MRT 7 PROJECTDEPARTMENT OF TRANSPORTATION
and
SMC MASS RAIL TRANSIT 7, INC.
-
THE PROJECT CONCESSION
CA CONCESSION AGREEMENTSigned: June 18, 2008Confirmed and Approved by NEDA Board: July 9, 2009Effectivity of CA: February 19, 2016
Conceptualized: 2001NEDA Board re-approval of Cost: 21 November 2013Signing of Implementation Guidelines (IG): 21July 2014Effectivity of CA: 19 February 2016Start of Construction: August 2016Concession Period: 25 Years
Milestones
USD 1,540,004,020.86
Project Cost
-
COMPONENTS OF THE PROJECT
INTERMODAL
TRANSPORTATION
TERMINAL
• 22.6 kms rail system from North Avenue EDSA to San Jose del Monte Bulacan
• Joint Station with LRT Line 1, MRT Line 3 and Subway along North EDSA• 108 cars or 36 trainsets (3-car configuration)• Can operate at 6-car configuration• 3rd rail power systemRAIL
METRO RAIL TRANSIT SYSTEM (MRTS)
• 6-lane Highway that will connect the Intermodal Transportation Terminal (ITT) in San Jose Del Monte, Bulacan to Bocaue/Balagtas Interchange North Luzon Expressway (NLEX).
• Located adjacent to Depot which can accommodate 60 buses at any given time, complete with facilities, i.e., passenger waiting areas, lounges, ticket booths, etc.
• With facilities standard to an intermodal terminal
INTERMODAL TRANSPORTATION TERMINAL (ITT)
HIGHWAY
MRT 7 – ROAD ACCESS
-
MRT7 ALIGNMENT
STATION TO STATION DISTANCE
(m)
North Avenue - QMC 2,195
QMC - University Avenue 836
University Avenue - Tandang Sora 1,664
Tandang Sora - Don Antonio 2,356
Don Antonio – Batasan 973
Batasan - Manggahan 1391
Manggahan - Doña Carmen 1,470
Doña Carmen - Regalado 1,145
Regalado - Mindanao 3,430
Mindanao - Quirino 787
Quirino - Sacred Heart 1,855
Sacred Heart - Tala 2,025
Tala - San Jose Del Monte 2,543
TOTAL 22,623
-
Particulars Physical
Accomplishment
Remarks/Status
I. Civil Works 40.16%
i. Guideway On-going guideway construction (14,000m out of 23,200m) along Sta. 2,4,5,6,7,8 & 9
1. Underground/Depressed Excavation/concreting works in progress
2. At-grade Excavation/concreting works in progress
3. Elevated Installation of coping beam, girder & trans-slabs are
in progress
ii. Stations On-going construction on 9 stations
1. Elevated On-progress
2. Underground/Depressed On-progress
II. Rolling Stock and E&M Works 53.22% The shipment of the 1st set of trains which is available January 2018 was deferred due to unavailability of
the holding/depot area. At present, 108 cars are
already completed.
Total Accomplishment 46.44% As of July 2019
PROJECT STATUS
-
01-North Avenue Station (Elevated)
On-going Column Rebar Installation and Bored Piling Works
02-Quezon Memorial Circle Station (Depressed)
Preparation for Track Works
-
03-University Avenue Station (Depressed)
On going Construction of Mat foundation
04-Tandang Sora Station (Elevated)
Bored Piling Works
-
05-Don Antonio Station (Elevated)
Girders and Trans-Slab Erection
06-Batasan Station (Elevated)
Steel Beams and Girder Erection
-
07-Manggahan Station (At-Grade)
Installation of Columns and Bored Piling Works
08-Doña Carmen Station (Elevated)
Column Installation
-
09-Regalado Station (Elevated)
Installation of Columns
10-Mindanao Avenue Station (Elevated)
Column Rebar Installation and Bored Piling Works
-
11-Quirino Station (Elevated)
Girder and Trans-Slab Erection
12-Sacred Heart Station (At-Grade)
Installation of Girders along Sacred Heart Guideway
-
13-Tala Station (Elevated)
Guideway to Tala with Several Coping Beams and Girders
14-San Jose Del Monte Station (Depressed)
Under Expropriation
-
22.6 km
16.9 km
19.65 km
-
COMPLETED TRAINS
-