210 240 270 300 330 360

TimeSeconds

M11-10-12 Sample 3 B Dual Eye Mounting

Load and Break

-2011

Max load - 41,623 Pounds

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

360 390

Page 17: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 17 Test Requests:

Housing Tracking and Erosion Test

Quadri*Sil

Introduction:

Two samples of Quadri*Sil Series 300 line post insulators, c

tested using the protocol described in ANSI C29.17, clause 7.3. The insulators were manufactured

with 1800-120V silicone rubber polymer,

epoxy fiberglass rod.

Test Protocol:

The test protocol of the standard follows:

7.3 Housing tracking and erosion tests

7.3.1 Test Specimen.

Two insulators or test specimens will be tested, in accordance with ANSI C29.11. . The specimen

length will be chosen such that the leakage

least two weathersheds.

If the same elastomeric materials and manufacturing method have been previously qualified, per

ANSI C29.11, this qualification section will not be repeated.

7.3.1.1 Test chamber.

The test is to be performed in a test apparatus as defined in ANSI C29.11.

7.3.1.2 Test Conditions.

The test is to be performed for a duration of 1000 hours as described in ANSI C29.11.

7.3.1.3 Evaluation.

No tracking is allowed. No weath

the core.

The IEC method regarding flashovers was adopted from standard 62217 as a modification.

If more than one flashover occurs at the initial NaCl content, the test shall be re

halved value of the NaCl content. The insulators are washed by tap water and the test re

within 8 h (interruption times shall not be counted as part of the test duration). This may be

repeated until interruptions no longer occur. The appl

be noted.

The numbers of flashovers and trip

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

Housing Tracking and Erosion Test

ANSI C29.17 – Clause 7.3

Quadri*Sil Series 300 Line Post Insulator

E12-02-18

Two samples of Quadri*Sil Series 300 line post insulators, catalog number P300008S0360, were

tested using the protocol described in ANSI C29.17, clause 7.3. The insulators were manufactured

120V silicone rubber polymer, Chemlok 608 coupling agent and Aiken manufactured

The test protocol of the standard follows:

Housing tracking and erosion tests

or test specimens will be tested, in accordance with ANSI C29.11. . The specimen

length will be chosen such that the leakage distance falls between 200 and 700 mm and includes at

If the same elastomeric materials and manufacturing method have been previously qualified, per

ANSI C29.11, this qualification section will not be repeated.

The test is to be performed in a test apparatus as defined in ANSI C29.11.

The test is to be performed for a duration of 1000 hours as described in ANSI C29.11.

No tracking is allowed. No weathershed punctures are allowed. Erosion is not allowed to reach

The IEC method regarding flashovers was adopted from standard 62217 as a modification.

If more than one flashover occurs at the initial NaCl content, the test shall be re-starte

halved value of the NaCl content. The insulators are washed by tap water and the test re

within 8 h (interruption times shall not be counted as part of the test duration). This may be

repeated until interruptions no longer occur. The application of any of the above measures shall

The numbers of flashovers and trip-outs shall be recorded and noted in the test report.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

atalog number P300008S0360, were

tested using the protocol described in ANSI C29.17, clause 7.3. The insulators were manufactured

coupling agent and Aiken manufactured

or test specimens will be tested, in accordance with ANSI C29.11. . The specimen

distance falls between 200 and 700 mm and includes at

If the same elastomeric materials and manufacturing method have been previously qualified, per

The test is to be performed for a duration of 1000 hours as described in ANSI C29.11.

ershed punctures are allowed. Erosion is not allowed to reach

The IEC method regarding flashovers was adopted from standard 62217 as a modification.

started at a

halved value of the NaCl content. The insulators are washed by tap water and the test re-started

within 8 h (interruption times shall not be counted as part of the test duration). This may be

ication of any of the above measures shall

outs shall be recorded and noted in the test report.

Page 18: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE May 29, 2012

PAGE: 18 Test Requests:

Test Data:

The samples evaluated would have been catalog number

that can be manufactured would include 20 weathersheds. These insulators only utilized

weathersheds and so had one end with a normal seal, with the opposite seal filled with RTV

end fitting.

The two sample insulators were mounted as prescribed i

on March 7th, 2012, and concluded on

A synopsis of the event log for the salt fog chamber is shown in table 1.

Date Stop Time

3/7/12

3/19/12

3/20/12

3/21/12

3/22/12

3/27/12

3/28/12

4/28/12 0700

A bus fault resulted in numerous trip

of the test.

Upon removal, each of the insulators was visually examined. There were no holes, tracki

erosion to the core.

Conclusion:

The Quadri*Sil Series 300 line post insulators (catalog number P300008S0360)

requirements of the protocol for ANSI C29.17, clause 7.3.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

May 29, 2012

Test Requests: R12-11-03 Report Number: R12

would have been catalog number P300008S0360. The smallest insulator

at can be manufactured would include 20 weathersheds. These insulators only utilized

weathersheds and so had one end with a normal seal, with the opposite seal filled with RTV

The two sample insulators were mounted as prescribed in the test protocol. The test was initiated

and concluded on April 28th, 2012. The applied voltage was 18.62

A synopsis of the event log for the salt fog chamber is shown in table 1.

Stop Time Start Time Timer hours

0 Start test

kV

0830 217 Power Outage

1000 228 Power Outage

1500 259 Power Outage

1300 264 Power Outage

0800 359 Power Outage

1245 368 Power Outage

1012

Table 2

A bus fault resulted in numerous trip-outs. There were no identified flashovers during the course

Upon removal, each of the insulators was visually examined. There were no holes, tracki

The Quadri*Sil Series 300 line post insulators (catalog number P300008S0360) met all of the

requirements of the protocol for ANSI C29.17, clause 7.3.

ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

The smallest insulator

at can be manufactured would include 20 weathersheds. These insulators only utilized 6

weathersheds and so had one end with a normal seal, with the opposite seal filled with RTV at the

n the test protocol. The test was initiated

, 2012. The applied voltage was 18.62 kV.

Remarks

Start test – 18.62

kV – 10 kg/m3

Power Outage

Power Outage

Power Outage

Power Outage

Power Outage

Power Outage

End of Test

outs. There were no identified flashovers during the course

Upon removal, each of the insulators was visually examined. There were no holes, tracking or

met all of the

Page 19: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T

DATE November 7, 2012

PAGE: 19 Test Requests:

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

November 7, 2012

Test Requests: R12-11-03 Report Number: R12

est Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

Page 20: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T

DATE November 7, 2012

PAGE: 20 Test Requests:

ANSI C29.17

Introduction:

Weathershed and shank sections were cut from an insulator molded by PNT using HPS silicone rubber

compound 1800-120V. The Aging or Weathering Test as outlined in ANSI C29.17

performed using the Fluorescent UV Method (ASTM G 53). The test was performed in QUV machines

using UVB-313 bulbs.

Details:

The test was performed on both stressed and unstressed samples of the polymer. Stressed samples were

placed in tension by bending them in half and positioning them in the machine so that the maximum UV

exposure occurred on the section under tensile stress. The daily exposure cycle was 16 hours of UV

exposure and 8 hours of condensation. The test protocol requires a min

without evidence of cracking or crazing.

Conclusions:

The samples were exposed for 1505 hours total time (1004 hours UV exposure). There were no indications

of degradation, cracking, fading, chalking or loss of hydrophobi

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

November 7, 2012

Test Requests: R12-11-03 Report Number: R12

ANSI C29.17 – Clause 7.3.2 – Aging or Weathering Test

Silicone Rubber 1800-120V

M05-04-07

Weathershed and shank sections were cut from an insulator molded by PNT using HPS silicone rubber

120V. The Aging or Weathering Test as outlined in ANSI C29.17 – clause 7.

performed using the Fluorescent UV Method (ASTM G 53). The test was performed in QUV machines

The test was performed on both stressed and unstressed samples of the polymer. Stressed samples were

n by bending them in half and positioning them in the machine so that the maximum UV

exposure occurred on the section under tensile stress. The daily exposure cycle was 16 hours of UV

exposure and 8 hours of condensation. The test protocol requires a minimum of 1000 hours exposure

without evidence of cracking or crazing.

The samples were exposed for 1505 hours total time (1004 hours UV exposure). There were no indications

of degradation, cracking, fading, chalking or loss of hydrophobicity.

est Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

Weathershed and shank sections were cut from an insulator molded by PNT using HPS silicone rubber

clause 7.3.2, was

performed using the Fluorescent UV Method (ASTM G 53). The test was performed in QUV machines

The test was performed on both stressed and unstressed samples of the polymer. Stressed samples were

n by bending them in half and positioning them in the machine so that the maximum UV

exposure occurred on the section under tensile stress. The daily exposure cycle was 16 hours of UV

imum of 1000 hours exposure

The samples were exposed for 1505 hours total time (1004 hours UV exposure). There were no indications

Page 21: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T

DATE November 7, 2012

PAGE: 21 Test Requests:

Quadri*Sil Series 300 Line Post Insulators

Introduction:

The dye penetration test was performed on

number P300046S0360. The insulators were manufactured with Chance Epoxy E

1800-120V silicone rubber and Chemlok 608 coupling agent.

Test Protocol:

The test was performed in accordance with ANSI C29.

7.4.1 Dye Penetration Test

Ten samples will be prepared and tested in accordance with ANSI C29.11. There will be

no dye solution penetration through the sample after fifteen minutes of exposure.

ANSI C29.11

7.4.1 Dye Penetration Test

7.4.1.1 Test specimens

Ten core samples shall be cut from an insulator. The length of the samples shall

be 10 mm ± 0.5 mm. They shall be cut nominally 90° to the axis of the core with

diamond

shall be smoothed with a 180

and approximately parallel

7.4.1.2 Test

The samples shall be placed on a layer of steel or glass balls in a vessel with the

fiber vertical. The balls shall be of the same dia

to 2 mm. The dye, composed of 1 gram of fuchsin in 100 grams of methanol, is

poured into the vessel until its level is 2 mm to 3 mm above the top of the balls.

7.4.1.3 Evaluation

The time for the dye to rise through the sampl

than 15 minutes.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

November 7, 2012

Test Requests: R12-11-03 Report Number: R12

Dye Penetration test

ANSI C29.17 - Clause 7.4.1

Quadri*Sil Series 300 Line Post Insulators

Catalog Number P300046S0360

M11-10-13

The dye penetration test was performed on samples of Quadri*Sil Series 300 line post insulators, catalog

number P300046S0360. The insulators were manufactured with Chance Epoxy E-CR DD fiberglass rod,

120V silicone rubber and Chemlok 608 coupling agent.

The test was performed in accordance with ANSI C29.17 clause 7.4.1

7.4.1 Dye Penetration Test

Ten samples will be prepared and tested in accordance with ANSI C29.11. There will be

no dye solution penetration through the sample after fifteen minutes of exposure.

7.4.1 Dye Penetration Test

.4.1.1 Test specimens

Ten core samples shall be cut from an insulator. The length of the samples shall

be 10 mm ± 0.5 mm. They shall be cut nominally 90° to the axis of the core with

diamond-coated circular saw blade under cool running water. The cut surfa

shall be smoothed with a 180-grit abrasive cloth. The cut ends shall be clean

and approximately parallel

The samples shall be placed on a layer of steel or glass balls in a vessel with the

fiber vertical. The balls shall be of the same diameter and in the range of 1 mm

to 2 mm. The dye, composed of 1 gram of fuchsin in 100 grams of methanol, is

poured into the vessel until its level is 2 mm to 3 mm above the top of the balls.

7.4.1.3 Evaluation

The time for the dye to rise through the samples by capillarity shall be more

than 15 minutes.

est Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

ine post insulators, catalog

CR DD fiberglass rod,

Ten samples will be prepared and tested in accordance with ANSI C29.11. There will be

no dye solution penetration through the sample after fifteen minutes of exposure.

Ten core samples shall be cut from an insulator. The length of the samples shall

be 10 mm ± 0.5 mm. They shall be cut nominally 90° to the axis of the core with

coated circular saw blade under cool running water. The cut surfaces

grit abrasive cloth. The cut ends shall be clean

The samples shall be placed on a layer of steel or glass balls in a vessel with the

meter and in the range of 1 mm

to 2 mm. The dye, composed of 1 gram of fuchsin in 100 grams of methanol, is

poured into the vessel until its level is 2 mm to 3 mm above the top of the balls.

es by capillarity shall be more

Page 22: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T

DATE November 7, 2012

PAGE: 22 Test Requests:

Test Results:

The characteristics of the samples and the results of the dye penetration test are contained in table 1.

Sample

1

2

3

4

5

6

7

8

9

10

Conclusion:

All of the samples of the 3” rod manufactured with the 1800

the test.

ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

November 7, 2012

Test Requests: R12-11-03 Report Number: R12

The characteristics of the samples and the results of the dye penetration test are contained in table 1.

Sample Length Time Pass/Fail

10.15 > 15 minutes P

10.30 > 15 minutes P

10.47 > 15 minutes P

10.45 > 15 minutes P

10.45 > 15 minutes P

10.48 > 15 minutes P

10.42 > 15 minutes P

9.98 > 15 minutes P

10.48 > 15 minutes P

10.50 > 15 minutes P

Table 3

es of the 3” rod manufactured with the 1800-120V silicone rubber met the requirements of

est Report; Quadri*Sil Series 300 Line Post Insulators

R12-11-03

The characteristics of the samples and the results of the dye penetration test are contained in table 1.

120V silicone rubber met the requirements of

Page 23: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE: November 7, 2012

PAGE 23 Test Requests: R12-11-03 Report Number: R12-11-03

Page 24: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE: November 7, 2012

PAGE 24 Test Requests: R12-11-03 Report Number: R12-11-03

ANSI C29.17 - Clause 7.4.2

Water Diffusion Test

P300046S0360 Series 300 Quadri*Sil

Introduction:

The water diffusion test was performed on samples cut from a P300046S0360 Series 300 Quadri*Sil line

post. The insulator was manufactured with Chance epoxy fiberglass rod with E-CR DD glass fibers,

Chemlok 608 coupling agent and 1800-120V silicone rubber polymer housings.

Test Protocol:

The test was performed in accordance with ANSI C29.17 clause 7.4.2

7.4.2 Water diffusion test

Six samples will be prepared in accordance with ANSI C29.11. The electrodes will be

modified to provide total coverage of the cross sectional area, which insures puncture of

the rod sample. The test arrangement is shown in figure 1. No puncture or surface

flashover is allowed. The current during the test shall not exceed 1-mA, rms.

Test Results:

Samples were cut and prepared as prescribed in ANSI C29.11. Boiling was initiated on October 23rd, 2011,

at 10:45 a.m. and ended on October 27th, 2011, at 2:50 p.m. The samples were removed from the vessel

and subjected to the electrical test. The data is contained in table 1.

Sample

No.

Length

(mm)

Voltage

(kV)

Current

(µA –

peak)

Time

(minutes)

Results Comments

1 29.95 12.1 220 1 Pass

2 30.10 12.1 220 1 Pass

3 30.48 12.1 220 1 Pass

4 30.45 12.2 220 1 Pass

5 29.65 12.1 220 1 Pass

6 30.42 12.0 220 1 Pass

Table 4

Conclusion

All of the samples of the Series 300 Quadri*Sil line post insulator met the requirements of the test protocol.

Page 25: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE: November 7, 2012

PAGE 25 Test Requests: R12-11-03 Report Number: R12-11-03

ANSI C29.17 – Clause 7.5

Flammability Tests

Silicone Rubber 1800-120V Rubber Compound

R.K. Niedermier

October 26, 2001

Page 26: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE: November 7, 2012

PAGE 26 Test Requests: R12-11-03 Report Number: R12-11-03

I. INTRODUCTION

This report describes the results of flammability tests on OB polymer compound

1800-120V. This rubber compound is used for the injection molding of insulators

manufactured by The Ohio Brass Company.

The tests were conducted in accordance with IEC Publication 707, “Methods of

test for the determination of flammability of solid electrical insulating materials

when exposed to an igniting source.”

The specific tests employed were IEC Method FV: Flame – Vertical specimen.

II. RESULTS

Method FV:

The igniting source and test units are defined in paragraphs 9.1 and 9.2 of the

referenced publication.

Procedure:

“Each specimen is to be fixed vertically by the clamp on the ring stand. The

burner is placed remote from the specimen, ignited and adjusted in the vertical

position to produce a blue flame 20+-2 mm high. The flame is obtained by

adjusting the gas supply and the air ports of the burner until a 20+-2 mm yellow

tipped blue flame is produced and then the air supply is increased until the yellow

tip disappears. The height of the flame is measured again and corrected in

necessary.

The burner is to be placed centrally under the lower end of the test specimen and

allowed to remain for 10 s. The burner is then to be withdrawn at least 150 mm

away and the duration of flaming of the specimen noted. When flaming of the

specimen ceases, the burner is to be immediately placed again under the

specimen. After 10 s the burner is again to be withdrawn and the duration of

flaming and glowing to be noted.

If the specimen drips molten or flaming material during either of the flame

applications, the burner may be tilted to an angle up to 45 degrees and also

slightly withdrawn away from one of the 13 mm sides of the specimen during the

flame application, to avoid material dripping into the tube of the burner.

If the specimen drips molten or flaming material or is consumed during the test,

the burner is to be hand-held, and the 10 mm distance between the bottom of the

specimen and the top of the burner tube is to be maintained during the flame

application. Any molten strings of the material are to be ignored and the flame is

to be applied to the major portion of the specimen.”

Page 27: ANSI C29.17 Prototype Test Report - hubbellcdn · ENGINEERING REPORT SUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators DATE May 29, 2012 PAGE:

ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators

DATE: November 7, 2012

PAGE 27 Test Requests: R12-11-03 Report Number: R12-11-03

Evaluation:

1800-120V is classified as Category FV 0 material based on the following test

results:

Flaming Combustion Time (s)

First flame Second flame

Sample Application Application

1 0 0

2 0 0

3 0 0

4 0 0

5 0 0

6 0 0

7 0 0

8 0 0

As shown, the total flaming combustion time for the sixteen flame applications to

the set of eight specimens was 0 seconds.