and limited ressetlement action plan for …kplc.co.ke/fileadmin/user_upload/documents/rap/rap...

71
THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE PROPOSED MUMIASRANGALAKISUMU 132 kV TRANSMISSION LINE AUGUST, 2010 Name and Address of Consultant Otieno Odongo& Partners Consulting Engineers P.O Box 5402100200 Nairobi Tel : 02038700222 Fax : 0203870103 Fax : 0203870103 Email: [email protected] Name and Address of Proponent The Kenya Power & Lighting Co.Ltd. Stima Plaza, Kolobot Road P.O Box 3009901000 Nairobi Tel : 0203201000

Upload: dothuan

Post on 19-Apr-2018

237 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

 THE KENYA POWER AND LIGHTING COMPANY LIMITED 

RESSETLEMENT ACTION PLAN FOR THE PROPOSED MUMIAS‐RANGALA‐KISUMU 132 kV TRANSMISSION LINE 

                             

AUGUST,  2010  

Name and Address of Consultant Otieno Odongo& Partners Consulting Engineers P.O Box 54021‐00200 Nairobi Tel : 020‐38700222 Fax : 020‐3870103 Fax : 020‐3870103 Email: [email protected]                              

Name and Address of Proponent The Kenya Power & Lighting Co.Ltd. Stima Plaza, Kolobot Road P.O Box 30099‐01000 Nairobi Tel : 020‐3201000  

 

Page 2: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

ii 

 

    Document Authentication  This report is prepared for: The Kenya Power & Lighting Co. Limited P.O. Box 30099‐00100 Nairobi    Received by;  John Guda, Deputy Manager (Safety Health and Environment‐SHE), Signature…………………………………………………………... Date…………………………………………………………………   

Page 3: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

iii 

TABLE OF CONTENTS LIST OF TABLES ....................................................................................................................... vii 

LIST OF FIGURES ..................................................................................................................... vii 

LIST OF ABBREVIATIONS........................................................................................................ viii 

EXECUTIVE SUMMARY ............................................................................................................ ix 

1.0  INTRODUCTION ............................................................................................................... 1 

1.1 Scope of the RAP ................................................................................................................................ 1 

1.2 Project Background ............................................................................................................................ 2 

1.3 Project Description ............................................................................................................................. 2 

1.4 Project Location .................................................................................................................................. 3 

1.5 Objectives of the Resettlement Action Plan ...................................................................................... 4 

1.6 Justification for Resettlement Action Plan ......................................................................................... 4 

1.7 Land Compensation and Wayleave Acquisition ................................................................................. 5 

1.8 Guiding Principles and objectives for the RAP ................................................................................... 6 

2.0 LEGAL FRAMEWORK ........................................................................................................... 7 

2.1 Introduction ........................................................................................................................................ 7 

2.2 Summary of Relevant Acts. ................................................................................................................ 7 

2.3 Land Acquisition Act Cap 295 ............................................................................................................. 7 

2.4 The Way leaves Act Cap 292 .............................................................................................................. 8 

2.5 Government Lands Act Cap 280 ......................................................................................................... 8 

2.6 Registered Land Act Cap 300 .............................................................................................................. 8 

2.7 Trust Land Act Cap 285 ....................................................................................................................... 8 

2.8 Land control Act 302 .......................................................................................................................... 8 

2.9 The Mining Act 306 ............................................................................................................................ 8 

2.10 The Agriculture Act 318 .................................................................................................................... 8 

2.11 Environmental Management Co‐ordination Act (1999) .................................................................. 9 

2.12 World Bank Group Safeguard Policies.............................................................................................. 9 

Page 4: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

iv 

2.13 Land Legal Issues .............................................................................................................................. 9 

3.0 SCOPE OF LAND COMPENSATION, WAYLEAVE AGREEMENT AND RESETTLEMENT ............ 12 

3.1 Source of data .................................................................................................................................. 12 

3.2 Survey Methodology and schedule .................................................................................................. 12 

3.3 Limitations of study .......................................................................................................................... 12 

3.4 Right of way ...................................................................................................................................... 13 

3.5 Impacts on Land and structures ....................................................................................................... 13 

3.6 Impact of relocation on Services ...................................................................................................... 13 

4.0 MEASURES TO MINIMIZE WAYLEAVE AGREEMENTS AND LOSSES .................................... 15 

4.1 Consultation and participation ......................................................................................................... 15 

4.2 Impact limitation measures in the design stage .............................................................................. 15 

4.3 Preliminary evaluation of alternatives ............................................................................................. 15 

4.4 Impact mitigation measures in the construction stage ................................................................... 15 

5.0 SOCIO‐ECONOMIC FEATURES OF THE PROJECT AFFECTED PERSONS ................................. 17 

5.1 Sources of Data ................................................................................................................................ 17 

5.2 Socio‐Economics of PAPs in the Project affected Areas .................................................................. 17 

5.3 Summary of Socio‐Economics of the Project affected Area ............................................................ 17 

6.0 RESETTLEMENT POLICY AND ENTITLEMENTS .................................................................... 20 

6.1 Compensation Policy ........................................................................................................................ 20 

6.2 Project principles of compensation for Resettlement ..................................................................... 20 

6.2.1 Compensation policy for loss of land ....................................................................................... 20 

6.2.2 Guiding Principles and objectives for the RAP ......................................................................... 20 

6.2.3 Valuation Methodology ........................................................................................................... 22 

6.2.4 Entitlement Matrix ................................................................................................................... 24 

7.0 RESETTLEMENT SITE ......................................................................................................... 26 

7.1 Method of Site Selection and Site Alternatives ............................................................................... 26 

7.2 Influx Management .......................................................................................................................... 26 

Page 5: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

7.3 Location of Resettlement Site .......................................................................................................... 26 

7.4 Resettlement Options ...................................................................................................................... 26 

7.5 Resettlement Site Development (Infrastructure, Social Service, etc.) ............................................. 26 

7.6 Livelihood Restoration ..................................................................................................................... 27 

8.0 INCOME RESTORATION .................................................................................................... 28 

8.1 Introduction ...................................................................................................................................... 28 

8.2 Income Restoration and Improvement Component ........................................................................ 28 

8.3 Land‐Based Component ................................................................................................................... 30 

8.4 Non‐farm Component ...................................................................................................................... 30 

8.5 Compensation Preferences .............................................................................................................. 30 

9.0 IMPLEMENTATION ARRANGEMENTS ................................................................................ 31 

9.1 Organization Structure ..................................................................................................................... 31 

9.2 KPLC Resettlement Unit ................................................................................................................... 31 

9.3 Local RAP PAP Committee ................................................................................................................ 31 

9.4 Capacity of KPLC Resettlement Unit ................................................................................................ 32 

10. IMPLEMENTATION SCHEDULE AND THE RAP BUDGET ...................................................... 33 

10.1 Implementation Schedule .............................................................................................................. 33 

10.2 The RAP Budget .............................................................................................................................. 33 

11.0 PARTICIPATION AND CONSULTATION ............................................................................. 35 

11.1 Policy of participation and consultation ........................................................................................ 35 

11.2 Interviews and Group Discussions ................................................................................................. 36 

11.3 Project affected persons involvement ........................................................................................... 37 

12.0 MONITORING AND SUPERVISION ................................................................................... 38 

12.1 RAP Monitoring Framework ........................................................................................................... 38 

12.2 Internal monitoring ........................................................................................................................ 38 

12.3 Monitoring indicators ..................................................................................................................... 38 

12.4 Monitoring process ........................................................................................................................ 40 

Page 6: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

vi 

12.5 External monitoring ........................................................................................................................ 40 

12.6 Agency responsibilities ................................................................................................................... 40 

13.0 GRIEVANCE AND APPEALS .............................................................................................. 41 

13.1 Subject matter of grievance ........................................................................................................... 41 

13.2 Method of lodging complaints ....................................................................................................... 41 

13.3 Proposed procedure ....................................................................................................................... 41 

14.0 RECOMMEDATIONS AND CONCLUSIONS ........................................................................ 43 

14.1 Conclusions..................................................................................................................................... 43 

14.2 Recommendations ......................................................................................................................... 43 

REFERENCES ........................................................................................................................... 44 

APPENDIX .............................................................................................................................. 45 

Appendix 1: List of Affected PAPs indicating their names and lost property ........................................ 46 

Appendix 2: Household Questionnaires ESIA / RAP Socio‐Economic Survey ........................................ 47 

Appendix 3: Locations where socio‐economic survey and household census were undertaken .......... 52 

Appendix 4: Resettlement Action Plan Activity Schedule ...................................................................... 53 

Appendix 5: Resettlement Action Plan Public Grievance Form ............................................................. 54 

Page 7: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

vii 

 LIST OF TABLES  Table 1: Summary of the number of Project Affected Persons and Property found along the 

proposed project route .......................................................................................................... xi 

Table 2: Itemized costs of affected property in districts within project areas ............................ xvi 

Table 3: Entitlement matrix ........................................................................................................... 25 

Table 4: Livelihood Restoration Options ....................................................................................... 29 

Table 5: Cost Estimates for lost Property ...................................................................................... 33 

Table 6: Cost disturbance Allowances and Livelihood Restoration Programmes ......................... 34 

Table7: Monitoring Indicators ....................................................................................................... 38 

  LIST OF FIGURES Figure 1: Location of Mumias‐Rangala section of the Transmission Line ....................................... 3 

Figure 2: Location of Rangala‐Kisumu section of the Transmission Line ........................................ 4 

Figure 3: Grievance Redress Procedure ........................................................................................ 42 

 

  

Page 8: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

viii 

LIST OF ABBREVIATIONS  Abbreviation   Description  

ADC  Area Development Committees

BP     Bank Policies    

CIP  Community Involvement Programme  

CSR  Corporate Social Responsibility 

DC  District Commissioner 

DF  Displaced  Families  

DO  District Officer 

DRC  Dispute Resolution Centre 

EAP  Environmental Action Programmes

EC  Entitlement Card 

EIA  Environmental Impact Assessment

EMA  External Monitoring Agent 

EMCA   Environmental Management and Coordination Act 

EP  Eligible Persons 

ESIA  Environmental and Social Impact Assessment

GoK  Government Of Kenya

GPS  Geographical Positioning System 

GRRM  Grievances Referral and Redress Mechanism 

ID  Identity Cards 

ISK  Institution of Surveyors of Kenya 

KPLC  Kenya Power and Lighting Company 

LDC  Land Dispute Committee 

LIRP  Livelihood and Income Restoration Programme 

LPAP  Land Purchase Assistance Programme

LRC  Land Resolution Committee 

M&E  Monitoring and Evaluation

MOW  Ministry of Works 

NEMA  National Environment Management Authority 

O&M     Operations and Maintenance

OP  Operation Procedure 

PAF  Project  Affected  Families

PAH  Project  Affected  Households

PAP  Project  Affected  Persons

PAPC  PAP Committee 

PC  Provincial Commissioner

PCDP  Public Consultation and Disclosure Plan

PIM  Project Information Memorandum

PIU  Project Implementation Unit 

PMU  Project Management Unit

R.D.A  Registration of Documents Act  Cap 285 Laws of Kenya 

RAP  Resettlement Action Plan

RPF  Resettlement  Policy  Framework  

WB  World  Bank  

Page 9: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

ix 

EXECUTIVE SUMMARY  Introduction The Government of Kenya plans to increase access to electricity in Kenya tenfold from the current 6% in the rural areas and 18% of the total population to about 20% of rural areas and 40% of total population by 2020. To achieve this goal, Government has prepared the Energy Scale up Program covering the period 2008 to 2017. The government plans to  improve and expand the network as well as raise power generation to match the demand. To do this, the transmission lines network is being considered for construction and upgrading with the communication system required for line protection and management purposes. The KPLC power development plan  identified various 132 kV power  transmission  lines requiring development  in order  to  improve  the performance of  the national grid network  to cater  for  the  increasing  load growth and meet  the objectives of 2030. Mumias‐Rangala‐Kisumu  transmission  line  is  one  of  the  single  circuits  132kV  that  KPLC  has identified and intends to construct.  The  proposed  project  involves  construction  of  approximately  one  hundred  and  two  kilometers (101.2 km)  stretch of a high voltage  transmission  line  from Mumias via Rangala  to Kisumu. The proposed  transmission  line  starts  at  the Mumias  Sugar  Factory  substation  at  the  periphery  of Mumias  and  traverses  through  six  districts  to  reach  the  existing Mamboleo  substation  in  the outskirts of Kisumu town.  A  main  criterion  considered  in  preparing  conceptual  design  has  been  to  ensure  that  the transmission line is designed in a safe, cost effective and reliable manner. Land for the way leave would  have  to  be  expropriated  from  the  community members  as  no  public  land  exists  in  the project  area.  The  area  of  land  to  be  acquired  from  the  community member’s measures  590.3 hectares (1475.67 acres).   The Resettlement Action Plan (RAP’s) main objective is to develop a programme that will facilitate restoration of livelihoods of the Project Affected Persons (PAPs) to the pre‐impacts levels. This was achieved by conducting a socio‐economic survey in the project area to gather information on the project impacts on the PAP’s. The information gathered identified the nature and diversity of the potential impacts on the PAP’s assets, livelihoods, public infrastructure and households. This RAP is developed  in accordance with  the World Bank’s  Involuntary Resettlement Policy and  relevant sections of the Operations Manual together with the Laws of Kenya. 

Page 10: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

 

This study provides the project proponent with considerations on socio‐economic  impacts of the project. The project is required to comply with international best practice as regards resettlement. The main guiding principles included;  

• Resettlement to be avoided or minimized 

• Genuine consultation to take place 

• Establishment of a pre‐resettlement baseline data 

• Assistance in relocation to be available 

• A fair and equitable set of compensation options to be negotiated 

• Resettlement to take place as a development that ensures that PAPs benefit 

• Vulnerable social groups to be specifically catered for 

• Resettlement to be seen as an upfront project cost 

• An independent monitoring and grievance procedure to be in place, and 

• World Bank’s operational procedure on forced resettlement to be adopted.  Methodology Primary and  secondary data  collection  techniques were used  for  the purposes of providing  the social and economic status of the community which eventually culminated in development of this RAP  report. Specific  techniques used  for  the data  collection  included: Key  Informant and Semi‐Structured  Interviews,  Open‐ended  household  questionnaires,  Focus  Group  Discussions,  Public Barazas, observations and Transect walks.  Legal Framework  The   Kenyan   Law   recognizes    three   categories   of    land   ownership   namely Public  land, Trust  land  and Private  land. There are several Relevant Acts/statutes that handle the issue of land and the  development  of  infrastructure  in  Kenya  namely:  Compulsory  Acquisition  Act  Cap  295;  The Wayleave Act Cap 292; Government Lands Act Cap 280; Land Titles Act Cap 282; Registration of Titles Act Cap 281; Land (Group Representatives) Act Cap 287; Trust Land Act Cap 285; Registered Land Act Cap 300; Land control Act 302; Mining Act 306; Agriculture Act 318 and Environmental Management and Co‐ordination Act. In addition, the World Bank Policy O.P 4.12 whose emphasise are to ensure participation and wide consultations with PAPs; assistance to the displaced persons to  improve  their  livelihoods, avoid/minimize  involuntary  resettlement and safeguard production systems of a community.  The World Bank Safeguard Policies This  project  is  being  undertaken  in  compliance  with  Kenyan  legislation  and  The World  Bank policies.  However,  where  gaps  exist  between  Kenyan  Law  and  the  Bank’s  policy,  the  latter’s standards will be followed. The objective of the World Bank's environmental and social safeguard policies  is  to  prevent  and  mitigate  undue  harm  to  people  and  their  environment  in  the 

Page 11: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xi 

development  process.  These  policies  provide  guidelines  for  bank  and  borrower  staffs  in  the identification, preparation, and  implementation of programs and projects. The Mumias‐Rangala‐Kisumu  resettlement action  triggers  the World Bank's operational policy OP 4.12 on  Involuntary Resettlement  in  that  it  shall  require  [involuntary]  acquisition  of  land  as well  as  restrictions  of access  in  areas within  the  transmission  line Wayleave.  This  has  however  been  complied with through  the  ESIA  study  of  project  alternatives;  participatory wide  consultations with  PAPs  and other stakeholders have been conducted and; PAPs have been  informed   of their rights  including prompt  compensation  at  full  replacement  cost  for  loss  of  assets  attributable  to  the  project including assistance during relocation, and transitional support and development assistance.   Minimizing Resettlement and Associated Cost  The  social  and  economic  assessment  revealed  that  the  project  will  result  in  land  acquisition amounting  to  590.3  hectares  (1475.67  acres)  owned  by  eight  hundred  and  fifty  nine  (859) households.  It  will  affect  three  hundred  and  eighty  homesteads  leading  to  demolition  of  six hundred and twenty four structures in the different districts it shall traverse as shown in Table 1. Further, the project will lead to loss of at least one thousand six hundred and nineteen trees and loss of crops mainly sugarcane and Maize.  

Table 1: Summary of the number of Project Affected Persons and Property found along the proposed project route District     

Total number of  homesteads affected 

Total number  of structures to  be affected   

Total  number of  trees affected   

Total number of  affected households 

Total number  of persons  affected 

Total number of persons to be physically affected‐‐relocation 

Total acreage of land  affected 

Mumias  36  64  987  219  384  6  290.94  

Ugenya   24  31  250  110  186  0  146.42 

Gem   231  299  168  240  1386  6  493.3 

Emuhaya  52  138  160  146  312  24  306.3 

Kisumu North 

31  85  50  120   186  3  222.34 

Kisumu East 

6  7  4  24   36  3  16.37 

Totals  380  624  1619  859   2490  42  1475.67 

 

Page 12: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xii 

Resettlement displacements and disturbance impacts will be minimized through consultations and participation  with  the  PAPs,  redesigning  the  project  (facility  relocation/rerouting)  and  putting appropriate impact limitation and mitigation measures in the construction and design stages   Socio‐economic features of the project affected persons Residents in the project area are mostly the middle aged, 21‐70 years who form over 93% of the population. Nuclear families are the majority (71.3%), and 88.8% of the population are Christians. Land  in the project area has various ownership namely communal (91.7%),  individual (5.1%) and commercial  (3.2%).  62%  of  the  land  is  freehold  and  the  rest  is  either  traditional/communally owned  (28%)  or  leased  (1%).  The  land  to  be  affected  by  the  project  is  currently  used  for agriculture and settlement.  Majority (73.6%) of the PAPs owned residential property in which they live in with only a negligible proportion of 26.4% having rented the premises they occupy. 81.2% of the houses are built with blocks,  iron  sheets and wood and homesteads  consist of either  single or  clustered houses. The project  area  has  twelve  main  business  centres  namely  Mumias,  Lureko,  Sigomero,  Simerro, Bungasi, Sindindi, Yala, aya, Emukhaya, Maseno, Chulaimbo, Kisian and Riat. Infrastructures in the area included tarmac roads and communication is efficient through mobile phones. Existing water sources  include boreholes, piped water and rivers. Only 4 shops are  likely  to be affected by  the project at Emukhaya Trading Centre.  Majority (50.8%) of the residents carry out farming. Household  incomes are relatively  low below Ksh  25,000  per month  of  which  they  spent  80%  on  basic  needs  namely  food, medicine  and education. The main source of energy is electricity 55.8%. Gender disparity in the project area was evident with 28.8% of women having title in their names against 71.2 % of men. The main decision makers at the household level are male 61.6%, 11% of female make decisions and 27.4% indicated both partners make decisions.  Findings of the RAP Majority of  the population were not willing  to be resettled  far  from  their current sites. Further, most  of  the  respondents  wanted  to  be  relocated  together  with  their  community.  Property valuation by the residents was based at present market value in the area.  Resettlement policy and entitlements Compulsory acquisition occurs when  the  state has  to acquire  land compulsorily  for purposes of public  interest as entrenched  in the constitution, Section 75 (1).  In the case of Mumias‐Rangala‐Kisumu  transmission  line,  the acquisition  is guided by Compulsory Acquisition Act Cap 295, and Wayleave Act Cap 292 which authorizes the Government to carry out sewers, drains and pipelines through,  over  and  under  any  lands  and  whenever  crops,  structures  or  trees  are  affected  to compensate  for  it  promptly.  Further,  to  ensure  that  the  RAP  complies with  international  best 

Page 13: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xiii 

practice  as  regards  resettlement,  the  principle  implementing  agent,  KPLC  shall  bind  itself  to following all guiding principles of the World Bank O.P 4.12:  Valuation Methodology  Valuation  of  property  on  the Mumias‐Rangala‐Kisumu  transmission  line was  undertaken  using three methods  namely:  Comparison,  Investment  and  Cost  approach methods.  A  further  15% disturbance  allowance  was  provided  for  to  cater  for  disturbance/movement  of  the  affected people.  Resettlement site There were no specific Resettlement Sites  identified during  the RAP except  that  the community members preferred to be resettled  in the same community or with family members. Households with  small  parcels  of  land  and  those  that  depend  on  the  towns  for  their  livelihoods mainly  in Mumias District would like resettlement site to be developed with all necessary facilities to enable them  adequately  restore  their  livelihood  as  they understand  the  line  cannot be  relocated. This indicated that the Resettlement Developments Site to be earmarked should be  in an agricultural area  and  include  improvement  or  provision  of  better  residential  and  communal/social infrastructures, water sources, business centres and transport routes.  Compensation, Income and Livelihoods Restoration The major assets for which compensation will be paid are:  

i. Private houses and fences  ii. Farm land (cash and food crop loss)  iii. Private plantation (tree loss)  iv. Grazing land (fodder loss)  v. Public buildings and temporary loss to social services infrastructure;  

Considering that majority of the PAPs are farmers and small scale businesses, the main livelihood loses will  include crops, trees, business and commercial properties. Livelihood restoration should therefore target the two areas of  improving agriculture and small scale business development as well as enhancement of income generating activities through enhanced market linkages, provision of  relocation  assistance,  training  on  skill  development  and  capacity  building  on  areas  such  as enterprise,  job  creation,  agriculture,  community  participation  and  management,  Health  and Hygiene education and PAP’s empowerment. During project  implementation and operation,  it  is advisable that, local people whose livelihood is impacted by the project will get preference in jobs associated with the project construction.   

Page 14: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xiv 

Implementation of the RAP The  Mumias‐Rangala‐Kisumu  land  acquisition,  compensation,  relocation  and,  income  and livelihood restoration programs calls for an all inclusive and participatory organizational structure to manage the RAP. Such an organizational structure will include the following: 

i.  KPLC Resettlement Project Implementing Unit. The aim of this unit is to involve other key stakeholders  and  institutions  who  will  play  collective  roles  implementation  of  the Resettlement  Action  Plan  including  land  acquisition,  award  of  compensation  and resettlement  for  the  project.  Further,  KPLC  should  vote  in  adequate  resources  for implementing  the  RAP  as  outlined  in  the  budget.  This  implies  that  KPLC  should  be strengthened and endowed in terms of resources to implement the RAP.  

ii. Project Affected Persons Committee whose mandate will be  to conduct extensive Public Awareness and consultations with the affected people, ratify compensation rates and resolve disputes that may arise relating to resettlement process. 

All PAP’s would be resettled before commencement of the project. The RAP budget  is estimated to cost Kenya Shillings five hundred and eighty seven million, seven hundred and three thousand, seven hundred and  fifty  four and  fifty one cents.  (Ksh. 587,703,754.51),   which  is  inclusive of  the cost of  land purchase, compensation  for  lost structures, compensation  for  lost  trees and, crops, reconstruction  of  social  infrastructures  (schools,  trading  centres  and  a  church)  and  livelihood restoration programmes.  Participation and consultation Under this RAP, participation and consultation is aimed at ensuring that: 

i. All stakeholders are consulted and effectively  involved  in a two‐way communication with the project proponents; 

ii. All  relevant  and  accurate  information  is  provided  and  disclosed  by  the  proponent  to affected persons and communities; 

iii. Consultations with different stakeholders  is undertaken  through a  language and medium they are comfortable with; and  

iv. A  specific  and  transparent mechanism  for  the  recording  of  grievances  and  their  timely resolution is put in place.  

These objectives were achieved through interviews and group discussions as well as stakeholders and community public meetings. Further, a household census and socio‐economic survey of  the PAPs was conducted. These activities created awareness of the project and its implications on the community members thereby preparing them for eventual results.   Monitoring and supervision Monitoring  of  the  RAP  will  be  carried  out  during  the  whole  process  of  land  acquisition  and resettlement. It will involve both the internal (conducted PIU as well as overall monitoring by the PAPC) and external monitoring (conducted by an External consultant). Under these activities, KPLC Project  Office  will  maintain  the  basic  database  of  land  acquisition,  house  relocation  and 

Page 15: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xv 

resettlement. It will monitor all of the relocated households, and supervise the whole process of resettlement preparation and implementation.   Internal monitoring of the resettlement performance will be based on set timelines as per the RAP and  have the following indicators:  

• Acquisition of land, building and other structures and; destruction of crops and trees 

• Compensation and re‐establishment of affected owners/individuals 

• Re‐establishment of community resources e.g  health, educational and social facilities 

• Introduction of nuisance factors 

• Changes to homestead livelihoods 

• Changes in social organization and access to infrastructure 

• Population influx  External RAP monitoring if need be will be conducted by an External consultant. It will Endeavour to accomplish the following objectives: 

• Review the results and success of internal monitoring  

• Assess whether relocation objectives have been met  

• Assess general efficiency of relocation and formulate lessons for future guidance; and 

• Determine overall adequacy of resettlement and compensation process  Grievance and appeals Grievance  redress mechanisms  are  essential  tools  for  facilitating  PAPs  to  voice  their  concerns about the resettlement and compensation process as they arise and are fundamental to achieving transparency  in  the  acquisition  and  resettlement  processes.  The  key  grievance  subject matters likely  to  arise  for  the Mumias‐Rangala‐Kisumu  transmission  line  include,  advance  provision  of timeframe for relocation; values for land, building and plants; ownership rights and; resettlement assistance,  relocation  as  well  as  disturbance  and  compensation  of  livelihoods.  During implementation of  the RAP, grievances will be  launched  through either  filling a  specifically pre‐designed compliant form and appending the PAPs signature and formally submitting it to the GRC office. The proposed procedures of Grievances Referral and Redress  incase of Mumias‐Rangala‐Kisumu transmission RAP will involve various steps as follows. 

i. PAPs are  informed of their  losses and entitlement  in writing through personal contact by the PIU.  

ii. If satisfied, the PAP claims resettlement payment from the PIU.  iii. If  dissatisfied  or  the  PAP  do  not  clearly  understand  the  entitlement/any  aspect  of  the 

resettlement plan,  s/he  approaches  the PIU  for  clarification.  The PIU makes  a note  and explains the unclear issues to the PAP according to the RAP. If the issue(s) are resolved, the PAP collects the payment from the PIU. If not solved PAP moves to step 3. 

iv. The PAP writes up or a fills a complaints form appended with his signature formally to the Grievance Redress Committee  (GRC)  at  their office. Within  two weeks,  the GRC holds  a 

Page 16: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xvi 

session with the aggrieved PAP, minutes recorded and duly constituted. If resolved, the PIU approves and the PAP collects his/her entitlements.  

v. If  necessary,  the  Project  Affected  People  Committees  (PAPC)  will  be  asked  to  provide recommendations as to how the grievance is to be addressed. If deemed necessary by the PAP committee the case will be re‐investigated and, depending on the nature of the issue, referred to the a court of law for settlement  

 Cost estimates The cost estimates for the total value of land to be acquired is Kenya Shillings Three Hundred and Thirty Nine Million,  Five Hundred  and  Seventy  Six  Thousand,  Seven hundred  and  Seventy  Four Only  (Ksh.  339,576,774) while built  structures  are  estimated  to  cost  about Kenya  Shillings One Hundred and Ten, Million, Two Hundred and Fifty Nine Thousand, Two Hundred  (Ksh. 110,259, 200). In addition, 15% disturbance allowance will be legally added to the declared value as stated by Compulsory acquisition Act. Summary of cost estimates of the value of  land to be acquired  in each district the line shall traverse is provided in table 2.  

Table 2: Itemized costs of affected property in districts within project areas   

District   

Total  costs of land 

Total costsof trees 

Total costs of structures 

Total cost of crops 

GRAND TOTALS 

 Mumias  98660371.15  100,800  47,443,200  24665092.79  170,869,464 

Ugenya   61269927.6  96,000  24,972,800  15317481.9  101,656,210 

Gem   110854002  30,000  15,859,200  11117276.1  137,860,478 

Emuhaya  16308600  2400  2352000  815430  19,478,430 

Kisumu North  34913750.4  593,600  12,785,600  4,257,497  56,807,944 

Kisumu East  17570123.57  147,305  6,846,400  1,104,300  26,772,428. 

Totals  339,576,774.00  970,105  110,259,200  57,277,078.  513,444,954. 

 Conclusions and Recommendations  The  proposed  Mumias‐Rangala‐Kisumu  Transmission  Line  will  lead  to  loss  of  property  and displacement of a number of PAPs. There  is therefore a need to ensure that the  identified PAPs are adequately compensated with the aim of  improving or restoring their  livelihoods to the pre‐impact standards. To realize this objective, the implementing agency (KPLC) should undertake the following activities: 

• Continuous public consultation making the PAPs aware of the RAP schedule in adequate time. 

• Appropriate amount of land is allocated; 

Page 17: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

xvii 

• Land where PAPs are resettled are provided with necessary infrastructure facilities and services and   improved farming methods; 

• All payments should be made before demolition commences;  

• Compensation    for   structures   should    include the    full   cost   of   materials, transport and  labour  required  for  reconstructing  buildings  of  similar  surface and  standing;   

Page 18: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

1.0  INTRODUCTION  1.1 Scope of the RAP  Otieno  Odongo,  also  referred  to  as  the  Consultant,  was  contracted  by  KPLC  to  develop  a Resettlement Action Plan (RAP) for the proposed 132kV Mumias‐Rangala‐Kisumu transmission line. The RAP was developed to ensure that the PAP’s livelihoods are restored as much as possible and the project impacts on them are minimized to acceptable standards during the RAP implementation phase. The scope of work undertaken during the RAP preparation phase included:    

• Project description; 

• Analyzing objectives of the resettlement programmes; 

• Analysis  and  evaluation  of  potential  project  impacts    through  identification  of  the  PAP, estimating their number and evaluating the impacts of the project on them; 

• Conducting  socio‐economic  studies  including  census  survey,  land  tenure  and  transfer systems,  public  infrastructure  and  social  services  which  will  be  affected,  social‐cultural characteristics  of  community  to  be  affected  and  patterns  of  social  interactions  in  the affected communities, including social networks and social support systems;  

• Analysis of the legal framework; 

• Analysis of  institutional  framework  covering  the  identification of  agencies  responsible  for resettlement activities, an assessment  of the institution capacity of such agencies and steps that  are  proposed  to  enhance  the  institutional  capacity  of  the  agencies  responsible  for resettlement implementation; 

• Evaluating  affordable  and  accessible  procedures  for  grievances  redress  mechanisms  for third party settlement of disputes arising from resettlement including judicial resources and, community and traditional settlement mechanism; 

• Assessing  the  appropriate  organizational  framework  for  implementing  resettlement including  identification  of  agencies  responsible  for  delivery  of  resettlement measure  and provision of services, arrangements  to ensure appropriate coordination between agencies and jurisdiction involved in implementation.  

• Developing  an  implementation  schedule  covering  all  resettlement  activities  from preparation  through  implementation  including  target  dates  for  the  achievement  of expected  benefits  to  resettlers  and  hosts.  The  schedule  indicates  how  the  resettlement activities are linked to the implementation of the overall project; 

• Costing  items  and  all  activities,  including  allowances  for  inflation, population  growth  and other  contingencies  timetables  for  expenditure,  sources  of  funds  and  arrangements  for timely flow of funds and funding of resettlement,  if any  in areas outside the jurisdiction of the implementing agencies; and 

• Listing monitoring of resettlement activities by the implementing agency, supplemented by independent monitors as  considered appropriate by World Bank  to ensure  complete and objective  information performance monitoring  indicators  to measure  inputs, outputs  and outcome for resettlement activities.   

Page 19: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

1.2 Project Background  Kenya Power and Lighting Company Limited (KPLC), also referred to as the implementing agency, is a  limited  liability  company  responsible  for  the  transmission,  distribution  and  retail  of  electricity throughout Kenya. The Proponent owns and operates  the national  transmission and distribution grid, and as at June 2009 was retailing electricity to approximately 1,262,309 customers throughout the nation. The Proponent proposes to construct and operate approximately 101.56 Km of single circuit 132 kV transmission line between Mumias and Kisumu.    The Government of Kenya plans to increase access to electricity in Kenya tenfold from the current 4%  in  the  rural areas  to about 40% by 2020. To do  this,  the  transmission  lines network  is being considered  for  construction  and  upgrading  with  the  communication  system  required  for  line protection and management purposes.   The generating system  in Kenya consists of hydropower as well as  thermal power plants,  in  total 1,197 MW installed capacity. The largest power plant is Gitaru hydropower plant with an installed capacity at 225 MW  (as at the end of FY 2007). The transmission system voltage as of June 2007 consisted of 1,323 km 220 kV and 2,122 km 132 kV. Almost all  the 220 kV and 132 KV  lines are single circuit  lines with the conductor coat at 220 kV and Wolf or Lynx for more than 50 % of the 132  kV  lines.  Kenya  is  today  interconnected with Uganda  through  a  132  kV  double  circuit  line. (Norconsult AS, August 2009).  The KPLC least cost power development plan identified various 132 KV developments for improving the performance of the national grid network to cater for the increasing load growth and meet the objectives  of  2030.  To  meet  this  objective  KPLC  intends  to  construct  a  single  circuit  132KV transmission  line  from Mumias  via Rangala  to Kisumu. The proposed  transmission  line offers an opportunity  to  expand  the  dedicated  telecommunications  network  so  as  to  offer  enhanced protection of the lines and upgrade the communication system. (Norconsult AS, August 2009) 

1.3 Project Description  The proposed project is part of the project proponent’s energy access scale‐up program, which has the following objectives:  

• Extending the transmission of new 132 kV line from Mumias‐Rangala‐Kisumu, as well as new and  reinforced  transmission  lines with  the aim of  reducing  technical  losses and  improving voltage conditions, thereby coping with additional demand. 

• Increasing access to electricity to 20% by 2010 by accelerating connection rates; 

• Voltage upgrading to increase supply capacity and reduce system losses; 

• Provide alternative electricity supply paths to increase reliability and improve power quality in the regions. 

Currently electricity is accessible to less than 20% of the total population and approximately 5% of rural population. The Government’s goal is to accelerate access rate to 20% of rural population by 2010 and to at least 40% by 2020. To achieve this goal, Government has prepared the Energy Scale 

Page 20: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

up  Program  covering  the  period  2008  to  2017.  This  would  be  approached  not  only  from improvement  and  expansion  of  the  network,  but  also  on  raising  the  generation  to match  the demand. A main criterion when concluding on the adopted conceptual design has been to ensure that  the  transmission  line  is  designed  in  a  safe,  cost  effective  and  reliable manner.  This  study provides  the project proponent with considerations on social‐economic  impacts of  the project as proposed.  Installation of the proposed line will require a way leave acquisition throughout its stretch. To meet requirements  of  the  proposed  project,  land  for  the  way  leave  will  be  expropriated  from  the community members as no public  land exists  in the project area. The area of  land to be acquired from the community members measures 590.3 hectares (1475.67 acres). 

1.4 Project Location The proposed project  involves  construction of approximately 101.2  km  stretch of  a high  voltage transmission  line  from Mumias‐Rangal‐Kisumu. The proposed  transmission  line  traverses  through six districts namely Mumias, Ugenya, Gem, Emukhaya, Kisumu West and Kisumu East districts as shown on the way leave map (figure 1 and 2).   

Figure 1: Location of Mumias‐Rangala section of the Transmission Line  

 

Page 21: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

 

       Figure 2: Location of Rangala­Kisumu section of the Transmission Line 

 

1.5 Objectives of the Resettlement Action Plan  The main objective of the RAP is to develop a programme to enable restore livelihoods of the PAPs to the pre‐impacts levels. To achieve this objective, a socio‐economic survey was conducted in the project area to gather  information on the project  impacts on the PAP’s. The  information gathered identified the nature and diversity of the potential  impacts on the PAP’s assets, livelihoods, public infrastructure and households.   The objectives of the RAP were to:  

• Identify  all  the  Project  Affected  Persons  (PAPs)  including  their  gender,  vulnerability, household and assets to be compensated;  

• Develop an inventory of all assets to be affected or damaged;  

• Value  the  affected  assets  at  full  replacement  value  and  determine  any  supplementary payments  e.g.  unit  price  lists  and  itemized  breakdowns  of  compensation  offers  and  participation;  

• Evaluate the available grievance procedures and redress mechanisms as well as the existing institutional arrangements within the Kenyan law; 

• Develop Monitoring and Evaluation Parameters;  

• Develop a timeline for the RAP and prepare a Budget for all activities.   

1.6 Justification for Resettlement Action Plan  The identified line route will lead to physical displacement of people, loss of shelter, assets, income sources and  livelihood, and restriction of access  to economic resources. The Resettlement Action Plan will help to define the resettlement and compensation necessary as a result of implementing the Mumias‐Rangala‐Kisumu power transmission line project, in accordance with the World Bank’s 

Page 22: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

Involuntary Resettlement Policy and relevant sections of the Operations Manual together with the Laws of Kenya.  

 The  RAP  ensures  that  all  Project  Affected  Persons  are  to  be  compensated  for  their  losses  at replacement cost at current market value and to be provided with rehabilitation measures where applicable,  in  order  to  assist  them  to  improve  or  sustain  their  pre‐project  living  standards  and income generating capacity.  

1.7 Land Compensation and Wayleave Acquisition  KPLC  has  guidelines  on wayleave  acquisition  and  land  compensation which  are  outlined  in  the wayleave acquisition procedures and the Resettlement Policy Framework (RPF) for similar projects undertaken by the organization.  The objectives of Wayleave Acquisition procedure  is to ensure that quality and binding wayleaves consents/approval  are  obtained/acquired  effectively  and  correctly  by  following  strict  laid  down rules to ensure that the construction of power line is done to satisfactory levels and to the highest standard  compliant  to  statutory  ISO  9001:2000.  The  wayleaves  acquisition  is  a  compulsory procedure  applied  to  all power  lines network  throughout KPLC’s  regions of operation. Acquiring wayleaves legalizes the building of power lines and is undertaken using the documented operating procedures listed below.   

i. Acquisition of maps and plans‐ The purpose of acquisition of maps and plans  is to provide the  right  tools  (data)  and  information  for  survey  and  quality  design  requirements  in compliant to statutory ISO 900:2000 requirements; 

ii. Property Damage Assessment and Payments –The purpose of this operating procedure is to record all damaged properties, cost them using set and approved KPLC rates and organize payments  for  compensating  affected  people.  The  aim  of  this  procedure  is  to  provide satisfactory  service  and  enhance  a  warm  relationship  with  KPLC’s  direct  and  indirect customers in order to achieve quality service compliant to ISO 9001:2000; 

iii. Sorting  out wayleaves  trace  infringement‐The  purpose  of  this  operating  procedure  is  to clear the wayleaves of traces of infringements in order to ensure that risk to life is reduced in the event of high voltage lines collapsing on human habitation and at the same time avail smooth passage or access to power line maintenance teams for maintenance, disconnection of power incase of emergencies or in case of necessity to repair the line and to ensure the safety of the power line. The wayleaves trace inspection is normally carried out for all power line networks within the country.  

 The process of wayleave acquisition according to KPLC operating procedures are;  

• The Wayleaves Officer  identifies  if  Public  approvals  are  required  or wayleave  agreement  forms are necessary for an identified wayleave;  

• If  Public  approvals  are  required,  application  for  public  approval  is  made  with  colored drawings attached; 

Page 23: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

• If wayleave  agreements  are  required  they  are  prepared  and  a  list  of  the  plot  numbers  affected are also prepared to enable carry‐out personal title searches  and to determine the registered land owners and their contacts;  

• The names are inserted to each wayleaves agreement form prepared;  

• The wayleaves officer allocates the agreement form to wayleaves assistant to physically look for the landowners to sign the agreements forms; 

• The wayleaves officer  counter  check  signed agreement  forms  and  they are  recorded and filed. Where  land owners dissents, Project/Design  is notified and  further negotiations are arranged or Project/Design Engineer explores alternative route  if negotiation  fails and  the exercise is repeated;  

• Once the public approval is obtained and wayleave consents granted, the Design   Engineer notifies Construction works to proceed.  

1.8 Guiding Principles and objectives for the RAP In order to ensure that the RAP complies with international best practice as regards resettlement, the principle implementing agent, KPLC shall bind itself to World Bank safe guard policy (O.P 4.12) on involuntary resettlement summarized as follows  

• Resettlement must be avoided or minimized 

• Genuine consultation must take place 

• Establishment of a pre‐resettlement baseline data 

• Assistance in relocation must be made available 

• A fair and equitable set of compensation options must be negotiated 

• Resettlement must take place as a development that ensures that PAPs benefit 

• Vulnerable social groups must be specifically catered for 

• Resettlement must be seen as an upfront project cost 

• An independent monitoring and grievance procedure must be in place 

• World Bank’s operational procedure on forced resettlement 

Page 24: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

2.0 LEGAL FRAMEWORK   2.1 Introduction The  Kenyan  Law  recognizes  three  categories  of  land  ownership  in which  basic  or  radical  title  vests  namely:  ‐  (i)  Government‐owned  land  (ii) Trust  land  and,  (iii)  Private  land. Government land  refers  to  land  that was  vested  in  the  government of Kenya by  section 204  and 205 of  the constitution that was contained in the schedule 2 of the Kenya independence order in council 1963 and section 21,22,25,and 26 of the constitution of Kenya (amendment) Act 1964. Trust land is the land  that  is  declared  to  be  trust  land  and  defined  in  section  114  of  the  Constitution  of  Kenya. Private land is land that is registered in accordance with any of the laws that provide registration of title. Land may be registered in the name of an individual or company. According to the constitution section 75, private  land can only be acquired when  it  is proved that there  is “overriding  interest” which allows  the government  to compulsorily acquire  the  land after proving  that  it’s needed  for public purpose. The acquisitions require fully and prompt compensation of the land owners. 

2.2 Summary of Relevant Acts. Kenya has  several  statutes  that handle  the  issue of  land and  the development of  infrastructure. These are: 

• Compulsory acquisition Act Cap 295 

• The Wayleave Act Cap 292 

• Government Lands Act Cap 280 

• Land Titles Act Cap 282  

• Registration of Titles Act Cap 281  

• Land (Group Representatives) Act Cap 287  

• Trust Land Act Cap 285  

• Registered Land Act Cap 300  

• Land control Act 302 

• Mining Act 306 

• Agriculture Act 318 

• Environmental Management and Co‐ordination Act 

2.3 Land Acquisition Act Cap 295 The Act applies where public  interest overrides private  interest as  indicated  in  section 75 of  the Constitution of Kenya. The  initiatives and procedures of acquisition  is  set out  in  the Act and  the following highlights are salient, 

i) Section  6(1),  the Minister  has  to  be  satisfied  that  the  land  required  is  for  public purpose by a public body before he directs the commissioner of  lands to acquire  it compulsorily 

ii) Section 6(2),the commissioner of lands then publishes the notice of acquisition iii) Section  9(1),  the  commissioner  holds  an  inquiry  for  hearing  of  claims  by  persons 

interested in the land 

Page 25: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

iv) Section 8,  the Act  recommends  that  full  compensation  to be paid promptly  to  all persons interested in the land. 

This is a critical Act when dealing with the acquisition of the corridor because it traverses through private land which has to be acquired under the Act. 

2.4 The Way leaves Act Cap 292 The Act authorizes  the Government  to  carry out  sewers, drains and pipelines  through, over and under any  lands whatsoever.  It however cautions  that “....but may not  in so doing  interfere with any  existing  buildings”.  Where  any  developments  are  affected,  the  Act  recommends  for compensation. Section 6 (1), “the Government shall make good all compensation to the owner of any tree or crops destroyed or damaged”. The Act further explains the process of resolving conflicts that arise in determining the compensation value. 

2.5 Government Lands Act Cap 280 Under this act the president through the commissioner of lands, allocates any un‐alienated land to any person he  so wishes. Such a  land once allocated  is held as a grant  from  the government on payment of such rents to the government as the government wishes.  

2.6 Registered Land Act Cap 300 Under  this act any person may acquire absolute ownership  to any  land once he or she has been registered as the absolute owner. On registration such a person acquires freehold interests on the land. Freehold implies absolute ownership. Such land becomes private land and this is the form of tenure that many of the people on the site enjoy. 

2.7 Trust Land Act Cap 285 All land, which is not registered under any Act of parliament, is vested in local authorities as Trust. In  these Trust Lands a person may acquire  leasehold  interest  for a specific number of years. The local authorities retain the powers to repossess such land for their own use should the need arise.  

2.8 Land control Act 302 This act restricts transfer of land and as such has some bearing on the flexibility with which affected farmers  can  acquire  replacement  land.  It  also  controls  subdivision  of  agricultural  land  to uneconomical sizes. 

2.9 The Mining Act 306 This  act  makes  direct  reference  to  the  responsibility  of  the  holder  of  a  mining  lease  for  the provision of compensation  to people who hold  land  for any disturbances created  (section 26). A section 48 and 32 ensures that a developer (subject to section 26) has the right to remove timber from a site upon which the lease is held. 

2.10 The Agriculture Act 318 This  act  provides  for  the maintenance  of  stable  agriculture  and  the  conservation  of  soil  and  its fertility.  

Page 26: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

2.11 Environmental Management Co­ordination Act (1999) This act makes provision for adequate environmental investigations to be undertaken in respect of certain  listed  developments.  The  need  to  carry  out  an  environmental  Impact  Assessment  (EIA) before any listed development may take place, are provided for in the act. 

2.12 World Bank Group Safeguard Policies  According to the World Bank safeguard policies,  

• Displaced persons should be meaningfully consulted and have opportunities to participate in planning and implementing resettlement programs  

• Displaced  persons  should  be  assisted  in  their  efforts  to  improve  their  livelihoods  and standards of living or at least to restore them, in real terms, to pre‐displacement levels or to levels prevailing prior to beginning of project implementation, whichever is higher. 

• Avoiding  or  minimizing  involuntary  resettlement  where  feasible,  exploring  all  viable alternative  project  design;  where  it  is  not  feasible  to  avoid  resettlement,  resettlement activities  should  be  conceived  and  executed  as  sustainable  development  programs, providing sufficient  investment resources  to give  the persons displaced by  the project  the opportunity to share in project benefits.  

• The production systems of a community are safeguarded to the extent that guarantees their livelihoods and that their skills base remain relevant regardless of the resettlement site. The policy objectives are also designed to minimize kinship group dislocation that might subject the affected persons to unfair competition when mutual help is diminished or lost.  

2.13 Land Legal Issues Interests  in  land  broadly  fall  into  two  groups.  Rights  that  are  held  through  traditional  African systems and  rights  that derive  from  the English  system  introduced and maintained  through  laws enacted  first by colonial and  later by  the national parliament. The  former  is known as customary tenure bound  through  traditional  rules  (customary  law). The  latter body of  law  is  referred  to as statutory tenure, secured and expressed through national law, in various Acts of Parliament as set out above. 

a) Customary Land Tenure This refers to unwritten land ownership practices by certain communities under customary law. Kenya being a diverse country in terms of its ethnic composition has multiple customary tenure systems,  which  vary  mainly  due  to  different  agricultural  practices,  climatic  conditions  and cultural  practices.  However  most  customary  tenure  systems  exhibit  a  number  of  similar characteristics as follows: First,  individuals or groups by virtue of  their membership  in some social unit of production or political  community  have  guaranteed  rights  of  access  to  land  and  other  natural  resources (Ogendo, 1979). Individuals or families thus claim property rights by virtue of their affiliation to the group. Secondly,  rights of  control are  rested  in  the political authority of  the unit or community. This control  is derived  from sovereignty over  the area  in which  the  relevant  resources are  located. Control  is  for  the purpose of  guaranteeing  access  to  the  resources  and  is  redistributive  both spatially and intergenerational. Its administrative component entails the power to allocate land 

Page 27: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

10 

and  other  resources within  the  group,  regulate  their  use  and  defend  them  against  outsiders (Ogolla and Mugabe, 1996). Thirdly,  rights  analogous  to  private  property  accrue  to  individuals  out  of  their  investment  of labour in harnessing, utilizing and maintaining the resource. Thus the present cultivator of some piece of land has the greatest rights to it. These rights transcend mere usufruct and encompass transmission  and  in  some  communities  transfer  (Elias,  1956).  Lastly,  resources  that  do  not require extensive investment of labour or which by their nature have to be shared, for example, common  pasturage,  are  controlled  and  managed  by  the  relevant  political  authority.  Every individual member of the political community has guaranteed equal rights of access thereto. The regulatory mechanisms  imposed by  the political units  such as exclusion of outsiders,  seasonal variations in land use and social pressure ensured sustainable resource utilization. This mode of ownership  in Kenya  is currently governed by  the Trust Land Act by which all  land  in  the  rural areas which is neither government land nor individually owned is vested in the county council in trust for the residents living there. 

 b) Statutory Tenures 

i) Freehold tenure This  tenure  confers  the  greatest  interest  in  land  called  absolute  right  of  ownership  or possession of land for an indefinite period of time, or in perpetuity. The Registered Land Act (RLA)  Cap  300  of  the  Laws  of  Kenya  governs  freehold  land.  The  Act  provides  that  the registration  of  a  person  as  the  proprietor  of  the  land  vests  in  that  person  the  absolute ownership of  that  land  together with all  rights, privileges  relating  thereto. With  regard  to the areas with  lower agricultural potential, mostly arid and semi arid parts of  the country where the dominant land use was pastoralism, a different registration system was instituted in 1968. This  is  the  regime of  Land  (Group Representatives) Act. Here  the  registration of group ranches was viewed as a compromise between individual ownership and the need for access to wider resources in dry lands. Under this system ‘communal lands’ are divided into smaller ‘ranches,’ which are then registered in the names of group representatives (three to ten members) elected by the members of the group (Wanjala 2000). Every member of the group has rights in the ownership of the group  land  in undivided shares. The members are entitled  to  reside  therein  free  of  charge  with  their  family  and  dependants  and  make exclusive use for the grouped ranches resources.  ii) Leasehold Tenure Leasehold  is  an  interest  in  land  for  a  definite  term  of  years  and may  be  granted  by  a freeholder,  usually  subject  to  the  payment  of  a  fee  or  rent  and  is  subject  to  certain conditions  which  must  be  observed.  For  government  land  the  government  also  grants leases,  the  local  authorities  for  trust  land  and  by  individuals  or  organisations  owning freehold  land. The maximum  term of government  leases granted  in Kenya  is 999 year  for agricultural land and 99 years for urban plots. There are few cases of 33 years leases granted by government in respect of urban trust lands. The local authorities have granted leases for 50 and 30 years as appropriate.  

Page 28: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

11 

c) Public Tenure This  is  land  owned  by  the  Government  for  own  purpose  and  which  includes  unutilised  or unalienated  government  land  reserved  for  future  use  by  the  Government  itself  or may  be available to the general public for various uses. The land is administered under the Government Lands  Act  Cap  280.  These  lands  are  vested  in  the  president who  has,  normally  through  the Commissioner of Lands, powers to allocate or make grants of any estates, interests or rights in or over unalienated government land. Categories of government land include forest reserves, other government  reserves,  alienated  and  unalienated  government  land,  national  parks,  townships and other urban centres and open water bodies (GOK, 1996). The Government Lands Act does not  contain  any notion of  trusteeship by  government of  the  land on behalf of  the people of Kenya. Indeed the government at times acts as a private owner and allocates parcels to those in its favour. d) Other Interests These include: 

• Reservations of other government or trust land to government ministries, departments or parastatals for their use. 

• Minor interest such as easements, wayleaves or temporary occupation licences. 

• Non‐formalised  defacto  tenure  by  which  people,  individually  or  in  groups  invade  and occupy other peoples government land particularly in the major urban centres of Nairobi, Mombasa and Kisumu. 

The issue of land ownership has been at the centre stage of local politics in Kenya for a long while; this is expected to improve with the implementation of land policy which was approved in 2009.  

Page 29: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

12 

3.0 SCOPE OF LAND COMPENSATION, WAYLEAVE AGREEMENT AND RESETTLEMENT 3.1 Source of data  Both secondary and primary data was collected during the survey of the project area; the primary data were collected through the qualitative and quantitative methods of data collection. Qualitative data  was  collected  through  field  visits/site  walks,  public  and  stakeholders  consultation  while quantitative data was  collected  through  the use of  sampled questionnaires.  The  secondary data was collected through literature review which included study of the following documents: 

• Policies, Acts and Regulations;  

• District Development Plans; 

• Project area topographical and cadastral maps; 

• Previous project study documents; and 

• Literature materials on project including those on IBA, Plant Species, Culture, Power Project Installation and Management  among other project parameters.  

3.2 Survey Methodology and schedule Detailed  field  surveys  for  this  study were  undertaken within  the  proposed  project  area  and  its surroundings by a team of experts comprising of the socio‐economist, environmentalist, surveyor and land valuer. These consultations were conducted through: 

• Socio‐economic survey and census/inventory of all PAPs including their properties. This was undertaken from 7th October 2009 to 11th November 2009 as presented in Appendix 3. 

• Detailed  Focus  Group  Discussions  and  key  informant  interviews  were  held  with stakeholders. This was also undertaken from the 7th October 2009 to 11th November 2009 and follow‐up meetings held from 15th ‐25th May 2010 in the entire project area. 

3.3 Limitations of study The study faced a number of constraints that: While World  Bank  Policy  4.12  recognizes  the  imperative  need  to  offer  compensation  to  those whose land is affected by government activities, such as compulsory acquisition where such land is envisaged to be used for the public good, the current Kenyan  legislation  is silent on resettlement.  The  scope of  coverage of Kenyan  legislation and  the World Bank Policy 4.12 differs as well. The  World    Bank    Safeguards    favour    a    policy    of  avoidance    or   minimization    of    involuntary  resettlement   and recommends the design of appropriate mitigation provision    in case   avoidance  or  minimisation  is not possible.  Whereas both recognize customary tenure as equivalent to legal title, the World Bank Policy 4.12 extends beyond this principle and recognizes informal occupancy as a form of customary tenure so long as such  informal occupancy can be established prior to the project  cut‐off  date.  Therefore,  in  accordance  with  the  legal  agreement  of  the  credit  for  the development of the project, the preparation of this RAP has been executed in line with the policies and guidelines as set out in the World Bank Policy 4.12 which emphasises  that  affected  people  be  provided   with    compensation    at    replacement    cost    and    supported  during    the    transitional  period  to  improve  or  at  least  restore  their living  standards  to  pre‐displacement  levels.  The  Kenya  system recognises only title  holders as bonafide property owners while under OP  4.12,  lack  of    legal    title    is    no    bar    in    extending    assistance    and  support  to  those  affected  by  the investments.  

Page 30: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

13 

3.4 Right of way  According to wayleaves Act, the Government is authorized to carry out sewers, drains and pipelines through, over and under any lands whatsoever. It however cautions that “....in so doing should not interfere with any existing buildings”. Where any structures, trees and crops are affected, the Act recommends  for  compensation. Whenever  a  conflict  arises on determining  compensation  value, the Act further explains the process of resolving such conflicts. 

3.5 Impacts on Land and structures Linear  resettlement  describes  projects  having  linear  patterns  of  land  acquisition  (highways, railways, canals, and power transmission  lines).  In sparsely populated rural areas, a  linear project such  as  an  electric  transmission  line  may  have  minimal  impact  on  any  single  landholder. Compensation  is  characterized  by  a  large  number  of  small  payments  for  the  temporary  loss  of assets  such  as  standing  crops.  If well  designed,  linear  projects  can  easily  avoid  or minimize  the demolition of permanent structures. Linear  resettlement contrasts with site specific  resettlement because of the problems that  frequently arise when resettlement actions have to be coordinated across multiple administrative  jurisdictions and/or different cultural and  linguistic areas. Mumias‐Rangala‐Kisumu transmission power  line  is a typical  linear project and  if well designed, can easily minimize demolition of permanent  structures. The  total  amount of  land  to be acquired  is 590.3 hectares (14575.67 acres).  The proposed project will  lead to demolition of several buildings  including residential houses and communal social infrastructure such a church. In total six hundred and twenty four (624) structures are  likely to be affected by the project; of which  four  (4) are commercial outlets, one  is a church and the rest are residential houses. Most of the commercial buildings to be affected were made of masonry stones beneath GCI sheets roof on trusses and parallels.   Loss of Trees  The proposed project will not only  lead to acquisition of  land and structures but also of trees. At least  one  thousand  six  hundred  and  nineteen  (1619)  would  be  lost  to  pave  way  for  the development of the transmission line.   Loss of Crops  The area to be acquired passes through several sugarcane plantation and maize farms. Depending on the time of project implementation, it was estimated that at least crops worth Kshs. 57,277,078 will be cleared to enable put up the transmission line.  

3.6 Impact of relocation on Services  The  community members obtained  fresh water  supply mainly  from  the  streams and water wells found within their neighborhoods apart from those in area like Sidindi, with water supply from the Siaya‐Bondo  (SIBO) and Winam‐Gulf both of  Lake Victoria South Water and Sewerage Company. Sanitary management was mainly through the use of pit latrines. Most areas had adequate access either through the tarmac Mumias‐Rangala‐Kisumu Road or earth roads in the area. The areas with 

Page 31: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

14 

the  least  road network were  found  in Ugenya, Gem, Emukhaya,  Kisumu West  and Kisumu East. Hence relocation will require development of such infrastructural services.   

Page 32: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

15 

4.0 MEASURES TO MINIMIZE WAYLEAVE AGREEMENTS AND LOSSES Construction  of  the Mumias‐Rangala‐Kisumu  transmission  line will  lead  to  land  acquisition  and resettlement as well as  limited access  to  land  traversed by  the  line. Consequently,  resettlers are expected to take some time to recover their production and livelihoods. It is therefore important to minimize displacements and disturbances arising from land acquisition in line with the World Bank OP 4.12. This will be realized through consultations and participation with the PAPs, redesigning the project  (facility  relocation/rerouting)  and  putting  appropriate  impact  limitation  and  mitigation measures in the construction and design stages which are detailed in the following paragraphs. 

4.1 Consultation and participation During the ESIA, the study interviewed people from all walks of life on the construction of project as well  as  efforts  that  should  be  put  in  place  to  mitigate  against  adverse  impacts.  The  PAPs participated in the establishment of the RAP by generating primary resettlement opinions and data base.  Further,  PAPs  will  determine  the  final  version  of  the  RAP  and  participate  during  its implementation in the following ways: 

i. Assisting in the update of the detailed site investigation of private and community assets ii. Negotiation of compensation agreements  to  fully  reflect  resettlers’  interests and opinions 

and transparency of the KPLC resettlement work iii. Regular Consultation Meetings attended by PAPs to keep the communities informed of the 

RAP progress and to continue soliciting opinions and proposals from the affected people. iv. Dissemination  and  sharing  of  information  about  relevant  policies,  laws  and  regulations, 

compensation criteria, and others 

4.2 Impact limitation measures in the design stage The  field  studies  and  comments  obtained  from  the  community  members  indicated  that  the proposed way leave would be difficult to re‐align to enable avoid acquisition of structures especially for the densely populated Shivale and Angola villages  in Mumias  town. Sections between Kisumu Mamboleo to Kisian will also limit re‐alignment of the line due to presence of the airport flight, the Lake Vitoria and  the Kisian Hills.  It was noted  that  the presence of  the Nzoia River  limits  the  re‐alignment of the power  line to  less densely populated areas. The community members stated  it  is advisable that all the affected people be resettled at one place to enable them adapt easily to their new areas of settlement.  

4.3 Preliminary evaluation of alternatives The  Consultant  identified  community  relocation  sites  and  ensured  the  involvement  of  affected people in participatory process to identify sites. It was noted that except for a few farmers (8.5%) who stated that resettlement site does not matter, majority of the PAP wanted to be resettled  in the  same  community  or  compensated  with  cash  grant  (65%)  equivalent  to  loss  they  were  to experience so that they would settle on areas of their choice, they also wanted training to do other businesses. 

4.4 Impact mitigation measures in the construction stage Minimizing impacts during construction will include:  

Page 33: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

16 

• Hiring existing rental houses instead of establishing camps. This should be complemented by hiring of local residents who would reside in their homes 

• Establishing  access  roads  on  existing  tracks  for  construction  vehicles  working  on  the transmission  line.  This  would  also  limit  social  disturbances  and  destruction  of  the environment. 

• Construction  of  pole  foundations  and  laying  tension  lines  will  be  carried  out  after  the harvest of crops so as to minimize the damage of crops 

• It is proposed that all those that shall be affected by the project should be compensated to ensure that their livelihoods have improved or restored to the pre‐impact status. 

Page 34: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

17 

5.0 SOCIO­ECONOMIC FEATURES OF THE PROJECT AFFECTED PERSONS 

5.1 Sources of Data The RAP data sources and analysis was undertaken by a team of experts comprising of the socio‐economist,  environmentalist,  surveyor  and  land  valuer.  The  main  sources  of  data  utilized  to document  the  status  of  the  project  area  and  identify  the  PAPs during RAP,  including  a  detailed inventory of their assets, livelihoods, social interactions and associations were:  

i. Desktop  review  of  relevant  documents  including:  World  Bank  Safeguard  Policy  on Resettlement, Acts and Regulations; District Development Plans and Environment Reports for Mumias/Butere,  Siaya  and  Kisumu Districts;  Project  area  topographical  and  cadastral maps and; Previous project study documents. 

ii. Field surveys using observation/site walks, checklists, questionnaires, public  interviews and geographical positioning systems (GPS), targeting the PAPs along the proposed transmission line  and  households  surrounding  the  proposed  project  area.  All  data  collected  were analyzed for production of the RAP. Samples of the questionnaires used during the study are provided in Appendix 2.   

iii. Conducting discussions with the proponent on the project issues  iv. Conducting  public  and  stakeholders  consultative  meetings  in  various  sites  presented  in 

appendix 3. 

5.2 Socio‐Economics of PAPs in the Project affected Areas Residents  in the project area are mostly the middle aged, 21‐60 years who  form over 85% of the population. Most households have many dependants with 73% having 6‐15 dependants. Nuclear families are  the majority  (71.3%),  the  rest being extended  families. 88.8% of  the population  are Christians and the rest include Traditionalists and Muslims. Majority of the population (42.1%) had reached primary level of education 

 5.3 Summary of Socio‐Economics of the Project affected Area  Land affected The area earmarked to be traversed by the transmission line covers the following villages; Shivale, Angola,  Shitukumi,  Nyakwakwa,  Lureko,  Edokho  A&B,,  Emukanga,  Matora,  Buchifi,  Emaunga, Buyole, Bukhweso, Ebuyunjere, Mundindi,Ebuyenjere, Mushechere, Khushipare Kit Luiyo, Lukongo, Kulumuayo,  Bumala,  Buhkwayo, Madungu,  Ugolwe,  Simerro,  Rangala,  Simenya,  Yala,  Kadongo, Kanyakwar, Karombo and   Kunya among others.   The  total area of  land  to be acquired measures 1475.67 acres which  is currently under  several uses namely agricultural,  settlement,  institutional and commercial. 

 91.7% of the  land  in  the project area  is communally owned, 5.1%  individually owned and 3.2%  is commercial  according  to  those  interviewed. With  regards  to  land  tenure  for  the household,  the respondents said 62% of the land is freehold, leased 1%, traditional land 28% and 9% could not tell the  type of  land  tenure. All  Institutional  land  is owned by  the  institutions, 60% acquired  through 

Page 35: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

18 

purchase and have been  fully paid  for and  title deeds available. All  land occupied by commercial property was acquired through purchase and have no outstanding payments.    Housing and Asset Ownership 73.6% of the PAPs own residential property they lived in and had lived in the housing for 20 years and more. 40% of businesses were on tenancy basis and only 60% owned the premises. 81.2% of the houses are built with Blocks, iron sheets and wood. Majority of homes consisting of 60% have one house, 175 have  two houses, 9% have up  to 3 houses, 6% have  four houses and  those who have more than four houses constituted 10% of the respondents.  Majority of homes consisting of 51.2% have one house, 12% have two houses, 15.2% have up to 3 houses, 6.4% have  four houses and those who have more than  four houses constituted 15.2% of the respondents. The commercial centres to be affected are made of masonry stones beneath GCI sheets roof on trusses and parallels.   Access to Infrastructure 12.5% of the road is tarmac, 83.7% are rough road and only 3.8% are impassable. Use mobile phone was greater with 89.2% and 10.8% use post office  infrastructures/equipments of communication. 40.4% of  the population has access  to borehole water, majority 45.5% use  river water and only 14.1% have piped water.   Tenure, Length of Time in the Location and Use of Land The number of years the households had lived in the area varied from one to fifty as follows: 0 to 20  years  (49.1%),  21  to  40  years  (28.3%),  41  to  60  years  (15.7%)  and  above  60  years  (6.9%).  Regarding businesses premises, a greater percentage of occupants 60% being property owners and 40% are tenants.  Occupation, Income and Expenditure  50.8% of the PAPs carry out farming, a negligible 9.8% are employed, 33.6% engage in various types of  business  and  5.7%  of  the  respondents  were  casual  labourers.  Majority  of  the  household respondents earn monthly income of below Ksh 25,000. Majority of PAPs stated they do not keep records of their expenditures but spent 80% (20,000) of their incomes on basic needs namely food, medicine and education.  Energy  55.8% of the project area population use electricity, 3.8% uses charcoal and 16.5% depend on solar energy.     Expenditure on energy ranged from ksh. 200 to 1,600 per month with a majority paying between Ksh. 200‐400 per month 

Page 36: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

19 

 Issues related to Gender, Poverty and Vulnerable Groups Gender disparity  in the project area was evident with 6.8% of women having title  in their names against 71.2 % of men. The main decision makers at the household  level are male 61.6%, 11% of female make decisions and 27.4% indicated both partners make decisions.  Commercial Activities and Businesses There are  twelve business centres  in  the project area  including Mumias Town, Lureko, Sigomero, Simerro, Bungasi, Sindindi, Yala, Emukhaya, Maseno, Chulaimbo, Kisian and Riat Market. Despite the fact that the trading centres are not within the project corridor apart from Emukhaya, majority of the PAPs conduct their trading activities there as it is the main source of livelihood for all those dependent on business for income.    Findings of the RAP Majority of the population in areas with small parcels of land  like Mumias and sections of Ugenya were willing to move as they understood re‐aligning the line will be difficult as the area is densely settled  because  in  the  area  families  are  generally  large.  Households  preliminary  resettlement options were, people to be resettled near their present homes (37%), in the same District (10.4%), none response and not considered yet (1.3%). A good number of the PAPs (65%) would  like to be given monetary  compensation  to  enable  them  choose  resettlement  areas  for  themselves  and  a large number of  them 74.4%  stated  they  shall  resettle  in  the  same community. Businesses were also  indifferent as they  indicated that  if resettlement  is to occur, they would  like to remain  in the same community area as they are used to conducting business  in the area.   Regarding preference for resettlement majority of  the respondents  (76.4%) wanted to be relocated together with their community members. A greater proportion of the respondents of 66.7% seem to base the value of their property at present market value  in the area while the remaining 33.3% prefer to use assets value of property found on the plot including land value. 

Page 37: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

20 

6.0 RESETTLEMENT POLICY AND ENTITLEMENTS 

6.1 Compensation Policy  Compulsory  acquisition  occurs when  the  state has  to  acquire  land  compulsorily  for  purposes of public  interest or what  is referred to as overriding  interests.  In Kenya the right of expropriation  is entrenched  in  the constitution, Section 75  (1) and  the process  is guided by several Acts with  the principal one being the Land Acquisition Act Cap 295 which empowers the Government to acquire land for public body where the acquisition is necessary for public interest.  Under the Trust  land Act Cap 288 Section 7 (1) Local Authorities are empowered to set apart land for public benefit.     Other acts which deals with acquisition of  land  in Kenya  include: ‐ The Energy Act, 2006 Section 54(1), the Water Act Cap 372 Section 78(1) and the Local government Act Cap 265 Section 144. These acts give the Minister the power to acquire Land compulsory for public interest in accordance with the relevant laws.  In the case of Mumias‐Rangala‐Kisumu transmission  line, the acquisition  is guided by Compulsory acquisition Act Cap 295, and Wayleave Act Cap 292 which authorizes the Government to carry out sewers, drains and pipelines through, over and under any lands and whenever crops, structures or trees are affected to compensate for it promptly. 

6.2 Project principles of compensation for Resettlement  

6.2.1 Compensation policy for loss of land In general, land use rights can be withdrawn by the state in the public interest. However, the state has  the  responsibility  for  paying  fair  compensation  for  any  losses  and  improvements  The  Act specifies compensation payment  for expropriated  land, which  is done  in  the public  interest.  It  is silent  on  compensation  issues  such  as  the  principles,  forms,  eligibility,  valuation,  adequacy, procedures, timing and responsibilities.  The legal recourse available to affected persons who are not satisfied with the compensation is the courts  of  the  country.  Fortunately,  there  are  well‐established  local  mechanisms  for  conflict resolution  concerning  land  among  local  communities  consisting  of  land  issues  resolution committees, area development committees or village elders. 

6.2.2 Guiding Principles and objectives for the RAP In order to ensure that the RAP complies with international best practice as regards resettlement, the principle implementing agent, KPLC shall bind itself to the following guiding principles: 

Principle 1: Resettlement must be avoided or minimized Action: To  comply with  the principle, KPLC has demonstrated  that  the proposed  resettlement  is both necessary and viable, and that its scope and extent cannot be lessened. KPLC has shown that they  aim  to  design  the  proposed  project  so  as  to  cause  the  least  possible  displacement  and/or disruption. 

Page 38: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

21 

Principle 2: Genuine consultation must take place Action: Given  its  focus on  resettlement,  the primary  concern  is  to  take  seriously  the  rights  and interests of the PAPs. For this to take place, their voices need to be made clear, via the formation of local level consultative forum. These structures have been co‐ordinated at the community level by the client’s personnel and the consulting team. 

Principle 3: Establishment of a pre‐resettlement baseline data Action: To support the successful reestablishment of affected property, the following activities will be undertaken prior to displacement. 

• An inventory of landholdings and immovable/non‐retrievable improvements (buildings and structures) to determine fair and reasonable levels of compensation or mitigation. This will be used to determine and negotiate entitlements. 

• A census detailing household composition and demography, and other relevant socio‐economic characteristics to assist in monitoring homestead reestablishment  

The  information  obtained  from  the  inventories  and  census will  be  entered  into  a  database  to facilitate resettlement planning, implementation and monitoring. 

Principle 4: Assistance in relocation must be made available Action:  KPLC  will  guarantee  the  provision  of  any  necessary  compensation  for  people  whose property will  be  disturbed  to make way  for  the  transmission  line,  or  any  other  disturbances  of livelihood associated with the project in proportion to their loss. 

Principle 5: A fair and equitable set of compensation options must be negotiated Action: Compensation will be paid for structures, land and trees that are disturbed according to set rates derived from market value comparables. 

Principle 6: Resettlement must take place as a development that ensures that PAPs benefit Action: Where practical,  the  employment  and  sub‐contracting opportunities  that  arise  from  the project will be made available to the affected population. 

Principle 7: Vulnerable social groups must be specifically catered for Action: Members of vulnerable groups are often physically weaker, and may need special help  in the relocation/disturbance phase. In particular, female and child headed households may  lose out to more  powerful  households when  assets  will  be  demolished  to make  way  for  the  proposed project.  This will  entail  KPLC  ensuring  that  the  pre‐resettlement  database  specifically  identifies vulnerable social groups and makes provision for them to be  included  in consultative forum. KPLC must  further  ensure  that  they  are  given  the  necessary  protection  to  ensure  that  they  receive equitable  access  to  replacement  resources.  In  addition,  KPLC  will  make  specific  reference  to vulnerable  social  groups  being  paid  particular  attention  in  the  monitoring  process.  Vulnerable groups will include those with minimal assets, the illiterate, and the aged (over 65 years). 

Principle 8: Resettlement must be seen as an upfront project cost Action: KPLC should ensure that compensation costs, as well as those resettlement costs that  fall within their scope of commitment, are built into the overall project budget as up‐front costs. 

Page 39: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

22 

Principle 9: An independent monitoring and grievance procedure must be in place Action:  In  addition  to  internal monitoring  that will be provided by  KPLC,  a  consultant  team will undertake monitoring  of  the  resettlement  aspect  of  the  project.  Grievance  procedures  will  be organized in such a way that they are accessible to all affected parties, with particular concern for the  situation  of  vulnerable  groupings. Monitoring  will  specifically  take  place  via  measurement against the pre‐resettlement database. 

Principle 10: World Bank’s operational procedure on forced resettlement Action: Displaced persons should be meaningfully consulted and given opportunities to participate in planning and implementing resettlement programs. They should also be assisted in their efforts to improve their livelihoods and standards of living or at least to restore them, in real terms, to pre‐displacement  levels or  to  levels prevailing prior  to  the beginning of  the project  implementation, whichever is higher. 

6.2.3 Valuation Methodology  Valuation  can  simply  be  defined  as  the  art  or  science  of  establishing  the  value  (worth)  of  a particular interest in property for a specific purpose and at a particular moment in time; taking into considerations all the features of the property and also considering all the underlying factors of the market.  All  valuation  techniques  rely  on  the  collection  and  analysis  of  data  such  as  social,  Economic, Government and Environmental attributes. Specific data include local market conditions and details of property transactions such as location, physical and functional form and legal characteristics. The value of  the property  is affected by  the  rights of enjoyment or compensation when such benefit may be alienated. In Kenya, compensation value requires that the value paid to include all the other miscellaneous expenses as well as the  injurious affection due to the disturbance to them. Thus  in such circumstances, the value paid  is higher than normal market. Thus the  factors that affect the value are those that affect the rights on land, thus location, legal rights and permitted use.  Basically there are three methods of valuation namely,  

1. Comparison Method: while  it  is true that no two properties can be the same, this method compares  like  properties.  It  is  the  most  reliable  and  requires  an  active  market  while adjustments are made to fit specific properties. The  limitation faced by this method  is  lack of data and sometimes misleading data. Comparables may be biased where the seller may sell more or less depending on the needs at the time. Elsewhere the data given may not be correct because of personal secrecy. Thus  in  long run, valuers have been able to come up with values per square foot/meter that can be used in various regions and give a reasonable value. Adjustments are made depending on various factors. 

2. Investment Method:  on  the other hand  is based  on  the  expected  future  returns  and  its applicable  where  active  investment  market  is  available.  Just  like  comparison  method, investment method is limited due to lack of varied data. 

Page 40: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

23 

3. Cost Approach Method: this  is where the property value  is assessed based on  the cost of buying the site and constructing the building.  It  is based on the reproduction/replacement value.  

 The  above  methods  together  with  the  above  factors  lead  to  the  value  of  the  property.  It  is important to note that the above methods can apply to the same property if the data was available. They however give varied values; experience and  the knowledge of  the existing property market are  necessities  for  any  property  valuer  to  come  up  with  appropriate  value  and  not  just  the quantification and method of calculation.   For Mumias‐Rangala‐Kisumu  transmission  line,  the  three methods were applied  to come up with the  estimate  of  the  Resettlement  value  and  15%  disturbance  allowance  included  to  cater  for disturbance/movement of the affected people. The acquisition of  land  from private as outlined  in  the Acquisition Act cap 295  is as described as follows.  Step 1: Formal request by the benefiting authority is made to the Commissioner of Lands indicating the purpose of the land to be acquired. The request should prove that the land is needed for public purpose.    Step 2: The Commissioner will then forward the application to the Minister  in charge of  lands.    If  the  minister  is  convinced  that  the  land  is  required  for  public purpose,  the  Minister  will  write  to    the   Commissioner    to    that   effect,   and directs    the   Commissioner    to   acquire    the    land  (Section  6(1).    Step 3: The Commissioner   will   then   give   “Notice   of    Intention”   to   acquire   the    land (section  6(2)    in    the    “Kenya   Gazette”    side    by    side   with    the    “Notice    of    Inquiry”.      The    public  announcements   will   be   made       widely    in standard   mass   communication   avenues   such   as  newspapers  and  on  the radio.     The “Notice  of  Intention”  must mention the public body or  the  public purpose  for  which   the  land  is    to   be   acquired. The “Notice   of  Inquiry”   must mention places   and    fixed   dates when  persons  interested in  the  subject  land are to submit  their claims  to the  Commissioner  of  Lands  or his appointee.   Step 4: “Valuation Officer” also known as “Collector of compensation” according to Section 9 of the Act inspects  the  said land and value it for compensation. After the inquiry the Collector will issue an  award  depending  on  his  own  assessment  and  the  representations  of  interested parties as submitted at the inquiry  

  Step 5: The  award  is  issued  in  the  prescribed  form  indicating  the  amount  of compensation  awarded  while  the  statement  form  gives  the  landowners option of acceptance or rejection of  

Page 41: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

24 

the  award.  If  the  landowner  accepts  the  award,  the  collector will  issue  a  cheque  in  settlement together with a form.  Step 6: “Notice of Taking Possession and Vesting” (section 19).  The  notice instructs the  landowner  to  take  his/her  title  for  amendment  or  cancellation.  It  is copied  to  the  Government  Surveyor  and  the  Land  Registrar  to  make necessary  changes  to  the  affected  deed.  On  the  other  hand,  if    the   owner  rejects    the   award,    the   collector   deposits    the   money    in   court   pending    the former’s appeal. Compensation is based on open market value.   Section  12  of  Cap  295 allows  for  in‐kind  compensation  as  follows:‐  Notwithstanding  anything contained  in  the  Government  Lands  Act,  where  the  land  is  acquired  for  the Government,  the  Commissioner  may  agree  with  the  person  whom  he  has determined  to  be  the  proprietor  of  the  land  that  person,  instead  of receiving an award, shall  receive  a grant of land, not  exceeding in value   the   amount   of   compensation   which   the   Commissioner   considers   would   have been awarded, and upon the conclusion  of  the  agreement that  person shall, subject  to  section 18, be deemed  conclusively to have been  awarded  and  to have received all  the  compensation to which  he is  entitled  in respect  of  his interest.  An agreement under subsection (1) shall be recorded in the award. 

 6.2.4 Entitlement Matrix  Table 3 indicates the entitlements for the different categories of PAPs.  

Page 42: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

25 

Table 3: Entitlement Matrix  No   Type of loss  Entitled person  Legal requirement  Restorative 

compensation  1  Land   Owners of land 

through customary or legal acquisitions  

Compensation for the area of land affected at prevailing market rates –pay additional 15% disturbance allowance 

Same as the legal requirement entitlement  

2  Main structures(totally affected residential and commercial) 

Owners  of  structures including  Kiosks, and    stalls    in the project area  who have  no  title declaration to the land  and  or  other acceptable proof of ownership 

Compensation of the entire structure at replacement cost as determined by valuation without deductions for salvaged building material. Provide relocation fee 

Same as the legal entitlement  

3  Crops/trees affected  Owners   Compensation of the affected trees at prevailing market rate for sugar cane plantation observe lease agreement entered between farmers and Mumias sugar company  

Same as the legal entitlement  Consult Mumias sugar company on conditions of breach of lease 

4  Other fixed assets and or structures  

Owners of fixed assets and structures  

Compensation in cash for affected portion of the structure including cost of restoring the remaining structure as determined by valuation without deductions for salvage building materials 

Same as the legal entitlement 

5  Electric lines and or water connections  

Project affected persons with utility connections  

Compensation to cover cost of restoring the facilities 

Same as the legal entitlement 

6  Social amenities including water, electricity, roads, schools, churches, markets/trading centres and revegetation  

Communities whose members are affected by the project 

To be carried out as a corporate social responsibility  

No legal entitlement but may be carried out in response to community requests 

Page 43: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

26 

7.0 RESETTLEMENT SITE 7.1 Method of Site Selection and Site Alternatives Method site selection was based on GPS data given  to consultant by KPLC and alternatives were proposed by community members during public participation and were based on the size of their land mainly.  Densely populated areas especially in Mumias District had minimum options in terms of resettlement due to existence of the flood prone Nzoia River. The community members would like that during selection of the resettlement site consideration should be taken on the  livelihood losses they will incur as those around Mumias Town living in Shivale, Angola and Shitukumu will be delineated  from  the  town  thus  they will  lose  their  businesses  and  clientele  base;  those  in  the farming areas will lose income from sugar‐cane farms and others will lose jobs as causal labourers in the sugar‐cane plantations. Loss of business due to relocation will also be experienced in Kisumu East between Mamboleo and Kisian Hills. 

7.2 Influx Management Influx management will be necessary to prevent land speculation or influx of illegible persons at the selected sites. The local administration and PIU will be responsible for development of measures to prevent the influx of ineligible  person (encroachers and  squatters)  into  the selected sites  such  as  the  identification  and  recording  of  affected  people  at  the  project  identification stages;  

7.3 Location of Resettlement Site Majority of the PAPs likely to lose their structures stated that if they were to choose their preferred area  of  resettlement,  they would  choose  to  be  resettled  in  the  same  community  or  the  same district.  Identification of  the area of  resettling  those affected  should be  conducted early enough and  the  host  community  should  also  be  sensitized  on  the  proposed  move  to  enable  them understand how this will affect them and ensure co‐existence of the host and the resettlers.  It  is advisable  that  during  the  sensitization  of  the  host  community  the  two  parties  should meet  to enable  initiate  interactions. Alternatively  the PAPs who are  likely  to  lose  their structures and still remain with sustainable land should be offered monetary compensation before hand to allow them time to construct their houses.  

7.4 Resettlement Options The  community  members  preferred  to  be  resettled  in  the  same  community  or  with  family members. The community members with  large parcels of  land generally had no problem with the project as the line will not affect them after installation as they could either move their houses to other areas on the farm or continue undertaking their activities if the houses are not affected. But those with small parcels of  land mainly areas  like Mumias where community members have  large families, or areas where  community members have been  resettled  severally  like Angola,  Shivale and, Shitukumu villages  in Mumias Town and Kongony sub‐location  in Kisumu East district would like special consideration during resettlement. 

7.5 Resettlement Site Development (Infrastructure, Social Service, etc.) The  proposed  project will  lead  to  loss  and/or  inaccessibility  to  residential  and  communal/social infrastructure  (schools  and  churches),  water  sources  and  transport  routes.  Considering  that majority of the people in the area has small farm  lands and those relocated will have to purchase 

Page 44: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

27 

land elsewhere, KPLC will have to develop structures  for them. Residents therefore envisioned to be  compensated  through  construction  of  better  houses  and  social  facilities  than  those  they currently owned or used. Where there is relocation to distant sites, KPLC will have to develop not only residential and communal infrastructures but also other facilities namely fresh water sources, communication, business structures, schools and travel infrastructures. 

7.6 Livelihood Restoration It is proposed that all those that shall be affected by the project should be compensated to ensure that  their  livelihoods  have  improved  or  restored  to  the  pre‐impact  status.  The main  livelihood losses  will  include  crops,  trees,  business  and  commercial  properties  among  others.  Livelihood restoration should therefore be  inform of development of new shops, enhanced market  linkages, provision of relocation assistance, training on skill development and capacity building on areas such as    enterprise,  job  creation,  agriculture,  community  participation  and management, Health  and Hygiene education and PAP’s empowerment. 

Page 45: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

28 

8.0 INCOME RESTORATION 8.1 Introduction Majority  of  the  PAPs  are  farmers  and  small  scale  business  owners.  Livelihood  restoration programmes will therefore target the two areas of  improving agriculture and small scale business development as well as enhancement of  income generating activities. The major assets  for which compensation will be paid are:  

i. Private houses and fences  ii. Farm land (crop loss)  iii. Private plantation (tree loss)  iv. Grazing land (fodder loss)  v. Public buildings and temporary loss to social services infrastructure;  

8.2 Income Restoration and Improvement Component The  household  respondents  proposed  measures  aimed  at  improving  their  living  conditions included:  KPLC  to  initiate  income  generating  activities  (13.9%),  PAPs  be  provided  with  new agricultural plots  (40%),  training  for  self‐employment  (3.6%) and getting  loans or grants  to  jump start development in the area (49%).    

i. Capital Support Funds  for  income  restoration programs become a major constraint  to  the PAP utilizing  their skill obtained/enhanced  through  Income Generating Activities  (IGA)  training. Capital  support for  potential  IGAs  to  the  trained  and  efficient  target  group  people  should  therefore  be provided from any source arranged by the development projects in the form of grant or credit. Technical  and  financial  support may  be  received  from  financial  institutions  including micro‐finance  institutions. At  least capital support of Kshs. 100,000 can be allocated to each eligible person  to  enable  them  start  the  income  generating  activities.  It  is  recommended  that programmes  for  income  replacers  should be  incorporated  in  the project especially  for  those who shall loose commercial properties.  ii. Employment at Construction  It is advisable that, local people whose livelihood is impacted by the project will get preference in  jobs associated with  the project construction. Female affected people  should  form  labour contracting  groups with  the  help  of  the  PIU  and  be  deployed  by  the  contractor  in  simple excavations,  bush  clearing,  revegitating  programmes  (e.g  tree  planting  and watering).  PAPS should get preferential employment in project civil works based on their eligibility in the semi‐skilled  and  unskilled  category.  A  clause  should  be  incorporated  in  the  contract  document requiring contractors to give employment, if available to PAPs having ID cards in preference to other persons. 

Page 46: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

29 

 iii. Small business development. This will be accomplished through training in improved income‐generating covering such topics as selecting optimal business alternative, managerial training for businesses among others. 

 iv.  Re‐establishing Common Property Resources (CPR)  In  addition  to  loss  of  personal  properties  and  assets,  the  project will  also  have  impacts  on community  structures.  If  required,  the  CPR will  receive  replacement  value  as  stated  in  the entitlement matrix in (chapter 6 table 3) and as budgeted for in the RAP budget.The short‐term livelihood  regeneration assistance under  the RAP and  long‐term  income generation program under the Livelihood and Income Restoration Programme (LIRP) will be organized as follows: 

 

         Table 4: Livelihood Restoration Options No./S  Vulnerable Group  Action 

1.  Eligible  members  of  poor households  to  be  relocated from the project right of way 

1.1  Short‐Term:  Compensation  for  structure, shifting  allowance,  reconstruction  assistance, alternative  site  cash  assistance  for  loss  of workdays  due  to  relocation,  and  priority  in employment  in  construction,  employment referrals  or  priority  in  employment  in  project activities.  1.2 Long‐Term: Needs and Capacity  identification, human  development  and  skill  training  , institutional  and  credit  (micro‐credit)  support under the LIRP 

2.  Eligible  members  from  poor female  headed  households having no adult male members to  shoulder  household responsibility  

2.1 Short‐Term:  In  addition  to  support  as  in  1.1, additional subsistence allowance. 2.2 Long‐term: As 1.2 above. 

3.  Poor  vulnerable  employees  of affected businesses 

3.1 Short‐term: Subsistence for loss of income and employment  3.1 Long –term: As 1.2 Above 

4.  Eligible  members  of  poor households  losing  access  to commercial  land  including business proprietorship,  urban agricultural land etc. 

4.1 Short‐term: Compensation for loss of business income,  shifting  and  reconstruction  assistance, alternative site. 4.2 Long‐Term: As per need, credit support  to be provided for strengthening business capital  

5.  Eligible  members  of  poor households  losing  more  than 10% of their plots 

Short‐term: Replacement value of land, assistance for land purchase and employment in constructionLong‐term: As 1.2 above 

Page 47: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

30 

 

8.3 Land‐Based Component Income  restoration  for  the  land  based  component  through  agricultural  improvement  will  be accomplished  through  training  in  improved  crop  varieties,  fertilization,  and  post  harvest  grain conservation;  Provision  of  fertilizers  and  improved  seeds,  Extension  services  and  related monitoring.  

8.4 Non‐farm Component The Mitigation of adverse impacts at the community level include acquisition of sections or whole parcels of land from about 859 households in settlement, farming and commercial blocks, transfer of  stress  to  vulnerable  groups  who  include  the  elderly  (61‐70  years  old)  and  female  headed households, loss of trees, loss of rental revenue, loss of communal facilities (churches, schools and  hand dug wells), loss of  undeveloped residential and commercial plots and the spread of HIV/AIDS. Project proponent should create awareness on the process of land acquisition and resettlement to the PAPs to allow psychological preparedness of the whole process. 

8.5 Compensation Preferences  All  discussions  conducted with  focus  groups  and  sector  offices  have  revealed  that  the  general preference  for  compensation  is  for  financial  reimbursement  for  lost  or  damaged  assets. Where land‐for‐land compensation is often not possible, financial restitution is the only option available.   

Page 48: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

31 

9.0 IMPLEMENTATION ARRANGEMENTS 

9.1 Organization Structure Land  acquisition,  resettlement  and  management  is  usually  a  major  issue  in  the  project implementation  process  and  these  calls  for  an  appropriate  institutional  framework  for  all concerned parties  including  the client.  It  is always  important  to ensure  timely establishment and effective functioning of appropriate organizations mandated and is capable to plan and implement land  acquisition,  compensation,  relocation,  income  and  livelihood  restoration  programs.  The organizational  structure or  the  institutional  capability  should be elaborate on  the  role of various stakeholders  in  the  implementation and administration of  the RAP.  It  further clarifies  the  role of PAPs and their responsibility in the entire process. 

9.2 KPLC Resettlement Unit KPLC will put  in place a Project  Implementing Unit  (PIU) dedicated  to  the  implementation of  this RAP,  under  the  leadership  of  a  RAP  manager.  The  aim  of  this  unit  is  to  involve  other  key stakeholders and  institutions who will play collective roles  in  implementation of the Resettlement Action Plan  including  land acquisition, award of  compensation  and  resettlement  for  the project. This unit will comprise  the  following; Legal Advisor, Way‐Leave Officer, Land Valuer, Accountant, Environmentalist  and  a  socio  economist.  Further,  KPLC  should  vote  in  adequate  resources  for implementing the RAP as outlined in the budget. 

9.3 Local RAP PAP Committee The  local Resettlement Action Plan  for Project Affected Persons Committee will be  formed under the guidance and coordination of PIU. It will be formed two to three weeks after the formation of the PIU and will act as the voice of the PAPs.  Each district will form its own PAPC. The committee shall comprise of the following: 

• Government officials such as (NEMA, housing, lands, agriculture among others) 

• PAPs Representatives – to be appointed by PAPs. 

• Provincial administration 

• KPLC representative 

• Interested NGOs/CBOs representatives The PAPC shall have a Chairperson and a Secretary appointed or elected by PAPs. The chairperson ought to be from the local area. The roles of PAPC will include: 

i. Conducting extensive Public Awareness and consultations with the affected people so that they can air their concerns, interests and grievances. This consultation will ensure that they own up the whole process of resettlement so that they do not oppose the implementation of the project. 

ii. Ratifying compensation rates and resolving disputes that may arise relating to resettlement process.  If  it  is  unable  to  resolve  any  such  problems,  will  channel  them  through  the appropriate grievance procedures laid out in this RAP. 

iii. Over see resettlement process  iv. Ensure efficiency of resettlement  

Page 49: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

32 

v. Ensure  employment  (for  those  who  cannot  find  alternative  employment)  and,  conduct training and counseling the PAPs both socially and economically. 

9.4 Capacity of KPLC Resettlement Unit The  capacity  and  commitment of KPLC  resettlement  institution  to  implement  the RAP has been assessed.  Strengthening  of  the  institutions  should  be  considered  if  necessary.  

Page 50: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

33 

10. IMPLEMENTATION SCHEDULE AND THE RAP BUDGET  

10.1 Implementation Schedule The responsibility for the RAP  implementation will  lie with the PIU. It is anticipated that the PAP’s will be resettled as agreed before commencement of the rehabilitation project. An implementation schedule namely Resettlement Action Plan Activity  Schedule  covering  all    resettlement  activities from  project  preparation    through  implementation    to   monitoring    and    evaluation    indicating  dates    for    achievement    of    expected  benefits  to  resettled  persons  and  hosts  and  dates  for terminating the various forms of assistance  is shown in the appendix 4. 

10.2 The RAP Budget The RAP budget  is estimated to cost Kenya Shillings  five hundred and eighty seven million, seven hundred and three thousand, seven hundred and fifty four and fifty one cents. (Ksh. 587,703,754.51). The figure gives estimates for the following activities: compensation for lost property and services, costs  of  professional  services  including  project  management,  capacity  building  of  PAPs  and monitoring services.  Based on  the valuation principles discussed  in chapter six  the consulting  team came up with  the following  cost  estimates  to  be  used  in  computing  the  compensation  costs  for  PAP.  The  cost estimates for the total value of land to be acquired is Kenya Shillings Three Hundred and Thirty Nine Million,  Five  Hundred  and  Seventy  Six  Thousand,  Seven  hundred  and  Seventy  Four  Only  (Ksh. 339,576,774) while built structures are estimated to cost about Kenya Shillings One Hundred and Ten, Million, Two Hundred and Fifty Nine Thousand, Two Hundred (Ksh. 110,259, 200). The figures were  calculated based on  the  land  values of  the different  locations  found within  the  project. A detail of the cost estimates for the loss incurred by each PAP is found under Appendix 1.  15%  disturbance  allowance  is  legally  added  to  the  declared  value  as  stated  by  Compulsory acquisition Act. This is supposed to cater for economic, social and physical disturbance caused to a PAP who  is  required  to  relocate  from  areas  they  had  gotten  used  to  and  sometimes  lose  their livelihood. The costs are shown in table 5 and 6 

Table 5: Cost Estimates for lost Property  

District   

Total  costs of land 

Total costs of trees 

Total costsof structures

Total costof crops 

TOTALS 

Mumias  98660371.15  100,800 47,443,200 24665092.79 170,869,464 

Ugenya   61269927.6  96,000 24,972,800 15317481.9 101,656,210 

Gem   110854002  30,000 15,859,200 11117276.1 137,860,478 

Emuhaya  16308600  2400 2352000 815430 19,478,430 

Kisumu North  34913750.4  593,600  12,785,600  4,257,497  56,807,944 

Kisumu East  17570123.57  147,305 6,846,400 1,104,300 26,772,428. 

Totals  339,576,774.00  970,105 110,259,200 57,277,078 513,444,954. 

Page 51: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

34 

 

Table 6: Cost disturbance Allowances and Livelihood Restoration Programmes 

Categories    Unit Quantity Unit Price Ksh. 

Compensation Cost Ksh. 

Compensation  moving expenses  and  allowance‐Transport  Assistance  to Resettlers  

  No. 624 30,000  18,720,000

Compensation to business    No. 12*4 6,000  288,000

Compensation  Skill development  and  capacity building  

Health  and  Hygiene education 

5,000,000

Agriculture 5,000,000

Enterprise  training and job creation  

1,000,000

Community participation  and management  

5,000,000

PAPs empowerment  5,000,000

Sub‐Total 1    40,008,000

Professional Services   Key  Stakeholders Allowances 

Days 60*12*6 5,000  21,600,000

Monitoring  and Evaluation Unit 

No. 6*3 300,000  5,400,000

Completions Audit No. 1 Lump  500,000

Sub‐Total 2  27,500,000

Sub‐Total (1+2+)  67,508,000

Inflation 5%  3,375400

Unmeasured Items at 5%  3,375400

Total Disturbance Allowance  74,258,800

GRAND TOTAL FOR RAP   587,703,754.

Page 52: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

35 

11.0 PARTICIPATION AND CONSULTATION 

11.1 Policy of participation and consultation 

A community engagement plan should be developed and implemented as a continuous process to allow  stakeholders  participate  in  meaningful  consultations  on  the  proposed  project  and  its associated  impacts. The concerns and aspirations presented should be addressed and fed back to the community members so as to have an effective information exchange procedure which will also play a major role in monitoring implementation of RAP.  

The Principles of community engagement should ensure that: 

• All stakeholders must be consulted and be effectively involved in a two‐way communication with  the project proponents. Special efforts  should be made  to  consult with women and vulnerable communities.  

• The RAP should  include an explicit public  information strategy. This should  include the use of provincial administration to advise the dates and times of public meetings, availability of documents, selection criteria, cut‐off dates, and compensation.  

• The consultation should be preceded by providing all the relevant and accurate information.  • All  relevant  information  should  be  disclosed  by  the  proponent  to  affected  persons  and 

communities,  including host communities and  they  should be  involved  in decision‐making processes  related  to  resettlement.  These  disclosure  and  consultations  should  continue during the  implementation and monitoring of compensation payment and resettlement to achieve outcomes that are consistent with the objectives of the OP 4.12.  

• That consultation with different stakeholders is undertaken through a language and medium they are comfortable with; and in areas where the stakeholder is not comfortable with the language or do not easily understand  the  information  relied, proponent  (KPLC)  shall  take responsibility for simplifying and ensuring that the whole process is understood by the PAPs, using appropriate methods of communication.  

• There  are  specific  and  transparent mechanism  for  the  recording  of  grievances  and  their timely  resolution. KPLC  should make every effort  to  resolve grievances at  the  community level  without  impeding  access  to  any  judicial  or  administrative  remedies  that  may  be available.  

• Where  affected  population  do  not  have  land  titles,  cadastral  surveys  will  have  to  be undertaken to establish the basis for compensation and procedures should be established to regularize and recognize claims to land, including claims that derive from customary law and traditional usage.  

• Clear  communication  of  responsibility  and  accountability  procedures,  personnel  and resource availability for effective implementation of plan shall be put in place.  

• A schedule should be prepared and disseminated in appropriate places within the footprint of  the  project  detailing  the  time,  place  for  consultation  and  contact  details  of  the  lead person.  

Page 53: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

36 

11.2 Interviews and Group Discussions The resettlement exercise often  leads to the dislocation of kinship groups, reduction  in  livelihood standards of the PAPs and might also affect the host community residing where the PAPs shall be resettled. The participation of stakeholders  in the planning and execution of the RAP can cushion the PAPs against adverse project impacts and thus promote its acceptability. The  local community members took part  in the preparation of this RAP by attending public  forum and, participating  in interviews held  in  the project  area  and by  filling pre‐defined questionnaires, discussing pressing issues  with  the  project  team  consisting  of  land  valuer,  land  surveyor,  socio‐expert  and environmental experts.   Information exchange enables  the  resettlement  team and  the PAPs evaluate  the project  impacts and  develop  mitigation  measures  in  an  amicable  manner.  Key  issues  likely  to  arise  during discussions  are:  identification  of  alternatives  to  avoid  or  minimize  displacement;  provision  of assistance  in  inventory and assessment of  losses; provision of assistance  in developing alternative options  for  relocation  and  income  restoration;  identification  of  relocation  sites  for  displaced households  and  businesses;  types  of  entitlement  and,  process  and,  period  of  award  and, identification of likely conflict during and after resettlement.   Several  stakeholders  and  community  public  meetings  were  held  in  the  project  area  and  the consultants explained to the community members the details of the proposed project and areas it is  likely  to  traverse.  The  public  forum  attendants  were  then  asked  to  air  their  concerns  and expectations regarding the project. Generally, many had heard about the project and were anxious about it but their main concern was how they will be compensated for their lost property and how the project will be maintained sustainably during the operation phase to avoid accidents and other health impacts associated with the project area.  A household census and socio‐economic survey was conducted from the 7th October 2009 to 11th November 2009 and follow‐up meetings held from 18th ‐24th May 2010 in the entire project area. The census  finding  indicated at  least 859 households will be affected by  the project and  this will include residential and four commercial outlets.   The survey identified the PAPs in terms of gender, age, educational levels, type of occupation, their opinion  on  the  project,  including  alternatives  to  be  considered  and  their  preference  for resettlement among other socio‐economic parameters. Other data collected included identification of  direct  and  indirect  impacts  on  the  people  including  impacts  on  physical  infrastructure  and economical activities.   

The socio‐economic survey enabled the consultants collect the following details: 

• Name and family details  • Demographic  information on social classification, education and occupation of each  family 

member  • Skill base/ education level for each member  

Page 54: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

37 

• Total family income (from all sources)  • Details of  land ownership and extent of  land  loss due to the  land acquisition/ negotiation. 

(Actual land ownership, and not only in terms of land records)  • Details  of  income  loss  due  to  loss  of  land  (from  agriculture,  plantation,  labour  and 

sharecropping).  • Details of any structure or asset on the impacted land  • Identification  of  vulnerability  (women‐headed  household,  family  with  physically  and 

mentally  challenged  members,  family  with  aged  members,  family  with  income  below poverty  line  and  family  losing more  than  the  economic  threshold  of  their  land  through acquisition/ negotiation)  

11.3 Project affected persons involvement The community members should be  involved  in the  implementation of the RAP through  intensive consultative meetings which should be held at the project  level. The agenda of the RAP should be clearly stated out and written statements should be provided to the PAPs and should be written in a language understood by the PAPs or written in simple English.    The PAPs in the project area are aware of the need of having a group to take care of their interests during  resettlement. This will be done by  the PAPC.  It  is  recommended  that  the  representatives should  attend  all  RAP  related  meetings  held  by  the  PIU.  To  avoid  imposing  leaders  on  the community members during RAP implementation, during the public consultation for preparing this RAP,  the  project  consultants  asked  the  community members  to  discuss  among  themselves  and choose representatives of their choice. The consultants further advised the community members to take group a step higher by legally registering it as an official organization so that it can look at all future development  issues  involving the community members. The community members took the advice seriously and stated that by the time the RAP will be implemented the committee will be in place. The main function of the PAPC will therefore be the following:  

• Assist in the mobilization and sensitization of the PAPs;   

•  Provide input into the PAPC and PIU meetings; and 

• Participate in resolving grievances.   

Page 55: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

38 

12.0 MONITORING AND SUPERVISION 

12.1 RAP Monitoring Framework Monitoring  and  evaluation  of  the  RAP  will  be  carried  out  during  the  whole  process  of  land acquisition  and  resettlement,  including  rehabilitation  activities,  to  ensure  successful implementation of the RAP. The monitoring and evaluation involves both the internal and external monitoring. 

12.2 Internal monitoring Internal monitoring will be conducted by the PIU as well as by the PAPC. Monitoring will be done on a continuous basis  to ensure  that all  responsible  implementing agencies  follow  the schedule and comply with the principles of the RAP. The PIU will develop an  internal monitoring  framework  to supervise the resettlement activities. The PIU will maintain the basic database of  land acquisition, house relocation and resettlement. It will monitor all of the relocated households, and be in charge of  the whole process of  resettlement preparation  and  implementation.  Performance monitoring will be conducted to assess the efficiency with which the RAP activities have been implemented. It will include environmental audit.  Impact monitoring will be conducted to assess the change in living standards of PAPs e.g. whether the RAP  is effective  in maintaining or restoring PAPs  livelihoods, especially  the vulnerable groups e.g housing conditions, access  to  basic amenities and infrastructure among others. 

12.3 Monitoring indicators These  indicators will  facilitate monitoring of  resettlement performance based on set  timelines as per  the RAP. Monitoring  and  evaluation will  assist  in  ensuring  that  compensation measures  are correct, all eligible persons have received their entitlements and that implementation of the RAP is proceeding well. A list of indicators will include those indicated in table 6: 

Table7: Monitoring Indicators Subject  Indicator  VariableLand   Acquisition of land • Area of cultivation land acquired for the transmission line 

• Area of communal, government or private land acquired for transmission line developments 

Buildings/ Structures  Acquisition of buildings • Number,  type  and  size  of  private  buildings  acquired (residential and commercial) 

• Number, type and size of community buildings acquired  • Number, type and size of government buildings acquired  

Acquisition  of  other structures 

• Number, type and size of other private structures acquired • Number,  type  and  size  of  other  community  structures acquired  

Trees and Crops  Acquisition of trees • Number and type of trees cutDestruction of crops • Crops cleared by area, type and ownership 

Compensation,  Re‐establishment  and Rehabilitation 

Compensation  and  re‐establishment of affected owners/individuals 

• Number  of  households affected  (buildings,  land,  trees, crops)  

• Number of owners compensated by type of loss  • Number of replacement houses constructed  • Size,  construction,  durability  and  environmental  suitability of replaced houses  

• Access to water and sanitation   

Page 56: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

39 

Re‐establishment  of community resources 

• Number of community buildings replaced  • Number, type of plants lost  • Number of seedlings supplied by type  • Number of trees planted 

Hazards  and Disturbances 

Introduction  of  nuisance factors 

• Number  of  homesteads  affected  by  hazards  and disturbances from construction (noise levels) 

Social/ Demographic  Changes  to  homestead structure 

• Changes in community ties experienced • Changes in safety nets experienced  

Population migration • Residential status of homestead members • PAPs relocated  

Changes to access • Distance/travel  time  to  nearest  school,  health  centre, church, shop, village 

Changes to health status • Access  to health  care  services  (distance  to nearest  facility, cost of services, quality of services) 

• Utilization of health care services • Disease prevention strategies • Extent of educational programmes • Latrine provision at schools (school child population per VIP on site) 

Changes  to  educational status 

• School attendance rates (age, gender) • Number, type of educational establishments 

Social/  Demographic (continued) 

Changes  to  status  of women 

• Participation in training programmes • Use of credit facilities • Landholding status • Participation in KPLC‐related activities and enterprises 

Homestead  earning capacity  

• Employment status of economically active members• Changes to income‐earning activities (agriculture) – pre‐ and post disturbance 

• Changes  to  income‐earning  activities  (off‐farm)  – pre‐  and post project 

• Amount and balance of income and expenditure • Possession of consumer durables • Realization  of  homestead  income  restoration  plans (components implemented, net income achieved) 

• Access  to  income‐generating natural  resource base  (wood, grass, sand, stones) 

Changes  in  social organization  

• Organizational membership of homestead members• Leadership positions held by homestead members 

Population influx  • Growth  in  number  and  size  of  settlements,  formal  and informal 

• Growth in market areas Consultation  Consultation  programme 

operation • Number of local committees established • Number and dates of local committee meetings • Type of issues raised at local committees meetings • Involvement  of  local  committees  in  the  development planning 

Grievances resolved • Number of grievances registered, by type • Number of grievances resolved • Number of cases referred to court 

Capacity building   Training programme • Number of people trained in income generating activities• Number  of  affected  population  trained  in  Project‐related training courses 

Management  Staffing  • Number of persons in PAPC by gender and roles  • Number of GoK ministry officials available  

Procedures in operation • Effectiveness of compensation delivery system • Number of land transfers effected • Co‐ordination between local community structures and GoK officials  

Page 57: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

40 

 

12.4 Monitoring process During  the RAP  implementation, monitoring will be  conducted on a  continuous basis by  the PIU who will collect and  record  the  information of  resettlement activities and submit  the monitoring reports, on  timely basis.    In  the overall  internal monitoring  framework,  there will be  continuous information circulation from the village level through to the PIU Office. 

12.5 External monitoring External resettlement monitoring will be conducted by an External consultant who shall be engaged by the KPLC. External monitoring will be  in two phase namely compliance monitoring and  impact evaluation. The overall objective of the external consultant will be to carry out the following: 

• Review the results of the internal monitoring and review overall compliance with the RAP; 

• Assess whether relocation objectives have been met especially with regard to housing, living standards, compensation levels, etc; 

• Assess general efficiency of relocation and formulate lessons for future guidance; and 

12.6 Agency responsibilities The monitoring responsibilities of the PIU (KPLC) during the RAP implementation will be as follows: 

• Set  up  the  resettlement  office,  train  resettlement  staff  to  be  involved  in  RAP implementation. 

• Train the PAPC on areas to monitor provide guidance in the implementation of the RAP. 

• Conduct monitoring 

  

Page 58: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

41 

13.0 GRIEVANCE AND APPEALS 

13.1 Subject matter of grievance Grievance redress mechanisms are essential tools for facilitating PAPs to voice their concerns about the resettlement and compensation process as they arise and, if necessary, for corrective action to be taken promptly. Such mechanisms are fundamental to achieving transparency in the acquisition and resettlement processes. 

 The key grievance subject matters  likely  to arise  in case of  resettlement of  the Mumias‐Rangala‐Kisumu  transmission  line  include, advance provision of  timeframe  for  relocation; values  for  land, building  and  plants;  ownership  rights  and;  resettlement  assistance,  relocation  as  well  as disturbance  and  compensation  of  livelihoods.  These  grievances  necessitate  the  setting  up  of  an independent grievance and appeals committee to address the grievance for the PAPs. 

13.2 Method of lodging complaints Complaints will be launched through either one or combination of the following methods: 

• Filling  a  specifically  pre‐designed  complaint  form  and  appending  the  PAPs  signature  and formally submitting it to the Grievance Redress Committee (GRC) office; or 

• Widely disseminating, through consultative forums. 

13.3 Proposed procedure It is for the benefit of both the Client and the PAPs to devise a procedures and mechanisms through which  complaints and disagreements  can be  resolved.   All  complaints  from  the PAPs  received  in writing or verbally by the will be documented. A copy will be maintained by the GRC. The specific terms of reference for the GRC will include settling, monitoring and facilitating effective and timely dispute  resolution  thereby  reducing  the  risk  of  escalation  of  conflicts  and  avoiding  unnecessary delays. The  proposed  step‐by‐step  procedures  of  Grievances  Referral  and  Redress  incase  of Mumias‐Rangala‐Kisumu transmission RAP are:  

 Step 1 PAPs are  informed of their  losses and entitlement  in writing and through personal contact by the PIU.   Step 2 If  satisfied,  the PAP claims  resettlement payment  from  the PIU.  If dissatisfied or  the PAP do not clearly understand the entitlement/any aspect of the resettlement plan, s/he approaches the PIU for clarification  through PAPC. The PIU makes a note and explains  the unclear  issues  to  the PAP according to the RAP. If the issue(s) are resolved, the PAP collects the payment from the PIU. If not solved PAP moves to step 3 

 Step 3 The PAP writes up or a fills a complaint’s form appended with his signature formally to the GRC at their office. The GRC holds a session with the aggrieved PAP, minutes recorded and duly signed. If 

Page 59: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

42 

resolved, the PIU approves and the PAP collects his/her entitlements.   The PIU has 2 weeks  from submission to hold a session with the PAP. 

 Step 4 If  necessary,  the  Project  Affected  People  Committees  (PAPC)  will  be  asked  to  provide recommendations  as  to how  the  grievance  is  to be  addressed.  If deemed necessary by  the PAP committee the case will be re‐investigated and, depending on the nature of the issue or referred to the a court of law for settlement  

 A schematic diagram of the grievance redress is represented in the following figure.  

Figure 3: Grievance Redress Procedure 

 Public grievance form is attached in Appendix 5  

Legal Action 

Grievances Resolved

Grievances Resolved

GRC hears grievances and Rules ‐2 weeks from submission date to respond  

Affected Party declares a      

grievance and forwards it to GRC 

 PADC hears the grievances 

And the n pass it to PIU  

No Further Action 

No Further Action 

Page 60: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

43 

14.0 RECOMMEDATIONS AND CONCLUSIONS 

14.1 Conclusions  The proposed project is important for the development of the economy in the project area and the country as a whole. However, it is likely to result in loss of property and displacement of a number of PAPs. While the overall objective of the project is noble, its positive impacts can be enhanced by ensuring  that  the  identified  PAPs  are  adequately  compensated  with  the  aim  of  improving  or restoring  their  livelihoods  to  the pre‐impact standards. To achieve  this,  the  implementing agency (KPLC) should ensure that RAP programmes are adequately implemented.     

14.2 Recommendations  PAPs  livelihoods  and  economic  activities  will  be  affected  as  a  result  of  implementation  of  the proposed project both during and after  relocation. Therefore, efforts must be made  to enhance restoration of the PAPs livelihoods by ensuring minimal shock as well as fast recovery and eventual realization of stability through successful implementation of the following RAP recommendations:     Continuous public consultation should be conducted in the project area and the PAPs made aware of  the  RAP  schedule  in  adequate  time.  The  RAP  schedule  should  include  all  key  RAP  activities including: formation of coordination and  implementation committees, monitoring and evaluation, income and  livelihood  restoration, assistance  to vulnerable groups, development of  inter‐agency committees, grievance referral and redress mechanism among others.  The consultants have proposed a compensation  schedule as  shown on Appendix 4 of  this  report that  should  be  presented  to  the  PAPs  for  ratification.  All  payments  should  be  made  before demolition commences. Compensation packages and  other resettlement measures should  ensure that  each  category  of  eligible  displaced  persons  get  their  fair  compensation and this should be done  in   conformity   with the World Bank Operational Policy (OP.4.12 of Dec   2001) which states that the displaced persons   should be assisted  in their   efforts   to    improve their    livelihoods   and standards   of    living   or   at    least    to    restore    them    to   pre‐displacement    levels   or    to    levels  prevailing prior to the start of project implementation whichever is higher.  Compensation   for   structures   should    include the   full   cost   of   materials, transport and   labour  required    for    reconstructing   buildings   of    similar    surface and    standing.    So  as  to enable  the  affected    person    to  comfortably  rebuilt  their    structures        in    a    different    location    using  compensation   paid  ;depreciation of property  value  should   not   be  taken    into   account   while  calculating    the   cost   of   affected   structures; and  the vulnerable PAPs  including  the elderly and single parent headed families should be given special considerations during resettlement especially for those who can’t read or have health problems. Thus the appointed implementing agent should ensure they understand the process and they get all the necessary help they require; such that for example,  affected  persons  should  be  exempted  from  all  administrative  and  legal  fees  incurred through the grievance redress procedures.   Finally, Monitoring procedures should be developed and appropriate  laws enforced  in  regards  to encroachment into and along the transmission line to reduce future encroachment by the public. 

Page 61: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

44 

 REFERENCES 1. Kenya Gazette  supplement Acts  2000,  Environmental Management  and  Coordination 

Act Number 8 of 1999.  Government Printer, Nairobi 2. Kenya  Gazette  Supplement  Acts  Land  Planning  Act  (Cap.  303)  Government  Printer, 

Nairobi 3. Kenya Gazette Supplement Acts Local Authority Act (Cap. 265) Government Printer 4. Kenya  Gazette  Supplement  Acts  Physical  Planning  Act,  1999  Government  printer, 

Nairobi 5. Kenya Gazette supplement Acts the Arbitration Act (2000); government printer, Nairobi. 6. Kenya  Gazette  supplement  Acts  The  Electricity  Supply  Line  Act  (Cap  315)  

(2002);government printer, Nairobi. 7. Kenya Gazette supplement Acts the Land Acquisition Act (Cap 295) government printer, 

Nairobi. 8. Kenya  Gazette  supplement  Acts  The  Land  Acquisition  Act  (Cap  Cap  288  ‐Trustland) 

government printer, Nairobi. 9. Kenya Gazette supplements Acts The Public Roads and Roads of Access Act  (Cap 399) 

government printer, Nairobi. 10. Kenya Gazette supplement Acts the Water Act (2002); government printer, Nairobi. 11. Kenya  Gazette  supplement  Acts  The Wayleave  Act  (Cap  292)  );government  printer, 

Nairobi. 12. Kenya Gazette supplement Acts the Wildlife Conservation and Management Act (1998); 

government printer, Nairobi. 13. Kenya  gazette  supplement  number  56.  Environmental  Impact  Assessment  and  Audit 

Regulations 2003. Government printer, Nairobi 14. The World Bank Safeguard Policies, 2005 15. District Development Plans 

  

Page 62: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

45 

 

                  

APPENDIX 

Page 63: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

46 

Appendix 1: List of Affected PAPs indicating their names and lost property   

Page 64: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

47 

Appendix 2: Household Questionnaires ESIA / RAP Socio­Economic Survey  I  SURVEY SAMPLE QUESTIONNAIRE IDENTIFICATION

  i. Survey Control Number 

  ii. Date of Interview: 

  iii. Place of Interview: 

  iv. Name of Interviewer: 

  v. Checked by Supervisor: 

II  BASIC PROFILE OF PAPs 

  A. Name of Interviewee: 

  B. Physical Address of the Interviewee  i. Division: 

  ii. Location: 

  iii. Sub‐location: 

  iv. Village: 

  v. Plot No: vi. Others vii. Mob. No. viii. Address 

  C. 1.Relation to Head of Family (Choose one)

        i.)Myself  ii) Wife iii) Child iv) Parents v) Other (Specify)

  2.How Many Years have you been living here?

  3.Is there any tenant in this house? If yes, number of tenants?

  4.How many years has/have the tenants (s) resided?

  (For Illegal occupant only) 5.How long are you planning to live here (in years)? 

  D. Profile of Head of Family 

  1.Name of head of Family 

  2.Gender:  Sex 1. Male, 2. Female

        3.Age 

        4.Marital Status: Married [  ] Unmarried, [  ] Widow [  ] Widower[  ]. 

        5.What  is  the  highest  educational  level  you  attained?i) None             [    ]ii). Primary does not read  [    ]iii). Primary reads      [    ]iv) Secondary & higher  [  ] 

      6.What other skills did you learn after School?

      7.List any employment jobs you have undertaken up to date

       8.No.  of  dependents        Wife(ves)‐‐‐‐‐‐‐‐‐‐‐‐Children(  below18)…………  Children(  above18)…….. 

       9.What is the educational level of the children?

Page 65: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

48 

                                                               (a)   Below18 No.            b) Above 18 No. i).  None              [    ]ii) Primary  [    ]iii)Secondary[    ]iv) Tertiary colleges & higher  [  ] v) University  [  ] vi) Others        [  ] 

     10.What other skills did each learn after School?

     11.Religion (choose one) i)Christian; ii). Muslim; iii). Hindu; iv). Buddhist; v). Other (specify‐‐‐‐‐) 

     12.Occupation (Choose all that apply)i)Government / Public Sector ii)Private Sector (employer) iii)Self‐Employed (specify) iv)Farmer v)Casual Labour vi)Unemployed; 

            vii)Others (Specify) 

       13.Total Number of family Members (including infants and children)

      14.List the family structures 

      15.Describe Social structures 

      16.Total Number of household in one house, record 2)(e.g if there are 2 households in one (your) structure 

  E.Resettlement 1.No. of affected persons 2.No. of people to be resettled 3.List of alternatives considered to avoid or minimize resettlement 4.Resettlement impacts 5.preliminary resettlement options 

  F.Institutions Present 1.List the institutions and Development Agencies in the area 

i. …………………………… ii. ……………………………. iii. ………………………….. iv. ……………………………. 

2.Indicate different roles of institutions in regard to: i. Use and access to credit ii. Use and access to marketing services iii. Use and access to commercial inputs 

3.Household level institutional structure         i)Nuclear family 

Page 66: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

49 

ii)Polygamous family       iii)Extended family 4.Information about how collective decisions are made at household and at local institutions 

  G.Gender & Cross cutting i.e.  1.Key gender differentials 2.Gender roles 3.Community participation i.e. attendance to meetings 4.Other special cross cutting issues 5.Sources of income along desegregated gender lines 6.Formal/informal use of natural resources 7.Domestic functions 8.Vulnerability to resettlement 9.Female‐headed households 10.Registration of property titles  11.Opportunities for income generation on resettlement 

  H.Income  1.Existing social‐economic activities  2.Income sources and Poverty levels (the full resource base of the affected) 3.Proposed measures to restore or improve incomes and living standards 4.Household  income/expenditures  (including  income derived  from  the  informal sector and from common property); 5.Skills 6.Employment and allocation of labor 7.Labour force and economic occupation  8.Opportunities for income generation on resettlement 9.Type of livelihood (subsistence, commercial or both) 10Gender roles in generation of household income 

  I.Assets 1.Types of assets i.e. land and livestock, equipment, buildings 2.Ownership of assets 3.Registration of property titles 

      4.What properties do you have inclusive the land  itself?            ‐Details of the properties;       5.Are the properties within the wayleave?       6.What is the value of your property?       7.On what do you base the value of your property       i. Market Value     ii. Property on Land iii. Others  

  J.Infrastructure , Public amenities communication 1.Transport in project area 

Page 67: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

50 

2.Communication mode 3.Water supply 4.Bridges 5.Power network 

             Distance from resources Source      6.How far is the your home/household from the amenities?           a)Under 1KM……………..1 

     b)Over 1 KM……………….2 

  K.Sources of energy1.Differentiate energy sources 2.Cost of the energy: How much will you be willing to pay for electricity monthly if supplied in your area…………………………. 3.In what mode are you willing to pay for the electricity meter? 

    1. In full   2.In installments    3.other modes specify       4.Availability of the sources 

i)Power Line ii)Generator (Private) iii)Generator (Common) iv)Car Battery v)Solar Energy 

            vi)Other (Specify) 

  L. 1.Cultural issues;      2.Traditional belief system with regard to gender, resource ownership and utilization 

  M.Land 1.Land ownership and settlement patterns;  2.Land size, 3. Type of land ( Public, commercial, communal),  4.Distribution of land within family/ community level  5.Types of tenure 

      6.nventory of affected assets 

        Resettlement 

• No. of people to be resettled • List of alternatives considered to avoid or minimize resettlement 

• Resettlement impacts preliminary resettlement options 

  N.Health      1.Type of Health facilities in the area       2.Common diseases, causes and preventive measurers      3.HIV/AIDS prevalence in the area      4.Health Risks 

  O.Impacts 

Page 68: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

51 

  1.List the potential Impacts of the Project oni. Households:…………………………. ii. Families:…………………………… iii. Communities …………………………. iv. Others……………………………………. 

   2.Social dynamics that  is  likely to hinder or facilitate the effectiveness of resettlement‐related options. 

    3.Potential adverse impacts on vulnerable groups.

    4.Risks presented by the project and the vulnerable groups likely to be affected 

    5.The needs and demands of affected persons

   6.Risks presented by the project to the vulnerable groups 

  P. Resettlement Preference      1.Where could you like to resettle? (Choose one) 

i)In the same community area ii)In the same district iii)The resettlement location does not matter iv)Others (specify) 

      2.Which way do you prefer to resettle?i)Resettling with community members ii)Resettling without community members 

            (For those whose livelihood and income sources are to be affected)   3.In  case  you  are  to  be  displaced  by  the  project,  what  would  be  your  choice?  (choose applicable, but not inconsistent) 

i)Provision of new agricultural plot ii)Provision of new plots/assets for economic activities (e.g. shop, workshop, office, etc) iii)Training for self employment iv)Cash grant equivalent to loss v)Others (specify) 

    4.What kind of assistance regarding resettlement and rehabilitation do you request/suggest for the Project Implementation Authority? 

Page 69: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

52 

 

Appendix 3: Locations where socio­economic survey and household census were undertaken  

Group Number 

Date  Area 

I  20/10/2009  

Matora  village,  Buchifi  sub‐location  Buchifi  location,  South  Wanga Division in Mumias District 

21/10/2009  Buchifi, Emaunga, Buyole villages in Buchifi sub‐location Buchifi location, South Wanga Division in Mumias District ‐Masinjira sub‐location  

22/10/2009  Buchifi and Emukanga villages

II  20/10/2009  Bukhweso village in Masinjira sub‐location, Buchifi location 

21/10/2009  Mundindi village in Masinjira sub‐location, Buchifi location  ‐  Ebuyenjere, Mushechere,  Khushipare  villages  in Bukaya  sub‐location, Itenje location   

22/10/2009  Kit Luiyo, Lukongo Bukaya sub‐location, Itenje location  

23/10/2009  

Kulumuayo,  Bumala,  Buhkwayo  in Madungu‐Sub‐location  , Uholo  East location  

III  21/10/2009  ‐Madungu and Simerro 

22/10/2009  Madungu, Ugolwe, Simerro and Rangala

23/10/2009  Simerro and Simenya

IV  20/10/2009  ‐Shivale village, Nabongo location ,Mumias Division 

21/10/2009  Angola  village,  Township  sub‐location,  Nabongo  location  ,  Mumias Division ‐Shitukumi Township sub‐location, Nabongo  location 

22/10/2009  Nyakwakwa,  Lureko,  Edokho  A&B  villages,  Lureko  sub‐location  , Nabongo  location,  Mumias Division 

  23/10/2009  Yala  

  22‐23/10/2009 

Kanyakwar

   

Page 70: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

53 

Appendix 4: Resettlement Action Plan Activity Schedule   Implementation activities   

Period in months

Sept ‘10 

Oct   Nov Dec Jan’11 Feb Mar April May  June  July Aug

Formation of PIU         

PIU meeting          

Verification of census data         

Valuation of assets and confirmation 

       

Sharing of RAP         

Payment of compensation          

Land purchase for resettlement 

       

Construction on resettlement site 

       

Relocation          

Income restoration programmes 

       

Internal Monitoring          

External monitoring   After the project has been implemented

Reporting          

 

Page 71: AND LIMITED RESSETLEMENT ACTION PLAN FOR …kplc.co.ke/fileadmin/user_upload/Documents/RAP/RAP Mumias...THE KENYA POWER AND LIGHTING COMPANY LIMITED RESSETLEMENT ACTION PLAN FOR THE

132kv Transmission Line: Mumias‐Rangala‐Kisumu Resettlement Action Plan 

54 

 

Appendix 5: Resettlement Action Plan Public Grievance Form  RAP Reference No.  

Full Name  Contact Information   Address: ‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐

Please  mark  how  you  wish  to  be contacted  

‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐  

(mail, telephone, e‐mail)  Telephone:‐___________________________________ Email‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐Preferred Language for   English Communication(Please  mark  how  you wish to be contacted)  

Kiswahili 

National Identity Number  Where did it happen?  Who did it happen to?  What is the result of the problem  Date of Incident/ Grievance  One time incident/ grievance( date‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐) Happened more than once (How many times‐‐‐‐‐‐‐‐) Ongoing (Currently experiencing problem………….) What would you like see happen to solve the problem?  Signature:  Date:  Please return this form to: