ams-02 tracker mechanics status of assembly and integration at unige

17
AMS-02 tracker mechanics status of assembly and integration at UniGe Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop Inner tracker integration: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - Tests of evaporator integration (pre-assembly) Preparations: - Pre-assembly of outer planes + inner tracker - TAS tests - Transport and storage at CERN Divic RAPIN, UniGe

Upload: faxon

Post on 09-Jan-2016

30 views

Category:

Documents


1 download

DESCRIPTION

Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop Inner tracker integration: - Assembly and cabling - Temperature and magnetic field sensors - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

AMS-02 tracker mechanicsstatus of assembly and integration at

UniGe

Outer planes: - Tests of evaporator (cooling loop) integration - Tools to develop Inner tracker integration: - Assembly and cabling - Temperature and magnetic field sensors - Shells closing and flanges mounting - Tests of evaporator integration (pre-assembly)Preparations: - Pre-assembly of outer planes + inner tracker - TAS tests - Transport and storage at CERN

Divic RAPIN, UniGe

Page 2: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

General view of Silicon tracker

• 5 planes, 8 layers

• Plane 1, layer 1

• Plane 2, layers 2&3

• Plane 3, layers 4&5

• Plane 4, layers 6&7

• Plane 5, layer 8

• 192 ladder modules

Page 3: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Ladder Assembly (Perugia-Geneva)

• ASSEMBLY• ~ 210 ladders build

• PHASE 2 hybrid box & legs gluing

• ~ completed

• EMI SHIELDING ( kapton foil wrapping)• ~ 31 ready for process

• Full test at each step with RA source and noise control

Page 4: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Installation of ladders on support planes (UniGe clean room)

Plane 3 being stored (under Nitrogen)

Details of fixation on both sides

FINISHED

Page 5: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Complete installation and assembly jigOuter ring assembly

and installation jig

Inner ring assembly and installation jig

Cooling loops are fragile and not self supporting. They need to be kept in jigs for

fabrication, storage, transport and assembly

Upper cooling loops (build at NIKHEF) were delivered for pre-assembly tests at UniGe

Page 6: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Test of outer cooling loop integration on plane 1

Page 7: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

The outer loop can be mounted-The fabrication jig is not well suited for installation

- Need to develop an new tool for installation of outer planes to tracker and vacuum case (compatible with cables and TAS).

- Need information from TAS about patch panel dimensions

Page 8: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Assembly of the inner tracker

• Set-up for storage & insertion into the magnet.

• Cables must be installed before the supporting shells and extra length must be attached to temporary supports.

• Further integration works delayed by cosmic and TAS tests

• UniGe manpower resources are decreasing

Page 9: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Tracker without closing and supporting shells

Page 10: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Inner cabling is finalized

Clamps to fix the cables on the back of the hybrids

Extra length of cables is stored on top and bottom temporary supports

Page 11: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Temperature sensors for inner tracker

Four double Dallas sensors will measure temperature at the center of inner tracker. (not foreseen from beginning of project)

Integration constraints lead us to join inner

measurement chain with upper loops

measurement chain.

Page 12: AMS-02  tracker mechanics status of assembly  and  integration at UniGe
Page 13: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Difficult locations (2 mm clearance from the edges of the bars to the shell)

Difficult locations

~Free apertures

Shown previously

Page 14: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

T-measurement chain installation

Pieces were developed and built to support and guide the wires of the Dallas sensors chains through difficult locations.

Page 15: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

T-measurement chain installation

T-sensors

Magnetic field sensors (ETHZ)

Page 16: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Installation of supporting shells is starting

Checking mechanical interferences and mountability

Page 17: AMS-02  tracker mechanics status of assembly  and  integration at UniGe

Near future integration operations at UniGe•Design of storage and transport jigs for inner tracker and outer planes (re-use of Alu frame used for AMS01 beam test) (in progress)

•Design and construction of outer plane installation jig (info from TAS needed).

•Supporting shells installation and remove inner tracker from Durga.

•Pre-assembly of inner evaporator on inner tracker (check mountability).

•Pre-assembly of outer planes (check mountability) on inner tracker.

•Time requested by TAS for laser beam alignment/installation.

•Orbital welding of new connectors is needed for upper/lower inner/outer evaporators (on critical path)