woe joint transport board metrowest phase 1 preliminary ... · 2 project objectives primary...
Post on 26-May-2020
1 Views
Preview:
TRANSCRIPT
WoE Joint Transport Board MetroWest Phase 1
Preliminary Business Case
Colin Medus
12 September 2014
2
Project Objectives
Primary Objectives •support economic growth, through enhancing transport links to major employment centres across the West of England
•deliver a more resilient transport offer, with more attractive & reliable journey times
•improve accessibility to the rail network with new and re-opened rail stations
•make a positive contribution to improving quality of life
Supporting Objectives •contribute to reducing traffic congestion
•contribute to enhancing the capacity of the local rail network
•contribute to reducing the overall environmental impact of the transport network.
3
4
Train Service Options
Preliminary Business Case • Strong case for intervention, good value for money,
sound commercial footing, financially affordable and deliverable by 2019.
• Two train service options both having the same infrastructure requirements.
• Half hourly service pattern (St.Andrews Road and Severn Beach hourly to fit with MW Phase 2). Symmetrical timetable feasible, giving close to a
‘clock face’ pattern.
• BCR 2.28 to 5.99 and total capital cost including development costs = £58.2m.
5
Preliminary Business Case Capital Costs
£58.2m capital cost comprises:
• £2.8m feasibility costs
• £6.1m preparation costs
• £49.3m construction costs
These figures include 30% contingency and allowance for
future inflation up to and during construction
Operational Costs
• Train service subsidy during first 3 years £1.141m to
£1.765m pa, based on current assumptions – potential to reduce. DfT to pick up subsidy there after until breakeven Point – subject to agreement
• Also some minor operating costs – bus services, car
parks etc
6
Preliminary Business Case
Economic Case We have tested 8 scenarios:
7
Scenario Train
Service
Option
Timetable –
Level of
Service
Number of
Train Sets
Scenario 1 5B Baseline 6 train sets
Scenario 2 5B Baseline 7 train sets
Scenario 3 6B Baseline 6 train sets
Scenario 4 6B Baseline 7 train sets
Scenario 5 5B Enhanced 6 train sets
Scenario 6 5B Enhanced 7 train sets
Scenario 7 6B Enhanced 6 train sets
Scenario 8 6B Enhanced 7 train sets
Preliminary Business Case • Assessed operation based on both 6 train sets and 7
train sets. More work detailed modelling of train paths needed to confirm number of train sets and formations.
• GRIP2 completed comprising comprehensive deliverables, confirming the engineering feasibility of the project.
• Early stages of environmental assessment will feed into a full Environmental Impact Assessment
• Conclusion project feasibility is sound and project should proceed to the next stage of development – Outline Business Case.
8
Preliminary Business Case Funding – Current Position
Capital Funding - of the £58.2m capital cost, the councils
collectively need to fund £4.8m. The remaining £53.4m is
to be funded from the DfT Devolved allocation £44.9m and
Local Growth Fund £8.5m.
To date the councils have collectively identified £3.5m of
the £4.8m, leaving up to £1.3m to find, pending more
detailed technical work through Outline Business Case.
Revenue Funding Current Position – train service subsidy
during first 3 years £1.141m to £1.765m pa, from April
2019. The Councils now need build this into their financial
planning so that each council can be in a position to confirm
its share of revenue funding upon completion of the
Outline Business Case – Oct 2015.
9
Business Case Stages The Business Case is in 3 stages
Preliminary Business Case – Sept 2014
Outline Business Case – Oct 2015
Full Business Case – Oct 2017
• Preliminary Business Case is needed for allocation of resources for the development of the project
• Outline Business Case is undertaken to support statutory processes including the Development Consent Order
• The Full Business Case follows procurement of construction works and operational arrangements including the train service and confirmation of powers to build and operate.
10
Next Business Case - Outline • GRIP 3 & 4 to be undertaken with Network Rail, which
essentially in engineering terms is Outline design.
• Early stages of technical evidence base and public consultation for the Development Consent Order. NB – DCO application to be submitted 4 months after completion of Outline Business Case.
• More detailed environmental assessment, inc flood risk, ecology, noise, heritage etc for EIA.
• More detailed technical work on train pathing / train sets, operational costs and demand modelling and revenues.
• Further progress with GW franchise / procurement of train service (priced option) / DfT Rail on operational arrangements. Including selection of train service option.
GRIP 3 – Option Selection
GRIP 4 – Single Option Development
11
12
GRIP 1-2 Findings
Summary of Engineering Works Needed Rebuild the Portishead to Pill Line Closure of historic crossings New station at Portishead Reopen former station at Pill Double track works at Pill and Ashton Gate Investigate improvement of highway access to Pill tunnel Environmental mitigation measures Enhancement to Parson Street Junction Re-signalling the entire line between Temple Meads and Portishead Bathampton Turnback Additional signalling at Avonmouth station Partial reinstatement of Down Relief Line to assist recessing / regulation of freight trains GRIP 1-2 includes substantial deliverables which highlight the complexity of the project
13
14
Infrastructure Needed in Pill
15
16
Parson Street Junction and Partial Reinstatement of the Down Relief Line
17
Bathampton Turnback
18
Initial Ground
Investigation
19
Ground Investigation bore sample
20
21
Portishead Station
Options Appraisal undertaken early 2014 involved detailed
assessment of 6 sites, under 3 headings:
• How each site fits with planning policy,
• Environmental impact of each site,
• Deliverability of each site,
Site options 2A, 2B & 2C identified as
potentially viable
Site options 1A, 1B and 3 identified as not viable
We published the detailed assessment on our website together with the consultation material, it can be down loaded from www.travelwest.info/mw/portishead
22
Portishead Station - Regulator
Office of Rail Regulation (ORR)
Following earlier engagement with the ORR in 2013, the ORR have recently updated
their position on a level crossing at Quays Avenue.
The ORR position is they will consider whether
there are exceptional circumstances for a level
crossing subject to the project team providing
further information in respect of 10 criteria.
The project team will put together the required
information over the next two months
and will then submit to ORR for consideration.
23
Powers to Build and Operate
MW Phase 1 requires a Development Consent Order (DCO), because it’s a nationally significant infrastructure project DCO entails a major planning application and is a 6 stage process that takes up to 3 years DCO work stream will run in parallel with other major work stream such as GRIP and the Business Case, which also require 3 years to complete DCO process includes a requirement for engagement and consultation DCO process requires an Environmental Impact Assessment and Environmental Statement
24
Stakeholder Engagement
Public Consultation in June & July 2014
was specifically about the location of
Portishead rail station.
Response to consultation was very positive
– 366 people attended the two consultation
exhibition events and over 400 responses
submitted to us.
More Stateholder Engagement Needed
Wider public consultation will be needed to
meet the statutory requirements of the
Development Consent Order process.
DCO Process & Planning
Inspectorate
25
Taking Forward MW Phase 1
Process of building the ‘Case’ for Phase 1, working through technical / planning processes and rail industry requirements for earliest possible delivery
Phase 1 Programme comprises of 4 stages:
Project Stage Stage Description Indicative Timescales
Stage 1 Preliminary Business Case
Feasibility (inc GRIP 1-2) Summer 2013 to Summer 2014
Stage 2 Outline Business Case
Option Development & Project Case (inc GRIP 3 & 4)
Autumn 2014 to Autumn 2015
Stage 3 Full Business Case
Planning Powers and Procurement (including GRIP 5)
Winter 2015/16 to Autumn 2017
Stage 4 Delivery
Construction & Opening (inc GRIP 6-8)
Autumn 2017 to Spring 2019
26
Delivering MetroWest Phase 1
The Preliminary Business Case demonstrates:
• there are no fundament impediments for the delivery of MetroWest Phase 1
• the project has a strong case for intervention, provides good value for money, has a sound commercial footing, is financially affordable and deliverable by 2019
• the project feasibility is sound and the project should proceed to the next stage of development – Outline Business Case
The Outline Business Case will entail:
• More detailed engineering design and operational figuration via GRIP 3 & 4
• Developing the technical evidence base for considerable processes including the Development Consent Order pre-application stage
• Continued joint working with the rail industry drawing on collective skills, knowledge & resources, to deliver this important project
MetroWest Governance WoE Strategic Leaders Board
27
WoE Joint Transport Board Decision Timescales
28
WoE Joint Transport Board Decisions on Preliminary Business Case
Report Recommendations:
1) To endorse the Preliminary Business Case,
2) To endorse progressing to the Outline Business Case (Programme Entry),
3) To recommend continued work with First Great Western on the operational business case,
4) To bring back to Joint Transport Board the Outline Business Case in late 2015.
29
/
Presentation Title: View > Header & Footer
25-Sep-14 1
Governance for Railway Investment Projects - GRIP Andrew Holley – Senior Development Manager
/
Presentation Title: View > Header & Footer
25-Sep-14 2
GRIP Lifecycle
top related