annual general & special meeting of shareholdersedg1.precisionir.com › companyspotlight ›...
TRANSCRIPT
Annual General & Special Meeting of Shareholders
Thursday, May 31, 2012
MANAGEMENT PRESENTATION Mike Azancot – President and CEO
Thursday 31st May 2012 Page 2
Presentation Themes
• Achievements
• Major Hurdles
• Cash Management
• Portfolio Expectations
Thursday 31st May 2012 Page 3
Disclaimer
The information in this presentation contains certain forward-looking statements including expectations of future production and capital expenditures. These statements
relate to future events or our future performance. All statements other than statements of historical fact may be forward-looking statements. Information concerning
reserves or resources may also be deemed to be forward-looking statements, as such estimates involve the implied assessment that the reserves or resources described
can be profitably produced in the future. These statements reflect current expectations that involve numerous assumptions and which are subject to a number of risks and
uncertainties that contribute to the possibility that the predictions, forecasts, projections and other forward-looking statements will prove inaccurate and which could cause
actual results to differ from those anticipated by the Company. Although management believes that the expectations reflected in the forward-looking statements are
reasonable, there can be no assurance that such expectations will prove to be correct. The Company cannot guarantee future results, levels of activity, performance, or
achievements. Actual results and future plans could differ materially from those anticipated in forward-looking statements contained in this presentation as a result of the
risks described below.
Certain of the risks and other factors, some of which are beyond the Company’s control, which could cause results to differ materially from those expressed in the
forward-looking statements contained in this presentation include, but are not limited to those as described in the Company’s annual information form for the year ended
December 31, 2011 (the “AIF”) which is available at www.sedar.com. Those factors should not be considered as exhaustive.
In addition, this presentation may contain forward-looking statements attributed to third-party industry sources. These sources are not endorsed or adopted by the
Company explicitly or implicitly. Undue reliance should not be placed on these forward-looking statements, as there can be no assurance that the plans, intentions or
expectations upon which they are based will occur.
The forward-looking statements contained in this presentation are expressly qualified by the foregoing cautionary statement. Financial outlook information contained in this
presentation about prospective results of operations, financial position or cash flows is based on assumptions about future events, including economic conditions and
proposed courses of action, based on management’s assessment of the relevant information currently available. Readers are cautioned that any such financial outlook
information contained in this presentation should not be used for purposes other than for which it is disclosed herein.
Nothing contained herein is intended to constitute an offer to sell or a solicitation of an offer to purchase securities. Any such offer or solicitation may only be made by
prospectus or otherwise pursuant to an exemption from prospectus and registration requirements applicable to the Company.
Information on reserves and resources in this presentation are drawn from the Company’s most recent Statement of Reserves Data and Other Oil and Gas Information on
Form 51-101F1 for the year ended December 31, 2011 appended to the Company’s AIF dated April 12, 2012 and filed on SEDAR at www.sedar.com.
Thursday 31st May 2012 Page 4
Investment Proposition
• Outstanding track record of finding oil & gas
– Discovered a total of > 200 MMbbls OIIP and > 1.5 Tcf of GIIP
• Breagh gas project in development for first production later this year
• Government support in Romania allows development and exploration to proceed and deliver significant value
• Broad portfolio of high impact exploration prospects
– 460 MMboe(1) of Best Estimate Unrisked Prospective Resources(2) (with additional significant unconventional targets in Romania and France)
• Several near-term catalysts for value creation
– Breagh on production by 4Q 2012
– Commence exploration drilling (2 wells) offshore Romania 3Q 2012
– Cladhan draft FDP submission May 2012
– Seismic programs in Romania, UK & Netherlands
– Portfolio rationalization
Thursday 31st May 2012 Page 5
(1) RPS year-end report 2011 (2) Prospective Resources are those quantities of petroleum estimated as of a given date to be potentially recoverable from undiscovered accumulations by applications of future development
projects. There is no certainty that any portion of the Prospective Resources will be discovered or, if discovered, that it will be commercially viable to produce any portion of the Resources. These Prospective Resources are in areas of the field or geological horizon, in which the presence of hydrocarbons require confirmation by drilling.
Asset Working Interest Net Reserves
& Resources Description
NEAR-TERM PRODUCTION
Breagh
UK Southern North Sea
30%
Op: RWE Dea
31.4 MMboe (proved plus
probable) (1)
Phase 1 in development, first gas
expected 4Q 2012
Cladhan
UK Northern North Sea
26.4%, Op 7.3 MMboe
(CR P50)(1)
Northern North Sea oil development
and appraisal activities in 2012 and
2013
Doina & Ana
Offshore Romania
65%, Op 37.3 MMboe
(CR P50)(1)
Offshore gas discoveries, first
production expected in 2015
APPRAISAL P50 CR(1)
Crosgan
UK Southern North Sea
30%
Op: RWE Dea
5.1 MMboe
Appraisal planned for H1 2013;
potential subsea tie-back to Breagh
in 2015
Offshore Netherlands 35%, Op 12.6 MMboe Four oil discoveries, appraisal in
progress
UK North Sea Various 13.5 MMboe 5 Central North Sea discoveries
EXPLORATION P50 PR(1)
Offshore Romania 65%, Op 325 MMboe 9 prospects across 2 blocks
UK North Sea Various 8 MMboe 3 Central North Sea prospects
Onshore Romania 50%, Op 242 MMboe Potential shale gas play
Onshore France 33.4%, Egdon 24 MMboe Seismic over Audignon 2012
CR = Contingent Resources, PR = Prospective Resources The definitions of Contingent and Prospective Resources can be found on Page 28 of the Sterling 2011 Annual Report
(1) RPS, Year-end Report 2011 , adjusted for WI% changes
Finding and Developing Oil & Gas in Europe Three field developments, all discovered or appraised by Sterling, and material exploration upside in asset portfolio
Thursday 31st May 2012 Page 6
A sustainable business model focused on shareholder value
Thursday 31st May 2012 Page 7
The Sterling Business Model: Consistent, Repeatable
Balance high impact exploration with major projects and funding
Thursday 31st May 2012 Page 8
Licence Awards, High Working Interest
• Portfolio includes licences in:
– UK
– Netherlands
– France
– Romania
• Awarded UKNS licences since 2003
• Extensive geophysical capabilities
Drill, Discover and Appraise, Reduce Working Interest
• High calibre exploration team
• Discoveries include
– Cladhan
– Breagh
– Doina
– Ana
– Sheryl
– Blakeney
Monetise, Reduce Working Interest
• Sold 15% working interest in Breagh + surrounding exploration to RWE Dea
• Sold 13.5% working interest of North Cladhan & 12.5% of South Cladhan to TAQA
Develop and Produce
• Breagh Phase I first gas expected Q4 2012
– Sterling’s first development
• Cash flow will partially fund ongoing high impact drilling programme and future development capex
Consider Farm Down
Breagh 2004 2007 / 2008 2009 2012
Cladhan 2003 2008 / 2010 2012 2014 / 2015
Doina/Ana 1997 2007 / 2008 2H 2012 2015
Reinvest Cashflow and Cash Proceeds
Health Safety & Environment
Performance from 2006 to 2011
• 1.99 million man-hours
• 1 environmental incident
• 1 lost time incident
Achieved by
• Commitment to HSE standards throughout the organization (company
and contractors)
• Open and continuous dialogue with operations contractors
• Hands-on approach with adherence to policies and procedures
Thursday 31st May 2012 Page 9
Reserves and Resources Portfolio
Sterling’s reserves and resources portfolio now offers a balanced spread of developed,
undeveloped and extensive exploration upside in both oil and gas
Thursday 31st May 2012 Page 10
33MMboe
Proved plus Probable Reserves
94MMboe
Company Interest P50
Contingent Resources Unrisked
460MMboe
Company Interest Best Estimate
Prospective Resources Conventional, unrisked (excludes unconventional gas resources in Romania).
Source RPS, Year-end Report 2011
Near-Term Production Expectations
Sterling expects to achieve first gas from Breagh by Q4 2012 with Cladhan & Doina/Ana to follow in 2015
Thursday 31st May 2012 Page 11
(1) Sterling’s evaluation of profiles based
on RPS, year-end 2011. Unrisked P50
Contingent Resources plus Best Estimate
Prospective Resources
Breagh; RWE FDP Phase 1
adjusted for 2012 delay
Cladhan; FDP
4 Producers, 3 Injectors
Cladhan Core Area; draft FDP
2 Producers, 1 Injector
Ana & Doina (1)
(1)
(1)
mb
oe
pd
Breagh: Near-term gas production
Thursday 31st May 2012 Page 12
Crosgan
Breagh
97% of 2P
Reserves
2P Reserves(1) 184 Bcf, 0.8 MMbbls condensate
31.4 MMboe (Net Sterling)
Working Interest 30%
Operator RWE Dea (70%)
First Production 4Q 2012
Breagh Phase 1 (Alpha Platform)
• 2P Reserves (1): 28.7 MMboe
• FDP approval from DECC in July 2011
• Development activities: Offshore pipelines and cabling laid, jacket and topsides installed.
Onshore operations ongoing. Well hook up and rig operation started in May 2012.
3-4 wells expected online by year end.
Breagh Phase 2 (Bravo Platform or Subsea )
• Incremental 2P Reserves (1) : 2.7 MMboe
• Project sanction: 2012
• First production target : 2014
Crosgan
• P50 Contingent Resources(1): (30.3 Bcf) 5.1 MMboe
• Potential subsea tie-back to Breagh in 2014/15
(1) RPS, Year-end Report 2011
Breagh: Field Development
Thursday 31st May 2012 Page 13
• £95 million main tranche, £10 million cost-overrun tranche with 4 banks. Use of cost-overrun facility requires matching amount of additional equity
funding.
• After discussions with banks, reduced minimum group cash requirement for each forward-looking cash flow statement (CFS) from £35 million to £20
million, with effect from April 1, 2012.
• After clarification of cost overrun and production delay, Sterling will work with the banks to recalculate availability under both tranches. May need to
use a material part or all of the cost-overrun tranche.
• 90 day period to remedy any shortfall in minimum group cash level in CFS.
Project Financing
Breagh Cost Overruns
£ million net % of overrun
FDP 145
Drilling 9 28
Offshore Pipeline 11 33
Onshore Terminal 7 22
Onshore Pipeline 4 12
Other 2 5
Cost update May 21, 2012 (mid case) 178 100
C$ million
RPS 10% NPV Sterling total 2P Reserves as at December 31, 2011 (per AIF) 393
Breagh Phases 1&2 value included in total above 374
Breagh Phase 1 value included in total above 369
Adjustment for reference date of Mar 31, 2012 +30
Adjustment for UK b/f tax loss at Mar 31, 2012 +93
Adjustment for 3 month production delay (to October 2012) -6
Adjustment for capex increase (to £592.5 million mid case, 100%) -11
Adjustment for change in capex phasing +3
Adjusted 10% NPV as at Mar 31, 2012 478
Equivalent value C$ per share (222.7 million shares in issue) 2.15
Adjustment to Breagh Phase 1 value
Note: this is an estimated management proforma adjustment, not independently verified, and
does not represent fair market value
Cladhan: Achieved Commerciality, Further Upside
Thursday 31st May 2012 Page 14
• Discovered in 2008
• Initial appraisal in August 2010
• Five fields within tie-back distance to Cladhan discovery
• Completed four-well appraisal programme H1 2011
• Successful in delineating the northern core area with a new effective oil column of over 1,200 feet
• Better understanding of the field’s limits – enabling Sterling to proceed with development planning
• Field development submission in mid 2012
• Subsea development options being considered are to own FPSO or via host platform
• Acquired Geostreamer data Sept 2011
• Acquired a 25% interest in Cladhan South in March 2011 through an asset swap with Valiant Petroleum,
provides further potential upside.
• Divested 13.5% of North Cladhan & 12.5% of South Cladhan to TAQA
• Drilled Cladhan South Exploration well
P50 Contingent Resources(1) 7.2 MMbbls
P50 Prospective Resources(1) 9.0 MMbbls
Working Interest 26.4%
Operator Sterling (TAQA Designate)
Field Partners Wintershall (33.5%)
TAQA (40.1%)
First Production 2014 / 2015
(1) RPS, Year-end Report 2011, adjusted to 26.4% WI
26.4% WI
12.5% WI
Cladhan Summary
Cladhan sand fairways & recent wells
Thursday 31st May 2012 Page 15
Development well locations
Detailed
Development Plan
Cladhan: Development Schedule
Thursday 31st May 2012 Page 16
Offshore Romania: Summary
Thursday 31st May 2012 Page 17
Country Highlights XV Midia (Gas Prone Block) – 65% WI XIII Pelican (Oil Prone Block) – 65% WI
Discoveries P50 CR (1) Prospects P50 PR(1)
Doina and Ana 37.4 MMboe Eugenia 78 MMboe
Prospects P50 PR(1) Eugenia South 12 MMboe
Ioana 71 MMboe Mihaela 59 MMboe
Clara 6 MMboe Cati 4 MMboe
Florina 8 MMboe Irina (2) 44 MMboe
Gina 12 MMboe
Bianca 12 MMboe
Anca (2) 56 MMboe
Nadia (2) 33 MMboe
Maria (2) 13 MMboe
Paula (2) 6 MMboe
Updip Voinicul (2) 3 Mmboe
(1) RPS, Year-end Report 2011 (2) RPS, May 2012 review
Addition of Block 27
• 40% Working Interest, adjacent to Pelican block
• 3D seismic to be acquired 2H 2012
Other Participants now in Region
• 345 Bcf discovered on Doina and Ana (XV Midia block)
• 1st gas 2015
• 224 Bcf (37.4 MMboe) net to Sterling (1)
• 10 further prospects on XV Midia block
• 6 oil prospects identified on XIII Pelican block
• Favourable fiscal regime
• Strong local demand for gas
• Gas price liberalization plans
• ExxonMobil
• Melrose Resources
• LUKOIL
• PETROM / OMV
• Petro Ventures
• Gas Plus
• Petromar
• Vanco
Romania Offshore: Significant Opportunities
Progressing development of material gas discoveries and new regional infrastructure
Thursday 31st May 2012 Page 18
Romanian Gas Price Liberalization
According to quoted government sources there will be a new Gas law
to be provided mid June 2012 as an Emergency Ordinance that has
the following main issues that are pertinent to us:
• The status of transit pipelines will be changed by end June, by
renegotiating the intergovernmental agreements with the
Russian Federation to provide for access.
• Gas will be liberalized gradually from Dec 1 2012 to Oct 1 2014
for industrial customers and from July 1 2013 to October 1st
2018 for domestic customers
Thursday 31st May 2012 Page 19
Gas Price Liberalization Infrastructure Map
PRODUCER GAS PRICE FORECAST
Purvin & Gertz, September 2011
Central North Sea: Beverley Play Type & Regional Setting
Thursday 31st May 2012 Page 20
Top Row - Beverley (Left to Right):
• Regional Setting
• Schematic showing potential for multiple targets
Bottom Row - Beverley (Left to Right):
• Regional setting & line of section
• Seismic detail showing Beverley together with
analogue significant producing fields Gannet B &
Gannet C
• Beverley – the last undrilled salt
diapir in the Central North Sea
• A number of analogous diapirs
have been drilled resulting in
discoveries (e.g. Gannet B,
Gannet C, Kyle and Banff)
• Success would add to the
existing Evelyn and Belinda
discoveries to create producing
hub
Offshore Netherlands
Thursday 31st May 2012 Page 21
1) Appraising oil discoveries
2) Exploration
• Additional prospectivity identified in the F Quad area by recent 3D analysis
• Recently awarded 50% working interest in the Wintershall operated E3/F1 blocks
(1) RPS, Year-end Report 2011, adjusted for WI%
Prospects SLG WI Drill Date Development Scenario
F17 35% 1H 2012 Host Facility
F17-4 35% 1H 2013* Subsea tie-back to F17
F14 35% TBD Subsea tie-back to F17
F18 35% 2H 2013* Subsea tie-back to F17
L01-FB 35% TBD Subsea tie-back to F17
* - Potential Drill date
• Owner and operator of shallow horizons in licences F14, F16 (excluding the F16-E and
F16-P production units), F17a, F18 and L01b
• Four oil discoveries in five blocks, previous wells have tested at flow rates between
2,000 bbls/d and 4,000 bbls/d
• Gross acreage position of 479,000 acres
• Appraisal well in Block F17a completed, F17-9 well encountered 10m gross oil section
and OWC – remapping in progress
• P50 Contingent Resources 12.6 MMbbl and Prospective Resources of 19.6 MMbbl (1)
• Lack of existing oil infrastructure in region but development solutions available
• Acquired additional 10% interest from Enquest 2Q 2012
Offshore Netherlands: Discoveries and Exploration Potential
Thursday 31st May 2012 Page 22
F17 F18
Korvet Brigantijn
Barkentijn
Fregat
F17-4 Amplitude
Brigantijn
“New Play” - Barkentijn
Seismic Section across F17-4 “New Play”
KEY
ODT WUT
Fregat
APPRAISAL / DEVELOPMENT
EXPLORATION
• Continued 3D analysis presents
additional prospectivity associated with
amplitude and salt ridges – as per
Barkentijn example given
• Exploration portfolio recently
supplemented by addition of E3/F1
blocks awarded early 2012
LKO
Korvet (F17-A)
Brigantijn (F17-4 )
New Well
Onshore France
Thursday 31st May 2012 Page 23
Paris Basin:
• 9.5 blocks of gross 150,000 acres
• Jurassic & Triassic aged targets
• Potential drilling in 2013
Aquitaine Basin: • Sterling to be operator with 40% interest of St
Laurent & Donzacq licences. • 3D seismic reprocessing and acquisition. • Potential well in 2013 on Audignon gas prospect. • 144 Bcf Best Estimate Unrisked Prospective
Resources(1)
(1) RPS, Year-end Report 2011
2011 Actual & 2012 Planned Activity
Thursday 31st May 2012 Page 24
Financial Management in a Challenging Period
• Bought deal July 2011 for $42.5 million to secure Breagh debt financing (RBL) to receive
government approval of Breagh Phase 1 programme
• RBL terms amended in April 2012 releasing $24 million from liquidity buffer
• Cladhan divestment in April 2012 to raise $26 million mid 2012, further cash or carry
payment later
• Probable Breagh cost over-runs and 1st gas delay along with a proactive 2013 work
campaign in Romania will require additional funding later in 2012 from sources such as:
– Divestment of a portion of our 65% equity position of offshore Romanian assets
– UK divestments
– Breagh RBL refinancing
Thursday 31st May 2012 Page 25
Presentation Themes
• Achievements
• Major Hurdles
• Cash Management
• Portfolio Expectations
Thursday 31st May 2012 Page 26
Moving through our first
development project whilst
maintaining significant E & A
portfolio upside potential.
Management Team
Thursday 31st May 2012 Page 27
Mike Azancot – President and Chief Executive Officer
A Petroleum Engineer (Master of Engineering) specialising in
Upstream business optimisation. 30 years of broad experience in the
E&P sector holding senior management positions in International
businesses with Occidental, LASMO and Petrokazakhstan in the North
Sea, China, Indonesia and Kazakhstan.
David Blewden – Chief Financial Officer
A senior financial executive with over twenty five years of international
experience in oil and gas financial management, corporate finance and
energy investment banking. He has held senior financial positions at
PetroSaudi International, African Arabian Petroleum, Yukos Oil
Company and energy investment banking roles at Citigroup, UBS,
Chase Manhattan and Schroders. Mr Blewden holds a BA (Honours)
and MA in Natural Sciences from Cambridge University, England.
John Rapach – Chief Operating Officer
Over twenty-five years of operations experience in both offshore and
onshore environments. He is an industry renowned specialist in the
preparation of reserve assessments, well testing, field development
and performance enhancement.
Annual General & Special Meeting of Shareholders
Thursday, May 31, 2012