    Angkor Bio CogenRice Husk Power Project

    Adisorn ChieuProject Manager

    Angkor Bio Cogen Co., Ltd.

  • 8/4/2019 Angkor Bio Cogen Project

    2/17

    Project Details

    2 MW. Power plant

    Generate electricity

    using rice husk thatproduced from arice mill and sellthe power back tothe mill.

  • 8/4/2019 Angkor Bio Cogen Project

    3/17

    CDM activity (1)

    The Project will avoid methane emissions that would be produced from rice husk leftto decay in the absence of the Project.

  • 8/4/2019 Angkor Bio Cogen Project

    4/17

    CDM activity (2)

    The Project also displace the use of diesel oil for power generation at the rice mill.

  • 8/4/2019 Angkor Bio Cogen Project

    5/17

    Location

  • 8/4/2019 Angkor Bio Cogen Project

    6/17

    Rice Husk Storage Area

    Power Plant Area

  • 8/4/2019 Angkor Bio Cogen Project

    7/17

    CDM details

    The annual amount of emission reductions

    Baseline emission 55,349 tCO2

    -Project Emission Emission Reduction 3,729 tCO2

    Total 51,620 tCO2

  • 8/4/2019 Angkor Bio Cogen Project

    8/17

    Status and Challenges Video clip of the construction from the start to now.

  • 8/4/2019 Angkor Bio Cogen Project

    9/17

    Main features of the project

    The first time in the world using the TORBED technology to burn the rice husk.

    As a result, a complete burning of the husk will turn them into amorphous silica.

  • 8/4/2019 Angkor Bio Cogen Project

    10/17

    Result finding from a lab test shows that the ash is 100% amorphous.

  • 8/4/2019 Angkor Bio Cogen Project

    11/17

    Note:crystallite ash is usually produced by other typical rice husk reactors

    used in the region. Crystallite ash could cause lung problem among the workers.

  • 8/4/2019 Angkor Bio Cogen Project

    12/17

    Amorphous silica ash is also an important ingredient toproduce high strength concrete.

  • 8/4/2019 Angkor Bio Cogen Project

    13/17

    Challenges

    The challenges of the project is the time to build this thing, which expect atthe beginning that it would take only 24 months maximum, and the crediting

    period would start in 2008.

    The 3 years delay, make the project loss a lot of opportunities not only on theCDM but also chance to utilize cheaper power for the rice mill.

    Reasons

    - This is the first of its kind to apply this technology in the world andalso in Cambodia. . The project is somehow a prototype.

    - lacking supply / equipment in the country.

    - lacking skilled workforce in the country.

    - transportation issue country infrastructure.

  • 8/4/2019 Angkor Bio Cogen Project

    14/17

    Merits

    Technological breakthrough

    Indirect benefits goes to the rice industry in Cambodia which at the momenthas higher operating costs than other neighboring countries (e.g. Thailand,Vietnam)

  • 8/4/2019 Angkor Bio Cogen Project

    15/17

    Comparison among 3 countries

    Population 14 millionPaddy production 8.0 million tonsWhite rice export 0.3 million tonsPaddy export 3.0 million tons

    Population 63 million

    Paddy production 30.9 million tonsWhite rice export 8.0 million tonsPaddy export - million tons

    Population 83 millionPaddy production 35.8 million tonsWhite rice export 6.0 million tonsPaddy export - million tons

  • 8/4/2019 Angkor Bio Cogen Project

    16/17

    Recommendations on CDM rules

    1. Flexibility of the verification

    since a plant might have some minor details different from itsoriginal PDD.

    2. More flexibility on start of the crediting period (e.g. allowing tochange the start of the crediting period more than one time)

    a project might face unforeseen difficulties from the delay ofconstruction or commissioning.

  • 8/4/2019 Angkor Bio Cogen Project

    17/17

    End

    Presented by Adisorn Chieu

    [email protected]

    Tel: +855-99-238282