Activity ID Activity Name OriginalDuration
Start Finish
CC-05 STRUCTURAL, MECHANICAL & PIPING - DRY AREACC-05 STRUCTURAL, MECHANICAL & PIPING - DRY AREA 634 26-Mar-12 A 19-Dec-13
MILESTONE - CONTRACTMILESTONE - CONTRACT 634 26-Mar-12 A 19-Dec-13
GeneralGeneral 634 26-Mar-12 A 19-Dec-13
MCCC05 00030Notice of award 0 26-Mar-12 A
MCCC05 00060Autorización de inicio 0 09-Apr-12 A
MCCC05 000100Lodging Facilities available 0 02-May-12 A
MCCC05 000110Catering services available 0 02-May-12 A
MCCC05 00010Start Construction 0 21-May-12 A
MCCC05 000170Area 200 Complete Erection of Primary Crusher 200-CR-001 0 05-Sep-12*
MCCC05 000210Area 210 Pebble Crusher 0 05-Jun-13*
MCCC05 000200Area 205 Reclaim Tunnel 0 17-Aug-13*
MCCC05 00020Construction Completed 0 19-Dec-13*
MCCC05 000180Area 200 All Construction Complete Primary Crusher Building 0 19-Dec-13*
MCCC05 000190Area 200 Complete Overland Conveyor 200-CV-03 0 19-Dec-13
Area 200 Primary CrushingArea 200 Primary Crushing 139 22-Jun-12 A 30-Nov-12
MCCC05 00040Shared Access to Primary Crushing Building (Nivel 1 y 2) 0 22-Jun-12 A
MCCC05 000140Retiro de Torre Grúa que interfiere con Montaje (Por Jacobs) 0 26-Jul-12 A
MCCC05 000120Shared Access to Primary Crushing Building (Nivel 3) 0 10-Aug-12 A
MCCC05 00050Shared Access to Primary Crushing Building Completed 0 15-Aug-12 A
MCCC05 000130Reinforced Earth for Primary Crushing Completed 0 30-Nov-12*
Area 200 Overland ConveyorArea 200 Overland Conveyor 225 21-May-12 A 01-Jan-13
MCCC05 00070Start Installation of Precast Sleepers (5.2 km.) 0 21-May-12 A
MCCC05 00080Availability of Overland Conveyor Area from km 0+000 @ 1+500 0 21-May-12 A
MCCC05 00150Availability of Overland Conveyor Area from km 3+700 @ 4+200 0 12-Sep-12*
MCCC05 00160Availability of Overland Conveyor Area from km 1+800 @ 2+400 0 13-Sep-12*
MCCC05 000150Re-ingreso a overland Area from 0+000 @ 1+500 0 20-Sep-12*
MCCC05 000160Availability of Overland Conveyor Area from km 1+500 @ 1+800 0 15-Oct-12*
MCCC05 00190Availability of Overland Conveyor Area from km 2+400 @ 3+700 0 30-Nov-12*
MCCC05 00090Availability of Overland Conveyor Area from km 4+200 @ 5+065 0 01-Jan-13*
Area 205 Coarse Ore Storage & ReclaimArea 205 Coarse Ore Storage & Reclaim 0 05-Sep-12 05-Sep-12
MCCC05 00110Availability of Coarse Ore Tunnel #1 - North Reclaimer Tunnel 0 05-Sep-12*
Area 210 Grinding CircuitArea 210 Grinding Circuit 0 15-Nov-12 15-Nov-12
MCCC05 00120Availability of Grinding Circuit 0 15-Nov-12*
Area 400 General On Site FacilitiesArea 400 General On Site Facilities 0 24-Jan-13 24-Jan-13
A8120 Availability of General On Site Facilities 0 24-Jan-13
Area 800 Water Supply & StorageArea 800 Water Supply & Storage 0 01-Dec-12 01-Dec-12
MCCC05 001301Availability of Water Supply & Storage 0 01-Dec-12*
Area 262 Water ManagementArea 262 Water Management 0 01-Feb-13 01-Feb-13
A8160 Availability of Water Management 0 01-Feb-13*
MILESTONE - ENGINEERING (BY JACOBS)MILESTONE - ENGINEERING (BY JACOBS) 267 09-Apr-12 A 01-Jan-13
Area 200 Primary CrushingArea 200 Primary Crushing 0 01-May-12 A 01-May-12 A
A1000 Submission Engineering (Approved for Construction) 0 01-May-12 A
Area 200 Overland ConveyorArea 200 Overland Conveyor 149 09-Apr-12 A 05-Sep-12
A1010 Submission Engineering - Area from km 0+000 @ 2+970 (Approved for Construction) 0 09-Apr-12 A
A1070 Submission Engineering - Area from km 2+970 @ 3+500 (Approved for Construction) 0 05-Sep-12*
A1160 Submission Engineering - Area from km 3+500 @ 5+065 (Approved for Construction) 0 05-Sep-12*
Area 205 Coarse Ore Storage & ReclaimArea 205 Coarse Ore Storage & Reclaim 0 05-Sep-12 05-Sep-12
A1020 Submission Engineering (Approved for Construction) 0 05-Sep-12*
Area 210 Grinding CircuitArea 210 Grinding Circuit 0 16-Oct-12 16-Oct-12
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
19-Dec-13, CC-05 STRUCTURAL, MECHANICAL & PIPING - DRY AREA
19-Dec-13, MILESTONE - CONTRACT
19-Dec-13, General
Notice of award
Autorización de inicio
Lodging Facilities available
Catering services available
Start Construction
Area 200 Complete Erection of Primary Crusher 200-CR-001
Area 210 Pebble Crusher
Area 205 Reclaim Tunnel
Construction Completed
Area 200 All Construction Complete Primary Crusher Building
Area 200 Complete Overland Conveyor 200-CV-03
30-Nov-12, Area 200 Primary Crushing
Shared Access to Primary Crushing Building (Nivel 1 y 2)
Retiro de Torre Grúa que interfiere con Montaje (Por Jacobs)
Shared Access to Primary Crushing Building (Nivel 3)
Shared Access to Primary Crushing Building Completed
Reinforced Earth for Primary Crushing Completed
01-Jan-13, Area 200 Overland Conveyor
Start Installation of Precast Sleepers (5.2 km.)
Availability of Overland Conveyor Area from km 0+000 @ 1+500
Availability of Overland Conveyor Area from km 3+700 @ 4+200
Availability of Overland Conveyor Area from km 1+800 @ 2+400
Re-ingreso a overland Area from 0+000 @ 1+500
Availability of Overland Conveyor Area from km 1+500 @ 1+800
Availability of Overland Conveyor Area from km 2+400 @ 3+700
Availability of Overland Conveyor Area from km 4+200 @ 5+065
05-Sep-12, Area 205 Coarse Ore Storage & Reclaim
Availability of Coarse Ore Tunnel #1 - North Reclaimer Tunnel
15-Nov-12, Area 210 Grinding Circuit
Availability of Grinding Circuit
24-Jan-13, Area 400 General On Site Facilities
Availability of General On Site Facilities
01-Dec-12, Area 800 Water Supply & Storage
Availability of Water Supply & Storage
01-Feb-13, Area 262 Water Management
Availability of Water Management
01-Jan-13, MILESTONE - ENGINEERING (BY JACOBS)
01-May-12 A, Area 200 Primary Crushing
Submission Engineering (Approved for Construction)
05-Sep-12, Area 200 Overland Conveyor
Submission Engineering - Area from km 0+000 @ 2+970 (Approved for Construction)
Submission Engineering - Area from km 2+970 @ 3+500 (Approved for Construction)
Submission Engineering - Area from km 3+500 @ 5+065 (Approved for Construction)
05-Sep-12, Area 205 Coarse Ore Storage & Reclaim
Submission Engineering (Approved for Construction)
16-Oct-12, Area 210 Grinding Circuit
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 1 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A1030 Submission Engineering (Approved for Construction) Area 210 0 16-Oct-12
Area 400 General On Site FacilitiesArea 400 General On Site Facilities 0 01-Jan-13 01-Jan-13
MCCC05 001311Submission Engineering (Approved for Construction) Area 400 0 01-Jan-13
Area 800 Water Supply & StorageArea 800 Water Supply & Storage 0 08-Nov-12 08-Nov-12
A1050 Submission Engineering (Approved for Construction) Area 800 0 08-Nov-12
MILESTONE - SUPPLY (BY JACOBS)MILESTONE - SUPPLY (BY JACOBS) 353 21-May-12 A 25-Apr-13
Area 200 Primary CrushingArea 200 Primary Crushing 239 08-Aug-12 A 25-Apr-13
A1230 Primary Crusher 200-CR-01 0 08-Aug-12 A
A1610 Estructural Steel 0 22-Aug-12 A
A1240 Jib Crane 200-CN-001 0 05-Sep-12*
A1250 Rock Breaker 200-RB-01 0 05-Sep-12*
A1260 Hoist Monorail 200-HS-001/002/003/004/005 0 05-Sep-12*
A1280 Dust Collector 200-FA-001 0 05-Sep-12*
A1290 Baghouse 200-DC-001 0 05-Sep-12*
A1310 Submersible Pump 200-PP-001 0 05-Sep-12*
A1340 Metal Detector 200-MD-001 0 05-Sep-12*
A1830 Eccentric Car Maintenance 0 05-Sep-12*
A1440 Monorrieles para instalación de Hoist 0 15-Oct-12*
A1710 Monorriel del carro excéntrico 0 18-Oct-12*
A1630 Entrega de Estructuras de 200-BL-003 0 01-Nov-12*
A1640 Entrega de Estructuras de 200-BL-004 0 01-Nov-12*
A1300 Conveyor 200-CV-001 0 01-Nov-12*
A1270 Apron Feeder 200-FE-001 0 25-Apr-13*
Area 200 Overland ConveyorArea 200 Overland Conveyor 207 21-May-12 A 30-Nov-12
A1600 Precast Sleepers 200-CV-003 0 21-May-12 A
A1330 Structural steel and conveyor idlers 200-CV-003 Area from km 0+000 @ 2+970 0 04-Jun-12 A
A1570 Overland Conveyor 200-CV-003 Area from km 0+000 @ 2+970 0 15-Jul-12 A
A1580 Structural steel and conveyor idlers 200-CV-003 Area from km 3+500 @ 5+065 0 05-Sep-12*
A1590 Overland Conveyor 200-CV-003 Area from km 3+500 @ 5+065 0 01-Oct-12*
A1550 Overland Conveyor 200-CV-003 Area from km 2+970 @ 3+500 0 15-Oct-12*
A1320 Structural steel and conveyor idlers 200-CV-002 0 30-Nov-12*
Area 205 Coarse Ore Storage & ReclaimArea 205 Coarse Ore Storage & Reclaim 131 15-Dec-12 25-Apr-13
A1620 Entrega de Estructuras metálicas 205 0 15-Dec-12*
A1390 Dust Supression System 205-DN-001 0 25-Feb-13*
A1400 Dust Supression System 205-DN-002 0 25-Feb-13*
A1410 Dust Supression System 205-DN-003 0 25-Feb-13*
A1420 Dust Supression System 205-DN-004 0 25-Feb-13*
A1430 Submersible Pump 205-PP-011 0 25-Feb-13*
A1350 Apron Feeder 205-FE-001 0 25-Apr-13*
A1360 Apron Feeder 205-FE-002 0 25-Apr-13*
A1370 Apron Feeder 205-FE-003 0 25-Apr-13*
A1380 Apron Feeder 205-FE-004 0 25-Apr-13*
Area 210 Grinding CircuitArea 210 Grinding Circuit 178 15-Oct-12 11-Apr-13
A1460 Suministro de Conveyor 210-CV-001 0 15-Oct-12*
A1450 Suministro de Estructuras Metalicas Area 210 0 15-Nov-12*
A1490 Suministro de Pebble Crusher 210-CR-002 0 09-Dec-12
A1960 Suministro de Piping Area 210 0 17-Jan-13*
A1470 Suministro de Conveyor 210-CV-006 0 27-Jan-13
A1850 Suministro de Belt Feeder 210-FE-001/002 0 13-Feb-13
A1480 Suministro de Pebble Crusher 210-CR-001 0 23-Feb-13
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
Submission Engineering (Approved for Construction) Area 210
01-Jan-13, Area 400 General On Site Facilities
Submission Engineering (Approved for Construction) Area 400
08-Nov-12, Area 800 Water Supply & Storage
Submission Engineering (Approved for Construction) Area 800
25-Apr-13, MILESTONE - SUPPLY (BY JACOBS)
25-Apr-13, Area 200 Primary Crushing
Primary Crusher 200-CR-01
Estructural Steel
Jib Crane 200-CN-001
Rock Breaker 200-RB-01
Hoist Monorail 200-HS-001/002/003/004/005
Dust Collector 200-FA-001
Baghouse 200-DC-001
Submersible Pump 200-PP-001
Metal Detector 200-MD-001
Eccentric Car Maintenance
Monorrieles para instalación de Hoist
Monorriel del carro excéntrico
Entrega de Estructuras de 200-BL-003
Entrega de Estructuras de 200-BL-004
Conveyor 200-CV-001
Apron Feeder 200-FE-001
30-Nov-12, Area 200 Overland Conveyor
Precast Sleepers 200-CV-003
Structural steel and conveyor idlers 200-CV-003 Area from km 0+000 @ 2+970
Overland Conveyor 200-CV-003 Area from km 0+000 @ 2+970
Structural steel and conveyor idlers 200-CV-003 Area from km 3+500 @ 5+065
Overland Conveyor 200-CV-003 Area from km 3+500 @ 5+065
Overland Conveyor 200-CV-003 Area from km 2+970 @ 3+500
Structural steel and conveyor idlers 200-CV-002
25-Apr-13, Area 205 Coarse Ore Storage & Reclaim
Entrega de Estructuras metálicas 205
Dust Supression System 205-DN-001
Dust Supression System 205-DN-002
Dust Supression System 205-DN-003
Dust Supression System 205-DN-004
Submersible Pump 205-PP-011
Apron Feeder 205-FE-001
Apron Feeder 205-FE-002
Apron Feeder 205-FE-003
Apron Feeder 205-FE-004
11-Apr-13, Area 210 Grinding Circuit
Suministro de Conveyor 210-CV-001
Suministro de Estructuras Metalicas Area 210
Suministro de Pebble Crusher 210-CR-002
Suministro de Piping Area 210
Suministro de Conveyor 210-CV-006
Suministro de Belt Feeder 210-FE-001/002
Suministro de Pebble Crusher 210-CR-001
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 2 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A1500 Suministro de Feed Bin 210-BN-002 0 09-Mar-13
A1950 Suministro de Equipos Miscelaneos Area 210 0 11-Apr-13
Area 400 General On Site FacilitiesArea 400 General On Site Facilities 0 16-Jan-13 16-Jan-13
A8130 Suministro de Estructuras Metalicas Area 400 0 16-Jan-13*
A8140 Suministro 400-PP-011 Bomba Sumidero 0 16-Jan-13
A8150 Suministro de Piping Area 400 0 16-Jan-13
Area 800 Water Supply & StorageArea 800 Water Supply & Storage 47 08-Dec-12 24-Jan-13
A1510 Suministro de Tanque 800-TK-101 0 08-Dec-12
A1560 Suministro de Equipos Misceláneos Area 800 0 15-Dec-12*
A1520 Suministro de Tanque 800-TK-105 0 15-Dec-12*
A1530 Suministro de Tanque 800-TK-110 0 15-Dec-12*
A1540 Suministro de Tratamiento de Agua Package 800-WT-01 0 15-Dec-12*
A1840 Suministro de Piping Area 800 0 24-Jan-13
SITE FACILITIESSITE FACILITIES 634 02-May-12 A 19-Dec-13
SFCC05 00010Staff Movilization 42 02-May-12 A 08-Jun-12 A
SFCC05 00020Office Building 45 11-May-12 A 23-Aug-12 A
SFCC05 00030Start Desmovilization 0 19-Dec-13
CONSTRUCTION WORKSCONSTRUCTION WORKS 506 21-May-12 A 19-Dec-13
Area 200 Primary CrushingArea 200 Primary Crushing 382 03-Aug-12 A 17-Aug-13
Primary Crushing BuildingPrimary Crushing Building 382 03-Aug-12 A 17-Aug-13
Structural Steel WorksStructural Steel Works 111 05-Sep-12 24-Dec-12
Torre de Escaleras del Edificio de ChancadoTorre de Escaleras del Edificio de Chancado 96 05-Sep-12 09-Dec-12
A5565 Stair Tower1 35 05-Sep-12 09-Oct-12
A5570 Stair Tower2 30 30-Sep-12 29-Oct-12
A5520 Lower Stair 10 10-Oct-12 19-Oct-12
A5530 Misc Plataform 12 20-Oct-12 31-Oct-12
A5510 Excentric Removal Car Access 12 30-Oct-12 10-Nov-12
A5560 Plataf. removibles 12 01-Nov-12 12-Nov-12
A5515 Handrail 15 13-Nov-12 27-Nov-12
A5500 Bobcat Access Door to Surge Bin 12 28-Nov-12 09-Dec-12
MonorrielesMonorrieles 27 04-Nov-12 30-Nov-12
A5535 Monorail El.+ 4688.12 5 04-Nov-12 08-Nov-12
A5540 Monorail El.+ 4694.22 7 09-Nov-12 15-Nov-12
A5545 Monorail El.+ 4698.667 3 16-Nov-12 18-Nov-12
A5550 Monorail El.+ 4704.627 7 19-Nov-12 25-Nov-12
A5555 Monorail El.+ 4710.800 5 26-Nov-12 30-Nov-12
MiscelaneosMiscelaneos 36 19-Nov-12 24-Dec-12
A5505 Control Room 200-BL-011 Support 10 19-Nov-12 28-Nov-12
A5580 Pipe Rack 200-PB-001 12 28-Nov-12 09-Dec-12
A5525 Main Shaft Platform 15 10-Dec-12 24-Dec-12
Mechanical WorksMechanical Works 382 03-Aug-12 A 17-Aug-13
Concentrator Primary Crushing 200-CR-01Concentrator Primary Crushing 200-CR-01 199 20-Aug-12 A 03-Mar-13
Trabajos PreliminaresTrabajos Preliminares 196 20-Aug-12 A 03-Mar-13
A5800 200-CR-001 Primary Crusher 196 20-Aug-12 A 03-Mar-13
MiscelaneosMiscelaneos 28 13-Jan-13 09-Feb-13
A5015 200-ZM-011 Primary crusher shaft seal 4 13-Jan-13 16-Jan-13
A5010 200-ZM-010 Primary crusher eccentric removal motorized cart 20 17-Jan-13 05-Feb-13
A5020 200-ZM-012 Primary crusher spider seal 4 06-Feb-13 09-Feb-13
Sistema Hidráulico y de LubricaciónSistema Hidráulico y de Lubricación 164 05-Sep-12 15-Feb-13
A5045 200-LU-001 Primary crusher lubrication system 10 05-Sep-12 14-Sep-12
A5040 200-HU-001 Primary crusher hydroset system 8 13-Sep-12 20-Sep-12
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
Suministro de Feed Bin 210-BN-002
Suministro de Equipos Miscelaneos Area 210
16-Jan-13, Area 400 General On Site Facilities
Suministro de Estructuras Metalicas Area 400
Suministro 400-PP-011 Bomba Sumidero
Suministro de Piping Area 400
24-Jan-13, Area 800 Water Supply & Storage
Suministro de Tanque 800-TK-101
Suministro de Equipos Misceláneos Area 800
Suministro de Tanque 800-TK-105
Suministro de Tanque 800-TK-110
Suministro de Tratamiento de Agua Package 800-WT-01
Suministro de Piping Area 800
19-Dec-13, SITE FACILITIES
Staff Movilization
Office Building
Start Desmovilization
19-Dec-13, CONSTRUCTION WORKS
17-Aug-13, Area 200 Primary Crushing
17-Aug-13, Primary Crushing Building
24-Dec-12, Structural Steel Works
09-Dec-12, Torre de Escaleras del Edificio de Chancado
Stair Tower1
Stair Tower2
Lower Stair
Misc Plataform
Excentric Removal Car Access
Plataf. removibles
Handrail
Bobcat Access Door to Surge Bin
30-Nov-12, Monorrieles
Monorail El.+ 4688.12
Monorail El.+ 4694.22
Monorail El.+ 4698.667
Monorail El.+ 4704.627
Monorail El.+ 4710.800
24-Dec-12, Miscelaneos
Control Room 200-BL-011 Support
Pipe Rack 200-PB-001
Main Shaft Platform
17-Aug-13, Mechanical Works
03-Mar-13, Concentrator Primary Crushing 200-CR-01
03-Mar-13, Trabajos Preliminares
200-CR-001 Primary Crusher
09-Feb-13, Miscelaneos
200-ZM-011 Primary crusher shaft seal
200-ZM-010 Primary crusher eccentric removal motorized cart
200-ZM-012 Primary crusher spider seal
15-Feb-13, Sistema Hidráulico y de Lubricación
200-LU-001 Primary crusher lubrication system
200-HU-001 Primary crusher hydroset system
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 3 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A5025 200-CK-001/002 Primary crusher lubrication system air coolers 10 21-Sep-12 30-Sep-12
A5030 200-FA-002 Primary crusher lubrication room ventilation fan 6 17-Jan-13 22-Jan-13
A5050 200-LU-003 Primary crusher spider bushing lubrication system 10 23-Jan-13 01-Feb-13
A5035 200-GB-001 Primary crusher dust seal air blower 8 02-Feb-13 09-Feb-13
A5055 200-VL-001 Hydraulic assembly mantle relief valve 6 10-Feb-13 15-Feb-13
Instalación de ChutesInstalación de Chutes 155 23-Aug-12 A 06-Feb-13
A5180 200-CH-007 Apron feeder dribble chute 6 23-Aug-12 A 28-Aug-12 A
A5310 200-CH-001 Primary crusher discharge chute 6 25-Aug-12 A 30-Aug-12 A
A5315 200-CH-002 Surge bin discharge chute 6 27-Aug-12 A 01-Sep-12 A
A5305 200-BN-003 Primary crusher surge bin 10 13-Jan-13 22-Jan-13
A5300 200-BN-001 Dump hopper 15 23-Jan-13 06-Feb-13
Apron FeederApron Feeder 79 25-Apr-13 12-Jul-13
A5185 200-FE-001 Primary crusher discharge apron feeder 30 25-Apr-13 24-May-13
A5160 200-CH-003 Apron feeder feed chute 25 25-May-13 18-Jun-13
A5190 200-LU-002 Primary crusher discharge apron feeder lubrication system 20 25-May-13 13-Jun-13
A5165 200-CH-004 Apron feeder skirtboard 12 19-Jun-13 30-Jun-13
A5175 200-CH-006 Apron feeder lower chute 12 19-Jun-13 30-Jun-13
A5170 200-CH-005 Apron feeder discharge chute 12 01-Jul-13 12-Jul-13
Hydraulic Power PackHydraulic Power Pack 51 14-Jun-13 03-Aug-13
A5060 200-HP-002 Primary crusher discharge apron feeder hydraulic power unit 10 14-Jun-13 23-Jun-13
A5065 200-HP-004 Primary crusher discharge apron feeder hydraulic power unit 10 24-Jun-13 03-Jul-13
A5070 200-HT-001/002 Apron feeder hydraulic power unit heaters 16 04-Jul-13 19-Jul-13
A5075 200-PP-002/003 Apron feeder power unit hydraulic pumps 10 20-Jul-13 29-Jul-13
A5080 200-PP-004/005 Apron feeder power unit hydraulic pumps 10 25-Jul-13 03-Aug-13
HoistHoist 27 02-Dec-12 28-Dec-12
A5195 200-HS-001 Motor maintenance monorail hoist 6 02-Dec-12 07-Dec-12
A5200 200-HS-002 Hydraulic system primary crusher lube room monorail hoist 6 05-Dec-12 10-Dec-12
A5205 200-HS-003 Apron feeder maintenance hoist 6 11-Dec-12 16-Dec-12
A5210 200-HS-004 Conveyor maintenance hoist 6 14-Dec-12 19-Dec-12
A5215 200-HS-005 Tramp iron magnet trolley 6 17-Dec-12 22-Dec-12
A5220 200-HS-006 Spider lubricant drum maintenance hoist 6 20-Dec-12 25-Dec-12
A5225 200-HS-007 Motor maintenance manual hoist 6 23-Dec-12 28-Dec-12
Miscelaneos Edificio del ChancadorMiscelaneos Edificio del Chancador 347 03-Aug-12 A 17-Aug-13
A5585 200-ER-005 Electrical Room - Primary Crushing 5 03-Aug-12 A 05-Aug-12 A
A5235 200-EL-001 Manlift elevator 30 09-Nov-12 08-Dec-12
A5575 200-BL-011 Control Room Modular 15 28-Nov-12 12-Dec-12
A5230 200-CN-001 Jib crane 20 04-Mar-13 23-Mar-13
A5255 200-RB-001 Primary crusher rock breaker 20 14-Mar-13 02-Apr-13
A5245 200-HP-003 Jib crane hydraulic power unit 20 14-Mar-13 02-Apr-13
A5240 200-HP-001 Rock breaker hydraulic power unit 20 24-Mar-13 12-Apr-13
A5250 200-LU-004 Rock breaker hydraulic auto lubrication system 10 13-Apr-13 22-Apr-13
A5260 200-ZP-808 Miscellaneous piping 60 19-Jun-13 17-Aug-13
Sistema de Supresión de PolvoSistema de Supresión de Polvo 95 15-May-13 17-Aug-13
A5110 200-BL-002 Crusher area baghouse area 26 15-May-13 09-Jun-13
A5115 200-DC-001 Primary crushing area baghouse 20 10-Jun-13 29-Jun-13
A5130 200-FA-001 Dust collector fan 6 30-Jun-13 05-Jul-13
A5105 200-AL-001 Dust collector rotary air lock 6 06-Jul-13 11-Jul-13
A5125 200-DU-001 Dust collector system ducting 25 12-Jul-13 05-Aug-13
A5120 200-DN-001 Primary crusher dust suppression system 12 06-Aug-13 17-Aug-13
Air Compressor BuildingAir Compressor Building 54 09-Nov-12 01-Jan-13
A5140 200-BL-009 Air compressor building 20 09-Nov-12 28-Nov-12
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
200-CK-001/002 Primary crusher lubrication system air coolers
200-FA-002 Primary crusher lubrication room ventilation fan
200-LU-003 Primary crusher spider bushing lubrication system
200-GB-001 Primary crusher dust seal air blower
200-VL-001 Hydraulic assembly mantle relief valve
06-Feb-13, Instalación de Chutes
200-CH-007 Apron feeder dribble chute
200-CH-001 Primary crusher discharge chute
200-CH-002 Surge bin discharge chute
200-BN-003 Primary crusher surge bin
200-BN-001 Dump hopper
12-Jul-13, Apron Feeder
200-FE-001 Primary crusher discharge apron feeder
200-CH-003 Apron feeder feed chute
200-LU-002 Primary crusher discharge apron feeder lubrication system
200-CH-004 Apron feeder skirtboard
200-CH-006 Apron feeder lower chute
200-CH-005 Apron feeder discharge chute
03-Aug-13, Hydraulic Power Pack
200-HP-002 Primary crusher discharge apron feeder hydraulic power unit
200-HP-004 Primary crusher discharge apron feeder hydraulic power unit
200-HT-001/002 Apron feeder hydraulic power unit heaters
200-PP-002/003 Apron feeder power unit hydraulic pumps
200-PP-004/005 Apron feeder power unit hydraulic pumps
28-Dec-12, Hoist
200-HS-001 Motor maintenance monorail hoist
200-HS-002 Hydraulic system primary crusher lube room monorail hoist
200-HS-003 Apron feeder maintenance hoist
200-HS-004 Conveyor maintenance hoist
200-HS-005 Tramp iron magnet trolley
200-HS-006 Spider lubricant drum maintenance hoist
200-HS-007 Motor maintenance manual hoist
17-Aug-13, Miscelaneos Edificio del Chancador
200-ER-005 Electrical Room - Primary Crushing
200-EL-001 Manlift elevator
200-BL-011 Control Room Modular
200-CN-001 Jib crane
200-RB-001 Primary crusher rock breaker
200-HP-003 Jib crane hydraulic power unit
200-HP-001 Rock breaker hydraulic power unit
200-LU-004 Rock breaker hydraulic auto lubrication system
200-ZP-808 Miscellaneous piping
17-Aug-13, Sistema de Supresión de Polvo
200-BL-002 Crusher area baghouse area
200-DC-001 Primary crushing area baghouse
200-FA-001 Dust collector fan
200-AL-001 Dust collector rotary air lock
200-DU-001 Dust collector system ducting
200-DN-001 Primary crusher dust suppression system
01-Jan-13, Air Compressor Building
200-BL-009 Air compressor building
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 4 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A5150 200-GC-001/002 Primary crushing plant air compressors 12 29-Nov-12 10-Dec-12
A5135 200-AR-001/002 Primary crushing plant air receiver 10 11-Dec-12 20-Dec-12
A5155 200-GD-001 Primary crushing instrument air dryer 6 21-Dec-12 26-Dec-12
A5145 200-FL-001/002 Coalescing air filters 6 27-Dec-12 01-Jan-13
Crushed Ore Transfer Conveyor 200-CV-001Crushed Ore Transfer Conveyor 200-CV-001 100 01-Nov-12 08-Feb-13
A5265 200-CV-001 Crushed ore transfer conveyor 90 01-Nov-12 29-Jan-13
A5270 200-SL-001 Belt scale 10 30-Jan-13 08-Feb-13
Torre de Transferencia #1 200-BL-003Torre de Transferencia #1 200-BL-003 63 01-Nov-12 02-Jan-13
A5275 200-BL-003 Transfer station # 1 20 01-Nov-12 20-Nov-12
A5290 200-MA-001 Self-cleaning electromagnet 15 21-Nov-12 05-Dec-12
A5280 200-BN-002 Trash bin 10 06-Dec-12 15-Dec-12
A5285 200-CH-008 Crushed ore transfer conveyor discharge chute 12 16-Dec-12 27-Dec-12
A5295 200-PP-001 Primary crusher area submersible pump 6 28-Dec-12 02-Jan-13
Torre de Transferencia #2 200-BL-004Torre de Transferencia #2 200-BL-004 52 01-Nov-12 22-Dec-12
A5085 200-BL-004 Transfer station # 2 25 01-Nov-12 25-Nov-12
A5095 200-LU-005/006 Crushed ore inclined conveyor cst drive lubrication systems 15 26-Nov-12 10-Dec-12
A5090 200-CH-009 Crushed ore inclined conveyor discharge chute 7 11-Dec-12 17-Dec-12
A5100 200-MD-001 Crushed ore inclined conveyor metal detector 5 18-Dec-12 22-Dec-12
Piping WorksPiping Works 78 10-Dec-12 25-Feb-13
A5700 Piping Agua fresca 20 10-Dec-12 29-Dec-12
A5710 Piping Aire de Planta 40 30-Dec-12 07-Feb-13
A5705 Piping Aire de Instrumentación 10 08-Feb-13 17-Feb-13
A5720 Piping Relave concentrado 8 18-Feb-13 25-Feb-13
Area 200 ConveyingArea 200 Conveying 471 21-May-12 A 19-Dec-13
Crushed Ore Inclined Conveyor 200-CV-002Crushed Ore Inclined Conveyor 200-CV-002 130 30-Nov-12 08-Apr-13
Mechanical WorksMechanical Works 130 30-Nov-12 08-Apr-13
A5320 200-CV-002 Crushed ore inclined conveyor 130 30-Nov-12 08-Apr-13
Crushed Ore Overland Conveyor 200-CV-003Crushed Ore Overland Conveyor 200-CV-003 471 21-May-12 A 19-Dec-13
Mechanical WorksMechanical Works 471 21-May-12 A 19-Dec-13
Instalación de Tramos de FajaInstalación de Tramos de Faja 471 21-May-12 A 19-Dec-13
200-CV-003 Area from km 0+000 to 1+500200-CV-003 Area from km 0+000 to 1+500 246 21-May-12 A 08-May-13
A1060 Installation Precast Sleepers 120 21-May-12 A 10-Aug-12 A
A1100 Install Crushed Ore Overland Conveyor (frames) 150 19-Jun-12 A 10-Aug-12 A
A1120 Instalación y alineamiento de frames y polines 200 20-Sep-12 07-Apr-13
A1080 Install structural steel and micellaneous 80 18-Feb-13 08-May-13
200-CV-003 Area from km 1+500 to 1+800200-CV-003 Area from km 1+500 to 1+800 200 30-Oct-12 17-May-13
A1650 Installation Precast Sleepers 50 30-Oct-12 18-Dec-12
A1660 Install Crushed Ore Overland Conveyor (frames) 70 09-Mar-13 17-May-13
A1670 Install structural steel and micellaneous 40 08-Apr-13 17-May-13
200-CV-003 Area from km 1+800 to 2+400200-CV-003 Area from km 1+800 to 2+400 235 13-Sep-12 05-May-13
A1090 Installation Precast Sleepers 100 13-Sep-12 21-Dec-12
A1130 Install Crushed Ore Overland Conveyor (frames) 120 22-Nov-12 21-Mar-13
A1110 Install structural steel and micellaneous 60 07-Mar-13 05-May-13
200-CV-003 Area from km 2+400 to 3+700200-CV-003 Area from km 2+400 to 3+700 333 22-Dec-12 19-Nov-13
A1700 Installlation Precast Sleepers 180 22-Dec-12 19-Jun-13
A1690 Install Crushed Ore Overland Conveyor (frames) 210 24-Apr-13 19-Nov-13
A1680 Install structural steel and micellaneous 110 23-Jul-13 09-Nov-13
200-CV-003 Area from km 3+700 to 4+200200-CV-003 Area from km 3+700 to 4+200 70 11-Aug-12 A 24-Oct-12
A1760 Installlation Precast Sleepers 40 11-Aug-12 A 28-Aug-12 A
A1750 Install Crushed Ore Overland Conveyor (frames) 50 13-Aug-12 A 29-Sep-12
A1740 Install structural steel and micellaneous 25 30-Sep-12 24-Oct-12
200-CV-003 Area from km 4+200 to 5+065200-CV-003 Area from km 4+200 to 5+065 303 01-Jan-13 30-Oct-13
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
200-GC-001/002 Primary crushing plant air compressors
200-AR-001/002 Primary crushing plant air receiver
200-GD-001 Primary crushing instrument air dryer
200-FL-001/002 Coalescing air filters
08-Feb-13, Crushed Ore Transfer Conveyor 200-CV-001
200-CV-001 Crushed ore transfer conveyor
200-SL-001 Belt scale
02-Jan-13, Torre de Transferencia #1 200-BL-003
200-BL-003 Transfer station # 1
200-MA-001 Self-cleaning electromagnet
200-BN-002 Trash bin
200-CH-008 Crushed ore transfer conveyor discharge chute
200-PP-001 Primary crusher area submersible pump
22-Dec-12, Torre de Transferencia #2 200-BL-004
200-BL-004 Transfer station # 2
200-LU-005/006 Crushed ore inclined conveyor cst drive lubrication systems
200-CH-009 Crushed ore inclined conveyor discharge chute
200-MD-001 Crushed ore inclined conveyor metal detector
25-Feb-13, Piping Works
Piping Agua fresca
Piping Aire de Planta
Piping Aire de Instrumentación
Piping Relave concentrado
19-Dec-13, Area 200 Conveying
08-Apr-13, Crushed Ore Inclined Conveyor 200-CV-002
08-Apr-13, Mechanical Works
200-CV-002 Crushed ore inclined conveyor
19-Dec-13, Crushed Ore Overland Conveyor 200-CV-003
19-Dec-13, Mechanical Works
19-Dec-13, Instalación de Tramos de Faja
08-May-13, 200-CV-003 Area from km 0+000 to 1+500
Installation Precast Sleepers
Install Crushed Ore Overland Conveyor (frames)
Instalación y alineamiento de frames y polines
Install structural steel and micellaneous
17-May-13, 200-CV-003 Area from km 1+500 to 1+800
Installation Precast Sleepers
Install Crushed Ore Overland Conveyor (frames)
Install structural steel and micellaneous
05-May-13, 200-CV-003 Area from km 1+800 to 2+400
Installation Precast Sleepers
Install Crushed Ore Overland Conveyor (frames)
Install structural steel and micellaneous
19-Nov-13, 200-CV-003 Area from km 2+400 to 3+700
Installlation Precast Sleepers
Install Crushed Ore Overland Conveyor (frames)
Install structural steel and micellaneous
24-Oct-12, 200-CV-003 Area from km 3+700 to 4+200
Installlation Precast Sleepers
Install Crushed Ore Overland Conveyor (frames)
Install structural steel and micellaneous
30-Oct-13, 200-CV-003 Area from km 4+200 to 5+065
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 5 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A1790 Installlation Precast Sleepers 180 01-Jan-13 29-Jun-13
A1780 Install Crushed Ore Overland Conveyor (frames) 230 15-Mar-13 30-Oct-13
A1770 Install structural steel and micellaneous 120 23-Jun-13 20-Oct-13
200-CV-003 Install Splice Belt200-CV-003 Install Splice Belt 120 22-Aug-13 19-Dec-13
A1210 Pull & Install of Splice Belt 200-CV-003 120 22-Aug-13 19-Dec-13
Overland Conveyor Drive Structure 200-BL-005Overland Conveyor Drive Structure 200-BL-005 110 09-Dec-12 28-Mar-13
A5330 200-BL-005 Overland conveyor drive structure 90 09-Dec-12 08-Mar-13
A5335 200-LU-007@010 Crushed ore overland conveyor cst drive lubrication systems 30 27-Feb-13 28-Mar-13
Equipos de Miscelaneos para instalación de fajaEquipos de Miscelaneos para instalación de faja 410 16-Aug-12 A 19-Oct-13
A5595 200-ER-006 Electrical Room - TT #2 5 16-Aug-12 A 19-Aug-12 A
A5605 200-ER-007 Electrical Room - Drive 200-CV-003 5 09-Mar-13 13-Mar-13
A5350 200-WI-001 Belt pulling winch 10 22-Aug-13 31-Aug-13
A5355 200-WI-003 Take-up winch for 200-cv-003 12 27-Aug-13 07-Sep-13
A5360 200-ZM-005@008 Belt installation and handling equipment 24 08-Sep-13 01-Oct-13
A5340 200-HP-005@007 Belt installation and handling equipment hydraulic power packs 20 22-Sep-13 11-Oct-13
A5345 200-HP-008 Portable belt installation and handling equipment hydraulic power pack 18 02-Oct-13 19-Oct-13
Area 205 Coarse Ore Storage Facility Reclaim AreasArea 205 Coarse Ore Storage Facility Reclaim Areas 246 15-Dec-12 17-Aug-13
Discharge Apron FeedersDischarge Apron Feeders 246 15-Dec-12 17-Aug-13
Structural Steel WorksStructural Steel Works 90 15-Dec-12 14-Mar-13
A3005 205-BL-001 Estructuras 90 15-Dec-12 14-Mar-13
Mechanical WorksMechanical Works 218 09-Jan-13 14-Aug-13
Apron Feeder 205-FE-001Apron Feeder 205-FE-001 116 15-Mar-13 08-Jul-13
A3025 205-CH-013 Apron feeder underneath chute 10 15-Mar-13 24-Mar-13
A3030 205-FE-001 Coarse ore stockpile apron feeders 30 25-Apr-13 24-May-13
A3010 205-CH-001 Coarse ore stockpile hopper discharge chutes 15 25-May-13 08-Jun-13
A3035 205-LU-001 Apron feeder lubrication units 12 25-May-13 05-Jun-13
A3015 205-CH-005 Apron feeder reclaim chutes 20 09-Jun-13 28-Jun-13
A3020 205-CH-009 Apron feeders discharge chutes 10 29-Jun-13 08-Jul-13
Apron Feeder 205-FE-002Apron Feeder 205-FE-002 111 25-Mar-13 13-Jul-13
A3055 205-CH-014 Apron feeder underneath chute 10 25-Mar-13 03-Apr-13
A3060 205-FE-002 Coarse ore stockpile apron feeders 30 30-Apr-13 29-May-13
A3040 205-CH-002 Coarse ore stockpile hopper discharge chutes 15 30-May-13 13-Jun-13
A3065 205-LU-002 Apron feeder lubrication units 12 30-May-13 10-Jun-13
A3045 205-CH-006 Apron feeder reclaim chutes 20 14-Jun-13 03-Jul-13
A3050 205-CH-010 Apron feeders discharge chutes 10 04-Jul-13 13-Jul-13
Apron Feeder 205-FE-003Apron Feeder 205-FE-003 103 04-Apr-13 15-Jul-13
A3085 205-CH-015 Apron feeder underneath chute 10 04-Apr-13 13-Apr-13
A3090 205-FE-003 Coarse ore stockpile apron feeders 30 05-May-13 03-Jun-13
A3070 205-CH-003 Coarse ore stockpile hopper discharge chutes 15 04-Jun-13 18-Jun-13
A3095 205-LU-003 Apron feeder lubrication units 12 04-Jun-13 15-Jun-13
A3075 205-CH-007 Apron feeder reclaim chutes 20 16-Jun-13 05-Jul-13
A3080 205-CH-011 Apron feeders discharge chutes 10 06-Jul-13 15-Jul-13
Apron Feeder 205-FE-004Apron Feeder 205-FE-004 98 14-Apr-13 20-Jul-13
A3115 205-CH-016 Apron feeder underneath chute 10 14-Apr-13 23-Apr-13
A3120 205-FE-004 Coarse ore stockpile apron feeders 30 10-May-13 08-Jun-13
A3100 205-CH-004 Coarse ore stockpile hopper discharge chutes 15 09-Jun-13 23-Jun-13
A3125 205-LU-004 Apron feeder lubrication units 12 09-Jun-13 20-Jun-13
A3105 205-CH-008 Apron feeder reclaim chutes 20 21-Jun-13 10-Jul-13
A3110 205-CH-012 Apron feeders discharge chutes 10 11-Jul-13 20-Jul-13
Hydraulic Power PackHydraulic Power Pack 60 16-Jun-13 14-Aug-13
A3130 205-HP-001@004 Apron feeder hydraulic power pack 20 16-Jun-13 05-Jul-13
A3135 205-HP-006 Spile bar machine hydraulic power pack 7 06-Jul-13 12-Jul-13
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
Installlation Precast Sleepers
Install Crushed Ore Overland Conveyor (frames)
Install structural steel and micellaneous
19-Dec-13, 200-CV-003 Install Splice Belt
Pull & Install of Splice Belt 200-CV-003
28-Mar-13, Overland Conveyor Drive Structure 200-BL-005
200-BL-005 Overland conveyor drive structure
200-LU-007@010 Crushed ore overland conveyor cst drive lubrication systems
19-Oct-13, Equipos de Miscelaneos para instalación de faja
200-ER-006 Electrical Room - TT #2
200-ER-007 Electrical Room - Drive 200-CV-003
200-WI-001 Belt pulling winch
200-WI-003 Take-up winch for 200-cv-003
200-ZM-005@008 Belt installation and handling equipment
200-HP-005@007 Belt installation and handling equipment hydraulic power packs
200-HP-008 Portable belt installation and handling equipment hydraulic power pack
17-Aug-13, Area 205 Coarse Ore Storage Facility Reclaim Areas
17-Aug-13, Discharge Apron Feeders
14-Mar-13, Structural Steel Works
205-BL-001 Estructuras
14-Aug-13, Mechanical Works
08-Jul-13, Apron Feeder 205-FE-001
205-CH-013 Apron feeder underneath chute
205-FE-001 Coarse ore stockpile apron feeders
205-CH-001 Coarse ore stockpile hopper discharge chutes
205-LU-001 Apron feeder lubrication units
205-CH-005 Apron feeder reclaim chutes
205-CH-009 Apron feeders discharge chutes
13-Jul-13, Apron Feeder 205-FE-002
205-CH-014 Apron feeder underneath chute
205-FE-002 Coarse ore stockpile apron feeders
205-CH-002 Coarse ore stockpile hopper discharge chutes
205-LU-002 Apron feeder lubrication units
205-CH-006 Apron feeder reclaim chutes
205-CH-010 Apron feeders discharge chutes
15-Jul-13, Apron Feeder 205-FE-003
205-CH-015 Apron feeder underneath chute
205-FE-003 Coarse ore stockpile apron feeders
205-CH-003 Coarse ore stockpile hopper discharge chutes
205-LU-003 Apron feeder lubrication units
205-CH-007 Apron feeder reclaim chutes
205-CH-011 Apron feeders discharge chutes
20-Jul-13, Apron Feeder 205-FE-004
205-CH-016 Apron feeder underneath chute
205-FE-004 Coarse ore stockpile apron feeders
205-CH-004 Coarse ore stockpile hopper discharge chutes
205-LU-004 Apron feeder lubrication units
205-CH-008 Apron feeder reclaim chutes
205-CH-012 Apron feeders discharge chutes
14-Aug-13, Hydraulic Power Pack
205-HP-001@004 Apron feeder hydraulic power pack
205-HP-006 Spile bar machine hydraulic power pack
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 6 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A3140 205-HT-001@004 Apron feeder power pack heaters 6 06-Jul-13 11-Jul-13
A3150 205-HX-001@004 Apron feeder oil cooling water heat exchangers 12 12-Jul-13 23-Jul-13
A3145 205-HT-005 Spile bar machine heater 6 13-Jul-13 18-Jul-13
A3165 205-PP-010 Spile bar machine hydraulic pump 6 19-Jul-13 24-Jul-13
A3155 205-PP-001@004 Apron feeder hydraulic pumps 14 24-Jul-13 06-Aug-13
A3160 205-PP-005@008 Apron feeder hydraulic pumps 8 07-Aug-13 14-Aug-13
Sistema de Supresión de PolvoSistema de Supresión de Polvo 30 16-Jun-13 15-Jul-13
A3170 205-DN-001@004 Coarse ore stockpile dust suppression system 30 16-Jun-13 15-Jul-13
Reclaim TunnelReclaim Tunnel 46 29-Jan-13 15-Mar-13
A3175 205-DU-001 Reclaim tunnel exhaust fan duct system 12 29-Jan-13 09-Feb-13
A3180 205-DU-002 Reclaim tunnel exhaust fan transition duct 12 10-Feb-13 21-Feb-13
A3185 205-DU-003 Reclaim tunnel ventilation ductwork 12 22-Feb-13 05-Mar-13
A3190 205-FA-001 Reclaim tunnel exhaust fan 10 06-Mar-13 15-Mar-13
Monorail hoist, Hidraulic winch and Mobile platafor mMonorail hoist, Hidraulic winch and Mobile platafor m 39 15-Mar-13 22-Apr-13
A3195 205-HS-001/002 Reclaim tunnel monorail hoists 15 15-Mar-13 29-Mar-13
A3200 205-HS-005/006 Spile bar machine monorail hoists 6 30-Mar-13 04-Apr-13
A3205 205-WI-001/002 Spile bar machine hydraulic winch 6 05-Apr-13 10-Apr-13
A3210 205-ZM-003/004 Spile bar machines 6 11-Apr-13 16-Apr-13
A3215 205-ZM-005/006 Spile bar machine mobile platforms 6 17-Apr-13 22-Apr-13
MiscelaneosMiscelaneos 177 09-Jan-13 04-Jul-13
A5615 205-ER-009 Electrical Room 5 09-Jan-13 13-Jan-13
A3220 205-AR-001 Coarse ore stockpile air receiver 7 21-Jun-13 27-Jun-13
A3225 205-PP-011 Reclaim tunnel sump pump 7 28-Jun-13 04-Jul-13
Piping WorksPiping Works 166 05-Mar-13 17-Aug-13
A3320 Piping Agua cruda 40 05-Mar-13 13-Apr-13
A3340 Piping Aire de Planta 50 25-Mar-13 13-May-13
A3370 Piping Suministro de agua de enfriamiento 30 24-Apr-13 23-May-13
A3350 Piping Recuperación de agua de enfriamiento 15 19-May-13 02-Jun-13
A3330 Piping Agua de incendio 20 03-Jun-13 22-Jun-13
A3360 Piping Relave concentrado 20 13-Jun-13 02-Jul-13
A3300 Piping Aceite hidráulico HP 20 14-Jul-13 02-Aug-13
A3310 Piping Aceite hidráulico LP 15 03-Aug-13 17-Aug-13
Area 210 Grinding CircuitArea 210 Grinding Circuit 274 09-Aug-12 A 05-Jun-13
Grinding CircuitGrinding Circuit 274 09-Aug-12 A 05-Jun-13
Structural Steel WorksStructural Steel Works 114 15-Nov-12 08-Mar-13
210-BL-003 Pebble Crusher Structure210-BL-003 Pebble Crusher Structure 114 15-Nov-12 08-Mar-13
A2800 Montaje de Edificio Pebble Cruher 100 15-Nov-12 22-Feb-13
A2820 Montaje de Estructura Pebble Feed Bin 30 04-Jan-13 02-Feb-13
A2810 Montaje de Escaleras de Acceso 35 19-Jan-13 22-Feb-13
A2830 Montaje de Vigas de apoyo de Grúa Pórtico 10 03-Feb-13 12-Feb-13
A2840 Montaje de Estructura Pebble Bin Hooper 12 13-Feb-13 24-Feb-13
A2850 Montaje de Estructura Sag Ball Bin 12 25-Feb-13 08-Mar-13
Mechanical WorksMechanical Works 273 09-Aug-12 A 04-Jun-13
Lime Silo PackageLime Silo Package 102 09-Aug-12 A 15-Dec-12
A2110 210-BN-011 Silo para Cal (Cuerpo) 80 09-Aug-12 A 24-Oct-12
A2100 210-AT-001 Activador del Silo para Cal 5 25-Oct-12 29-Oct-12
A2130 210-DC-001 Filtro de Ventilación del Silo para Cal 8 25-Oct-12 01-Nov-12
A2160 210-GC-001@003 Compresores de desplazamiento positivo para el Silo para Cal 15 25-Oct-12 08-Nov-12
A2140 210-GA-008 Desviador por gravedad del Silo para Cal 15 30-Oct-12 13-Nov-12
A2170 210-LM-001 Silo para Cal (Package) 22 09-Nov-12 30-Nov-12
A2150 210-GA-009/010 Válvula de cuchilla neumática del Silo para Cal 5 14-Nov-12 18-Nov-12
A2180 210-SC-001/002 Alimentadores sin fin del Silo para Cal 15 23-Nov-12 07-Dec-12
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
205-HT-001@004 Apron feeder power pack heaters
205-HX-001@004 Apron feeder oil cooling water heat exchangers
205-HT-005 Spile bar machine heater
205-PP-010 Spile bar machine hydraulic pump
205-PP-001@004 Apron feeder hydraulic pumps
205-PP-005@008 Apron feeder hydraulic pumps
15-Jul-13, Sistema de Supresión de Polvo
205-DN-001@004 Coarse ore stockpile dust suppression system
15-Mar-13, Reclaim Tunnel
205-DU-001 Reclaim tunnel exhaust fan duct system
205-DU-002 Reclaim tunnel exhaust fan transition duct
205-DU-003 Reclaim tunnel ventilation ductwork
205-FA-001 Reclaim tunnel exhaust fan
22-Apr-13, Monorail hoist, Hidraulic winch and Mobile plataform
205-HS-001/002 Reclaim tunnel monorail hoists
205-HS-005/006 Spile bar machine monorail hoists
205-WI-001/002 Spile bar machine hydraulic winch
205-ZM-003/004 Spile bar machines
205-ZM-005/006 Spile bar machine mobile platforms
04-Jul-13, Miscelaneos
205-ER-009 Electrical Room
205-AR-001 Coarse ore stockpile air receiver
205-PP-011 Reclaim tunnel sump pump
17-Aug-13, Piping Works
Piping Agua cruda
Piping Aire de Planta
Piping Suministro de agua de enfriamiento
Piping Recuperación de agua de enfriamiento
Piping Agua de incendio
Piping Relave concentrado
Piping Aceite hidráulico HP
Piping Aceite hidráulico LP
05-Jun-13, Area 210 Grinding Circuit
05-Jun-13, Grinding Circuit
08-Mar-13, Structural Steel Works
08-Mar-13, 210-BL-003 Pebble Crusher Structure
Montaje de Edificio Pebble Cruher
Montaje de Estructura Pebble Feed Bin
Montaje de Escaleras de Acceso
Montaje de Vigas de apoyo de Grúa Pórtico
Montaje de Estructura Pebble Bin Hooper
Montaje de Estructura Sag Ball Bin
04-Jun-13, Mechanical Works
15-Dec-12, Lime Silo Package
210-BN-011 Silo para Cal (Cuerpo)
210-AT-001 Activador del Silo para Cal
210-DC-001 Filtro de Ventilación del Silo para Cal
210-GC-001@003 Compresores de desplazamiento positivo para el Silo para Cal
210-GA-008 Desviador por gravedad del Silo para Cal
210-LM-001 Silo para Cal (Package)
210-GA-009/010 Válvula de cuchilla neumática del Silo para Cal
210-SC-001/002 Alimentadores sin fin del Silo para Cal
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 7 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A2120 210-CH-040/041 Chutes de transferencia del Silo para Cal 8 08-Dec-12 15-Dec-12
Pebble CrusherPebble Crusher 150 15-Dec-12 13-May-13
A2380 210-LN-007/008 Placas de desgaste para descarga de Chancadora 6 15-Dec-12 20-Dec-12
A2320 210-CH-028/029 Chute de descarga de Chancadora 8 21-Dec-12 28-Dec-12
A2345 210-CR-002 Chancadora Cónica 60 29-Dec-12 26-Feb-13
A2230 210-CH-015 Chute de descarga 3 29-Dec-12 31-Dec-12
A2290 210-CH-024/025 Chute descarga de Alimentador de correa 6 27-Feb-13 04-Mar-13
A2350 210-FE-001/002 Alimentador de correa 10 05-Mar-13 14-Mar-13
A2260 210-CH-020/021 Chute de descarga de cajón alimentador 8 15-Mar-13 22-Mar-13
A2340 210-CR-001 Chancadora Cónica 60 15-Mar-13 13-May-13
A2390 210-LN-009 Placas de desgaste para descarga de Alimentador 6 23-Mar-13 28-Mar-13
A2190 210-BN-002 Cajón Alimentador de Chancadora 10 29-Mar-13 07-Apr-13
A2280 210-CH-023 Chute desviador 1 08-Apr-13 08-Apr-13
A2210 210-CH-009 Chute desviador 4 09-Apr-13 12-Apr-13
A2360 210-GA-003 Desviador de compuerta 1 09-Apr-13 09-Apr-13
A2240 210-CH-018 Chute de conexión 2 10-Apr-13 11-Apr-13
A2270 210-CH-022 Chute de conexión 1 13-Apr-13 13-Apr-13
A2300 210-CH-026 Chute de conexión 2 14-Apr-13 15-Apr-13
A2310 210-CH-027 Chute desviador 2 16-Apr-13 17-Apr-13
A2370 210-GA-007 Desviador de compuerta 1 18-Apr-13 18-Apr-13
A2250 210-CH-019 Chute by pass 4 19-Apr-13 22-Apr-13
A2220 210-CH-011 Chute de descarga 2 23-Apr-13 24-Apr-13
A2330 210-CH-030 Chute de descarga bypass 4 23-Apr-13 26-Apr-13
A2200 210-BN-010 Tolva 6 25-Apr-13 30-Apr-13
A2400 210-ZM-003 Plataforma de acceso a Chancadora 2 25-Apr-13 26-Apr-13
A2410 210-ZM-057@059 Plataforma de mantenimiento 2 27-Apr-13 28-Apr-13
A2420 210-ZM-061/062 Sellos 2 29-Apr-13 30-Apr-13
Hidraulic Unit (Pebble Crusher)Hidraulic Unit (Pebble Crusher) 28 14-Apr-13 11-May-13
A2450 210-HP-003/004 Unidad Hidráulica 5 14-Apr-13 18-Apr-13
A2460 210-PP-044/045 Unidad de Bombeo Hidráulico 5 19-Apr-13 23-Apr-13
A2470 210-PP-079/080 Unidad de Bombeo Hidráulico 5 24-Apr-13 28-Apr-13
A2480 210-ZM-063/064 Soporte del Filtro del Soplador 5 29-Apr-13 03-May-13
A2490 210-ZM-065/066 Soporte del Soplador 5 29-Apr-13 03-May-13
A2430 210-FL-005/006 Caja para filtro (Soplador de contraeje de Chancadora) 8 04-May-13 11-May-13
A2440 210-GB-003/004 Soplador (contraeje de Chancadora) 3 04-May-13 06-May-13
Lubrication Room (Pebble Crusher)Lubrication Room (Pebble Crusher) 42 24-Apr-13 04-Jun-13
A2540 210-LU-008/009 Sistema de Lubricación 11 24-Apr-13 04-May-13
A2520 210-HT-010/011 Calentadores de inmersión del Sistema de Lubricación 10 05-May-13 14-May-13
A2530 210-HT-014/015 Calentadores de inmersión del Sistema de Lubricación 5 15-May-13 19-May-13
A2550 210-PP-040@043 Bombas de Lubricación 4 20-May-13 23-May-13
A2500 210-FA-002@005 Ventiladores de enframiento del Sistema de Lubricación 5 24-May-13 28-May-13
A2510 210-FA-081 Ventilador de Sala de Lubricación 7 29-May-13 04-Jun-13
Conveyor 210-CV-001Conveyor 210-CV-001 132 15-Oct-12 23-Feb-13
A2560 210-CV-001 Feed Conveyor 100 15-Oct-12 22-Jan-13
A2610 210-MH-001 Detector de humedad de faja 2 23-Jan-13 24-Jan-13
A2630 210-SL-001 Balanza de faja 1 5 25-Jan-13 29-Jan-13
A2600 210-LU-011 Sistema de Lubricacion y Enfriamiento Conveyor 1 6 30-Jan-13 04-Feb-13
A2590 210-HT-049/050 Calentadores Lubricación y Enfriamiento Conveyor 1 4 05-Feb-13 08-Feb-13
A2570 210-FA-077 Ventilador Lubricacion y Enfriamiento Conveyor 1 4 09-Feb-13 12-Feb-13
A2620 210-PP-094 Bomba Lubricación y Enfriamiento Conveyor 1 5 13-Feb-13 17-Feb-13
A2580 210-FE-004 Alimentador rotativo de bolas 6 18-Feb-13 23-Feb-13
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
210-CH-040/041 Chutes de transferencia del Silo para Cal
13-May-13, Pebble Crusher
210-LN-007/008 Placas de desgaste para descarga de Chancadora
210-CH-028/029 Chute de descarga de Chancadora
210-CR-002 Chancadora Cónica
210-CH-015 Chute de descarga
210-CH-024/025 Chute descarga de Alimentador de correa
210-FE-001/002 Alimentador de correa
210-CH-020/021 Chute de descarga de cajón alimentador
210-CR-001 Chancadora Cónica
210-LN-009 Placas de desgaste para descarga de Alimentador
210-BN-002 Cajón Alimentador de Chancadora
210-CH-023 Chute desviador
210-CH-009 Chute desviador
210-GA-003 Desviador de compuerta
210-CH-018 Chute de conexión
210-CH-022 Chute de conexión
210-CH-026 Chute de conexión
210-CH-027 Chute desviador
210-GA-007 Desviador de compuerta
210-CH-019 Chute by pass
210-CH-011 Chute de descarga
210-CH-030 Chute de descarga bypass
210-BN-010 Tolva
210-ZM-003 Plataforma de acceso a Chancadora
210-ZM-057@059 Plataforma de mantenimiento
210-ZM-061/062 Sellos
11-May-13, Hidraulic Unit (Pebble Crusher)
210-HP-003/004 Unidad Hidráulica
210-PP-044/045 Unidad de Bombeo Hidráulico
210-PP-079/080 Unidad de Bombeo Hidráulico
210-ZM-063/064 Soporte del Filtro del Soplador
210-ZM-065/066 Soporte del Soplador
210-FL-005/006 Caja para filtro (Soplador de contraeje de Chancadora)
210-GB-003/004 Soplador (contraeje de Chancadora)
04-Jun-13, Lubrication Room (Pebble Crusher)
210-LU-008/009 Sistema de Lubricación
210-HT-010/011 Calentadores de inmersión del Sistema de Lubricación
210-HT-014/015 Calentadores de inmersión del Sistema de Lubricación
210-PP-040@043 Bombas de Lubricación
210-FA-002@005 Ventiladores de enframiento del Sistema de Lubricación
210-FA-081 Ventilador de Sala de Lubricación
23-Feb-13, Conveyor 210-CV-001
210-CV-001 Feed Conveyor
210-MH-001 Detector de humedad de faja
210-SL-001 Balanza de faja 1
210-LU-011 Sistema de Lubricacion y Enfriamiento Conveyor 1
210-HT-049/050 Calentadores Lubricación y Enfriamiento Conveyor 1
210-FA-077 Ventilador Lubricacion y Enfriamiento Conveyor 1
210-PP-094 Bomba Lubricación y Enfriamiento Conveyor 1
210-FE-004 Alimentador rotativo de bolas
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 8 of 10
Activity ID Activity Name OriginalDuration
Start Finish
Conveyor 210-CV-004@005Conveyor 210-CV-004@005 60 24-Dec-12 21-Feb-13
A2640 210-BL-002 Torre de Transferencia #3 20 24-Dec-12 12-Jan-13
A2650 210-BL-007 Torre de Accionamiento Conveyor 5 20 13-Jan-13 01-Feb-13
A2660 210-CH-016 Chute de descarga Conveyor 4 7 02-Feb-13 08-Feb-13
A2670 210-CH-017 Chute de descarga Conveyor 5 8 09-Feb-13 16-Feb-13
A2680 210-MD-002 Detector de metal 2 17-Feb-13 18-Feb-13
A2690 210-SL-002 Balanza de faja 5 3 19-Feb-13 21-Feb-13
Conveyor 210-CV-006Conveyor 210-CV-006 40 02-Feb-13 13-Mar-13
A2700 210-BL-006 Torre de Transferencia #4 14 02-Feb-13 15-Feb-13
A2720 210-CV-006 Recirculating Conveyor 20 16-Feb-13 07-Mar-13
A2710 210-CH-032 Chute de descarga Conveyor 6 6 08-Mar-13 13-Mar-13
Miscellaneous EquipmentMiscellaneous Equipment 26 01-May-13 26-May-13
A2730 210-AR-002 Tanque Pulmón 3 01-May-13 03-May-13
A2740 210-CN-003 Grúa Pórtico 10 04-May-13 13-May-13
A2750 210-DO-001/002 Puerta Enrrollable de Sala de Lubricación 3 14-May-13 16-May-13
A2760 210-HS-001 Polipasto monoriel para polea de cabeza Conveyor 5 7 17-May-13 23-May-13
A2770 210-PP-006 Bomba Sumergible 3 24-May-13 26-May-13
Piping WorksPiping Works 120 06-Feb-13 05-Jun-13
A2900 Piping Agua Enfriamiento 40 06-Feb-13 17-Mar-13
A2960 Piping Agua Cruda 25 26-Feb-13 22-Mar-13
A2920 Piping Lubricación HP 30 18-Mar-13 16-Apr-13
A2950 Piping Agua Molienda 10 23-Mar-13 01-Apr-13
A2910 Piping Agua Contra Incendio 25 02-Apr-13 26-Apr-13
A2930 Piping Lubricación LP 20 17-Apr-13 06-May-13
A2970 Piping Slurry, Neutral 5 27-Apr-13 01-May-13
A2980 Piping Vendor 20 02-May-13 21-May-13
A2940 Piping Aire de Planta 30 07-May-13 05-Jun-13
Area 262 Water ManagementArea 262 Water Management 50 01-Feb-13 22-Mar-13
Piping WorksPiping Works 50 01-Feb-13 22-Mar-13
A3000 Piping Agua Cruda 50 01-Feb-13 22-Mar-13
Area 400 General On Site FacilitiesArea 400 General On Site Facilities 122 31-Jan-13 01-Jun-13
Structural Steel WorksStructural Steel Works 92 31-Jan-13 02-May-13
A4010 Montaje de Muros Cortafuego Sala Eléctrica 200-ER-005 8 31-Jan-13 07-Feb-13
A4110 Muro Cortafuego 220-US-001/002 y 220-TF-003/004/005 15 05-Feb-13 19-Feb-13
A4020 Montaje de Muros Cortafuego Sala Eléctrica 200-ER-006 8 08-Feb-13 15-Feb-13
A4030 Montaje de Muros Cortafuego Sala Eléctrica 200-ER-007 8 16-Feb-13 23-Feb-13
A4120 Muro Cortafuego 230-US-001/002 y 230-TF-004/005/006 15 20-Feb-13 06-Mar-13
A4040 Muro Cortafuego 205-US-001/205-TF-002 10 24-Feb-13 05-Mar-13
A4050 Muro Cortafuego 210-TF-004/005/006 12 06-Mar-13 17-Mar-13
A4130 Muro Cortafuego 255-PP-048TF/049TF/050TF/051TF/052TF y 255-PP-054TF/055TF/056TF/057TF/058TF20 07-Mar-13 26-Mar-13
A4060 Muro Cortafuego 210-TF-007/008/009 12 18-Mar-13 29-Mar-13
A4140 Muro Cortafuego 255-US-001/002/003 y 255-TF-005/006/007 18 27-Mar-13 13-Apr-13
A4070 Muro Cortafuego 210-TF-011 4 30-Mar-13 02-Apr-13
A4080 Muro Cortafuego 210-TF-012 5 03-Apr-13 07-Apr-13
A4090 Muro Cortafuego 210-TF-017/018 10 08-Apr-13 17-Apr-13
A4150 Muro Cortafuego 260-US-001 6 14-Apr-13 19-Apr-13
A4100 Muro Cortafuego 210-US-013/014/015 15 18-Apr-13 02-May-13
Mechanical WorksMechanical Works 7 27-Mar-13 02-Apr-13
A4000 400-PP-011 Bomba Sumidero 7 27-Mar-13 02-Apr-13
Piping WorksPiping Works 60 03-Apr-13 01-Jun-13
A4160 Piping Combustible 40 03-Apr-13 12-May-13
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
21-Feb-13, Conveyor 210-CV-004@005
210-BL-002 Torre de Transferencia #3
210-BL-007 Torre de Accionamiento Conveyor 5
210-CH-016 Chute de descarga Conveyor 4
210-CH-017 Chute de descarga Conveyor 5
210-MD-002 Detector de metal
210-SL-002 Balanza de faja 5
13-Mar-13, Conveyor 210-CV-006
210-BL-006 Torre de Transferencia #4
210-CV-006 Recirculating Conveyor
210-CH-032 Chute de descarga Conveyor 6
26-May-13, Miscellaneous Equipment
210-AR-002 Tanque Pulmón
210-CN-003 Grúa Pórtico
210-DO-001/002 Puerta Enrrollable de Sala de Lubricación
210-HS-001 Polipasto monoriel para polea de cabeza Conveyor 5
210-PP-006 Bomba Sumergible
05-Jun-13, Piping Works
Piping Agua Enfriamiento
Piping Agua Cruda
Piping Lubricación HP
Piping Agua Molienda
Piping Agua Contra Incendio
Piping Lubricación LP
Piping Slurry, Neutral
Piping Vendor
Piping Aire de Planta
22-Mar-13, Area 262 Water Management
22-Mar-13, Piping Works
Piping Agua Cruda
01-Jun-13, Area 400 General On Site Facilities
02-May-13, Structural Steel Works
Montaje de Muros Cortafuego Sala Eléctrica 200-ER-005
Muro Cortafuego 220-US-001/002 y 220-TF-003/004/005
Montaje de Muros Cortafuego Sala Eléctrica 200-ER-006
Montaje de Muros Cortafuego Sala Eléctrica 200-ER-007
Muro Cortafuego 230-US-001/002 y 230-TF-004/005/006
Muro Cortafuego 205-US-001/205-TF-002
Muro Cortafuego 210-TF-004/005/006
Muro Cortafuego 255-PP-048TF/049TF/050TF/051TF/052TF y 255-PP-054TF/055TF/056TF/057TF/058TF
Muro Cortafuego 210-TF-007/008/009
Muro Cortafuego 255-US-001/002/003 y 255-TF-005/006/007
Muro Cortafuego 210-TF-011
Muro Cortafuego 210-TF-012
Muro Cortafuego 210-TF-017/018
Muro Cortafuego 260-US-001
Muro Cortafuego 210-US-013/014/015
02-Apr-13, Mechanical Works
400-PP-011 Bomba Sumidero
01-Jun-13, Piping Works
Piping Combustible
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 9 of 10
Activity ID Activity Name OriginalDuration
Start Finish
A4170 Piping Slurry 20 13-May-13 01-Jun-13
Area 800 Water Supply & StorageArea 800 Water Supply & Storage 182 08-Dec-12 07-Jun-13
Mechanical WorksMechanical Works 110 08-Dec-12 27-Mar-13
A8090 800-TK-101 Tanque de Suministro de Agua (Laguna Haucracocha) 17 08-Dec-12 24-Dec-12
A8060 800-TK-105 Tanque de Agua Potable 17 15-Dec-12 31-Dec-12
A8070 800-TK-110 Tanque de Almacenamiento de Agua 36 01-Jan-13 05-Feb-13
A8080 800-WT-001 Tratamiento de Agua Package 16 06-Feb-13 21-Feb-13
A8020 800-PP-105/106 Bomba de Alimentación de Agua 10 22-Feb-13 03-Mar-13
A8030 800-PP-115 Bomba de Agua 4 04-Mar-13 07-Mar-13
A8040 800-PP-152 Bomba de Agua Contra Incendio 4 08-Mar-13 11-Mar-13
A8050 800-PP-162 Bomba de Agua Contra Incendio 4 12-Mar-13 15-Mar-13
A8000 800-CO-002 Casa de Bombas Contra Incendio 6 16-Mar-13 21-Mar-13
A8010 800-DL-152 Máquina operadora de Diesel 6 22-Mar-13 27-Mar-13
Piping WorksPiping Works 135 24-Jan-13 07-Jun-13
A8100 Piping Agua Fresca 55 24-Jan-13 19-Mar-13
A8110 Piping Agua Contra Incendio 80 20-Mar-13 07-Jun-13
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb2012 2013 2014
Piping Slurry
07-Jun-13, Area 800 Water Supply & Storage
27-Mar-13, Mechanical Works
800-TK-101 Tanque de Suministro de Agua (Laguna Haucracocha)
800-TK-105 Tanque de Agua Potable
800-TK-110 Tanque de Almacenamiento de Agua
800-WT-001 Tratamiento de Agua Package
800-PP-105/106 Bomba de Alimentación de Agua
800-PP-115 Bomba de Agua
800-PP-152 Bomba de Agua Contra Incendio
800-PP-162 Bomba de Agua Contra Incendio
800-CO-002 Casa de Bombas Contra Incendio
800-DL-152 Máquina operadora de Diesel
07-Jun-13, Piping Works
Piping Agua Fresca
Piping Agua Contra Incendio
CC-05 STRUCTURAL, MECHANICAL PIPING - DRY AREA
Date Revision Checked Approved
05-Sep-12 Programa Target Price E. Vilca R. Castillo
Page 10 of 10