Page 1: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

An Overview of the

SIBC Process and Projects

Presented By: Rebecca Nix, SE Michael Arens, SE

UDOT Michael Baker International

February 2015

Page 2: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

ABC – Development to Standard Practice

Procurement Tools to Implement Innovation

Early Development of New Process

Evolution of ABC to Norm

Slide-In Bridge Construction (SIBC) Guide

Page 3: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Design-Build (DB)

Owner Prescribes Outcome with DB Teams Innovating

Fosters Innovation in a Competitive Forum

Transfers Majority of Risk to DB Team

Requires Owner Flexibility

Requires Owner Involvement in Construction

Page 4: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Construction Manager / General Contractor (CM/GC)

Designer & Contractor Innovation

Joint Development of Plans & Specs - Ownership

Continued Partnership of Designer & Contractor into Construction

Gives Owner Authority to Steer Project to ABC

Page 5: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Development of UDOT’s Early Slide-In Bridge

Construction

Design-Build RFP Severely Limited Closure Times

Terrain Not Conducive to SPMTs

Cross-Street Not Primary; Allowed Closures

Approach Slab Sliding with Bridge

UDOT Open & Encouraging

Team Provided Overall Engineering Approach

Page 6: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Moving ABC to More Mainstream

FHWA’s Encouragement

Project Showcases

Industry Presentations

Development of Guidance Documents

Move into Bid-Build

Page 7: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Development of SIBC Guide

Every Day Counts (EDC) II Initiative by FHWA through DOTs

Utah Department of Transportation (UDOT) Assigned SIBC Guide:

Michael Baker International

H. Boyle Engineering

Ralph L. Wadsworth

Page 8: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Overview of SIBC Guide

Introduction of SIBC

Owner Considerations

Design Considerations

Construction Considerations

Page 9: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Slide-In Bridge Construction (SIBC)

Is an Accelerated Bridge Construction (ABC) technique

New bridge superstructure is constructed adjacent to the existing structure while it remains in service

New substructures constructed:

Simultaneously under or behind existing bridge

Immediately after demolition

OR – existing substructures rehabilitated

Page 10: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Benefits to SIBC vs. Traditional Construction

Reduced Traffic/Mobility Impacts

Shortened On-Site Construction Time

Potentially Reduced Project Costs

Enhanced Safety – Workers and Public

Improved Quality & Constructability

Page 11: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Common Applications of SIBC

More Traffic over the Bridge than under

Significant User Cost Savings & Safety

Long Detour/No Detour Routes

Shortened Overpass Bridges

Narrow Bridge or Limited Phasing

Applicable for Common Bridge Replacements

Page 12: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Challenges to Evaluate During Planning of SIBC Include:

Profile Changes

Limited ROW for Staging

Geometric Constraints

Utility Impacts

Lack of SIBC Experience

Page 13: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

For the Owner:*

Define Desired Benefits

How Fast? Detour Required?

Incentives / Disincentives

Procurement Method

Public Involvement Plan

*(see Table 2-4 of SIBC Guide)

Page 14: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

$ SIBC Can Decrease Cost By:

Eliminate Crossovers or Temporary Bridges

Less Maintenance of Traffic (MOT) & Detours

Reduced Time & Project OH Costs:

DOT Oversight, Administration, and CE&I

Contractor OH Costs

User Costs

Page 15: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

$ SIBC Can Increase Cost with:

Slide Equipment

Labor for Slide

Right-of-Way (ROW)

Temporary Supports

Time/Penalty Costs (RISK)

First-Time Costs

Page 16: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

SIBC Bridge Layout Options

Shorten Bridge

Build new abutments concurrently

Installing Abutments behind Existing Bridge

Other ABC elements

Working in protected trench

Semi-Integral Abutments Work Best

Page 17: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

SIBC Bridge Layout Options (Continued)

Foundation Solutions

Micropiles

Straddle abutments or bent

Spread

Re-Use existing

Page 18: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Temporary Works & Material Design

Calculate Loads for Temporary Supports

Sliding Forces Should Account for Conditions

Temporary Support to Permanent Substructure Connection

Soil Conditions Affect Support Foundations

Bridge to Roadway Connection

Approach & Sleeper Slabs

Joints & Backfill

Roadway Tie-In Design

Page 19: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Types of Slide Systems

Industrial Rollers

Teflon Pads

Page 20: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Types of Slide Systems (Continued)

Winches & Mechanical Pulling Devices

Hydraulic Jack

Post-Tensioned (PT) Jack

Page 21: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

Schedule Considerations

Partial Demolition with Phased Bridge Slide

Bridge Demolition & Slide Time

Approach Slab & Roadway

Tie-In

Bridge Layout Considerations

Approach Slab Challenges

Roadway Impacts and Geometry

Page 22: An Overview of the SIBC Process and Projects...Slide-In Bridge Construction (SIBC) Is an Accelerated Bridge Construction (ABC) technique New bridge superstructure is constructed adjacent

SIBC GUIDE, Information, and Presentations

www.slideinbridgeconstruction.com

www.fhwa.dot.gov/construction/sibc/

+ =