analysis of a pipe arch culvert subjected to exceptional live loaiy
TRANSCRIPT
z9~y q~5" :1 5'1/
~XPERIMENTAL AND NUMERICAL
ANALYSIS OF A PIPE ARCH CULVERT SUBJECTED
TO EXCEPTIONAL LIVE LOAIY
A Thesis Presented to
The Faculty of the College of Engineering and Technology
Ohio University
Athens, Ohio
In Partial Fulfillment
of the Requirementsfor the Degree
Master of Science in Civil Engineering
by
Devarajan ~helliat;'
March, 1992
This thesis has been approved
for the Department of Civil Engineering
and the College of
Engineering and Technology
Russ Professertif Civil Enginee
Dean of the College of
Engineering and Technology
11
ABSTRACT
A full-scale field test was conducted to determine the response of a corrugated
metal pipe arch culvert for the exceptional live load. The design span and rise of the culvert
were 15 feet 8 inches and 9 feet 6 inches respectively. The cover for the first and second
day of testing were approximately 7.5 feet and 3 feet respectively. Position transducer and
strain gage techniques were used to measure the deflection and strains. Data was collected
by using computer controlled data acquisition system. A tape extensometer was used to
determine the shape of the culvert before and after the testing. Exceptional live load was
applied through the two seven inch diameter piston rod hydraulic cylinders. They had a
capacity of 230 tons and connected to a hydraulic control unit for simultaneous operation.
A total of three loading sequences were applied, one on the first day and two on the
second day.
The ultimate load carrying capacity of this type of culvert under 3 feet cover was
determined to be 100 tons approximately. Maximum vertical deflection of 6.989 inches
occured at the crown point during the third loading sequence. During the first sequence the
magnitude of moment and thrust was insignificant. In the first loading sequence symmetric
nature prevailed in the culvert response. No section exceeded its ultimate moment capacity
of 3.745 kips-ft/ft, During the second and third loading sequences of only section four
exceeded its plastic moment capacity and formed a plastic hinge. The formation of creases
at both sides of the instrumented section were reported. The slip occured at a bolted
connection near to the crown was also reported.
A numerical analysis was done using the CANDE finite element program.
Parameters for Duncan's hyperbolic model were derived from the triaxial tests conducted
using the undisturbed soil samples from the field. The numerical predictions were
compared with the field response. Although the magnitude didn't agree well an identical
trend was observed between the numerical simulations and the field results.
iii
ACKNOWLEDGEMENTS
I would like to express my sincere appreciation and gratitude to Dr. Shad M. Sargand
for his instructive guidance and supervision that made this research work possible. I would
also like to thank him for supporting me during my entire stay in Athens.
I would like to thank Dr. Glenn A. Hazen for his helpful suggestions and constructive
criticism. I am deeply indebted to Mr. Teruhisa Masada for the long hours of tireless work
that he put in from the beginning to the end of this project.
I am also grateful to all the students and technicians who were responsible for the
experimental set-up and data acquisition.
Funding for this project was provided through a research grant from the Ohio
Department of Transportation.
IV
TABLE OF CONTENTS
Abstract iii
Acknowledgements iv
Table of Contents v
List of Tables ~ vii i
· f F' ·LIst 0 igures IX
Chapter 1
INTRODUCTION
1.1 GENERAL STATEMENT 1
1.2 OBJECTIVES 2
1.3 OUTLINE OF RESEARCH 2
1.4 ~I11ERA~~V~~ 3
Chapter 2
PIPE ARCH CULVERT AND FIELD INSTRUMENTATION
2.1 GENERAL 6
2.2 DESCRIPTION OF PIPE ARCH CULVERT AND BACKFILL
~TERIAL 7
2.3 ~IVE~OADAPPLICATION SYSTEM I0
2.4 FIELD INSTRUMENTATION OF PIPE ARCH CULVERT 17
v
Chapter 3
MEASUREMENT OF CULVERT DEFORMATION
3.1 OVERVIEW OF DEFORMATION MEASUREMENT 24
3.2 TAPE EXTENSOMETER MEASUREMENTS 24
3.3 POSITION TRANSDUCER MEASUREMENTS 30
3.4 DISCUSSION 64
Chapter 4
MEASUREMENT OF PLATE FORCES
4.1 INTRODUCTION 66
4.2 REDUCfION OF STRAINS TO AXIAL THRUST AND BENDING
MOMENf 66
4.3 ANALYSIS OF RESULTS 68
4.4 PLASTIC MOMENT CAPACI1'Y 107
4.5 FORMATION OF PLASTIC HINGES AND CREASES I07
Chapter 5
FINITE ELEMENT ANALYSIS
5.1 INTRODUCTION 114
5.2 CANDE BACKGROUND 115
5.2.1 SOLUTION LEVEL 115
5.2.2 PIPE TyPES 115
5.2.3 ELEMENT TyPES 116
5.2.4 SOIL MODEL 116
vi
5.3 FIELD SOIL SAMPLING WORK 116
5.4 lABORATORY SOIL TESTING METHOD ll?
5.5 RECOMMENDED SOIL PARAMETERS 119
5.6 FINITE ELEMENT SIMULATION 119
5.7 DISCUSSION 128
Chapter 6
CONCLUSIONS AND RECOMMENDATIONS
6.1 SUMMARY AND CONCLUSIONS 143
6.2 RECOMMENDATIONS 144
REFERENCES 146
vii
LIST OF TABLES
Chapter 2
Table 2.1 Characteristics of pipe arch culverts 9
Table 2.2 Soil boring data for test hole #1 11
Table 2.3 Soil boring data for test hole #2 12
Table 2.4 Live load application-First day l 7
Table 2.5 Live load application-Second day 18
Chapter 3
Table 3.1 Results of initial triangulation measurements 27
Table 3.2 Results of final triangulation measurements 28
Table 3.3 Initial tape measurement data 32
Table 3.4 Final tape measurement data 33
Table 3.5 Co-ordinates of position transducer wire at it's base 35
Table 3.6 Change of angle on position transducer wire during the experiment. .. 36
Chapter 4
Table 4.1 Computed axial thrust 70
Table 4.2 Computed bending moment 71
Table 4.3 Yield stress reached during failure tests 11()
Table 4.4 Location and length of creases detected 111
Chapter 5
Table 5.1 Basic information on triaxial tests 118
Table 5.2 Duncan's hyperbolic soil model parameters 120
Table 5.3 A summary of material parameters 121
Table 5.4 Load factor (K4) for various cover depths and loading conditions 124
viii
Chapter 2
Figure 2.1
Figure 2.2
Figure 2.3
Figure 2.4
Figure 2.5
Figure 2.6
Figure 2.7
Chapter 3
Figure 3.1
Figure 3.2
Figure 3.3
Figure 3.4
Figure 3.5
Figure 3.6
Figure 3.7
Figure 3.8
Figure 3.9
Figure 3.10
Figure 3.11
Figure 3.12
Figure 3.13
Figure 3.14
Figure 3.15
Figure 3.16
LIST OF FIGURES
Geometry of pipe arch culvert 8
Locations of test soil borings 10
Live load application system (view parallel to roadway) 13
Live load application system (view perpendicular to roadway) 14
Field picture of live load system 15
System used for cross-sectional shape and deflection
measurements 20
Typical installation of biaxial strain gages 22
Measurements for cross-sectional shape determination 25
Final cross-sectional shape at center location 29
Types of tape measurements taken 31
Deflection of monitoring point #1 during first load sequence ~37
Deflection of monitoring point #2 during first load sequence 38
Deflection of monitoring point #3 during first load sequence 39
Deflection of monitoring point #4 during first load sequence 40
Deflection of monitoring point #5 during first load sequence 41
Deflection of monitoring point #6 during first load sequence 42
Deflection of monitoring point #7 during first load sequence 43
Deflection of monitoring point #8 during first load sequence 44
Deflection of monitoring point #9 during first load sequence 45
Deflection of monitoring point #1 during second load sequence 46
Deflection of monitoring point #2 during second load sequence 47
Deflection of monitoring point #3 during second load sequence 48
Deflection of monitoring point #4 during second load sequence 49
ix
Figure 3.17
Figure 3.18
Figure 3.19
Figure 3.20
Figure 3.21
Figure 3.22
Figure 3.23
Figure 3.24
Figure 3.25
Figure 3.26
Figure 3.27
Figure 3.28
Figure 3.29
Figure 3.30
Chapter 4
Figure 4.1
Figure 4.2
Figure 4.3
Figure 4.4
Figure 4.5
Figure 4.6
Figure 4.7
Deflection of monitoring point #5 during second load sequence 50
Deflection of monitoring point #6 during second load sequence 51
Deflection of monitoring point #7 during second load sequence 52
Deflection of monitoring point #8 during second load sequence 53
Deflection of monitoring point #9 during second load sequence 54
Deflection of monitoring point #1 during third load sequence 55
Deflection of monitoring point #2 during third load sequence 56
Deflection of monitoring point #3 during third load sequence 57
Deflection of monitoring point #4 during third load sequence 58
Deflection of monitoring point #5 during third load sequence 59
Deflection of monitoring point #6 during third load sequence 60
Deflection of monitoring point #7 during third load sequence 61
Deflection of monitoring point #8 during third load sequence 62
Deflection of monitoring point #9 during third load sequence 63
Definition of distances c1 and c2 taken from neutral axis 69
Distributions of thrust and moment under load of 69.27 tons
during first loading sequence 72
Distributions of thrust and moment under load of 86.59 tons
during first loading sequence 73
Distributions of thrust and moment under load of 100.06 tons
during first loading seq uence 74
Distributions of thrust and moment under load of 107.76 tons
during first loading sequence 75
Distributions of thrust and moment under load of 115.45 tons
during first loading sequence 76
Distributions of thrust and moment under load of 123.15 tons
x
during first loading sequence 77
Figure 4.8 Distributions of thrust and moment under load of 30.79 tons
during second loading sequence 78
Figure 4.9 Distributions of thrust and moment under load of 38.48 tons
during second loading sequence 79
Figure 4.10 Distributions of thrust and moment under load of 50.03 tons
during second loading sequence 80
Figure 4.11 Distributions of thrust and moment under load of 65.43 tons
during second loading sequence 81
Figure 4.12 Distributions of thrust and moment under load of 78.89 tons
during second loading sequence 82
Figure 4.13 Distributions of thrust and moment under load of 88.51 tons
during second loading sequence 83
Figure 4.14 Distributions of thrust and moment under load of 101.6 tons
during second loading sequence 84
Figure 4.15 Distributions of thrust and moment under load of 103.91 tons
during second loading sequence 85
Figure 4.16 Distributions of thrust and moment under load of 111.6 tons
during second loading sequence 86
Figure 4.17 Distributions of thrust and moment under load of 113.9 tons
during second loading sequence 87
Figure 4.18 Distributions of thrust and moment under load of 50.03 tons
during third loading sequence 88
Figure 4.19 Distributions of thrust and moment under load of 57.73 tons
during third loading sequence 89
Figure 4.20 Distributions of thrust and moment under load of 80.81 tons
during third loading sequence 90
Figure 4.21 Distributions of thrust and moment under load of 100.1 tons
xi
during third loading sequence 91
Figure 4.22 Distributions of thrust and moment under load of 107.8 tons
during third loading sequence 92
Figure 4.23 Distributions of thrust and moment under load of 115.5 tons
during third loading sequence 93
Figure 4.24 Thrust vs load plots for second and third loading sequences
at point. #1 94
Figure 4.25 Moment vs load plots for second and third loading sequences
at point #1 95
Figure 4.26 Thrust vs load plots for second and third loading sequences
at section #4 96
Figure 4.27 Moment vs load plots for second and third loading sequences
at point #4 97
Figure 4.28 Thrust vs load plots for second and third loading sequences
at point #5 98
Figure 4.29 Moment vs load plots for second and third loading sequences
at point #5 99
Figure 4.30 Thrust vs load plots for second and third loading sequences
at point #6 100
Figure 4.31 Moment vs load plots for second and third loading sequences
at point #6 101
Figure 4.32 Thrust vs load plots for second and third loading sequences
at point #9 102
Figure 4.33 Moment vs load plots for second and third loading sequences
at point #9 103
Figure 4.34 Failure mode of bolted crown plates under load 106
Figure 4.35 Formation of plastic hinges 109
Figure 4.36 Measurements taken to locate creases 112
xii
Chapter 5
Figure 5.1
Figure 5.2
Figure 5.3
Figure 5.4
Node numbering system used for the half mesh 122
Various material zones defined for simulation #3 126
various material zones defined for simulation #5 127
Comparison of deflection of monitoring point #5 between
field results and various CANDE program simulations 129
Figure 5.5 Comparison of deflection of monitoring point #6 between
field results and various CANDE program simulations 130
Figure 5.6 Comparison of deflection of monitoring point #7 between
field results and various CANDE program simulations 131
Figure 5.7 Comparison of deflection of monitoring point #8 between
field results and various CANDE program simulations 132
Figure 5.8 Comparison of deflection of monitoring point #9 between
field results and various CANDE program simulations 133
Figure 5.9 Comparison of thrust due to 30.79 ton load between
field result and various CANDE simulations 134
Figure 5.10 Comparison of moment due to 30.79 ton load between
field result and various CANDE simulations 135
Figure 5.11 Comparison of thrust due to 38.48 ton load between
field result and various CANDE simulations 136
Figure 5.12 Comparison of moment due to 38.48 ton load between
field result and various CANDE simulations 137
Figure 5.13 Comparison of thrust due to 50.03 ton load between
field result and various CANDE simulations 138
Figure 5.14 Comparison of moment due to 50.03 ton load between
field result and various CANDE simulations 139
Figure 5.15 Comparison of thrust due to 65.43 ton load between
xiii
field result and various CANDE simulations 140
Figure 5.16 Comparison of moment due to 65.43 ton load between
field result and various CANDE simulations 141
XIV
CHAPTER 1
INTRODUCTION
1.1 GENERl\L S'lAl~El\1ENT
Corrugated metal buried conduits have been used as drainage structures for many
years and, especially in the past two decades as short-span bridge substitutes. The reasons
for this development are light weight, lower material cost, relatively easy handling and
installation procedures. These structures other than the very smallest, are constructed by
bolting together curved, corrugated metal plates. One of the most popular type of
corrugated metal pipes (CMPs) has been the corrugated steel pipe arch culvert. The pipe
arch culverts do not require concrete footings and are advantageous over some other CMPs
where head room is limited and hydraulic capacity is demanded.
In the last two decades, there have been many investigations dealing with the
analysis and design of corrugated steel culverts [2,5,7,8,17,18]. Laboratory testing, field
testing, and analytical methods have been utilized. Most of these reported studies are
related to the performance of culverts under various backfill and under normal live-load
conditions. However, very few investigations have been focused on the maximum load
carrying capacity and the failure mechanism of these soil-structure systems. This is because
a full-scale field failure test of a culvert is generally costly, time consuming, and presents
problems to the construction plan and/or local traffic conditions.
The strength of a culvert depends on properties of backfill material, plate and soil
structure interaction. There is limited Information on the amount of deflection, shape of
deformation and live-load capacity of these culverts before full or partial failure occurs. For
more rational design, it is very important to inquire into possible failure mechanisms.
1.2 OBJECTIVES
The objectives of the investigation were as follows:
a) To determine the maximum moment capacity of the pipe arch culvert.
b) To define the collapse mechanism.
c) To identify critical sections on the geometry of the pipe arch culvert.
d) To evaluate the load-deflection relation of the pipe arch culvert under
exceptionally large live loads.
e) To compare the measured ultimate moment capacity with AASHTO
design guidelines and with CANDE Finite Element Method
predictions.
1.3 ()UTLINE OF RESEARCII
In 1989, the Ohio Department of Transportation (ODOT) made a decision, after a
careful hydrologic and hydraulic evaluation, to remove a large span pipe arch culvert
structure identified as MER-707-1703, which had been existing under State Route 707,
near the north limit of the village of Mendon in Mercer county, Ohio. This pipe was
originally installed in 1953 as an overflow structure, for a nearby short span bridge
structure, MER-707-1697, over St. Mary's river. On September 24 and 26, 1990, a
research group from Ohio University took full advantage of this unique situation and
conducted one of the first comprehensive full-scale field failure testing of the pipe arch
culvert structure.
This thesis presents details of the findings of previous investigations on failure of
culverts, descriptions of the pipe arch culvert structure tested, field instrumentation
methods utilized, related background theory and design guidelines, experimental results,
CANDE Finite Element Analysis and the conclusions drawn.
Chapter two describes in detail the information regarding the geometry of the
2
corrugated steel pipe arch culvert structure and its surrounding subsurface conditions in the
field. This chapter also presents the concept and descriptions of the field instrumentation
and live-load application methods used to fulfill the objectives of the investigation.
Chapter three presents necessary background information utilized in the analysis of
the field data for deflection. It also provides the field measured data which were obtained
before, during"and after the testing. Field measurements of initial and fmal geometry of the
pipe arch culvert are presented.
Chapter four presents necessary theory utilized for analysis of strain gage data and
the results obtained. Bending moments and thrusts are computed and presented for the
corresponding loading conditions. Locations of plastic hinges and creases observed in the
field are also reported here.
Chapter five gives details about the laboratory testing of backfill material. It also
represents the calculated soil model parameters for the CANDE finite element analysis. It
explains the numerical analysis of the pipe arch culvert/soil system using the CANDE
computer program. Predictions of the CANDE program are presented, in terms of
deformations, thrusts, and moments, in correlation with the measured field values.
And, finally Chapter six presents the summary of the results and conclusions drawn
from this investigation.
1 .4 LITERA1'URE REVIEW
The corrugated steel culvert has been increasingly subjected to investigation during
the last two decades. Mayerhof and Baikie [16] as part of their study investigated the
strength of corrugated metal culverts under fills.
From this investigation they concluded that for small values of the co-efficient of
3
soil reaction or modulus of deformation of the soil, and for small values of the flexural
rigidity of the plates, the sheets would fail by buckling, but for larger values of these
parameters the sheets would fail by yielding of the section. The observed ultimate loads and
modes of failure of the sheets were in reasonable agreement with these estimates and also
support the ring compression theory.
Buckling of culvert structures was studied by Ghobrial and Abdel-Sayed [12]. In
their study of this phenomenon, they considered the formation of plastic hinges in the
culvert walls. They observed sudden snap-through failure for large spans and shallow
cover conditions. Short span culverts with deep soil cover did not exhibit this response but
experienced increasing displacements after each load step. In addition, the first plastic hinge
formed at the crown. The formation of the second plastic hinge was observed farther away
from the crown.
Duncan [8] after an extensive study suggested controlling the factor of safety
against formation of a plastic hinge as a design requirement for flexible culverts with
shallow fill, and has given three reasons why structural collapse will not occur at this point:
1) Multiple plastic hinges are required to form a collapse mechanism.
2) The soil will restrain deformations after formation of a mechanism.
3) The design estimates are based on minimum values of yield stress.
Selig and Musser [18] rated the performance of a rib reinforced, long-span culvert
by field tests and a limited finite element analysis. Results were compared with current
design practice. They concluded that rib stiffeners decrease deflections, increase moments,
and do not affect thrusts. Reinforcing ribs increase the factor of safety against plastic hinge
formation.
Cary [4] examined the inelastic flexural stability of corrugations. He investigated
the local stability of are-and-tangent corrugated profiles when subjected to moments in the
4
5
inelastic range. Twenty four flexural tests were used to obtain empirical expressions. The
expressions related design variables, corrugation dimensions, minimum curvature radius,
maximum moment capacity, and critical buckling strain. Results show that as the radius of
curvature to thickness ratio increases the strain at which buckling occurs reduces.
Seed and Rains r171 analyzed three full-scale field case studies involving failure of
flexible long span culvert structures due to inadvertent application of exceptional live loads.
Each case was simulated using nonlinear finite element analysis methods with a modified
Duncan and Drawsky procedure to develop equivalent line loads. Their numerical results
indicate that the nonlinear finite element analysis can provide excellent agreement with
observed field behavior, in terms of not only failure conditions but also locations of plastic
hinge formation.
Dessouki A.K. and Monforton G.R. [6] used a plane strain finite element analysis
procedure to determine the effect of soil failure on soil-steel structures. They used
hyperbolic soil model to represent the interface element and the soil elements far from the
structure. An elasto-plastic model represented the soil behavior in the severely stressed
regions. They reported good agreement between the model tests they conducted in the
laboratory and the analytical results. Their investigation clearly indicated the significant
effect on the load carrying capacity of the soil-steel structure due to soil failure.
In all of the above investigations, full-sized culverts were not instrumented and
loaded to failure to determine their actual ultimate moment capacity, load-deflection relation,
and influence of soil-structure interaction.
CHAPTER 2
PIPE ARCH CULVERT AND FIELD INSTRUMENTATION
2.1 GENERAL
The details of the history, general information and geometrical characteristics of the
culvert, results of the subsurface boring work performed close to the culvert, methods of
instrumentation, and live load application system for the pipe arch culvert tested for failure
are presented in this chapter.
In order to meet the objectives outlined in chapter one, it was necessary to develop a
system which could simulate exceptional vehicular live load to the culvert and to instrument
the pipe to obtain deflection, moment and thrust measurements before and during the full
scale field failure test. Two large-capacity hydraulic cylinders, connected in parallel, were
set over the culvert and extended against a dead load, consisting of more than forty 2.2 ton
concrete blocks placed on top of a steel I-beam frame, to achieve application of exceptional
live load. In oder to obtain deflection data, position transducers were attached to a reference
truss structure erected inside the culvert, and transducer's wires were connected to selected
points on the inside perimeter of the culvert. Movement of the reference truss structure was
monitored with the conventional level surveying technique to single out true deflections of
the pipe. Measurements of moment and thrust were made using electric strain gages. An
assumption was made that effects of exceptional live load would be significant mostly in a
cross section under the loading points (plain stress). Therefore, a mid-length plane section
along the longitudinal axis of the culvert was chosen to establish instrumentation and to
apply live load. A tape extensometer was used to establish the initial and final cross
sectional shapes of the selected mid-section of the culvert.
To perform realistic CANDE numerical simulation of the culvert, a knowledge of
the vertical profile of the surrounding subsurface conditions and the stress-strain relations
of backfill material is required. This information was obtained by performing subsurface
exploration work at two locations next to the culvert structure on the day of testing.
2 .2 DESCRIPTION OF PIPE ARCH CULVERT AND BACKFILL
l\1ATERIAL
The pipe arch culvert (MER-707-1703), the main subject of the investigation, was
installed in 1953, parallel to St. Marys River at an appropriate distance of 400 feet, under
state route 707, near the north limit of the village of mendon in Mercer County, Ohio. The
culvert, situated in a flood plain, was designed as an overflow structure for a nearby short
span bridge structure (MER-707-1697) and supposed to have a minimum safe load capacity
ofS-15.
The design span and rise dimensions for the culvert were 15 feet-8 inches and 9
feet-6 inches respectively. Figure 2.1 illustrates the geometry of the pipe arch culvert. The
contract document stated that a maximum of 1 inch tolerance was permitted on nominal
span and rise dimensions. The steel structural plates for the culvert had #7 gage thickness
for the top section and #5 gage thickness for the corner and bottom sections. Corrugation
pattern was defined by a pitch of 6 inches and a depth of 2 inches. Table 2.1 summarizes
the geometrical characteristics of the pipe arch culvert. Backfill material used during
construction was a typical cohesive earth material available locally. According to a record
dated 1955, the vertical profile surrounding the culvert included a 2 inch asphalt concrete
layer and 33.5 foot wide, 7.4 foot thick fill above the culvert crown. The culvert was
installed perpendicular to the centerline of the road, and it had a total length of 86 feet and a
grade of 0.0%. No stiffeners were attached to the culvert structure during its construction.
On September 24,1990 just before the first loading, a drilling rig equipped with a
rotary auger was utilized to obtain detailed subsurface soil data at two locations within the
shoulder section of the roadway one on each side, near the west end of the culvert.
7
<LI Elev. 814.70Ft.
8
I...
I
Roadway~mbankment
ConcreteHeadwall
Elev. 798.00 Ft.0.00%
86.0 Ft.
(a) GeneralSide View
S an 15Ft, - 8 In.
(b) General Cross-Sectional View
, ,
c~
~~\C)
..J ..:tt.. u,r-- 0'\
ve",
~
, , , , , , ,
Figure 2.1 Geometry of Pipe Arch Culvert
Table 2.1 Characteristics of Pipe Arch Culvert
Type Corrugated Steel
Design Span 15 feet - 8 inches
Design Rise 9 feet - 6 inches
Length 86 feet
Height of Cover Over Crown 7 feet - 5 inches
Corrugation Pitch 6 inches
Corrugation Depth 2 inches
Plate Thickness:Above Springline 0.188 inch (Galvanized)
Plate Thickness:0.218 inch (Galvanized)Below Springline
Section Area of Plate 2.739 in;1ft.
~ornentoflnertia 1.296 in~1ft.
Section Modulus 1.187 in~1ft.
Radius of Gyration 0.688 inch
9
10
Locations of the boreholes with respect to the culvert structure are shown in fig 2.2. These
borings were extended down to a depth of approximately 3 feet below the bottom invert of
the culvert. A 18 inch length split spoon sampler was used and the SPT values were
recorded. Soil samples were placed in seal-tight containers and transported to the Ohio
DOT soil laboratory for analysis. Tables 2.2 and 2.3 provide a summery of the data
obtained from the two test borings and results of the laboratory soil tests. The backfill
material encountered in the bore holes are regarded as a stiff to very stiff silty clay with
varying amounts of sand and gravel. In addition to the soil boring work, the thickness of
the asphalt concrete layer was measured after the first sequence of loading, and it was
determined to be 16 inches. It is apparent that the Ohio DOT bridge maintenance has placed
several layers of asphalt concrete, since the culvert has been developing a moderate amount
of sagging which results in a minor dip/cracking on the asphalt pavement surface.
2 .3 LI"E LOAD APPLICATION SYSTEM
In this investigation, it was necessary to apply exceptional live load, simulating the
rear axle of a heavy vehicle. The traditional concept of pressing against a large dead load,
often used in the pile load test procedure, was chosen to achieve this goal. Figures 2.3 and
2.4 illustrate the overall setting, .and figure 2.5 presents actual pictures of the loading
system taken in the field. First, two 4 feet by 8 feet pedestals, made up with concrete
blocks and guard rail posts, were set on the roadway surface at a 36 foot spacing from
center to center, across the culvert structure. A 6 to 8 inch thick well compacted sandy
material layer was placed under the pedestals to smooth out the roadway surface slopes and
to keep the pedestals vertical. A steel I-beam frame was constructed by welding eight 5
foot long 12 x 65 H piles at a 5 foot spacing between two 40 foot long W36 x 182 beams.
Web stiffeners 1/2 inch thick were attached to these I beams at the mid-span. This frame
was laid atop across the pedestals. Concrete blocks (or jersey barriers), each weighing
about 2.2 tons, were lifted by a crane and placed over the I-beams. On the first day of
testing (sept 24, 1990), a total of 45 jersey barriers were piled in three layers-20 in the first
layer, 15 in the second layer, and 10 in the third layer. On the second day of testing (Sept
11
N
4State Route 707-, CL•
c c 2 12 1 ....... 9 0 ................ ... .,.."'lllIlIlI o u
u uen CI')
I
#21
",*,
~ ~-~-- - - - - - - - - - - - - - -
18.5' Pipe ArchCulvert
~ ,- #1---- --. - - - ---- -."¥'
II
2 1 ....... ~~ .... 2 10 u
"'lllIlIlI ""0 ""0I.....:; :;
0 0.c .cen en
Figure 2.2 Locations of Test Soil Borings
Tab
le2.
2So
ilB
orin
gD
ata
For
Tes
tH
ole
#1
Ele
v.D
epth
SP
TM
ater
ial
Des
crip
tion
Phy
sica
lC
hara
cter
isti
csS
HT
LL
.LP.
I.W
.C.
(Ft.
)(F
t.)V
alue
Cla
ss%
Ag
g%
C.S
.%
F.S.
%Si
lt%
Cla
y
814.
20
.0-
Top
of
Ber
mS
houl
der
Sec
tion
--
--
--
--
--
-H1
2 .2
~:~=
11.7
-4/
8/8
Bro
wn
San
dyC
lay
07
1337
4331
1216
A-6
A
809.
25
.0- -
2/4/
5B
row
nA
ndG
ray
San
dyC
lay
126
1131
4033
1219
A-6
A-
806.
77.
5- -
3/5/
8B
row
nA
ndG
ray
San
dyC
lay
08
1436
4233
1418
A-6
A80
4.2
10
.0- -
4/5/
9B
row
nA
ndG
ray
San
dy
-G
rave
lly
Cla
y18
510
2740
3312
20A
-6A
801.
712
.5- -
4n
/12
Bro
wn
And
Gra
yS
andy
Cla
y8
511
3046
3413
19A
-6A
799.
21
5.0
- -5/
8/15
Gra
yS
ilty
Cla
y5
210
4934
4518
26A
-7-6
-79
6.7
17.5
_4/
9/13
Gra
yG
rave
lly
Cla
y17
37
3142
4616
27A
-7-5
795.
219
.0-
Bot
tom
of
Bor
ing
........
tv
Tab
le2.
3So
ilB
orin
gD
ata
For
Tes
tI-
Iole
#2
Ele
v.D
epth
SP
TM
ater
ial
Des
crip
tion
Phy
sica
lC
hara
cter
isti
csS
HT
LL
.LP.
I.W
.C.
(Ft.
)(F
t.)
Val
ueC
lass
%A
gg
%C
.S.
%F
.S.
%S
ilt
%C
lay
813.
80
.0-
Top
of
Ber
mS
houl
der
Sec
tion
--
--
--
--
-81
2.8
1.0
--
-81
1.3
2.5
_ -3/
4/5
Bro
wn
San
dyC
lay
86
1234
4031
1117
A-6
A
808.
85
.0- -
3/4/
5B
row
nA
nd
Gra
yS
andy
Cla
y9
612
3439
3111
18A
-6A
-80
6.3
7.5
_ -3/
6/9
Bro
wn
San
dyC
lay
75
1233
4333
1317
A-6
A8{
)3.8
10
.0- -
3/5n
Gra
yS
ilty
Cla
y-
44
1132
4938
1720
A-6
B80
1.3
12.5
_ -3/
6/9
Gra
yS
iltA
ndC
lay
0S
1235
4835
1521
A-6
A79
8.8
15
.0- -
5/1
Sn
.G
ray
Sil
tyG
rave
lly
San
d22
3113
1915
NP
NP
24A
-2-4
-79
6.3
17.5
_sn
»B
row
nA
nd
Gra
yS
ilty
Cla
y0
015
4240
2022
A-7
-643
794.
81
9.0
-B
otto
mo
fB
orin
g
~ (Jo,
)
14
40Ft
arriers
I-beam Frame
Backfill Soil
FIGURE 2.3 LIVE LOAD APPLICAnON SYSTEM(VIEWPA~ELL TO ROADWAY)
Hyd
raul
icC
ylin
ders A
spha
ltC
oncr
ete
Lay
er
Top
Cen
terl
ine
ofPi
peA
rch
Cul
vert
FIG
UR
E2.
4L
IVE
LO
AD
AP
PL
ICA
TIO
NS
YS
TE
M(V
IEW
PE
RP
EN
DIC
UL
AR
TO
RO
AD
WA
Y)
~ Ul
16
17
26, 1990), the number was increased to 53, placed in four layers. Under the web-stiffened
I-beam sections, two 14 inch bore, 24 inch stroke, 7 inch diameter piston rod hydraulic
cylinders were set 5 feet apart to simulate the rear axle load. Both cylinders had a capacity
of 230 tons, and they were connected to a hydraulic control unit for simultaneous
operation.
The testing was conducted in the field under two different subsurface conditions.
On the first day of testing ( Sept. 24, 1990), the hydraulic cylinders were placed on top of
the existing asphalt pavement layer, and pressure of up to 800 psi was developed in each
cylinder. On the second day of testing (Sept. 26, 1990), the asphalt material layer was
completely removed as well as some portion of the cohesive backfill material, so that there
would be only 3 feet of soil cover between the crown point and the bottom of the hydraulic
cylinders. Two cycles of monotonically increasing large live load was applied on the
second day, since the total stroke was almost used up during the first cycle. Tables 2.4 and
2.5 summarize the actual sequence of load application which took place on these two
testing days. Each load increment was maintained approximately 15 to 20 minutes before
the next load was applied, since the data acquisition system required that amount of time to
sweep through all the (forty two) strain gage channels, readout outputs from the nine
position transducers, and to print out hard copies of the data.
2.4 FIELD INSTRmlENTATION .OF PIPE ARCH CULVERT
Cross-sectional Shape Measurement
The initial and final shapes of the culvert's cross section at the center location are
determined by the technique called the "triangulation method". Details of the concept of this
method is provided in section 3.2. In this method, two ground reference points are
established at known locations inside the pipe, and distances are measured from these
reference points to each of the monitoring points installed on the inside culvert periphery.
The x, y coordinate values for each of the monitoring points are computed applying simple
TABLE 2.4 LIVE LOAD APPLICAnON - FIRST DAY(FIRST SEQUENCE OF LOADING)
Load Increment Total Live Load Applied (Tons)
1 JL 69.27 (= 450 psi in Each Cylinder)
2 86.59 (= 562.5 psi in Each Cylinder)
3 100.06 (= 650 psi in Each Cylinder)
4 107.76 (= 700 psi in Each Cylinder)
5 eo 115.45 (= 750 psi in Each Cylinder)c.....
6~
, 123.15 (= 800 psi in Each Cylinder)~
~7 c..-
107.76 (= 700 psi in Each Cylinder)0~o
8 c 123.15 (= 800 psi in Each Cylinder)~::s0-
9 ~ 123.15 (= 800 psi in Each Cylinder)en...VJ
10 '-- 123.15 (= 800 psi in Each Cylinder).....~
11 123.15 (= 800 psi in Each Cylinder)
12 123.15 (= 800 psi in Each Cylinder)
13 123.15 (= 800 psi in Each Cylinder)
14 123.15 (= 800 psi in Each Cylinder)
15,~ 123.15 (= 800 psi in Each Cylinder)
18
TABLE 2.5 LIVE LOAD APPLICATION - SECOND DAY(SECOND AND TIllRD SEQUENCES OF LOADING)
19
Load Increment Total Live Load Applied (Tons)
1
2
3
4
5
6
7
8
9
10
11
12
1
2
3
4
5
6
7
30.79 (= 200 psi in Each Cylinder)
38.48 (= 250 psi in Each Cylinder)
50.03 (= 325 psi in Each Cylinder)
65.43 (= 425 psi in Each Cylinder)
78.89 (= 512.5 psi in Each Cylinder)
88.51 (= 575 psi in Each Cylinder)
101.6 (= 660 psi in Each Cylinder)
103.91 (= 675 psi in Each Cylinder)
111.6 (= 725 psi in Each Cylinder)
101.6 (= 660 psi in Each Cylinder)
111.6 (= 725 psi in Each Cylinder)
113.9 (= 740 psi in Each Cylinder)
46.18 (= 300 psi in Each Cylinder)
57.73 (= 375 psi in Each Cylinder)
80.81 (= 525 psi in Each Cylinder)
100.06 (= 650 psi in Each Cylinder)
107.76 (= 700 psi in Each Cylinder)
115.46 (= 750 psi in Each Cylinder)
115.46 (= 750 psi in Each Cylinder)
20
principles of geometry. For the pipe arch culvert of concern, a total of nine monitoring
points were established by installing eyebolts directly onto the corrugated plates, within the
arc above the springline. The two ground reference points were established by installing
larger size eyebolts on the top surface of a concrete support constructed for the reference
truss structure (which was used to attach position transducers for deflection measurements
during the tests). The distances were then measured with an accuracy of plus or minus
0.005 inch, using a tape extensometer. Figure 2.6 presents a clear picture of the set-up. The
possible movements of the reference points were observed with the conventional level
surveying method. Independent of the above triangulation measurements, the Ohio DOT
engineers took detailed dimensions of the pipe arch, such as rise, span, top mid-ordinate,
top left and right chords and mid-ordinates, by stretching a cloth tape and/or a nylon string
at several sections along the longitudinal axis of the pipe,
Deflection Measurement
In this investigation, response of the culvert structure under the application of
exceptional live load was entirely unknown before the test. There was a need to develop a
deflection measurement system which would not require presence of any field personnel
inside the culvert and which could achieve a relatively rapid collection and storage of
deflection readings. After considering various options, it was decided to use constant
tension wire type position transducers. Nine units of the 10 inch range position transducers
manufactured were utilized along with the data acquisition system. A minimum of nine
units were required since the deflection measurement would have to be obtained for the
nine monitoring points used for the cross-sectional shape measurement. It was assumed
that deflection of the pipe due to the live load would be primarily in the direction normal to
the surface of the plate, confmed within the two dimensional cross-sectional plane.
These position transducers were attached to a reference truss structure erected at the
mid-length section inside the culvert. The transducer wires were then extended carefully
and hooked to each of the nine monitoring eyebolts installed on the pipe. Figure 2.6 shows
£IIII
il!IIII!!!!II!il!I!!!!!I!I!!!I!!I!'IIlI!I!I!lili!I!III!1!!!I!!!!li'I!IIII!!I!!i!111
A, B = Ground Reference Points
FIGURE 2.6 SYSTEM USED FOR CROSS-SECI10NAL SHAPE ANDDEFLECI10N MEASUREMENTS
21
22
the installation of the position transducers with respect to the culvert pipe geometry.
Biaxial Strain Measurement
The nine locations across the center section of the culvert, where both cross
sectional shape and deflection measurements were to be obtained, were also chosen to
measure biaxial strains. Two biaxial electrical strain gages were mounted on the inside
corrugated plate at each location, except for the crown, and the two shoulder locations
where the third strain gage was added. The first gage was installed at the peak of the inside
corrugation, and the second gage was installed, half a corrugation away from the first, in
the valley of the inside corrugation, as shown in Figure 2.7. Each strain gage was
positioned so that its two axes would be oriented parallel and perpendicular to the direction
of the plate corrugation and therefore strains could be read in the circumferential and the
longitudinal directions. Computations of moment and thrust values based on the strain
readings are explained in chapter four. A computer data acquisition system was loaded on
the back of the CGGR research vehicle and utilized in the field to obtain the strain gage
readings and the position transducer outputs during the loading steps.
Bac
kfil
lSoi
lM
ater
ial
~2
Inch
Fir
stSt
rain
Gag
eT
hird
Stra
inG
age
0)
I6
Inch
"-
Eye
bolt
Inst
alle
dat
Sec
ond
Stra
inM
onit
orin
gP
oint
Gag
e
FIG
UR
E2.
7T
YP
ICA
LIN
ST
AL
LA
TIO
NO
FB
IAX
IAL
STR
AIN
GA
GE
S
N W
CHAPTER 3
MEASUREMENT OF CULVERT DEFORMATION
3.1 OVERVIEW OF DEFORMATION MEASUREMENT
Culvert deformations were monitored after each increment of monotonically applied
live load. Deformation measurements were made by position transducers. A tape
extensometer was used to take readings to determine the shape of the culvert before and
after the test. This chapter explains the instruments used to collect the deformation data,
principles used for data reduction and the results obtained from the analysis. Movement of
the control hooks A and B were monitored by the ODOT personnel.
3.2 TAPE EXTENSOMETER MEASUREMENTS
The tape extensometer, used to determine the shape of the culvert, does not read out
the true length between two points. Instead, a calibration constant of 17.458 inches must be
applied to obtain the true length. The principle of this equipment and probable error in any
reading have been studied and well documented by Allan Rauch.(1990)
The tape extensometer measurements were taken between twocontrol hooks A, B
and the nine reference hooks distributed along the culvert periphery. Hooks A and B were
permanently installed into the four foot square concrete pedestal. It is reported that only
negligible movement occured in concrete pedestal. Therefore, throughout this chapter it is
assumed that there was no movement of control hooks.
DATA REDUCTION:
The readings ai and bi were taken from control hooks to all nine reference points as
shown in Fig.3.1. As shown in Fig.3.1, control hooks A and B were not on the same
plane as the nine reference hooks. Control hooks A and B were off by 1.5 inches and 2.25
A, B =Ground Reference Points
FIGURE 3.1 MEASUREMENTS FOR CROSS-SECTIONALSHAPE DETERMINATION
25
26
inches respectively. Therefore, the actual readings of the tape extensometer, after adding
the tape constant:
b. = J(b~ -2.25~ + 17.458I I
Eqn. (3.1)
Eqn. (3.2)
Coordinates of all nine reference points were calculated using the triangularization
method. By establishing the origin of a two dimensional x,y coordinate system at a point
where reference point A is projected onto the cross-sectional plane and applying simple
geometry principles, the x and y coordinate values for the monitoring point i can be
expressed as:
y. =Jtil: - x~I 1 I
Eqn. (3.3)
Eqn. (3.4)
It is assumed that there is no elevation difference between control hooks A and B.
Initial co-ordinates and final co-ordinates of all nine reference points were tabulated in
Tables 3.1 and 3.2, respectively. Initial and final shapes of the culvert 'are given in Fig 3.2.
Initial shape of the pipe is superpositioned over the final shape curve, with a magnification
factor of five applied to the vertical movements, to clearly indicate the overall deformation
pattern.
The establishment and the evaluation of the initial and the final cross-section of the
pipe arch was accomplished using two approaches. The first approach using tape
extensometer is more accurate than the second method. The second method, which
TABLE 3.1 RESULTS OF INITIAL TRIANGULATIONMEASUREMENTS
Monitoring x. v.Point 1 1
1 - 78.4764 7.283646
2 - 67.7104 32.82528
3 - 45.8207 56.49094
4 - 16.0193 70.90557
5 16.62255 74.56251
6 48.06325 69.91524
7 78.06078 55.16796
8 100.6137 31.77941
9 111.4759 6.716778
(Note) The Above Data Reflects The Cross-Sectional Condition OfThe Pipe Arch Culvert Before The Test On Sept 24, 1990.
27
TABLE 3.2 RESULTS OF FINAL TRIANGULATIONMEASUREMENTS
Monitoring x. Y. 8 X. 8 Y.Point 1 1 1 1
1 -78.4588 7.502599 0.011615 0.218953
2 - 67.9353 32.71373 -0.22499 -0.11156
3 - 46.2760 56.84925 -0.45531 0.358302
4 - 16.6364 70.05201 -0.61708 -0.85356
5 15.88784 67.24892 -0.73471 -7.31359
6 48.12747 66.56939 0.064227 -3.34586
7 78.61048 55.45415 0.549698 0.286184
8 100.8489 31.78826 0.235275 0.008845
9 111.5824 6.04567 0.106518 -0.67111
(Note) The Above Data Reflects The Cross-Sectional Condition OfThe Pipe Arch Culvert After The Test On Sept. 26, 1990.
28
200
180
160
,..-...140..c:u
.5'-' 120~~
~c.....-
100'"0~
00u 80I
~
60
40
20
0-80 -60 -40 -20
(NOlE) The final shape is plottedwith the vertical deflectionmagnified five times.
I:J Initial Shape
• Final Shape
o 20 40 60 80 100 120
X-Coordinate (inch)
29
FIGURE 3.2 FINAL CROSS-SECTIONAL SHAPE ATCENTER LOCATION
30
consisted of taking tape measurements of rise, span, skew span, chords and mid ordinates,
was applied through out almost the entire length of the pipe. Figure 3.3 presents the
different tape measurements taken by the Ohio DOT engineers and Tables 3.3 and 3.4
presents the various measurements recorded inside the pipe along its length before and after
the test respectively
Reduction in the rise was initially detected due to sagging of the pipe arch in the
middle. Measurements in the rise varied from 4.74% to 10.0%, with the maximum
reduction was observed at the center. Span is increased by 1.15% near the west end to
2.94% at the center location. No significant leaning of the pipe to one side was detected.
Final tape measurements taken after the experiment indicate that there was very
small outward movement at the monitoring points one and nine, agreeing well with the
position transducer measurements. Both the rise and the top center mid-ordinate
dimensions experienced more than 10% reduction from their initial values, while the top
left and right mid-ordinates increased by 16% to 17% and the top left and right chords
decreased by about 4%.
3.3 POSITION TRANSDUCER MEASUREMENTS
Position transducers were utilized to measure the deformation because of their
simple and remote ability to obtain highly accurate measurement. Since taking readings
with the tape extensometer is a time consuming process and requires persons to be inside
the culvert it was done only before and after the testing to find out the shape of the culvert. '
An excitation voltage was applied to the position transducer and the resulting
electrical outputs were set proportional to the linear position of the extension of a stainless
steel cable. Measurements were made by attaching the cable clip to a moving element and
mounting the position transducer to a fixed surface. Extension of the cable rotates the shaft
___________________ L _
IIIIII
31
Sleft. (SL)
Span (S)
Sright (SR)
FIGURE 3.3 TYPES OF TAPE ?v1EASURE?v1ENTSTAKEN
TA
BL
E3.
3IN
ITIA
LT
AP
EM
EA
SU
RE
ME
NT
DA
TA
Dis
tanc
eF
rom
Var
ious
Dim
ensi
ons
Tak
en(i
nn
.)
Sta
tion
Wes
tPi
peE
nd(f
1.)
SSL
SRR
TC
MO
TL
MO
TR
MO
TL
CT
RC
124
.015
.85
7.90
7.95
9.05
6.86
2.14
2.00
10.4
010
.42
232
.015
.98
NT
NT
8.77
6.69
2.02
2.01
10.3
810
.38
340
.016
.13
NT
NT
8.55
6.60
2.13
2.05
10.3
610
.39
W N
TA
BL
E3.
4FI
NA
LT
APE
ME
AS
UR
EM
EN
TD
AT
A
Dis
tanc
eF
rom
Var
ious
Dim
ensi
ons
Tak
en(i
nft.
)
Stat
ion
Wes
tPi
peE
nd(f
1.)
SSL
SRR
TC
MO
TL
MO
TR
MO
TL
CT
RC
124
.015
.85
7.90
7.95
9.05
6.84
2.17
1.97
10.4
410
.43
232
.015
.98
NT
NT
8.81
6.69
2.16
2.02
10.3
710
.38
340
.016
.13
NT
NT
7.81
5.90
2.50
2.39
9.90
9.99
448
.016
.06
NT
NT
8.49
6.54
2.23
2.11
10.3
510
.28
556
.016
.08
NT
NT
8.66
6.65
2.09
2.08
10.4
110
.32
w w
34
of the internal electromechanisms.
A constant-tension spring maintains the tension on the cable during extension from
the base and provides torque for rewinding the cable during retraction. The cable may
accelarate in retraction until the terminal velocity is reached.
The model used had a ran~e of zero to ten inches. During the test, a total of nine
position transducers were used. These transducers were calibrated in the laboratory.
Instrumentation of these transducers were explained in Chapter 2. Data was collected
using the HP3497A data aquisition system.
In order to calculate the deflection of the reference points the coordinates of the base
of the wire needed to be determined. These coordinates are tabulated in Table 3.5. During
the course of the experiment, the angle of the position transducer wire from the horizontal
changed considerably for the reference points #4, #5, and #6. The change in the angle of all
nine reference points are tabulated in Table 3.6.
During the analysis of transducer data, a decision was made to distribute the change
in angle proportional to the change in the lenth of the wire during the application of the live
load. At each step of loading, readings were taken from all nine units. For each step of the
loading, the deflection was presented in both the x and the y direction. These deflections
are presented in Figs. 3.4 through 3.12 for the first cycle of loading, Figs. 3.13 through
3.21 for the second cycle of loading and Figs.3.22 through 3.30 for the third cycle of
loading.
3.4 DISCUSSION
Section one which was located at the west springline, had hardly moved during the
TABLE: 3.5 Co-ordinates of position transducerwire at its base
Pas it i on transducerX y
no j j
1 -74.78 2.00
2 -58.04 29.03
3 -36.06 48.56
4 -7.02 58.57
5 16.46 63.25
6 42.64 62.22
7 71.85 49.57
8 94.87 29.39
9 93.33 0.97
35
TABLE: 3.6 Change of angle on position transducer wireduring the experiment
Position transducer Angle on wireno. a
~a
Initial Final
1 55.02 56.24 1.22
2 21.43 20.42 -1.01
3 39.1 39.06 -0.04
4 54.11 50.3 -3.81
5 89.18 81.86 -7.32
6 54.83 38.53 -16.3
7 42.03 41.04 -0.99
8 22.59 21.86 -0.73
9 17.57 15.54 -2.03
36
37
-0- Horizontal Component~ Vertical Component
80 100 120 140604020
0.04
0.03
0.00 1--..--io--.--.......-...---1---.--+-.....--1-.--.----+-----..-1
o
....~
Total Load Applied (ton)
FIGURE 3.4 DEFLECTION OF MONITORING POINT#!(SPRINGLINE) DURING FIRST LOADSEQUENCE
38
0.08
--[J- Horizontal Component
--d- l iVertical Component
0.06~
.cC.J
=.-"-'"CQ
0.04........C.Jcu
CaJ
Q
0.02
80 100 120 '1406040200.00 n-r=~:"'+--..-~--.-~-.--4--r---t---r---+----,.---1
o
Total Load Applied (ton)
FIGURE 3.5 DEFLECTION OF MONITORING POINT #2DURING FIRST LOAD SEQUENCE
39
80 100 120 140604020o.00 ~P--i---..--+---.----I--r---i--......---i---.----+----,r----I
o
0.08
--rr- Horizontal Component1 i I
----0- Vertical Component
0.06...-.....cCJ
=.-~c
0.040--......CJQJ-c..QJ
Q
0.02
Total Load Applied (ton)
FIGURE 3.6 DEFLECTION OF MONITORING POINT#3(SHOULDER) DURING FIRST LOADSEQUENCE
40
0.02
--0-- Horizontal Componenti E t i--0-- Vertical Component
20 40 60 80 100 120 140
Total Load Applied (tons)
-0.08 ~-...--+---.----+--.....-+---.--...-i---.---t---.,~+--..,.--f
o
:2 0.00~
c
c -0.02e-...C.JaJ--c.-
O -0.04
FIGURE 3.7 DEFLECTION OF MONITORING POINT #4DURING THE FIRST LOAD SEQUENCE
0.1
0.0
,..-......c(j -0.1c...
'-'"
c0... -0.2~
C.J~...-..~
Q-0.3
Horizontal Component
-b- f ! E
Vertical Component-0.4
41
-0.5o 20 40 60 80 100 120 140
Total Load Applied (ton)
FIGURE 3.8 DEFLECTION OF MONITORING POINT #5(CROWN) DURING FIRST LOADSEQUENCE
42
0.1
~ Horizontal Component~, I ,
~ Vertical Component
~ 0.0.cC.J
=.-"-'"
=0........C.J~
c:~ -0.1Q
80 100 120 140604020-0.2 -J--......,--4--.----+_r---1---r--+-.....,.---+-----wr---+--......---t
o
Total Load Applied (ton)
FIGURE 3.9 DEFLECTION OF MONITORING POINT #6DURING FIRST LOAD SEQUENCE
43
80 100 120 140604020
--a- Horizontal Component []-t'""-'-~
} V-J- JVertical Component
If
JI
A.
~/..
a
0.06
0.05
0.00
-0.01o
~ 0.04.cC.Jc....~
c 0.030.......-C.JQJ 0.02-c..QJ
Q
0.01
Total Load Applied (ton)
FIGURE 3.10 DEFLECTION OF MONITORING POINT #7(SHOULDER) DURING FIRST LOADSEQUENCE
44
0.10
80 100 120 1406040
Venical Component
20
----u- Horizontal Component
0.08
o.00 ~;;""---+--......---+-..--+-....---+---.----+-...---+----.----I
o
§ 0.06
0.02 -I----4--~---I--~__t_-_;:if__-_t_-__t
.....C.JQJ-c.-~
Q 0.04 -+---'-"---+--~.......--....f------+-.....--+-t-'--'+---"""""--1
Total Load Applied (ton)
FIGURE 3.11 DEFLECTION OF MONITORING POINT #8DURING FIRST LOAD SEQUENCE
45
0.04
:2 0.03(j
c
80 100 120 1406040200.00 ~~-i---......--+--.....----+-.--..;-........----i--"'--+----"-1
o
0.01
Horizontal Component
-0-, I I I
Vertical Component
ce.-~ 0.02 -I---4--~---I--+---r---t----t-----I...e.-QJ
Q
Total Load Applied (ton)
FIGURE 3.12 DEFLECTION OF MONITORING POINT #9(SPRINGLINE) DURING FIRST LOADSEQUENCE
46
0.00
0.04
Horizontal Component
~ I I0.03 Vertical Component
~
.cCJc...
"-'"
= 0.020....-~
~-..~ 0.01Q
12020 40 60 80 100Total Load Applied (ton)
-0.01 -+----w----+--w----+----.--.f.--.....,---+----..,,..---.-t----r----I
o
FIGURE 3.13 DEFLECTION OF MONITORING POINT #1(SPRINGLINE) DURING SECONDLOAD SEQUENCE
47
0.30 -r-------.~-__..,._--~--_r__-___r--__,
Horizontal Component0.25 """"--""""--0-1 E r -...--...--~........---...-~
Vertical Componentt
~
.c~ 0.20 +--~f-------+----+-----t---~---v.........
12010080604020
0.05 -t------l~---+---+---+__~___+-_f___t
0.00 n-......-......--I~,...=O:~~...---+--.----I-..,.-~o
Total Load Applied (ton)
FIGURE 3.14 DEFLECTION OF MONITORING POINT #2DURING SECOND LOAD SEQUENCE
0.4
~ Horizontal Componentt s s~ Vertical Component
~
.c~ 0.3.-"-'"
48
ce.-~
C.JQJc 0.2 ......................-.......~.......-...-..._-+-..-...-.... ...............+---............--+--~~r----tQJQ
20 40 60 80 100
Total Load Applied (ton)
FIGURE 3.15 DEFLECTION OF MONITORING POINT #3(SHOULDER) DURING SECOND LOADSEQUENCE
0.1
-0--, Horizontal Component--0- ~ Vertical Component'
49
~
.c 0.0C.JC--'-'"
c0--..C.JQJ -0.1--c...QJ
Q
-0.2-f...--~;----+----t---+----+---t---t
20 40 60 80 100
Total Load Applied (ton)
FIGURE 3.16 DEFLECTION OF MONITORING POINT #4DURING SECOND LOAD SEQUENCE
50
-2 -+--~i------"----+-----t----+---t--1
--0- Horizontal ComponentE ~ I
-0- Vertical Component
Ie
12020 40 60 80 100Total Load Applied (ton)
-4 -+---...-~------.----i---.--f----.-_p--.....----t--...----t
o
FIGURE 3.17 DEFLECTION OF MONITORING POINT #5(CROWN) DURING SECOND LOADSEQUENCE
0.2
0.0
.-~
-0.2ce.-.....CjaJ
c:: -0.4aJ
Q
-0.6
-0.8
~ Horizontal ComponentE i I
Vertical Component ~
51
20 40 60 80 100
Total Load Applied (ton)
FIGURE 3.18 DEFLECTION OF MONITORING POINT #6DURING SECOND LOAD SEQUENCE
52
12020 40 60 80 100
Total Load Applied (ton)
-0- Horizontal Component 0
--10-- l ( ,Vertical Component
~
p
;I~
- - - - -c----e,;~ -0.0
0.4
-0.1o
0.3~
.cCJc--"-'"
c 0.2Q--...C.JQJ-~QJ
Q 0.1
FIGURE 3.19 DEFLECTION OF MONITORING POINT #7(SHOULDER) DURING SECONDLOAD SEQUENCE
53
0.30......----,.----r---r----r--..,.-----,
0.25~
.::c.Jc~ 0.20
-0- Horizontal Component
--0-- Vertical Component
12020 40 60 80 100Total Load Applied (ton)
0.00 n-...........IIiiiiiif::J=a:~~~-=-..-I--..,..--+----..--Io
0.10
0.05 +--~'-""---i----+-----l~---t-u_-_t
ce--....~ 0.15 *-----l~---i----+---+__---t-,.,..-__t....
r..Q.)
Q
FIGURE 3.20 DEFLECTION OF MONITORING POINT #8DURING SECOND LOAD SEQUENCE
54
0.08....------..----r----,..----r---.,.-----,
-6o.06 ~Io'----o-
Horizontal Component~........-...----t-"""""""'-tc ~
Vertical Component
12020 40 60 80 100
Total Load Applied (ton)
-0.02 -+---.-----+-......-.....;-.----.--+----.---+--...-----+---.-----t
o
FIGURE 3.21 DEFLECTION OF MONITORING POINT #9(SPRINGLINE) DURING SECONDLOAD .SEQUENCE
Horizontal Component~ I
Vertical Component
0.04
0.03
..."-""
ce:: 0.02
C.JQJ-c.....QJ
Q
0.01
0.00o 20 40 60 80 100 120
55
Total Load Applied (ton)
FIGURE 3.22 DEFLECTION OF MONITORING POINT #1(SPRINGLINE) DURING THIRD LOADSEQUENCE
~ Horizontal Componentt
~ Vertical Component~
.>
~V V
~~
------[r--
- ~~-.-£'"
\r- «r:
0.30
0.25
~
.cCj 0.20c...
'-"
CQ.- 0.15.....CjQJ~c...QJ
Q0.10
0.05
0.00o 20 40 60 80 100 120
56
Total Load Applied (ton)
FIGURE 3.23 DEFLECTION OF MONITORING POINT #2DURING THIRD LOAD SEQUENCE
0.50
--0- Horizontal Component
----b- Vertical Component _'"-_--+__-10.45~"- c
.~
.cC.J.: 0.40 -J------1~-_+---+---+__-__t_...,.t___."'-"
=e.-~
~ 0.35-'-QJ
Q
0.30
20 40 60 80 100
Total Load Applied (ton)
FIGURE 3.24 DEFLECTION OF MONITORING POINT #3(SHOULDER) DURING THIRD LOADSEOUENCE
57
58
0.0
:c -0.1 .J--~~~-+--~-t---+-----t----t~
C--...........
ce--.....(j
~ -0.2c~
Q--o-c
Horizontal Component
Vertical Component I
-0.4o 20 40 60 80 100 120
Total Load Applied (ton)
FIGURE 3.25 DEFLECTION OF MONITORING POINT #4 .DURING THIRD LOAD SEQUENCE
o
-1,-......cy
=.- -2'-'"
=0.-....~
QJ -3---~Q-4
-5
[5 o-e--c .... 1""'" L~
'------~- ------.
~I\
\~ Horizontal Component--!..o- ~ t bVertical Component
59
-6o 20 40 60 80 100 120
Total Load Applied (ton)
FIGURE 3.26 DEFLECTION OF MONITORING POINT #5(CROWN) DURING THIRD LOADSEQUENCE
60
-0.6
-0.8~
.cCJc.-~
c -1.00.-~
CJaJ...~
aJQ
-1.2Horizontal ComponentE ~
Vertical Component
-1.4
20 40 60 80 100
Total Load Applied (ton)
FIGURE 3.27 DEFLECTION OF MONITORING POINT #6DURING THIRD LOAD SEQUENCE
0.5 .....---....--~--,...----,---..,..-----,
-0- Horizontal Component--b- Vertical Component
,..-.....cC.Jc~ 0.4
ce
61
20 40 60 80 100
Total Load Applied (ton)
FIGURE 3.28 DEFLECTION OF MONITORING POINT #7(SHOULDER) DURING THIRD LOADSEQUENCE
62
0.30
0.20~
.cCJc.-'-'"
0.15cQ.-...CJ~- 0.10c..~
Q
0.05
Horizontal Component
Vertical Component
0.00o 20 40 60 80 100 120
Total Load Applied (ton)
FIGURE 3.29 DEFLECTION OF MONITORING POINT#8DURING THIRD LOAD SEQUENCE
63
0.07
Horizontal Component~
5 5
0.06 Vertical Component
,--.....c 0.05(.J
c.-~c 0.04Q.-......(.JQJ-c:..... 0.03QJ
Q
0.02
0.01-I------+---i--~,::;;...-__+_--_t__-__t
12010080604020
0.00 -+----..-........-....--+---..-P--....---+-~....__+___.,._____I
o
Total Load Applied (ton)
FIGURE 3.30 DEFLECTION OF MONITORING POINT #9(SPRINGLINE) DURING THIRD LOADSEQUENCE
64
test, with the total maximum vertical movement being O.037(i inches. The first two loading
steps of the second loading cycle resulted in an inward movement. Afterwards, that it
always moved outward.
Section two constantly moved outward. The magnitute of the movement was
similar during the second and third cycles. The maximum vertical movement at this section
was 0.084 inches.
Section three which was located at the west shoulder also constantly moved
outward. There was a slight variation in movement between the second and the third
loading. Careful consideration of the data revealed a permanent deformation of 0.05 inches
during the second cycle at this section.
Section four, located close to the crown, continuously moved inward. There was a
considerable difference in total vertical deflection during the second and third cycles under
the same load of 115 tons. The reason for this is that the stress level in this region
exceeded the yield limit of the corrugated steel material during the second cycle of loading.
Maximum vertical deflections at, this section for the second and third loading cycle were
0.2282 inches and 0.5977 inches respectively.
Section five, located at the crown, experienced the maximum vertical deflection.
This is understandable since the load application point was over this section. The maximum
vertical deflections at the crown for the second and third cycles of loading were 3.435 and
6.989 inches respectively.
In section six, during the first step of second cycle loading, the hook moved
upward, and afterwards it always moved downwards. The maximum deflections were
0.9487 inches and 1.8047 inches for the second and third cycles respectively. A maximum
horizontal deflection of 2.4752 inches occured at this section during the third loading cycle.
65
The magnitude of the deflection did not coincide with that of section four.
Sections 7, 8, and 9 behaved in a similar manner to sections 3, 2, and 1,
respectively. The maximum vertical deflection was 0.3625 inches at section 7,0.1082
inches at section eight and 0.197 inches at section nine. All the maximum deflections
occured during the third sequence of loading.
The positive x axis for #1 through #5 was towards west and for points #6 through
#9 towards east. The positive y axis was always upwards. Deflection of all nine points
started from the non-zero value for the third sequence of loading. Total maximum vertical
deflection of 6.989 inches was recorded at the crown point. when the total load reached
approximately 100 tons, rapid increase in the rate of deflection was monitored. The points
at the crown moved downwards and the points at the haunch and springline moved
outwards.
CHAPTER 4
MEASUREMENT OF PLATE FORCES
4.1 INTRODUCTION
This chapter presents the bending moment and axial thrust obtained from the field
testing. In order to detennine the axial force and bending moment due to monotonically
applied live load, biaxial gages were installed at nine sections along the periphery of the
culvert plate as described in Chapter 2. The bonded-foil electrical resistance strain gages
were read using a computerized data acquisition system. Biaxial plane stress assumptions
were used to compute circumferential stresses in the culvert plate. The data from the strain
gages were reduced to moment and thrust as described in this chapter. The strain gages and
the data acquisition system have been described in detail by Alan Rauch.(1990)
4.2 REDUCTION OF STRAINS TO AXIAL THRUST AND BENDING
MOMENTS
The data acquisition system reads the two voltages, Vin and Vout, and returns the
ratio, Vout / Vin. The computer program,"RATIO"stores this data in the diskettes for
future analysis. Computer program "NEW" is used to calculate the strains from the stored
ratios. Strains were computed using first set of readings, the readings taken before the load
was applied, as an initial value.
As discussed earlier we had at least two biaxial gages at each section, one at the peak
and the other at the crust. Assuming plane strain theory, we can calculate the circumferential
stresses as follows:
67
E =Young's modulus 30x106 psi
i} = Poisson's ratio 0.3
cc= circumferential strain
tl= longitudinal strain
Eqn. 4.1
Stresses were assumed to be due to bending moment and axial forces.
Superposition of these results gives the expression shown in Eqn. 4.2
p + MeCfe =A I
P =axial thrust
A = area of cross section
M =bending moment
I = moment of inertia
C = distance from the neutral axis
Eqn.4.2
At each monitoring location, two circumferential stress values were obtained,
one from the biaxial strain gage installed at the peak and the other is from the gage placed
in the valley of the corrugation. From Eqn. 4.2, moment and thrust can be obtained by
simple calculation. The equations obtained for moment and thrust are given in Eqns. 4.3
and 4.4 respectively.
68
Eqn.4.3
C1 =distance from neutral axis to interested
point in tension zone (1.094 inches)
C2 =distance from neutral axis to interested
point in compression zone (0.906 inches)
Eqn.4.4
Figure. 4.1 presents the calculation details of Cl and C2. Calculated thrust and
moment are presented in Tables 4.1 and 4.2. Figures. 4.2 through 4.7 presents moment
and thrust graphically for the first sequence of loading. Figures 4.8 through 4.17 presents
moment and thrust for the second sequence of loading and the Figures 4.18 through 4.23
presents the moment and thrust for the third sequence of loading. Figures 4.24 through
4.33 presents how the culvert responded at selected sections for the applied live load for the
last two cycles of loading.. A consistent sign convention is employed throughout this
study. Positive bending moments imply a concave-up bending in the crown region and for
thrusts tensile forces are positive.
4.3 ANALYSIS OF RESULTS
Initial stages of the loading resulted in the negative moment at sections #land #9 at
the spring line indicating the outward movement of the culvert at those locations. During
the second cycle of loading after load step 6 moment at these locations were changed to
d
t
Strain Gageon Peak
Neutral- -- Axis
69
FIGURE 4.1 DEFINITION OF DISTANCES ci AND C2 TAKENFROM NEUTRAL AXIS
rrA
BL
E4.
1C
OM
PUT
ED
AX
IAL
TI-
lRU
ST
Loa
dL
oad
To
tal
Thr
ust
(kip
s/ft
)@
Mon
itor
ing
Poi
nt:
Cyc
leSt
epL
oad
No.
No.
(to
n)
Ifl
#211
3#4
#5#6
#7#8
#9....
...~
.
00.
000
O.C~OO
0.00
00.
000
0.00
00.
000
0.00
00.
000
0.00
00.
000
13
0.8
0.(
J.~·\()6
-0.6
67-1
.:\29
-1.3
600.
468
-1.1
29-1
.558
-0.9
00-0
.141
238
.48
-0./1
590.
818
-1.R
48-1
.913
-0.8
26-1
.660
-2.3
12-1
.374
1.17
13
50.0
3..O
.t)74
-1.6
03-2
.H64
-3.0
76-1
.324
-2.5
97-3
.245
-2.2
210.
876
465
.43
-().
X')
9-2
.307
-3.H
56-4
.286
-2.2
92-3
.885
-5.4
30-3
.421
0.42
72
578
.89
-1.(
)()7
-2.9
54-4
.Y72
-5.6
75-2
.947
-4.8
14-6
.256
-4.3
450.
271
688
.51
-1.7
35-3
.632
-6.3
05-7
.849
-5.1
57-6
.508
-8.1
51-5
.596
-0.0
177
101.
6-1
.337
-4.6
22-7
.X63
-11.
11-5
.226
-9.1
03-1
0.16
-4.6
22-0
.245
810
3.9
-1.3
2Y-5
.967
-X.6
45-1
0.82
-3.7
14-9
.984
-9.3
80-5
.967
-0.2
929
111.
6-
J..l
()4
-6.9
00
-q.7
15N
C-1
.706
-8.8
14-8
.121
-6.9
000.
197
1010
2.0
-I"~10
-7.2
30-9
.357
NC
-0.6
00-7
.150
-6.9
73-7
.230
0.05
911
111.
6-
--
--
--
--
1211
3.9
-0.9
9I
-9.9
77-1
0.55
NC
11.2
93.
844
-6.8
18-9
.977
0.16
8
00.
000.
000
0.00
00.
000
0.00
00.
000
0.00
00.
000
0.00
00.
000
150
.03
-0.6
30-1
.687
-2.5
74-2
.540
0.74
6-1
.318
-3.3
00-6
.743
-0.4
242
57.7
3-1
.2)
6-3
.404
-4.9
56-4
.634
1.88
5-1
.948
-6.6
90-8
.288
-0.8
29
33
80.8
1-1
.573
-4.4
76-6
.657
-5.9
092.
998
-2.1
41-9
.129
-10.
04-0
.979
410
0.1
-2.1
47-6
.102
-9.1
51-6
.214
5.10
8-0
.982
-11.
46-1
2.20
-1.3
475
107.
8-2
.359
-6.4
83-9
.861
-2.1
047.
552
0.67
4-1
1.70
-12.
86-1
.580
611
5.5
-2.2
93-5
.951
-10.
6612
.57
14.1
57.
881
-10.
44-1
3.40
-1.5
67
(Not
e)"N
ett=
No
tC
ompu
ted
Sin
ceth
eY
ield
Str
ess
was
Rea
ched
.~ o
TA
BL
E4
.2C
OM
PU
TE
DB
EN
DIN
GM
OM
EN
T
Loa
dL
oad
Tot
alM
omen
t (ki
ps-f
t/ft
)@
Mon
itor
ing
Poi
nt:
Cyc
leSt
epL
oad
IN
o.N
o.(t
on)
#1#
2#3
#4#5
#6#7
#8,#
9
00.
000
0.00
00.
000
0.00
00.
000
0.00
00.
000
i 0.0
000.
000
0.00
01
30.8
0-0
.015
-0.0
04-0
.048
-0.0
810.
195
-0.0
36%
-0.0
51-0
.014
-0.0
222
38.4
8-0
.022
-0.0
69-0
.079
-0.1
240.
291
·0.0
50I -
0.08
1-0
.015
-0.0
803
50.0
3-0
.028
0.01
4-0
.142
-0.2
250.
519
-0.0
81i -
0.15
0.-0
.013
-0.0
794
65.4
3-0
.030
0.03
2-0
.255
-0.3
610.
842
-0.0
92I
-0,.2
86-0
.010
-0.0
712
578
.89
-0.0
250.
052
-0.3
90-0
.489
1.20
0-0
.073
-0.4
51-0
.009
-0.0
596
88.5
1-0
.012
0.08
2-0
.582
-0.7
401.
494
.-0
.198
-0.7
000.
003
-0.0
297
101.
6O
.()17
0.16
0--0
.808
-1.3
751.
416
-0.8
71-1
.101
0.16
00.
031
810
3.9
O.O
(,30.
249
-1.0
55-2
.113
1.30
2-1
.469
-1.4
170.
249
0.09
09
111.
6O
.O()6
0.30
9-1
.238
NC
1.18
9-1
.782
-1.5
650.
309
0.13
010
102.
00.
126
0.34
6-1
.353
NC
1.09
4-1
.879
-1.6
330.
346
0.15
911
111.
6-
--
--
--
--
1211
3.9
0.31
30.
636
-2.1
57N
C-0
.226
-2.1
54-1
.559
0.63
60.
344
00.
000.
000
0.00
00.
000
0.00
00.
000
0.00
0.
0.00
00.
000
0.00
01
50.0
3-0
.012
0.01
8-0
.147
-0.4
000.
719
-0.1
14-0
.252
-0.2
02-0
.006
257
.73
-0.0
160.
032
-0.3
43-0
.759
1.41
7-0
.079
-0.6
03-0
.180
-0.0
073
380
.81
-0.0
150.
043
-0.5
18-1
.021
.1.
952
-0.0
32·
..0.9
15-0
.200
0.00
2·
410
0.1
0.00
10.
061
-0.8
47-1
.501
2.54
50.
094
-1.2
35-0
.204
0.02
25
107.
80.
013
0.08
1-0
.979
-1.6
712.
313
0.08
1-1
.261
-0.1
960.
032
611
5.5
0.03
40.
125
-1.1
40-2
.056
1.48
3-0
.130
-1.2
04-0
.199
0.05
7
(Not
e)"N
C"=
Not
Com
pute
dSi
nce
the
Yie
ldSt
ress
was
Rea
ched
....
...]~
Moment
Thrust8' -0.5--......
tf.)
c.~ -1.0 ................~~......."....,,~ ............'-""
-2.5
-3.0o 50 100 150 200 250 300
Unfolded Length (inch)
0.2 -.----.....---..,.----..,.-----r-~-____,
~
~e.--......~e.-~ 0.1 -..--~--i---I-~--+-_t-___.c..-~'-""
=0.0CJ
EQ
::; -0.1 +--~~~~-~......--..~-............
-0.2 -+-r-~~..,-,.-.,....;-,..................._+_,.....................~r__r_i_..,....,._...._r_I
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.2 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 69.27 TONS DURING FIRSTLOADING SEQUENCE
72
73
0.0
Thrust~-0.5c=""""""r.n
~-1.0""-""
~ -1.5·#1l.eE- _2.0 -J--~---t--I---+w\r--+---i'------t
-2.5
-3.0o 50 100 150 200 250 300
Unfolded Length (inch)
50 100 150 200 250 300Unfolded Length (inch)
-0.20 ....................-+-.-......................-.--.-..--+-.......................-.--.~.................
o
cO.05QJ
E~0.10
-0.15 -+---+r--J~~---+-_~~~_---I
0.10~c=~O.05e.-•r.n.e.O.OO~""-""
FIGURE 4.3 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 86.59 TONS DURING FIRSTLOADING SEQUENCE
74
-1Thrust
r:I
#9~
~
~
-2-.......rI'JC..-~""-'"
~
-3rI'J
=~.cE--
-4
-5o 50 100 150 200 250 300
Unfolded Length (inch)
0.2~c=~ 0.1c...
I
.~ 0.0-~1~~~~~~~~~~~""-'"
=-0.1QJ
§ -0.2-I--~--I-_~w--3~-+---+_~~
-0.3
-0.4o 50 100 150 200 250 300
Unfolded Length (inch)
FIGURE 4.4 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 100.06 TONS DURINGFIRST LOADING SEQUENCE
75
10
#5 Thrust,-.....,.....c.. 5""-
t'-)
c..-~~
.....0t'-)
=l-.eE- :#1
-5
-10 -+-.-....-....~...,........,...+-,...,...,.....,.......,...,....,-r-t-..,...,....,.....,...,-,.-,-...-r-1
o 50 100 150 200 250 300Unfolded Length (inch)
i
Moment0.1 ......----ro----,-.---.,--~-_.,.-_..
-0.5-+-r-~.........................-i-~"""-+""""'........-~--r-r--+-r-"""""r-1
o 50 100 150 200 250 300Unfolded Length (inch)
C -0.2QJ
§ -0.3 -I---+-+o--+-+---+-+--+--I---t--..
~
-0.4 ...............~..............~¥1- .............................-~~.,.".,........~-----t
,-.....,....c.. 0 O~·--t----f----+----t----t~__.-;:; .c..
I~
.9- -0.1 ...............~~ ...............~-~-~~,.".,"_t ...............__.
~~
FIGURE 4.5 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 107.76 TONS DURINGFIRST LOADING SEQUENCE
-10 -+-.-.......--.~................-+--.~...,...,...~...,....,...,..,...,........,..........,....,....,...,
o 50 100 150 200 250 300Unfolded Length (inch)
Moment
oW
ce-0.3e~ -0.4
-0.5 -t---+----~.......;--. ~~f'___T'-.........___.
-0.6 ~.....,...,~ ~ ~................,.....
o 50 100 150 200 250 300Unfolded Length (inch)
~
~ 0.0 ~~-4----+----i-----+--~~
~ #5Q. -0.1 -I--I!l~--t---- .----+--~--1.-~'"-"' -0.2 -I----4----i-~~-__+_-'l__t-___t
FIGURE 4.6 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 115.45 TONS DURINGFIRST LOADING SEQUENCE
#9
Moment
15#5 Thrust
2 10 -I---+---+---A-+----+--t-~.............
fI.)
c....C 5-1--4---+--+--l----+----t-----t~fI.)
::s.E O...............~~-~.....J.--.---+-J~~----t.............-----t~
-5
-10 ....J--r-...........~..........,.....p...,-,...,....,....;-~_r+..,.............___t.......-.-..,..,...,
o 50 100 150 200 250 300
Unfolded Length (inch)
0.2 .....--......----,-----.,...---,..---,.---,~ #1~.............
~ 0.0I
fI.)
C....C -0.2 4--...w----+--~---+---+--t---t~
c5 -0.4Q
~-0.6 -t----+--\-~-__+__+__--+-_+__--+----t
-0.8~............--+-r-...................;--..-.-.-~~...................-.-i-~."...,....-t
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.7 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 123.15 TONS DURINGFIRST LOADING SEQUENCE
77
78
0.5
#5
...CI.)
E-1.0.c~
-1.5
-2.a-I-.-..........-+-,-..,...-,-,.-+-,...,..,...,..-+-r-r-r......-T-or-or-,....,....,...,.....,....,..,...,
a 50 100 150 200 250 300
Unfolded Length (inch)
Moment
50 100 150 200 250 300Unfolded Length (inch)
0.05
-0.10 ............~-+-r-.......-.-+-w- ...........-+-r-..........r-+-.-........................-.--r-'"I"-t
o
0.20
...=E 0.00e~ -0.05
~
~ 0.15---........~
ICI.)
c..--~"-'"
FIGURE 4.8 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 30.79 TONS DURING SECONDLOADING SEQUENCE
79
2Thrust
1~
#9c=-......CI'JC. 0.-~"'-'"
....CI'J
== -1s..cE--
-2
-3o 50 100 150 200 250 300
Unfolded Length (inch)
0.3Moment
....c~ 0.0Ee~ -0.1 -f.--~~'-I--+----+----+----t
-0.2~...................~.........-..-.........................................~................o 50 100 150 200 250 300
Unfolded Length (inch)
FIGURE 4.9 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 38.48 TONS DURINGSECOND LOADING SEQUENCE,
Moment
80
1
~ 0~
-----tI'JQ...-~
-1'-'"
~
tI'J
=I..c -2E-c
-3
-4 4-.-..........-..+-.-..---,r-+-~,..-+-..,.....,.-..,....;-...,.-,.-r-t--.--.~
o 50 100 150 200 250 300
Unfolded Length (inch)
0.6 -.----,------.r--~-~-___r-___,
~r::~ 0.4 -I---+--~--4~---+-----t'----tc...•tI'JC..-.::.= 0.2 -4--~-~-I-~~"""""""'---+--t
"-'"
.-=E 0.0e~
-0.2 -+---+---~---i--_""O_-___+-__t
-0.4 .......-...........-+-r-.......-..........-.-.-...................-.-+-...................-+.........~
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.10 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 50.03 TONS DURINGSECOND LOADING SEQUENCE
81
1Thrusts
-4
-5o 50 100 150 200 250 300
Unfolded Length (inch)
Moment
......c50.00e~0.25 -+--~~+-I--~--"~--+r
1.00
20.75-<;......e.-
~0.50.-~
~ 0.25 -f---+-----+---+---+-\--~-_+__-_1
50 100 150 200 250 300Unfolded Length (inch)
-0.50 ...........--.-.........................-.-...........--i--r-...........P"""""'i-I-...............-+-r....-.-~
o
FIGURE 4.11 DISTRIBUTION OF THRUST AND MOMENTUNDER LOAD OF 65.43 TONS DURINGSECOND LOADING SEQUENCE
822
~ 0c::............
CI'Je,~ -2 ...............~~ ...............~-"-"'"
-6
-8o 50 100 150 200 250 300
Unfolded Length (inch)
Moment#5
2.0~
~e.- 1.5............
r:::I
CI'Jc. 1.0.-~"-"'"=0.5aJ
Ee 0.0~
-0.5"'-"'---f--~-~_~IIIIw-----+-_---I
-1.0o 50 100 150 200 250 300
Unfolded Length (inch)
FIGURE 4.12 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 78.89 TONS DURINGSECOND LOADING SEQUENCE
83
Thrust~ 0~............
r:I'.Jc..-- -2~'-"
......= -4r-.c~
-6
-8
-1 0~.........-+-'-""""''''''''''''~~~-r-+-~......,....,....,....,..~o 50 100 150 200 250 300
Unfolded Length (inch)
2.0#5 Moment
~
~ 1.5...............,..•tI'.) 1.0e,--~
'-"
...... 0.5c: #9QJ~ 0.0...0
~-0.5
-1.0o 50 100 150 200 250 300
Unfolded Length (inch)
FIGURE 4.13 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 88.51 TONS DURINGSECOND LOADING SEQUENCE
84
50 100 150 200 250 300Unfolded Length (inch)
0#1
~ -2.....c-..--........fI'Jc.. -4.-~..........,
...-6fI'J
=L..cE- -8
-10
-120
-2 -+-.-.....-.-..........................-+-..........-.-+-.--.-....-.--.........-.--............~........
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.14 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 101.6 TONS DURINGSECOND LOADING SEQUENCE
85
0#1
-2~
~"""'"r:rJ
-4Q...-~~
-- -6~
::2'-.cE- -8
-10
-120 50 100 150 200 250 300
Unfolded Length (inch)
Moment#5
......c -1 ~-~~~wwI-........-....+-~~~~...............~~
EQ
:; -2 ...............-~~~Irw-------+-~~----Jrr-- ...........i
~
r::: 1--..............-.
I~
c.. 0 -I-W-'-~---1----f---+\----+----I--+---:;;;~....~~
-3 ..........~......-.-.........-r-+-r..,.........-+-r-r-r ......................-r-t-............,...,.....
o 50 100150200250300
Unfolded Length (inch)
FIGURE 4.15 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 103.91 TONS DURINGSECOND LOADING SEQUENCE
2Thrust
-8
-10o 50 100 150 200 250 300
Unfolded Length (inch)
2~
#5.-'-- Moment............-c.-•tI'.)c....~'-""
~ 0r::QJ
E0
~ -1
-2 ...........................................-i-..........--.-+-r-..-.....-.--.....................-+-r-.........-..-t
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.16 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 111.6 TONS DURINGSECOND LOADING SEQUENCE
86
20 .....---.......--~----.,.--,..----r-----.
87
Thrust#5
~ O~--f.----w~---+-~"i-----t---P--1
=.cE--10 ....a------I~~---i--_+--t___"U_t___-__t
-20 -+-r-...........~..,....,..-r-+-..,.-,-.,,....,........,..-,.~+-r-r-r--I-t-r---r-r--r-t
o 50 100 150 200 250 300Unfolded Length (inch)
1~c::
...............c....• 0~
c....~'-'"... -1=aJ
EQ
~ -2
-3 .....,.........................................~.......-..-.--.- ..................-.--..............~......-t
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.17 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 113.9 TONS DURINGSECOND LOADING SEQUENCE
2 .....--......--.......---....".-----,------r--....,
88
#5 Thrust
#9
-8 ...+-..,.-...........................-t-P-~r-+-r-_r_r_.........,...,...,...,....,.-,...,_..r_~
o 50 100 150 200 250 300Unfolded Length (inch)
0.8 ......---..---~-__._-___r-----.,.-----,
~ ~ornent~ 0.6 -I----4----4---I-+-t-----i--......c.-•~ 0.4.-~
~ 0.2......cE0.0Q
~ -0.2
-0.4 -t---+----~rnr'"""-...............-__+__~-+---_t
-0.6 .................................................-.-.-...-+-,............-+-.......--.r-r-i-~.....-r-1o 50 100 150 200 250 300
Unfolded Length (inch)
FIGURE 4.18 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 50.03 TONS DURINGTHIRD LOADING SEQUENCE
89
-8
-10 ..................-+-.-..........-+-r-.,....,..,.........,...,...,..,....,...,...,...,...,..,...,....,....,..~
o 50 100 150 200 250 300Unfolded Length (inch)
2.0Moment#5~
~~ 1.5c...
I~
.9- 1.0 -I---......a..---~~~----+-""",..,.,...........-.;.---t~'-'"=0.5aJ
§ 0.0 ~~~--+--f---i---+--+----t~:J--'I:E
-0.5
-1.0o 50 1·00 150 200 250 300
Unfolded Length (inch)
FIGURE 4.19 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 57.73 TONS DURINGTHIRD LOADING SEQUENCE.
-10
Thrust
90
-15o 50 100 150 200 250 300
Unfolded Length (inch)
2 i,.......Moment....-"""""-...-I 1tf.:)
e,.-~"'-'".. 0=Q)
E0
~ -1
-2 -+-r-...........,,......,................-+-,-..,-.,.......-+.........-r-r-t-r-r...,...,..-r-r-~......
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.20 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 80.81 TONS DURINGTHIRD LOADING SEQUENCE
91
10 ...--......-----,------,------p------r----,
Thrust
-15o 50 100 150 200 250 300
Unfolded Length (inch)
#9
IMoment
....-........."""-r: 2~----+---~-lJ-\+--...............-___t--_"'t
ItI:.)
Q.--:::, 1-1---4----4--I--+--\---f-----t--t
-2 ...................-+-.-..............................-+-..-.--...................~...............-1
o 50 100 150 200 250 300Unfolded Length (inch)
~IGURE 4.21 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 100.1 TONS DURINGTHIRD LOADING SEQUENCE
92
10
-10
Thrust
-15o 50 100 150 200 250 300
Unfolded Length (inch)
Moment#5
3~...c."'-c= 2 .............-.--+---+-................,~+----+-----t----i
Ir.nC..-~ 1-1----+-----+---I-~\-~-----+---t
-2o 50 100 150 200 250 300
Unfolded Length (inch)
FIGURE 4.22 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 107.8 TONS DURINGTHIRD LOADING SEQUENCE
93
#5 Thrust~
~~ 10 ..............................~...............~Iuuu...............~:~ ...............~~~~~
C.......~"'-'"
-10
~ 0 #1 ~~---I-~-----+-~-+--~---tt..cE--
-20 -+-r-.........-+-w-.........'I""""'t-t'...........~~~..,..........,I"""'""r""T'-r-r-r-r-t
o 50 100 150 200 250 300Unfolded Length (inch)
Moment
~
=QJ
5 -1e~
~
~
~-........~ 1 ..............................~...............~..............., ".........."",...............~~~~...-rr4
Ic;nC.......e O~-~---+----f-~~~"'--~~~
-3 -+-r-.........................................-............--i-..............--+-............................................
o 50 100 150 200 250 300Unfolded Length (inch)
FIGURE 4.23 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 115.5 TONS DURINGTHIRD LOADING SEQUENCE
94
~.... 0----....CFJC..-~~
....CFJ -1=s...cE-
--0--
•2nd Load Seq.3rd Load Seq.
12020 40 60 80 100
Total Load Applied (ton)
-3 -+---....----t~...,.---+----,,...._._+____._-+____r___+_-~_t
o
FIGURE 4.24 THRUST VS "LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSPRINGLINE (POINT #1)
95
oI
2nd Load Seq.3rd Load Seq. --+--....-..-~-----..-.........-..•
I--0--
....-...~ 0.3 ;---,-.....--..............
~•tne,.-~ 0.2 -+------+-----t----+------i----t-~r___1.....CQJ
Ee 0.1 -+------+----+---+----t----t---r't--1
:;
120
~
I
20 40 60 80 100
Total Load Applied (ton)
-0.1 -+-----.-----a~.....---+--r___......-___._-t____r__---t--..-__t
o
FIGURE 4.25 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUEN'CES ATSPRINGLINE (POINT #1)
96
2nd Load. Seq
3rd Load Seq•
-10~-~---+----+----;--~-=----t
~
10...c-..-"""'-CI'.)
c..-~"-""
....CI'.)
0=l-.eE-
1201008040 .. 6020-20 .....--..-----i-.....---+-.--......--+---,--+--....----t--....---t
o
Total Load Applied (ton)
FIGURE 4.26 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #4
97
,.-.....c...-...........
0~c...I~
C.....~~
~
-1cQJ
Ee~
---0-- 2nd Load Seq.-2 -+--_.., ~ '\ -- --+----+-t--~
• 3rd Load Seq.
12010080604020-3 -+--...---l~.....---+--.....--+--...-+----r----t-~---t
oTotal Load Applied (ton)
FIGURE 4.27 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #4
98
20
-0- 2nd Load Seq.15 • 3rd Load Seq.
,~
~-......-..tn
10e,.-.::.::"-'"
.....tn 5='-.c
E--0
20 40 60 80 100
Total Load Applied (ton)
FIGURE 4.28 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATCROWN (POINT #5)
3I--0- 2nd Load Seq.
...-.... • 3rd Load Seq.......-........... 2~-•CI.:)
c..-~~
~
1cQJ
E0
:E
0
20 40 60 80 100
Total Load Applied (ton)
FIGURE 4.29 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATCROWN (POINT #5)
99
10 -.---'---r'---.,----.,..--~--...,..__-___,
~5
......c...""""-~
Q..-~ 0"'-'-'
......~
=I..c
-5~
-0- 2nd Load Seq.e ~
• 3rd Load Seq.-10
20 40 60 80 100
Total Load Applied (ton)
FIGURE 4.30 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #6
100
101
~...c:..-""'"""- 0..c:..-
IfI'.}
c...-~"-'"..
-1cQJ
50
~
-2--0--
•
I2nd Load Seq.I I
3rd Load Seq.
20 40 60 80 100
Total Load Applied (ton)
FIGURE 4.31 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #6
102
~....... 1~-........fI.:)
c.--.:.c:"'-'"
.....fI.:)
0='-.cE-
-0--
•2nd Load Seq.3rd Load Seq.
I20 40 60 80 100
Total Load Applied (ton)
FIGURE 4.32 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSPRINGLINE (POINT #9)
103
12020 40' 60 80 100
Total Load Applied (ton)
-0.1 -+----.-----+-..,..---t----.--o+---.,---t--,.---t----r-----1
o
0.4
..-....0.3
2nd Load Seq .....c0..- I
"""'" 3rd Load Seq.....c0..-
If.I:)
e,.-~ 0.2'-"
....cCJ
E0.10
~
0.0
FIGURE 4.33 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSPRINGLINE (POINT #9)
104
positive indicating the inward movement of the culvert. Small value of moment agrees well
with small deflection data at these locations. In general, the magnitude of the thrust and the
moment in the springline region was much smaller than those in the shoulder or in the
crown region and agreed well with the deflection data.
Sections #2 and #8 responded similarly. Bending moment is positive in both the
sections and both were in compression. Values of bending moment and the thrust were
increased with increase of loading. Response at sections #3 and #7 which were at the
haunch region also responded similar to each other indicating the symmetric conditions
prevailed at the field. Moments at these two sections were negative indicating the outward
movement of the culvert at these locations. Thrust values are in compression and increased
with the load.
During the second loading sequence, the magnitude of the moment increased as the
load increased at point #5 where the magnitude of the moment decreased when the load
reached approximately 100 tons. The moment and thrust decreased when additional load
increments were applied. At the load of 113.9 tons, the moment changed its sign and
became insignificant and the thrust changed from compression to a large tension
magnitude. Moment values at sections #4 and #6 were negative but not equal. Moment
value at section #4 is more than the plastic moment capacity of this type of structural plate
indicating the formation of plastic hinge at that location. Moments at section #5 and #6 were
close to it's plastic moment capacity. Visual inspection showed us the formation of hinges at
those locations also. This may be due to the fact that corrosion might have reduced the
~tiffness of the culvert plate since it was exposed to adverse field conditions for the past
fifty years. Thrust value at these sections were in compression and increasing with the load
until 101.6 tons load was on. After the eighth load (103.9 tons) step thrust value started
decreasing and changed to tension at the last step of loading of the second sequence of
loading.
105
During the early stage of second loading cycle, the system acted as a composite
beam. The moment and thrust distribution increased in magnitude as applied load
increased. These distribution pattern were symmetrical about the crown point upto the
eighth load increment. Beyond this loading step circumferential stress at the section #4
reached the yield stress. Moment value at this section became higher than that at point #6
therefore, disturbing the symmetric nature of the distribution.
Figure 4.34 explains the nature and exact location of the slippage occured near
the instrumented plane, where the crown seam was the weakest. After the slippage occured
at the bolted joints that section didn't behave like a composite beam rather the system
responded as a truss. Strain gages then gave localized responses.
Fig.4.28 and 4.29 gives the thrust and moment values obtained for section #5 with
increments of the load. Moment values didn't change much after the 88.51 tons in the first
cycle; instead it reduced little and turned negative during the last step of the second cycle
and the whole of the third cycle. Thrust also behaved in the same way. It decreased after
101.6 tons of load and had sudden drastic increase at the last step of the second cycle of
loading. Axial thrust was in compression until the last step of the first cycle and changed
into tension during the last step of loading and remained in tension throughout the third
cycle of loading. After the slippage occured at the bolted joints that section didn't behave
like a composite beam.
Although the load was removed after the second loading sequence, the culvert, as
indicated by the measured deflections, did not recover its original shape. Outside the crown
region, the thrust response did not differ much between the second and the third loading
sequence, and the moment response was smaller during the third loading sequence. The
responses at points #4, #5, and #6 showed some difference between the last two loading
sequences. The moment at point #5 responded slightly more but the thrust remained in
tension. Yield was reached in the longitudinal direction at the crown under 115.5 ton load
Vertical Pressure 106
Strain Gages @Point #4
Strain Gages @Point #5
c::::J
Thrust f
Strain Gages @Point #6
Bolted Crown Seam
(a) Initial Stage
Vertical Pressure
Strain Gages @Point #4
Strain Gages @POiI1t #5
Bolted Crown Seam
(b) .Final Stage
FIGURE 4.34 FAILURE MODE OF BOLTED CROWN PLATES UNDER LOAD
107
during the third loading sequence.
4.4 PLASTIC MOMENT CAPACITY
The determination of the plastic moment capacity is obviously of great importance
because it is the limiting or maximum moment for the corrugated steel plate. Increasing the
bending moment above the yield moment will cause the strains at the extreme fibers to
increase and the maximum strain will exceed the yield strain Ey . However, because of
perfectly plastic yielding, the maximum stresses will remain constant and equal to cry
The plastic moment capacity of the tested corrugated steel culvert is equal to
3.745 kips-ft/ft, using ultimate yield stress of 30 ksi. Here, it must be noted that the above
definition of the plastic moment doesn't take into account the axial forces. The value of
3.745 kips-ft/ft represents an upper limit. Actual moment capacity will be slightly reduced
when axial forces are considered.
4.5 FORMATION OF PLASTIC HINGES AND CREASES
When Mmax becomes equal to Mp' the cross-section at the center of the beam is
completely plastic. The curvature at the center of the beam is completely plastic. The
curvature. at the center of the corrugation then becomes extremely large and unrestrained
plastic flow may take place. No further increase in the maximum moment can occur, and
the load on the beam is at its maximum value. The corrugation fails by excessive rotations
that occur at the middle cross-section, while the two halves of the corrugation remain
comparatively rigid. Thus, corrugation behaves like two rigid bars linked by a plastic hinge
that permits the two bars to rotate relative to each other under the action of a constant
momentMp.
108
Available data from this test indicates that a plastic hinge is formed only at section
#4, at the load of 113 tons of the second cycle of loading. Moment at points #5 and #6
became close to the upper bound plastic moment capacity. After the test, plastic hinge
formation was also observed at these locations. Figure 4.35 shows the formation of plastic
hinges. All the other sections are under their plastic moment capacity. According to
Dessouki. A.K. and Monforton. G.R, "the formation of plastic hinges in the conduit
doesn't constitute complete failure but rather affects the load carrying capacity". Duncan.
J.M. in his study [8] considering both the axial force and the bending moment has
concluded that:
1) Formation of a single plastic hinge will not result in formation of a failure mechanism,
even in an arch structure pinned at the footings. Additional plastic hinges would have to
form before the structure collapses.
2) Even after sufficient hinges have developed in the structure to form a failure
mechanism, the soil will continue to restrain the deformations of the structure.
3) Both aluminum and steel harden when deformed plastically. Therefore, the use of the
value of M p based on minimum values of yield stress provides a conservative estimate of
the ultimate esistance of the metal.
From the above findings we can conclude that the culvert we tested didn't develop a
failure mechanism that would have caused the full failure of the culvert for the above cited
reasons. Further, the maximum load that can be carried by the culvert is equal to 100 tons.
Sections which reached their yield limit were tabulated in Table 4.3. This gives an idea of
the critical sections of the pipe arch culvert with shallow cover.
After the testing was over close inspection of the culvert showed us the formation of
creases in the plate at various location of the culvert. Table 4.4 and the Fig. 4.36 presents
an idea of the location and the size of the creases. Although the formation of the creases
doesn't have any significance towards this study, for the sake of completeness of this
document it is presented here. Creases #1 through #9 were lined up at a distance of about
L"",::
.:'Y~~
;~;;":
"',",'i:
:<.·.~f:
~J;.:..t·t
·,::,7:
~'·'
','.
...,.--
,.
..
"0
'."''''f~/-
..··'#
1'1(
'·.'f("'~~.hlr;'t{;b~
--~
·"t."'~-~~,
....".
}~'if
~'"
'-'
-ll"lt
"'1
\fi:.
af&W
o~
.Ii
.J11
00
.~t.Ii
~-_.
,!oo
d•••
:••
...,••••~
.~,
•'-
:'b
r.
••••.
~•••
",'.
,.~;
•.0'
.·,.
••t'~1,'
'o":.~
.o
'-,
w,.
..
~.'.
,.'.
:,[\.~"'~
1~!lSf;tl
'Ii•
.,~~,.~_~.~
•••~;).
••l'
'-,
FIG
UR
E4.
35F
IEL
DP
ICT
UR
EO
FC
UL
VE
RT
CR
OW
NR
EG
ION
SIIO
WIN
GP
LA
STIC
HIN
GE
FOR
MA
TIO
N.....
... ~
TABLE 4.3 YIELD STRESS REACHED DURING FAILURE TESTS
* First Sequence of Loading - Sept. 24, 1990
Yield stress was never reached at any monitoring point during loading
* Second Sequence of Loading - Sept. 26, 1990
Section Load Increment No.No. Location Direction
6 7 8 9 10 11 12
Circumf. N N N -Y -Y -Y -yCrest
Longit.4 N N N N N N N
Valley Circumf. N N N N N +Y +y
Longit. N N N N N N N
CrestCircumf. N N N N N N NLongit. N N N N N N N
5 Valley Circumf. N N N N N N NLongit. N N N N N N +Y
Side Circumf. N N N N N N NLongit. N N N N N N N
* Third Sequence of Loading .- .Sept. 26, 1990
Section Load Increment No.No.
Location Direction1 2 3 4 5 6 7
CrestCircumf. N N N N N N NLongit. N N N N N -Y -y
5 Valley Circumf. N N N N N N NLongit. N N N N N +y +y
Side Circumf. N N N N N N NLongit. N N N N N N N
(Note) N =Yield Stress Not Reached; -Y =-cy Reached; +Y =+cy Reached
110
TABLE 4.4 LOCATION AND LENGTH OF CREASES DETECTED
Crease Crease Length General LocationL 1 L2
No. (in.) (in.) (in.)
1 3/8 South Side of Crown 13-11/16 24-3/4
2 5/8 South Side of Crown 17-1/4 24-3/4
3-a 3/8 South Side of Crown 20-1/8 24-3/8
3-b 3/8 South Side of Crown 20-1/2 24-3/8
4 5/8 South Side of Crown 23-1/2 24-1/8
5 1-3/4 South Side of Crown 26-5/8 23-3/8
6 1-1/4 South Side of Crown 29-1/2 24-0
7 1/2 South Side of Crown 35-3/8 24-0
8 1-0 South Side of Crown 38-3/4 24-0
9 7/8 South Side of Crown 45-1/8 24-7/8
A 3/4 North Side of Crown 14-1/4 36-3/4
B 1-1/2 North Side of Crown 20-3/8 35-1/2
C 1-5/8 North Side of Crown 26-1/4 36-0
D 1-3/8 North Side of Crown 38-1/8 35-1/2
E 1-1/4 North Side of Crown 44-1/4 35-3/8
111
II
I
-----tsiI
I
FIGURE 4.36 MEASUREMENTS TAKEN. TO LOCATE CREASES
112
113
24 inches south of the crown (or at a distance of about 9.25 inches north of monitoring
point #6). Creases A through E were detected at a distance of about 36 inches north of the
crown (or at a distance of 2.75 inches north of monitoring point #4).
CHAPTER 5
FINITE ELEMENT ANALYSIS
5.1 INTRODUCTION
The design of corrugated metal culverts, until recently, has been largely based on
empirical relations and on past experience with these types of structures. Although these
methods can result in satisfactory designs, their ability to predict the behavior of the soil
culvert system is rather limited. In these methods, analysis of the structure was done by
assuming a plane strain ring structure subjected to vertical loading. The soil pressure
distribution on the structure is then found from the calculated pipe deflections.
Due to rapid improvements made on the computational ability in the past few
decades, the finite element method has gained large popularity and wide applications. In the
last two decades, the finite element method of analysis was effectively applied to culvert
problems [1,2,5,8,17,]. After its successful introduction in the early 1970's, advances
have been made to incorporate material nonlinearity, construction sequences, and soil
structure interface elements. In this method, both the soil and the pipe are modeled as
plane-strain continuum.
Finite element method is capable of providing a more comprehensive representation
of the complex soil-structure interaction problem involved. The essential requirement for a
comprehensive finite element simulation are:
1) Inclusion of live load as well as dead load.
2) Adequate presentation of the true geometry and realistic boundary condition.
3) Realistic modeling of the nonlinearities in soil and structure properties.
In this investigation, numerical simulations of structural behavior of the pipe arch
culvert during the failure tests were attempted with the use of the CANDE (Culvert
115
ANalysis and DEsign) computer program. It is capable of representing the nonlinear
properties of structural and soil elements as well as the interface element. More detailed
information on the CANDE program is found in References (13,14)
5.2 CANDE BACKGROUND
CANDE can be operated in a design or analysis mode. Here in this chapter only the
analysis mode is briefly discussed. The assumptions common to all solution levels in
CANDEare:
1) Two dimensional analysis with plain strain.
2) Small strain theory
5.2. 1 SOLUTION LEVEL
There are three solution levels in CANDE. Levell corresponds to the elastic,
closed form solution. However this level cannot consider such features as arch-shaped
structures on footings, and the several zones of backfill material, all of which are important
consideration in this study. Level 2 is finite element solution where the mesh is
automatically created by CANDE whereas in level 3, which is also finite element analysis,
the mesh is defined by the user.
5.2.2 PIPE TYPES
The pipe material library in CANOE includes corrugated steel, corrugated
aluminum, concrete, plastic and basic pipe types. In our case corrugated steel pipe type
was used. In this type uniform geometric properties of the wall section are assumed
throughout the culvert periphery. Both linear and bilinear constitutive models of the pipe
material are allowed under this type. In this analysis the bilinear model is used.
116
5 .2 .3 ELEMENT TYPES
There are three basic types of elements available in CANDE (1) Beam-Column
element; (2) Quadrilateral element (3) Interface element. In this analysis only Beam
Column element and quadrilateral element are used. Normally Interface element is provided
to allow frictional sliding, separation and rebinding of elements meeting at a common
interface. Here in this analysis we avoided using this element to solve the convergence
problem encountered by others.
5.2.4 SOIL MODEL
At present there are five soil models available in CANDE:
1) elastic
2) ortho-elastic
3) over-burden dependent
4) hardin model
5) Duncan model
Considering soil's non-linearity and non-homogeneity it is determined that soil can
be best represented by Duncan's stress-strain hyperbola model [9,10,11]. In order to derive
the Duncan's constitutive parameters several triaxial tests were conducted with the samples
obtained from the test site. The main reasons for selecting this model are; (1) its availability
as a part of the soil model library in the CANDE program, (2) its incorporation of the minor
principal stress in defining initial and failure stresses; and (3) ease in obtaining its
parameters from ere (conventional triaxial compression) tests. Someshortcomings of this
model is that it is not suitable for predicting the soil behavior where the loading conditions
induced stress paths other than that of the ere within the soil mass.
5.3 FIELD SOIL SAMPLING WORK
The backfill soil sampling work was conducted on April, 1, 1991, about six
months after the completion of the field testing. The equipment utilized was a standard
117
truck mounted rotary drilling rig. The rig was set within the west shoulder section of the
the roadway above the culvert, since the subsurface soil data was previously obtained at the
location (as seen in Fig. 2.2) and a complete blockage of the local traffic posed a problem.
The goal of the sampling work was to obtain a few relatively undisturbed soil samples from
each of the three (crown, haunch, and springline) regions on both the east and west sides
of the culvert structure. A total of six soil samples were taken by hydraulically pressing at
a constant rate three inch O.D. thin-walled sampler. Upon removal of the sample tubes
from the holes, their ends were double-sealed with special caps. Later, they were
transported to the CGGR research laboratory in a wooden cradle.
5.4 LABORATORY SOIL TESTING METHOD
The conventional, consolidated and undrained (or CD) triaxial testing procedure
was selected as a method to characterize the shear strength parameters and stress-strain
characteristics of the sampled backfill soil materials. A total of 14 tests were performed
using T-1500 triaxial testing device. To measure volumetric strains during the test, changes
in the volume of water inside the triaxial cell were monitored with a graduated tube. For
each test, a soil sample extracted from the tube was inspected to make sure that it had no
defect and then trimmed down to a diameter of 2.8 inches and a height atleast twice the
diameter. It was wrapped completely with a rubber membrane. Loading platens were
attached with O-rings at the top and at the bottom, inside the triaxial chamber, with porous
stone plates inserted between the soil specimen and the platens. To initiate the testing
process, the chamber was filled with distilled water and a confining pressure ranging from
5 to 15 psi was applied to consolidate the soil. Table 5.1 presents some basic information
regarding each triaxial test. Strain-controlled axial loading was exerted with a ram and the
load was measured using a proving ring. To compute axial stresses during the test, the
cross-sectional area of the specimen was corrected to account for Poisson's effects. The
instantaneous area was computed using volumetric strain data and assuming the cross
section was equal along the length of the specimen.
TA
BL
E5.
1B
AS
ICIN
FO
RM
An
ON
ON
TR
IAX
IAL
TE
ST
S
Tes
tS
ampl
eS
ampl
eC
on
fin
ing
Mo
istu
re•
Den
sity
•N
o.B
orin
g1.
0.D
epth
(ft.
)Z
one
Pre
ssur
e(p
si)
Co
nte
nt
(%)
(pef
)
1A
IP9.
1-9.
6C
row
n10
.017
.44
136.
74
2A
IP8.
5-9.
0C
row
n5.
013
.91
121.
67
3B
IP7.
9-8.
4C
row
n15
.018
.40
NT
4B
IP7.
4-7.
9C
row
n5.
017
.60
133.
39.
5A
2P
12.4
-12.
9S
ho
uld
er
15.0
2~.28
133.
60
6A
2P11
.9-1
2.4
Sh
ou
lde
r10
.032
.65
133.
33
7.B
2P12
.4-1
2.9
Sho
ulde
r10
.016
.67
131.
50
8A
2P10
.9-1
1.4
Cro
wn/
Shou
lder
5.0
28.1
312
3.10
9B
3P15
.8-1
6.3
Spr
ingl
ine
10.0
21.2
711
9.67
10B
2P11
.9-1
2.4
Sho
ulde
r5.
022
.84
132.
48
IIB
3P15
.3-1
5.8
Spri
nglin
e5.
024
.80
117.
40
12A
3P15
.8-1
6.3
Spri
nglin
e15
.029
.05
120.
56
13A
3P15
.3-1
5.8
Spri
nglin
e10
.018
.56
135.
37
14B
3P14
.8-1
5.3
Spr
ingl
ine
15.0
26.7
111
9.05
(Not
e)T
hesy
mbo
l".
"in
dica
tes
initi
alva
lues
.~ ~ 0
0
119
5.5 RECOMMENDED SOIL PARAMETERS
The Duncan soil model is a variable moduli (or nonlinear) model which
characterizes soil behavior with tangent Young's modulus and bulk modulus. The
guidelines suggested by Duncan [Duncan et al.,1980] were followed in deriving the
hyperbolic model parameters.
Duncan recommends fitting the hyperbola throug~ only two points on the stress
strain curve: 70% and 95% of the failure strength of each test. This is accomplished on the
plot of transforrned axes where a hyperbola plots as a straight line. The Duncan soil model
contains a total of eight parameters K,n,Rf,<I>O,~$,c,Kb' and m. Derivation procedure of
the two shear strength parameters c and <t> through triaxial test results is well known. A
systematic determination of the remaining six soil parameters out of triaxial test data has
been presented in details by Duncan [10]. These procedures are briefly summarized in
Table 5.2. Recommended values for all eight parameters were tabulated in Table 5.3.
5.6 FINITE ELEMENT SIMULATION
Half mesh is used to represent structure and backfill for our problem. This is
acceptable since the structure and the loading conditions were assumed to be symmetrical.
Mesh was created using both design and the measured shape of the culvert. Figure 5.1
explains the node numbering and element numbering system used for this analysis.
The boundary conditions established at the nodes are 1) nodal points along the bottom
boundary were fixed in both the vertical and horizontal directions. 2) The nodes on the
right and left sides of the mesh are fixed in the horizontal direction but free to move in the
vertical direction.
The asphalt layer was represented by quadrilateral elements. The modulus of 1000
ksi was used to simulate the compacted form of the asphalt. The pipe material selected out
of the CANDE library was corrugated steel with bilinear constitutive models. Pipe was
TABLE 5.2 DUNCAN'S HYPERBOLIC SOIL MODEL PARAMETERS
120
Parameters
K = Modulus Number:
n = Modulus Exponent:
R f = Failure Ratio:
c = Cohesion Intercept:
<t>0 = Friction Angle:
~ <p = Reduction in <t>
For IO-Fold Increases:
Kb= Bulk Modulus Number:
m =Bulk Modulus Exponent:
Determination Procedure
From Relating Initial Modulus ToConfining Pressure
From Relating Initial Modulus ToConfining Pressure
By Dividing Failure Shear Stress ByUltimate Shear Stress
From Mohr-Coulomb Failure Criterion
From Mohr-Coulomb Failure Criterionand Relating <t> To o 3
From Mohr-Coulomb Failure Criterionand Relating <I> To 0'3
From Relating B To o 3
From Relating B To a 3
TABLE 5.3 A SUMMARY OF MATERIAL PARAMETERS
* Steel (Bilinear Elastic)
Initial Young's Modulus, E1 =30 x 106@'si.Secondary Your Modulus, ~= 1.76 x 10 psi.Poisson's Ratio, U =0.3.Yield Stress, 0y = 33,000 psi.
* Asphalt (Linear Elastic)
Young's Modulus, E =lxlO6
psi
Poisson's Ratio, U = 0.41
* Backfill Soil (Hyperbolic Model)
~ Experimental CLIOO SMI00
c 1.44 psi 2.78 psi O. psi
<P 0.423 radians 0.524 radians 0.628 radians
~<P o. o. 0.14
Rf 0.706· 0.700 0.700
K 37 150 600
n 0.217 0.450 0.250
Kb 410 140 450
m 0.49 0.20 o.
121
122
24
61
03
74
64
54
41
28
36
84
48
94
73
79
85
67
175 1
I165
ISS 1
1
131 I
124 1~ ..... Ll 3 112 10 106114 -- 111 08
109 97107 105
99 100 101 102 I
104 96 .e
9S89
90 91 92 9388
87
86 81 82 83 84
8
'7475 76 77 78
) 68 69 70 71 72
/62 63 64 65 66
:c 57 58 59 60
S5-~ 54
50 51 52 5349
37 38 39 40 41 42 43 44 45 46 47
25 26 27 28 29 3C 31 32 33 34 3S
13 14 IS 16 17 16 19 20 21 22 23
142129116
115
2 3 4 5 6 7 8 10 1 J 12
FIGURE5.1 NODE NUMBERING SYSTEM USED FOR THE HALF MESH
123
represented by the beam-column elements. Interface elements between pipe and backfill
material were not used inorder to avoid the convergence problems as reported by others.
(Alan Rauch 1990)
Live load applied by hydraulic cylinders was converted to line load by the method
proposed by Duncan and Drawsky. This method is based on load distribution in a semi
finite space. This method models an axle with several wheels by a line load which provides
the same maximum vertical stress beneath the wheels on a plane at the depth of the top of
the culvert crown as would the actual three-dimensional wheel loading, based on
Boussinesq linear elastic vertical stress distribution analysis. This method is considered to
be conservative because it provides a line load producing this peak stress along the full
length of the culvert, whereas wheel loads provide this stress only beneath the wheels with
stresses away from the wheel loading points. This inherent conservatism is minimized in
corrugated culverts which do not have significant flexural stiffness longitudinally along the
culvert and which are, therefore, vulnerable to localized overstressing directly beneath
discrete wheel loads.
Duncan and Drawsky developed a simple equation and tabulated solution
expressing their equivalent line load estimation procedure as
LL=AL/K4
where LL equivalent line load (kips/ft)
AL. total axle load (kips) and
K4 load factor (ft)
In this analysis K4=8.7 ft was used, which is corresponding to 3 ft. cover and 4
wheels per the axle. The load factor (K4) values, based on Boussinesq elastic analysis for
various depths of soil cover and under different contact areas, are presented in Table 5.4.
No simulation of the first day test (the first load sequence ) conditions was
TABLE 5.4 LOAD FACTOR (~) FOR VARIOUS COVER DEPTHSAND LOADING CONDITIONS
Values of Load Factor K4 (ft.)
Number of Wheels Per AxleCover Depth
(ft.)
2 4 8
1 4.3 5.0 8.5
2 5.3 6.4 9.2
3 7.9 8.7 10.6
5 12.3 12.5 13.5
7 14.4 14.5 14.6
10 16.0 16.0 16.0
(Note) This information was obtained after Ref. [7].
124
125
attempted, since most of the deflections took place and a moderate degree of structural
failure was achieved during the second and third loading sequences. The mesh consists of
184 nodes, 21 beam elements and 151 quadrilateral elements. A total of 5 types of CANDE
computer program simulations were made. These simulations were done as summarized
below:
Simulation #1: Experimentally derived soil parameters were input for the entire
backfill soil region. (A symbol "K" is used in the graphical plots
to indicate results from this simulation.)
Simulation #2:
Simulation #3:
Simulation #4:
Simulation #5:
Same as simulation #1, but the parameter K value was increased
to 3K. (A notation "3K" is used in the graphical plots to indicate
results from this simulation)
Two material types from the CANDE soil material property
library (CLIOO and SMlOO) were specified in the backfill soil
region according to the boring log data. (see Figure 5.2 for
locations of the two soil types. Results from this simulation
were denoted by "FIELD-K" in the graphical plots.)
Same as simulation #3, but the K values were magnified by a
factor of 3. (Results from this simulation were denoted by
"FIELD-3K" in the graphical plots.)
Two material types from the CANDE soil material property
library (CLl00 and SMl(0) were specified in the backfill
region, as shown in Figure 5.3. (Results from this simulation
were denoted by "ClOOS100" in the graphical plots.)
6
151 152 154
136 142 143 145124 130 131 133
24
12 3 119 120 121
FIGURE 5.2 VARIOUS MATERIAL ZONES DEFINED FORSIMULATION #3
20
FIGURE 5.3 VARIOUS MATERIAL ZONES DEFINED FOR SIMULATION #5
127
128
s. 7 CANDE PREDICTIONS AND DISCUSSION .
The parameters for Duncan's soil model were obtained from the triaxial test results
and from the CANDE library. Calculation of CANDE predictions were stopped whenever
the stress level at any point of the structure reaches it's yield limit. Deflections predicted by
CANDE were compared with the field results. Figures 5.4 through 5.8 presents the
comparisons for #5 through #9. The deflections predicted by CANDE for all the points
were in the conservative side. The large error in the CANDE predictions occured because
of one or more of the following factors.
1. The soil samples obtained for the triaxial testing came from the shoulder part of
the road section. These soil samples were relatively loose compared to the soil
under the pavement section because of the compaction occured due to live loads
applied over the last 37 years.
2. It is very difficult to simulate in the laboratory that the type of compaction the
soil material experienced in the field.
3. The stress distribution did not distributed uniformly, after the slip took place at
the bolted crown seam.
4. The maximum deflection in the field occured little away from the instrumented
section. CANDE is not capable of analyzing the three dimensional problem.
The finite element simulation predictions for moment and thrust were generally
higher, but the trend was similar. Figures 5.9 through 5.16 presents the moment and thrust
distribution graphs. Thrust predictions agreed well in the higher loading steps. Moment
predictions agreed well at points #6 and #9. variation in the magnitude of the moment is
high at the crown and haunch region. The reasons for high discrepancy in the finite element
predictions were may be due to the above cited reasons.
129
70605040-8 -+--~-.....---...---......----..---~--.-~
30
0-0-- EXPT.
• K,..-.....c --a-- 3K~ -2= --0-- FIELD-K....
'""-'"N FIELD-3K,......
0 -{;r- CIOOSIOO...-4~
QJ.....QJ
Q
-6
Total Load Applied (tons)
FIGURE 5.4 COMPARISON OF DEFLECTION OFMONITORING POINT #5 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS
.-.....-2~
~......~
Q-3
-4
-530
1...,...-------------- --0-- EXPT.
• K~ 0 D ,,,"" ,,,,,,,,-"',,,,,w''',,, , eM,""'""",,,,, ~ 3K
~ 1e::::::~===:T-t::=:::-----....._~ -0- FIELD-K
=~ -1 " FIELD-3K
= ---tr- Cl00S 100o
40 50 ~ 70Total Load Applied (tons)
FIGURE 5.5 COMPARISON OF DEFLECTION OFMONITORING POINT #6 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS
130
131
70605040
0.2 ...,.---------------. ---iJ-- EXPT.
• K---a- 3K
-0- FIELD-K
M FIELD-3K
--tr- C1005100
-1.2 -+-----.--.....---..--.---.,.----+------.,.----1
30
0.0 a a~
~ 0==--.: -0.2 ... "..."..,.'-'."'-'"
=.= -0.4-~~
~ -0.6Q
-0.8
Total Load Applied (tons)
FIGURE 5.6 COMPARISON OF DEFLECTION OFMONITORING POINT #7 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS
132
0.2 ~---------------. ---cr- EXPT.
• K~ 3K
70605040-0.8 -+-------.---......---....--.-----,.--.....----flA-----I
30
=-0.2...........~~
cQ-0.4
Total Load Applied (tons)
FIGURE 5.7 COMPARISON OF DEFLECTION OFMONITORING POINT #8 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS
133
70
--0-- EXPT.
• Ko 0 Q,u",u,,,,,n, "'"
~; --a-- 3K--0-- FIELD-K
M FIELD-3K--t:r- CIOOSIOO
40 50 60Total Load Applied (tons)
-1.2-+-----.---+-----..--.----..--..+------,,.......----1
30
0.2-r----------~---
=.:-0.4......~QJ
~·O.6Q
-0.8
FIGURE 5.8 COMPARISON OF DEFLECTION OFMONITORING POINT #9 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS
134
-5 ~,............. ..........t
125 150 175 200 225 250 275 300
0--0-- EXPT.
• K~ -I
~ 3K"....----~ ----0-- FIELD-KQ..-~ -2
M FIELD-3K---ts:-- CIOOSIOO.......
ir:
=-,.c -3~
-4
Unfolded Length (inch)
FIGURE 5.9 COMPARISON OF THRUST DUE TO30.79 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS
4-iJ-- EXPT.
3 • K
---a-- 3K~ --0-- FIELD-K..
». FIELD-3K
--fr-- CIOOSIOO
-1
-2 ~~""""""-~~"""""".....-r-P"""""""~~......-r-i"-~......-t
125 150 175 200 225 250 275 300
Unfolded Length (inch)
F-'IGURE 5.10 COMPARISON OF MOMENT DUE TO'30.79 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIlVlULATIONS
135
136
.,...--0- EXPT.
• K
---a-- 3K...-... 0~ -0-- FIELD-K--v:
M FIELD-3KQ....~ --&- CIOOSIOO'-'"
..... -2v:='-.c
E--
-4
-6 .............~~...........,...................................~~-r-r-i-......,..,.~
125 150 175 200 225 250 275 300
Unfolded Length (inch)
FIGURE 5.11 COMPARISON OF THRUST DUE TO38.48 TON LPAP BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS
5..,....------------
4
-3 -+-t-P...........~..................................,I"""'P'"'P"....._r_9.................,...,......,...,......._t
125 150 175 200 225 250 275 300
Unfolded Length (inch)
~ EXPT.
• K--e-- 3K
--<>-- FIELD-K
M FIELD-3K
----&- CIOOSIOO
137
FIGURE 5.12 COMPARISON OF MOMENT DUE TO38.48 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS
138
-6
-7
-8 ~-.--.-r..............~--.--.--,~~~~,.-.,-,-~or-r-r-I
125 150 175 200 225 250 275 300
1-0-- EXPT.
0 • K
~ -1--a-- 3K
~ ---<>-- FIELD-K---~ 2Q. - )4 FIELD-3K...~
~ CIOOSIOO'-"'" -3~v:
= -4~
.cE- -5
Unfolded Length (inch)
FIGURE 5.13 COMPARISON OF THRUST DUE TO50.03 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANOESIMULATIONS
139
150 175 200 225 250 2"75 300
--0-- EXPT.• K
----e- 3K-0-- FIELD-K
a FIELD-3K
• CIOOSIOO
6-r---------------.
5
~ 4~--~ 3
Iv:c.. ~..... ~
~'-'" 1......~ 0ee -1:;
-2
-3
-4-5 ~~_.__.__r~~~.............._.__._r""'_;_'O~...,....,...,~
125
Unfolded Length (inch)
FIGURE 5.14 COMPARISON OF MOMENT DUE TO50.03 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS
2..,...------------
o,-.............~ -2c..-~""-'" -4
-8
-10
-12 ............-----.......--....~---..-- .............~~.....-............-- .......
125 150 175 200 225 250 275 300
Unfolded Length (inch)
---0-- EXPT.
• K----a- 3K--0-- FIELD-K
M FIELD-3K
--fr- CIOOSIOO
140
FIGURE 5.15 COMPARISON OF THRUST DUE TO65.43 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS
7
5
~
3~--~
IrI). 1c..-~"'-'"
~ -1=~eQ -3:;
-5
-7 -+-.-.--.-.r-.............-.........................................,.....,..-,...............,..-,--,.-....-r-r-or-r-r-.,.-r-r.......-t
125 150 175200 225 250 275 300
Unfolded Length (inch)
141
--0- EXPT.• K
--a-- 3K---0- FIELD-K
M FIELD-3K
--lr- CIOOSIOO
FIGURE 5.16 COMPARISON OF MOMENT DUE TO65.43 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS
142
A parametric study was also conducted to determine the influence of the modulus
number. Duncan and his co-workers have speculated, for loose soils modulus number may
be increased upto three times the value of K to incorporate the loading and unloading
effect. To determine this effect, we have done a simulation by increasing the value of the K
by three times. Influence of the parameter changes was not significant. The value of the
modulus exponent "n" is always very similar for primary loading and unloading, and in the
hyperbolic relationships it is assumed to be the same.
CHAPTER 6
CONCLUSIONS AND RECOMMENDATIONS
6.1 SUMMARY AND CONCI.JUSIONS
A full-scale field test was conducted in a long span pipe arch culvert. An
exceptional live load was applied through two hydraulic cylinders. Field data were collected
and analysed for all three loading sequences. Finite element simulations were conducted
using the CANDE computer code. Duncan's hyperbolic soil model was used to simulate the
backfill soil. Tape extensometer was used to determine the shape of the culvert before and
after the test. Although it gave fairly accurate data, collection of such data was very time
consuming. Position transducers were used to collect deflection data upon each loading
step. Strain gage data was also collected upon each loading step. Hp data acquisition
system was used to collect data from the position transducers and strain gages. The
following conclusions were made at the end of the study:
* The maximum load carrying capacity of a pipe arch culvert, with 3 feet
cover of cohesive soil was determined to be approximately 100 tons.
* The maximum moment capacity of the pipe arch culvert is 3.745 kips-ftlft
(without taking axial forces,into account)
* The maximum vertical crown deflection was 6.99 inches for approximately
115 tons during the third loading sequence.
* Partial failure occured due to the formation of plastic hinges.
* Severe distress occured at the crown region and a slip occured at the bolted
connection. After that the culvert responded like a truss rather than a
composite beam. 144
* Critical sections of this type of culvert was determined to be sections four
five and six. (Although section six didn't reach its yield limit, it was very
close to doing so.)
* Formation of creases were observed approximately two feet away from the
instrumented region on both south and north sides.
* Generaly moment and thrust distribution were as expected. Both increased
till the loadwas approximately 100 tons during the second loading sequence.
Severe distress occured at the crown region for the higher loading steps and
the thrust at the crown increased sharply and moment became very small.
* Deflection predicted by finite element simulations always larger than the
field results. Moment and thrust predictions were also very large but the
trend agreed well with the field results.
* Parametric study undertaken to determine the influence of modulus number
"K" gave better agreement for the deflection between the field and CANOE
predictions. This parametric study didn't give good agreement for
moment and thrust between field results and theoretical values.
6.2 RECOMMENDATIONS
Tape extensometer readings should be taken after each step of the loading to
eliminate the error caused in the deflection calculation because of the change of angle in the
the position transducer wire. Actual deflection is not two dimension as we assumed.
Attempts should be made to measure the three dimensional deflection in the future research
work.
145
Soil boring should be done exactly over the crown region to get good soil
parameters for the Duncan's soil model. Using multiaxial device and different stress paths
for the soil testing is recommended.
For finite element simulation of live load, a better method for converting the
concentrated load to line load should be used. A simpler technique is needed to model this
type of loads for plane strain analysis. Although it may be on the conservative side, it is
safer to use CANDE as a design tool for these type of structures. Analysis of this type of
structures using CANDE should be subjected to further research.
REFERENCES
1. Abdel-sayed, George, and Baidar Bakt (1982), "Analysis of live-load effects in soil
steel structures," Soil-structure interaction of subsurface conduits,Trans.Research Record 878, TRB, Washington, D.C., pp. 49-55.
146
2. Alan, F. Rauch (1990) "Experimental and numerical investigation of a deep-eorrugated
steel, box-type culvert." Thesis presented to Ohio University, Athens, Ohio, inpartial fulfillment of the requirements for the Degree of Master of Science in Civil
Engineering,June.
3. Beal, David B. (1982), "Field test of long-span aluminum culvert," Joum. ofGeotechnical Eng. Div., ASCE, Vol. 108, No.GT6, June, pp. 873-890.
4. Cary, Raymond L. (1986), "Inelastic flexural stability of corrugations," Durability,
strength, and analysis of culverts and tunneling machines, Trans. Research Record1087, TRB, Washington, D.C., pp 87-91
5. Chang, Ching S., Julio M. Espinoza, and Ernest T. Selig (1980), "Computer analysis
of Newton Creek culvert," Joum. of Geotechnical Eng. Div., ASCE, Vol. 106,No. GT5, May, pp.531-556.
6. Dessouki, A.K., and G.R. Monforton (1986), "Effect of soil failure on soil-steel
structures," Joum. of Geotechnical Eng., ASCE, Vol.112, No.5, May, pp.522-36.
7. Duncan, James M., Seed R. B., and Drawsky, R.H (1985) "Design of Corrugated
Metal Box Culverts," Trans. Research Record 1008,TRB,Washington D.C., pp 33-41.
8. Duncan, James M. (1979), "Behavior and design of long-span metal culverts," Joum.
of Geotechnical Eng. Div., ASCE, Vol. 105, No GT3, March, pp. 399-418.
9. Duncan, James M. (1980), "Hyperbolic stress-strain relationships," Proc. of theWorkshop on Limit Equilibrium, Plasticity, and Generalized Stress-Strain in
Geotechnical Engineering, ASCE, New York, May, pp. 443-60.
10. Duncan, J.M., and C.~Chang (1970), "Nonlinear analysis of stress and strain in
soils," Joum. of Soil Mechanics and Foundations Div.,ASCE, Vol.96, No.SM5,
September, pp. 1629-53. 147
11. Duncan,J.M., Byrne,P., Wong, K.S., and Mabry, P., "Strength, Stress-Strain and
Bulk Modulus Parameters of Finite Element Analysis and Movements in Soil Masses",
Report No. UCB/GT/80-01, University of California, Berkeley, 70pp, August 1980.
12. Ghobrial, Medhat, and George Abdel-Sayed (1985), "Inelastic buckling of soil-steel
structures," Culverts: analysis of soil-culvert interaction and design, Trans.
Research Record 1008, TRB, Washington, D.C., pp. 7-14.
13. Katona, M.G., and J.M.Smith (1976), "CANDE user manual," Report No. RD-77-6,
Fed. Highway Adrnin., Washington, D.C., October.
14. Katona, M.G., J.M. Smith, R.S.Odello, and J.R. Allgood (1976), "CANDE: amodern approach for the structural design and analysis of
buried culverts," Report No. FHWA-RD-77-5, Fed. Highway
Admin.., Washington, D.C., October.
15. Kondner, R.L. (1963), "Hyperbolic stress-strain response: cohesive soils," Jour. of
the Soil Mechanics and Foundations Div., ASCE, Vol 89, No. 8M1, February, pp.115-143.
16. Meyerhof, G.G., and Baikie, L.D., "Strength of steel culvert sheets bearing against
compacted sand backfill."
17. Seed, R.B., and J.R.Raines (1988), "Failure of flexible long-span culverts under
exceptional live loads," Presented at 67th Annual Meeting of the TRB, Washington,
D.C.,pp. 37-45.
18. Selig, Ernest T., and Samuel C.Musser (1985), "Performance evaluation of a ribreinforced culvert," Culverts: analysis of soil-eulvert interaction and design, Trans.
Research Record 1008, TRB, Washington, D.C., pp. 117-122.
19. Wong, K.S., and J.M. Duncan (1974), "Hyperbolic stress-strain parameters for
nonlinear finite element analyses of stresses and movement in soil masses," Report
No. TE 74-3, University of California, Berkeley, July.