    SHEET   1   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED CHECKED PROJECT/PROPOSAL NO.

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date: By: Date:243332.0003 

J. Hotstream  11/15/2017  T. Martin  12/13/2017 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐002_2017 INSPECTION.DOCX   12/22/17 

INSPECTION REPORT 

Landfill Annual Inspection Report 

Purpose: 

This inspection checklist has been developed to meet the requirements for inspections by a 

qualified professional engineer for a coal combustion residual (CCR) landfill.  This checklist 

exceeds the requirements for 40 Code of Federal Regulations 257.84(b).  This inspection of the 

Alma Off‐Site Disposal Facility Phase IV Landfill was performed by TRC Environmental 

Corporation on behalf of Dairyland Power Cooperative (DPC). 

The goal of the inspection is to ensure that the design, construction, operation, and maintenance 

is consistent with recognized good engineering practices.  In addition, the inspection looked for 

conditions of structural weakness or conditions that may affect the safe operation of the CCR 

unit. 

The following were performed for the inspection of the CCR unit. 

Review of Available Information:  

The following documents were reviewed in preparation of the site visit. 

Health and Safety Plan 

Fugitive Dust Control Plan (12/19/2016) 

Groundwater Monitoring Program (10/2017) 

Dust Control Report (12/5/2016) 

Post‐Closure Plan (10/2016) 

Closure Plan (10/2016) 

Run‐on and Run‐off Control System Plan (10/2016) 

Annual Landfill Inspection Report (12/16/2016) 

Weekly inspections performed by qualified personnel (11/2/2016 through 11/10/2017) 

Comments on the Operating Record:  Electronic system, well organized, accessible from the 

office at the landfill   

Summary of the Site Conditions (based on document review): 

DPC operates a CCR landfill (Alma Off‐Site Disposal Facility, Phase IV Landfill) located in the 

NE 1/4 of the NE 1/4 of Section 19 and portions of Sections 18 and 20, T21N, R12W, Town of 

Belvidere, Buffalo County, Wisconsin.  The location of the Phase IV landfill is in a valley 

 

    SHEET   2   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED CHECKED PROJECT/PROPOSAL NO.

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date: By: Date:243332.0003 

J. Hotstream  11/15/2017  T. Martin  12/13/2017 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐002_2017 INSPECTION.DOCX   12/22/17 

INSPECTION REPORT 

including 3 phases of non‐contiguous closed landfills.  This inspection addresses only the Phase 

IV landfill, because the Phase 1, II, and III landfills were closed prior to the promulgation of the 

federal CCR rule (40 Code of Federal Regulations 257.50 through 107). 

The Phase IV landfill is permitted through the state of Wisconsin.  To date the liner system of 

Cells 1, 2A, 2B, 3A, and 3B have been constructed with final cover installed over a portion of 

Cells 1, 2A, and 2B.  Cell 3B of the Phase IV landfill was constructed during May through 

August 2015.  The landfill construction includes a composite liner system, composite cover 

system, leachate collection system, leachate storage tank, and storm water controls (diversion 

berms, sedimentation basin, ditching, and downslope flumes). 

Changes to the unit since the previous report: 

Since the inspection in 2016, there has been continued placement of CCR into Cell 3A and 3B. 

Approximate volume of CCR in the unit at the time of the inspection:  Approximately 1,044,100 

cubic yards based on the November 14, 2017, topographic survey 

Visual Inspection: 

A site visit and visual inspection were performed by Jonathan Hotstream, P.E., P.G. (TRC 

Environmental Corporation) on November 15, 2017 

Time arrived on site:  10:14 AM ________________________  

Time departed from site:  12:10 PM _____________________  

DPC Personnel Present:  Leif Tolokken _________________  

Weather Conditions:  Cool, overcast, lower to upper 40s °F  

Summary of Items Visually Inspected:  Electronic operating record, weekly inspection forms, 

sedimentation basin, perimeter berm/access road, perimeter run‐on controls including 

stormwater channels, outlets, culverts; final cover areas including diversion berms and 

vegetation; working area conditions; Cell 3A and 3B/Future Cell 4 delineation berm; and surface 

conditions at the leachate collection tank controls.  _______________________________________   

  ___________________________________________________________________________________   

Site Operations during Inspection:  No site operations were occurring during inspection due to 

a safety training. _____________________________________________________________________   

  ___________________________________________________________________________________   

 

    SHEET   3   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED CHECKED PROJECT/PROPOSAL NO.

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date: By: Date:243332.0003 

J. Hotstream  11/15/2017  T. Martin  12/13/2017 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐002_2017 INSPECTION.DOCX   12/22/17 

INSPECTION REPORT 

Appearance of structural conditions: 

Final Cover Conditions (Cell 1 and 2A areas): 

Vegetation Condition:  Well established, dense vegetation  

Evidence of Erosion:   Yes:      None:     X   

Evidence of slumping, sloughing, or slope distress:   Yes:      None:     X   

Evidence of seepage:   Yes:      None:     X   

Comments:  Good establishment of native grasses emerging on newer final cover, older phases 

of final cover have a mature dense stand of state approved tall grass prairie vegetation.   ______   

Perimeter Berm: 

Vegetation Condition:  Well established, dense vegetation _________________________________   

Evidence of Erosion:   Yes:      None:     X   

Cracking along crest:  Access road along crest  Yes:      None:     X   

Evidence of slumping, sloughing, or slope distress:   Yes:      None:     X   

Evidence of seepage:   Yes:      None:     X   

Cell Delineation Berms:  Exposed geomembrane covering berm ____________________________   

Comments:  Separation with waste filling for adequate run‐off control.  No observed 

irregularities in the slope or geomembrane cover. ________________________________________   

Stormwater Controls: 

Run‐on Controls:  Diversion berms provide adequate drainage and slope away from open areas.  

Perimeter Drainage Ditches:  Cleared of sediment and obstructive vegetation, well‐

maintained rip‐rap, grouted rip‐rap clear of obstructions, and good conveyance present.   

 _____________________________________________________________________________   

Comments:  Well‐maintained. No concerns at this time.  ____________________________   

 _____________________________________________________________________________   

 _____________________________________________________________________________   

Run‐off Controls:  Final Cover 

Diversion Berms:  Good condition. Well‐maintained with dense vegetative cover, no 

erosion observed, and clear of obstructions. _______________________________________   

 

    SHEET   4   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED CHECKED PROJECT/PROPOSAL NO.

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date: By: Date:243332.0003 

J. Hotstream  11/15/2017  T. Martin  12/13/2017 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐002_2017 INSPECTION.DOCX   12/22/17 

INSPECTION REPORT 

Downslope Flumes:  Inlets and outlets were cleared of vegetation and no erosion 

observed at rock protection.  ____________________________________________________   

Ditching:  No erosion observed; clear of obstructions, sloped for positive drainage, and 

no standing water observed.   ___________________________________________________   

Comments:  Stormwater controls are well‐maintained at the site. Good drainage and 

conveyance to the sedimentation basin.  No obstructions observed. __________________   

 _____________________________________________________________________________   

 _____________________________________________________________________________   

Sedimentation Basin No. 1: 

Outlets Operational:  Yes, repaired and upgraded from previous inspection. (Added 

stone at outlet.)  _______________________________________________________________   

Culverts Operational:  Yes, box culverts cleared and grout added for protection.  ______   

Comments:  Well‐maintained and vegetated. The basin has been cleared, stone added at 

outlet, and side slopes are in good condition.  _____________________________________   

 _____________________________________________________________________________   

Operating Conditions:  

Changes in Operation since the previous annual inspection:  Continued filling of cells 3A and 

3B _________________________________________________________________________________   

Access Road Conditions:  Well‐maintained, clear of tracked material, no rutting or cracking 

observed. ___________________________________________________________________________   

Landfill Operations: 

Temporary Storm Water Controls:  Adequate slopes to contain water within landfill and convey 

water to leachate collection system.  ____________________________________________________   

  ___________________________________________________________________________________   

Working Face Conditions:  Placed material has been graded and rolled to minimize infiltration 

into CCR. ___________________________________________________________________________   

  ___________________________________________________________________________________   

Access roads: Good access conditions into and out of site.   ________________________________   

Fugitive Dust Observed:   Yes:      No:      X   

 

    SHEET   5   OF   5    

708 Heartland Trail, Suite 3000 (53717)      Madison, WI      (608) 826‐3600      FAX: (608) 826‐3941  

PROJECT/PROPOSAL NAME  PREPARED CHECKED PROJECT/PROPOSAL NO.

Dairyland Power Cooperative; Phase IV 

Alma Off‐site Disposal Facility 

By:  Date: By: Date:243332.0003 

J. Hotstream  11/15/2017  T. Martin  12/13/2017 

 

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐002_2017 INSPECTION.DOCX   12/22/17 

INSPECTION REPORT 

Comments:  No site operations were occurring at time of inspection.  Moist conditions 

observed around site.  Water truck is available as needed.  DPC installed larger motors 

for pin mixer and lowered operating temperature of silo, which resulted in less moisture 

evaporating from ash and improved dust control. _________________________________   

Leachate Management:  No standing leachate observed.  Exposed areas of leachate collection 

system and drainage layer at perimeter and base of landfill to manage contact with water 

effectively. __________________________________________________________________________   

  ___________________________________________________________________________________   

Ash Tracked Out on Access Road?  Yes:      None:     X   

Leachate Collection System:  Pipes buried, but not visible; system recently jetted and video 

inspected in October according to weekly reports; system working properly. ________________   

Pipe Cleanouts:  Clean & accessible, bollards protecting ____________________________   

Tank:  Controls are accessible and appeared operational.   __________________________   

Loadout Area:  Accessible and operational ________________________________________   

Comments:  Appears to be a well‐maintained system used daily for operation of the site.  

Conditions that may potentially impact safety:  None observed.  __________________________   

  ___________________________________________________________________________________   

  ___________________________________________________________________________________   

Observed Deficiencies and Proposed Corrective Actions:  Items identified in the previous 

inspection have been addressed. No new deficiencies observed. ____________________________   

  ___________________________________________________________________________________   

Future Action: 

– Continue monitoring and maintenance of stormwater controls.  __________________________   

– Continued implementation of dust control practices.   ___________________________________   

  ___________________________________________________________________________________   

    __________________________________________________________________________________   

 

 

  

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐001.DOCX  1 

Photographic Log 

Client Name:  Site Location:  Project No.: 

Dairyland Power Cooperative  Phase IV Off‐Site Disposal  243332.0003 

Photo No.  Date   

1  11/15/2017 

Description: 

Asphalt paved site entrance 

road looking south. No material 

tracked off site. 

 

 

Photo No.  Date 

2  11/15/2017 

Description: 

Sedimentation Basin 1 outlet. 

Sediment removed and 

vegetation established in the 

base.  Gravel placed 

surrounding base of outlet pipe.  

Standing water present from 

recent precipitation.  

  

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐001.DOCX  2 

Photographic Log 

Client Name:  Site Location:  Project No.: 

Dairyland Power Cooperative  Phase IV Off‐Site Disposal  243332.0003 

Photo No.  Date 

3  11/15/2017 

Description: 

Vegetation established on 

Area 1 and Area 2 final cover. 

 

Photo No.  Date 

4  11/15/2017 

Description: 

CCR filling area showing Cell 3 

delineation berm.  Sufficient 

space and berm height provided 

to control runoff within the 

landfill. 

 

  

\\NTAPB‐MADISON\MSN‐VOL6\‐\WPMSN\PJT2\243332\0003\Z2433320003‐001.DOCX  3 

Photographic Log 

Client Name:  Site Location:  Project No.: 

Dairyland Power Cooperative  Phase IV Off‐Site Disposal  243332.0003 

Photo No.  Date 

11/15/2017  5 

Description 

Perimeter drainage ditch with 

rock check dam. 

 

Photo No.  Date 

6  11/15/2017 

Description: 

Grouted riprap perimeter ditch 

conveying stormwater off site.