An integral analysis of a UN program for rural electrification with renewable energy
II Congreso Boliviano de Ingeneria Mechanica Electromechanica
Ing. Michiel van der Griendt, translated by Sergio Muñoz
Research project of:
07 October 2005 2
Research project of:
Index
• Project description• Research plan• Phase I: Obtain information about RREE projects• Phase II : Selection of RREE projects• Phase III : Evaluation of the selected projects• Phase IV : Asses the self-supporting potential• Phase V : Investigate possibilities for further
development• Current state of the research• Conclusions• Questions
07 October 2005 3
Research project of:
Project description• Objective of the research project:
- Get more insight into the UN Rural Renewable Energy Electrification projects in the Department of Oruro
- Assessment of the self-supportive potential of the projects
- Investigate possibilities for future development
• Period of the research:Three months (01-09-05 to 15-09-05)
• Project people:Prof.dr.ir. A.H.M. Verkooijen in Holland Ing. E. Peñaranda Muñoz in BoliviaIng. M. van der Griendt
07 October 2005 4
Research project of:
Research plan
• The research program consist of 5 phases
I Obtaining information about the RREE projectsII Selecting of the RREE projectsIII Evaluating the selected projectsIV Asses the self-supporting potentialV Investigate possibilities for further development
07 October 2005 5
Research project of:
Phase I : Obtain information about RREE projects
For obtaining complete information there are mainly tree information sources:
• The Technical University of Oruro
• The governmental institutions Oruro(La Prefectura and municipial governments)
• The electricity distribution company (ELFEO)
• The United Nations Development Program
07 October 2005 6
Research project of:
Phase I : Obtain information about RREE projects and the conventional grid
Current state of the electricity grid and some rural electrification projects
=> LIST OF GOVERNMENTAL RRE PROJECTS
07 October 2005 7
Research project of:
Phase I : Obtain information about RREE projects and the conventional grid
Project Used TechnologyChipaya PV-TechnologyBella Vista PV-TechnologyTodos Santos Small HydroSajama PV-TechnologyConception de Belen Huari PV-TechnologyOrinoca PV-TechnologyPoopo PV-TechnologyPasna PV-Technology
MORE INFORMATION NEEDED!!!
07 October 2005 8
Research project of:
Phase II : Selection of rural RREE projects
Selection criteria for the further evaluation of RREE
• Part of a governmental program between 1997-2001(Probably UNDP financing)
• Complete information about the projects• Variety of renewable energy technology• Existence of connection to the conventional grid
07 October 2005 9
Research project of:
Phase III : Evaluation of the selected projects
Within the evaluation of the projects the technological and financial sustainability of the projects will be assessed
For the evaluation the use of electricity, the technological efficiencies and electricity costs are of major importance.
07 October 2005 10
Research project of:
Phase III : Evaluation of the selected projects
Model of actors within the integral analysis
07 October 2005 11
Research project of:
Phase III : Evaluation of the selected projects
Renewable Electricity vs. Conventional Energy
• Technological analysis (efficiencies of both systems)• Economical analysis (costs now and in future) • Organizational aspects
This analysis may be a trade off in future projects!!
07 October 2005 12
Research project of:
Phase IV : Asses the self-supporting potential
Self-supporting potential: the ability of a rural community to be successful in their electricity supply with renewable energies
07 October 2005 13
Research project of:
Phase V : Investigate possibilities for further development
• The presence of a great self-supporting potential can be the start of further electrification of the rural areas
• This further electrification can stimulate the economical activities in these areas
07 October 2005 14
Research project of:
Current state of the project
September• Overview of conventional electrification• Contact with relevant information sources• First list of RREE projects
Next steps:• More information about RREE projects is needed• Selection of the RREE projects
07 October 2005 15
Research project of:
Conclusions
• In order to make a complete evaluation it is important that the electrification situation in Oruro is centrally and clearly documented
• Only with good communication between the electrification parties an efficient rural electrification policy can be developed
• The evaluation of some RREE projects can give a first indication about the efficiency of Oruro’s electrification
07 October 2005 16
Research project of:
Conclusions