Review of deliverablesReview of deliverables
Three levels of deliverables:
Level 3: Deliverable at Tasks
Level 2: Deliverable at Design Study
Level 1: Deliverable at Project
Level 0: Deliverable at Board Level
We present progress in terms of the Level 0 deliverables
André van Es2nd SKADS Workshop 10-11 October 2007
DS-1DS-1ASTRONASTRON
University of University of ManchesterManchester
Observatoire Observatoire de Parisde Paris
DS-2DS-2Rijks Universiteit Rijks Universiteit
GroningenGroningen
ASTRONASTRON
INAF-IRAINAF-IRA
MPIfRMPIfR
Universidad de ValenciaUniversidad de Valencia
CSIROCSIRO
SwinburneSwinburne
Leiden ObservatoryLeiden Observatory
ChalmersChalmers
OxfordOxford
University of University of ManchesterManchester
Observatoire de ParisObservatoire de Paris
CambridgeCambridge
University of MelbourneUniversity of Melbourne
Natal UniversityNatal University
PRAO-LPIPRAO-LPI
University of LeedsUniversity of Leeds
University of GlasgowUniversity of Glasgow
University of AdelaideUniversity of Adelaide
DS-3DS-3University of University of CambridgeCambridge
ASTRONASTRON
University of University of ManchesterManchester
CSIROCSIRO
INAF-IRAINAF-IRA
University of University of OxfordOxford
Cambridge Cambridge UniversityUniversity
Observatoire Observatoire de Parisde Paris
National National Research Research
FoundationFoundation
DS-4DS-4University of University of ManchesterManchester
ASTRON ASTRON
Observatoire Observatoire de Parisde Paris
INAF-IRAINAF-IRA
FG-IGNFG-IGN
University of University of OxfordOxford
CSIROCSIRO
National National Research Research CouncilCouncil
University of University of CambridgeCambridge
University of University of OrléansOrléans
CNRSCNRS
OMMIROMMIR
DS-5DS-5ASTRONASTRON
University of University of ManchesterManchester
Observatoire Observatoire de Parisde Paris
JIVEJIVE
INAF-IRAINAF-IRA
MPIfRMPIfR
Oxford Oxford UniversityUniversity
CSIROCSIRO
National National Research Research
FoundationFoundation
UMKUMK
University of University of CambridgeCambridge
OMMICOMMIC
DS-6DS-6INAF-IRAINAF-IRA
ASTRONASTRON
JIVEJIVE
CSIROCSIRO
Univ. SydneyUniv. Sydney
DS-7: DS-7: University of Manchester, Observatoire de ParisUniversity of Manchester, Observatoire de Paris
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-1Review on deliverables: DS-1
Deliverable/ Milestone No
Planned (in months)
Achieved (in months)
Deliverable/Milestone Name
DS1 1. 1-oct-05 Nov-05 Organize kick-off DS1 2. 1-oct-05 1-jan-06 Implement adequate management tools DS1 - ongoing Continuous coordination and management DS1 - ongoing Continuous assessment and control DS1 3 1-Nov-05 30-June-
06 Document on outreach policy
DS1 4 1-Apr-05 1-Oct-05 Establish web-page DS1 5 1-Nov-05 1-Feb-06 Document on IPR Policy DS1 6 1-Apr-06 4-Sep-06 SKADS international workshop 2006 DS1 7 1-Apr-07 10-Oct-07 SKADS international workshop 2007 DS1 8 1-Apr-08 Sep 08 SKADS international workshop 2008 DS1 9 1-Apr-09 Sep 09 SKADS international workshop 2009
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-2Review on deliverables: DS-2
Nominal
Completion Date
Actual/ Planned
completion Date
Milestone
DS2 1 1-jun-07 1-jun-07 Conclusion on Science Drivers
DS2 2 1-dec-08 1-dec-08 Conclusion on Year in the Life for different SKA realizations
DS2 3 1-jul-08 1-jul-08 Optimised Configuration for the SKA
DS2 4 1-mei-09 1-mei-09 Demonstration of new calibration and imaging Techniques
André van Es2nd SKADS Workshop 10-11 October 2007
A Report and Proceedings...A Report and Proceedings...
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-3Review on deliverables: DS-3
Nominal
Completion Date
Actual/ Planned
completion Date
Milestone
DS3 1 30-jun-08 31-dec-08 Delivery of prototype phase transfer link DS3 2 31-dec-08 31-dec-08 Development cost of model for the network DS3 3 30-mei-09 30-mei-09 Report on technology roadmapping and costing DS3 4 1-jul-07 1-jul-07 Delivery of framework for functional simulator DS3 5 30-mei-09 30-mei-09 Report on network achtitecture DS3 6 30-jun-08 30-jun-08 Overview reports on site selection DS3 7 31-dec-08 31-dec-08 Final reports on site selection DS3 8 30-jun-08 30-jun-08 Reports on SKA for the user
DS3 9 30-dec-05 30-dec-05 Model driven architecture specification of control and data processing
DS3 10 30-jun-08 30-jun-08 Report MDA constructs, interfaces and platforms DS3 11 30-dec-07 30-dec-07 report on scalable platform specific composition DS3 12 30-jun-08 30-jun-08 MDA assessment and scalability recommendations
André van Es2nd SKADS Workshop 10-11 October 2007
SKADS Design & Costing SKADS Design & Costing Paper (SKA Memo 93)Paper (SKA Memo 93)
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-4Review on deliverables: DS-4
Nominal
Completion Date
Planned Completion
Milestone
DS4 1 30-dec-06 done SiGe band pass filter using PIC technology prototype DS4 2 30-dec-07 31-dec-08 ADC performance evaluation
DS4 3 1-jul-07 1-jul-08 Hybrid LNA first devices
DS4 4 1-jul-06 1-jul-08 Inventory of RFI mitigation techniques and applicability to SKA
DS4 5 1-jul-07 1-jul-08 Evaluation of impact of moving interference sources on SKA DS4 6 31-okt-07 1-mrt-08 Characterised antenna element DS4 7 1-mrt-08 1-jul-08 antenna element with integrated MMIC prototype
DS4 8 1-jul-07 1-mrt-08 Simulated Digital beamformer for 2-PAD
DS4 9 30-dec-06 done Prototype low cost SiGe analogue beamformer DS4 10 29-dec-08 2-feb-09 Prototype complete 2-PAD digital tile
DS4 11 30-jun-09 30-jun-09
Final reports on semiconductor technologies, RFI mitigation strategies, antenna element design, digital beamformer design 2-PAD performance (T1-T6)
André van Es2nd SKADS Workshop 10-11 October 2007
Prototype of Low Cost SiGe Prototype of Low Cost SiGe BeamformerBeamformer
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-5Review on deliverables: DS-5
Nominal
Completion Date
Planned Completion
Milestone
DS5 1 30-dec-05 30-dec-05 Completion of System Requirements DS5 2 1-mrt-06 15 May-06 Design Review of First Tile
DS5 3 1-jul-06 1-jul-06 Delivery of first manufactured tile
DS5 4 1-mrt-07 1-okt-07 completion of 10 tile system DS5 5 31-mei-08 1-sept-2008 completion of first 100 tiles DS5 6 1-jan-09 1-jan-2009 completion of m anufacturing of all tiles
André van Es2nd SKADS Workshop 10-11 October 2007
EMBRACE 10 tile prototypeEMBRACE 10 tile prototype
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-5Review on deliverables: DS-5
Nominal
Completion Date
Planned Completion Milestone
DS5 1 30-dec-05 30-dec-05 Completion of System Requirements DS5 2 1-mrt-06 15 May-06 Design Review of First Tile
DS5 3 1-jul-06 1-jul-06 Delivery of first manufactured tile
DS5 4 1-mrt-07 1-okt-07 completion of 10 tile system DS5 5 31-mei-08 1-sept-2008 completion of first 100 tiles DS5 6 1-jan-09 1-jan-2009 completion of manufacturing of all tiles
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-6Review on deliverables: DS-6
Nominal
Completion Date
Planned Completion
Milestone
DS6 1 1-jul-06 done Design Report on Analog Optical link DS6 2 30-apr-07 done Design Report on Analog and digital optical link
DS6 3 31-aug-08 31-aug-08 Report on data handling for large telescopes
DS6 4 30-sep-08 30-sep-08 Wide band high dynamic range A/D FX correlator, small
prototype DS6 5 30-sep-08 30-sep-08 Software beamforming and multibeaming on BEST-x DS6 6 30-sep-08 30-sep-08 Algorithms for RFI mitigation DS6 7 1-jul-08 1-jul-08 Calibration methods for large array DS6 8 30-sep-08 30-sep-08 report on High sensitivity astronomical tests
André van Es2nd SKADS Workshop 10-11 October 2007
BEST Report on optical linksBEST Report on optical links
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS-7Review on deliverables: DS-7
Task number Deliverable No
Deliverable Name Planned (in months)
Achieved (in months)
DS7-T1 1 SKADS Quarterly Report Q4/2006
19 19
DS7-T1 2 SKADS Quarterly Report Q1/2007
22 22
DS7-T1 3 SKADS Quarterly Report Q3/2007
25 25
DS7-T1 4 SKADS Quarterly Report Q4/2007
19 19
DS7-T1 5 SKADS Quarterly Report Q1/2008
22 22
DS7-T1 6 SKADS Quarterly Report Q3/2008
25 25
DS7-T1 7 SKADS Quarterly Report Q4/2008
19 19
DS7-T1 8 SKADS Quarterly Report Q1/2009
22 22
DS7-T1 9 2007 Annual Report to International SKA Project Office
24 25
DS7-T1 10 2008 Annual Report to International SKA Project Office
24 25
DS7-T1 11 2009 Annual Report to International SKA Project Office
24 25
André van Es2nd SKADS Workshop 10-11 October 2007
Updated PlanUpdated Plan
Prior to 2nd Annual Report project planning was updated
All Design Studies submitted new milestone/deliverable table
New milestone dates were discussed and agreed with DS leaders
SKADS on track to finish on 30th June 2009
André van Es2nd SKADS Workshop 10-11 October 2007
Deliverables/Milestones planned Deliverables/Milestones planned (update 2(update 2ndnd annual report) annual report)
Level 0 Deliverables
0
10
20
30
40
50
60
0,5 1 1,5 2 2,5 3 3,5 4
Time
Tot. N
r. o
f D
eliv
era
ble
s
Planned (DoW)
Current Plan
André van Es2nd SKADS Workshop 10-11 October 2007
Next 18 months Next 18 months (major milestone for each DS)(major milestone for each DS)
DS2: Final Report on SKA configurations
DS 3: – Implementation of Cost and Functional simulator tool
– Selection of networking and computing technologies
DS 4: Completion of 2-PAD design
DS 5: Build and first testing of EMBRACE at Westerbork and Nancay (100 tiles)
DS 6: BEST demonstrating beamforming and Hl sensitivity astronomical tests
DS 8 : First iteration of Overall System Design and Project plan
André van Es2nd SKADS Workshop 10-11 October 2007
Review on deliverables: DS 8Review on deliverables: DS 8
Design Study 8 produces the major deliverables of the project (the focal and cohering point of SKADS):
1. Overall System Design
2. Preliminary SKA Plan
3. White Paper for the ISSC
It is the collection of all activities and will show and establish the direction towards the SKA