Eric Swisher of All4 Inc. explains "Compliance with the Low Emitting Electrical Generating Units(EGU) (LEE) Compliance Options". This presentation goes into both emission testing and monitoring for LEEs. Information included within this presentation explains: reduced emission testing, minimal monitoring requirements, quarterly emission testing, and monitoring (Continuous Emission Monitoring Systems (CEMS) and Parametric monitoring).

TRANSCRIPT

www.all4inc.comKimberton, PA | 610.933.5246Columbus, GA | 706.221.7688

Utility MATS -Compliance with the Low Emitting EGU Compliance

Option

Eric M Swisher| eswisher@all4inc.com | 610.933.5246 ext. 117April 8, 2013

Presented by All4 Inc.

2 Your environmental compliance is clearly our business.

Low Emission Electrical Generating Unit (LEE)• Reduced Emission Testing• Minimal Monitoring Requirements

Emission Testing• Quarterly

Monitoring• CEMS• Parametric

Utility MATS Compliance Strategies

3 Your environmental compliance is clearly our business.

Hydrogen Chloride HCl• CEMS (SO2 Monitor)

Particulate Matter (PM)• LEE

Mercury (Hg)• LEE

Presentation Homework

4 Your environmental compliance is clearly our business.

Evaluate Various Emission Testing Firms• Negotiate Contracted Rates• Assess Resources

Personnel Trucks/Trailers/Equipment Location(s) Reporting

• Award Multiple Contracts• Start Testing Early

Emission Testing

5 Your environmental compliance is clearly our business.

U.S. EPA Reference Method 5 (Filterable) Initial Performance Test (LEE Qualification)

• 3-Run Emission Test Program ~90-min Sampling Time Each Onsite analysis

• Maximum Normal Operating Load Conditions 90 and 110% of unit design capacity

• Quarterly Testing for 3 Consecutive Years Unit operating quarter (> 168 hours) 80 to 100 calendar days after the previous performance test

Subsequent Performance Test (LEE Status) Every 36 calendar months

~$12,000 per Test Program

PM Testing

6 Your environmental compliance is clearly our business.

U.S. EPA Reference Method 30B Initial Performance Test (LEE Qualification)

• 30-day Performance Test • Facility’s 40 CFR 75 Monitoring Systems

Subsequent Performance Test (LEE Status)• Every 12 calendar months

~$44,000 per Test Program• Plant Personnel Training• Internet Access• Analysis (1 set of tubes per 5 days)

Hg Testing

7 Your environmental compliance is clearly our business.

0 5 10 15 20 25 30 35 40$0

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

$800,000

Operating Quarter

LEE

Em

issio

n T

esti

ng

Co

st

LEE Status

Annual Hg Test-

ing

3-yr PM Testing

Annual Hg &

Quarterly PM Test-

ing

$117 K

$55 - 70 K

LEE Emission Testing Costs

8 Your environmental compliance is clearly our business.

Resume Quarterly PM Testing Monitoring Compliance Options

• PM CEMS• PM CPMS

Lose PM LEE Status

9 Your environmental compliance is clearly our business.

PM Compliance Option Cost Comparison

0 5 10 15 20 25 30 35 40$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

PM CEMS PM CPMS Emission TestingQuarter

Op

era

tin

g C

ost $116

K

10 Your environmental compliance is clearly our business.

Resume Quarterly Hg Testing Install and certify Hg CEMS within 6 months

Lose Hg LEE Status

11 Your environmental compliance is clearly our business.

Hg Compliance Option Cost Comparison

0 5 10 15 20 25 30 35 40$0

$200,000

$400,000

$600,000

$800,000

$1,000,000

Hg CEMS Hg Sorbent TrapQuarter

Op

era

tin

g C

ost

www.all4inc.comKimberton, PA | 610.933.5246Columbus, GA | 706.221.7688

Questions ?

Eric M Swisher| eswisher@all4inc.com | 610.933.5246 ext. 117