annika seiler - ccs - a cost competitive approach for decarbonizing power sector in emerging...
TRANSCRIPT
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
1/17
1
Annika SeilerAsian Development Bank
Manila, 7 June 2012
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
2/17
Content
Why CCS is needed in emerging countries?
Unique challenges for CCS demonstration
Financing CCS Demonstration Need and role
of various support mechanismsADBs support in PRC to enhance CCS
demonstration
Levers enable CCS demonstration projects inpipeline in emerging economies
Conclusions
2
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
3/17
Large capacity addition, especially innext 10 15 years, with highproportion of coal-based plants
Rapidly rising coal consumption haswider implications for the globalclimate change mitigation efforts
CCS is the only near commercialtechnology to decouple CO2emissions into the atmosphere fromlarge single-point sourcesof fossil fuel combustion
Shift of coalconsumption towardsAsia-Pacific Region
3
Need for CCS in emerging economies
Global Coal Consumption,Mtce
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
4/17
IEA (2012): 72% of 1Gt ofincremental CO2emissions globally in2011 originated from the
PRC.
Without strong supportfor investments in energyefficiency and renewableenergy over 11th FYP,
20062010, PRCs CO2emissions would haveexceeded 1.5Gt from coalcombustion in powersector and industries.
Each GW of coal fired power generation withCCS avoids more CO2 than avoided by 1GW eachof solar and wind plants combined.
4
RE is not sufficient CCS is needed
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
5/17
CCS is not astrategic
choice ofpolicy makers
Lack ofexperiences inplanning, constructing andoperatingpower plants
with CCS
Limitedtechnicalreadiness ofasset base
Higher additionalCAPEX, OPEX &auxiliaryconsumptions
Insufficient public
and concessionalfinancing, no fiscalor financial supportmechanism
Limitedpublicawareness
ADB (2011): key barriers toCCS are amplified in
developing countries.
5
Key Issues and Barriers
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
6/17
Coal-fired power plantprojects with CCS havehigher CAPEX + OPEX
Using captured CO2 forEOR could allow foradditional revenue andenhance viability ofprojects
But ..
BaseCost
24%
200
400
600
800
01/10/2010
400 MW IGCC
BaseCost
65%
01/10/2010
600 MW SC
Cost-$million
30
60
90
120
ElectricityTariff$/MWh
51
90
73
112
With CCS
Without CCS
53%
80%
Benchmark tariff for coal-fired power plantswithout CCS are applied to those with CCS
which make them financially unviable atthe existing tariff. 6
Impact of Higher Capital Cost and Energy Penalty
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
7/17
Additional capitalcost and energypenalty could be
compensated
Concessionalfinancing could bringwith CCS down so
that it would requireonly a tariff mark-upof 20%.
CCS demonstration will requireinternational support in developingcountries
7
Importance of Concessional Financing and Fiscaland Financial Support Measures
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
8/17
with CCS power is
competitive with otherlow-carbon
technologies
The tariff should bebenchmarked againstthe levelized cost ofelectricity of a cleankWh
Electricity Tariff and Capital Cost Comparison in PRC
0.05
0.19 $/kWh
0.09 $/kWh
0.11 $/kWh
0.08 $/kWh
0
0.5
1
1.5
2
2.5
3
3.5
Wind IGCC + CCS SC+CCS Solar Std Coal
Cost($million/MW)
0
0.05
0.1
0.15
0.2
Tariff($/kWh)
Cost ($M/MW) Std Coal tariff (ct $/kWh)
Comparing a coal-fired with CCS to awithout CCS plant neglects environ-
mental impacts of coal-fired powerplants without CCS8
Comparison of levelized cost of electricity
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
9/17
Feed-in tariff
Tax rebates
Operationsubsidies
CDM
Quota obligations
Green pricing
Consumersubsidies
Fiscal measures
Investment grants
Concessionalfinancing
Sovereignguarantees
Exemption onimport duties
Quota obligations
Concessional financingis essential to facilitateearly stage
demonstration projects
Capital investmentsupport measuresneed to becomplemented with anappropriate mix ofsupply side operationoriented support as wellas demand sidestimulus measures
.
9
Financing CCS Demonstration - Role of varioussupport mechanisms
Capital investment oriented
Operation oriented
Supplyside
Demandside
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
10/17
ADB submitted a reportto CSLF on financingCCS in emerging
economiesKey recommendation -set up $5 billion CCSdedicated fund fordeveloping countries to
supportstorage characterization
FEED studies
incremental CapEx andOpEx.
.
10
Financing CCS in Developing Countries ADBReport (TA 7278-REG)
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
11/17Realized demonstration projects
Levers to enable CCS Demonstration Projects inPipeline in Emerging Economies
11
Government Commitment, incl.policy targets, regulatory, fiscal,
and financial support measures
Awareness and support from civil
society
Higher upfront development costs, capital
investment cost, and auxiliary consumption
Concessional financing and adequate
business models for early stage
demonstration projects
Demonstration projects in
identification stage
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
12/17
Pre-combustiontechnology:
Financial and technical assistance toChina Huaneng Group to study thetechnology, build and operate anIntegrated Gasification Combined Cycle
power plant with a carbon capture,utilization and storage plant
Post-combustion
technology:
Capacitystrengthening ofDatang
International toassess, pilot-test,and apply post-combustionmethod in gas-firedpower plant and toestablish CCS-
ready criteria powerplants
Oxyfuel-combustiontechnology:
Assisting Dongfang BoilerCo. to assess feasibility andestablish technical standardsfor a 100MW demonstrationcoal-fired power plant
.
12
ADB approach to support CCS in PRC (1/3)Upstream analysis and pilot testing of available technologies for energycompanies and dissemination of lessons learnt:
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
13/17
Policy&r
egulatory
framework:ADB is working
with the NationalDevelopment andReformCommission toformulate acomprehensiveroadmap, policy,and regulations toenable CCS
demonstration anddeployment
BusinessModels: ADB in
consultation with
major oil, gas, coalmining, and powerindustries seeks toidentify andfacilitate jointventures for early
stagedemonstrationprojects
Kn
owledgetransfer: ADB organizes
internationalconferences or sitevisits for PRCstakeholders tofacilitateknowledge sharing
and exchange ongood practices inCCS development
13
ADB approach to support CCS in PRC (2/3)Establishing an Enabling Environment for CCS Demonstration:
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
14/17
ADB is administering an dedicated multi-donor trust fundestablished with an initial contribution from the Global CCSInstitute of A$21 million for capacity development and financing of
demonstration projects
Dedicated fund:
Co-financing of Tianjin Integrated Gasification Combined Cyclepower plant $135 million loan and $5 million grant
Assessing $10 million grant assistance to carbon capture,
utilization and storage small-scale demonstration plant
Financing of demonstration projects:
CCS partnership with the CCI, stakeholder in the CSLF, Member -Global CCS Institute
Participation in Action Group to identify and establish a CCS
financing mechanism in developing countries
International Networking:
14
ADB approach to support CCS in PRC (3/3)Mobilizing funding and financing of demonstration projects :
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
15/17
CCS technologiesface uniquechallenges
Compelling reasonsto fast track CCSdemonstration indeveloping countries
MDBs have a criticalrole to play incapacity developmentand creating enablingenvironment
Unlike other low-carbon technologies, there isweak policy support for CCS technologies.
Surging demand for fossil fuel butunsatisfactory progress on CCS in developingcountries demands early CCS demonstrationto benefit from locking-in low carbondevelopment
Without a targeted CCS Fund to substantiallymitigate higher CAPEX and operationalsupply-sde support to compensate higherOPEX, the CCS demonstration
at-scale will be difficult15
Conclusions
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
16/17
Compelling reasons tofast track CCSdemonstration in
developing countries
MDBs like ADB areready to support PRC
and other developingcountries
PRC has a critical role to play in CCSdemonstration and deployment
China is swing country for determining the
speed of CCS demonstration and deployment
Pilot CCS activities have laid the groundworkfor near-term CCS demonstrations (by 2015)if right funding and policy supports areavailable in time
Conclusions
-
7/31/2019 Annika Seiler - CCS - A Cost Competitive Approach for Decarbonizing Power Sector in Emerging Economies of Asia
17/17
For further information and comments please contact:
Ashok Bhargava, Director East Asia Energy Division (EAEN)[email protected]
Annika Seiler, Finance Specialist (Energy) [email protected]
17