analysis of a pipe arch culvert subjected to exceptional live loaiy

161
z9 5" :1 5'1 / AND NUMERICAL ANALYSIS OF A PIPE ARCH CULVERT SUBJECTED TO EXCEPTIONAL LIVE LOAIY A Thesis Presented to The Faculty of the College of Engineering and Technology Ohio University Athens, Ohio In Partial Fulfillment of the Requirements for the Degree Master of Science in Civil Engineering by Devarajan March, 1992

Upload: others

Post on 11-Sep-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: analysis of a pipe arch culvert subjected to exceptional live loaiy

z9~y q~5" :1 5'1/

~XPERIMENTAL AND NUMERICAL

ANALYSIS OF A PIPE ARCH CULVERT SUBJECTED

TO EXCEPTIONAL LIVE LOAIY

A Thesis Presented to

The Faculty of the College of Engineering and Technology

Ohio University

Athens, Ohio

In Partial Fulfillment

of the Requirementsfor the Degree

Master of Science in Civil Engineering

by

Devarajan ~helliat;'

March, 1992

Page 2: analysis of a pipe arch culvert subjected to exceptional live loaiy

This thesis has been approved

for the Department of Civil Engineering

and the College of

Engineering and Technology

Russ Professertif Civil Enginee

Dean of the College of

Engineering and Technology

11

Angela McCutcheon
Text Box
a
Angela McCutcheon
Text Box
a
Angela McCutcheon
Text Box
a
Page 3: analysis of a pipe arch culvert subjected to exceptional live loaiy

ABSTRACT

A full-scale field test was conducted to determine the response of a corrugated

metal pipe arch culvert for the exceptional live load. The design span and rise of the culvert

were 15 feet 8 inches and 9 feet 6 inches respectively. The cover for the first and second

day of testing were approximately 7.5 feet and 3 feet respectively. Position transducer and

strain gage techniques were used to measure the deflection and strains. Data was collected

by using computer controlled data acquisition system. A tape extensometer was used to

determine the shape of the culvert before and after the testing. Exceptional live load was

applied through the two seven inch diameter piston rod hydraulic cylinders. They had a

capacity of 230 tons and connected to a hydraulic control unit for simultaneous operation.

A total of three loading sequences were applied, one on the first day and two on the

second day.

The ultimate load carrying capacity of this type of culvert under 3 feet cover was

determined to be 100 tons approximately. Maximum vertical deflection of 6.989 inches

occured at the crown point during the third loading sequence. During the first sequence the

magnitude of moment and thrust was insignificant. In the first loading sequence symmetric

nature prevailed in the culvert response. No section exceeded its ultimate moment capacity

of 3.745 kips-ft/ft, During the second and third loading sequences of only section four

exceeded its plastic moment capacity and formed a plastic hinge. The formation of creases

at both sides of the instrumented section were reported. The slip occured at a bolted

connection near to the crown was also reported.

A numerical analysis was done using the CANDE finite element program.

Parameters for Duncan's hyperbolic model were derived from the triaxial tests conducted

using the undisturbed soil samples from the field. The numerical predictions were

compared with the field response. Although the magnitude didn't agree well an identical

trend was observed between the numerical simulations and the field results.

iii

Page 4: analysis of a pipe arch culvert subjected to exceptional live loaiy

ACKNOWLEDGEMENTS

I would like to express my sincere appreciation and gratitude to Dr. Shad M. Sargand

for his instructive guidance and supervision that made this research work possible. I would

also like to thank him for supporting me during my entire stay in Athens.

I would like to thank Dr. Glenn A. Hazen for his helpful suggestions and constructive

criticism. I am deeply indebted to Mr. Teruhisa Masada for the long hours of tireless work

that he put in from the beginning to the end of this project.

I am also grateful to all the students and technicians who were responsible for the

experimental set-up and data acquisition.

Funding for this project was provided through a research grant from the Ohio

Department of Transportation.

IV

Page 5: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE OF CONTENTS

Abstract iii

Acknowledgements iv

Table of Contents v

List of Tables ~ vii i

· f F' ·LIst 0 igures IX

Chapter 1

INTRODUCTION

1.1 GENERAL STATEMENT 1

1.2 OBJECTIVES 2

1.3 OUTLINE OF RESEARCH 2

1.4 ~I11ERA~~V~~ 3

Chapter 2

PIPE ARCH CULVERT AND FIELD INSTRUMENTATION

2.1 GENERAL 6

2.2 DESCRIPTION OF PIPE ARCH CULVERT AND BACKFILL

~TERIAL 7

2.3 ~IVE~OADAPPLICATION SYSTEM I0

2.4 FIELD INSTRUMENTATION OF PIPE ARCH CULVERT 17

v

Page 6: analysis of a pipe arch culvert subjected to exceptional live loaiy

Chapter 3

MEASUREMENT OF CULVERT DEFORMATION

3.1 OVERVIEW OF DEFORMATION MEASUREMENT 24

3.2 TAPE EXTENSOMETER MEASUREMENTS 24

3.3 POSITION TRANSDUCER MEASUREMENTS 30

3.4 DISCUSSION 64

Chapter 4

MEASUREMENT OF PLATE FORCES

4.1 INTRODUCTION 66

4.2 REDUCfION OF STRAINS TO AXIAL THRUST AND BENDING

MOMENf 66

4.3 ANALYSIS OF RESULTS 68

4.4 PLASTIC MOMENT CAPACI1'Y 107

4.5 FORMATION OF PLASTIC HINGES AND CREASES I07

Chapter 5

FINITE ELEMENT ANALYSIS

5.1 INTRODUCTION 114

5.2 CANDE BACKGROUND 115

5.2.1 SOLUTION LEVEL 115

5.2.2 PIPE TyPES 115

5.2.3 ELEMENT TyPES 116

5.2.4 SOIL MODEL 116

vi

Page 7: analysis of a pipe arch culvert subjected to exceptional live loaiy

5.3 FIELD SOIL SAMPLING WORK 116

5.4 lABORATORY SOIL TESTING METHOD ll?

5.5 RECOMMENDED SOIL PARAMETERS 119

5.6 FINITE ELEMENT SIMULATION 119

5.7 DISCUSSION 128

Chapter 6

CONCLUSIONS AND RECOMMENDATIONS

6.1 SUMMARY AND CONCLUSIONS 143

6.2 RECOMMENDATIONS 144

REFERENCES 146

vii

Page 8: analysis of a pipe arch culvert subjected to exceptional live loaiy

LIST OF TABLES

Chapter 2

Table 2.1 Characteristics of pipe arch culverts 9

Table 2.2 Soil boring data for test hole #1 11

Table 2.3 Soil boring data for test hole #2 12

Table 2.4 Live load application-First day l 7

Table 2.5 Live load application-Second day 18

Chapter 3

Table 3.1 Results of initial triangulation measurements 27

Table 3.2 Results of final triangulation measurements 28

Table 3.3 Initial tape measurement data 32

Table 3.4 Final tape measurement data 33

Table 3.5 Co-ordinates of position transducer wire at it's base 35

Table 3.6 Change of angle on position transducer wire during the experiment. .. 36

Chapter 4

Table 4.1 Computed axial thrust 70

Table 4.2 Computed bending moment 71

Table 4.3 Yield stress reached during failure tests 11()

Table 4.4 Location and length of creases detected 111

Chapter 5

Table 5.1 Basic information on triaxial tests 118

Table 5.2 Duncan's hyperbolic soil model parameters 120

Table 5.3 A summary of material parameters 121

Table 5.4 Load factor (K4) for various cover depths and loading conditions 124

viii

Page 9: analysis of a pipe arch culvert subjected to exceptional live loaiy

Chapter 2

Figure 2.1

Figure 2.2

Figure 2.3

Figure 2.4

Figure 2.5

Figure 2.6

Figure 2.7

Chapter 3

Figure 3.1

Figure 3.2

Figure 3.3

Figure 3.4

Figure 3.5

Figure 3.6

Figure 3.7

Figure 3.8

Figure 3.9

Figure 3.10

Figure 3.11

Figure 3.12

Figure 3.13

Figure 3.14

Figure 3.15

Figure 3.16

LIST OF FIGURES

Geometry of pipe arch culvert 8

Locations of test soil borings 10

Live load application system (view parallel to roadway) 13

Live load application system (view perpendicular to roadway) 14

Field picture of live load system 15

System used for cross-sectional shape and deflection

measurements 20

Typical installation of biaxial strain gages 22

Measurements for cross-sectional shape determination 25

Final cross-sectional shape at center location 29

Types of tape measurements taken 31

Deflection of monitoring point #1 during first load sequence ~37

Deflection of monitoring point #2 during first load sequence 38

Deflection of monitoring point #3 during first load sequence 39

Deflection of monitoring point #4 during first load sequence 40

Deflection of monitoring point #5 during first load sequence 41

Deflection of monitoring point #6 during first load sequence 42

Deflection of monitoring point #7 during first load sequence 43

Deflection of monitoring point #8 during first load sequence 44

Deflection of monitoring point #9 during first load sequence 45

Deflection of monitoring point #1 during second load sequence 46

Deflection of monitoring point #2 during second load sequence 47

Deflection of monitoring point #3 during second load sequence 48

Deflection of monitoring point #4 during second load sequence 49

ix

Page 10: analysis of a pipe arch culvert subjected to exceptional live loaiy

Figure 3.17

Figure 3.18

Figure 3.19

Figure 3.20

Figure 3.21

Figure 3.22

Figure 3.23

Figure 3.24

Figure 3.25

Figure 3.26

Figure 3.27

Figure 3.28

Figure 3.29

Figure 3.30

Chapter 4

Figure 4.1

Figure 4.2

Figure 4.3

Figure 4.4

Figure 4.5

Figure 4.6

Figure 4.7

Deflection of monitoring point #5 during second load sequence 50

Deflection of monitoring point #6 during second load sequence 51

Deflection of monitoring point #7 during second load sequence 52

Deflection of monitoring point #8 during second load sequence 53

Deflection of monitoring point #9 during second load sequence 54

Deflection of monitoring point #1 during third load sequence 55

Deflection of monitoring point #2 during third load sequence 56

Deflection of monitoring point #3 during third load sequence 57

Deflection of monitoring point #4 during third load sequence 58

Deflection of monitoring point #5 during third load sequence 59

Deflection of monitoring point #6 during third load sequence 60

Deflection of monitoring point #7 during third load sequence 61

Deflection of monitoring point #8 during third load sequence 62

Deflection of monitoring point #9 during third load sequence 63

Definition of distances c1 and c2 taken from neutral axis 69

Distributions of thrust and moment under load of 69.27 tons

during first loading sequence 72

Distributions of thrust and moment under load of 86.59 tons

during first loading sequence 73

Distributions of thrust and moment under load of 100.06 tons

during first loading seq uence 74

Distributions of thrust and moment under load of 107.76 tons

during first loading sequence 75

Distributions of thrust and moment under load of 115.45 tons

during first loading sequence 76

Distributions of thrust and moment under load of 123.15 tons

x

Page 11: analysis of a pipe arch culvert subjected to exceptional live loaiy

during first loading sequence 77

Figure 4.8 Distributions of thrust and moment under load of 30.79 tons

during second loading sequence 78

Figure 4.9 Distributions of thrust and moment under load of 38.48 tons

during second loading sequence 79

Figure 4.10 Distributions of thrust and moment under load of 50.03 tons

during second loading sequence 80

Figure 4.11 Distributions of thrust and moment under load of 65.43 tons

during second loading sequence 81

Figure 4.12 Distributions of thrust and moment under load of 78.89 tons

during second loading sequence 82

Figure 4.13 Distributions of thrust and moment under load of 88.51 tons

during second loading sequence 83

Figure 4.14 Distributions of thrust and moment under load of 101.6 tons

during second loading sequence 84

Figure 4.15 Distributions of thrust and moment under load of 103.91 tons

during second loading sequence 85

Figure 4.16 Distributions of thrust and moment under load of 111.6 tons

during second loading sequence 86

Figure 4.17 Distributions of thrust and moment under load of 113.9 tons

during second loading sequence 87

Figure 4.18 Distributions of thrust and moment under load of 50.03 tons

during third loading sequence 88

Figure 4.19 Distributions of thrust and moment under load of 57.73 tons

during third loading sequence 89

Figure 4.20 Distributions of thrust and moment under load of 80.81 tons

during third loading sequence 90

Figure 4.21 Distributions of thrust and moment under load of 100.1 tons

xi

Page 12: analysis of a pipe arch culvert subjected to exceptional live loaiy

during third loading sequence 91

Figure 4.22 Distributions of thrust and moment under load of 107.8 tons

during third loading sequence 92

Figure 4.23 Distributions of thrust and moment under load of 115.5 tons

during third loading sequence 93

Figure 4.24 Thrust vs load plots for second and third loading sequences

at point. #1 94

Figure 4.25 Moment vs load plots for second and third loading sequences

at point #1 95

Figure 4.26 Thrust vs load plots for second and third loading sequences

at section #4 96

Figure 4.27 Moment vs load plots for second and third loading sequences

at point #4 97

Figure 4.28 Thrust vs load plots for second and third loading sequences

at point #5 98

Figure 4.29 Moment vs load plots for second and third loading sequences

at point #5 99

Figure 4.30 Thrust vs load plots for second and third loading sequences

at point #6 100

Figure 4.31 Moment vs load plots for second and third loading sequences

at point #6 101

Figure 4.32 Thrust vs load plots for second and third loading sequences

at point #9 102

Figure 4.33 Moment vs load plots for second and third loading sequences

at point #9 103

Figure 4.34 Failure mode of bolted crown plates under load 106

Figure 4.35 Formation of plastic hinges 109

Figure 4.36 Measurements taken to locate creases 112

xii

Page 13: analysis of a pipe arch culvert subjected to exceptional live loaiy

Chapter 5

Figure 5.1

Figure 5.2

Figure 5.3

Figure 5.4

Node numbering system used for the half mesh 122

Various material zones defined for simulation #3 126

various material zones defined for simulation #5 127

Comparison of deflection of monitoring point #5 between

field results and various CANDE program simulations 129

Figure 5.5 Comparison of deflection of monitoring point #6 between

field results and various CANDE program simulations 130

Figure 5.6 Comparison of deflection of monitoring point #7 between

field results and various CANDE program simulations 131

Figure 5.7 Comparison of deflection of monitoring point #8 between

field results and various CANDE program simulations 132

Figure 5.8 Comparison of deflection of monitoring point #9 between

field results and various CANDE program simulations 133

Figure 5.9 Comparison of thrust due to 30.79 ton load between

field result and various CANDE simulations 134

Figure 5.10 Comparison of moment due to 30.79 ton load between

field result and various CANDE simulations 135

Figure 5.11 Comparison of thrust due to 38.48 ton load between

field result and various CANDE simulations 136

Figure 5.12 Comparison of moment due to 38.48 ton load between

field result and various CANDE simulations 137

Figure 5.13 Comparison of thrust due to 50.03 ton load between

field result and various CANDE simulations 138

Figure 5.14 Comparison of moment due to 50.03 ton load between

field result and various CANDE simulations 139

Figure 5.15 Comparison of thrust due to 65.43 ton load between

xiii

Page 14: analysis of a pipe arch culvert subjected to exceptional live loaiy

field result and various CANDE simulations 140

Figure 5.16 Comparison of moment due to 65.43 ton load between

field result and various CANDE simulations 141

XIV

Page 15: analysis of a pipe arch culvert subjected to exceptional live loaiy

CHAPTER 1

INTRODUCTION

1.1 GENERl\L S'lAl~El\1ENT

Corrugated metal buried conduits have been used as drainage structures for many

years and, especially in the past two decades as short-span bridge substitutes. The reasons

for this development are light weight, lower material cost, relatively easy handling and

installation procedures. These structures other than the very smallest, are constructed by

bolting together curved, corrugated metal plates. One of the most popular type of

corrugated metal pipes (CMPs) has been the corrugated steel pipe arch culvert. The pipe

arch culverts do not require concrete footings and are advantageous over some other CMPs

where head room is limited and hydraulic capacity is demanded.

In the last two decades, there have been many investigations dealing with the

analysis and design of corrugated steel culverts [2,5,7,8,17,18]. Laboratory testing, field

testing, and analytical methods have been utilized. Most of these reported studies are

related to the performance of culverts under various backfill and under normal live-load

conditions. However, very few investigations have been focused on the maximum load

carrying capacity and the failure mechanism of these soil-structure systems. This is because

a full-scale field failure test of a culvert is generally costly, time consuming, and presents

problems to the construction plan and/or local traffic conditions.

The strength of a culvert depends on properties of backfill material, plate and soil­

structure interaction. There is limited Information on the amount of deflection, shape of

deformation and live-load capacity of these culverts before full or partial failure occurs. For

more rational design, it is very important to inquire into possible failure mechanisms.

Page 16: analysis of a pipe arch culvert subjected to exceptional live loaiy

1.2 OBJECTIVES

The objectives of the investigation were as follows:

a) To determine the maximum moment capacity of the pipe arch culvert.

b) To define the collapse mechanism.

c) To identify critical sections on the geometry of the pipe arch culvert.

d) To evaluate the load-deflection relation of the pipe arch culvert under

exceptionally large live loads.

e) To compare the measured ultimate moment capacity with AASHTO

design guidelines and with CANDE Finite Element Method

predictions.

1.3 ()UTLINE OF RESEARCII

In 1989, the Ohio Department of Transportation (ODOT) made a decision, after a

careful hydrologic and hydraulic evaluation, to remove a large span pipe arch culvert

structure identified as MER-707-1703, which had been existing under State Route 707,

near the north limit of the village of Mendon in Mercer county, Ohio. This pipe was

originally installed in 1953 as an overflow structure, for a nearby short span bridge

structure, MER-707-1697, over St. Mary's river. On September 24 and 26, 1990, a

research group from Ohio University took full advantage of this unique situation and

conducted one of the first comprehensive full-scale field failure testing of the pipe arch

culvert structure.

This thesis presents details of the findings of previous investigations on failure of

culverts, descriptions of the pipe arch culvert structure tested, field instrumentation

methods utilized, related background theory and design guidelines, experimental results,

CANDE Finite Element Analysis and the conclusions drawn.

Chapter two describes in detail the information regarding the geometry of the

2

Page 17: analysis of a pipe arch culvert subjected to exceptional live loaiy

corrugated steel pipe arch culvert structure and its surrounding subsurface conditions in the

field. This chapter also presents the concept and descriptions of the field instrumentation

and live-load application methods used to fulfill the objectives of the investigation.

Chapter three presents necessary background information utilized in the analysis of

the field data for deflection. It also provides the field measured data which were obtained

before, during"and after the testing. Field measurements of initial and fmal geometry of the

pipe arch culvert are presented.

Chapter four presents necessary theory utilized for analysis of strain gage data and

the results obtained. Bending moments and thrusts are computed and presented for the

corresponding loading conditions. Locations of plastic hinges and creases observed in the

field are also reported here.

Chapter five gives details about the laboratory testing of backfill material. It also

represents the calculated soil model parameters for the CANDE finite element analysis. It

explains the numerical analysis of the pipe arch culvert/soil system using the CANDE

computer program. Predictions of the CANDE program are presented, in terms of

deformations, thrusts, and moments, in correlation with the measured field values.

And, finally Chapter six presents the summary of the results and conclusions drawn

from this investigation.

1 .4 LITERA1'URE REVIEW

The corrugated steel culvert has been increasingly subjected to investigation during

the last two decades. Mayerhof and Baikie [16] as part of their study investigated the

strength of corrugated metal culverts under fills.

From this investigation they concluded that for small values of the co-efficient of

3

Page 18: analysis of a pipe arch culvert subjected to exceptional live loaiy

soil reaction or modulus of deformation of the soil, and for small values of the flexural

rigidity of the plates, the sheets would fail by buckling, but for larger values of these

parameters the sheets would fail by yielding of the section. The observed ultimate loads and

modes of failure of the sheets were in reasonable agreement with these estimates and also

support the ring compression theory.

Buckling of culvert structures was studied by Ghobrial and Abdel-Sayed [12]. In

their study of this phenomenon, they considered the formation of plastic hinges in the

culvert walls. They observed sudden snap-through failure for large spans and shallow

cover conditions. Short span culverts with deep soil cover did not exhibit this response but

experienced increasing displacements after each load step. In addition, the first plastic hinge

formed at the crown. The formation of the second plastic hinge was observed farther away

from the crown.

Duncan [8] after an extensive study suggested controlling the factor of safety

against formation of a plastic hinge as a design requirement for flexible culverts with

shallow fill, and has given three reasons why structural collapse will not occur at this point:

1) Multiple plastic hinges are required to form a collapse mechanism.

2) The soil will restrain deformations after formation of a mechanism.

3) The design estimates are based on minimum values of yield stress.

Selig and Musser [18] rated the performance of a rib reinforced, long-span culvert

by field tests and a limited finite element analysis. Results were compared with current

design practice. They concluded that rib stiffeners decrease deflections, increase moments,

and do not affect thrusts. Reinforcing ribs increase the factor of safety against plastic hinge

formation.

Cary [4] examined the inelastic flexural stability of corrugations. He investigated

the local stability of are-and-tangent corrugated profiles when subjected to moments in the

4

Page 19: analysis of a pipe arch culvert subjected to exceptional live loaiy

5

inelastic range. Twenty four flexural tests were used to obtain empirical expressions. The

expressions related design variables, corrugation dimensions, minimum curvature radius,

maximum moment capacity, and critical buckling strain. Results show that as the radius of

curvature to thickness ratio increases the strain at which buckling occurs reduces.

Seed and Rains r171 analyzed three full-scale field case studies involving failure of

flexible long span culvert structures due to inadvertent application of exceptional live loads.

Each case was simulated using nonlinear finite element analysis methods with a modified

Duncan and Drawsky procedure to develop equivalent line loads. Their numerical results

indicate that the nonlinear finite element analysis can provide excellent agreement with

observed field behavior, in terms of not only failure conditions but also locations of plastic

hinge formation.

Dessouki A.K. and Monforton G.R. [6] used a plane strain finite element analysis

procedure to determine the effect of soil failure on soil-steel structures. They used

hyperbolic soil model to represent the interface element and the soil elements far from the

structure. An elasto-plastic model represented the soil behavior in the severely stressed

regions. They reported good agreement between the model tests they conducted in the

laboratory and the analytical results. Their investigation clearly indicated the significant

effect on the load carrying capacity of the soil-steel structure due to soil failure.

In all of the above investigations, full-sized culverts were not instrumented and

loaded to failure to determine their actual ultimate moment capacity, load-deflection relation,

and influence of soil-structure interaction.

Page 20: analysis of a pipe arch culvert subjected to exceptional live loaiy

CHAPTER 2

PIPE ARCH CULVERT AND FIELD INSTRUMENTATION

2.1 GENERAL

The details of the history, general information and geometrical characteristics of the

culvert, results of the subsurface boring work performed close to the culvert, methods of

instrumentation, and live load application system for the pipe arch culvert tested for failure

are presented in this chapter.

In order to meet the objectives outlined in chapter one, it was necessary to develop a

system which could simulate exceptional vehicular live load to the culvert and to instrument

the pipe to obtain deflection, moment and thrust measurements before and during the full

scale field failure test. Two large-capacity hydraulic cylinders, connected in parallel, were

set over the culvert and extended against a dead load, consisting of more than forty 2.2 ton

concrete blocks placed on top of a steel I-beam frame, to achieve application of exceptional

live load. In oder to obtain deflection data, position transducers were attached to a reference

truss structure erected inside the culvert, and transducer's wires were connected to selected

points on the inside perimeter of the culvert. Movement of the reference truss structure was

monitored with the conventional level surveying technique to single out true deflections of

the pipe. Measurements of moment and thrust were made using electric strain gages. An

assumption was made that effects of exceptional live load would be significant mostly in a

cross section under the loading points (plain stress). Therefore, a mid-length plane section

along the longitudinal axis of the culvert was chosen to establish instrumentation and to

apply live load. A tape extensometer was used to establish the initial and final cross­

sectional shapes of the selected mid-section of the culvert.

To perform realistic CANDE numerical simulation of the culvert, a knowledge of

the vertical profile of the surrounding subsurface conditions and the stress-strain relations

Page 21: analysis of a pipe arch culvert subjected to exceptional live loaiy

of backfill material is required. This information was obtained by performing subsurface

exploration work at two locations next to the culvert structure on the day of testing.

2 .2 DESCRIPTION OF PIPE ARCH CULVERT AND BACKFILL

l\1ATERIAL

The pipe arch culvert (MER-707-1703), the main subject of the investigation, was

installed in 1953, parallel to St. Marys River at an appropriate distance of 400 feet, under

state route 707, near the north limit of the village of mendon in Mercer County, Ohio. The

culvert, situated in a flood plain, was designed as an overflow structure for a nearby short

span bridge structure (MER-707-1697) and supposed to have a minimum safe load capacity

ofS-15.

The design span and rise dimensions for the culvert were 15 feet-8 inches and 9

feet-6 inches respectively. Figure 2.1 illustrates the geometry of the pipe arch culvert. The

contract document stated that a maximum of 1 inch tolerance was permitted on nominal

span and rise dimensions. The steel structural plates for the culvert had #7 gage thickness

for the top section and #5 gage thickness for the corner and bottom sections. Corrugation

pattern was defined by a pitch of 6 inches and a depth of 2 inches. Table 2.1 summarizes

the geometrical characteristics of the pipe arch culvert. Backfill material used during

construction was a typical cohesive earth material available locally. According to a record

dated 1955, the vertical profile surrounding the culvert included a 2 inch asphalt concrete

layer and 33.5 foot wide, 7.4 foot thick fill above the culvert crown. The culvert was

installed perpendicular to the centerline of the road, and it had a total length of 86 feet and a

grade of 0.0%. No stiffeners were attached to the culvert structure during its construction.

On September 24,1990 just before the first loading, a drilling rig equipped with a

rotary auger was utilized to obtain detailed subsurface soil data at two locations within the

shoulder section of the roadway one on each side, near the west end of the culvert.

7

Page 22: analysis of a pipe arch culvert subjected to exceptional live loaiy

<LI Elev. 814.70Ft.

8

I...

I

Roadway~mbankment

ConcreteHeadwall

Elev. 798.00 Ft.0.00%

86.0 Ft.

(a) GeneralSide View

S an 15Ft, - 8 In.

(b) General Cross-Sectional View

, ,

c~

~~\C)

..J ..:tt.. u,r-- 0'\

ve",

~

, , , , , , ,

Figure 2.1 Geometry of Pipe Arch Culvert

Page 23: analysis of a pipe arch culvert subjected to exceptional live loaiy

Table 2.1 Characteristics of Pipe Arch Culvert

Type Corrugated Steel

Design Span 15 feet - 8 inches

Design Rise 9 feet - 6 inches

Length 86 feet

Height of Cover Over Crown 7 feet - 5 inches

Corrugation Pitch 6 inches

Corrugation Depth 2 inches

Plate Thickness:Above Springline 0.188 inch (Galvanized)

Plate Thickness:0.218 inch (Galvanized)Below Springline

Section Area of Plate 2.739 in;1ft.

~ornentoflnertia 1.296 in~1ft.

Section Modulus 1.187 in~1ft.

Radius of Gyration 0.688 inch

9

Page 24: analysis of a pipe arch culvert subjected to exceptional live loaiy

10

Locations of the boreholes with respect to the culvert structure are shown in fig 2.2. These

borings were extended down to a depth of approximately 3 feet below the bottom invert of

the culvert. A 18 inch length split spoon sampler was used and the SPT values were

recorded. Soil samples were placed in seal-tight containers and transported to the Ohio

DOT soil laboratory for analysis. Tables 2.2 and 2.3 provide a summery of the data

obtained from the two test borings and results of the laboratory soil tests. The backfill

material encountered in the bore holes are regarded as a stiff to very stiff silty clay with

varying amounts of sand and gravel. In addition to the soil boring work, the thickness of

the asphalt concrete layer was measured after the first sequence of loading, and it was

determined to be 16 inches. It is apparent that the Ohio DOT bridge maintenance has placed

several layers of asphalt concrete, since the culvert has been developing a moderate amount

of sagging which results in a minor dip/cracking on the asphalt pavement surface.

2 .3 LI"E LOAD APPLICATION SYSTEM

In this investigation, it was necessary to apply exceptional live load, simulating the

rear axle of a heavy vehicle. The traditional concept of pressing against a large dead load,

often used in the pile load test procedure, was chosen to achieve this goal. Figures 2.3 and

2.4 illustrate the overall setting, .and figure 2.5 presents actual pictures of the loading

system taken in the field. First, two 4 feet by 8 feet pedestals, made up with concrete

blocks and guard rail posts, were set on the roadway surface at a 36 foot spacing from

center to center, across the culvert structure. A 6 to 8 inch thick well compacted sandy

material layer was placed under the pedestals to smooth out the roadway surface slopes and

to keep the pedestals vertical. A steel I-beam frame was constructed by welding eight 5

foot long 12 x 65 H piles at a 5 foot spacing between two 40 foot long W36 x 182 beams.

Web stiffeners 1/2 inch thick were attached to these I beams at the mid-span. This frame

was laid atop across the pedestals. Concrete blocks (or jersey barriers), each weighing

about 2.2 tons, were lifted by a crane and placed over the I-beams. On the first day of

testing (sept 24, 1990), a total of 45 jersey barriers were piled in three layers-20 in the first

layer, 15 in the second layer, and 10 in the third layer. On the second day of testing (Sept

Page 25: analysis of a pipe arch culvert subjected to exceptional live loaiy

11

N

4State Route 707-, CL•

c c 2 12 1 ....... 9 0 ................ ... .,.."'lllIlIlI o u

u uen CI')

I

#21

",*,

~ ~-~-- - - - - - - - - - - - - - -

18.5' Pipe ArchCulvert

~ ,- #1---- --. - - - ---- -."¥'

II

2 1 ....... ~~ .... 2 10 u

"'lllIlIlI ""0 ""0I.....:; :;

0 0.c .cen en

Figure 2.2 Locations of Test Soil Borings

Page 26: analysis of a pipe arch culvert subjected to exceptional live loaiy

Tab

le2.

2So

ilB

orin

gD

ata

For

Tes

tH

ole

#1

Ele

v.D

epth

SP

TM

ater

ial

Des

crip

tion

Phy

sica

lC

hara

cter

isti

csS

HT

LL

.LP.

I.W

.C.

(Ft.

)(F

t.)V

alue

Cla

ss%

Ag

g%

C.S

.%

F.S.

%Si

lt%

Cla

y

814.

20

.0-

Top

of

Ber

mS

houl

der

Sec

tion

--

--

--

--

--

-H1

2 .2

~:~=

11.7

-4/

8/8

Bro

wn

San

dyC

lay

07

1337

4331

1216

A-6

A

809.

25

.0- -

2/4/

5B

row

nA

ndG

ray

San

dyC

lay

126

1131

4033

1219

A-6

A-

806.

77.

5- -

3/5/

8B

row

nA

ndG

ray

San

dyC

lay

08

1436

4233

1418

A-6

A80

4.2

10

.0- -

4/5/

9B

row

nA

ndG

ray

San

dy

-G

rave

lly

Cla

y18

510

2740

3312

20A

-6A

801.

712

.5- -

4n

/12

Bro

wn

And

Gra

yS

andy

Cla

y8

511

3046

3413

19A

-6A

799.

21

5.0

- -5/

8/15

Gra

yS

ilty

Cla

y5

210

4934

4518

26A

-7-6

-79

6.7

17.5

_4/

9/13

Gra

yG

rave

lly

Cla

y17

37

3142

4616

27A

-7-5

795.

219

.0-

Bot

tom

of

Bor

ing

........

tv

Page 27: analysis of a pipe arch culvert subjected to exceptional live loaiy

Tab

le2.

3So

ilB

orin

gD

ata

For

Tes

tI-

Iole

#2

Ele

v.D

epth

SP

TM

ater

ial

Des

crip

tion

Phy

sica

lC

hara

cter

isti

csS

HT

LL

.LP.

I.W

.C.

(Ft.

)(F

t.)

Val

ueC

lass

%A

gg

%C

.S.

%F

.S.

%S

ilt

%C

lay

813.

80

.0-

Top

of

Ber

mS

houl

der

Sec

tion

--

--

--

--

-81

2.8

1.0

--

-81

1.3

2.5

_ -3/

4/5

Bro

wn

San

dyC

lay

86

1234

4031

1117

A-6

A

808.

85

.0- -

3/4/

5B

row

nA

nd

Gra

yS

andy

Cla

y9

612

3439

3111

18A

-6A

-80

6.3

7.5

_ -3/

6/9

Bro

wn

San

dyC

lay

75

1233

4333

1317

A-6

A8{

)3.8

10

.0- -

3/5n

Gra

yS

ilty

Cla

y-

44

1132

4938

1720

A-6

B80

1.3

12.5

_ -3/

6/9

Gra

yS

iltA

ndC

lay

0S

1235

4835

1521

A-6

A79

8.8

15

.0- -

5/1

Sn

.G

ray

Sil

tyG

rave

lly

San

d22

3113

1915

NP

NP

24A

-2-4

-79

6.3

17.5

_sn

»B

row

nA

nd

Gra

yS

ilty

Cla

y0

015

4240

2022

A-7

-643

794.

81

9.0

-B

otto

mo

fB

orin

g

~ (Jo,

)

Page 28: analysis of a pipe arch culvert subjected to exceptional live loaiy

14

40Ft

arriers

I-beam Frame

Backfill Soil

FIGURE 2.3 LIVE LOAD APPLICAnON SYSTEM(VIEWPA~ELL TO ROADWAY)

Page 29: analysis of a pipe arch culvert subjected to exceptional live loaiy

Hyd

raul

icC

ylin

ders A

spha

ltC

oncr

ete

Lay

er

Top

Cen

terl

ine

ofPi

peA

rch

Cul

vert

FIG

UR

E2.

4L

IVE

LO

AD

AP

PL

ICA

TIO

NS

YS

TE

M(V

IEW

PE

RP

EN

DIC

UL

AR

TO

RO

AD

WA

Y)

~ Ul

Page 30: analysis of a pipe arch culvert subjected to exceptional live loaiy

16

Page 31: analysis of a pipe arch culvert subjected to exceptional live loaiy

17

26, 1990), the number was increased to 53, placed in four layers. Under the web-stiffened

I-beam sections, two 14 inch bore, 24 inch stroke, 7 inch diameter piston rod hydraulic

cylinders were set 5 feet apart to simulate the rear axle load. Both cylinders had a capacity

of 230 tons, and they were connected to a hydraulic control unit for simultaneous

operation.

The testing was conducted in the field under two different subsurface conditions.

On the first day of testing ( Sept. 24, 1990), the hydraulic cylinders were placed on top of

the existing asphalt pavement layer, and pressure of up to 800 psi was developed in each

cylinder. On the second day of testing (Sept. 26, 1990), the asphalt material layer was

completely removed as well as some portion of the cohesive backfill material, so that there

would be only 3 feet of soil cover between the crown point and the bottom of the hydraulic

cylinders. Two cycles of monotonically increasing large live load was applied on the

second day, since the total stroke was almost used up during the first cycle. Tables 2.4 and

2.5 summarize the actual sequence of load application which took place on these two

testing days. Each load increment was maintained approximately 15 to 20 minutes before

the next load was applied, since the data acquisition system required that amount of time to

sweep through all the (forty two) strain gage channels, readout outputs from the nine

position transducers, and to print out hard copies of the data.

2.4 FIELD INSTRmlENTATION .OF PIPE ARCH CULVERT

Cross-sectional Shape Measurement

The initial and final shapes of the culvert's cross section at the center location are

determined by the technique called the "triangulation method". Details of the concept of this

method is provided in section 3.2. In this method, two ground reference points are

established at known locations inside the pipe, and distances are measured from these

reference points to each of the monitoring points installed on the inside culvert periphery.

The x, y coordinate values for each of the monitoring points are computed applying simple

Page 32: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 2.4 LIVE LOAD APPLICAnON - FIRST DAY(FIRST SEQUENCE OF LOADING)

Load Increment Total Live Load Applied (Tons)

1 JL 69.27 (= 450 psi in Each Cylinder)

2 86.59 (= 562.5 psi in Each Cylinder)

3 100.06 (= 650 psi in Each Cylinder)

4 107.76 (= 700 psi in Each Cylinder)

5 eo 115.45 (= 750 psi in Each Cylinder)c.....

6~

, 123.15 (= 800 psi in Each Cylinder)~

~7 c..-

107.76 (= 700 psi in Each Cylinder)0~o

8 c 123.15 (= 800 psi in Each Cylinder)~::s0-

9 ~ 123.15 (= 800 psi in Each Cylinder)en...VJ

10 '-- 123.15 (= 800 psi in Each Cylinder).....~

11 123.15 (= 800 psi in Each Cylinder)

12 123.15 (= 800 psi in Each Cylinder)

13 123.15 (= 800 psi in Each Cylinder)

14 123.15 (= 800 psi in Each Cylinder)

15,~ 123.15 (= 800 psi in Each Cylinder)

18

Page 33: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 2.5 LIVE LOAD APPLICATION - SECOND DAY(SECOND AND TIllRD SEQUENCES OF LOADING)

19

Load Increment Total Live Load Applied (Tons)

1

2

3

4

5

6

7

8

9

10

11

12

1

2

3

4

5

6

7

30.79 (= 200 psi in Each Cylinder)

38.48 (= 250 psi in Each Cylinder)

50.03 (= 325 psi in Each Cylinder)

65.43 (= 425 psi in Each Cylinder)

78.89 (= 512.5 psi in Each Cylinder)

88.51 (= 575 psi in Each Cylinder)

101.6 (= 660 psi in Each Cylinder)

103.91 (= 675 psi in Each Cylinder)

111.6 (= 725 psi in Each Cylinder)

101.6 (= 660 psi in Each Cylinder)

111.6 (= 725 psi in Each Cylinder)

113.9 (= 740 psi in Each Cylinder)

46.18 (= 300 psi in Each Cylinder)

57.73 (= 375 psi in Each Cylinder)

80.81 (= 525 psi in Each Cylinder)

100.06 (= 650 psi in Each Cylinder)

107.76 (= 700 psi in Each Cylinder)

115.46 (= 750 psi in Each Cylinder)

115.46 (= 750 psi in Each Cylinder)

Page 34: analysis of a pipe arch culvert subjected to exceptional live loaiy

20

principles of geometry. For the pipe arch culvert of concern, a total of nine monitoring

points were established by installing eyebolts directly onto the corrugated plates, within the

arc above the springline. The two ground reference points were established by installing

larger size eyebolts on the top surface of a concrete support constructed for the reference

truss structure (which was used to attach position transducers for deflection measurements

during the tests). The distances were then measured with an accuracy of plus or minus

0.005 inch, using a tape extensometer. Figure 2.6 presents a clear picture of the set-up. The

possible movements of the reference points were observed with the conventional level

surveying method. Independent of the above triangulation measurements, the Ohio DOT

engineers took detailed dimensions of the pipe arch, such as rise, span, top mid-ordinate,

top left and right chords and mid-ordinates, by stretching a cloth tape and/or a nylon string

at several sections along the longitudinal axis of the pipe,

Deflection Measurement

In this investigation, response of the culvert structure under the application of

exceptional live load was entirely unknown before the test. There was a need to develop a

deflection measurement system which would not require presence of any field personnel

inside the culvert and which could achieve a relatively rapid collection and storage of

deflection readings. After considering various options, it was decided to use constant­

tension wire type position transducers. Nine units of the 10 inch range position transducers

manufactured were utilized along with the data acquisition system. A minimum of nine

units were required since the deflection measurement would have to be obtained for the

nine monitoring points used for the cross-sectional shape measurement. It was assumed

that deflection of the pipe due to the live load would be primarily in the direction normal to

the surface of the plate, confmed within the two dimensional cross-sectional plane.

These position transducers were attached to a reference truss structure erected at the

mid-length section inside the culvert. The transducer wires were then extended carefully

and hooked to each of the nine monitoring eyebolts installed on the pipe. Figure 2.6 shows

Page 35: analysis of a pipe arch culvert subjected to exceptional live loaiy

£IIII

il!IIII!!!!II!il!I!!!!!I!I!!!I!!I!'IIlI!I!I!lili!I!III!1!!!I!!!!li'I!IIII!!I!!i!111

A, B = Ground Reference Points

FIGURE 2.6 SYSTEM USED FOR CROSS-SECI10NAL SHAPE ANDDEFLECI10N MEASUREMENTS

21

Page 36: analysis of a pipe arch culvert subjected to exceptional live loaiy

22

the installation of the position transducers with respect to the culvert pipe geometry.

Biaxial Strain Measurement

The nine locations across the center section of the culvert, where both cross­

sectional shape and deflection measurements were to be obtained, were also chosen to

measure biaxial strains. Two biaxial electrical strain gages were mounted on the inside

corrugated plate at each location, except for the crown, and the two shoulder locations

where the third strain gage was added. The first gage was installed at the peak of the inside

corrugation, and the second gage was installed, half a corrugation away from the first, in

the valley of the inside corrugation, as shown in Figure 2.7. Each strain gage was

positioned so that its two axes would be oriented parallel and perpendicular to the direction

of the plate corrugation and therefore strains could be read in the circumferential and the

longitudinal directions. Computations of moment and thrust values based on the strain

readings are explained in chapter four. A computer data acquisition system was loaded on

the back of the CGGR research vehicle and utilized in the field to obtain the strain gage

readings and the position transducer outputs during the loading steps.

Page 37: analysis of a pipe arch culvert subjected to exceptional live loaiy

Bac

kfil

lSoi

lM

ater

ial

~2

Inch

Fir

stSt

rain

Gag

eT

hird

Stra

inG

age

0)

I6

Inch

"-

Eye

bolt

Inst

alle

dat

Sec

ond

Stra

inM

onit

orin

gP

oint

Gag

e

FIG

UR

E2.

7T

YP

ICA

LIN

ST

AL

LA

TIO

NO

FB

IAX

IAL

STR

AIN

GA

GE

S

N W

Page 38: analysis of a pipe arch culvert subjected to exceptional live loaiy

CHAPTER 3

MEASUREMENT OF CULVERT DEFORMATION

3.1 OVERVIEW OF DEFORMATION MEASUREMENT

Culvert deformations were monitored after each increment of monotonically applied

live load. Deformation measurements were made by position transducers. A tape

extensometer was used to take readings to determine the shape of the culvert before and

after the test. This chapter explains the instruments used to collect the deformation data,

principles used for data reduction and the results obtained from the analysis. Movement of

the control hooks A and B were monitored by the ODOT personnel.

3.2 TAPE EXTENSOMETER MEASUREMENTS

The tape extensometer, used to determine the shape of the culvert, does not read out

the true length between two points. Instead, a calibration constant of 17.458 inches must be

applied to obtain the true length. The principle of this equipment and probable error in any

reading have been studied and well documented by Allan Rauch.(1990)

The tape extensometer measurements were taken between twocontrol hooks A, B

and the nine reference hooks distributed along the culvert periphery. Hooks A and B were

permanently installed into the four foot square concrete pedestal. It is reported that only

negligible movement occured in concrete pedestal. Therefore, throughout this chapter it is

assumed that there was no movement of control hooks.

DATA REDUCTION:

The readings ai and bi were taken from control hooks to all nine reference points as

shown in Fig.3.1. As shown in Fig.3.1, control hooks A and B were not on the same

plane as the nine reference hooks. Control hooks A and B were off by 1.5 inches and 2.25

Page 39: analysis of a pipe arch culvert subjected to exceptional live loaiy

A, B =Ground Reference Points

FIGURE 3.1 MEASUREMENTS FOR CROSS-SECTIONALSHAPE DETERMINATION

25

Page 40: analysis of a pipe arch culvert subjected to exceptional live loaiy

26

inches respectively. Therefore, the actual readings of the tape extensometer, after adding

the tape constant:

b. = J(b~ -2.25~ + 17.458I I

Eqn. (3.1)

Eqn. (3.2)

Coordinates of all nine reference points were calculated using the triangularization

method. By establishing the origin of a two dimensional x,y coordinate system at a point

where reference point A is projected onto the cross-sectional plane and applying simple

geometry principles, the x and y coordinate values for the monitoring point i can be

expressed as:

y. =Jtil: - x~I 1 I

Eqn. (3.3)

Eqn. (3.4)

It is assumed that there is no elevation difference between control hooks A and B.

Initial co-ordinates and final co-ordinates of all nine reference points were tabulated in

Tables 3.1 and 3.2, respectively. Initial and final shapes of the culvert 'are given in Fig 3.2.

Initial shape of the pipe is superpositioned over the final shape curve, with a magnification

factor of five applied to the vertical movements, to clearly indicate the overall deformation

pattern.

The establishment and the evaluation of the initial and the final cross-section of the

pipe arch was accomplished using two approaches. The first approach using tape

extensometer is more accurate than the second method. The second method, which

Page 41: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 3.1 RESULTS OF INITIAL TRIANGULATIONMEASUREMENTS

Monitoring x. v.Point 1 1

1 - 78.4764 7.283646

2 - 67.7104 32.82528

3 - 45.8207 56.49094

4 - 16.0193 70.90557

5 16.62255 74.56251

6 48.06325 69.91524

7 78.06078 55.16796

8 100.6137 31.77941

9 111.4759 6.716778

(Note) The Above Data Reflects The Cross-Sectional Condition OfThe Pipe Arch Culvert Before The Test On Sept 24, 1990.

27

Page 42: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 3.2 RESULTS OF FINAL TRIANGULATIONMEASUREMENTS

Monitoring x. Y. 8 X. 8 Y.Point 1 1 1 1

1 -78.4588 7.502599 0.011615 0.218953

2 - 67.9353 32.71373 -0.22499 -0.11156

3 - 46.2760 56.84925 -0.45531 0.358302

4 - 16.6364 70.05201 -0.61708 -0.85356

5 15.88784 67.24892 -0.73471 -7.31359

6 48.12747 66.56939 0.064227 -3.34586

7 78.61048 55.45415 0.549698 0.286184

8 100.8489 31.78826 0.235275 0.008845

9 111.5824 6.04567 0.106518 -0.67111

(Note) The Above Data Reflects The Cross-Sectional Condition OfThe Pipe Arch Culvert After The Test On Sept. 26, 1990.

28

Page 43: analysis of a pipe arch culvert subjected to exceptional live loaiy

200

180

160

,..-...140..c:u

.5'-' 120~~

~c.....-

100'"0~

00u 80I

~

60

40

20

0-80 -60 -40 -20

(NOlE) The final shape is plottedwith the vertical deflectionmagnified five times.

I:J Initial Shape

• Final Shape

o 20 40 60 80 100 120

X-Coordinate (inch)

29

FIGURE 3.2 FINAL CROSS-SECTIONAL SHAPE ATCENTER LOCATION

Page 44: analysis of a pipe arch culvert subjected to exceptional live loaiy

30

consisted of taking tape measurements of rise, span, skew span, chords and mid ordinates,

was applied through out almost the entire length of the pipe. Figure 3.3 presents the

different tape measurements taken by the Ohio DOT engineers and Tables 3.3 and 3.4

presents the various measurements recorded inside the pipe along its length before and after

the test respectively

Reduction in the rise was initially detected due to sagging of the pipe arch in the

middle. Measurements in the rise varied from 4.74% to 10.0%, with the maximum

reduction was observed at the center. Span is increased by 1.15% near the west end to

2.94% at the center location. No significant leaning of the pipe to one side was detected.

Final tape measurements taken after the experiment indicate that there was very

small outward movement at the monitoring points one and nine, agreeing well with the

position transducer measurements. Both the rise and the top center mid-ordinate

dimensions experienced more than 10% reduction from their initial values, while the top

left and right mid-ordinates increased by 16% to 17% and the top left and right chords

decreased by about 4%.

3.3 POSITION TRANSDUCER MEASUREMENTS

Position transducers were utilized to measure the deformation because of their

simple and remote ability to obtain highly accurate measurement. Since taking readings

with the tape extensometer is a time consuming process and requires persons to be inside

the culvert it was done only before and after the testing to find out the shape of the culvert. '

An excitation voltage was applied to the position transducer and the resulting

electrical outputs were set proportional to the linear position of the extension of a stainless

steel cable. Measurements were made by attaching the cable clip to a moving element and

mounting the position transducer to a fixed surface. Extension of the cable rotates the shaft

Page 45: analysis of a pipe arch culvert subjected to exceptional live loaiy

___________________ L _

IIIIII

31

Sleft. (SL)

Span (S)

Sright (SR)

FIGURE 3.3 TYPES OF TAPE ?v1EASURE?v1ENTSTAKEN

Page 46: analysis of a pipe arch culvert subjected to exceptional live loaiy

TA

BL

E3.

3IN

ITIA

LT

AP

EM

EA

SU

RE

ME

NT

DA

TA

Dis

tanc

eF

rom

Var

ious

Dim

ensi

ons

Tak

en(i

nn

.)

Sta

tion

Wes

tPi

peE

nd(f

1.)

SSL

SRR

TC

MO

TL

MO

TR

MO

TL

CT

RC

124

.015

.85

7.90

7.95

9.05

6.86

2.14

2.00

10.4

010

.42

232

.015

.98

NT

NT

8.77

6.69

2.02

2.01

10.3

810

.38

340

.016

.13

NT

NT

8.55

6.60

2.13

2.05

10.3

610

.39

W N

Page 47: analysis of a pipe arch culvert subjected to exceptional live loaiy

TA

BL

E3.

4FI

NA

LT

APE

ME

AS

UR

EM

EN

TD

AT

A

Dis

tanc

eF

rom

Var

ious

Dim

ensi

ons

Tak

en(i

nft.

)

Stat

ion

Wes

tPi

peE

nd(f

1.)

SSL

SRR

TC

MO

TL

MO

TR

MO

TL

CT

RC

124

.015

.85

7.90

7.95

9.05

6.84

2.17

1.97

10.4

410

.43

232

.015

.98

NT

NT

8.81

6.69

2.16

2.02

10.3

710

.38

340

.016

.13

NT

NT

7.81

5.90

2.50

2.39

9.90

9.99

448

.016

.06

NT

NT

8.49

6.54

2.23

2.11

10.3

510

.28

556

.016

.08

NT

NT

8.66

6.65

2.09

2.08

10.4

110

.32

w w

Page 48: analysis of a pipe arch culvert subjected to exceptional live loaiy

34

of the internal electromechanisms.

A constant-tension spring maintains the tension on the cable during extension from

the base and provides torque for rewinding the cable during retraction. The cable may

accelarate in retraction until the terminal velocity is reached.

The model used had a ran~e of zero to ten inches. During the test, a total of nine

position transducers were used. These transducers were calibrated in the laboratory.

Instrumentation of these transducers were explained in Chapter 2. Data was collected

using the HP3497A data aquisition system.

In order to calculate the deflection of the reference points the coordinates of the base

of the wire needed to be determined. These coordinates are tabulated in Table 3.5. During

the course of the experiment, the angle of the position transducer wire from the horizontal

changed considerably for the reference points #4, #5, and #6. The change in the angle of all

nine reference points are tabulated in Table 3.6.

During the analysis of transducer data, a decision was made to distribute the change

in angle proportional to the change in the lenth of the wire during the application of the live

load. At each step of loading, readings were taken from all nine units. For each step of the

loading, the deflection was presented in both the x and the y direction. These deflections

are presented in Figs. 3.4 through 3.12 for the first cycle of loading, Figs. 3.13 through

3.21 for the second cycle of loading and Figs.3.22 through 3.30 for the third cycle of

loading.

3.4 DISCUSSION

Section one which was located at the west springline, had hardly moved during the

Page 49: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE: 3.5 Co-ordinates of position transducerwire at its base

Pas it i on transducerX y

no j j

1 -74.78 2.00

2 -58.04 29.03

3 -36.06 48.56

4 -7.02 58.57

5 16.46 63.25

6 42.64 62.22

7 71.85 49.57

8 94.87 29.39

9 93.33 0.97

35

Page 50: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE: 3.6 Change of angle on position transducer wireduring the experiment

Position transducer Angle on wireno. a

~a

Initial Final

1 55.02 56.24 1.22

2 21.43 20.42 -1.01

3 39.1 39.06 -0.04

4 54.11 50.3 -3.81

5 89.18 81.86 -7.32

6 54.83 38.53 -16.3

7 42.03 41.04 -0.99

8 22.59 21.86 -0.73

9 17.57 15.54 -2.03

36

Page 51: analysis of a pipe arch culvert subjected to exceptional live loaiy

37

-0- Horizontal Component~ Vertical Component

80 100 120 140604020

0.04

0.03

0.00 1--..--io--.--.......-...---1---.--+-.....--1-.--.----+-----..-1

o

....~

Total Load Applied (ton)

FIGURE 3.4 DEFLECTION OF MONITORING POINT#!(SPRINGLINE) DURING FIRST LOADSEQUENCE

Page 52: analysis of a pipe arch culvert subjected to exceptional live loaiy

38

0.08

--[J- Horizontal Component

--d- l iVertical Component

0.06~

.cC.J

=.-"-'"CQ

0.04........C.Jcu

CaJ

Q

0.02

80 100 120 '1406040200.00 n-r=~:"'+--..-~--.-~-.--4--r---t---r---+----,.---1

o

Total Load Applied (ton)

FIGURE 3.5 DEFLECTION OF MONITORING POINT #2DURING FIRST LOAD SEQUENCE

Page 53: analysis of a pipe arch culvert subjected to exceptional live loaiy

39

80 100 120 140604020o.00 ~P--i---..--+---.----I--r---i--......---i---.----+----,r----I

o

0.08

--rr- Horizontal Component1 i I

----0- Vertical Component

0.06...-.....cCJ

=.-~c

0.040--......CJQJ-c..QJ

Q

0.02

Total Load Applied (ton)

FIGURE 3.6 DEFLECTION OF MONITORING POINT#3(SHOULDER) DURING FIRST LOADSEQUENCE

Page 54: analysis of a pipe arch culvert subjected to exceptional live loaiy

40

0.02

--0-- Horizontal Componenti E t i--0-- Vertical Component

20 40 60 80 100 120 140

Total Load Applied (tons)

-0.08 ~-...--+---.----+--.....-+---.--...-i---.---t---.,~+--..,.--f

o

:2 0.00~

c

c -0.02e-­...C.JaJ--c.-

O -0.04

FIGURE 3.7 DEFLECTION OF MONITORING POINT #4DURING THE FIRST LOAD SEQUENCE

Page 55: analysis of a pipe arch culvert subjected to exceptional live loaiy

0.1

0.0

,..-......c(j -0.1c...

'-'"

c0... -0.2~

C.J~...-..~

Q-0.3

Horizontal Component

-b- f ! E

Vertical Component-0.4

41

-0.5o 20 40 60 80 100 120 140

Total Load Applied (ton)

FIGURE 3.8 DEFLECTION OF MONITORING POINT #5(CROWN) DURING FIRST LOADSEQUENCE

Page 56: analysis of a pipe arch culvert subjected to exceptional live loaiy

42

0.1

~ Horizontal Component~, I ,

~ Vertical Component

~ 0.0.cC.J

=.-"-'"

=0........C.J~

c:~ -0.1Q

80 100 120 140604020-0.2 -J--......,--4--.----+_r---1---r--+-.....,.---+-----wr---+--......---t

o

Total Load Applied (ton)

FIGURE 3.9 DEFLECTION OF MONITORING POINT #6DURING FIRST LOAD SEQUENCE

Page 57: analysis of a pipe arch culvert subjected to exceptional live loaiy

43

80 100 120 140604020

--a- Horizontal Component []-t'""-'-~

} V-J- JVertical Component

If

JI

A.

~/..

a

0.06

0.05

0.00

-0.01o

~ 0.04.cC.Jc....~

c 0.030.......-C.JQJ 0.02-c..QJ

Q

0.01

Total Load Applied (ton)

FIGURE 3.10 DEFLECTION OF MONITORING POINT #7(SHOULDER) DURING FIRST LOADSEQUENCE

Page 58: analysis of a pipe arch culvert subjected to exceptional live loaiy

44

0.10

80 100 120 1406040

Venical Component

20

----u- Horizontal Component

0.08

o.00 ~;;""---+--......---+-..--+-....---+---.----+-...---+----.----I

o

§ 0.06

0.02 -I----4--~---I--~__t_-_;:if__-_t_-__t

.­....C.JQJ-c.-~

Q 0.04 -+---'-"---+--~.......--....f------+-.....--+-t-'--'+---"""""--1

Total Load Applied (ton)

FIGURE 3.11 DEFLECTION OF MONITORING POINT #8DURING FIRST LOAD SEQUENCE

Page 59: analysis of a pipe arch culvert subjected to exceptional live loaiy

45

0.04

:2 0.03(j

c

80 100 120 1406040200.00 ~~-i---......--+--.....----+-.--..;-........----i--"'--+----"-1

o

0.01

Horizontal Component

-0-, I I I

Vertical Component

ce.-~ 0.02 -I---4--~---I--+---r---t----t-----I...e.-QJ

Q

Total Load Applied (ton)

FIGURE 3.12 DEFLECTION OF MONITORING POINT #9(SPRINGLINE) DURING FIRST LOADSEQUENCE

Page 60: analysis of a pipe arch culvert subjected to exceptional live loaiy

46

0.00

0.04

Horizontal Component

~ I I0.03 Vertical Component

~

.cCJc...

"-'"

= 0.020....-~

~-..~ 0.01Q

12020 40 60 80 100Total Load Applied (ton)

-0.01 -+----w----+--w----+----.--.f.--.....,---+----..,,..---.-t----r----I

o

FIGURE 3.13 DEFLECTION OF MONITORING POINT #1(SPRINGLINE) DURING SECONDLOAD SEQUENCE

Page 61: analysis of a pipe arch culvert subjected to exceptional live loaiy

47

0.30 -r-------.~-__..,._--~--_r__-___r--__,

Horizontal Component0.25 """"--""""--0-1 E r -...--...--~........---...-~

Vertical Componentt

~

.c~ 0.20 +--~f-------+----+-----t---~---v.........

12010080604020

0.05 -t------l~---+---+---+__~___+-_f___t

0.00 n-......-......--I~,...=O:~~...---+--.----I-..,.-~o

Total Load Applied (ton)

FIGURE 3.14 DEFLECTION OF MONITORING POINT #2DURING SECOND LOAD SEQUENCE

Page 62: analysis of a pipe arch culvert subjected to exceptional live loaiy

0.4

~ Horizontal Componentt s s~ Vertical Component

~

.c~ 0.3.-"-'"

48

ce.-~

C.JQJc 0.2 ......................-.......~.......-...-..._-+-..-...-.... ...............+---............--+--~~r----tQJQ

20 40 60 80 100

Total Load Applied (ton)

FIGURE 3.15 DEFLECTION OF MONITORING POINT #3(SHOULDER) DURING SECOND LOADSEQUENCE

Page 63: analysis of a pipe arch culvert subjected to exceptional live loaiy

0.1

-0--, Horizontal Component--0- ~ Vertical Component'

49

~

.c 0.0C.JC--'-'"

c0--..C.JQJ -0.1--c...QJ

Q

-0.2-f...--~;----+----t---+----+---t---t

20 40 60 80 100

Total Load Applied (ton)

FIGURE 3.16 DEFLECTION OF MONITORING POINT #4DURING SECOND LOAD SEQUENCE

Page 64: analysis of a pipe arch culvert subjected to exceptional live loaiy

50

-2 -+--~i------"----+-----t----+---t--1

--0- Horizontal ComponentE ~ I

-0- Vertical Component

Ie

12020 40 60 80 100Total Load Applied (ton)

-4 -+---...-~------.----i---.--f----.-_p--.....----t--...----t

o

FIGURE 3.17 DEFLECTION OF MONITORING POINT #5(CROWN) DURING SECOND LOADSEQUENCE

Page 65: analysis of a pipe arch culvert subjected to exceptional live loaiy

0.2

0.0

.-~

-0.2ce.-.....CjaJ

c:: -0.4aJ

Q

-0.6

-0.8

~ Horizontal ComponentE i I

Vertical Component ~

51

20 40 60 80 100

Total Load Applied (ton)

FIGURE 3.18 DEFLECTION OF MONITORING POINT #6DURING SECOND LOAD SEQUENCE

Page 66: analysis of a pipe arch culvert subjected to exceptional live loaiy

52

12020 40 60 80 100

Total Load Applied (ton)

-0- Horizontal Component 0

--10-- l ( ,Vertical Component

~

p

;I~

- - - - -c----e,;~ -0.0

0.4

-0.1o

0.3~

.cCJc--"-'"

c 0.2Q--...C.JQJ-~QJ

Q 0.1

FIGURE 3.19 DEFLECTION OF MONITORING POINT #7(SHOULDER) DURING SECONDLOAD SEQUENCE

Page 67: analysis of a pipe arch culvert subjected to exceptional live loaiy

53

0.30......----,.----r---r----r--..,.-----,

0.25~

.::c.Jc~ 0.20

-0- Horizontal Component

--0-- Vertical Component

12020 40 60 80 100Total Load Applied (ton)

0.00 n-...........IIiiiiiif::J=a:~~~-=-..-I--..,..--+----..--Io

0.10

0.05 +--~'-""---i----+-----l~---t-u_-_t

ce--....~ 0.15 *-----l~---i----+---+__---t-,.,..-__t....

r..­Q.)

Q

FIGURE 3.20 DEFLECTION OF MONITORING POINT #8DURING SECOND LOAD SEQUENCE

Page 68: analysis of a pipe arch culvert subjected to exceptional live loaiy

54

0.08....------..----r----,..----r---.,.-----,

-6­o.06 ~Io'----o-

Horizontal Component~........-...----t-"""""""'-tc ~

Vertical Component

12020 40 60 80 100

Total Load Applied (ton)

-0.02 -+---.-----+-......-.....;-.----.--+----.---+--...-----+---.-----t

o

FIGURE 3.21 DEFLECTION OF MONITORING POINT #9(SPRINGLINE) DURING SECONDLOAD .SEQUENCE

Page 69: analysis of a pipe arch culvert subjected to exceptional live loaiy

Horizontal Component~ I

Vertical Component

0.04

0.03

..."-""

ce:: 0.02

C.JQJ-c.....QJ

Q

0.01

0.00o 20 40 60 80 100 120

55

Total Load Applied (ton)

FIGURE 3.22 DEFLECTION OF MONITORING POINT #1(SPRINGLINE) DURING THIRD LOADSEQUENCE

Page 70: analysis of a pipe arch culvert subjected to exceptional live loaiy

~ Horizontal Componentt

~ Vertical Component~

.>

~V V

~~

------[r--

- ~~-.-£'"

\r- «r:

0.30

0.25

~

.cCj 0.20c...

'-"

CQ.- 0.15.....CjQJ~c...QJ

Q0.10

0.05

0.00o 20 40 60 80 100 120

56

Total Load Applied (ton)

FIGURE 3.23 DEFLECTION OF MONITORING POINT #2DURING THIRD LOAD SEQUENCE

Page 71: analysis of a pipe arch culvert subjected to exceptional live loaiy

0.50

--0- Horizontal Component

----b- Vertical Component _'"-_--+__-10.45~"- c

.~

.cC.J.: 0.40 -J------1~-_+---+---+__-__t_...,.t___."'-"

=e.-~

~ 0.35-'-QJ

Q

0.30

20 40 60 80 100

Total Load Applied (ton)

FIGURE 3.24 DEFLECTION OF MONITORING POINT #3(SHOULDER) DURING THIRD LOADSEOUENCE

57

Page 72: analysis of a pipe arch culvert subjected to exceptional live loaiy

58

0.0

:c -0.1 .J--~~~-+--~-t---+-----t----t~

C--...........

ce--.....(j

~ -0.2c~

Q--o-c

Horizontal Component

Vertical Component I

-0.4o 20 40 60 80 100 120

Total Load Applied (ton)

FIGURE 3.25 DEFLECTION OF MONITORING POINT #4 .DURING THIRD LOAD SEQUENCE

Page 73: analysis of a pipe arch culvert subjected to exceptional live loaiy

o

-1,-......cy

=.- -2'-'"

=0.-....~

QJ -3---~Q-4

-5

[5 o-e--c .... 1""'" L~

'------~- ------.

~I\

\~ Horizontal Component--!..o- ~ t bVertical Component

59

-6o 20 40 60 80 100 120

Total Load Applied (ton)

FIGURE 3.26 DEFLECTION OF MONITORING POINT #5(CROWN) DURING THIRD LOADSEQUENCE

Page 74: analysis of a pipe arch culvert subjected to exceptional live loaiy

60

-0.6

-0.8~

.cCJc.-~

c -1.00.-~

CJaJ...~

aJQ

-1.2Horizontal ComponentE ~

Vertical Component

-1.4

20 40 60 80 100

Total Load Applied (ton)

FIGURE 3.27 DEFLECTION OF MONITORING POINT #6DURING THIRD LOAD SEQUENCE

Page 75: analysis of a pipe arch culvert subjected to exceptional live loaiy

0.5 .....---....--~--,...----,---..,..-----,

-0- Horizontal Component--b- Vertical Component

,..-.....cC.Jc~ 0.4

ce

61

20 40 60 80 100

Total Load Applied (ton)

FIGURE 3.28 DEFLECTION OF MONITORING POINT #7(SHOULDER) DURING THIRD LOADSEQUENCE

Page 76: analysis of a pipe arch culvert subjected to exceptional live loaiy

62

0.30

0.20~

.cCJc.-'-'"

0.15cQ.-...CJ~- 0.10c..~

Q

0.05

Horizontal Component

Vertical Component

0.00o 20 40 60 80 100 120

Total Load Applied (ton)

FIGURE 3.29 DEFLECTION OF MONITORING POINT#8DURING THIRD LOAD SEQUENCE

Page 77: analysis of a pipe arch culvert subjected to exceptional live loaiy

63

0.07

Horizontal Component~

5 5

0.06 Vertical Component

,--.....c 0.05(.J

c.-~c 0.04Q.-......(.JQJ-c:..... 0.03QJ

Q

0.02

0.01-I------+---i--~,::;;...-__+_--_t__-__t

12010080604020

0.00 -+----..-........-....--+---..-P--....---+-~....__+___.,._____I

o

Total Load Applied (ton)

FIGURE 3.30 DEFLECTION OF MONITORING POINT #9(SPRINGLINE) DURING THIRD LOADSEQUENCE

Page 78: analysis of a pipe arch culvert subjected to exceptional live loaiy

64

test, with the total maximum vertical movement being O.037(i inches. The first two loading

steps of the second loading cycle resulted in an inward movement. Afterwards, that it

always moved outward.

Section two constantly moved outward. The magnitute of the movement was

similar during the second and third cycles. The maximum vertical movement at this section

was 0.084 inches.

Section three which was located at the west shoulder also constantly moved

outward. There was a slight variation in movement between the second and the third

loading. Careful consideration of the data revealed a permanent deformation of 0.05 inches

during the second cycle at this section.

Section four, located close to the crown, continuously moved inward. There was a

considerable difference in total vertical deflection during the second and third cycles under

the same load of 115 tons. The reason for this is that the stress level in this region

exceeded the yield limit of the corrugated steel material during the second cycle of loading.

Maximum vertical deflections at, this section for the second and third loading cycle were

0.2282 inches and 0.5977 inches respectively.

Section five, located at the crown, experienced the maximum vertical deflection.

This is understandable since the load application point was over this section. The maximum

vertical deflections at the crown for the second and third cycles of loading were 3.435 and

6.989 inches respectively.

In section six, during the first step of second cycle loading, the hook moved

upward, and afterwards it always moved downwards. The maximum deflections were

0.9487 inches and 1.8047 inches for the second and third cycles respectively. A maximum

horizontal deflection of 2.4752 inches occured at this section during the third loading cycle.

Page 79: analysis of a pipe arch culvert subjected to exceptional live loaiy

65

The magnitude of the deflection did not coincide with that of section four.

Sections 7, 8, and 9 behaved in a similar manner to sections 3, 2, and 1,

respectively. The maximum vertical deflection was 0.3625 inches at section 7,0.1082

inches at section eight and 0.197 inches at section nine. All the maximum deflections

occured during the third sequence of loading.

The positive x axis for #1 through #5 was towards west and for points #6 through

#9 towards east. The positive y axis was always upwards. Deflection of all nine points

started from the non-zero value for the third sequence of loading. Total maximum vertical

deflection of 6.989 inches was recorded at the crown point. when the total load reached

approximately 100 tons, rapid increase in the rate of deflection was monitored. The points

at the crown moved downwards and the points at the haunch and springline moved

outwards.

Page 80: analysis of a pipe arch culvert subjected to exceptional live loaiy

CHAPTER 4

MEASUREMENT OF PLATE FORCES

4.1 INTRODUCTION

This chapter presents the bending moment and axial thrust obtained from the field

testing. In order to detennine the axial force and bending moment due to monotonically

applied live load, biaxial gages were installed at nine sections along the periphery of the

culvert plate as described in Chapter 2. The bonded-foil electrical resistance strain gages

were read using a computerized data acquisition system. Biaxial plane stress assumptions

were used to compute circumferential stresses in the culvert plate. The data from the strain

gages were reduced to moment and thrust as described in this chapter. The strain gages and

the data acquisition system have been described in detail by Alan Rauch.(1990)

4.2 REDUCTION OF STRAINS TO AXIAL THRUST AND BENDING

MOMENTS

The data acquisition system reads the two voltages, Vin and Vout, and returns the

ratio, Vout / Vin. The computer program,"RATIO"stores this data in the diskettes for

future analysis. Computer program "NEW" is used to calculate the strains from the stored

ratios. Strains were computed using first set of readings, the readings taken before the load

was applied, as an initial value.

As discussed earlier we had at least two biaxial gages at each section, one at the peak

and the other at the crust. Assuming plane strain theory, we can calculate the circumferential

stresses as follows:

Page 81: analysis of a pipe arch culvert subjected to exceptional live loaiy

67

E =Young's modulus 30x106 psi

i} = Poisson's ratio 0.3

cc= circumferential strain

tl= longitudinal strain

Eqn. 4.1

Stresses were assumed to be due to bending moment and axial forces.

Superposition of these results gives the expression shown in Eqn. 4.2

p + MeCfe =A I

P =axial thrust

A = area of cross section

M =bending moment

I = moment of inertia

C = distance from the neutral axis

Eqn.4.2

At each monitoring location, two circumferential stress values were obtained,

one from the biaxial strain gage installed at the peak and the other is from the gage placed

in the valley of the corrugation. From Eqn. 4.2, moment and thrust can be obtained by

simple calculation. The equations obtained for moment and thrust are given in Eqns. 4.3

and 4.4 respectively.

Page 82: analysis of a pipe arch culvert subjected to exceptional live loaiy

68

Eqn.4.3

C1 =distance from neutral axis to interested

point in tension zone (1.094 inches)

C2 =distance from neutral axis to interested

point in compression zone (0.906 inches)

Eqn.4.4

Figure. 4.1 presents the calculation details of Cl and C2. Calculated thrust and

moment are presented in Tables 4.1 and 4.2. Figures. 4.2 through 4.7 presents moment

and thrust graphically for the first sequence of loading. Figures 4.8 through 4.17 presents

moment and thrust for the second sequence of loading and the Figures 4.18 through 4.23

presents the moment and thrust for the third sequence of loading. Figures 4.24 through

4.33 presents how the culvert responded at selected sections for the applied live load for the

last two cycles of loading.. A consistent sign convention is employed throughout this

study. Positive bending moments imply a concave-up bending in the crown region and for

thrusts tensile forces are positive.

4.3 ANALYSIS OF RESULTS

Initial stages of the loading resulted in the negative moment at sections #land #9 at

the spring line indicating the outward movement of the culvert at those locations. During

the second cycle of loading after load step 6 moment at these locations were changed to

Page 83: analysis of a pipe arch culvert subjected to exceptional live loaiy

d

t

Strain Gageon Peak

Neutral- -- Axis

69

FIGURE 4.1 DEFINITION OF DISTANCES ci AND C2 TAKENFROM NEUTRAL AXIS

Page 84: analysis of a pipe arch culvert subjected to exceptional live loaiy

rrA

BL

E4.

1C

OM

PUT

ED

AX

IAL

TI-

lRU

ST

Loa

dL

oad

To

tal

Thr

ust

(kip

s/ft

)@

Mon

itor

ing

Poi

nt:

Cyc

leSt

epL

oad

No.

No.

(to

n)

Ifl

#211

3#4

#5#6

#7#8

#9....

...~

.

00.

000

O.C~OO

0.00

00.

000

0.00

00.

000

0.00

00.

000

0.00

00.

000

13

0.8

0.(

J.~·\()6

-0.6

67-1

.:\29

-1.3

600.

468

-1.1

29-1

.558

-0.9

00-0

.141

238

.48

-0./1

590.

818

-1.R

48-1

.913

-0.8

26-1

.660

-2.3

12-1

.374

1.17

13

50.0

3..O

.t)74

-1.6

03-2

.H64

-3.0

76-1

.324

-2.5

97-3

.245

-2.2

210.

876

465

.43

-().

X')

9-2

.307

-3.H

56-4

.286

-2.2

92-3

.885

-5.4

30-3

.421

0.42

72

578

.89

-1.(

)()7

-2.9

54-4

.Y72

-5.6

75-2

.947

-4.8

14-6

.256

-4.3

450.

271

688

.51

-1.7

35-3

.632

-6.3

05-7

.849

-5.1

57-6

.508

-8.1

51-5

.596

-0.0

177

101.

6-1

.337

-4.6

22-7

.X63

-11.

11-5

.226

-9.1

03-1

0.16

-4.6

22-0

.245

810

3.9

-1.3

2Y-5

.967

-X.6

45-1

0.82

-3.7

14-9

.984

-9.3

80-5

.967

-0.2

929

111.

6-

J..l

()4

-6.9

00

-q.7

15N

C-1

.706

-8.8

14-8

.121

-6.9

000.

197

1010

2.0

-I"~10

-7.2

30-9

.357

NC

-0.6

00-7

.150

-6.9

73-7

.230

0.05

911

111.

6-

--

--

--

--

1211

3.9

-0.9

9I

-9.9

77-1

0.55

NC

11.2

93.

844

-6.8

18-9

.977

0.16

8

00.

000.

000

0.00

00.

000

0.00

00.

000

0.00

00.

000

0.00

00.

000

150

.03

-0.6

30-1

.687

-2.5

74-2

.540

0.74

6-1

.318

-3.3

00-6

.743

-0.4

242

57.7

3-1

.2)

6-3

.404

-4.9

56-4

.634

1.88

5-1

.948

-6.6

90-8

.288

-0.8

29

33

80.8

1-1

.573

-4.4

76-6

.657

-5.9

092.

998

-2.1

41-9

.129

-10.

04-0

.979

410

0.1

-2.1

47-6

.102

-9.1

51-6

.214

5.10

8-0

.982

-11.

46-1

2.20

-1.3

475

107.

8-2

.359

-6.4

83-9

.861

-2.1

047.

552

0.67

4-1

1.70

-12.

86-1

.580

611

5.5

-2.2

93-5

.951

-10.

6612

.57

14.1

57.

881

-10.

44-1

3.40

-1.5

67

(Not

e)"N

ett=

No

tC

ompu

ted

Sin

ceth

eY

ield

Str

ess

was

Rea

ched

.~ o

Page 85: analysis of a pipe arch culvert subjected to exceptional live loaiy

TA

BL

E4

.2C

OM

PU

TE

DB

EN

DIN

GM

OM

EN

T

Loa

dL

oad

Tot

alM

omen

t (ki

ps-f

t/ft

)@

Mon

itor

ing

Poi

nt:

Cyc

leSt

epL

oad

IN

o.N

o.(t

on)

#1#

2#3

#4#5

#6#7

#8,#

9

00.

000

0.00

00.

000

0.00

00.

000

0.00

00.

000

i 0.0

000.

000

0.00

01

30.8

0-0

.015

-0.0

04-0

.048

-0.0

810.

195

-0.0

36%

-0.0

51-0

.014

-0.0

222

38.4

8-0

.022

-0.0

69-0

.079

-0.1

240.

291

·0.0

50I -

0.08

1-0

.015

-0.0

803

50.0

3-0

.028

0.01

4-0

.142

-0.2

250.

519

-0.0

81i -

0.15

0.-0

.013

-0.0

794

65.4

3-0

.030

0.03

2-0

.255

-0.3

610.

842

-0.0

92I

-0,.2

86-0

.010

-0.0

712

578

.89

-0.0

250.

052

-0.3

90-0

.489

1.20

0-0

.073

-0.4

51-0

.009

-0.0

596

88.5

1-0

.012

0.08

2-0

.582

-0.7

401.

494

.-0

.198

-0.7

000.

003

-0.0

297

101.

6O

.()17

0.16

0--0

.808

-1.3

751.

416

-0.8

71-1

.101

0.16

00.

031

810

3.9

O.O

(,30.

249

-1.0

55-2

.113

1.30

2-1

.469

-1.4

170.

249

0.09

09

111.

6O

.O()6

0.30

9-1

.238

NC

1.18

9-1

.782

-1.5

650.

309

0.13

010

102.

00.

126

0.34

6-1

.353

NC

1.09

4-1

.879

-1.6

330.

346

0.15

911

111.

6-

--

--

--

--

1211

3.9

0.31

30.

636

-2.1

57N

C-0

.226

-2.1

54-1

.559

0.63

60.

344

00.

000.

000

0.00

00.

000

0.00

00.

000

0.00

0.

0.00

00.

000

0.00

01

50.0

3-0

.012

0.01

8-0

.147

-0.4

000.

719

-0.1

14-0

.252

-0.2

02-0

.006

257

.73

-0.0

160.

032

-0.3

43-0

.759

1.41

7-0

.079

-0.6

03-0

.180

-0.0

073

380

.81

-0.0

150.

043

-0.5

18-1

.021

.1.

952

-0.0

32·

..0.9

15-0

.200

0.00

410

0.1

0.00

10.

061

-0.8

47-1

.501

2.54

50.

094

-1.2

35-0

.204

0.02

25

107.

80.

013

0.08

1-0

.979

-1.6

712.

313

0.08

1-1

.261

-0.1

960.

032

611

5.5

0.03

40.

125

-1.1

40-2

.056

1.48

3-0

.130

-1.2

04-0

.199

0.05

7

(Not

e)"N

C"=

Not

Com

pute

dSi

nce

the

Yie

ldSt

ress

was

Rea

ched

....

...]~

Page 86: analysis of a pipe arch culvert subjected to exceptional live loaiy

Moment

Thrust8' -0.5--......

tf.)

c.~ -1.0 ................~~......."....,,~ ............'-""

-2.5

-3.0o 50 100 150 200 250 300

Unfolded Length (inch)

0.2 -.----.....---..,.----..,.-----r-~-____,

~

~e.­--......~e.-~ 0.1 -..--~--i---I-~--+-_t-___.c..-~'-""

=0.0CJ

EQ

::; -0.1 +--~~~~-~......--..~-............

-0.2 -+-r-~~..,-,.-.,....;-,..................._+_,.....................~r__r_i_..,....,._...._r_I

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.2 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 69.27 TONS DURING FIRSTLOADING SEQUENCE

72

Page 87: analysis of a pipe arch culvert subjected to exceptional live loaiy

73

0.0

Thrust~-0.5c=""""""r.n

~-1.0""-""

~ -1.5·#1l­.eE- _2.0 -J--~---t--I---+w\r--+---i'------t

-2.5

-3.0o 50 100 150 200 250 300

Unfolded Length (inch)

50 100 150 200 250 300Unfolded Length (inch)

-0.20 ....................-+-.-......................-.--.-..--+-.......................-.--.~.................

o

cO.05QJ

E~0.10

-0.15 -+---+r--J~~---+-_~~~_---I

0.10~c=~O.05e.-•r.n.e.O.OO~""-""

FIGURE 4.3 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 86.59 TONS DURING FIRSTLOADING SEQUENCE

Page 88: analysis of a pipe arch culvert subjected to exceptional live loaiy

74

-1Thrust

r:I

#9~

~

~

-2-.......rI'JC..-~""-'"

~

-3rI'J

=~.cE--

-4

-5o 50 100 150 200 250 300

Unfolded Length (inch)

0.2~c=~ 0.1c...

I

.~ 0.0-~1~~~~~~~~~~~""-'"

=-0.1QJ

§ -0.2-I--~--I-_~w--3~-+---+_~~

-0.3

-0.4o 50 100 150 200 250 300

Unfolded Length (inch)

FIGURE 4.4 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 100.06 TONS DURINGFIRST LOADING SEQUENCE

Page 89: analysis of a pipe arch culvert subjected to exceptional live loaiy

75

10

#5 Thrust,-.....,.....c.. 5""-

t'-)

c..-~~

.....0t'-)

=l-.eE- :#1

-5

-10 -+-.-....-....~...,........,...+-,...,...,.....,.......,...,....,-r-t-..,...,....,.....,...,-,.-,-...-r-1

o 50 100 150 200 250 300Unfolded Length (inch)

i

Moment0.1 ......----ro----,-.---.,--~-_.,.-_..

-0.5-+-r-~.........................-i-~"""-+""""'........-~--r-r--+-r-"""""r-1

o 50 100 150 200 250 300Unfolded Length (inch)

C -0.2QJ

§ -0.3 -I---+-+o--+-+---+-+--+--I---t--..

~

-0.4 ...............~..............~¥1- .............................-~~.,.".,........~-----t

,-.....,....c.. 0 O~·--t----f----+----t----t~__.-;:; .c..

I~

.9- -0.1 ...............~~ ...............~-~-~~,.".,"_t ...............__.

~~

FIGURE 4.5 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 107.76 TONS DURINGFIRST LOADING SEQUENCE

Page 90: analysis of a pipe arch culvert subjected to exceptional live loaiy

-10 -+-.-.......--.~................-+--.~...,...,...~...,....,...,..,...,........,..........,....,....,...,

o 50 100 150 200 250 300Unfolded Length (inch)

Moment

oW

ce-0.3e~ -0.4

-0.5 -t---+----~.......;--. ~~f'___T'-.........___.

-0.6 ~.....,...,~ ~ ~................,.....

o 50 100 150 200 250 300Unfolded Length (inch)

~

~ 0.0 ~~-4----+----i-----+--~~

~ #5Q. -0.1 -I--I!l~--t---- .----+--~--1.-~'"-"' -0.2 -I----4----i-~~-__+_-'l__t-___t

FIGURE 4.6 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 115.45 TONS DURINGFIRST LOADING SEQUENCE

Page 91: analysis of a pipe arch culvert subjected to exceptional live loaiy

#9

Moment

15#5 Thrust

2 10 -I---+---+---A-+----+--t-~.............

fI.)

c....C 5-1--4---+--+--l----+----t-----t~fI.)

::s.E O...............~~-~.....J.--.---+-J~~----t.............-----t~

-5

-10 ....J--r-...........~..........,.....p...,-,...,....,....;-~_r+..,.............___t.......-.-..,..,...,

o 50 100 150 200 250 300

Unfolded Length (inch)

0.2 .....--......----,-----.,...---,..---,.---,~ #1~.............

~ 0.0I

fI.)

C....C -0.2 4--...w----+--~---+---+--t---t~

c5 -0.4Q

~-0.6 -t----+--\-~-__+__+__--+-_+__--+----t

-0.8~............--+-r-...................;--..-.-.-~~...................-.-i-~."...,....-t

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.7 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 123.15 TONS DURINGFIRST LOADING SEQUENCE

77

Page 92: analysis of a pipe arch culvert subjected to exceptional live loaiy

78

0.5

#5

...CI.)

E-1.0.c~

-1.5

-2.a-I-.-..........-+-,-..,...-,-,.-+-,...,..,...,..-+-r-r-r......-T-or-or-,....,....,...,.....,....,..,...,

a 50 100 150 200 250 300

Unfolded Length (inch)

Moment

50 100 150 200 250 300Unfolded Length (inch)

0.05

-0.10 ............~-+-r-.......-.-+-w- ...........-+-r-..........r-+-.-........................-.--r-'"I"-t

o

0.20

...=E 0.00e~ -0.05

~

~ 0.15---........~

ICI.)

c..--~"-'"

FIGURE 4.8 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 30.79 TONS DURING SECONDLOADING SEQUENCE

Page 93: analysis of a pipe arch culvert subjected to exceptional live loaiy

79

2Thrust

1~

#9c=-......CI'JC. 0.-~"'-'"

....CI'J

== -1s..cE--

-2

-3o 50 100 150 200 250 300

Unfolded Length (inch)

0.3Moment

....c~ 0.0Ee~ -0.1 -f.--~~'-I--+----+----+----t

-0.2~...................~.........-..-.........................................~................o 50 100 150 200 250 300

Unfolded Length (inch)

FIGURE 4.9 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 38.48 TONS DURINGSECOND LOADING SEQUENCE,

Page 94: analysis of a pipe arch culvert subjected to exceptional live loaiy

Moment

80

1

~ 0~

-----tI'JQ...-~

-1'-'"

~

tI'J

=I..c -2E-c

-3

-4 4-.-..........-..+-.-..---,r-+-~,..-+-..,.....,.-..,....;-...,.-,.-r-t--.--.~

o 50 100 150 200 250 300

Unfolded Length (inch)

0.6 -.----,------.r--~-~-___r-___,

~r::~ 0.4 -I---+--~--4~---+-----t'----tc...•tI'JC..-.::.= 0.2 -4--~-~-I-~~"""""""'---+--t

"-'"

.-=E 0.0e~

-0.2 -+---+---~---i--_""O_-___+-__t

-0.4 .......-...........-+-r-.......-..........-.-.-...................-.-+-...................-+.........~

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.10 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 50.03 TONS DURINGSECOND LOADING SEQUENCE

Page 95: analysis of a pipe arch culvert subjected to exceptional live loaiy

81

1Thrusts

-4

-5o 50 100 150 200 250 300

Unfolded Length (inch)

Moment

......c50.00e~0.25 -+--~~+-I--~--"~--+r

1.00

20.75-<;......e.-

~0.50.-~

~ 0.25 -f---+-----+---+---+-\--~-_+__-_1

50 100 150 200 250 300Unfolded Length (inch)

-0.50 ...........--.-.........................-.-...........--i--r-...........P"""""'i-I-...............-+-r....-.-~

o

FIGURE 4.11 DISTRIBUTION OF THRUST AND MOMENTUNDER LOAD OF 65.43 TONS DURINGSECOND LOADING SEQUENCE

Page 96: analysis of a pipe arch culvert subjected to exceptional live loaiy

822

~ 0c::............

CI'Je,~ -2 ...............~~ ...............~-"-"'"

-6

-8o 50 100 150 200 250 300

Unfolded Length (inch)

Moment#5

2.0~

~e.- 1.5............

r:::I

CI'Jc. 1.0.-~"-"'"=0.5aJ

Ee 0.0~

-0.5"'-"'---f--~-~_~IIIIw-----+-_---I

-1.0o 50 100 150 200 250 300

Unfolded Length (inch)

FIGURE 4.12 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 78.89 TONS DURINGSECOND LOADING SEQUENCE

Page 97: analysis of a pipe arch culvert subjected to exceptional live loaiy

83

Thrust~ 0~............

r:I'.Jc..-- -2~'-"

......= -4r-.c~

-6

-8

-1 0~.........-+-'-""""''''''''''''~~~-r-+-~......,....,....,....,..~o 50 100 150 200 250 300

Unfolded Length (inch)

2.0#5 Moment

~

~ 1.5...............,..•tI'.) 1.0e,--~

'-"

...... 0.5c: #9QJ~ 0.0...0

~-0.5

-1.0o 50 100 150 200 250 300

Unfolded Length (inch)

FIGURE 4.13 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 88.51 TONS DURINGSECOND LOADING SEQUENCE

Page 98: analysis of a pipe arch culvert subjected to exceptional live loaiy

84

50 100 150 200 250 300Unfolded Length (inch)

0#1

~ -2.....c-..--........fI'Jc.. -4.-~..........,

...-6fI'J

=L..cE- -8

-10

-120

-2 -+-.-.....-.-..........................-+-..........-.-+-.--.-....-.--.........-.--............~........

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.14 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 101.6 TONS DURINGSECOND LOADING SEQUENCE

Page 99: analysis of a pipe arch culvert subjected to exceptional live loaiy

85

0#1

-2~

~"""'"r:rJ

-4Q...-~~

-- -6~

::2'-.cE- -8

-10

-120 50 100 150 200 250 300

Unfolded Length (inch)

Moment#5

......c -1 ~-~~~wwI-........-....+-~~~~...............~~

EQ

:; -2 ...............-~~~Irw-------+-~~----Jrr-- ...........i

~

r::: 1--..............-.

I~

c.. 0 -I-W-'-~---1----f---+\----+----I--+---:;;;~....~~

-3 ..........~......-.-.........-r-+-r..,.........-+-r-r-r ......................-r-t-............,...,.....

o 50 100150200250300

Unfolded Length (inch)

FIGURE 4.15 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 103.91 TONS DURINGSECOND LOADING SEQUENCE

Page 100: analysis of a pipe arch culvert subjected to exceptional live loaiy

2Thrust

-8

-10o 50 100 150 200 250 300

Unfolded Length (inch)

2~

#5.-'-- Moment............-c.-•tI'.)c....~'-""

~ 0r::QJ

E0

~ -1

-2 ...........................................-i-..........--.-+-r-..-.....-.--.....................-+-r-.........-..-t

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.16 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 111.6 TONS DURINGSECOND LOADING SEQUENCE

86

Page 101: analysis of a pipe arch culvert subjected to exceptional live loaiy

20 .....---.......--~----.,.--,..----r-----.

87

Thrust#5

~ O~--f.----w~---+-~"i-----t---P--1

=­.cE--10 ....a------I~~---i--_+--t___"U_t___-__t

-20 -+-r-...........~..,....,..-r-+-..,.-,-.,,....,........,..-,.~+-r-r-r--I-t-r---r-r--r-t

o 50 100 150 200 250 300Unfolded Length (inch)

1~c::

...............c....• 0~

c....~'-'"... -1=aJ

EQ

~ -2

-3 .....,.........................................~.......-..-.--.- ..................-.--..............~......-t

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.17 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 113.9 TONS DURINGSECOND LOADING SEQUENCE

Page 102: analysis of a pipe arch culvert subjected to exceptional live loaiy

2 .....--......--.......---....".-----,------r--....,

88

#5 Thrust

#9

-8 ...+-..,.-...........................-t-P-~r-+-r-_r_r_.........,...,...,...,....,.-,...,_..r_~

o 50 100 150 200 250 300Unfolded Length (inch)

0.8 ......---..---~-__._-___r-----.,.-----,

~ ~ornent~ 0.6 -I----4----4---I-+-t-----i--......c.-•~ 0.4.-~

~ 0.2......cE0.0Q

~ -0.2

-0.4 -t---+----~rnr'"""-...............-__+__~-+---_t

-0.6 .................................................-.-.-...-+-,............-+-.......--.r-r-i-~.....-r-1o 50 100 150 200 250 300

Unfolded Length (inch)

FIGURE 4.18 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 50.03 TONS DURINGTHIRD LOADING SEQUENCE

Page 103: analysis of a pipe arch culvert subjected to exceptional live loaiy

89

-8

-10 ..................-+-.-..........-+-r-.,....,..,.........,...,...,..,....,...,...,...,...,..,...,....,....,..~

o 50 100 150 200 250 300Unfolded Length (inch)

2.0Moment#5~

~~ 1.5c...

I~

.9- 1.0 -I---......a..---~~~----+-""",..,.,...........-.;.---t~'-'"=0.5aJ

§ 0.0 ~~~--+--f---i---+--+----t~:J--'I:E

-0.5

-1.0o 50 1·00 150 200 250 300

Unfolded Length (inch)

FIGURE 4.19 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 57.73 TONS DURINGTHIRD LOADING SEQUENCE.

Page 104: analysis of a pipe arch culvert subjected to exceptional live loaiy

-10

Thrust

90

-15o 50 100 150 200 250 300

Unfolded Length (inch)

2 i,.......Moment....-"""""-...-I 1tf.:)

e,.-~"'-'".. 0=Q)

E0

~ -1

-2 -+-r-...........,,......,................-+-,-..,-.,.......-+.........-r-r-t-r-r...,...,..-r-r-~......

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.20 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 80.81 TONS DURINGTHIRD LOADING SEQUENCE

Page 105: analysis of a pipe arch culvert subjected to exceptional live loaiy

91

10 ...--......-----,------,------p------r----,

Thrust

-15o 50 100 150 200 250 300

Unfolded Length (inch)

#9

IMoment

....-........."""-­r: 2~----+---~-lJ-\+--...............-___t--_"'t

ItI:.)

Q.--:::, 1-1---4----4--I--+--\---f-----t--t

-2 ...................-+-.-..............................-+-..-.--...................~...............-1

o 50 100 150 200 250 300Unfolded Length (inch)

~IGURE 4.21 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 100.1 TONS DURINGTHIRD LOADING SEQUENCE

Page 106: analysis of a pipe arch culvert subjected to exceptional live loaiy

92

10

-10

Thrust

-15o 50 100 150 200 250 300

Unfolded Length (inch)

Moment#5

3~...c.­"'-c= 2 .............-.--+---+-................,~+----+-----t----i

Ir.nC..-~ 1-1----+-----+---I-~\-~-----+---t

-2o 50 100 150 200 250 300

Unfolded Length (inch)

FIGURE 4.22 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 107.8 TONS DURINGTHIRD LOADING SEQUENCE

Page 107: analysis of a pipe arch culvert subjected to exceptional live loaiy

93

#5 Thrust~

~~ 10 ..............................~...............~Iuuu...............~:~ ...............~~~~~

C.......~"'-'"

-10

~ 0 #1 ~~---I-~-----+-~-+--~---tt..cE--

-20 -+-r-.........-+-w-.........'I""""'t-t'...........~~~..,..........,I"""'""r""T'-r-r-r-r-t

o 50 100 150 200 250 300Unfolded Length (inch)

Moment

~

=QJ

5 -1e~

~

~

~-........~ 1 ..............................~...............~..............., ".........."",...............~~~~...-rr4

Ic;nC.......e O~-~---+----f-~~~"'--~~~

-3 -+-r-.........................................-............--i-..............--+-............................................

o 50 100 150 200 250 300Unfolded Length (inch)

FIGURE 4.23 DISTRIBUTIONS OF THRUST AND MOMENTUNDER LOAD OF 115.5 TONS DURINGTHIRD LOADING SEQUENCE

Page 108: analysis of a pipe arch culvert subjected to exceptional live loaiy

94

~.... 0----....CFJC..-~~

....CFJ -1=s...cE-

--0--

•2nd Load Seq.3rd Load Seq.

12020 40 60 80 100

Total Load Applied (ton)

-3 -+---....----t~...,.---+----,,...._._+____._-+____r___+_-~_t

o

FIGURE 4.24 THRUST VS "LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSPRINGLINE (POINT #1)

Page 109: analysis of a pipe arch culvert subjected to exceptional live loaiy

95

oI

2nd Load Seq.3rd Load Seq. --+--....-..-~-----..-.........-..•

I--0--

....-...~ 0.3 ;---,-.....--..............

~•tne,.-~ 0.2 -+------+-----t----+------i----t-~r___1.....CQJ

Ee 0.1 -+------+----+---+----t----t---r't--1

:;

120

~

I

20 40 60 80 100

Total Load Applied (ton)

-0.1 -+-----.-----a~.....---+--r___......-___._-t____r__---t--..-__t

o

FIGURE 4.25 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUEN'CES ATSPRINGLINE (POINT #1)

Page 110: analysis of a pipe arch culvert subjected to exceptional live loaiy

96

2nd Load. Seq

3rd Load Seq•

-10~-~---+----+----;--~-=----t

~

10...c-..-"""'-CI'.)

c..-~"-""

....CI'.)

0=l-.eE-

1201008040 .. 6020-20 .....--..-----i-.....---+-.--......--+---,--+--....----t--....---t

o

Total Load Applied (ton)

FIGURE 4.26 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #4

Page 111: analysis of a pipe arch culvert subjected to exceptional live loaiy

97

,.-.....c...-...........

0~c...I~

C.....~~

~

-1cQJ

Ee~

---0-- 2nd Load Seq.-2 -+--_.., ~ '\ -- --+----+-t--~

• 3rd Load Seq.

12010080604020-3 -+--...---l~.....---+--.....--+--...-+----r----t-~---t

oTotal Load Applied (ton)

FIGURE 4.27 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #4

Page 112: analysis of a pipe arch culvert subjected to exceptional live loaiy

98

20

-0- 2nd Load Seq.15 • 3rd Load Seq.

,~

~-......-..tn

10e,.-.::.::"-'"

.....tn 5='-.c

E--0

20 40 60 80 100

Total Load Applied (ton)

FIGURE 4.28 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATCROWN (POINT #5)

Page 113: analysis of a pipe arch culvert subjected to exceptional live loaiy

3I--0- 2nd Load Seq.

...-.... • 3rd Load Seq.......-........... 2~-•CI.:)

c..-~~

~

1cQJ

E0

:E

0

20 40 60 80 100

Total Load Applied (ton)

FIGURE 4.29 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATCROWN (POINT #5)

99

Page 114: analysis of a pipe arch culvert subjected to exceptional live loaiy

10 -.---'---r'---.,----.,..--~--...,..__-___,

~5

......c...""""-~

Q..-~ 0"'-'-'

......~

=I..c

-5~

-0- 2nd Load Seq.e ~

• 3rd Load Seq.-10

20 40 60 80 100

Total Load Applied (ton)

FIGURE 4.30 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #6

100

Page 115: analysis of a pipe arch culvert subjected to exceptional live loaiy

101

~...c:..-""'"""- 0..c:..-

IfI'.}

c...-~"-'"..

-1cQJ

50

~

-2--0--

I2nd Load Seq.I I

3rd Load Seq.

20 40 60 80 100

Total Load Applied (ton)

FIGURE 4.31 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSECTION #6

Page 116: analysis of a pipe arch culvert subjected to exceptional live loaiy

102

~....... 1~-........fI.:)

c.--.:.c:"'-'"

.....fI.:)

0='-.cE-

-0--

•2nd Load Seq.3rd Load Seq.

I20 40 60 80 100

Total Load Applied (ton)

FIGURE 4.32 THRUST VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSPRINGLINE (POINT #9)

Page 117: analysis of a pipe arch culvert subjected to exceptional live loaiy

103

12020 40' 60 80 100

Total Load Applied (ton)

-0.1 -+----.-----+-..,..---t----.--o+---.,---t--,.---t----r-----1

o

0.4

..-....0.3

2nd Load Seq .....c0..- I

"""'" 3rd Load Seq.....c0..-

If.I:)

e,.-~ 0.2'-"

....cCJ

E0.10

~

0.0

FIGURE 4.33 MOMENT VS LOAD PLOTS FOR SECONDAND THIRD LOADING SEQUENCES ATSPRINGLINE (POINT #9)

Page 118: analysis of a pipe arch culvert subjected to exceptional live loaiy

104

positive indicating the inward movement of the culvert. Small value of moment agrees well

with small deflection data at these locations. In general, the magnitude of the thrust and the

moment in the springline region was much smaller than those in the shoulder or in the

crown region and agreed well with the deflection data.

Sections #2 and #8 responded similarly. Bending moment is positive in both the

sections and both were in compression. Values of bending moment and the thrust were

increased with increase of loading. Response at sections #3 and #7 which were at the

haunch region also responded similar to each other indicating the symmetric conditions

prevailed at the field. Moments at these two sections were negative indicating the outward

movement of the culvert at these locations. Thrust values are in compression and increased

with the load.

During the second loading sequence, the magnitude of the moment increased as the

load increased at point #5 where the magnitude of the moment decreased when the load

reached approximately 100 tons. The moment and thrust decreased when additional load

increments were applied. At the load of 113.9 tons, the moment changed its sign and

became insignificant and the thrust changed from compression to a large tension

magnitude. Moment values at sections #4 and #6 were negative but not equal. Moment

value at section #4 is more than the plastic moment capacity of this type of structural plate

indicating the formation of plastic hinge at that location. Moments at section #5 and #6 were

close to it's plastic moment capacity. Visual inspection showed us the formation of hinges at

those locations also. This may be due to the fact that corrosion might have reduced the

~tiffness of the culvert plate since it was exposed to adverse field conditions for the past

fifty years. Thrust value at these sections were in compression and increasing with the load

until 101.6 tons load was on. After the eighth load (103.9 tons) step thrust value started

decreasing and changed to tension at the last step of loading of the second sequence of

loading.

Page 119: analysis of a pipe arch culvert subjected to exceptional live loaiy

105

During the early stage of second loading cycle, the system acted as a composite

beam. The moment and thrust distribution increased in magnitude as applied load

increased. These distribution pattern were symmetrical about the crown point upto the

eighth load increment. Beyond this loading step circumferential stress at the section #4

reached the yield stress. Moment value at this section became higher than that at point #6

therefore, disturbing the symmetric nature of the distribution.

Figure 4.34 explains the nature and exact location of the slippage occured near

the instrumented plane, where the crown seam was the weakest. After the slippage occured

at the bolted joints that section didn't behave like a composite beam rather the system

responded as a truss. Strain gages then gave localized responses.

Fig.4.28 and 4.29 gives the thrust and moment values obtained for section #5 with

increments of the load. Moment values didn't change much after the 88.51 tons in the first

cycle; instead it reduced little and turned negative during the last step of the second cycle

and the whole of the third cycle. Thrust also behaved in the same way. It decreased after

101.6 tons of load and had sudden drastic increase at the last step of the second cycle of

loading. Axial thrust was in compression until the last step of the first cycle and changed

into tension during the last step of loading and remained in tension throughout the third

cycle of loading. After the slippage occured at the bolted joints that section didn't behave

like a composite beam.

Although the load was removed after the second loading sequence, the culvert, as

indicated by the measured deflections, did not recover its original shape. Outside the crown

region, the thrust response did not differ much between the second and the third loading

sequence, and the moment response was smaller during the third loading sequence. The

responses at points #4, #5, and #6 showed some difference between the last two loading

sequences. The moment at point #5 responded slightly more but the thrust remained in

tension. Yield was reached in the longitudinal direction at the crown under 115.5 ton load

Page 120: analysis of a pipe arch culvert subjected to exceptional live loaiy

Vertical Pressure 106

Strain Gages @Point #4

Strain Gages @Point #5

c::::J

Thrust f

Strain Gages @Point #6

Bolted Crown Seam

(a) Initial Stage

Vertical Pressure

Strain Gages @Point #4

Strain Gages @POiI1t #5

Bolted Crown Seam

(b) .Final Stage

FIGURE 4.34 FAILURE MODE OF BOLTED CROWN PLATES UNDER LOAD

Page 121: analysis of a pipe arch culvert subjected to exceptional live loaiy

107

during the third loading sequence.

4.4 PLASTIC MOMENT CAPACITY

The determination of the plastic moment capacity is obviously of great importance

because it is the limiting or maximum moment for the corrugated steel plate. Increasing the

bending moment above the yield moment will cause the strains at the extreme fibers to

increase and the maximum strain will exceed the yield strain Ey . However, because of

perfectly plastic yielding, the maximum stresses will remain constant and equal to cry

The plastic moment capacity of the tested corrugated steel culvert is equal to

3.745 kips-ft/ft, using ultimate yield stress of 30 ksi. Here, it must be noted that the above

definition of the plastic moment doesn't take into account the axial forces. The value of

3.745 kips-ft/ft represents an upper limit. Actual moment capacity will be slightly reduced

when axial forces are considered.

4.5 FORMATION OF PLASTIC HINGES AND CREASES

When Mmax becomes equal to Mp' the cross-section at the center of the beam is

completely plastic. The curvature at the center of the beam is completely plastic. The

curvature. at the center of the corrugation then becomes extremely large and unrestrained

plastic flow may take place. No further increase in the maximum moment can occur, and

the load on the beam is at its maximum value. The corrugation fails by excessive rotations

that occur at the middle cross-section, while the two halves of the corrugation remain

comparatively rigid. Thus, corrugation behaves like two rigid bars linked by a plastic hinge

that permits the two bars to rotate relative to each other under the action of a constant

momentMp.

Page 122: analysis of a pipe arch culvert subjected to exceptional live loaiy

108

Available data from this test indicates that a plastic hinge is formed only at section

#4, at the load of 113 tons of the second cycle of loading. Moment at points #5 and #6

became close to the upper bound plastic moment capacity. After the test, plastic hinge

formation was also observed at these locations. Figure 4.35 shows the formation of plastic

hinges. All the other sections are under their plastic moment capacity. According to

Dessouki. A.K. and Monforton. G.R, "the formation of plastic hinges in the conduit

doesn't constitute complete failure but rather affects the load carrying capacity". Duncan.

J.M. in his study [8] considering both the axial force and the bending moment has

concluded that:

1) Formation of a single plastic hinge will not result in formation of a failure mechanism,

even in an arch structure pinned at the footings. Additional plastic hinges would have to

form before the structure collapses.

2) Even after sufficient hinges have developed in the structure to form a failure

mechanism, the soil will continue to restrain the deformations of the structure.

3) Both aluminum and steel harden when deformed plastically. Therefore, the use of the

value of M p based on minimum values of yield stress provides a conservative estimate of

the ultimate esistance of the metal.

From the above findings we can conclude that the culvert we tested didn't develop a

failure mechanism that would have caused the full failure of the culvert for the above cited

reasons. Further, the maximum load that can be carried by the culvert is equal to 100 tons.

Sections which reached their yield limit were tabulated in Table 4.3. This gives an idea of

the critical sections of the pipe arch culvert with shallow cover.

After the testing was over close inspection of the culvert showed us the formation of

creases in the plate at various location of the culvert. Table 4.4 and the Fig. 4.36 presents

an idea of the location and the size of the creases. Although the formation of the creases

doesn't have any significance towards this study, for the sake of completeness of this

document it is presented here. Creases #1 through #9 were lined up at a distance of about

Page 123: analysis of a pipe arch culvert subjected to exceptional live loaiy

L"",::

.:'Y~~

;~;;":

"',",'i:

:<.·.~f:

~J;.:..t·t

·,::,7:

~'·'

','.

...,.--

,.

..

"0

'."''''f~/-

..··'#

1'1(

'·.'f("'~~.hlr;'t{;b~

--~

·"t."'~-~~,

....".

}~'if

~'"

'-'

-ll"lt

"'1

\fi:.

af&W

o~

.Ii

.J11

00

.~t.Ii

~-_.

,!oo

d•••

:••

...,••••~

.~,

•'-

:'b

r.

••••.

~•••

",'.

,.~;

•.0'

.·,.

••t'~1,'

'o":.~

.o

'-,

w,.

..

~.'.

,.'.

:,[\.~"'~

1~!lSf;tl

'Ii•

.,~~,.~_~.~

•••~;).

••l'

'-,

FIG

UR

E4.

35F

IEL

DP

ICT

UR

EO

FC

UL

VE

RT

CR

OW

NR

EG

ION

SIIO

WIN

GP

LA

STIC

HIN

GE

FOR

MA

TIO

N.....

... ~

Page 124: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 4.3 YIELD STRESS REACHED DURING FAILURE TESTS

* First Sequence of Loading - Sept. 24, 1990

Yield stress was never reached at any monitoring point during loading

* Second Sequence of Loading - Sept. 26, 1990

Section Load Increment No.No. Location Direction

6 7 8 9 10 11 12

Circumf. N N N -Y -Y -Y -yCrest

Longit.4 N N N N N N N

Valley Circumf. N N N N N +Y +y

Longit. N N N N N N N

CrestCircumf. N N N N N N NLongit. N N N N N N N

5 Valley Circumf. N N N N N N NLongit. N N N N N N +Y

Side Circumf. N N N N N N NLongit. N N N N N N N

* Third Sequence of Loading .- .Sept. 26, 1990

Section Load Increment No.No.

Location Direction1 2 3 4 5 6 7

CrestCircumf. N N N N N N NLongit. N N N N N -Y -y

5 Valley Circumf. N N N N N N NLongit. N N N N N +y +y

Side Circumf. N N N N N N NLongit. N N N N N N N

(Note) N =Yield Stress Not Reached; -Y =-cy Reached; +Y =+cy Reached

110

Page 125: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 4.4 LOCATION AND LENGTH OF CREASES DETECTED

Crease Crease Length General LocationL 1 L2

No. (in.) (in.) (in.)

1 3/8 South Side of Crown 13-11/16 24-3/4

2 5/8 South Side of Crown 17-1/4 24-3/4

3-a 3/8 South Side of Crown 20-1/8 24-3/8

3-b 3/8 South Side of Crown 20-1/2 24-3/8

4 5/8 South Side of Crown 23-1/2 24-1/8

5 1-3/4 South Side of Crown 26-5/8 23-3/8

6 1-1/4 South Side of Crown 29-1/2 24-0

7 1/2 South Side of Crown 35-3/8 24-0

8 1-0 South Side of Crown 38-3/4 24-0

9 7/8 South Side of Crown 45-1/8 24-7/8

A 3/4 North Side of Crown 14-1/4 36-3/4

B 1-1/2 North Side of Crown 20-3/8 35-1/2

C 1-5/8 North Side of Crown 26-1/4 36-0

D 1-3/8 North Side of Crown 38-1/8 35-1/2

E 1-1/4 North Side of Crown 44-1/4 35-3/8

111

Page 126: analysis of a pipe arch culvert subjected to exceptional live loaiy

II

I

-----tsiI

I

FIGURE 4.36 MEASUREMENTS TAKEN. TO LOCATE CREASES

112

Page 127: analysis of a pipe arch culvert subjected to exceptional live loaiy

113

24 inches south of the crown (or at a distance of about 9.25 inches north of monitoring

point #6). Creases A through E were detected at a distance of about 36 inches north of the

crown (or at a distance of 2.75 inches north of monitoring point #4).

Page 128: analysis of a pipe arch culvert subjected to exceptional live loaiy

CHAPTER 5

FINITE ELEMENT ANALYSIS

5.1 INTRODUCTION

The design of corrugated metal culverts, until recently, has been largely based on

empirical relations and on past experience with these types of structures. Although these

methods can result in satisfactory designs, their ability to predict the behavior of the soil­

culvert system is rather limited. In these methods, analysis of the structure was done by

assuming a plane strain ring structure subjected to vertical loading. The soil pressure

distribution on the structure is then found from the calculated pipe deflections.

Due to rapid improvements made on the computational ability in the past few

decades, the finite element method has gained large popularity and wide applications. In the

last two decades, the finite element method of analysis was effectively applied to culvert

problems [1,2,5,8,17,]. After its successful introduction in the early 1970's, advances

have been made to incorporate material nonlinearity, construction sequences, and soil­

structure interface elements. In this method, both the soil and the pipe are modeled as

plane-strain continuum.

Finite element method is capable of providing a more comprehensive representation

of the complex soil-structure interaction problem involved. The essential requirement for a

comprehensive finite element simulation are:

1) Inclusion of live load as well as dead load.

2) Adequate presentation of the true geometry and realistic boundary condition.

3) Realistic modeling of the nonlinearities in soil and structure properties.

In this investigation, numerical simulations of structural behavior of the pipe arch

culvert during the failure tests were attempted with the use of the CANDE (Culvert

Page 129: analysis of a pipe arch culvert subjected to exceptional live loaiy

115

ANalysis and DEsign) computer program. It is capable of representing the nonlinear

properties of structural and soil elements as well as the interface element. More detailed

information on the CANDE program is found in References (13,14)

5.2 CANDE BACKGROUND

CANDE can be operated in a design or analysis mode. Here in this chapter only the

analysis mode is briefly discussed. The assumptions common to all solution levels in

CANDEare:

1) Two dimensional analysis with plain strain.

2) Small strain theory

5.2. 1 SOLUTION LEVEL

There are three solution levels in CANDE. Levell corresponds to the elastic,

closed form solution. However this level cannot consider such features as arch-shaped

structures on footings, and the several zones of backfill material, all of which are important

consideration in this study. Level 2 is finite element solution where the mesh is

automatically created by CANDE whereas in level 3, which is also finite element analysis,

the mesh is defined by the user.

5.2.2 PIPE TYPES

The pipe material library in CANOE includes corrugated steel, corrugated

aluminum, concrete, plastic and basic pipe types. In our case corrugated steel pipe type

was used. In this type uniform geometric properties of the wall section are assumed

throughout the culvert periphery. Both linear and bilinear constitutive models of the pipe

material are allowed under this type. In this analysis the bilinear model is used.

Page 130: analysis of a pipe arch culvert subjected to exceptional live loaiy

116

5 .2 .3 ELEMENT TYPES

There are three basic types of elements available in CANDE (1) Beam-Column

element; (2) Quadrilateral element (3) Interface element. In this analysis only Beam­

Column element and quadrilateral element are used. Normally Interface element is provided

to allow frictional sliding, separation and rebinding of elements meeting at a common

interface. Here in this analysis we avoided using this element to solve the convergence

problem encountered by others.

5.2.4 SOIL MODEL

At present there are five soil models available in CANDE:

1) elastic

2) ortho-elastic

3) over-burden dependent

4) hardin model

5) Duncan model

Considering soil's non-linearity and non-homogeneity it is determined that soil can

be best represented by Duncan's stress-strain hyperbola model [9,10,11]. In order to derive

the Duncan's constitutive parameters several triaxial tests were conducted with the samples

obtained from the test site. The main reasons for selecting this model are; (1) its availability

as a part of the soil model library in the CANDE program, (2) its incorporation of the minor

principal stress in defining initial and failure stresses; and (3) ease in obtaining its

parameters from ere (conventional triaxial compression) tests. Someshortcomings of this

model is that it is not suitable for predicting the soil behavior where the loading conditions

induced stress paths other than that of the ere within the soil mass.

5.3 FIELD SOIL SAMPLING WORK

The backfill soil sampling work was conducted on April, 1, 1991, about six

months after the completion of the field testing. The equipment utilized was a standard

Page 131: analysis of a pipe arch culvert subjected to exceptional live loaiy

117

truck mounted rotary drilling rig. The rig was set within the west shoulder section of the

the roadway above the culvert, since the subsurface soil data was previously obtained at the

location (as seen in Fig. 2.2) and a complete blockage of the local traffic posed a problem.

The goal of the sampling work was to obtain a few relatively undisturbed soil samples from

each of the three (crown, haunch, and springline) regions on both the east and west sides

of the culvert structure. A total of six soil samples were taken by hydraulically pressing at

a constant rate three inch O.D. thin-walled sampler. Upon removal of the sample tubes

from the holes, their ends were double-sealed with special caps. Later, they were

transported to the CGGR research laboratory in a wooden cradle.

5.4 LABORATORY SOIL TESTING METHOD

The conventional, consolidated and undrained (or CD) triaxial testing procedure

was selected as a method to characterize the shear strength parameters and stress-strain

characteristics of the sampled backfill soil materials. A total of 14 tests were performed

using T-1500 triaxial testing device. To measure volumetric strains during the test, changes

in the volume of water inside the triaxial cell were monitored with a graduated tube. For

each test, a soil sample extracted from the tube was inspected to make sure that it had no

defect and then trimmed down to a diameter of 2.8 inches and a height atleast twice the

diameter. It was wrapped completely with a rubber membrane. Loading platens were

attached with O-rings at the top and at the bottom, inside the triaxial chamber, with porous

stone plates inserted between the soil specimen and the platens. To initiate the testing

process, the chamber was filled with distilled water and a confining pressure ranging from

5 to 15 psi was applied to consolidate the soil. Table 5.1 presents some basic information

regarding each triaxial test. Strain-controlled axial loading was exerted with a ram and the

load was measured using a proving ring. To compute axial stresses during the test, the

cross-sectional area of the specimen was corrected to account for Poisson's effects. The

instantaneous area was computed using volumetric strain data and assuming the cross­

section was equal along the length of the specimen.

Page 132: analysis of a pipe arch culvert subjected to exceptional live loaiy

TA

BL

E5.

1B

AS

ICIN

FO

RM

An

ON

ON

TR

IAX

IAL

TE

ST

S

Tes

tS

ampl

eS

ampl

eC

on

fin

ing

Mo

istu

re•

Den

sity

•N

o.B

orin

g1.

0.D

epth

(ft.

)Z

one

Pre

ssur

e(p

si)

Co

nte

nt

(%)

(pef

)

1A

IP9.

1-9.

6C

row

n10

.017

.44

136.

74

2A

IP8.

5-9.

0C

row

n5.

013

.91

121.

67

3B

IP7.

9-8.

4C

row

n15

.018

.40

NT

4B

IP7.

4-7.

9C

row

n5.

017

.60

133.

39.

5A

2P

12.4

-12.

9S

ho

uld

er

15.0

2~.28

133.

60

6A

2P11

.9-1

2.4

Sh

ou

lde

r10

.032

.65

133.

33

7.B

2P12

.4-1

2.9

Sho

ulde

r10

.016

.67

131.

50

8A

2P10

.9-1

1.4

Cro

wn/

Shou

lder

5.0

28.1

312

3.10

9B

3P15

.8-1

6.3

Spr

ingl

ine

10.0

21.2

711

9.67

10B

2P11

.9-1

2.4

Sho

ulde

r5.

022

.84

132.

48

IIB

3P15

.3-1

5.8

Spri

nglin

e5.

024

.80

117.

40

12A

3P15

.8-1

6.3

Spri

nglin

e15

.029

.05

120.

56

13A

3P15

.3-1

5.8

Spri

nglin

e10

.018

.56

135.

37

14B

3P14

.8-1

5.3

Spr

ingl

ine

15.0

26.7

111

9.05

(Not

e)T

hesy

mbo

l".

"in

dica

tes

initi

alva

lues

.~ ~ 0

0

Page 133: analysis of a pipe arch culvert subjected to exceptional live loaiy

119

5.5 RECOMMENDED SOIL PARAMETERS

The Duncan soil model is a variable moduli (or nonlinear) model which

characterizes soil behavior with tangent Young's modulus and bulk modulus. The

guidelines suggested by Duncan [Duncan et al.,1980] were followed in deriving the

hyperbolic model parameters.

Duncan recommends fitting the hyperbola throug~ only two points on the stress­

strain curve: 70% and 95% of the failure strength of each test. This is accomplished on the

plot of transforrned axes where a hyperbola plots as a straight line. The Duncan soil model

contains a total of eight parameters K,n,Rf,<I>O,~$,c,Kb' and m. Derivation procedure of

the two shear strength parameters c and <t> through triaxial test results is well known. A

systematic determination of the remaining six soil parameters out of triaxial test data has

been presented in details by Duncan [10]. These procedures are briefly summarized in

Table 5.2. Recommended values for all eight parameters were tabulated in Table 5.3.

5.6 FINITE ELEMENT SIMULATION

Half mesh is used to represent structure and backfill for our problem. This is

acceptable since the structure and the loading conditions were assumed to be symmetrical.

Mesh was created using both design and the measured shape of the culvert. Figure 5.1

explains the node numbering and element numbering system used for this analysis.

The boundary conditions established at the nodes are 1) nodal points along the bottom

boundary were fixed in both the vertical and horizontal directions. 2) The nodes on the

right and left sides of the mesh are fixed in the horizontal direction but free to move in the

vertical direction.

The asphalt layer was represented by quadrilateral elements. The modulus of 1000

ksi was used to simulate the compacted form of the asphalt. The pipe material selected out

of the CANDE library was corrugated steel with bilinear constitutive models. Pipe was

Page 134: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 5.2 DUNCAN'S HYPERBOLIC SOIL MODEL PARAMETERS

120

Parameters

K = Modulus Number:

n = Modulus Exponent:

R f = Failure Ratio:

c = Cohesion Intercept:

<t>0 = Friction Angle:

~ <p = Reduction in <t>

For IO-Fold Increases:

Kb= Bulk Modulus Number:

m =Bulk Modulus Exponent:

Determination Procedure

From Relating Initial Modulus ToConfining Pressure

From Relating Initial Modulus ToConfining Pressure

By Dividing Failure Shear Stress ByUltimate Shear Stress

From Mohr-Coulomb Failure Criterion

From Mohr-Coulomb Failure Criterionand Relating <t> To o 3

From Mohr-Coulomb Failure Criterionand Relating <I> To 0'3

From Relating B To o 3

From Relating B To a 3

Page 135: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 5.3 A SUMMARY OF MATERIAL PARAMETERS

* Steel (Bilinear Elastic)

Initial Young's Modulus, E1 =30 x 106@'si.Secondary Your Modulus, ~= 1.76 x 10 psi.Poisson's Ratio, U =0.3.Yield Stress, 0y = 33,000 psi.

* Asphalt (Linear Elastic)

Young's Modulus, E =lxlO6

psi

Poisson's Ratio, U = 0.41

* Backfill Soil (Hyperbolic Model)

~ Experimental CLIOO SMI00

c 1.44 psi 2.78 psi O. psi

<P 0.423 radians 0.524 radians 0.628 radians

~<P o. o. 0.14

Rf 0.706· 0.700 0.700

K 37 150 600

n 0.217 0.450 0.250

Kb 410 140 450

m 0.49 0.20 o.

121

Page 136: analysis of a pipe arch culvert subjected to exceptional live loaiy

122

24

61

03

74

64

54

41

28

36

84

48

94

73

79

85

67

175 1

I165

ISS 1

1

131 I

124 1~ ..... Ll 3 112 10 106114 -- 111 08

109 97107 105

99 100 101 102 I

104 96 .e

9S89

90 91 92 9388

87

86 81 82 83 84

8

'7475 76 77 78

) 68 69 70 71 72

/62 63 64 65 66

:c 57 58 59 60

S5-~ 54

50 51 52 5349

37 38 39 40 41 42 43 44 45 46 47

25 26 27 28 29 3C 31 32 33 34 3S

13 14 IS 16 17 16 19 20 21 22 23

142129116

115

2 3 4 5 6 7 8 10 1 J 12

FIGURE5.1 NODE NUMBERING SYSTEM USED FOR THE HALF MESH

Page 137: analysis of a pipe arch culvert subjected to exceptional live loaiy

123

represented by the beam-column elements. Interface elements between pipe and backfill

material were not used inorder to avoid the convergence problems as reported by others.

(Alan Rauch 1990)

Live load applied by hydraulic cylinders was converted to line load by the method

proposed by Duncan and Drawsky. This method is based on load distribution in a semi­

finite space. This method models an axle with several wheels by a line load which provides

the same maximum vertical stress beneath the wheels on a plane at the depth of the top of

the culvert crown as would the actual three-dimensional wheel loading, based on

Boussinesq linear elastic vertical stress distribution analysis. This method is considered to

be conservative because it provides a line load producing this peak stress along the full

length of the culvert, whereas wheel loads provide this stress only beneath the wheels with

stresses away from the wheel loading points. This inherent conservatism is minimized in

corrugated culverts which do not have significant flexural stiffness longitudinally along the

culvert and which are, therefore, vulnerable to localized overstressing directly beneath

discrete wheel loads.

Duncan and Drawsky developed a simple equation and tabulated solution

expressing their equivalent line load estimation procedure as

LL=AL/K4

where LL equivalent line load (kips/ft)

AL. total axle load (kips) and

K4 load factor (ft)

In this analysis K4=8.7 ft was used, which is corresponding to 3 ft. cover and 4

wheels per the axle. The load factor (K4) values, based on Boussinesq elastic analysis for

various depths of soil cover and under different contact areas, are presented in Table 5.4.

No simulation of the first day test (the first load sequence ) conditions was

Page 138: analysis of a pipe arch culvert subjected to exceptional live loaiy

TABLE 5.4 LOAD FACTOR (~) FOR VARIOUS COVER DEPTHSAND LOADING CONDITIONS

Values of Load Factor K4 (ft.)

Number of Wheels Per AxleCover Depth

(ft.)

2 4 8

1 4.3 5.0 8.5

2 5.3 6.4 9.2

3 7.9 8.7 10.6

5 12.3 12.5 13.5

7 14.4 14.5 14.6

10 16.0 16.0 16.0

(Note) This information was obtained after Ref. [7].

124

Page 139: analysis of a pipe arch culvert subjected to exceptional live loaiy

125

attempted, since most of the deflections took place and a moderate degree of structural

failure was achieved during the second and third loading sequences. The mesh consists of

184 nodes, 21 beam elements and 151 quadrilateral elements. A total of 5 types of CANDE

computer program simulations were made. These simulations were done as summarized

below:

Simulation #1: Experimentally derived soil parameters were input for the entire

backfill soil region. (A symbol "K" is used in the graphical plots

to indicate results from this simulation.)

Simulation #2:

Simulation #3:

Simulation #4:

Simulation #5:

Same as simulation #1, but the parameter K value was increased

to 3K. (A notation "3K" is used in the graphical plots to indicate

results from this simulation)

Two material types from the CANDE soil material property

library (CLIOO and SMlOO) were specified in the backfill soil

region according to the boring log data. (see Figure 5.2 for

locations of the two soil types. Results from this simulation

were denoted by "FIELD-K" in the graphical plots.)

Same as simulation #3, but the K values were magnified by a

factor of 3. (Results from this simulation were denoted by

"FIELD-3K" in the graphical plots.)

Two material types from the CANDE soil material property

library (CLl00 and SMl(0) were specified in the backfill

region, as shown in Figure 5.3. (Results from this simulation

were denoted by "ClOOS100" in the graphical plots.)

Page 140: analysis of a pipe arch culvert subjected to exceptional live loaiy

6

151 152 154

136 142 143 145124 130 131 133

24

12 3 119 120 121

FIGURE 5.2 VARIOUS MATERIAL ZONES DEFINED FORSIMULATION #3

Page 141: analysis of a pipe arch culvert subjected to exceptional live loaiy

20

FIGURE 5.3 VARIOUS MATERIAL ZONES DEFINED FOR SIMULATION #5

127

Page 142: analysis of a pipe arch culvert subjected to exceptional live loaiy

128

s. 7 CANDE PREDICTIONS AND DISCUSSION .

The parameters for Duncan's soil model were obtained from the triaxial test results

and from the CANDE library. Calculation of CANDE predictions were stopped whenever

the stress level at any point of the structure reaches it's yield limit. Deflections predicted by

CANDE were compared with the field results. Figures 5.4 through 5.8 presents the

comparisons for #5 through #9. The deflections predicted by CANDE for all the points

were in the conservative side. The large error in the CANDE predictions occured because

of one or more of the following factors.

1. The soil samples obtained for the triaxial testing came from the shoulder part of

the road section. These soil samples were relatively loose compared to the soil

under the pavement section because of the compaction occured due to live loads

applied over the last 37 years.

2. It is very difficult to simulate in the laboratory that the type of compaction the

soil material experienced in the field.

3. The stress distribution did not distributed uniformly, after the slip took place at

the bolted crown seam.

4. The maximum deflection in the field occured little away from the instrumented

section. CANDE is not capable of analyzing the three dimensional problem.

The finite element simulation predictions for moment and thrust were generally

higher, but the trend was similar. Figures 5.9 through 5.16 presents the moment and thrust

distribution graphs. Thrust predictions agreed well in the higher loading steps. Moment

predictions agreed well at points #6 and #9. variation in the magnitude of the moment is

high at the crown and haunch region. The reasons for high discrepancy in the finite element

predictions were may be due to the above cited reasons.

Page 143: analysis of a pipe arch culvert subjected to exceptional live loaiy

129

70605040-8 -+--~-.....---...---......----..---~--.-~

30

0-0-- EXPT.

• K,..-.....c --a-- 3K~ -2= --0-- FIELD-K....

'""-'"N FIELD-3K,......

0 -{;r- CIOOSIOO...-4~

QJ.....QJ

Q

-6

Total Load Applied (tons)

FIGURE 5.4 COMPARISON OF DEFLECTION OFMONITORING POINT #5 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS

Page 144: analysis of a pipe arch culvert subjected to exceptional live loaiy

.-.....-2~

~......~

Q-3

-4

-530

1...,...-------------- --0-- EXPT.

• K~ 0 D ,,,"" ,,,,,,,,-"',,,,,w''',,, , eM,""'""",,,,, ~ 3K

~ 1e::::::~===:T-t::=:::-----....._~ -0- FIELD-K

=~ -1 " FIELD-3K

= ---tr- Cl00S 100o

40 50 ~ 70Total Load Applied (tons)

FIGURE 5.5 COMPARISON OF DEFLECTION OFMONITORING POINT #6 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS

130

Page 145: analysis of a pipe arch culvert subjected to exceptional live loaiy

131

70605040

0.2 ...,.---------------. ---iJ-- EXPT.

• K---a- 3K

-0- FIELD-K

M FIELD-3K

--tr- C1005100

-1.2 -+-----.--.....---..--.---.,.----+------.,.----1

30

0.0 a a~

~ 0==--.: -0.2 ... "..."..,.'-'."'-'"

=.= -0.4-­~~

~ -0.6Q

-0.8

Total Load Applied (tons)

FIGURE 5.6 COMPARISON OF DEFLECTION OFMONITORING POINT #7 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS

Page 146: analysis of a pipe arch culvert subjected to exceptional live loaiy

132

0.2 ~---------------. ---cr- EXPT.

• K~ 3K

70605040-0.8 -+-------.---......---....--.-----,.--.....----flA-----I

30

=-0.2...........~~

cQ-0.4

Total Load Applied (tons)

FIGURE 5.7 COMPARISON OF DEFLECTION OFMONITORING POINT #8 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS

Page 147: analysis of a pipe arch culvert subjected to exceptional live loaiy

133

70

--0-- EXPT.

• Ko 0 Q,u",u,,,,,n, "'"

~; --a-- 3K--0-- FIELD-K

M FIELD-3K--t:r- CIOOSIOO

40 50 60Total Load Applied (tons)

-1.2-+-----.---+-----..--.----..--..+------,,.......----1

30

0.2-r----------~---

=.:-0.4......~QJ

~·O.6Q

-0.8

FIGURE 5.8 COMPARISON OF DEFLECTION OFMONITORING POINT #9 BETWEENFIELD RESULTS AND VARIOUSCANDE PROGRAM SIMULATIONS

Page 148: analysis of a pipe arch culvert subjected to exceptional live loaiy

134

-5 ~,............. ..........t

125 150 175 200 225 250 275 300

0--0-- EXPT.

• K~ -I

~ 3K"....----~ ----0-- FIELD-KQ..-~ -2

M FIELD-3K---ts:-- CIOOSIOO.......

ir:

=-,.c -3~

-4

Unfolded Length (inch)

FIGURE 5.9 COMPARISON OF THRUST DUE TO30.79 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS

Page 149: analysis of a pipe arch culvert subjected to exceptional live loaiy

4-iJ-- EXPT.

3 • K

---a-- 3K~ --0-- FIELD-K..

». FIELD-3K

--fr-- CIOOSIOO

-1

-2 ~~""""""-~~"""""".....-r-P"""""""~~......-r-i"-~......-t

125 150 175 200 225 250 275 300

Unfolded Length (inch)

F-'IGURE 5.10 COMPARISON OF MOMENT DUE TO'30.79 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIlVlULATIONS

135

Page 150: analysis of a pipe arch culvert subjected to exceptional live loaiy

136

.,...--0- EXPT.

• K

---a-- 3K...-... 0~ -0-- FIELD-K--v:

M FIELD-3KQ....~ --&- CIOOSIOO'-'"

..... -2v:='-.c

E--

-4

-6 .............~~...........,...................................~~-r-r-i-......,..,.~

125 150 175 200 225 250 275 300

Unfolded Length (inch)

FIGURE 5.11 COMPARISON OF THRUST DUE TO38.48 TON LPAP BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS

Page 151: analysis of a pipe arch culvert subjected to exceptional live loaiy

5..,....------------

4

-3 -+-t-P...........~..................................,I"""'P'"'P"....._r_9.................,...,......,...,......._t

125 150 175 200 225 250 275 300

Unfolded Length (inch)

~ EXPT.

• K--e-- 3K

--<>-- FIELD-K

M FIELD-3K

----&- CIOOSIOO

137

FIGURE 5.12 COMPARISON OF MOMENT DUE TO38.48 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS

Page 152: analysis of a pipe arch culvert subjected to exceptional live loaiy

138

-6

-7

-8 ~-.--.-r..............~--.--.--,~~~~,.-.,-,-~or-r-r-I

125 150 175 200 225 250 275 300

1-0-- EXPT.

0 • K

~ -1--a-- 3K

~ ---<>-- FIELD-K---~ 2Q. - )4 FIELD-3K...~

~ CIOOSIOO'-"'" -3~v:

= -4~

.cE- -5

Unfolded Length (inch)

FIGURE 5.13 COMPARISON OF THRUST DUE TO50.03 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANOESIMULATIONS

Page 153: analysis of a pipe arch culvert subjected to exceptional live loaiy

139

150 175 200 225 250 2"75 300

--0-- EXPT.• K

----e- 3K-0-- FIELD-K

a FIELD-3K

• CIOOSIOO

6-r---------------.

5

~ 4~--~ 3

Iv:c.. ~..... ~

~'-'" 1......~ 0ee -1:;

-2

-3

-4-5 ~~_.__.__r~~~.............._.__._r""'_;_'O~...,....,...,~

125

Unfolded Length (inch)

FIGURE 5.14 COMPARISON OF MOMENT DUE TO50.03 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS

Page 154: analysis of a pipe arch culvert subjected to exceptional live loaiy

2..,...------------

o,-.............~ -2c..-~""-'" -4

-8

-10

-12 ............-----.......--....~---..-- .............~~.....-............-- .......

125 150 175 200 225 250 275 300

Unfolded Length (inch)

---0-- EXPT.

• K----a- 3K--0-- FIELD-K

M FIELD-3K

--fr- CIOOSIOO

140

FIGURE 5.15 COMPARISON OF THRUST DUE TO65.43 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS

Page 155: analysis of a pipe arch culvert subjected to exceptional live loaiy

7

5

~

3~--~

IrI). 1c..-~"'-'"

~ -1=~eQ -3:;

-5

-7 -+-.-.--.-.r-.............-.........................................,.....,..-,...............,..-,--,.-....-r-r-or-r-r-.,.-r-r.......-t

125 150 175200 225 250 275 300

Unfolded Length (inch)

141

--0- EXPT.• K

--a-- 3K---0- FIELD-K

M FIELD-3K

--lr- CIOOSIOO

FIGURE 5.16 COMPARISON OF MOMENT DUE TO65.43 TON LOAD BETWEEN FIELDRESULT AND VARIOUS CANDESIMULATIONS

Page 156: analysis of a pipe arch culvert subjected to exceptional live loaiy

142

A parametric study was also conducted to determine the influence of the modulus

number. Duncan and his co-workers have speculated, for loose soils modulus number may

be increased upto three times the value of K to incorporate the loading and unloading

effect. To determine this effect, we have done a simulation by increasing the value of the K

by three times. Influence of the parameter changes was not significant. The value of the

modulus exponent "n" is always very similar for primary loading and unloading, and in the

hyperbolic relationships it is assumed to be the same.

Page 157: analysis of a pipe arch culvert subjected to exceptional live loaiy

CHAPTER 6

CONCLUSIONS AND RECOMMENDATIONS

6.1 SUMMARY AND CONCI.JUSIONS

A full-scale field test was conducted in a long span pipe arch culvert. An

exceptional live load was applied through two hydraulic cylinders. Field data were collected

and analysed for all three loading sequences. Finite element simulations were conducted

using the CANDE computer code. Duncan's hyperbolic soil model was used to simulate the

backfill soil. Tape extensometer was used to determine the shape of the culvert before and

after the test. Although it gave fairly accurate data, collection of such data was very time

consuming. Position transducers were used to collect deflection data upon each loading

step. Strain gage data was also collected upon each loading step. Hp data acquisition

system was used to collect data from the position transducers and strain gages. The

following conclusions were made at the end of the study:

* The maximum load carrying capacity of a pipe arch culvert, with 3 feet

cover of cohesive soil was determined to be approximately 100 tons.

* The maximum moment capacity of the pipe arch culvert is 3.745 kips-ftlft

(without taking axial forces,into account)

* The maximum vertical crown deflection was 6.99 inches for approximately

115 tons during the third loading sequence.

* Partial failure occured due to the formation of plastic hinges.

* Severe distress occured at the crown region and a slip occured at the bolted

connection. After that the culvert responded like a truss rather than a

Page 158: analysis of a pipe arch culvert subjected to exceptional live loaiy

composite beam. 144

* Critical sections of this type of culvert was determined to be sections four

five and six. (Although section six didn't reach its yield limit, it was very

close to doing so.)

* Formation of creases were observed approximately two feet away from the

instrumented region on both south and north sides.

* Generaly moment and thrust distribution were as expected. Both increased

till the loadwas approximately 100 tons during the second loading sequence.

Severe distress occured at the crown region for the higher loading steps and

the thrust at the crown increased sharply and moment became very small.

* Deflection predicted by finite element simulations always larger than the

field results. Moment and thrust predictions were also very large but the

trend agreed well with the field results.

* Parametric study undertaken to determine the influence of modulus number

"K" gave better agreement for the deflection between the field and CANOE

predictions. This parametric study didn't give good agreement for

moment and thrust between field results and theoretical values.

6.2 RECOMMENDATIONS

Tape extensometer readings should be taken after each step of the loading to

eliminate the error caused in the deflection calculation because of the change of angle in the

the position transducer wire. Actual deflection is not two dimension as we assumed.

Attempts should be made to measure the three dimensional deflection in the future research

work.

Page 159: analysis of a pipe arch culvert subjected to exceptional live loaiy

145

Soil boring should be done exactly over the crown region to get good soil

parameters for the Duncan's soil model. Using multiaxial device and different stress paths

for the soil testing is recommended.

For finite element simulation of live load, a better method for converting the

concentrated load to line load should be used. A simpler technique is needed to model this

type of loads for plane strain analysis. Although it may be on the conservative side, it is

safer to use CANDE as a design tool for these type of structures. Analysis of this type of

structures using CANDE should be subjected to further research.

Page 160: analysis of a pipe arch culvert subjected to exceptional live loaiy

REFERENCES

1. Abdel-sayed, George, and Baidar Bakt (1982), "Analysis of live-load effects in soil­

steel structures," Soil-structure interaction of subsurface conduits,Trans.Research Record 878, TRB, Washington, D.C., pp. 49-55.

146

2. Alan, F. Rauch (1990) "Experimental and numerical investigation of a deep-eorrugated

steel, box-type culvert." Thesis presented to Ohio University, Athens, Ohio, inpartial fulfillment of the requirements for the Degree of Master of Science in Civil

Engineering,June.

3. Beal, David B. (1982), "Field test of long-span aluminum culvert," Joum. ofGeotechnical Eng. Div., ASCE, Vol. 108, No.GT6, June, pp. 873-890.

4. Cary, Raymond L. (1986), "Inelastic flexural stability of corrugations," Durability,

strength, and analysis of culverts and tunneling machines, Trans. Research Record1087, TRB, Washington, D.C., pp 87-91

5. Chang, Ching S., Julio M. Espinoza, and Ernest T. Selig (1980), "Computer analysis

of Newton Creek culvert," Joum. of Geotechnical Eng. Div., ASCE, Vol. 106,No. GT5, May, pp.531-556.

6. Dessouki, A.K., and G.R. Monforton (1986), "Effect of soil failure on soil-steel

structures," Joum. of Geotechnical Eng., ASCE, Vol.112, No.5, May, pp.522-36.

7. Duncan, James M., Seed R. B., and Drawsky, R.H (1985) "Design of Corrugated

Metal Box Culverts," Trans. Research Record 1008,TRB,Washington D.C., pp 33-41.

8. Duncan, James M. (1979), "Behavior and design of long-span metal culverts," Joum.

of Geotechnical Eng. Div., ASCE, Vol. 105, No GT3, March, pp. 399-418.

9. Duncan, James M. (1980), "Hyperbolic stress-strain relationships," Proc. of theWorkshop on Limit Equilibrium, Plasticity, and Generalized Stress-Strain in

Geotechnical Engineering, ASCE, New York, May, pp. 443-60.

10. Duncan, J.M., and C.~Chang (1970), "Nonlinear analysis of stress and strain in

soils," Joum. of Soil Mechanics and Foundations Div.,ASCE, Vol.96, No.SM5,

Page 161: analysis of a pipe arch culvert subjected to exceptional live loaiy

September, pp. 1629-53. 147

11. Duncan,J.M., Byrne,P., Wong, K.S., and Mabry, P., "Strength, Stress-Strain and

Bulk Modulus Parameters of Finite Element Analysis and Movements in Soil Masses",

Report No. UCB/GT/80-01, University of California, Berkeley, 70pp, August 1980.

12. Ghobrial, Medhat, and George Abdel-Sayed (1985), "Inelastic buckling of soil-steel

structures," Culverts: analysis of soil-culvert interaction and design, Trans.

Research Record 1008, TRB, Washington, D.C., pp. 7-14.

13. Katona, M.G., and J.M.Smith (1976), "CANDE user manual," Report No. RD-77-6,

Fed. Highway Adrnin., Washington, D.C., October.

14. Katona, M.G., J.M. Smith, R.S.Odello, and J.R. Allgood (1976), "CANDE: amodern approach for the structural design and analysis of

buried culverts," Report No. FHWA-RD-77-5, Fed. Highway

Admin.., Washington, D.C., October.

15. Kondner, R.L. (1963), "Hyperbolic stress-strain response: cohesive soils," Jour. of

the Soil Mechanics and Foundations Div., ASCE, Vol 89, No. 8M1, February, pp.115-143.

16. Meyerhof, G.G., and Baikie, L.D., "Strength of steel culvert sheets bearing against

compacted sand backfill."

17. Seed, R.B., and J.R.Raines (1988), "Failure of flexible long-span culverts under

exceptional live loads," Presented at 67th Annual Meeting of the TRB, Washington,

D.C.,pp. 37-45.

18. Selig, Ernest T., and Samuel C.Musser (1985), "Performance evaluation of a rib­reinforced culvert," Culverts: analysis of soil-eulvert interaction and design, Trans.

Research Record 1008, TRB, Washington, D.C., pp. 117-122.

19. Wong, K.S., and J.M. Duncan (1974), "Hyperbolic stress-strain parameters for

nonlinear finite element analyses of stresses and movement in soil masses," Report

No. TE 74-3, University of California, Berkeley, July.