analysis of the results achieved by cip eco- innovation ... · analysis of results achieved by cip...
TRANSCRIPT
Executive Agency for Small & Medium Enterprises (EASME)
Analysis of the results achieved by CIP Eco-innovation market replication projects (EACI/ECO/2013/001)
Final Report
Annex A2 – Global project report
29th January 2016
This page is intentionally blank
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT – ANNEX X
i
Analysis of results achieved by CIP Eco-innovation market replication projects (EACI/ECO/2013/001)
Final Report
Annex A2 – Global project report
A report submitted by ICF
in association with VITO
Máté Péter Vincze
ICF Consulting Services Limited 146 Rue Royale B-1000 Brussels
T +32 (0) 2 275 01 00 F +32 (0) 2 275 01 09 [email protected]
www.icfi.com
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT – ANNEX X
ii
Document Control
Document Title Analysis of the results achieved by CIP Eco-innovation market replication projects (EACI/ECO/2013/001) Final Report Annex A2 – Global project report
Date 29th January 2016
This report is the copyright of the European Commission and has been prepared by ICF Consulting
Services Ltd under contract to the European Commission. The contents of this report may not be
reproduced in whole or in part, nor passed to any other organisation or person without the specific
prior written permission of the European Commission.
ICF has used reasonable skill and care in checking the accuracy and completeness of information
supplied by the client or third parties in the course of this project under which the report was produced.
ICF is however unable to warrant either the accuracy or completeness of such information supplied by
the client or third parties, nor that it is fit for any purpose. ICF does not accept responsibility for any
legal, commercial or other consequences that may arise directly or indirectly as a result of the use by
ICF of inaccurate or incomplete information supplied by the client or third parties in the course of this
project or its inclusion in this project or its inclusion in this report.
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT – ANNEX X
iii
Contents
1 Introduction .........................................................................................................1
2 Project portfolio ...................................................................................................2 Key figures ............................................................................................................................... 2 2.1
Terminated and other unsuccessful projects ........................................................................... 5 2.2
3 Participants profiles ..............................................................................................6 Key characteristics of participants ........................................................................................... 6 3.1
Innovation background ............................................................................................................. 8 3.2
4 Innovation outcomes .......................................................................................... 12
5 Economic benefits .............................................................................................. 14 Commercialisation .................................................................................................................. 14 5.1
Investment leverage ............................................................................................................... 14 5.2
Revenue from sales ............................................................................................................... 15 5.3
Gross Value Added ................................................................................................................ 16 5.4
Job generation ....................................................................................................................... 16 5.5
6 Environmental benefits ...................................................................................... 17
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
1
1 Introduction
This Annex summarises key findings from the assessment of CIP eco-innovation projects
from the 2008-2011 calls globally - broken down by the call.
The analytical work concerning all 185
projects funded under the four annual calls
2008-2011, undertaken for this Annex is
fully analogous to the statistical
assessments contained in the Main Report,
and uses the same project-level data
analysed there, with corrections for
‘optimism bias’ and imputed values for
projects where revenue or jobs data were
missing.
The Annex gives an introduction to the full
project portfolio and then briefly present the
composition of the eco-innovation projects
along various dimensions and the
participants behind them. Then it
summarises key innovation outcomes and
the estimated economic benefits (primarily
investment leverage, revenues and jobs).
Finally, they present the expected
environmental benefits by priority area,
taken from the estimates made by VITO for a subset of 133 projects with a full life-cycle
perspective.
Figure 3.4 Breakdown of all projects funded in 2008-2011
Source: EASME monitoring database
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
2
2 Project portfolio
Key figures 2.1
In total 185 projects received funding in the first four rounds of annual calls between 2008
and 2011. The use of the initiative increased during this period, with the number of project
proposals submitted more than doubling in two years from the launch of the initiative, and
remaining at these high levels in 2011-2012.
Table 2.1 Overview of CIP eco-innovation annual call results (2008-2011)
Criteria 2008 2009 2010 2011
No. of proposals submitted 134 202 287 280
No. of proposals funded 44 46 46 48
Success rate 32.8% 22.8% 16.0% 16.8%
Total funds committed (€m) 27.5 30.7 36.7 32.1
Average funding per project (€k) 626 668 798 684
Source: EASME analysis of calls, EASME project monitoring data
At the time of the analysis of project data
in this study, 31 projects were still open:
30 from the 2011 call and 1 from the 2010
call.
The ‘greening business’ priority are by
some margin the most common type of
projects, accounting for 56 projects
between 2008 and 2011, which
represents 30% of the total portfolio
(Figure 3.4). It is closely followed by the
recycling priority area totalling 54 projects
(29%). Projects under the ‘food and
drinks’ priority area account for 17.3%
while building and construction projects
as well as water-related projects
represent only 12.4% and 10.8%,
respectively.
Of the four original priority areas of the
initiative for the period between 2008 and
2011 (‘water’ has been added later as priority area), ‘recycling’ projects were the most
common in the first year (accounting for 41% of the projects in 2008), with ‘green business’
taking over the lead in 2009. In 2010, there were again more projects related to ‘recycling’
than in any other priority area, but this was reversed in 2011 when ‘green business’ became
the predominant priority area for projects.
Figure 3.5 Number of open projects in
September 2015, by call
Source: EASME monitoring database
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
3
Project coordinators for the four annual calls between 2008 and 2011, came from a total of
25 EU Member States and 3 non-EU members (Croatia, Israel and Turkey) – see Figure 3.5.
As observed already from the beginning of the initiative, the projects are rather unevenly
distributed geographically: 41 projects were coordinated from Spain while only 4 in Greece
and Ireland.
The breakdown of projects per call to which the project proposal was submitted varies shows
an exceptional dominance of Italy in the earliest (2008) call, with projects coordinated from
Spain, Germany, the Netherlands and the United Kingdom catching up from 2009 onwards
(see Figure 3.7 below). Interestingly, projects from countries not heavily represented in the
initiative (for instance, Finland, Estonia, Hungary, Turkey) tended to be selected in the early
two calls. The projects chosen for EC funding under the 2010 and 2011 calls came
disproportionately from a smaller number of Western European countries - Spain, Germany,
Denmark, the Netherlands and the UK.
Figure 3.6 Breakdown of all projects funded in 2008-2011, by country of coordinator
Source: EASME monitoring database
Figure 3.7 Number of eco-innovation projects hosted in 2008-2011 (location of project coordinator), broken down by call
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
4
Size of pies proportional to the number of projects
Source: ICF based on EASME monitoring database
In terms of the self-assessed novelty of the innovation, the CIP eco-initiative has been
characterised by a constantly increasing share of more ambitious ‘radical’ innovations over
the years, growing from only 2 projects under the 2008 call to 12 in the 2011 call. The
proportion of incremental innovations remained more or less stable at 20-30% of all projects.
Surprisingly, the very visible increase in radical innovations was not coupled with any
significant change in the composition of projects by their impact existing supply chains: the
share of projects calculating with sustaining, significantly modifying or disrupting existing
supply chain relations all remained more or less stable over the years.
Source: ICF survey of project coordinators, analysis of project documentation
Figure 3.8 Breakdown of projects by call and novelty of innovation
Figure 3.9 Breakdown of projects by call and impact on supply chain
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
5
Terminated and other unsuccessful projects 2.2
From the 23 failed projects, two thirds come from the first two years’ calls (2008 and 2009)
and only one third from 2010 and 2011 calls; the main explanation is that the newer projects
typically started in the year after the call had been published and most of them took the
maximum allowable 3 years, so not enough time passed to demonstrate success or concede
failure. Overall, unsuccessful projects represent about an eighth (12.4%) of the total of
projects funded in 2008-2011, which is certainly not too high, considering the risk profile of
innovation projects and the ambitious innovation results required by the calls.
Among terminated projects, the main reasons listed in EASME’s records were negative
change in the economic environment (i.e. sudden change of market conditions and
withdrawal of potential clients), technical difficulties (i.e. failure of testing phase), and
problems stemming from inadequate cooperation between consortium members.
A complementary quality analysis of projects
can be undertaken for purposes of triangulation
on the basis of EASME’s latest available
classification of the progress of the CIP eco-
innovation projects (including projects already
closed) into three brackets, which may be
referred to as ‘Good’, ‘Medium’ or ‘Concern’.
Understandably, projects last categorised by
EASME as giving ‘concern’ (many of which are
of course already closed, maybe cancelled
early) are more concentrated in the earlier
calls, as a certain degree of project maturity
was necessary to discover problems with the
consortium or to prove that the
commercialisation effort are very unlikely to
lead to any market success.
Figure 3.10 Breakdown of projects by EASME’s latest available classification of progress (2008-2011 calls
Source: EASME monitoring database
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
6
3 Participants profiles
Key characteristics of participants 3.1
Between 2008 and 2011, the 187 projects launched under the four eco-innovation calls of
the Competitiveness and Innovation Programme involved a total of 663 participants, of which
31 were appearing in two, and only 10 in more than two projects. The total number of
participant slots – i.e. with duplications – was 723.1 This indicates that the initiative was not
monopolised by a small circle of applicants (most participants with multiple contracts were
technological institutes supplying supportive innovation services), which is consistent with
the initiative’s aim to help companies in a crucial phase before establishing a new
sustainable business/activity, and not to provide continuous funding to permanent clients.
Project participants in projects funded under the 2008-2011 calls, by number of Table 3.1occurrences and role
Occurrence as project participant
Number of participants
Occurrence
Total As coordinator As partner
Once 621 621 468 153
Twice 31 62 50 12
Three times 5 15 8 7
Four times 2 8 5 3
Five times 1 5 2 3
Six times 2 12 6 6
TOTAL 662 723 539 184
Source: EASME administrative data
The highest share of beneficiaries as well
as EU funding allocated to beneficiaries
over the 2008-2011 period (see Figure 3.1
Figure 3.2 below) belong to Spain, Italy,
Germany, the UK, Netherlands and France.
While Germany, Italy and France are
among the largest countries in the EU and
thus they would be expected to have a high
share of beneficiaries, Spain and the
Netherlands seem to have a bigger weight
than expected, being over-represented
among beneficiaries.
There was somewhat surprisingly little
involvement of Sweden and Finland –
included among ‘other’ in the two figures
below – despite being eco-conscious
leading innovating countries.
1 All figures refer to the original composition of the consortia. For a small number of projects, partners were
dropped, replaced, or new partners added. 2 Covers individual beneficiaries who might be participating in more than one project.
Figure 3.11 Breakdown of beneficiaries2
participating in eco-innovation projects, by country (2008-2011)
Source: EASME monitoring database
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
7
As some projects may have a lot of
beneficiaries which all have only a small
input individually, taking account of
geographical patterns by participant may be
somewhat biased. A relatively useful proxy
measure to gauge the ‘significance’ of
participants’ inputs is the amount of EU
funding they receive. The breakdown of the
total EU funding committed to CIP eco-
innovation projects from the 2008-2011
calls is overall very similar to the
breakdown by participant, but smaller
differences exist. Notably, the share of the
two ‘frontrunners’ Spain and Italy in funding
is in total larger than the proportion of
participants coming from these countries.
Netherlands also enjoys a relatively large
share from the eco-innovation funding
compared to the number of beneficiaries
participating, whilst the opposite holds for
France.
The results of the online survey filled in by project coordinators reveals more detailed
information on who they are, as summarised in the two figures below. The overwhelming
majority of project coordinators surveyed (70% of them) are well established businesses,
being in operation over 11 years. At the time of applying for CIP funding, 43% of survey
respondents had been in operation between 11 and 25 years at the moment of their grant
application and another 27% had been in operation for over 25 years. Seven organisations
(5%) had been in operation for less than 2 years.
The vast majority (77%) of project coordinators responding to the survey were private
companies. Out of the non-private coordinators, only 6% were academic or research
institutes and even fewer were industry interest groups, chambers of commerce or publicly
Figure 3.12 Breakdown of EU funding allocated to beneficiaries (€ m), by country (2008-2011)
Source: EASME monitoring database
Figure 3.13 Length of time in operation for project coordinators applying for grants in 2008-2011
Source: ICF survey (N = 143)
Figure 3.14 Type of organisation of project coordinators receiving EU funding in 2008-2011
Source: ICF survey (N = 150)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
8
owned companies, accounting for 3% each of the share of total project coordinators
respondents. Other 3% of the consortium leaders categorised themselves as ‘other’; these
include Research and Technology Organisations (RTOs), privately funded research
institutes as well as public-private partnerships or other hybrid organisational forms.
The proportion of SME participants among the beneficiaries has been high already under the
first call (61%), and has further increased (to 67-68%) for the next three calls. The four-year
average was 66%. After de-duplicating the sample in order to only calculate with single
organisations rather than occurrences or ‘slots’ in projects as coordinator or project partner,
the share of SMEs increases even further, to about 68%. This indicates that SMEs are
slightly less likely to request funding again from the eco-innovation initiative.
Project participants in eco-innovation projects funded (2008-2011 calls), by SME Table 3.2categorisation
Call Total beneficiaries of which: SMEs SME proportion (%)
2008 186 114 61.3
2009 190 127 66.8
2010 178 121 68.0
2011 169 115 68.0
TOTAL 723 477 66.0
TOTAL (de-duplicated) 662 449 67.8
Source: EASME administrative data
Innovation background 3.2
The surveyed project coordinators of
CIP-funded eco-innovation projects –
and probably many of the additional
project partners, for which such
information was unfortunately not
available - exhibit a business culture
focused considerably on innovation
activities. The responding project
coordinators were about evenly split
in terms of their strategic focus
between being mainly user of
innovation (e.g. manufacturers),
supplier of innovation services
(research institutes, specialist
consultancies), or innovation
facilitators and others. Interestingly,
the weight of the two larger categories
- innovation users and innovation
service suppliers – increased
significantly in the latest two calls as
compared to 2008 and 2009, when
facilitators played a decisively large
role.
Innovation activities are typically important – or fundamental – parts of the operations of
project coordinators. In-house research and development has traditionally been important for
almost all of them (91% of respondents), and the large majority of them has a strong focus
on introducing new products/services. Project coordinators are also experienced in public
Figure 3.15 Main organisational focus of project coordinators (2008-2011 calls) in relation to innovation (%)
Source: ICF survey
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
9
funding applications. 68% of coordinators have applied to national R&D programmes while
23% had applied to the EU’s R&D framework programme (FP6 or FP7) and 18% had applied
to the EU’s LIFE Environmental programme.
Figure 3.16 Traditional importance of innovation for the business model of project coordinators
Source: ICF survey
A large number of innovations had been initially developed with the funding of other EU
funding initiatives. National R&D programmes are however the most common: 66% of
coordinators have applied to national R&D programmes, and 29% to a regional programme.
Project coordinators are however also reasonably experienced in applying for EU funding:
27% had applied to the EU’s R&D framework programme (FP6 or FP7), 19% had applied to
the EU’s LIFE Environmental programme, and 7% to the Eureka Eurostars programme for
SMEs.
Figure 3.17 Experience in public funding applications
Source: ICF survey
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
10
65% of project coordinators were the initial and primary developer of the innovation. A large
number of innovations had been initially developed with the funding of other EU funding
initiatives. Consortiums are often built up to include main collaborations in the supply chain
and a more technical/academic partner who is responsible for project management and
reporting, technical assistance and assessments (required for the environmental
performance assessment and for eventual Eco-labelling applications). The project developer
is in many cases is a private RTO who in collaboration with a client developed a certain
process or product and wants to further develop the innovation in collaboration with other
international actors in the supply chain.
Also from the survey, 42% of projects are SME-academic collaborations. Most project
coordinators operate in the manufacturing sector (37%) followed by a companies offering
environmental services (34%) and who are involved in scientific and technical activities
(25%).
Most consortia are led by private companies even though academic and research institutes
as well as industry associations and chambers of commerce still play a significant role in
many of the innovation projects funded under the CIP eco-innovation grant scheme.
A breakdown of survey respondents by consortium type shows four distinct groups: 42% of
the consortia could be described as a ‘SME-academic collaborations’, comprising SMEs and
research institutes. Consortia of SMEs were also common and accounted for 38% of the
sample. Of the remaining 21%, 14% were large businesses and 7% were individual SMEs.
Half of the consortia headed by Italian or Spanish undertakings were SME-academic
collaborations, i.e. collaborations between SMEs and academic and research centres. In
contrast, such networks have a lesser weight among the projects from the Netherlands and
in the United Kingdom, where SME-academic consortia or consortia between SMEs are
more common. In these two latter countries over 80% of the project consortia members are
private companies (see Figure 3.18).
Figure 3.18 Types of consortia by country of the project coordinator
Source: EASME monitoring data, ICF survey.
"Other" includes France, Austria, Denmark, Slovenia, Belgium, Estonia, Greece, Ireland, Israel,
Croatia, Cyprus, Hungary, Luxembourg, Portugal, Sweden, Turkey (less than 8 projects each)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
11
Prior cooperation between project partners
was the rule – in 65% of the projects all or
some of the partners have already been
working together (77% among projects with
at least two cooperating partners).
But a sizeable number of projects, close to
20%, generated cooperation between
companies, private innovation service
providers, academia or industrial
organisations in pursuit of eco-innovation
that did not exist before – an additional
benefit of the eco-innovation initiative.
These patterns did not change significantly
between calls - the figures 2012 only seem
to be outliers because of the very small
sample size for this year.
Figure 3.19 Prior cooperation of project partners
Source: ICF survey (n=118)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
12
4 Innovation outcomes
The targeted end users of the innovations –
often including the original project
consortium – are mostly businesses. A total
of 87% of the projects indicated that
businesses are among their targeted
customers – they are typically the only or
the overwhelmingly most important
customer type. Another 31% of projects
wants to sell to the public sector, and 21%
to private households (consumers).
The main reason for business clients using
the innovation is either Corporate Social
Responsibility, the perspective of gaining
competitive advantage (through more
efficient processes, for instance) or
compliance with regulations. The typical
business customer of the companies introducing innovations are SMEs, who account for
59% of their customer base.
Clients are mainly active in the manufacturing sector (28%) and the environmental services
(17%) (see Error! Reference source not found.). The main economic benefit of the
innovation for business customers are cost savings (72%), reduced energy consumption
(56%), increased sales of goods or services (45%) and reduced cost of compliance (45%).
Of the 54 respondents answering to this question in the main survey, 37% of projects have
prepared a business plan with a remaining 54% currently developing a business plan while
another 7% are still planning to develop a business plan. 34% claims to have fully
implemented their original business plan while 37% have only partially implemented it and
16% have rewritten their business plan (e.g. to reflect a change in strategy). 6% have
abandoned the commercialisation (sales) plans for their innovation.
Figure 3.21 Profile of typical business customer (by number of projects)
The innovation was already put to use for 80% of the responding projects (97 out of 121) –
either within the project consortium or outside, e.g. through selling or licensing the
Intellectual Property (IP). The corresponding proportion of projects under 2011 call was
lower, only 72%, partly probably reflecting that less time has passed since the project
initiation.
The direct gains for consortium members undertaking the innovation project often stems
from using the outcomes of the innovation in their own company (e.g. cutting costs or
increasing revenues), or selling the Intellectual Property to other companies (see also
chapter 5.1).
Figure 3.20 Targeted end users of the innovation (%)
Source: ICF survey (n=129)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
13
Some organisations may even disseminate the results at no cost. For the latter group, the
economic benefits they envisage may be winning new clients or simply being compensated
for their work.
Out of those projects that were already successful in putting their innovation to use, past or
planned utilisation within the own company or project partners – but also the sale of the IP -
is dominant, with remarkable differences across calls: own use or project partners’ use is
much less prevalent in the first two-three calls than amongst more recent successful
projects.
Unsurprisingly, projects under the early calls were much more likely to have already
experienced commercial benefits than newer ones: the typical time needed for the eco-
innovation projects from contract signature to actually produce such outcomes is relatively
long. It should be noted that among those who gave a positive response to this question,
many have only received expressions of interest from potential clients.
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
14
5 Economic benefits
Commercialisation 5.1
The typical commercial benefit of the
innovation for participants in the eco-
innovation projects comes from using it in
their own (mostly business) organisation:
60% of project coordinators thought this
would be/or already is an economic benefit
they derive from the innovation project. It is
a little less relevant for early projects – this
could be a maturation effect, as some
projects discover over time that they would
not be able to use the results in-house in
the end (although originally planned).
The production and selling of an innovative
product or licencing a process was the
source of benefit for 36% of project
coordinators (much more pronounced for
later calls); and selling or licencing the
intellectual property was a benefit for about
the same proportion of coordinators.
Simple reimbursement for contributions to
the project is the only source of commercial
benefit for some participants – interestingly
not only for partners (such as laboratories
testing new products, specialist consultancies, facility installers), but somewhat surprisingly
also for some project coordinators.3 These coordinators tended to be public entities, or in
case they were private company their main focus was on supplying specialist innovation-
related services or were seeing themselves as innovation facilitators.
Investment leverage 5.2
In total, €127 million EU funding has been committed to an initial 137 eco-innovation projects
(i.e. before early contract terminations or cancellations) under the 2008-2011 calls. This
funding is, as in all similar programmes, just one part of the actual investment in the
innovation project. This public co-financing is coupled with two types of additional monies,
which were committed to the projects by the consortia:
■ applicants’ own resources committed to the project and included in the budget. This
value was obtained by deducting the EC contribution from the overall project budget;
■ additional induced investments made – or commercialisation activities to be made during
later-stage – both additional monies, that do not form part of the project budget. This
value was estimated and supplied by project coordinators in the online survey.
Compared to the predecessor study, with data collection in 2012, a much larger part of these
figures is based on factual data. A small number of projects did not give updated figures,
here old data was multiplied with the previously established generic adjustment factor of 0.9,
and the value was statistically imputed for the rest of projects to obtain a grossed-up figure
for the initiative.
3 Note however that depending on the sub-question, 5 to 7 coordinators indicated they expect simple
reimbursement (i.e. no other benefit) and some other commercial benefit. Filtering out these responses from those expecting only simple reimbursement would decrease the corresponding percentages by 3-4 points.
Figure 3.22 Origin of expected/experienced commercial benefit from the innovation for coordinators (%)
Source; ICF survey (n=143)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
15
New data coming in from the 2015 survey, as compared to available information from the
previous study in 2012, led to a dramatic increase in our estimate for non-budgeted
investments and leverage factor. For the same group of 2008-2010 projects for which only
23.4 million euro additional (non-budgeted) investment was estimated (a total leverage factor
of 131%), the current updated estimate is 273.8 million. Adding the new projects from the
2011 call, this value increases to 319.8 million, corresponding to a leverage factor of 357%.
This is much higher than the 131% estimated in the predecessor study in 2012. The main
explanation for this increase is most likely that relatively few project coordinators were willing
to give an estimate back in 2012, being early in the commercialisation process, and reported
only the small additional investments already incurred (sometimes zero values).
The breakdown of data along different dimensions indicates that projects in the Food and
Drinks priority area had a higher investment leverage - although caution is warranted when
drawing conclusions from the data due to the small sample size and the heterogeneity of
projects. Similarly, projects implementing product innovation and targeting only incremental
improvements exhibited a higher leverage potential than other types of innovations.
Table 5.1 Own resources and investment leverage by call (successfully closed and ongoing projects), M euros
2008 2009 2010 2011 TOTAL
EC contribution 27.5 30.7 34.0 34.9 127.1
Budgeted own resources 28.4 33.9 34.7 36.6 133.6
Additional investment
(not budgeted)
112.1 124.1 37.6 46.0 319.8
Total own resources 140.5 158.0 72.3 82.6 453.4
Leverage
(Total / EC contribution)
510% 514% 213% 237% 357%
The table covers all projects for which financial information was available (including early terminations)
Source: EASME monitoring database, ICF survey
Revenue from sales 5.3
The CIP eco-innovation grant supports
mature innovation projects that can be
turned into successful business, which
usually involves – if the objective is not
only internal cost-saving - new sales
generated by the product, process or
service being developed. The
assessment of factual data and the
study’s estimates for the 2008-2011
project portfolio show that the 185
projects investigated have on average a
reasonably good revenue generation
potential, even though earlier estimates
from the predecessor study had to be
revised downwards.
Additional annual revenue generated by
the innovation projects – as a
consequence of the commercialisation of
the innovation – has reached, or is
estimated to reach about €140 million at
the end of the projects (a moving data
between 2012 and 2015, depending on the call when a project was selected), and over €500
Figure 3.23 Estimated additional business revenue per project (EUR ‘000)
Source: ICF survey (N = 185)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
16
million two years after. This corresponds to a grand average of €750,000 for each of the 185
projects at project end, and €2.7 million two years after (including projects which did not plan
to sell the outcomes of the innovation anyway).
The estimates obtained for the two key reference periods are presented in Figure 3.23Error!
Reference source not found.. According to this data projects under the 2010 calls are
producing the highest business revenues.
Gross Value Added 5.4
The project portfolio’s combined annual GVA contribution is estimated to be approximately
€56 million at project closure and ca. €219 million two years after closure. These calculations
take into account the ‘optimism bias’ corrections applied to the projected revenue figures. If
the GVA generated remains constant after the second year upon project closure for another
additional three years, as assumed for revenues, the combined value creation for the five-
year period counted from the end of projects will be just over €1 billion.
After adjusting for deadweight, market displacement and complementarity and multiplier
effects the net additional economic contribution two years after project end is estimated to be
some €260 million and the cumulative increase in GVA over the life of the projects and the
following two years is over €400m. This sum is approximately three times the programme
cost, even without taking into account continuing future contributions to GVA.
Job generation 5.5
The combined employment generation of
the eco-innovation project portfolio (in
new full-time equivalent jobs, FTE) is
estimated to have reached, or reach
shortly around 550 at the end of projects,
and almost 1500 two years after. The
current estimates correspond to an
average per-project value of three FTE
jobs at the end of projects, which is due
to increase to 8 FTE upon two years
(counting in supply chain effects, this
increases to 9).
The relatively moderate progression in
the FTE jobs for projects for the early
2008 and 2009 calls (as compared to the
more confident projections for the 2010
and 2011 calls) might indicate an
additional ‘maturity impact’, with projects
already being tested on the market and
finding that the number of jobs they can
create, on average, is lower than they
originally planned – in fact some of the most mature projects have been unfortunately wound
down as they were not as successful as expected.
Figure 3.24 Estimated additional employment per project (full-time equivalents)
Source: ICF survey (N = 185)
Analysis of results achieved by CIP Eco-innovation market replication projects FINAL REPORT ANNEX A2 – Global report
17
6 Environmental benefits
The table below summarizes the resulting environmental Key Performance Indicators (KPI).
Most KPI refer to tangible savings or reductions of materials, water, waste, emissions and
energy, achieved by the eco-innovation initiatives, in a full life cycle perspective. The
monetized savings indicator, however, allows to integrate the different types of
environmental impacts that arise as a consequence of the tangible savings, called inventory
savings, into a single score. The monetized savings indicator is the sum of all costs that will
have to be borne by society as a whole in order to avoid or repair damages to the
environment and human health. This approach offers the advantages to make value
judgments and assumptions explicit and avoid arbitrary weighting.
This way, the monetized savings indicator delivers a suitable proxy for the overall
environmental effect of an eco-innovation project.
Environmental Key Performance Indicators Table 6.1
Environmental indicator Projects analysed (133)
Grossed up to all projects (189)
End of project
2 years after
End of project
2 years after
Greenhouse gas emission
reductions (Ton CO2 eq.) 432,078 3,913,961 527,634 5,104,009
Water savings (m³) 4,306,952 187,868,772 5,691,413 198,384,331
Energy savings (Ton oil eq.) 164,632 1,673,470 214,417 2,175,683
Waste savings: Hazardous waste
(Ton) 24,681 29,377 24,705 29,503
Waste savings: Non-hazardous
waste (Ton) 224,284 938,610 252,856 1,155,735
Waste savings: Radioactive waste
(Ton) 12 122 14 155
Renewable materials savings (Ton) 57,745 156,742 59,597 176,558
Non-renewable materials savings
(Ton) 153,826 1,696,541 198,027 2,222,096
Monetized savings (‘000 €4) 76,895 917,271 93,670 1,192,041
Source: VITO analysis
4 2011 euro value