ansi c29.17 prototype test report - hubbellcdn · engineering report subject ansi c29.17 prototype...
TRANSCRIPT
ANSI C29.17 Prototype Quadri*Sil 300 Line Post
Report Number:
Section Prototype Tests I. Tests on Interfaces and Connections of End Fittings
II. Core Load - Time Test III. Tensile Load Test
IV. Housing Tracking and Erosion Tests
V. Aging or Weathering Test
VI. Dye Penetration Test VII. Water Diffusion Test
VIII. Flammability Tests
C29.17 Prototype Test Report
Quadri*Sil 300 Line Post InsulatorsReport Number: R12-11-03
Table of Contents
ANSI Clause
Tests on Interfaces and Connections of End Fittings 7.1
Time Test 7.2.1
7.2.2
g and Erosion Tests 7.3.1
athering Test 7.3.2
ation Test 7.4.1
usion Test 7.4.2
7.5
Design Test Report EU
Test Report nsulators
Page
3
11
13
17
20
21
24
25
Design Test Report EU-1603
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 2 Test Requests:
Introduction:
Sample insulators were evaluated according to the protocols established within ANSI C29.1
tested varied in length to match the requirements of the standard. The polymer weathersheds were
composed of 1800-120V silicone rubber. The coupling agent employed between the fiberglass rod and the
polymer was Chemlok 608. The fiberglass
(Electrical grade – Corrosion Resistant Direct Draw) glass fibers and pultruded in the Centralia, Missouri
or Aiken, South Carolina facility.
Details:
A summary of the tests performed and their
Test Name
Tests on interfaces and connection of end fittings
Core time-load test
Tensile load test
Housing tracking and erosion tests
Aging or weathering test
Dye penetration test
Water diffusion test
Flammability test
Discussion:
All of the tests were successfully completed.
Conclusions:
The Quadri*Sil Series 300 line post met all of the requirements of the ANSI C29.17 prototype tests.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Prototype Testing
ANSI C29.17
Quadri*Sil Series 300 Line Posts
Sample insulators were evaluated according to the protocols established within ANSI C29.17
tested varied in length to match the requirements of the standard. The polymer weathersheds were
120V silicone rubber. The coupling agent employed between the fiberglass rod and the
polymer was Chemlok 608. The fiberglass rod was an HPS epoxy resin system reinforced with E
Corrosion Resistant Direct Draw) glass fibers and pultruded in the Centralia, Missouri
A summary of the tests performed and their results is contained in table 1.
Standard/Clause Request Number
Tests on interfaces and connection of end fittings ANSI C29.17/7.1 E11
ANSI C29.17/7.2.1 M12
ANSI C29.17/7.2.2 M11
ANSI C29.17/7.3.1 E12
ANSI C29.17/7.3.2 M05
ANSI C29.17/7.4.1 M11
ANSI C29.17/7.4.2 E11
ANSI C29.17/7.5 R02
Table 1
All of the tests were successfully completed.
The Quadri*Sil Series 300 line post met all of the requirements of the ANSI C29.17 prototype tests.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
7. The samples
tested varied in length to match the requirements of the standard. The polymer weathersheds were
120V silicone rubber. The coupling agent employed between the fiberglass rod and the
rod was an HPS epoxy resin system reinforced with E-CR DD
Corrosion Resistant Direct Draw) glass fibers and pultruded in the Centralia, Missouri
Request Number
E11-10-19
M12-10-05
M11-10-12
E12-02-18
M05-04-07
M11-10-13
E11-10-18
R02-11-02
The Quadri*Sil Series 300 line post met all of the requirements of the ANSI C29.17 prototype tests.
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 3 Test Requests:
Tests on Interf
Introduction:
The tests on interfaces and connections of end fittings were performed on samples of Quadri*Sil Series
300 line posts. The procedure emp
of the test was performed at PowerTech Labs. The insulators tested were catalog number P300046S0040.
The samples were manufactured with 1800
and Chemlok 608 coupling agent.
Test Protocol:
The insulators were subjected to the test protocol that follows.
7.1 Tests on interfaces and connection of end fittings
7.1.1 Test specimens
Four insulators, representative of the production pro
shall be reserved as a reference for the power frequency voltage test in 7.1.3.3. The insulator length
(metal-to-metal) will be at least 15 times the core diameter. If shorter insulators are tested, the
results are valid only for insulators up to the length tested.
The insulators shall be subjected to the routine mechanical test, per section 10.
7.1.2 Pre-stressing
The following tests (7.1.2.1, 7.1.2.2) shall be carried out on three test insulators in the s
indicated below.
7.1.2.1 Thermal-mechanical test
The three insulators will be loaded in cantilever and subjected to the temperature cycle described
in Figure 2. The load shall be selected so as to produce the same bending moment at the base of
the insulator as is exerted by 50% of the SCL in normal application.
Each 24 hour cycle has a minimum of 8 hours at both +50ºC and
shall be run twice, with the direction of the load reversed after the first cycle.
The test may be interrupted for the load direction reversal and for maintenance of the test
equipment for a total duration of 2 hours.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
ANSI C29.17 - Clause 7.1
Tests on Interfaces and Connections of End Fittings
Quadri*Sil Series 300 Post
Catalog Number P300046S0040
E11-10-19
The tests on interfaces and connections of end fittings were performed on samples of Quadri*Sil Series
300 line posts. The procedure employed was as defined by ANSI C29.17. The thermal-mechanical portion
of the test was performed at PowerTech Labs. The insulators tested were catalog number P300046S0040.
The samples were manufactured with 1800-120V silicone rubber, Chance epoxy E-CR DD fiberglass rod
The insulators were subjected to the test protocol that follows.
Tests on interfaces and connection of end fittings
Four insulators, representative of the production process and design, shall be selected. One of these
shall be reserved as a reference for the power frequency voltage test in 7.1.3.3. The insulator length
metal) will be at least 15 times the core diameter. If shorter insulators are tested, the
sults are valid only for insulators up to the length tested.
The insulators shall be subjected to the routine mechanical test, per section 10.
The following tests (7.1.2.1, 7.1.2.2) shall be carried out on three test insulators in the s
mechanical test
The three insulators will be loaded in cantilever and subjected to the temperature cycle described
in Figure 2. The load shall be selected so as to produce the same bending moment at the base of
sulator as is exerted by 50% of the SCL in normal application.
Each 24 hour cycle has a minimum of 8 hours at both +50ºC and -35ºC ±5K. The 24 hour cycle
shall be run twice, with the direction of the load reversed after the first cycle.
interrupted for the load direction reversal and for maintenance of the test
equipment for a total duration of 2 hours.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
The tests on interfaces and connections of end fittings were performed on samples of Quadri*Sil Series
mechanical portion
of the test was performed at PowerTech Labs. The insulators tested were catalog number P300046S0040.
fiberglass rod
cess and design, shall be selected. One of these
shall be reserved as a reference for the power frequency voltage test in 7.1.3.3. The insulator length
metal) will be at least 15 times the core diameter. If shorter insulators are tested, the
The following tests (7.1.2.1, 7.1.2.2) shall be carried out on three test insulators in the sequence
The three insulators will be loaded in cantilever and subjected to the temperature cycle described
in Figure 2. The load shall be selected so as to produce the same bending moment at the base of
35ºC ±5K. The 24 hour cycle
interrupted for the load direction reversal and for maintenance of the test
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 4 Test Requests:
7.1.2.2 Water immersion test
The three test insulators will be immersed in boiling water for 42 continuous hours (de
water with 0.1% NaCl or tap water adjusted to a conductivity of 1650 µS/cm ±50 µS/cm at 20º C
25ºC). After the 42 hour boiling period, the insulators will remain in the vessel until the water
cools to approximately 50ºC. This temperature will be maintained until the
started.
7.1.3 Verification tests
The following verification tests (7.1.3.1, 7.1.3.2, 7.1.3.3) shall be completed within 48 hours
following the removal of the insulators from the water.
7.1.3.1 Visual examination
The housing shall be inspec
are permitted.
7.1.3.2 Steep-front impulse test
The three test specimens will be fitted with a sharp edged electrode, consisting of a clip made of
copper strip approximately 20mm wide and le
firmly on the housing or sheath between the weathersheds, forming two sections of 500 mm or
smaller axial length. If the test specimens have an insulating length that is less than or equal to
500mm, the voltage will be applied between the end fittings (no clip is necessary).
An impulse voltage with a steepness of at least 1000 kV/µs will be applied to each test section.
Each section will be stressed with 25 impulses of positive polarity and 25 impulses of
polarity. Each impulse shall cause an external flashover of the test section. No punctures of any
part of the insulator shall occur.
The electrodes used to form the test sections will be removed prior to the power frequency voltage
test.
7.1.3.3 Power frequency voltage test
The dry power frequency flashover voltage will be determined by averaging five flashover
voltages on each insulator per ANSI/IEEE 4. The flashover voltage will be reached within 1
minutes by increasing the voltage linearly fro
insulator will be determined using the same procedure.
The average flashover voltage for each test insulator will be at least 90% of the flashover voltage
of the reference insulator.
The three test insulators and the reference insulator will be allowed to reach thermal equilibrium
with the surrounding atmosphere. All four insulator will then be subjected to 80% of the reference
insulator flashover voltage for 30 minutes. No puncture of any part of the in
and the temperature of the shank (measured immediately after the test) will not be more than 20ºC
above the ambient temperature.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Water immersion test
The three test insulators will be immersed in boiling water for 42 continuous hours (de
% NaCl or tap water adjusted to a conductivity of 1650 µS/cm ±50 µS/cm at 20º C
25ºC). After the 42 hour boiling period, the insulators will remain in the vessel until the water
cools to approximately 50ºC. This temperature will be maintained until the verification tests are
The following verification tests (7.1.3.1, 7.1.3.2, 7.1.3.3) shall be completed within 48 hours
following the removal of the insulators from the water.
Visual examination
The housing shall be inspected visually. No cracks or crazing of the elastomeric shed or housing
front impulse test
The three test specimens will be fitted with a sharp edged electrode, consisting of a clip made of
copper strip approximately 20mm wide and less than 1mm in thickness. The electrode will
firmly on the housing or sheath between the weathersheds, forming two sections of 500 mm or
smaller axial length. If the test specimens have an insulating length that is less than or equal to
tage will be applied between the end fittings (no clip is necessary).
An impulse voltage with a steepness of at least 1000 kV/µs will be applied to each test section.
Each section will be stressed with 25 impulses of positive polarity and 25 impulses of
polarity. Each impulse shall cause an external flashover of the test section. No punctures of any
part of the insulator shall occur.
The electrodes used to form the test sections will be removed prior to the power frequency voltage
ower frequency voltage test
The dry power frequency flashover voltage will be determined by averaging five flashover
voltages on each insulator per ANSI/IEEE 4. The flashover voltage will be reached within 1
minutes by increasing the voltage linearly from zero. The flashover voltage of the reference
insulator will be determined using the same procedure.
The average flashover voltage for each test insulator will be at least 90% of the flashover voltage
of the reference insulator.
tors and the reference insulator will be allowed to reach thermal equilibrium
with the surrounding atmosphere. All four insulator will then be subjected to 80% of the reference
insulator flashover voltage for 30 minutes. No puncture of any part of the insulator shall occur,
and the temperature of the shank (measured immediately after the test) will not be more than 20ºC
above the ambient temperature.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
The three test insulators will be immersed in boiling water for 42 continuous hours (de-ionized
% NaCl or tap water adjusted to a conductivity of 1650 µS/cm ±50 µS/cm at 20º C -
25ºC). After the 42 hour boiling period, the insulators will remain in the vessel until the water
verification tests are
The following verification tests (7.1.3.1, 7.1.3.2, 7.1.3.3) shall be completed within 48 hours
ted visually. No cracks or crazing of the elastomeric shed or housing
The three test specimens will be fitted with a sharp edged electrode, consisting of a clip made of
ss than 1mm in thickness. The electrode will be
firmly on the housing or sheath between the weathersheds, forming two sections of 500 mm or
smaller axial length. If the test specimens have an insulating length that is less than or equal to
An impulse voltage with a steepness of at least 1000 kV/µs will be applied to each test section.
Each section will be stressed with 25 impulses of positive polarity and 25 impulses of negative
polarity. Each impulse shall cause an external flashover of the test section. No punctures of any
The electrodes used to form the test sections will be removed prior to the power frequency voltage
The dry power frequency flashover voltage will be determined by averaging five flashover
voltages on each insulator per ANSI/IEEE 4. The flashover voltage will be reached within 1
m zero. The flashover voltage of the reference
The average flashover voltage for each test insulator will be at least 90% of the flashover voltage
tors and the reference insulator will be allowed to reach thermal equilibrium
with the surrounding atmosphere. All four insulator will then be subjected to 80% of the reference
sulator shall occur,
and the temperature of the shank (measured immediately after the test) will not be more than 20ºC
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 5 Test Requests:
Test Results:
Clause 7.1.1 – Test specimens:
The samples evaluated were catalog number P300046S0040 w
of the sales drawing is included as figure 1.
Clause 7.1.2.1 – Thermal-
The thermal-mechanical portion of the test was performed at
load profile is shown as figure 2.
PowerTech’s report stated, “No breakage of the end fittings or visible deformation or pullout of
the core rod occurred.”
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Test specimens:
The samples evaluated were catalog number P300046S0040 with an S.C.L. of 5400 lbf. A copy
of the sales drawing is included as figure 1.
Figure 1
-mechanical Test:
mechanical portion of the test was performed at PowerTech Labs. A typical thermal
load profile is shown as figure 2.
PowerTech’s report stated, “No breakage of the end fittings or visible deformation or pullout of
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
ith an S.C.L. of 5400 lbf. A copy
PowerTech Labs. A typical thermal-
PowerTech’s report stated, “No breakage of the end fittings or visible deformation or pullout of
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 6 Test Requests:
Clause 7.1.2.2 – Water Immersion Test:
The samples were immersed in boiling water in accordance with the standard.
Clause 7.1.3.1 – Visual examination:
Each of the insulators was examined. No cracks were found.
Clause 7.1.3.2 – Steep-front impulse voltage test:
Each of the insulators was subjected to a steep
insulators into sections shorter than 500 mm. All flashovers were external. The data is contained
in tables 1 2and 3.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Water Immersion Test:
mersed in boiling water in accordance with the standard.
Figure 2
Visual examination:
Each of the insulators was examined. No cracks were found.
front impulse voltage test:
of the insulators was subjected to a steep-front impulse voltage by sub-dividing the
insulators into sections shorter than 500 mm. All flashovers were external. The data is contained
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
dividing the
insulators into sections shorter than 500 mm. All flashovers were external. The data is contained
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 7 Test Requests:
Sample
Line 9 sheds
End/Pol. Top/+ Top/-
1 399 368
2 396 366
3 399 366
4 394 366
5 394 368
6 394 368
7 394 366
8 394 366
9 394 366
10 396 368
11 394 366
12 394 366
13 391 366
14 394 366
15 391 366
16 396 366
17 396 366
18 394 368
19 391 366
20 399 366
21 391 366
22 391 366
23 394 368
24 391 366
25 394 366
Pass Pass
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Table 1
Sample #1
Line Mid 10 sheds Ground Mid 10 sheds Ground 9 sheds
- Mid/+ Mid/- Mid/+ Mid/- Grd./+
368 362 370 401 370 384
366 362 373 404 370 384
366 362 375 401 370 387
366 365 373 404 368 384
368 362 373 404 368 387
368 362 373 404 368 387
366 365 373 404 370 384
366 362 373 404 368 387
366 365 373 401 368 387
368 360 373 404 368 387
366 362 370 404 370 387
366 362 373 408 370 387
366 365 373 404 368 387
366 365 373 405 370 381
366 365 370 401 366 384
366 365 373 404 370 384
366 362 375 401 368 384
368 365 373 404 370 384
366 365 373 399 370 384
366 362 370 401 368 384
366 362 370 404 370 384
366 362 373 404 368 384
368 362 373 404 370 384
366 365 370 404 368 384
366 365 370 408 370 384
Pass Pass Pass Pass Pass Pass
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
Ground 9 sheds
Grd./-
368
368
361
370
370
370
370
370
370
370
370
370
370
368
370
370
370
368
370
370
370
366
368
370
370
Pass
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 8 Test Requests:
Sample
Line 9 sheds
End/Pol. Top/+ Top/-
1 394 375
2 399 375
3 391 370
4 391 370
5 394 373
6 391 373
7 399 370
8 391 373
9 394 373
10 394 373
11 391 370
12 394 373
13 394 370
14 391 370
15 394 370
16 391 373
17 396 370
18 394 370
19 394 370
20 394 370
21 396 375
22 394 370
23 394 370
24 394 370
25 394 370
Pass Pass
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Table 2
Sample #2 Line Mid 10 sheds Ground Mid 10 sheds Ground 9 sheds
- Mid/+ Mid/- Mid/+ Mid/- Grd./+
375 401 366 396 368 384
375 404 370 399 368 387
370 405 370 396 368 384
370 404 370 399 366 381
373 410 368 399 370 387
373 405 370 396 370 387
370 404 366 399 370 384
373 401 370 399 366 387
373 404 368 401 368 384
373 404 370 399 370 381
370 404 373 401 368 384
373 408 370 401 368 384
370 401 370 399 370 384
370 408 373 399 368 384
370 401 370 399 370 384
373 399 370 399 368 384
370 401 370 401 370 384
370 404 370 399 370 384
370 404 370 399 368 381
370 404 368 399 368 384
375 404 370 399 368 381
370 404 368 399 368 384
370 404 368 399 370 384
370 404 366 399 368 384
370 404 368 399 370 387
Pass Pass Pass Pass Pass Pass
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
Ground 9 sheds
Grd./-
370
373
373
375
373
375
375
373
375
373
370
370
373
373
370
370
370
373
370
373
370
370
370
370
370
Pass
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 9 Test Requests:
Clause 7.1.3.3 – Dry power frequency voltage test:
The 3 sample insulators were tested for dry flas
was performed. Data is contained in tables 4 and 5. All corrections are in accordance with ANSI
C29.1
Reference
Bar (cmHg) 73.4
Temp dry (ºC) 23.05
Rel. Hum. 17.7
Sample
Line 9 sheds
End/Pol. Top/+ Top/-
1 391 375
2 391 375
3 391 373
4 390 373
5 396 373
6 391 375
7 394 375
8 394 373
9 394 370
10 394 373
11 391 373
12 396 373
13 394 373
14 391 373
15 391 373
16 391 373
17 394 373
18 394 373
19 391 375
20 391 373
21 394 370
22 394 373
23 394 375
24 394 373
25 391 373
Pass Pass
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Table 3
Dry power frequency voltage test:
The 3 sample insulators were tested for dry flashover values and a 30-minute, 80% withstand test
was performed. Data is contained in tables 4 and 5. All corrections are in accordance with ANSI
Reference Unit 1 Unit 2 Unit 3
73.4 73.4 73.4
23.05 23.5 23.5 23.0
17.6 17.3 17.7
Table 4
Sample #3 Line Mid 10 sheds Ground Mid 10 sheds Ground 9 sheds
- Mid/+ Mid/- Mid/+ Mid/- Grd./+
375 401 375 399 370 384
375 401 378 401 370 389
373 405 378 404 370 391
373 404 378 404 370 391
373 404 375 401 370 391
375 405 375 404 370 391
375 404 373 408 370 391
373 408 373 404 370 391
370 404 370 401 370 390
373 408 375 404 370 387
373 405 375 404 370 387
373 404 375 401 370 387
373 401 378 404 380 391
373 404 375 404 302 391
373 401 375 401 382 391
373 401 375 404 382 391
373 401 375 401 382 390
373 401 375 404 382 390
375 404 375 404 382 390
373 405 375 405 382 391
370 401 375 405 382 391
373 405 375 405 382 391
375 399 375 401 382 390
373 404 378 401 382 391
373 401 370 401 380 391
Pass Pass Pass Pass Pass Pass
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
minute, 80% withstand test
was performed. Data is contained in tables 4 and 5. All corrections are in accordance with ANSI
Ground 9 sheds
Grd./-
378
380
380
380
382
382
382
382
382
382
382
380
382
380
382
380
382
380
380
380
378
382
378
380
378
Pass
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 10 Test Requests:
Corrected Flashovers
Flashover No. Reference
1 491
2 491
3 485
4 497
5 504
6 504
7 479
8 491
9 479
10 479
Average
Flashover 490
30 Minute Withstand Test
Start Withstand
End Withstand
Temperature Differential
Differential from Ambient
Conclusions:
The samples of the Quadri*Sil Series 300 Line Post insulators manufactured with Chance Epoxy Series 300
E-CR DD rod and 1800-120V silicone rubber met all of the requirements of the test proto
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Reference Unit 1 Unit 2 Unit 3
491 498 497
479 480 497
473 498 497
461 498 491
479 498 497
473 498 497
479 480 497
461 504 491
473 480 479
473 480 497
474 491 494
30 Minute Withstand Test
kV ºC kV ºC kV ºC
392 18.7 392 17.5 392 17.5
392 21.8 392 23 392 21.7
Temperature Differential 3.1 5.5 4.2
ential from Ambient -1.7 -.5 -1.3
Table 5
The samples of the Quadri*Sil Series 300 Line Post insulators manufactured with Chance Epoxy Series 300
120V silicone rubber met all of the requirements of the test protocol.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
The samples of the Quadri*Sil Series 300 Line Post insulators manufactured with Chance Epoxy Series 300
col.
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 11 Test Requests:
Introduction:
Three samples of Quadri*Sil, series 300 line post, catalog number P300053S0020 were used for the
performance of the core time-load test in accordance wit
manufactured without polymer on the core rod and employed Epoxy E
in Aiken.
Test Protocol:
The testing was performed in accordance with the following protocol.
7.2.1 Core time-load test
7.2.1.1 Test specimens
Three insulators manufactured on the production line using the standard end fittings shall be
selected. The section length (pole face to line attachment) shall be between 15 and 24 times the
diameter of the core, or the lon
7.2.1.2 Core time load test
Each insulator shall be gradually loaded to 40% of the SCL or the manufacturer’s RCL (whichever is
greater) at a temperature of 20ºC ± 10 K. The load shall be applied to the insulat
position, approximately perpendicular to the intended orientation of the conductor and
approximately perpendicular to the core of the insulator. The load shall be maintained for at least
96 hours.
7.2.1.3 Evaluation
7.2.1.3.1 Visual examination
After removal of the load, visually inspect the base end fitting for cracks or permanent
deformation. All threaded connections must be intact and usable.
7.2.1.3.2 Dissection and dye penetration
Cut each insulator 90º to the axis
the base end fitting longitudinally into two halves in the plane of the previously applied cantilever
load. The cut surfaces shall be smoothed by means of fine abrasive cloth (grain size 180
The cut halves shall be visually inspected for cracks and delamination. The presence of cracks or
delamination in the fiberglass rod shall constitute failure.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Core Time-Load Test
ANSI C29.17 – Clause 7.2.1
Catalog Number P300047S0040
Three samples of Quadri*Sil, series 300 line post, catalog number P300053S0020 were used for the
load test in accordance with ANSI C29.17, clause 7.2.1. The insulators were
manufactured without polymer on the core rod and employed Epoxy E-CR DD fiberglass rod manufactured
testing was performed in accordance with the following protocol.
Three insulators manufactured on the production line using the standard end fittings shall be
selected. The section length (pole face to line attachment) shall be between 15 and 24 times the
diameter of the core, or the longest length to be manufactured, whichever is less.
Each insulator shall be gradually loaded to 40% of the SCL or the manufacturer’s RCL (whichever is
greater) at a temperature of 20ºC ± 10 K. The load shall be applied to the insulator at the conductor
position, approximately perpendicular to the intended orientation of the conductor and
approximately perpendicular to the core of the insulator. The load shall be maintained for at least
mination
After removal of the load, visually inspect the base end fitting for cracks or permanent
deformation. All threaded connections must be intact and usable.
7.2.1.3.2 Dissection and dye penetration
Cut each insulator 90º to the axis of the core and about 50 mm from the base end fitting, then cut
the base end fitting longitudinally into two halves in the plane of the previously applied cantilever
load. The cut surfaces shall be smoothed by means of fine abrasive cloth (grain size 180
The cut halves shall be visually inspected for cracks and delamination. The presence of cracks or
delamination in the fiberglass rod shall constitute failure.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
Three samples of Quadri*Sil, series 300 line post, catalog number P300053S0020 were used for the
h ANSI C29.17, clause 7.2.1. The insulators were
CR DD fiberglass rod manufactured
Three insulators manufactured on the production line using the standard end fittings shall be
selected. The section length (pole face to line attachment) shall be between 15 and 24 times the
Each insulator shall be gradually loaded to 40% of the SCL or the manufacturer’s RCL (whichever is
or at the conductor
position, approximately perpendicular to the intended orientation of the conductor and
approximately perpendicular to the core of the insulator. The load shall be maintained for at least
After removal of the load, visually inspect the base end fitting for cracks or permanent
of the core and about 50 mm from the base end fitting, then cut
the base end fitting longitudinally into two halves in the plane of the previously applied cantilever
load. The cut surfaces shall be smoothed by means of fine abrasive cloth (grain size 180).
The cut halves shall be visually inspected for cracks and delamination. The presence of cracks or
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 12 Test Requests:
A dye penetration test shall be performed on the cut surfaces in accordance with ISO 34
reveal cracks. The presence of cracks or delamination in the fiberglass rod shall constitute
failure.
Test Results:
The first two insulators were loaded in opposition to one another. A load cell was included in the
connecting link. The third sample was loaded against a reference insulator for which the data was not
included.
Sample No. Catalog No.
1R & 1L P300053S0020
1R & 1L P300053S0020
3R P300053S0020
3R P300053S0020
No failures occurred during the period of applied load. An examination of the bases and associated
hardware for each of the insulators found no damage.
The dye penetration test was performed on each of the samples. No dye penetration was found.
Conclusions:
The sample Quadri*Sil, series 300 line post insulators met the requirements of the test.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
A dye penetration test shall be performed on the cut surfaces in accordance with ISO 34
reveal cracks. The presence of cracks or delamination in the fiberglass rod shall constitute
The first two insulators were loaded in opposition to one another. A load cell was included in the
sample was loaded against a reference insulator for which the data was not
Date Time Load, lb
10/8/12 1200 2360
10/12/12 1200 2360
10/18/12 1130 2360
10/22/12 1130 2360
No failures occurred during the period of applied load. An examination of the bases and associated
for each of the insulators found no damage.
The dye penetration test was performed on each of the samples. No dye penetration was found.
The sample Quadri*Sil, series 300 line post insulators met the requirements of the test.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
A dye penetration test shall be performed on the cut surfaces in accordance with ISO 3452 to
reveal cracks. The presence of cracks or delamination in the fiberglass rod shall constitute
The first two insulators were loaded in opposition to one another. A load cell was included in the
sample was loaded against a reference insulator for which the data was not
Comments
Start of Test
End of Test
Start of Test
End of Test
No failures occurred during the period of applied load. An examination of the bases and associated
The dye penetration test was performed on each of the samples. No dye penetration was found.
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 13 Test Requests:
Introduction:
The tensile load test was performed on samples of Quadri*Sil Series 300 line posts, catalog number
P300046S0360. These insulators were manufactured with Chance Ep
nominal diameter), 1800-120V silicone rubber and Chemlok 608 coupling agent. The test was performed in
accordance with ANSI C29.17, clause 7.2.2.
Test Protocol:
The test protocol is listed below.
7.2.2 Specified tensile load test
7.2.2.1 Test specimens
Three insulators manufactured on the production line using the standard end fittings shall be
selected.
7.2.2.2 Test procedures
A tensile load shall be applied to each insulator in line with the axis of the core of t
load shall be increased rapidly but smoothly from zero to 75% of the Specified Tensile Load (S.T.L.)
and shall then gradually increased in a time between 30 and 90 seconds until the STL is reached. If
the S.T.L. is reached in less than
90 seconds. At the conclusion of 90s, the load shall be removed.
7.2.2.3 Test evaluation
The test shall be regarded as passed if there is no evidence of:
• Pull out of the core from the end
• Breakage of the end fitting
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Tensile Load Test
ANSI C29.17 – Clause 7.2.2
Catalog Number P300046S0360
The tensile load test was performed on samples of Quadri*Sil Series 300 line posts, catalog number
These insulators were manufactured with Chance Epoxy E-CR DD fiberglass rod (3”
120V silicone rubber and Chemlok 608 coupling agent. The test was performed in
accordance with ANSI C29.17, clause 7.2.2.
load test
Three insulators manufactured on the production line using the standard end fittings shall be
A tensile load shall be applied to each insulator in line with the axis of the core of the insulator. The
load shall be increased rapidly but smoothly from zero to 75% of the Specified Tensile Load (S.T.L.)
and shall then gradually increased in a time between 30 and 90 seconds until the STL is reached. If
the S.T.L. is reached in less than 90 seconds, the load shall be maintained for the remainder of the
90 seconds. At the conclusion of 90s, the load shall be removed.
The test shall be regarded as passed if there is no evidence of:
Pull out of the core from the end fitting
Breakage of the end fitting
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
The tensile load test was performed on samples of Quadri*Sil Series 300 line posts, catalog number
CR DD fiberglass rod (3”
120V silicone rubber and Chemlok 608 coupling agent. The test was performed in
Three insulators manufactured on the production line using the standard end fittings shall be
he insulator. The
load shall be increased rapidly but smoothly from zero to 75% of the Specified Tensile Load (S.T.L.)
and shall then gradually increased in a time between 30 and 90 seconds until the STL is reached. If
90 seconds, the load shall be maintained for the remainder of the
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 14 Test Requests:
Test Results:
The results of the test are contained in table 1.
Sample Number Catalog Number
1 P300046S0360
2 P300046S0360
3 P300046S0360
Analysis:
All three samples met the requirements of the test protocol.
Conclusions:
The Quadri*Sil Series 300 line post insulators manufactured with
tensile load test.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
The results of the test are contained in table 1.
Catalog Number STL (lbf) Sample Status
P300046S0360 33577 Crimp Slip
P300046S0360 40707 Crimp Slip
P300046S0360 41622 Crimp Sli
Table 1
All three samples met the requirements of the test protocol.
post insulators manufactured with Chance E-CR DD epoxy
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
Sample Status
Crimp Slip
Crimp Slip
Crimp Slip
CR DD epoxy rod passed the
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 15 Test Requests:
0
5000
10000
15000
20000
25000
30000
0
Load
Pounds
Tested on 11-18-2011 TJW300,000 lb load calibrated 04-25-
0
5000
10000
15000
20000
25000
30000
35000
40000
0 30
Load
Pounds
Tested on 11-18-2011 TJW300,000 lb load cell calibrated 04
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Appendix:
30 60 90
TimeSeconds
M11-10-12 Sample 1 B Dual Eye Mounting
Load and Break
-2011
Max load - 33,578 Pounds
60 90 120 150
TimeSeconds
M11-10-12 Sample 2 Dual Eye Mounting
Load and Break
300,000 lb load cell calibrated 04-25-2011
Max load - 40,707 Pounds
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
180
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 16 Test Requests:
0
5000
10000
15000
20000
25000
30000
35000
40000
0 30 60
Load
Pounds
Tested on 11-18-2011 TJW300,000 lb load calibrated 04-25-
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
90 120 150 180 210 240 270 300 330 360
TimeSeconds
M11-10-12 Sample 3 B Dual Eye Mounting
Load and Break
-2011
Max load - 41,623 Pounds
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
360 390
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 17 Test Requests:
Housing Tracking and Erosion Test
Quadri*Sil
Introduction:
Two samples of Quadri*Sil Series 300 line post insulators, c
tested using the protocol described in ANSI C29.17, clause 7.3. The insulators were manufactured
with 1800-120V silicone rubber polymer,
epoxy fiberglass rod.
Test Protocol:
The test protocol of the standard follows:
7.3 Housing tracking and erosion tests
7.3.1 Test Specimen.
Two insulators or test specimens will be tested, in accordance with ANSI C29.11. . The specimen
length will be chosen such that the leakage
least two weathersheds.
If the same elastomeric materials and manufacturing method have been previously qualified, per
ANSI C29.11, this qualification section will not be repeated.
7.3.1.1 Test chamber.
The test is to be performed in a test apparatus as defined in ANSI C29.11.
7.3.1.2 Test Conditions.
The test is to be performed for a duration of 1000 hours as described in ANSI C29.11.
7.3.1.3 Evaluation.
No tracking is allowed. No weath
the core.
The IEC method regarding flashovers was adopted from standard 62217 as a modification.
If more than one flashover occurs at the initial NaCl content, the test shall be re
halved value of the NaCl content. The insulators are washed by tap water and the test re
within 8 h (interruption times shall not be counted as part of the test duration). This may be
repeated until interruptions no longer occur. The appl
be noted.
The numbers of flashovers and trip
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
Housing Tracking and Erosion Test
ANSI C29.17 – Clause 7.3
Quadri*Sil Series 300 Line Post Insulator
E12-02-18
Two samples of Quadri*Sil Series 300 line post insulators, catalog number P300008S0360, were
tested using the protocol described in ANSI C29.17, clause 7.3. The insulators were manufactured
120V silicone rubber polymer, Chemlok 608 coupling agent and Aiken manufactured
The test protocol of the standard follows:
Housing tracking and erosion tests
or test specimens will be tested, in accordance with ANSI C29.11. . The specimen
length will be chosen such that the leakage distance falls between 200 and 700 mm and includes at
If the same elastomeric materials and manufacturing method have been previously qualified, per
ANSI C29.11, this qualification section will not be repeated.
The test is to be performed in a test apparatus as defined in ANSI C29.11.
The test is to be performed for a duration of 1000 hours as described in ANSI C29.11.
No tracking is allowed. No weathershed punctures are allowed. Erosion is not allowed to reach
The IEC method regarding flashovers was adopted from standard 62217 as a modification.
If more than one flashover occurs at the initial NaCl content, the test shall be re-starte
halved value of the NaCl content. The insulators are washed by tap water and the test re
within 8 h (interruption times shall not be counted as part of the test duration). This may be
repeated until interruptions no longer occur. The application of any of the above measures shall
The numbers of flashovers and trip-outs shall be recorded and noted in the test report.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
atalog number P300008S0360, were
tested using the protocol described in ANSI C29.17, clause 7.3. The insulators were manufactured
coupling agent and Aiken manufactured
or test specimens will be tested, in accordance with ANSI C29.11. . The specimen
distance falls between 200 and 700 mm and includes at
If the same elastomeric materials and manufacturing method have been previously qualified, per
The test is to be performed for a duration of 1000 hours as described in ANSI C29.11.
ershed punctures are allowed. Erosion is not allowed to reach
The IEC method regarding flashovers was adopted from standard 62217 as a modification.
started at a
halved value of the NaCl content. The insulators are washed by tap water and the test re-started
within 8 h (interruption times shall not be counted as part of the test duration). This may be
ication of any of the above measures shall
outs shall be recorded and noted in the test report.
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE May 29, 2012
PAGE: 18 Test Requests:
Test Data:
The samples evaluated would have been catalog number
that can be manufactured would include 20 weathersheds. These insulators only utilized
weathersheds and so had one end with a normal seal, with the opposite seal filled with RTV
end fitting.
The two sample insulators were mounted as prescribed i
on March 7th, 2012, and concluded on
A synopsis of the event log for the salt fog chamber is shown in table 1.
Date Stop Time
3/7/12
3/19/12
3/20/12
3/21/12
3/22/12
3/27/12
3/28/12
4/28/12 0700
A bus fault resulted in numerous trip
of the test.
Upon removal, each of the insulators was visually examined. There were no holes, tracki
erosion to the core.
Conclusion:
The Quadri*Sil Series 300 line post insulators (catalog number P300008S0360)
requirements of the protocol for ANSI C29.17, clause 7.3.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
May 29, 2012
Test Requests: R12-11-03 Report Number: R12
would have been catalog number P300008S0360. The smallest insulator
at can be manufactured would include 20 weathersheds. These insulators only utilized
weathersheds and so had one end with a normal seal, with the opposite seal filled with RTV
The two sample insulators were mounted as prescribed in the test protocol. The test was initiated
and concluded on April 28th, 2012. The applied voltage was 18.62
A synopsis of the event log for the salt fog chamber is shown in table 1.
Stop Time Start Time Timer hours
0 Start test
kV
0830 217 Power Outage
1000 228 Power Outage
1500 259 Power Outage
1300 264 Power Outage
0800 359 Power Outage
1245 368 Power Outage
1012
Table 2
A bus fault resulted in numerous trip-outs. There were no identified flashovers during the course
Upon removal, each of the insulators was visually examined. There were no holes, tracki
The Quadri*Sil Series 300 line post insulators (catalog number P300008S0360) met all of the
requirements of the protocol for ANSI C29.17, clause 7.3.
ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
The smallest insulator
at can be manufactured would include 20 weathersheds. These insulators only utilized 6
weathersheds and so had one end with a normal seal, with the opposite seal filled with RTV at the
n the test protocol. The test was initiated
, 2012. The applied voltage was 18.62 kV.
Remarks
Start test – 18.62
kV – 10 kg/m3
Power Outage
Power Outage
Power Outage
Power Outage
Power Outage
Power Outage
End of Test
outs. There were no identified flashovers during the course
Upon removal, each of the insulators was visually examined. There were no holes, tracking or
met all of the
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T
DATE November 7, 2012
PAGE: 19 Test Requests:
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
November 7, 2012
Test Requests: R12-11-03 Report Number: R12
est Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T
DATE November 7, 2012
PAGE: 20 Test Requests:
ANSI C29.17
Introduction:
Weathershed and shank sections were cut from an insulator molded by PNT using HPS silicone rubber
compound 1800-120V. The Aging or Weathering Test as outlined in ANSI C29.17
performed using the Fluorescent UV Method (ASTM G 53). The test was performed in QUV machines
using UVB-313 bulbs.
Details:
The test was performed on both stressed and unstressed samples of the polymer. Stressed samples were
placed in tension by bending them in half and positioning them in the machine so that the maximum UV
exposure occurred on the section under tensile stress. The daily exposure cycle was 16 hours of UV
exposure and 8 hours of condensation. The test protocol requires a min
without evidence of cracking or crazing.
Conclusions:
The samples were exposed for 1505 hours total time (1004 hours UV exposure). There were no indications
of degradation, cracking, fading, chalking or loss of hydrophobi
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
November 7, 2012
Test Requests: R12-11-03 Report Number: R12
ANSI C29.17 – Clause 7.3.2 – Aging or Weathering Test
Silicone Rubber 1800-120V
M05-04-07
Weathershed and shank sections were cut from an insulator molded by PNT using HPS silicone rubber
120V. The Aging or Weathering Test as outlined in ANSI C29.17 – clause 7.
performed using the Fluorescent UV Method (ASTM G 53). The test was performed in QUV machines
The test was performed on both stressed and unstressed samples of the polymer. Stressed samples were
n by bending them in half and positioning them in the machine so that the maximum UV
exposure occurred on the section under tensile stress. The daily exposure cycle was 16 hours of UV
exposure and 8 hours of condensation. The test protocol requires a minimum of 1000 hours exposure
without evidence of cracking or crazing.
The samples were exposed for 1505 hours total time (1004 hours UV exposure). There were no indications
of degradation, cracking, fading, chalking or loss of hydrophobicity.
est Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
Weathershed and shank sections were cut from an insulator molded by PNT using HPS silicone rubber
clause 7.3.2, was
performed using the Fluorescent UV Method (ASTM G 53). The test was performed in QUV machines
The test was performed on both stressed and unstressed samples of the polymer. Stressed samples were
n by bending them in half and positioning them in the machine so that the maximum UV
exposure occurred on the section under tensile stress. The daily exposure cycle was 16 hours of UV
imum of 1000 hours exposure
The samples were exposed for 1505 hours total time (1004 hours UV exposure). There were no indications
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T
DATE November 7, 2012
PAGE: 21 Test Requests:
Quadri*Sil Series 300 Line Post Insulators
Introduction:
The dye penetration test was performed on
number P300046S0360. The insulators were manufactured with Chance Epoxy E
1800-120V silicone rubber and Chemlok 608 coupling agent.
Test Protocol:
The test was performed in accordance with ANSI C29.
7.4.1 Dye Penetration Test
Ten samples will be prepared and tested in accordance with ANSI C29.11. There will be
no dye solution penetration through the sample after fifteen minutes of exposure.
ANSI C29.11
7.4.1 Dye Penetration Test
7.4.1.1 Test specimens
Ten core samples shall be cut from an insulator. The length of the samples shall
be 10 mm ± 0.5 mm. They shall be cut nominally 90° to the axis of the core with
diamond
shall be smoothed with a 180
and approximately parallel
7.4.1.2 Test
The samples shall be placed on a layer of steel or glass balls in a vessel with the
fiber vertical. The balls shall be of the same dia
to 2 mm. The dye, composed of 1 gram of fuchsin in 100 grams of methanol, is
poured into the vessel until its level is 2 mm to 3 mm above the top of the balls.
7.4.1.3 Evaluation
The time for the dye to rise through the sampl
than 15 minutes.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
November 7, 2012
Test Requests: R12-11-03 Report Number: R12
Dye Penetration test
ANSI C29.17 - Clause 7.4.1
Quadri*Sil Series 300 Line Post Insulators
Catalog Number P300046S0360
M11-10-13
The dye penetration test was performed on samples of Quadri*Sil Series 300 line post insulators, catalog
number P300046S0360. The insulators were manufactured with Chance Epoxy E-CR DD fiberglass rod,
120V silicone rubber and Chemlok 608 coupling agent.
The test was performed in accordance with ANSI C29.17 clause 7.4.1
7.4.1 Dye Penetration Test
Ten samples will be prepared and tested in accordance with ANSI C29.11. There will be
no dye solution penetration through the sample after fifteen minutes of exposure.
7.4.1 Dye Penetration Test
.4.1.1 Test specimens
Ten core samples shall be cut from an insulator. The length of the samples shall
be 10 mm ± 0.5 mm. They shall be cut nominally 90° to the axis of the core with
diamond-coated circular saw blade under cool running water. The cut surfa
shall be smoothed with a 180-grit abrasive cloth. The cut ends shall be clean
and approximately parallel
The samples shall be placed on a layer of steel or glass balls in a vessel with the
fiber vertical. The balls shall be of the same diameter and in the range of 1 mm
to 2 mm. The dye, composed of 1 gram of fuchsin in 100 grams of methanol, is
poured into the vessel until its level is 2 mm to 3 mm above the top of the balls.
7.4.1.3 Evaluation
The time for the dye to rise through the samples by capillarity shall be more
than 15 minutes.
est Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
ine post insulators, catalog
CR DD fiberglass rod,
Ten samples will be prepared and tested in accordance with ANSI C29.11. There will be
no dye solution penetration through the sample after fifteen minutes of exposure.
Ten core samples shall be cut from an insulator. The length of the samples shall
be 10 mm ± 0.5 mm. They shall be cut nominally 90° to the axis of the core with
coated circular saw blade under cool running water. The cut surfaces
grit abrasive cloth. The cut ends shall be clean
The samples shall be placed on a layer of steel or glass balls in a vessel with the
meter and in the range of 1 mm
to 2 mm. The dye, composed of 1 gram of fuchsin in 100 grams of methanol, is
poured into the vessel until its level is 2 mm to 3 mm above the top of the balls.
es by capillarity shall be more
ENGINEERING REPORTSUBJECT ANSI C29.17 Prototype T
DATE November 7, 2012
PAGE: 22 Test Requests:
Test Results:
The characteristics of the samples and the results of the dye penetration test are contained in table 1.
Sample
1
2
3
4
5
6
7
8
9
10
Conclusion:
All of the samples of the 3” rod manufactured with the 1800
the test.
ENGINEERING REPORT ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
November 7, 2012
Test Requests: R12-11-03 Report Number: R12
The characteristics of the samples and the results of the dye penetration test are contained in table 1.
Sample Length Time Pass/Fail
10.15 > 15 minutes P
10.30 > 15 minutes P
10.47 > 15 minutes P
10.45 > 15 minutes P
10.45 > 15 minutes P
10.48 > 15 minutes P
10.42 > 15 minutes P
9.98 > 15 minutes P
10.48 > 15 minutes P
10.50 > 15 minutes P
Table 3
es of the 3” rod manufactured with the 1800-120V silicone rubber met the requirements of
est Report; Quadri*Sil Series 300 Line Post Insulators
R12-11-03
The characteristics of the samples and the results of the dye penetration test are contained in table 1.
120V silicone rubber met the requirements of
ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE: November 7, 2012
PAGE 23 Test Requests: R12-11-03 Report Number: R12-11-03
ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE: November 7, 2012
PAGE 24 Test Requests: R12-11-03 Report Number: R12-11-03
ANSI C29.17 - Clause 7.4.2
Water Diffusion Test
P300046S0360 Series 300 Quadri*Sil
Introduction:
The water diffusion test was performed on samples cut from a P300046S0360 Series 300 Quadri*Sil line
post. The insulator was manufactured with Chance epoxy fiberglass rod with E-CR DD glass fibers,
Chemlok 608 coupling agent and 1800-120V silicone rubber polymer housings.
Test Protocol:
The test was performed in accordance with ANSI C29.17 clause 7.4.2
7.4.2 Water diffusion test
Six samples will be prepared in accordance with ANSI C29.11. The electrodes will be
modified to provide total coverage of the cross sectional area, which insures puncture of
the rod sample. The test arrangement is shown in figure 1. No puncture or surface
flashover is allowed. The current during the test shall not exceed 1-mA, rms.
Test Results:
Samples were cut and prepared as prescribed in ANSI C29.11. Boiling was initiated on October 23rd, 2011,
at 10:45 a.m. and ended on October 27th, 2011, at 2:50 p.m. The samples were removed from the vessel
and subjected to the electrical test. The data is contained in table 1.
Sample
No.
Length
(mm)
Voltage
(kV)
Current
(µA –
peak)
Time
(minutes)
Results Comments
1 29.95 12.1 220 1 Pass
2 30.10 12.1 220 1 Pass
3 30.48 12.1 220 1 Pass
4 30.45 12.2 220 1 Pass
5 29.65 12.1 220 1 Pass
6 30.42 12.0 220 1 Pass
Table 4
Conclusion
All of the samples of the Series 300 Quadri*Sil line post insulator met the requirements of the test protocol.
ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE: November 7, 2012
PAGE 25 Test Requests: R12-11-03 Report Number: R12-11-03
ANSI C29.17 – Clause 7.5
Flammability Tests
Silicone Rubber 1800-120V Rubber Compound
R.K. Niedermier
October 26, 2001
ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE: November 7, 2012
PAGE 26 Test Requests: R12-11-03 Report Number: R12-11-03
I. INTRODUCTION
This report describes the results of flammability tests on OB polymer compound
1800-120V. This rubber compound is used for the injection molding of insulators
manufactured by The Ohio Brass Company.
The tests were conducted in accordance with IEC Publication 707, “Methods of
test for the determination of flammability of solid electrical insulating materials
when exposed to an igniting source.”
The specific tests employed were IEC Method FV: Flame – Vertical specimen.
II. RESULTS
Method FV:
The igniting source and test units are defined in paragraphs 9.1 and 9.2 of the
referenced publication.
Procedure:
“Each specimen is to be fixed vertically by the clamp on the ring stand. The
burner is placed remote from the specimen, ignited and adjusted in the vertical
position to produce a blue flame 20+-2 mm high. The flame is obtained by
adjusting the gas supply and the air ports of the burner until a 20+-2 mm yellow
tipped blue flame is produced and then the air supply is increased until the yellow
tip disappears. The height of the flame is measured again and corrected in
necessary.
The burner is to be placed centrally under the lower end of the test specimen and
allowed to remain for 10 s. The burner is then to be withdrawn at least 150 mm
away and the duration of flaming of the specimen noted. When flaming of the
specimen ceases, the burner is to be immediately placed again under the
specimen. After 10 s the burner is again to be withdrawn and the duration of
flaming and glowing to be noted.
If the specimen drips molten or flaming material during either of the flame
applications, the burner may be tilted to an angle up to 45 degrees and also
slightly withdrawn away from one of the 13 mm sides of the specimen during the
flame application, to avoid material dripping into the tube of the burner.
If the specimen drips molten or flaming material or is consumed during the test,
the burner is to be hand-held, and the 10 mm distance between the bottom of the
specimen and the top of the burner tube is to be maintained during the flame
application. Any molten strings of the material are to be ignored and the flame is
to be applied to the major portion of the specimen.”
ENGINEERING REPORT SUBJECT: ANSI C29.17 Prototype Test Report; Quadri*Sil Series 300 Line Post Insulators
DATE: November 7, 2012
PAGE 27 Test Requests: R12-11-03 Report Number: R12-11-03
Evaluation:
1800-120V is classified as Category FV 0 material based on the following test
results:
Flaming Combustion Time (s)
First flame Second flame
Sample Application Application
1 0 0
2 0 0
3 0 0
4 0 0
5 0 0
6 0 0
7 0 0
8 0 0
As shown, the total flaming combustion time for the sixteen flame applications to
the set of eight specimens was 0 seconds.