  • MRT 7 PROJECTDEPARTMENT OF TRANSPORTATION

    and

    SMC MASS RAIL TRANSIT 7, INC.

  • THE PROJECT CONCESSION

    CA CONCESSION AGREEMENTSigned: June 18, 2008Confirmed and Approved by NEDA Board: July 9, 2009Effectivity of CA: February 19, 2016

    Conceptualized: 2001NEDA Board re-approval of Cost: 21 November 2013Signing of Implementation Guidelines (IG): 21July 2014Effectivity of CA: 19 February 2016Start of Construction: August 2016Concession Period: 25 Years

    Milestones

    USD 1,540,004,020.86

    Project Cost

  • COMPONENTS OF THE PROJECT

    INTERMODAL

    TRANSPORTATION

    TERMINAL

    • 22.6 kms rail system from North Avenue EDSA to San Jose del Monte Bulacan

    • Joint Station with LRT Line 1, MRT Line 3 and Subway along North EDSA• 108 cars or 36 trainsets (3-car configuration)• Can operate at 6-car configuration• 3rd rail power systemRAIL

    METRO RAIL TRANSIT SYSTEM (MRTS)

    • 6-lane Highway that will connect the Intermodal Transportation Terminal (ITT) in San Jose Del Monte, Bulacan to Bocaue/Balagtas Interchange North Luzon Expressway (NLEX).

    • Located adjacent to Depot which can accommodate 60 buses at any given time, complete with facilities, i.e., passenger waiting areas, lounges, ticket booths, etc.

    • With facilities standard to an intermodal terminal

    INTERMODAL TRANSPORTATION TERMINAL (ITT)

    HIGHWAY

    MRT 7 – ROAD ACCESS

  • MRT7 ALIGNMENT

    STATION TO STATION DISTANCE

    (m)

    North Avenue - QMC 2,195

    QMC - University Avenue 836

    University Avenue - Tandang Sora 1,664

    Tandang Sora - Don Antonio 2,356

    Don Antonio – Batasan 973

    Batasan - Manggahan 1391

    Manggahan - Doña Carmen 1,470

    Doña Carmen - Regalado 1,145

    Regalado - Mindanao 3,430

    Mindanao - Quirino 787

    Quirino - Sacred Heart 1,855

    Sacred Heart - Tala 2,025

    Tala - San Jose Del Monte 2,543

    TOTAL 22,623

  • Particulars Physical

    Accomplishment

    Remarks/Status

    I. Civil Works 40.16%

    i. Guideway On-going guideway construction (14,000m out of 23,200m) along Sta. 2,4,5,6,7,8 & 9

    1. Underground/Depressed Excavation/concreting works in progress

    2. At-grade Excavation/concreting works in progress

    3. Elevated Installation of coping beam, girder & trans-slabs are

    in progress

    ii. Stations On-going construction on 9 stations

    1. Elevated On-progress

    2. Underground/Depressed On-progress

    II. Rolling Stock and E&M Works 53.22% The shipment of the 1st set of trains which is available January 2018 was deferred due to unavailability of

    the holding/depot area. At present, 108 cars are

    already completed.

    Total Accomplishment 46.44% As of July 2019

    PROJECT STATUS

  • 01-North Avenue Station (Elevated)

    On-going Column Rebar Installation and Bored Piling Works

    02-Quezon Memorial Circle Station (Depressed)

    Preparation for Track Works

  • 03-University Avenue Station (Depressed)

    On going Construction of Mat foundation

    04-Tandang Sora Station (Elevated)

    Bored Piling Works

  • 05-Don Antonio Station (Elevated)

    Girders and Trans-Slab Erection

    06-Batasan Station (Elevated)

    Steel Beams and Girder Erection

  • 07-Manggahan Station (At-Grade)

    Installation of Columns and Bored Piling Works

    08-Doña Carmen Station (Elevated)

    Column Installation

  • 09-Regalado Station (Elevated)

    Installation of Columns

    10-Mindanao Avenue Station (Elevated)

    Column Rebar Installation and Bored Piling Works

  • 11-Quirino Station (Elevated)

    Girder and Trans-Slab Erection

    12-Sacred Heart Station (At-Grade)

    Installation of Girders along Sacred Heart Guideway

  • 13-Tala Station (Elevated)

    Guideway to Tala with Several Coping Beams and Girders

    14-San Jose Del Monte Station (Depressed)

    Under Expropriation

  • 22.6 km

    16.9 km

    19.65 km

  • COMPLETED TRAINS