US Army Corps of Engineers

BUILDING STRONG®

St. Louis District Dredging

Lance Engle

Dredging Project Manager

St. Louis District

WEDA – Midwest 2012

Agenda

• Maintenance Dredging– District / Mission– Floating Plant– 2011 / 2012 Dredging– Other Marine Work

St. District

Illinois River

Missouri River

Mississippi

River

St. Louis

Confluence of Missouri and Mississippi Rivers

Kask

aski

a

Rive

r

SEMO Port

4

Channel Patrol

M/V PATHFINDER

Multi Mission: Channel Recon, Survey, Buoy Positioning, Towing & L&D Repair

BUILDING STRONG®

Survey Boats

• 2 - AE Contracts• 4 – Gov.’t < 26-ft

6

Dredge Potter

.32 Inch diesel-electric dustpan dredge. 2011 New Texas Deck, Pump, ICMS

800 feet of fixed discharge pipeline, 2400 feet of floating pipeline.

Season July thru December.

7

Dredge Potter Flexible Pipeline

.

Cutterhead Dredge Contract

8

• 24” Cutterhead with 3000-ft of pipeline.

• Season July thru December.

• 4th year of 5 year contract.

BUILDING STRONG®

2011 Dredge Season - Stats

Dredge # Jobs Cubic Yards Dates

Potter 31 3.5M 9/4-12/16

America 11 1.3M 7/8-8/24

10/6-10/31

Total 42 4.8M

BUILDING STRONG®

Dredging 2012 Low flood risk

►Potential for less dredging requirement in Pools.

►Lower (Middle Miss) potential for low water & more dredging.

Funding►FY 12 flat for Upper, Lower & ILW; Kaskaskia

and SEMO none.►Supplemental Funding for Upper, Lower,

Kaskaskia and SEMO.

BUILDING STRONG®

Future Marine Work

Environmental Dredging Carlyle Lake & Kaskaskia River- IDIQ contract for small cutterhead & mechanical dredging equipment. Closes 4 June.

Lock & Dam 25 - Downstream Main Lock Scour Repairs, Phase II. Closes 11 May.

Lock & Dam 24 – Scour Repair – tbd, 4th Quarter. O&M & New Dike Contracts- typically issued

Jan.► FY13 budget is healthy.

Rock Removal FY14 – Thebes to Commerce

BUILDING STRONG®

Rock Removal Update•Current Status

•Rock Grinding contract unsuccessful.•(Phases 2–4) only removed 20 cu yds

out of 6,700 cu yds.

• Path Forward•Evaluated alt. methods (boring, saw cutting, etc.)•Concluded that nothing will work except for blasting.•Budget request for FY14 (blasting)•New AIS data will be used to determine tow tracks.

•Pinnacles and rock outcrops are shown as obstruction areas in the IENC.

•Trigger (10-ft Cape Girardeau and falling)•Coordinate with USCG and RIAC, issue Navigation Notice.•Rock pinnacles will begin effecting 9 ft draft barge traffic at a stage of 8.2 Cape Girardeau.

BUILDING STRONG®

The End